Cement plant equipment life prediction method

By combining the relevant vector model and the Bayesian framework, the problems of trend complexity and large error in the prediction of equipment life in cement plants are solved, and accurate prediction of equipment failure and life is achieved. Predicted values ​​and uncertainty information are provided, and the model complexity is reduced.

CN118886183APending Publication Date: 2024-11-01TANGSHAN DUNSHI INFORMATION TECH CO LTD
View PDF 4 Cites 0 Cited by

Patent Information

Application Number
CN202410921490.2
Authority / Receiving Office
CN · China
Patent Type
Applications(China)
Current Assignee / Owner
Filing Date
2024-07-10
Publication Date
2024-11-01

AI Technical Summary

Technical Problem

The monitoring characteristics of cement plant equipment are characterized by complex trend changes and random fluctuations, which makes it difficult and prone to large errors in predicting equipment lifespan trends.

Method used

We employ a correlation vector model for data normalization and regression, combine it with a Bayesian framework for trend prediction, determine the data type through feature parameter types, calculate the first arrival time of the threshold, and establish a nonlinear, highly robust trend fitting and time extrapolation model with small sample learning capabilities.

Benefits of technology

It enables accurate prediction of equipment failure and lifespan, provides predicted values ​​and uncertainty information, reduces model complexity, and improves the speed of processing large datasets.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN118886183A_ABST
    Figure CN118886183A_ABST
Patent Text Reader

Abstract

The invention discloses a cement plant equipment life prediction method, which comprises the steps of inputting characteristic parameters into a correlation vector model, judging a data specification, and throwing out abnormal data which does not accord with the specification; performing regression on the processed cement plant equipment characteristic parameters by using a correlation vector model by using correlation vectors; performing trend prediction based on the output of the relevance vector model regression module; after a required data type is determined through the type of the characteristic parameter, a correlation vector model trend prediction module predicts a corresponding parameter threshold value; calculating the first arrival time of the parameter threshold according to the predicted value, and outputting the cement plant equipment predicted life by the model. According to the scheme, under the condition of unequal step length sampling, the fault development trend features contained in the feature index sequence are extracted, and life prediction is achieved.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The invention relates to the technical field of cement plant equipment life cycle management, and in particular to a cement plant equipment life prediction method. Background Art

[0002] Equipment is an important asset component of an enterprise and an essential tool for production. When an enterprise is in a state of healthy operation, it takes into account the development trend of equipment management. On the basis of ensuring the good operation of the equipment, it strengthens the management of the equipment and analyzes the operation data of the equipment to provide data support for the equipment management department's equipment status management, data management, operation management, and cost control. It provides decision-making basis and tool handles for improving equipment reliability and optimizing equipment operation and maintenance costs, and provides data basis for the performance evaluation of the equipment management department. The study of the entire life cycle of cement production equipment to obtain the ideal goal of the most economical equipment life cycle cost and the highest comprehensive equipment production capacity is a problem that needs to be solved at present.

[0003] However, affected by factors such as monitoring instruments and working environment, the characteristic sequence of cement plant equipment monitoring has the characteristics of complex trend changes and random fluctuations, which makes it difficult to predict the equipment life trend and causes large errors. Summary of the invention

[0004] In view of the above technical problems, the present invention proposes a method for predicting the life of cement plant equipment, and the specific technical solution is as follows.

[0005] A method for predicting the life of cement plant equipment comprises the following steps:

[0006] Step S1: Input the characteristic parameters into the relevant vector model, determine the data specifications, and discard abnormal data that does not meet the specifications;

[0007] Step S2: using the correlation vector model to regress the processed cement plant equipment characteristic parameters using the correlation vector;

[0008] Step S3: performing trend prediction based on the output of the correlation vector model regression module;

[0009] Step S4: After determining the required data type through the type of characteristic parameters, the relevant vector model trend prediction module predicts the corresponding parameter threshold;

[0010] Step S5: Calculate the time when the parameter threshold is first reached based on the predicted value, and the model outputs the predicted life of the cement plant equipment.

[0011] Furthermore, the characteristic parameter data standard determination in step S1 includes:

[0012] Whether the time series and feature parameter sequence are empty, if any one is empty, it will be thrown;

[0013] Whether the length of the time series is equal to that of the characteristic parameter sequence. If the lengths are not equal, an error is thrown.

[0014] Whether the length of the time series and feature parameter sequence array is greater than 5. If the length is less than 5, the array cannot obtain a valid vector regression model and the data will be thrown out;

[0015] Whether the length of the time series and feature parameter sequence arrays is less than 10,000. If the array length is greater than 10,000, the training speed of the vector regression model will slow down and the data will be thrown out.

[0016] Furthermore, the calculation and learning process of the correlation vector includes the following steps:

[0017] Step S21: Selecting initial values ​​of hyperparameters α and β;

[0018] Step S22: Setting the convergence threshold δ Thresh and the maximum number of iterations M_Iter;

[0019] Step S23: Calculate the mean and covariance of the posterior probability using the mean and variance formula;

[0020] Step S24: re-estimate the hyperparameters, update the parameter equations, and increase the number of iterations by 1;

[0021] Step S25: Set a suitable convergence criterion for α, consider the change 6 as the accumulation of the difference between the nth and n+1th iteration values ​​of parameter α, and calculate the change δ, the formula is:

[0022]

[0023] Determine whether the iteration termination condition is met; if δ<δ Thresh Or the maximum number of iterations M_Iter has been reached, the iteration is terminated; otherwise, the process returns to step S23 to continue the iteration process;

[0024] Step S26: After the iteration, the weight parameter w i The accuracy of α i Set a threshold α Thresh , and α i Greater than α Thresh The hyperparameters and corresponding basis functions k(x, x n ) is removed from the model, and the remaining non-zero weights are input into x n is called the correlation vector.

[0025] Further, the calculation process of step S23 includes:

[0026] Given a sample D = (t1, y1), (t2, y2), ... (t n ,yn ), learn the regression model where w n b is the weight parameter and bias term to be determined;

[0027] The samples are clustered together and recorded as data matrix X. The nth row of matrix X is Where n = 1, ..., N, and the corresponding target value is t = (t1, ..., t N ) T , the likelihood function is:

[0028]

[0029] w is the weight parameter vector, whose prior distribution is a Gaussian prior with zero mean, and β is the noise accuracy;

[0030] For each weight parameter w i Both introduce a separate hyperparameter α i , the weight prior is in the form of:

[0031]

[0032] where α i Indicates the corresponding weight parameter w i The accuracy of i , ..., α M ) T , when performing regression, the hyperparameters tend to infinity, and the posterior probability distribution of the corresponding weight parameters is concentrated near zero;

[0033] The posterior distribution is proportional to the product of the likelihood function and the prior distribution. Both the posterior distribution and the prior distribution are Gaussian distributions. The form of the posterior distribution is:

[0034]

[0035] The mean and variance are:

[0036] m=β∑Φ T t;

[0037] ∑=(A+βΦ T Φ) -1 ;

[0038] Where Φ is the N×M design matrix, and the element Φ ni =φ i (x n )(i=1,...N), and Φ nM =1(n=1,...,N), A=diag(α i ) The values ​​of α and β are determined using the second-type maximum likelihood method by maximizing the marginal function.

[0039] Further, the step S24 of reestimating the hyperparameters includes the following steps:

[0040] The marginal function is obtained by integrating the weight vector, and the formula is:

[0041] p(t|X,α,β)=∫p(t|X,w,β)p(w|α)dw;

[0042] According to the marginal function formula, the logarithmic marginal likelihood function can be calculated, and the formula is:

[0043]

[0044] Where, t=(t1,..,t N ) T , C is an N×N matrix, and the formula is:

[0045] C=β -1 I+ΦA -1 Φ T .

[0046] Let the derivative of the solved logarithmic marginal likelihood function formula be equal to zero, and update the hyperparameters α and β equations as follows:

[0047]

[0048] m i is the i-th component of the posterior mean m defined by the mean formula, γ i Determines the corresponding parameter w i Determined by the data, defined as:

[0049] γ i =1-α i ∑ ii ;

[0050] Among them, ∑ ii is the i-th component of the posterior mean m defined by the variance formula.

[0051] Further, the step S3 comprises:

[0052] Step S31: The feature prediction value is represented by the distribution mean, and the prediction distribution formula on t is:

[0053]

[0054] The formula for calculating the predicted mean is:

[0055]

[0056] Here, w is set to the posterior mean m, and the variance of the predicted distribution is calculated as:

[0057] σ 2 (x) = (β * ) -1 +φ(x) T ∑φ(x));

[0058] Step S32: construct an equally spaced time series T = [t1, t2, ..., t n , ..., t end ], where t1 is the starting regression prediction time, t n is the regression termination time, t end To predict the termination time, the time series is applied to the vector regression model to obtain the predicted values ​​of the characteristic parameters.

[0059] Further, the calculation of the threshold comprises the following steps:

[0060] Step S41: After obtaining the data, select a confidence level C_Level and calculate the mean of the samples from the data And the sample standard deviation s, the standard error SE calculation formula is:

[0061]

[0062] Where n represents the size of the data;

[0063] Step S42: Calculate the upper bound U of the confidence interval using the following formula:

[0064]

[0065] Select a safety margin S_Margin, add the upper bound of the confidence interval to the safety margin value to get the final threshold, the calculation formula is:

[0066] threshold=U+S_Margin×U.

[0067] Further, the calculation of the first arrival time in step S5 includes: calculating the threshold first arrival time according to the predicted value F_Value output by the trend prediction module and the effective prediction days Val_D, wherein the threshold value of the characteristic parameter threshold is obtained from the threshold determination module; when i=1, t1 is the first prediction time, when a certain time t i When the predicted value of the feature parameter is greater than or equal to the threshold, output t i The first time the threshold value FAT is reached, 1≤i≤Val_D, if i>Val_D and the threshold value is still not reached, it means that the predicted value does not exceed the threshold value within the valid prediction days, and the output is that the threshold value has not been reached within the valid prediction days.

[0068] Beneficial effects of the invention: The invention proposes a method for predicting the life of cement plant equipment, constructs a unified engine adapter, uses the support vector regression method as a basic tool, establishes a trend prediction model for equipment status, forms a trend fitting and time extrapolation technology with nonlinear, high robustness and small sample learning characteristics, and extracts the fault development trend characteristics contained in the characteristic indicator sequence under the condition of unequal step sampling. Extrapolate the trend, calculate the moment when the characteristic value first reaches the threshold, and realize the prediction of faults and life. BRIEF DESCRIPTION OF THE DRAWINGS

[0069] Figure 1 This is a framework diagram of a cement plant equipment life prediction method of the present invention;

[0070] Figure 2 is a trend graph obtained by vector regression and prediction in an embodiment of the present invention;

[0071] Figure 3 It is a trend and prediction graph obtained by predicting the model obtained by regression in the embodiment of the present invention. DETAILED DESCRIPTION

[0072] In order to have a clearer understanding of the technical features, purposes and effects of the present invention, specific embodiments of the present invention are now described with reference to the accompanying drawings.

[0073] Correlation vector prediction is a prediction method based on the Bayesian framework, which is mainly used to process data with nonlinear relationships. Its theoretical basis is to use the automatic correlation determination (ARD) technology to achieve the sparsity of the model, that is, only a few key data points (correlation vectors) are used for prediction, thereby reducing the complexity of the model and improving the speed of processing large data sets. And the final model not only provides the predicted value when making predictions, but also provides the uncertainty information of the prediction.

[0074] Affected by factors such as monitoring instruments and working environment, the monitoring feature sequence has the characteristics of complex trend changes and random fluctuations, which makes trend prediction difficult and causes large errors. The present invention proposes a method for predicting the life of cement plant equipment. It uses the support vector regression method as the basic tool to establish a trend prediction model for equipment status, and forms a trend fitting and time extrapolation technology with nonlinear, high robustness and small sample learning characteristics. Under the condition of unequal step sampling, it extracts the fault development trend characteristics contained in the feature indicator sequence. Extrapolate the trend, calculate the moment when the characteristic value first reaches the threshold, and realize the prediction of the fault. Its architecture is as follows: Figure 1 As shown, the following steps are included:

[0075] Step S1: Input the characteristic parameters into the relevant vector model, determine the data specifications, and discard abnormal data that does not meet the specifications;

[0076] Step S2: using the correlation vector model to regress the processed cement plant equipment characteristic parameters using the correlation vector;

[0077] Step S3: performing trend prediction based on the output of the correlation vector model regression module;

[0078] Step S4: After determining the required data type through the type of characteristic parameters, the relevant vector model trend prediction module predicts the corresponding parameter threshold;

[0079] Step S5: Calculate the time when the parameter threshold is first reached based on the predicted value, and the model outputs the predicted life of the cement plant equipment.

[0080] In one embodiment, the first step of life prediction is data specification determination, which mainly determines whether the input feature parameters meet the following requirements:

[0081] (1) Whether the time series and feature parameter sequence are empty;

[0082] (2) Whether the length of the time series and the characteristic parameter sequence are equal;

[0083] (3) Whether the length of the time series and feature parameter sequence arrays is greater than 5 (if the array length is less than 5, an effective regression model cannot be obtained)

[0084] (4) Whether the length of the time series and feature parameter sequence arrays is less than 10,000 (when the array length is greater than 10,000, the training speed of the regression model will be significantly slowed down).

[0085] The second step is to use the correlation vector for regression. For a given sample D = (t1, y1), (t2, y2), ... (t n ,y n ), learn Such a regression model, where w n and b are weight parameters and bias terms to be determined. Group the samples together and record them as data matrix X, whose nth row is Where n = 1, ..., N. The corresponding target value is t = (t1, ..., t N ) T Therefore, the likelihood function is

[0086]

[0087] The prior distribution of the weight parameter vector w is usually considered to be a zero-mean Gaussian prior. Where β is the noise accuracy, since for each weight parameter w in the correlation vector regression i A separate hyperparameter α is introduced i , rather than a shared hyperparameter, so the weight prior takes the form

[0088]

[0089] where α i Indicates the corresponding weight parameter w i The accuracy of i , ..., α M ) T When performing regression, most of these hyperparameters tend to infinity, and the posterior probability distribution of the corresponding weight parameters is concentrated near zero. The basis functions associated with these parameters have no effect on the regression of the model, so they can be pruned to generate a sparse model.

[0090] The posterior distribution is proportional to the product of the likelihood function and the prior distribution. Since the prior distribution is a Gaussian distribution, considering the conjugate Gaussian distribution, the posterior distribution will also be a Gaussian distribution, in the form of

[0091]

[0092] Among them, the mean and variance are

[0093] m=β∑Φ T t

[0094] ∑=(A+βΦ T Φ) -1

[0095] Where Φ is the N×M design matrix, and the element Φ ni =φ i (x n )(i=1,...N), and Φ nM =1(n=1,...,N), A=diag(α i ). The values ​​of α and β can be determined using the second-type maximum likelihood method, in which the marginal function needs to be maximized. The marginal likelihood function is obtained by integrating the weight vector, that is,

[0096] p(t|X,α,β)=∫p(t|X,w,β)p(w|α)dw

[0097] Since this represents the convolution of two Gaussian distributions, the log-marginal likelihood function can be calculated as

[0098]

[0099] where t=(t1,...,t N ) T , and define an N×N matrix C in the form of

[0100] C=β -1 I+ΦA -1 ΦT

[0101] The next goal is to maximize the formula for the hyperparameters α and β, and let the derivative of the solved marginal likelihood function equal to zero, so that the update equation of the hyperparameters can be obtained

[0102]

[0103] Where m i is the i-th component of the posterior mean m defined by the formula. i Determines the corresponding parameter w i Determined by the data, defined as

[0104] γ i =1-α i ∑ ii

[0105] where ∑ ii is the i-th component of the posterior mean m defined by the formula.

[0106] Set a suitable convergence criterion for α, and consider the change δ as the accumulation of the difference between the nth and n+1th iteration values ​​of parameter α. The specific calculation formula is as follows

[0107]

[0108] There are two ways to stop iteration: the first is to set the threshold δ Thresh When δ<δ Thresh The second method is to set the maximum number of iterations M_Iter, and stop the iteration when the number of iterations exceeds M_Iter.

[0109] The learning process therefore proceeds as follows:

[0110] Step 1: Select the initial values ​​of α and β;

[0111] Step 2: Set the convergence threshold δ Thresh and the maximum number of iterations M_Iter;

[0112] Step 3: Calculate the mean and covariance of the posterior probability;

[0113] Step 4: Re-estimate the hyperparameters and increase the number of iterations by 1;

[0114] Step 5: Calculate the result of the change δ and determine whether the iteration termination condition is met. Thresh Or if the maximum number of iterations M_Iter has been reached, the iteration is terminated; otherwise, return to Step 3 to continue the iteration process.

[0115] When the optimization result is obtained, for α iSet a threshold α Thres h, α i Greater than α Thresh The weight parameter w corresponding to the hyperparameter i The mean and variance of the posterior probability are both zero. These parameters and the corresponding basis functions k(x, x n ) is removed from the model. The remaining non-zero weights are input to x n is called the correlation vector.

[0116] The hyperparameter α that maximizes the marginal likelihood function is found * and β * After the value of , for a new input x, the predicted distribution on t can be calculated, and the predicted distribution is:

[0117]

[0118] The predicted mean is calculated using the following formula:

[0119]

[0120] where w is set to the posterior mean m and the variance of the predicted distribution is:

[0121] σ 2 (x) = (β * ) -1 +φ(x) T ∑φ(x)).

[0122] The third step is to predict trends, which is mainly based on the output of the correlation vector regression module - the correlation vector model, extrapolation and extension, using the distribution mean to represent the feature prediction value, and grasp the operating status of the equipment in advance.

[0123] Construct an equally spaced time series T = [t1, t2, ..., t n , ..., t end ], where t1 is the starting regression prediction time, t n is the regression termination time, t end is the prediction end time. The prediction duration and time point interval are set according to the prediction requirements. The default prediction days are 7 days and the time interval is 5 minutes. Applying this time series to the regression model can obtain the predicted values ​​of the characteristic parameters. When using the predicted values ​​for plotting, only plot to the inflection point of the prediction curve, because the predicted values ​​beyond this point cannot reliably reflect the trend. The position of the inflection point indicates the number of effective prediction days that the model can provide, which is closely related to the length of the data used to train the model.

[0124] The fourth step is to determine the threshold. First, the required data type needs to be determined by the type of characteristic parameters, such as temperature, speed, etc. These data points should be taken from a data point before the fault occurs in the historical fault record. The second step is to verify the integrity and accuracy of the selected data to ensure the reliability of the analysis.

[0125] After acquiring the data, select a confidence level C_Level. If not specified, the default value is 95%, which means that there is a 95% confidence that the data one second before the failure will fall within the calculated confidence interval. Calculate the sample mean from the data and the sample standard deviation s, the standard error SE is calculated according to the following formula

[0126]

[0127] Where n is the size of the data, then find the corresponding critical value t from the t distribution based on the confidence level and the degrees of freedom of the sample size (n-1) critical , the upper bound U of the confidence interval can be calculated by the following formula

[0128]

[0129] When calculating the threshold, a safety margin S_Margin is selected. This value is used to increase the conservatism of the prediction in case the true value exceeds the confidence interval. If not specified, the default value is 5%. The upper limit of the confidence interval is multiplied by the safety margin percentage to calculate the additional margin value. The final threshold is the upper limit of the confidence interval plus the safety margin value. The calculation formula is as follows

[0130] threshold=U+S_Margin×U.

[0131] The fifth step is to calculate the first arrival time. The threshold first arrival time can be calculated based on the predicted value F_Value output by the trend prediction module and the effective prediction days Val_D, where the threshold of the characteristic parameter threshold is obtained from the threshold determination module. Search the predicted values ​​within the effective prediction days output by the trend prediction module in chronological order, where i=1, that is, t1 is the first prediction time, and when a certain time t i When the predicted value of the feature parameter (1≤i≤Val_D) is greater than or equal to the threshold, the output is t i (First reaching threshold time FAT) If i>Val_D still does not reach the threshold, it means that the predicted value does not exceed the threshold within the valid prediction days, and the output is "the threshold is not reached within the valid prediction days".

[0132] Taking the effective value of the speed of the non-driving end V of the 2# gearbox 2# shaft of the 1# raw material circulation elevator [216-BE38] as an example, the data standard is first determined, and then the trend chart obtained by using the correlation vector regression and prediction is as follows: Figure 2 As shown in the figure, the point where the trend intersects with the threshold is the first time the threshold is reached, that is, the life point. The trend and prediction diagram obtained by predicting the model obtained by regression are shown in the figure below. Figure 3 As shown, the speed effective value threshold calculated by statistical analysis is 4.24 (mm / s), the predicted effective number of days is 6 days, and the equipment life is expected to end at 2023-05-09 09:27.

[0133] The present invention has shown and described the basic principles and main features of the present invention and the advantages of the present invention. Those skilled in the art should understand that the present invention is not limited to the above embodiments. The above embodiments and descriptions are only for explaining the principles of the present invention. Without departing from the spirit and scope of the present invention, the present invention may have various changes and improvements, which fall within the scope of the present invention. The scope of protection of the present invention is defined by the attached claims and their equivalents.

Claims

1. A method for predicting the life of cement plant equipment, characterized in that: The following steps are involved: Step S1: Input the characteristic parameters into the relevant vector model, determine the data specifications, and discard abnormal data that does not meet the specifications; Step S2: using the correlation vector model to regress the processed cement plant equipment characteristic parameters using the correlation vector; Step S3: performing trend prediction based on the output of the correlation vector model regression module; Step S4: After determining the required data type through the type of characteristic parameters, the relevant vector model trend prediction module predicts the corresponding parameter threshold; Step S5: Calculate the time when the parameter threshold is first reached based on the predicted value, and the model outputs the predicted life of the cement plant equipment.

2. A cement plant equipment life prediction method according to claim 1, characterized in that: The characteristic parameter data standard determination in step S1 includes: Whether the time series and feature parameter sequence are empty, if any one is empty, it will be thrown; Whether the length of the time series is equal to that of the characteristic parameter sequence. If the lengths are not equal, an error is thrown. Whether the length of the time series and feature parameter sequence array is greater than 5. If the length is less than 5, the array cannot obtain a valid vector regression model and the data will be thrown out; Whether the length of the time series and feature parameter sequence arrays is less than 10,000. If the array length is greater than 10,000, the training speed of the vector regression model will slow down and the data will be thrown out.

3. A cement plant equipment life prediction method according to claim 1, characterized in that: The computational learning process of the correlation vector comprises the following steps: Step S21: Select the initial values ​​of hyperparameters α and β; Step S22: Setting the convergence threshold δ Thresh and the maximum number of iterations M_Iter; Step S23: Calculate the mean and covariance of the posterior probability using the mean and variance formula; Step S24: re-estimate the hyperparameters, update the parameter equations, and increase the number of iterations by 1; Step S25: Set a suitable convergence criterion for α, consider the change δ as the accumulation of the difference between the nth and n+1th iteration values ​​of parameter α, and calculate the change δ, the formula is: Determine whether the iteration termination condition is met; if δ<δ Thresh Or the maximum number of iterations M_Iter has been reached, the iteration is terminated; otherwise, the process returns to step S23 to continue the iteration process; Step S26: After the iteration, the weight parameter w i The accuracy of α i Set a threshold α Thresh , α i Greater than α Thresh The hyperparameters and corresponding basis functions k(x,x n ) is removed from the model, and the remaining non-zero weights are input into x n is called the correlation vector.

4. A cement plant equipment life prediction method according to claim 3, characterized in that: The calculation process of step S23 includes: Given a sample D = (t1, y1), (t2, y2), … (t n ,y n ), learn the regression model where w n b is the weight parameter and bias term to be determined; The samples are clustered together and recorded as data matrix X. The nth row of matrix X is Where n=1,…,N, and the corresponding target value is t=(t1,…,t N ) T , the likelihood function is: w is the weight parameter vector, whose prior distribution is a Gaussian prior with zero mean, and β is the noise accuracy; For each weight parameter w i Both introduce a separate hyperparameter α i , the weight prior is in the form of: where α i Indicates the corresponding weight parameter w i The accuracy of i ,…,α M ) T , when performing regression, the hyperparameters tend to infinity, and the posterior probability distribution of the corresponding weight parameters is concentrated near zero; The posterior distribution is proportional to the product of the likelihood function and the prior distribution. Both the posterior distribution and the prior distribution are Gaussian distributions. The form of the posterior distribution is: The mean and variance are: m=β∑Φ T t; ∑=(A+βΦ T F) -1 ; Where Φ is the N×M design matrix, and the element Φ ni =φ i (x n )(i=1,...N), and Φ nM =1(n=1,...,N), A=diag(α i ) The values ​​of α and β are determined using the second-type maximum likelihood method by maximizing the marginal function.

5. A cement plant equipment life prediction method according to claim 4, characterized in that: The step S24 of re-estimating the hyper parameters comprises the following steps: The marginal function is obtained by integrating the weight vector, and the formula is: p(t|X,α,β)=∫p(t|X,w,β)p(w|α)dw; According to the marginal function formula, the logarithmic marginal likelihood function can be calculated, and the formula is: Where t=(t1,…,t N ) T , C is an N×N matrix, and the formula is: C=β -1 I+F -1 F T ; Let the derivative of the solved logarithmic marginal likelihood function formula be equal to zero, and update the hyperparameters α and β equations as follows: m i is the i-th component of the posterior mean m defined by the mean formula, γ i Determines the corresponding parameter w i Determined by the data, defined as: c i =1-a i ∑ ii ; Among them, ∑ ii is the i-th component of the posterior mean m defined by the variance formula.

6. A cement plant equipment life prediction method according to claim 5, characterized in that: The step S3 comprises: Step S31: The feature prediction value is represented by the distribution mean, and the prediction distribution formula on t is: The formula for calculating the predicted mean is: Here, w is set to the posterior mean m, and the variance of the predicted distribution is calculated as: s 2 (x)=(β * ) -1 +φ(x) T ∑φ(x); Step S32: construct an equally spaced time series T = [t1, t2, ..., t n ,…,t end ], where t1 is the starting regression prediction time, t n is the regression termination time, t end To predict the termination time, the time series is applied to the vector regression model to obtain the predicted values ​​of the characteristic parameters.

7. A cement plant equipment life prediction method according to claim 6, characterized in that: The calculation of the threshold comprises the following steps: Step S41: After obtaining the data, select a confidence level C_Level and calculate the mean of the samples from the data And the sample standard deviation s, the standard error SE calculation formula is: Where n represents the size of the data; Step S42: Calculate the upper bound U of the confidence interval using the following formula: Select a safety margin S_Margin, add the upper bound of the confidence interval to the safety margin value to get the final threshold, the calculation formula is: threshold=U+S_Margin×U.

8. A cement plant equipment life prediction method according to claim 7, characterized in that: The calculation of the first arrival time in step S5 includes: calculating the threshold first arrival time according to the prediction value F_Value output by the trend prediction module and the effective prediction days Val_D, wherein the threshold value of the characteristic parameter threshold is obtained from the threshold determination module; when i=1, t1 is the first prediction time, when a certain time t i When the predicted value of the feature parameter is greater than or equal to the threshold, output t i The first time the threshold is reached FAT, 1≤i≤Val_D. If i>Val_D and the threshold is still not reached, it means that the predicted value does not exceed the threshold within the valid prediction days, and the output is that the threshold is not reached within the valid prediction days.

Citation Information

Patent Citations

  • Prediction method and system for cement mill equipment spare part service life

    CN107992971A

  • Rolling bearing life prediction method based on Frescher distance dynamic digital-analog linkage

    CN108846241A

  • Coal mill fault early warning method based on deep learning convolutional neural network

    CN115496188A

  • Lithium battery remaining service life prediction method based on multi-core relevance vector machine

    CN117110884A