A control method and system based on fluorine pump air conditioner
By dividing the computer room and analyzing the equipment temperature, calculating the refrigeration evaluation value and interference coefficient, and adjusting the operating power of the fluorine pump air conditioner, the problem of the inability to adjust the power of the fluorine pump air conditioner in the existing technology is solved, and the problem of the inability to adjust the power of the fluorine pump air conditioner according to the equipment distribution and operation conditions is realized. More accurate power control and more uniform cooling effect.
Patent Information
- Application Number
- CN202411393502.5
- Authority / Receiving Office
- CN · China
- Patent Type
- Patents(China)
- Current Assignee / Owner
- Filing Date
- 2024-10-08
- Publication Date
- 2024-12-06
- Estimated Expiration
- 2044-10-08
AI Technical Summary
The existing fluorine pump air conditioning system cannot adjust the power according to the distribution and operation of the equipment in the computer room, resulting in the fluorine pump air conditioning power not meeting the requirements, especially when the equipment is remote or when the load is running.
By dividing the computer room, analyzing the equipment temperature value of each area, calculating the refrigeration evaluation value and refrigeration interference coefficient, determining the control target range, and adjusting the operating power model of the fluorine pump air conditioner to output theoretical and actual operating power.
It realizes precise regulation of the power of fluorine pump air conditioner, ensures that the equipment in the computer room operates at a temperature that meets the requirements, improves the refrigeration effect and uniformity, and ensures the safety of equipment operation.
Smart Images

Figure CN118896379B_ABST
Abstract
Description
Technical Field
[0001] The present invention relates to the technical field of fluorine pump air conditioners, and in particular to a control method and system based on a fluorine pump air conditioner. Background Art
[0002] Fluorine pump air conditioner is an energy-saving way to control the heat load of computer room. Fluorine pump air conditioner is mainly composed of fluorine pump, pipeline and valve.
[0003] The Chinese patent discloses an energy-saving control system and method based on a fluorine pump air conditioner, which relates to the field of air conditioning control technology. The system discloses a temperature detection module, an energy-saving control module, and a detection adjustment module. By setting the energy-saving control module, the output power of the fluorine pump air conditioner can be adjusted in real time according to the temperature change of the computer room, and then the power of the fluorine pump air conditioner in the computer room can be adjusted in advance according to the temperature change. On the basis of energy-saving control of the fluorine pump air conditioner, the temperature in the computer room is ensured to be relatively stable. The detection adjustment module can be set to adjust the time interval of the temperature detection module for the temperature detection in the computer room in real time according to the special computer room mark, and the control system can rationalize the monitoring frequency of the internal temperature of the computer room;
[0004] In the prior art, the output power of the fluorine pump air conditioner is adjusted in real time only according to the temperature changes in the machine room. The power of the fluorine pump air conditioner cannot be controlled according to the distribution and operation conditions of the equipment in the machine room. This will result in the current power of the fluorine pump air conditioner being unable to meet the requirements for equipment that is set up far away from the fluorine pump air conditioner or is running under load. Summary of the invention
[0005] The object of the present invention is to provide a control method and system based on a fluorine pump air conditioner. The technical problem solved by the present invention is that the power of the fluorine pump air conditioner cannot be controlled according to the distribution and operation conditions of the equipment in the machine room. This will result in the current fluorine pump air conditioner power being unable to meet the requirements for equipment that is set at a distance from the fluorine pump air conditioner or is under load.
[0006] The purpose of the present invention can be achieved through the following technical solutions:
[0007] A control method based on a fluorine pump air conditioner comprises the following steps:
[0008] Step 1: Divide the computer room into zones and output the equipment temperature value of each analysis zone;
[0009] Step 2: Based on the equipment temperature value of each analysis area, the refrigeration evaluation value of the fluorine pump air conditioner is analyzed and obtained. If the refrigeration evaluation value of the fluorine pump air conditioner is greater than or equal to the refrigeration evaluation threshold, a refrigeration failure signal of the fluorine pump air conditioner is generated;
[0010] Step 3: Based on the refrigeration failure signal of the fluorine pump air conditioner, obtain the refrigeration interference coefficient of each device;
[0011] Step 4: Based on the refrigeration interference coefficient of each device, obtain the average operating temperature of each device during the monitoring period and determine the control target range; substitute the control target range into the fluorine pump air conditioner operating power model, output the fluorine pump air conditioner theoretical operating power, and then based on the fluorine pump air conditioner theoretical operating power, output the fluorine pump air conditioner actual operating power.
[0012] As a further solution of the present invention: in step 1, the refrigeration evaluation value analysis process of the fluorine pump air conditioner is:
[0013] By formula , the refrigeration evaluation value ZLP of the fluorine pump air conditioner is calculated, where a1 and a2 are weight proportional coefficients, ZWJ is the mean working temperature of the computer room, and ZWC is the working temperature difference of the computer room.
[0014] As a further solution of the present invention: the process of obtaining the mean value ZWJ of the working temperature of the computer room is as follows:
[0015] Obtain all device temperature values in each analysis area, perform mean calculation, and obtain the mean device temperature of each analysis area;
[0016] Then the temperature averages of all analysis areas are averaged to obtain the average operating temperature ZWJ of the computer room.
[0017] As a further solution of the present invention: the process of obtaining the operating temperature difference ZWC of the computer room is:
[0018] The temperature mean values of adjacent analysis areas are calculated to obtain the temperature difference of adjacent analysis areas. The temperature difference of all adjacent analysis areas is calculated to obtain the working temperature difference ZWC of the computer room.
[0019] As a further solution of the present invention: the process of obtaining the refrigeration interference coefficient XG of the equipment is:
[0020] By formula , the cooling interference coefficient XG of the equipment is calculated; among them, b1, b2, and b3 are all weight ratio coefficients, marked as BLg for distance interference ratio, BZg for blocking interference ratio, and ZFg for load interference ratio.
[0021] As a further solution of the present invention: the analysis process of the distance interference ratio is:
[0022] Measure the distance between the center of the equipment source and the air outlet of the fluorine pump air conditioner, and mark it as the actual setting distance of the equipment;
[0023] First, compare the actual setting distance of the equipment with the effective refrigeration distance of the fluorine pump air conditioner;
[0024] If the actual setting distance of the equipment is within the effective refrigeration distance of the fluorine pump air conditioner, it means that the equipment is within the working range of the fluorine pump air conditioner, and the distance interference ratio is recorded as 1;
[0025] If the actual setting distance of the equipment is not within the effective refrigeration distance of the fluorine pump air conditioner, it means that the equipment is not within the working range of the fluorine pump air conditioner. The actual setting distance of the equipment is compared with the effective refrigeration distance of the fluorine pump air conditioner to calculate the distance interference ratio.
[0026] As a further solution of the present invention: the analysis process of the blocking-interference ratio is:
[0027] Obtain the side projection area of the device source;
[0028] And, obtain the blocked area in the path from the equipment source to the air outlet of the fluorine pump air conditioner, marked as the refrigeration blocking area;
[0029] The blocking interference ratio is obtained by calculating the ratio of the cooling blocking area to the side projection area.
[0030] As a further solution of the present invention: the analysis process of the load interference ratio is:
[0031] Set a monitoring period, obtain the real-time power load of the equipment source within the monitoring period, and then perform mean calculation to obtain the average load of the equipment source;
[0032] First, the average load of the equipment source is compared with the standard load of the equipment source;
[0033] If the average load of the equipment source is less than or equal to the standard load of the equipment source, it means that the equipment is operating within the normal working range, and the distance interference ratio is recorded as 1;
[0034] If the average load of the equipment source is equal to the standard load of the equipment source, it means that the equipment is not operating within the normal working range. The load interference ratio is calculated by comparing the average load of the equipment source with the standard load of the equipment source.
[0035] As a further solution of the present invention: in step 4, within the monitoring period, the real-time operating temperature of the device source is obtained, and then the average value is calculated to obtain the average operating temperature of the device;
[0036] Calculate the difference between the average operating temperature of each device and the standard operating temperature to obtain the operating temperature difference of each device; extract the operating temperature difference of the largest device, and mark the operating temperature difference of the largest device as the control target range;
[0037] Substitute the control target range into the fluorine pump air conditioner operating power model, and output the fluorine pump air conditioner theoretical operating power PL;
[0038] By formula , calculate the actual operating power PS of the fluorine pump air conditioner.
[0039] A control system based on a fluorine pump air conditioner, the system comprising:
[0040] Acquisition module: divides the computer room into zones and outputs the equipment temperature value of each analysis zone;
[0041] Evaluation module: Based on the equipment temperature value of each analysis area, the refrigeration evaluation value of the fluorine pump air conditioner is analyzed and obtained. If the refrigeration evaluation value of the fluorine pump air conditioner is greater than or equal to the refrigeration evaluation threshold, a refrigeration failure signal of the fluorine pump air conditioner is generated;
[0042] Analysis module: based on the refrigeration failure signal of the fluorine pump air conditioner, obtain the refrigeration interference coefficient of each device;
[0043] Control module: Based on the refrigeration interference coefficient of each device, obtain the average operating temperature of each device during the monitoring period to determine the control target range; substitute the control target range into the fluorine pump air conditioner operating power model, output the fluorine pump air conditioner theoretical operating power, and then output the fluorine pump air conditioner actual operating power based on the fluorine pump air conditioner theoretical operating power.
[0044] Beneficial effects of the present invention:
[0045] (1) The present invention divides the machine room into zones and outputs the equipment temperature value of each analysis zone; based on the equipment temperature value of each analysis zone, the refrigeration evaluation value of the fluorine pump air conditioner is analyzed and obtained, and then compared with the refrigeration evaluation threshold value to generate a signal of whether the refrigeration of the fluorine pump air conditioner is qualified; the present invention analyzes the temperature in the machine room to determine whether the temperature in the machine room meets the requirements when the fluorine pump air conditioner is currently working, and specifically determines through the refrigeration evaluation value, thereby achieving a more accurate analysis of the refrigeration effect and refrigeration uniformity of the fluorine pump air conditioner;
[0046] (2) The present invention obtains the refrigeration interference coefficient of each device based on the refrigeration failure signal of the fluorine pump air conditioner; based on the refrigeration interference coefficient of each device, obtains the average operating temperature of each device within the monitoring period to determine the control target range; substitutes the control target range into the fluorine pump air conditioner operating power model, outputs the theoretical operating power of the fluorine pump air conditioner, and then outputs the actual operating power of the fluorine pump air conditioner based on the theoretical operating power of the fluorine pump air conditioner; the present invention determines the power required for the current fluorine pump air conditioner to work according to the operating conditions of the equipment in the machine room, that is, the operating temperature of the equipment does not meet the requirements, and then accurately controls the power of the fluorine pump air conditioner according to the distribution and operating conditions of the equipment in the machine room, so that the current fluorine pump air conditioner can more accurately control the power, ensure that all equipment in the machine room can operate under the temperature that meets the requirements, and ensure the operating safety of the equipment in the machine room. BRIEF DESCRIPTION OF THE DRAWINGS
[0047] The present invention will be further described below in conjunction with the accompanying drawings.
[0048] Figure 1 It is a flowchart of a control method based on a fluorine pump air conditioner provided by an embodiment of the present invention;
[0049] Figure 2 It is a flowchart of a control method based on a fluorine pump air conditioner provided by an embodiment of the present invention;
[0050] Figure 3 The present invention provides a system block diagram of a control system based on a fluorine pump air conditioner according to an embodiment of the present invention. DETAILED DESCRIPTION
[0051] The following will be combined with the drawings in the embodiments of the present invention to clearly and completely describe the technical solutions in the embodiments of the present invention. Obviously, the described embodiments are only part of the embodiments of the present invention, not all of the embodiments. Based on the embodiments of the present invention, all other embodiments obtained by ordinary technicians in this field without creative work are within the scope of protection of the present invention.
[0052] Example 1
[0053] like Figure 1 As shown, a control method based on a fluorine pump air conditioner proposed by the present invention comprises the following steps:
[0054] Step 1: Divide the computer room into zones and output the equipment temperature value of each analysis zone;
[0055] In some implementation schemes, multiple work areas are arranged in the machine room along the direction of the air outlet of the fluorine pump air conditioner;
[0056] A temperature sensor is provided at each device source in each analysis area, and the temperature value of all device sources in each analysis area is collected by the temperature sensor and marked as the device temperature value of each analysis area;
[0057] The process of setting multiple analysis areas is as follows: if the air outlet of the fluorine pump air conditioner includes four directions, four working areas will be set at the center of the fluorine pump air conditioner;
[0058] Step 2: Based on the equipment temperature value of each analysis area, the refrigeration evaluation value of the fluorine pump air conditioner is analyzed and obtained, and then compared with the refrigeration evaluation threshold value to generate a signal whether the refrigeration of the fluorine pump air conditioner is qualified;
[0059] Among them, whether the fluorine pump air conditioning refrigeration is qualified or not includes a fluorine pump air conditioning refrigeration qualified signal or a fluorine pump air conditioning refrigeration unqualified signal;
[0060] In some implementation schemes, all device temperature values in each analysis zone are obtained, and average calculation is performed to obtain the average device temperature of each analysis zone;
[0061] Then calculate the mean temperature of all analysis areas to obtain the mean operating temperature ZWJ of the computer room;
[0062] And the temperature mean values of adjacent analysis areas are calculated to obtain the temperature difference of adjacent analysis areas, and the temperature difference of all adjacent analysis areas is calculated to obtain the working temperature difference ZWC of the computer room;
[0063] By formula , the refrigeration evaluation value ZLP of the fluorine pump air conditioner is calculated, where a1 and a2 are weight ratio coefficients, a1+a2=1, a1 is 0.67, a2 is 0.33, and the values of a1 and a2 represent the influence of the mean working temperature of the computer room and the difference in working temperature of the computer room on the refrigeration evaluation value of the fluorine pump air conditioner;
[0064] Compare the refrigeration evaluation value of the fluorine pump air conditioner with the refrigeration evaluation threshold value;
[0065] If the refrigeration evaluation value of the fluorine pump air conditioner is greater than or equal to the refrigeration evaluation threshold, it means that the average operating temperature and temperature distribution in the equipment room do not meet the set operating requirements, and a fluorine pump air conditioner refrigeration failure signal is generated;
[0066] If the cooling evaluation value of the fluorine pump air conditioner is less than the cooling evaluation threshold, it means that the average operating temperature and temperature distribution in the equipment room meet the set operating requirements, and a qualified signal of the fluorine pump air conditioner is generated;
[0067] The technical solution of the embodiment of the present invention is as follows: the machine room is divided into zones, and the equipment temperature value of each analysis zone is output; based on the equipment temperature value of each analysis zone, the refrigeration evaluation value of the fluorine pump air conditioner is analyzed and obtained, and then compared with the refrigeration evaluation threshold value, to generate a signal whether the refrigeration of the fluorine pump air conditioner is qualified; the present invention analyzes the temperature in the machine room to determine whether the temperature in the machine room meets the requirements when the fluorine pump air conditioner is currently working, and specifically determines through the refrigeration evaluation value, thereby achieving a more accurate analysis of the refrigeration effect and refrigeration uniformity of the fluorine pump air conditioner.
[0068] Example 2
[0069] Based on the above embodiment 1, Figure 2 As shown, the control method based on the fluorine pump air conditioner proposed by the present invention also includes the following steps:
[0070] Step 3: Based on the refrigeration failure signal of the fluorine pump air conditioner, obtain the refrigeration interference coefficient of each device;
[0071] In some implementation schemes, when a signal of unqualified refrigeration of a fluorine pump air conditioner is obtained, each device source is analyzed to obtain the distance interference ratio, the blocking interference ratio, and the load interference ratio, which are marked as BLg, BZg, and ZFg, respectively. , the cooling interference coefficient XG of the equipment is calculated; among them, b1, b2, and b3 are all weight ratio coefficients, b1+b2+b3=1, b1 is 0.29, b2 is 0.38, and b3 is 0.33. The values of b1, b2, and b3 represent the influence of distance interference ratio, blocking interference ratio, and load interference ratio on the cooling interference coefficient of the equipment respectively;
[0072] First, specifically, the analysis process of the distance-to-interference ratio is:
[0073] Measure the distance between the center of the equipment source and the air outlet of the fluorine pump air conditioner, and mark it as the actual setting distance of the equipment;
[0074] First, compare the actual setting distance of the equipment with the effective refrigeration distance of the fluorine pump air conditioner (obtained by the technicians through experimental statistics of the fluorine pump air conditioner);
[0075] If the actual setting distance of the equipment is within the effective refrigeration distance of the fluorine pump air conditioner, it means that the equipment is within the working range of the fluorine pump air conditioner, and the distance interference ratio is recorded as 1;
[0076] If the actual setting distance of the equipment is not within the effective refrigeration distance of the fluorine pump air conditioner, it means that the equipment is not within the working range of the fluorine pump air conditioner. The actual setting distance of the equipment is compared with the effective refrigeration distance of the fluorine pump air conditioner to calculate the distance interference ratio.
[0077] Second, specifically, the analysis process of the blocking-to-interference ratio is:
[0078] Obtain the side projection area of the device source;
[0079] Also, obtain the blocked area in the path from the device source to the air outlet of the fluorine pump air conditioner (the blocked area can be obtained by performing projection analysis along the air outlet path to obtain the projection area of other device sources on the side of the device source), marked as the refrigeration blocking area;
[0080] The ratio of the cooling blocking area to the side projection area is calculated to obtain the blocking interference ratio;
[0081] Thirdly, the analysis process of the load interference ratio is as follows:
[0082] Set a monitoring period, obtain the real-time power load of the equipment source within the monitoring period, and then perform mean calculation to obtain the average load of the equipment source;
[0083] Firstly, the average load of the equipment source is compared with the standard load of the equipment source (obtained by the technical staff through experimental statistics of fluorine pump air conditioners);
[0084] If the average load of the equipment source is less than or equal to the standard load of the equipment source, it means that the equipment is operating within the normal working range, and the distance interference ratio is recorded as 1;
[0085] If the average load of the equipment source is equal to the standard load of the equipment source, it means that the equipment is not operating within the normal working range. The average load of the equipment source is compared with the standard load of the equipment source to calculate the load interference ratio.
[0086] Step 4: Based on the refrigeration interference coefficient of each device, obtain the average operating temperature of each device within the monitoring period and determine the control target range; substitute the control target range into the fluorine pump air conditioner operating power model, output the fluorine pump air conditioner theoretical operating power, and then output the fluorine pump air conditioner actual operating power based on the fluorine pump air conditioner theoretical operating power;
[0087] In some implementation schemes, during the monitoring period, the real-time operating temperature of the device source is obtained, and then the average value is calculated to obtain the average operating temperature of the device;
[0088] Calculate the difference between the average operating temperature of each device and the standard operating temperature to obtain the operating temperature difference of each device;
[0089] Arrange the operating temperature difference of each device from large to small, extract the operating temperature difference of the largest device, and mark the operating temperature difference of the largest device as the control target range;
[0090] Substitute the control target range into the fluorine pump air conditioner operating power model, and output the fluorine pump air conditioner theoretical operating power PL;
[0091] By formula , calculate the actual operating power PS of the fluorine pump air conditioner;
[0092] Specifically, the output process of the theoretical operating power of the fluorine pump air conditioner is:
[0093] With the operating temperature difference of the equipment as the X-axis and the theoretical operating power of the fluorine pump air conditioner as the Y-axis, a fluorine pump air conditioner operating power model is constructed, the theoretical operating power of the fluorine pump air conditioner corresponding to the operating temperature difference of the equipment in the historical data is substituted into the model, and then the theoretical operating power curve of the fluorine pump air conditioner is obtained by drawing, and then the control target range is substituted into the model, and the theoretical operating power of the fluorine pump air conditioner is obtained by output according to the theoretical operating power curve of the fluorine pump air conditioner;
[0094] The technical solution of the embodiment of the present invention is as follows: based on the refrigeration failure signal of the fluorine pump air conditioner, the refrigeration interference coefficient of each device is obtained; based on the refrigeration interference coefficient of each device, within the monitoring period, the operating temperature mean of each device is obtained to determine the control target range; the control target range is substituted into the fluorine pump air conditioner operating power model, the fluorine pump air conditioner theoretical operating power is output, and then based on the fluorine pump air conditioner theoretical operating power, the actual operating power of the fluorine pump air conditioner is output; the present invention determines the power required for the current fluorine pump air conditioner to work according to the operating conditions of the equipment in the machine room, that is, the equipment operating temperature does not meet the requirements, and then accurately controls the power of the fluorine pump air conditioner according to the distribution and operating conditions of the equipment in the machine room, so that the current fluorine pump air conditioner can more accurately control the power, ensure that all equipment in the machine room can operate under the temperature conditions that meet the requirements, and ensure the operating safety of the equipment in the machine room.
[0095] Example 3
[0096] Based on the above-mentioned embodiment 1 and embodiment 2, as Figure 3 As shown, the present invention proposes a control system based on a fluorine pump air conditioner, comprising:
[0097] Acquisition module: divides the computer room into zones and outputs the equipment temperature value of each analysis zone;
[0098] Evaluation module: Based on the equipment temperature value of each analysis area, the refrigeration evaluation value of the fluorine pump air conditioner is analyzed and obtained. If the refrigeration evaluation value of the fluorine pump air conditioner is greater than or equal to the refrigeration evaluation threshold, a refrigeration failure signal of the fluorine pump air conditioner is generated;
[0099] Analysis module: based on the refrigeration failure signal of the fluorine pump air conditioner, obtain the refrigeration interference coefficient of each device;
[0100] Control module: Based on the refrigeration interference coefficient of each device, obtain the average operating temperature of each device during the monitoring period to determine the control target range; substitute the control target range into the fluorine pump air conditioner operating power model, output the fluorine pump air conditioner theoretical operating power, and then output the fluorine pump air conditioner actual operating power based on the fluorine pump air conditioner theoretical operating power.
[0101] The above formulas are all dimensionless and numerical calculations. The formula is a formula for the most recent real situation obtained by collecting a large amount of data and performing software simulation. The preset parameters in the formula are set by technicians in this field according to actual conditions.
[0102] The above is a detailed description of an embodiment of the present invention, but the content is only a preferred embodiment of the present invention and cannot be considered to limit the scope of implementation of the present invention. All equivalent changes and improvements made within the scope of the present invention should still fall within the scope of the patent coverage of the present invention.
Claims
1. A control method based on a fluorine pump air conditioner, characterized in that: The following steps are involved: Step 1: Divide the computer room into zones and output the equipment temperature value of each analysis zone; Step 2: Based on the equipment temperature value of each analysis area, the refrigeration evaluation value of the fluorine pump air conditioner is analyzed and obtained. If the refrigeration evaluation value of the fluorine pump air conditioner is greater than or equal to the refrigeration evaluation threshold, a refrigeration failure signal of the fluorine pump air conditioner is generated; Step 3: Based on the refrigeration failure signal of the fluorine pump air conditioner, obtain the refrigeration interference coefficient of each device; Step 4: Based on the refrigeration interference coefficient of each device, obtain the average operating temperature of each device during the monitoring period and determine the control target range; substitute the control target range into the fluorine pump air conditioner operating power model, output the fluorine pump air conditioner theoretical operating power, and then output the fluorine pump air conditioner actual operating power based on the fluorine pump air conditioner theoretical operating power; In step 2, the refrigeration evaluation value analysis process of the fluorine pump air conditioner is: By formula , the refrigeration evaluation value ZLP of the fluorine pump air conditioner is calculated, where a1 and a2 are weight proportional coefficients, ZWJ is the mean working temperature of the computer room, and ZWC is the working temperature difference of the computer room; The process of obtaining the average working temperature ZWJ of the equipment room is as follows: Obtain all device temperature values in each analysis area, perform mean calculation, and obtain the mean device temperature of each analysis area; Then calculate the mean temperature of all analysis areas to obtain the mean operating temperature ZWJ of the computer room; The process of obtaining the room working temperature difference ZWC is as follows: The temperature mean of adjacent analysis areas is calculated to obtain the temperature difference of adjacent analysis areas. The temperature difference of all adjacent analysis areas is calculated to obtain the working temperature difference ZWC of the computer room. The process of obtaining the cooling interference coefficient XG of the equipment is as follows: By formula , the cooling interference coefficient XG of the equipment is calculated; among them, b1, b2, and b3 are weight ratio coefficients, marked as BLg for distance interference ratio, BZg for blocking interference ratio, and ZFg for load interference ratio; The analysis process of distance-to-interference ratio is: Measure the distance between the center of the equipment source and the air outlet of the fluorine pump air conditioner, and mark it as the actual setting distance of the equipment; First, compare the actual setting distance of the equipment with the effective refrigeration distance of the fluorine pump air conditioner; If the actual setting distance of the equipment is within the effective refrigeration distance of the fluorine pump air conditioner, it means that the equipment is within the working range of the fluorine pump air conditioner, and the distance interference ratio is recorded as 1; If the actual setting distance of the equipment is not within the effective refrigeration distance of the fluorine pump air conditioner, it means that the equipment is not within the working range of the fluorine pump air conditioner. The actual setting distance of the equipment is compared with the effective refrigeration distance of the fluorine pump air conditioner to calculate the distance interference ratio; The analysis process of blocking-interference ratio is: Obtain the side projection area of the device source; And, obtain the blocked area in the path from the equipment source to the air outlet of the fluorine pump air conditioner, marked as the refrigeration blocking area; The ratio of the cooling blocking area to the side projection area is calculated to obtain the blocking interference ratio; The analysis process of load interference ratio is: Set a monitoring period, obtain the real-time power load of the equipment source within the monitoring period, and then perform mean calculation to obtain the average load of the equipment source; First, the average load of the equipment source is compared with the standard load of the equipment source; If the average load of the equipment source is less than or equal to the standard load of the equipment source, it means that the equipment is operating within the normal working range, and the distance interference ratio is recorded as 1; If the average load of the equipment source is equal to the standard load of the equipment source, it means that the equipment is not operating within the normal working range. The average load of the equipment source is compared with the standard load of the equipment source to calculate the load interference ratio; In step 4, during the monitoring period, the real-time operating temperature of the device source is obtained, and then the average value is calculated to obtain the average operating temperature of the device; Calculate the difference between the average operating temperature of each device and the standard operating temperature to obtain the operating temperature difference of each device; extract the operating temperature difference of the largest device, and mark the operating temperature difference of the largest device as the control target range; Substitute the control target range into the fluorine pump air conditioner operating power model, and output the fluorine pump air conditioner theoretical operating power PL; By formula , calculate the actual operating power PS of the fluorine pump air conditioner.
2. A control system based on a fluorine pump air conditioner, characterized in that: The system is used to execute the method described in claim 1, and the system comprises: Acquisition module: divides the computer room into zones and outputs the equipment temperature value of each analysis zone; Evaluation module: Based on the equipment temperature value of each analysis area, the refrigeration evaluation value of the fluorine pump air conditioner is analyzed and obtained. If the refrigeration evaluation value of the fluorine pump air conditioner is greater than or equal to the refrigeration evaluation threshold, a refrigeration failure signal of the fluorine pump air conditioner is generated; Analysis module: based on the refrigeration failure signal of the fluorine pump air conditioner, obtain the refrigeration interference coefficient of each device; Control module: Based on the refrigeration interference coefficient of each device, obtain the average operating temperature of each device during the monitoring period to determine the control target range; substitute the control target range into the fluorine pump air conditioner operating power model, output the fluorine pump air conditioner theoretical operating power, and then output the fluorine pump air conditioner actual operating power based on the fluorine pump air conditioner theoretical operating power.
Citation Information
Patent Citations
Machine room air conditioner regulation and control method and device based on air conditioner load and area temperature evaluation
CN114923268A
Refrigeration air conditioner operation efficiency detection system based on Internet of Things
CN117073154A
Production equipment remote monitoring system based on Internet of Things
CN117215349A
Energy-saving control system and method based on fluorine pump air conditioner
CN118055602A
Machine room energy-saving operation and maintenance management method and system
CN118400976A