Photovoltaic module arrangement method and terminal equipment

Through roof partitioning and shadowed area calculations, the automated arrangement of photovoltaic modules is achieved, solving the problems of complex and low efficiency of traditional photovoltaic modules, improving design efficiency and power generation efficiency, and generating an accurate bill of materials.

CN118898104APending Publication Date: 2024-11-05ARCTECH SOLAR HOLDING CO LTD

Patent Information

Application Number
CN202411149024.3
Authority / Receiving Office
CN · China
Patent Type
Applications(China)
Current Assignee / Owner
Filing Date
2024-08-21
Publication Date
2024-11-05

AI Technical Summary

Technical Problem

In the design of BIPV photovoltaic power stations, due to the different shapes and obstacle distributions of each roof, the traditional photovoltaic module layout method requires engineers to design separately, resulting in design errors, time-consuming and labor-intensive, and when the size of the photovoltaic module is changed or the position of the photovoltaic module changes, it is not easy to use. Rearrangement is required, resulting in projects pile up and customers cannot obtain design plans in a timely manner.

Method used

By obtaining the outline diagram of object elements and obstacle information of the roof, partition the roof and calculate the shadow area of ​​each roof area, and automatically arrange it based on the arrangementable area and photovoltaic module parameter information to achieve standardized roof area division and photovoltaic module Quick arrangement.

Benefits of technology

Improve the efficiency and versatility of photovoltaic module arrangement, reduce the need for design errors and recalculation, ensure that photovoltaic modules maximize the roof area, optimize power generation efficiency, and generate an accurate bill of materials.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN118898104A_ABST
    Figure CN118898104A_ABST
Patent Text Reader

Abstract

The invention provides a photovoltaic module arrangement method and terminal equipment. The photovoltaic module arrangement method comprises the following steps: acquiring a profile diagram of each object element of a roof on which a photovoltaic module is to be installed and building obstacle information; the object elements comprise boundary object elements and non-boundary object elements; partitioning the contour map according to boundary object elements on the roof to form a plurality of roof regions; the boundary object elements comprise roof boundaries, roof boundaries and expansion joints; calculating a first shadow area generated by each non-boundary object element and each obstacle under sunlight all year round; determining an arrangement area according to the first shadow area in each roof area and the total area of each roof area; and arranging the photovoltaic modules in the arrangeable area of each roof area based on the arrangeable area and the parameter information of the photovoltaic modules. According to the invention, the roof is divided into a plurality of roof areas based on the boundary object elements, the method can be suitable for each roof, the universality is improved, and automatic arrangement of the photovoltaic modules is facilitated.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The invention relates to the field of photovoltaic building integrated design, and in particular to an arrangement method and terminal equipment of photovoltaic components. Background Art

[0002] When designing a BIPV photovoltaic power station, engineers need to design the layout of almost all roofs individually, because the shape, parapet, light belt, and obstacle distribution of each roof are different. When the size of the photovoltaic module is changed, the size or location of the maintenance channel is changed, the photovoltaic module needs to be re-designed, and the bill of materials for installing the photovoltaic module is calculated based on the results of the layout.

[0003] Based on the traditional photovoltaic module arrangement method, the roofs of different projects correspond to different situations. The arrangement design is not only prone to errors, but also time-consuming and labor-intensive, resulting in project backlogs and customers being unable to obtain design solutions in a timely manner. Summary of the invention

[0004] The purpose of the present invention is to provide a photovoltaic module arrangement method and terminal equipment, which can realize the classification of object elements on the roof and then partition the roof, and generate photovoltaic module arrangement information by combining the object elements of each roof area and the arrangement parameter information of the photovoltaic modules, which can be applied to various roofs, improve versatility, and facilitate the automatic arrangement of modules.

[0005] The technical solution provided by the present invention is as follows:

[0006] The present invention provides a method for arranging photovoltaic modules, comprising the following steps:

[0007] Obtain the outline of each object element on the roof where the photovoltaic components are to be installed and the building obstacle information; the object elements include boundary object elements and non-boundary object elements.

[0008] The contour map is partitioned according to boundary-type object elements on the roof to form a plurality of roof areas; the boundary-type object elements include roof boundaries, roof boundaries, and expansion joints.

[0009] Calculate the first shadow area generated by each non-boundary object element and obstacle under sunlight throughout the year; determine the arrangable area according to the first shadow area in each roof area and the total area of ​​each roof area; arrange the photovoltaic modules in the arrangable area of ​​each roof area based on the parameter information of the arrangable area and the photovoltaic modules.

[0010] Specifically, through the photovoltaic component arrangement method proposed in the present invention, combined with the actual roof types, the corresponding different elements in different roofs are defined and classified, so that different roof conditions are divided into standardized roof areas, the roof area is maximized, and the photovoltaic components can be quickly arranged.

[0011] Furthermore, the first shadow area generated by each non-boundary object element and obstacle under sunlight throughout the year is calculated, including:

[0012] Calculate the winter solstice shadow area generated by any vertex of the outer contour of non-boundary object elements and obstacles on the winter solstice; calculate the summer solstice shadow area generated by any vertex of the outer contour of non-boundary object elements and obstacles on the summer solstice; connect the outer vertices of the winter solstice shadow area and the summer solstice shadow area to obtain the year-round shadow area of ​​the vertex; calculate the year-round shadow area of ​​each vertex of the outer contour of non-boundary object elements and obstacles one by one, and obtain the year-round shadow area of ​​non-boundary object elements and obstacles, which is recorded as the first shadow area.

[0013] Specifically, before generating the photovoltaic module arrangement information, the shadow areas of non-boundary object elements and obstacles under sunlight throughout the year are calculated, and the photovoltaic module arrangement plan is further optimized according to the shadow areas.

[0014] Further, determining the arrangable area according to the first shadow area in each roof area and the total area of ​​each roof area comprises:

[0015] The arrangable area is obtained by deducting the first shadow area and the area occupied by each object element from the total area of ​​each roof area.

[0016] Further, based on the arrangable area and the parameter information of the photovoltaic modules, the photovoltaic modules are arranged in the arrangable area of ​​each roof area, including:

[0017] Identify and calculate the area of ​​the arrangable area, and based on the area of ​​each photovoltaic module to be arranged, fully arrange the arrangable area; based on the overlap between the first shadow area and each photovoltaic module, remove the overlapping photovoltaic modules to obtain a preliminary arrangement plan for the photovoltaic modules in the arrangable area of ​​each roof area.

[0018] Specifically, the photovoltaic modules overlapping with the first shadow area are removed to ensure that the photovoltaic modules can convert solar energy into electrical energy with optimal efficiency.

[0019] Further, based on the overlap between the first shadow area and each photovoltaic module, removing the overlapping photovoltaic modules includes:

[0020] The area where the first shadow area overlaps with each photovoltaic module is recorded as the overlapping area; calculate and determine whether the area ratio of the overlapping area to the corresponding photovoltaic module is within a preset value; if so, retain the corresponding photovoltaic module arrangement; if not, remove the corresponding photovoltaic module.

[0021] Further, after obtaining a preliminary arrangement plan of photovoltaic modules in the arrangable area of ​​each roof area, it includes:

[0022] Based on the preliminary arrangement plan of photovoltaic modules in the arrangeable area of ​​each roof area, scattered photovoltaic panel modules are eliminated in each roof area to optimize the preliminary arrangement plan in each roof area and generate the final photovoltaic module arrangement plan for each roof area.

[0023] Specifically, due to the irregularity of obstacles and shadow areas, there will be scattered photovoltaic panel arrangements. Removing scattered photovoltaic panel components in advance can facilitate installation and subsequent maintenance.

[0024] Furthermore, the contour image is partitioned according to the boundary object elements on the roof to form a plurality of roof areas, including:

[0025] Read the vertices of the contour map and the intersections formed by the boundary object element and the contour map; select a point from the vertices or intersections as the first vertex of a roof area, and identify the next vertex or intersection as the second vertex of a roof area along the extension direction of the contour map where the first vertex is located or the extension direction of the boundary object element; according to the left turn or right turn rule, continue to identify the next vertex of a roof area along the extension direction of the contour map where the second vertex is located or the extension direction of the boundary object element, until all vertices of a roof area are identified and connected to form a roof area; according to the above steps, continue to complete the next roof area until all partitions of the roof are completed.

[0026] Specifically, by dividing the roof into multiple roof areas, the layout information of the entire roof can be converted into the layout of multiple small roof areas, and the calculation efficiency is higher when arranging photovoltaic modules based on separate roof areas.

[0027] Furthermore, after arranging the photovoltaic modules in the arrangable area of ​​each roof area based on the arrangable area and the parameter information of the photovoltaic modules, the method further includes:

[0028] Based on the arrangement information of the photovoltaic modules generated for each roof area and the installation information of the photovoltaic modules, a bill of materials for installing the photovoltaic modules on the roof is generated.

[0029] Furthermore, before obtaining the outline of each object element on the roof where the photovoltaic module is to be installed and the obstacle information around the building, it also includes:

[0030] According to the type of roof, different object elements on the roof are defined separately, and the same definition is given to the same object element; and the object elements are classified.

[0031] Specifically, there are object elements on the roof, such as roof boundaries, divisions, expansion joints, ridge lines, air towers, obstacles, parapets, and light strips. Some object elements serve as divisions, while others will cast shadows under light. The classified object elements can perform standardized feature processing on the roof, making it easier to divide the roof into zones.

[0032] The present invention also provides a terminal device for arranging photovoltaic components, comprising a processor and a memory, wherein the processor can call instructions stored in the memory, and when the instructions are executed, the terminal device executes any one of the photovoltaic component arrangement methods described.

[0033] Through the photovoltaic component arrangement method and terminal device provided by the present invention, the object elements of the roof where the photovoltaic components are to be installed are classified and defined, the roof is divided into multiple roof areas based on the boundary object elements, the shadow area and the total area of ​​each roof are used to determine the area where the photovoltaic components can be arranged, and the photovoltaic component arrangement information is quickly generated in the arrangeable area in combination with the parameter information of the photovoltaic components. The method is suitable for various types of roofs and improves the arrangement efficiency and the secondary optimization arrangement efficiency. BRIEF DESCRIPTION OF THE DRAWINGS

[0034] The preferred implementation scheme will be described below in a clear and understandable manner with reference to the accompanying drawings to further illustrate the above-mentioned characteristics, technical features, advantages and implementation methods of a photovoltaic module arrangement method and terminal equipment.

[0035] Figure 1 It is a flow chart of an embodiment of a photovoltaic module arrangement method of the present invention;

[0036] Figure 2 is a profile diagram of a roof on which a photovoltaic module is to be installed according to the present invention;

[0037] Figure 3 is a flow chart of another embodiment of a photovoltaic module arrangement method of the present invention;

[0038] Figure 4 It is an external boundary contour diagram of a roof on which a photovoltaic module is to be installed according to the present invention;

[0039] Figure 5 A plurality of roof areas of a roof on which photovoltaic modules are to be installed according to the present invention;

[0040] Figure 6 is a flow chart of another embodiment of a photovoltaic module arrangement method of the present invention;

[0041] Figure 7 It is a shadow area of ​​a roof on which a photovoltaic module is to be installed according to the present invention;

[0042] Figure 8is a flow chart of another embodiment of a photovoltaic module arrangement method of the present invention;

[0043] Fig. 9 It is the preliminary arrangement information of a photovoltaic module of the present invention;

[0044] Fig.10 It is the final arrangement information of a photovoltaic module of the present invention;

[0045] Fig.11 It is the preliminary arrangement information of a photovoltaic module in a roof area of ​​the present invention;

[0046] Fig.12 This is the final arrangement information of a photovoltaic module in a roof area of ​​the present invention. DETAILED DESCRIPTION

[0047] In the following description, specific details such as specific system structures, technologies, etc. are provided for the purpose of illustration rather than limitation, so as to provide a thorough understanding of the embodiments of the present application. However, it should be clear to those skilled in the art that the present application may also be implemented in other embodiments without these specific details. In other cases, detailed descriptions of well-known systems, devices, circuits, and methods are omitted to prevent unnecessary details from obstructing the description of the present application.

[0048] It should be understood that when used in this specification and the appended claims, the term "comprising" indicates the presence of the described features, integers, steps, operations, elements and / or components, but does not exclude the presence or addition of one or more other features, integers, steps, operations, elements, components and / or collections.

[0049] It should be further understood that the term “and / or” used in the specification and appended claims refers to any combination and all possible combinations of one or more of the associated listed items, and includes these combinations.

[0050] In addition, in the description of the present application, the terms "first", "second", etc. are only used to distinguish the description and cannot be understood as indicating or implying relative importance.

[0051] In order to more clearly illustrate the embodiments of the present invention or the technical solutions in the prior art, the specific implementation methods of the present invention will be described below with reference to the accompanying drawings. Obviously, the accompanying drawings described below are only some embodiments of the present invention. For ordinary technicians in this field, other drawings and other implementation methods can be obtained based on these drawings without creative work.

[0052] Building Integrated Photovoltaics (BIPV) is a technology that closely integrates solar photovoltaic power generation systems with building structures. Unlike traditional rooftop or ground-mounted photovoltaic systems, BIPV systems are directly used as part of the building, such as roofs, walls or windows, thus achieving the goals of aesthetics, energy saving and environmental protection.

[0053] In the integrated design of photovoltaic buildings, since the shape, parapet, light strip, and obstacle distribution of each roof are different, almost all roofs require engineers to design the layout separately. When the size of photovoltaic modules is changed, the size or location of maintenance channels is changed, the photovoltaic modules need to be re-designed and the corresponding bill of materials for installing photovoltaic modules is calculated based on the layout results.

[0054] Based on the traditional photovoltaic module layout method, the shapes and structures of the roofs of different projects are different, making the photovoltaic module layout design more complicated. The physical elements on the roof may affect the installation position and layout of the photovoltaic modules. The layout design is not only prone to errors, but also time-consuming and labor-intensive, resulting in project backlogs, and customers are unable to obtain design solutions in a timely manner.

[0055] In the arrangement of photovoltaic modules, there are the following problems: When photovoltaic modules are arranged, the shadow area will block the battery string of the module, resulting in a reduction in the power output of the entire photovoltaic module, thereby reducing the amount of power generation loss. The matching of BIPV modules with building modules requires more adjustments, which increases the time for designing and arranging information. In order to integrate with the appearance and function of the roof, it is necessary to consider the aesthetics and overall design of the roof.

[0056] Therefore, the present invention provides a method for arranging photovoltaic components, which identifies and defines the object elements of the roof where the photovoltaic components are to be installed, divides the roof into multiple roof areas based on boundary object elements, and non-boundary object elements and obstacles form shadow areas. The shadow areas are combined with arrangement parameter information to quickly generate arrangement information of the photovoltaic components, thereby improving the arrangement efficiency and secondary optimization arrangement efficiency.

[0057] Based on the method proposed in the present invention, a modular design method is adopted to divide the roof into multiple roof areas, so that the roof is divided into multiple specific standardized roof areas. Arrangement for each roof area can simplify the design process and reduce the need for recalculation due to design changes, especially when secondary arrangement is required for replacement of photovoltaic modules, etc., there is no need to recalculate the arrangement of multiple roof areas. Through the shadow areas generated by non-boundary object elements and obstacles under sunlight throughout the year, the impact of shadow areas on the power generation of photovoltaic modules is evaluated to improve power generation efficiency.

[0058] The following is a description with reference to the accompanying drawings:

[0059] In one embodiment of the present invention, Figure 1 As shown, it shows a schematic flow chart of the photovoltaic assembly arrangement method provided in some embodiments of the present disclosure. It includes the following steps:

[0060] S100 obtains the outline of each object element on the roof where the photovoltaic module is to be installed and the building obstacle information; the object elements include boundary object elements and non-boundary object elements. Obstacles include objects such as trees and electric poles located around the building.

[0061] S200 partitions the contour image according to boundary object elements on the roof to form multiple roof areas; the boundary object elements include roof boundaries, roof boundaries, and expansion joints.

[0062] S300 calculates the first shadow area generated by each non-boundary object element and obstacle under sunlight throughout the year.

[0063] S400 determines an arrangable area according to the first shadow area in each roof area and the total area of ​​each roof area.

[0064] S500 arranges the photovoltaic modules in the arrangeable area of ​​each roof area based on the arrangeable area and the parameter information of the photovoltaic modules.

[0065] Specifically, the user first needs to conduct a detailed on-site survey of the roof to understand the structure and related contours of the roof, and upload the contour map of the roof to the terminal device, and the terminal device obtains the contour map of the roof where the photovoltaic components are to be installed.

[0066] When designing the installation of rooftop photovoltaic modules, the following elements on the roof need to be considered: roof boundaries, safety needs to be ensured at the edge of the roof to prevent photovoltaic modules from falling from the edge; boundaries, different areas of the roof may have different structures or materials, and attention needs to be paid to the installation method of photovoltaic modules and the selection of brackets at the boundaries; air towers, the shadow area of ​​the air tower under sunlight may affect the light reception of photovoltaic modules; obstacles and parapets may block light; expansion joints, ridge lines, etc.

[0067] like Figure 2 As shown, combined with the actual roof types, since the outlines and object element labels uploaded by users are different, the terminal device needs to define and classify the different elements corresponding to different roofs differently, and convert the actual outlines into standardized images, so that the terminal device can calculate the arrangement information of photovoltaic modules. Among them, displaying different types of object elements in the outline map with different icons can be generated after automatic recognition, or the user can manually drag the object elements and draw them according to the arrangement information.

[0068] In order to divide the entire roof into multiple roof areas, it is necessary to classify the roof boundaries, boundaries, expansion joints, ridge lines, air towers, roof obstacles, parapets, light strips and other object elements on the roof according to the boundary division. Among them, the object elements include boundary object elements and non-boundary object elements.

[0069] When determining the roof partitions, users need to select boundary objects such as roof boundaries and divisions in turn. The terminal device then uses the boundary object elements on the roof (such as roof boundaries, divisions, and expansion joints) as boundaries to partition the overall outline of the roof into multiple standardized roof areas. By establishing roof areas for the roof, it can be applied to various types of roofs in real scenarios, maximize the use of the roof area, and facilitate the rapid arrangement of photovoltaic modules.

[0070] Calculate the first shadow area created by each non-boundary object element (such as air towers, roof obstacles, etc.) and surrounding obstacles on the roof where the photovoltaic components are to be installed. The total area of ​​each roof area combined with the first shadow area in each roof area can determine the layout area of ​​the photovoltaic components.

[0071] The arrangable area in each roof area is combined with the parameter information of the photovoltaic modules to be installed (such as module size, module laying start and end positions, channel reservation conditions, etc.) to arrange the photovoltaic modules in each roof area.

[0072] Among them, the layout parameter information is the personalized setting information in the roof project set by the user according to the actual situation, such as the component layout setting including the starting and ending positions of the component laying, the reserved gaps in each row / column as maintenance channels, etc.; the project information includes the latitude, azimuth, specific dimensions of the component, etc. After receiving the personalized setting information provided by the user, the terminal device will fully lay out the entire roof.

[0073] Through the arrangement method of photovoltaic components proposed in the present invention, combined with the actual roof types, the corresponding different elements in different roofs are defined and classified, so that different roof conditions are divided into standardized roof areas, thereby maximizing the use of roof area and being applicable to all types of roofs for rapid design of photovoltaic building integration.

[0074] In one embodiment of the present invention, the contour image is partitioned according to the boundary object elements on the roof to form a plurality of roof areas, such as Figure 3 As shown, the above step S200 may include:

[0075] S210 reads the vertices of the contour image and the intersections formed by the boundary object elements and the contour image.

[0076] S220 selects a point from the vertices or intersections as the first vertex of a roof area, and identifies the next vertex or intersection as the second vertex of a roof area along the extension direction of the contour map where the first vertex is located or the extension direction of the boundary object element.

[0077] S230 continues to identify the next vertex of a roof area according to the left turn or right turn rule, along the extension direction of the contour map where the second vertex is located or the extension direction of the boundary object element, until all vertices of a roof area are identified and connected to form a roof area.

[0078] S240 follows the above steps to complete the next roof zone until all zones of the roof are completed.

[0079] Specifically, Figure 4 As shown in the figure, the outer contour of the roof outline is composed of 1-2-3-4-5-6-1 connected end to end. Among them, the ab line and the ef line are the dividing lines of two adjacent roofs on the building, and the cd line is the expansion joint on the roof. The intersection points formed by the boundary object elements and the outline are a, b, c, d, e, and f, among which ab and cd intersect at point g.

[0080] A vertex is selected from the vertices or intersections in the roof outline as the first vertex (starting vertex) of a roof area, and the first vertex is used to identify the next vertex or intersection along the extension direction of the outline or boundary object element. For example, when the main line where the starting point 1 is located begins to connect with the new intersection, the intersection that can be connected with the starting point 1 is a or c.

[0081] After the second vertex is identified, according to the left-turn or right-turn rule, the second vertex continues to identify the next vertex or intersection along the extension direction of the contour map or boundary object element, and a roof area is formed after all the vertices of a roof area are identified. For example, starting from starting point 1 to point a, the edge (i.e., main line) of a roof area starting from the starting point is 1-a. According to the left-turn rule, it is necessary to identify the intersection g along the direction of the ab line, and then identify the intersection c along the direction of the gc line. Finally, the starting point 1 is identified, and all the intersections are connected in sequence from the starting point to obtain the closed polygon 1-agc-1 connected end to end, that is, the first roof partition is obtained.

[0082] After obtaining a roof area, continue to complete the next roof area according to the above steps until all the roof areas are divided. For example, starting from a, continue to divide according to the above method to obtain a closed polygon aefga; starting from e, divide to obtain a closed polygon e-2-3-4-e; starting from 4, divide to obtain a closed polygon 4-5-bg-4; starting from b, divide to obtain a closed polygon b-6-cgb; the line segment from point c to the starting point 1 is already included in the polygon 1-agc-1 obtained above, so it is skipped. At this point, the roof area separated by the intersection with the original polygon outline 1-2-3-4-5-6-1 has been divided, and the following is obtained: Figure 5 All roof divisions shown.

[0083] By adopting a modular design approach and dividing the roof into multiple standardized roof areas, the layout information of the entire roof can be converted into the layout of multiple small roof areas, reducing the need to recalculate the entire roof due to a single design change. The bill of materials can be generated accurately and the calculation efficiency is also higher.

[0084] In a real-time example of the present invention, Figure 6 As shown, before determining the arrangable area of ​​each roof area, it is necessary to calculate the first shadow area generated by each non-boundary object element and the obstacles around the building under sunlight throughout the year. The above step S300 includes:

[0085] S310 calculates the winter solstice shadow area generated by any vertex of the outer contour of the non-boundary object element and the obstacle during the winter solstice.

[0086] S320 calculates the summer solstice shadow area generated by any vertex of the outer contour of the non-boundary object element and the obstacle during the summer solstice.

[0087] S330 connects the outer vertices of the winter solstice shadow area and the summer solstice shadow area to obtain the year-round shadow area of ​​the vertex.

[0088] S340 calculates the annual shadow area of ​​each vertex of the non-boundary object element and the outer contour of the obstacle one by one, and obtains the annual shadow area of ​​the non-boundary object element and the obstacle, which is recorded as the first shadow area. The above detailed calculation method is recorded in the patent application with Chinese application number 202310448665.8, and will not be described in detail here.

[0089] Specifically, after the roof is partitioned, the shadow area needs to be analyzed. Non-boundary object elements such as air towers (including ridge air towers and slope air towers), parapets, roof obstacles, and external building obstacles have a certain height and will produce a certain shadow area. The user sends a shadow drawing command to the terminal device, and the terminal device calculates the shadow area caused by non-boundary object elements and obstacles at any time based on the position, outline and height of the elements that will produce shadows (non-boundary object elements) combined with the latitude and azimuth of the roof.

[0090] When calculating the shadow area of ​​obstacles on the areas where photovoltaic panels are installed, the photovoltaic industry generally selects the winter solstice and the summer solstice as reference days, and calculates the vertices of any non-boundary object element and obstacle outside the building about the winter solstice shadow area and the summer solstice shadow area, respectively. Then, the outer vertices of the winter solstice shadow area and the summer solstice shadow area are connected to obtain the annual shadow area of ​​any vertex of the outer contour of non-boundary object elements and obstacles around buildings.

[0091] Non-boundary object elements and obstacles are usually polygons composed of multiple points. The vertices of the polygon are calculated cyclically to obtain the annual shadow area of ​​each vertex, and finally the outer vertices of the shadow area are connected to form the annual shadow area (first shadow area) of the non-boundary object elements and obstacles. The vertices are the points that constitute the outer contours of the non-boundary object elements and obstacles. The outer vertices of the shadow area refer to the outermost shadows formed by the sunlight shining on the non-boundary object elements and obstacles on different dates and at different times.

[0092] By combining information such as non-boundary object elements and obstacle contours, the shadow graphics of special points (non-boundary object elements and obstacle vertices) and special dates (summer solstice and winter solstice) are automatically calculated, and automatically combined into the shadow envelope map of the entire non-boundary object elements and obstacles, making the shadow calculation results more intuitive and in line with the actual environment, and suitable for photovoltaic power station projects.

[0093] In one embodiment of the present invention, after calculating the first shadow area, the arrangable area is determined in combination with the total area of ​​each roof area, and step S400 further includes:

[0094] S410: Deducting the area occupied by each object element from the total area of ​​each roof area to obtain an arrangable area.

[0095] Specifically, Figure 7 As shown, the area occupied by each non-boundary object element that can generate a shadow area includes not only the area of ​​the element installed on the roof, but also the area of ​​the shadow area generated by the element.

[0096] First, the total area of ​​each roof zone needs to be measured or determined. Each roof zone may have a first shadow area formed by buildings or other non-boundary object elements blocking the sunlight; secondly, the area occupied by each object element in each roof zone is identified, including all objects that already exist or are planned to be placed on the roof, such as air conditioning equipment, vents, etc.; finally, the area of ​​the first shadow area and the area occupied by all object elements is subtracted from the total area of ​​each roof zone to obtain the remaining arrangable area. Based on the remaining arrangable area, further space planning can be carried out, such as deciding how many photovoltaic modules can be placed, or how to optimize the existing layout to improve space utilization.

[0097] By analyzing the first shadow area, the layout of photovoltaic modules can be planned more effectively to avoid the waste of invalid space. In a limited space, photovoltaic modules can be reasonably arranged to maximize the use of space and improve the installed capacity and power generation capacity of the photovoltaic system.

[0098] In one embodiment of the present invention, after calculating the arrangable area, it is necessary to arrange the photovoltaic modules in the arrangable area of ​​each roof area, such as Figure 8 As shown, the above step S500 also includes:

[0099] S510 identifies and calculates the area of ​​the arrangable region, and performs full paving arrangement in the arrangable region based on the area of ​​each photovoltaic module to be arranged.

[0100] S520 removes the overlapping photovoltaic components based on the overlap between the first shadow area and each photovoltaic component, and obtains a preliminary arrangement plan for the photovoltaic components in the arrangable area of ​​each roof area.

[0101] S530 eliminates scattered photovoltaic components in each roof area based on the preliminary arrangement plan of photovoltaic components in the arrangeable area of ​​each roof area to optimize the preliminary arrangement plan in each roof area and generate a final photovoltaic component arrangement plan for each roof area.

[0102] Specifically, Fig. 9 As shown in the figure, after calculating the area of ​​the arrangable area, each roof area can be fully paved. Since the photovoltaic modules are rectangular and the arrangable area is irregular in shape, in the case of full paving, some photovoltaic modules will overlap with the first shadow area. Figure 7 The shaded area shown in the figure is removed by removing the photovoltaic panels that intersect or overlap with the shaded area, and the result is as follows Fig.10 The preliminary arrangement of photovoltaic modules is shown.

[0103] like Fig.11As shown in the partial enlarged view of a roof area, it can be seen that there are relatively scattered photovoltaic components, which is extremely unfavorable for installation and subsequent maintenance. Therefore, the user needs to set the maximum continuous number of scattered photovoltaic panels to be removed in the above personalized settings according to the actual situation of the roof area. After receiving the deletion command, the terminal device optimizes the arrangement information of the generated photovoltaic components to obtain the following Fig.12 The optimized photovoltaic panel arrangement information is shown.

[0104] Through this method, the scattered photovoltaic modules on the roof are eliminated. Based on centralized management, the difficulty and cost of subsequent maintenance can be reduced, the risk of installing scattered photovoltaic modules can be reduced, and the maintenance efficiency and system safety can be improved.

[0105] In one embodiment of the present invention, the above step S520 may include:

[0106] S521 records the area where the first shadow area overlaps with each of the photovoltaic modules as an overlapping area;

[0107] S522 calculates and determines whether the ratio of the area of ​​the overlapping region to the area of ​​the corresponding photovoltaic component is within a preset value; if so, retains the corresponding photovoltaic component arrangement; if not, removes the corresponding photovoltaic component.

[0108] In one embodiment of the present invention, after generating the final photovoltaic assembly arrangement plan for each roof area, the above step S530 may include:

[0109] S531 generates a bill of materials for installing photovoltaic modules on the roof based on the arrangement information of photovoltaic modules generated for each roof area and the installation information of photovoltaic modules.

[0110] Specifically, after the terminal device receives the user's statistical project list summary, it can generate a summary of the photovoltaic building integrated roof project material list (such as component quantity / size / type, horizontal / vertical installation, color steel tiles / water guide grooves, etc.) based on the final photovoltaic module arrangement results.

[0111] When factors such as replacing photovoltaic modules or changing the size or position of maintenance channels require re-designing the layout, users can adjust the layout parameter information (such as module size, module laying start and end positions, channel reservation conditions, etc.), and the terminal device can re-generate the layout information based on the adjusted layout parameter information.

[0112] The project material list obtained by this method can be used to guide the preparation and production of rooftop photovoltaic module projects, improving the design speed of rooftop photovoltaic projects; the layout parameter information can also be flexibly adjusted, and there is no need to design the layout of the roof separately. It is only necessary to change the parameters based on the original roof partition to regenerate the layout information. While ensuring accuracy, it also greatly improves the calculation efficiency.

[0113] In one embodiment of the present invention, a terminal device includes a processor and a memory, wherein the memory is used to store a computer program; the processor is used to execute the computer program stored in the memory to implement the method for arranging photovoltaic components in the above-mentioned corresponding method embodiment.

[0114] The terminal device may be a desktop computer, a notebook, a PDA, a tablet computer, a mobile phone, a human-computer interaction screen, etc. The terminal device may include, but is not limited to, a processor and a memory. Those skilled in the art will appreciate that this example does not constitute a limitation on the terminal device, and may include more or fewer components, or a combination of certain components, or different components.

[0115] The processor may be a central processing unit (CPU), or other general-purpose processors, digital signal processors (DSP), application-specific integrated circuits (ASIC), field-programmable gate arrays (FPGA) or other programmable logic devices, discrete gate or transistor logic devices, discrete hardware components, etc. A general-purpose processor may be a microprocessor or any conventional processor, etc.

[0116] The memory may be an internal storage unit of the terminal device, such as a hard disk or memory of the terminal device. The memory may also be an external storage device of the terminal device, such as a plug-in hard disk equipped on the smart device, a smart media card (SMC), a secure digital (SD) card, a flash card, etc. Further, the memory may include both an internal storage unit of the device terminal and an external storage device. The memory is used to store the computer program and other programs and data required by the terminal device. The memory may also be used to temporarily store data that has been output or is to be output.

[0117] In the above embodiments, the description of each embodiment has its own emphasis. For parts that are not described or recorded in detail in a certain embodiment, reference can be made to the relevant descriptions of other embodiments.

[0118] Those of ordinary skill in the art will appreciate that the units and algorithm steps of each example described in conjunction with the embodiments disclosed herein can be implemented with electronic hardware, or a combination of computer software and electronic hardware. Whether these functions are performed with hardware or software depends on the specific application and design constraints of the technical solution. Professional and technical personnel can use different methods to implement the described functions for each specific application, but such implementation should not be considered to be beyond the scope of this application.

[0119] It should be noted that the above embodiments can be freely combined as needed. The above is only a preferred embodiment of the present invention. It should be pointed out that for ordinary technicians in this technical field, several improvements and modifications can be made without departing from the principle of the present invention, and these improvements and modifications should also be considered as the protection scope of the present invention.

Claims

1. A method for arranging photovoltaic modules, It is characterized in that The following steps are involved: Obtain the outline of each object element on the roof where the photovoltaic modules are to be installed and the building obstacle information; The object elements include boundary object elements and non-boundary object elements; Partitioning the contour map according to the boundary-like object elements on the roof to form a plurality of roof areas; the boundary-like object elements include roof boundaries, roof boundaries, and expansion joints; Calculate the first shadow area generated by each of the non-boundary object elements and obstacles under sunlight throughout the year; Determine an arrangable area according to the first shadow area in each roof area and the total area of ​​each roof area; The photovoltaic components are arranged within the arrangeable area of ​​each roof area based on the arrangeable area and the parameter information of the photovoltaic components.

2. The photovoltaic module arrangement method according to claim 1, It is characterized in that The calculation of the first shadow area generated by each of the non-boundary object elements and obstacles under sunlight throughout the year includes: Calculate the winter solstice shadow area generated by any vertex of the outer contour of the non-boundary object element and the obstacle during the winter solstice; Calculate the summer solstice shadow area generated by any vertex of the outer contour of the non-boundary object element and the obstacle during the summer solstice; Connect the outer vertices of the winter solstice shadow area and the summer solstice shadow area to obtain the year-round shadow area of ​​the vertex; The annual shadow area of ​​each vertex of the non-boundary object element and the outer contour of the obstacle is calculated one by one to obtain the annual shadow area of ​​the non-boundary object element and the obstacle, which is recorded as the first shadow area.

3. The photovoltaic module arrangement method according to claim 1, It is characterized in that The step of determining the arrangable area according to the first shadow area in each roof area and the total area of ​​each roof area includes: The arrangable area is obtained by deducting the first shadow area and the area occupied by each object element from the total area of ​​each roof area.

4. The photovoltaic module arrangement method according to claim 1, It is characterized in that The arranging of the photovoltaic components within the arrangable area of ​​each roof area based on the arrangable area and the parameter information of the photovoltaic components comprises: Identify and calculate the area of ​​the arrangable region, and arrange the photovoltaic modules fully in the arrangable region based on the area of ​​each photovoltaic module to be arranged; Based on the overlap between the first shadow area and each of the photovoltaic components, the overlapping photovoltaic components are removed to obtain a preliminary arrangement plan for the photovoltaic components within the arrangable area of ​​each roof area.

5. The photovoltaic module arrangement method according to claim 4, It is characterized in that The removing of overlapping photovoltaic components based on the overlap between the first shadow area and each photovoltaic component comprises: Recording the area where the first shadow area overlaps with each of the photovoltaic modules as an overlapping area; Calculating and determining whether the ratio of the area of ​​the overlapping region to the area of ​​the corresponding photovoltaic module is within a preset value; If yes, the corresponding photovoltaic component arrangement is retained; if no, the corresponding photovoltaic component is removed.

6. The photovoltaic module arrangement method according to claim 4, It is characterized in that After obtaining the preliminary arrangement plan of the photovoltaic modules in the arrangable area of ​​each roof area, the method includes: Based on the preliminary arrangement plan of the photovoltaic components in the arrangeable area of ​​each roof area, the scattered photovoltaic components are eliminated in each roof area to optimize the preliminary arrangement plan in each roof area and generate a final photovoltaic component arrangement plan for each roof area.

7. The photovoltaic module arrangement method according to any one of claims 1 to 6, It is characterized in that The step of partitioning the contour image according to the boundary object elements on the roof to form a plurality of roof areas comprises: Reading the vertices of the contour map and the intersections formed by the boundary object elements and the contour map; Selecting a point from the vertices or intersections as a first vertex of a roof area, and identifying the next vertex or intersection as a second vertex of the roof area along the extension direction of the contour map where the first vertex is located or the extension direction of the boundary object element; According to the left turn or right turn rule, along the extension direction of the contour map where the second vertex is located or the extension direction of the boundary object element, continue to identify the next vertex of the one roof area until all the vertices of the one roof area are identified and connected to form a roof area; Continue to complete the next roof zone following the above steps until all zones of the roof are completed.

8. The photovoltaic module arrangement method according to any one of claims 1 to 6, It is characterized in that After arranging the photovoltaic components in the arrangable area of ​​each roof area based on the arrangable area and the parameter information of the photovoltaic components, the method further includes: Based on the arrangement information of the photovoltaic components generated for each roof area and the installation information of the photovoltaic components, a bill of materials for installing the photovoltaic components on the roof is generated.

9. The photovoltaic module arrangement method according to any one of claims 1 to 6, It is characterized in that Before obtaining the outline of each object element on the roof where the photovoltaic module is to be installed and the obstacle information around the building, it also includes: In combination with the type of the roof, different object elements on the roof are defined respectively, and the same object element is defined in the same way; and the object elements are classified.

10. A terminal device, It is characterized in that For the arrangement of photovoltaic components, comprising a processor and a memory, the processor can call instructions stored in the memory, when the instructions are executed, the terminal device executes the photovoltaic component arrangement method as described in any one of claims 1 to 9.

Citation Information

Patent Citations

  • Method and system for generating obstacle shadow area of photovoltaic module

    CN116976070A

Cited By

  • Roof photovoltaic intelligent arrangement method and system based on shadow analysis and region cutting

    CN121835192A