Large-diameter super-long pipe preparation and integral spraying construction method

Through the combined lifting technology of the roller frame and the module car and the combination of the arc plate, nozzle structure and micro fan of the spraying device, the problems of uneven spraying and notches of large diameter ultra-long tubes are solved, and the complete and smooth spraying effect and high efficiency are achieved. spraying process.

CN118904686APending Publication Date: 2024-11-08GUANGXI WENZHOU HEAVY IND CO LTD
View PDF 0 Cites 0 Cited by

Patent Information

Application Number
CN202411129809.4
Authority / Receiving Office
CN · China
Patent Type
Applications(China)
Current Assignee / Owner
Filing Date
2024-08-16
Publication Date
2024-11-08

AI Technical Summary

Technical Problem

Large diameter ultra-long tubes have problems such as uneven spraying, spray notches and curling edges during the spraying process, resulting in inefficiency.

Method used

The combined lifting technology of the roller frame and the module car is adopted, combined with the arc plate and nozzle structure of the spraying device, spraying in layers in batches and using a micro fan to remove surface dust to ensure even paint coverage.

Benefits of technology

Complete and smooth spray painting of large diameter ultra-long tubes is achieved, avoiding spray painting notches and paint loss, and improving spraying efficiency and quality.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN118904686A_ABST
    Figure CN118904686A_ABST
Patent Text Reader

Abstract

The invention discloses a large-diameter super-long pipe preparation and overall spraying construction method, and belongs to the technical field of long pipe preparation and processing, a single pile is sprayed in a graded and layered manner through cooperation of a roller frame and a module vehicle, so that paint sprayed on the overall surface of the single pile is more complete and smooth, and the construction efficiency is improved. The phenomenon of paint spraying notches or paint falling after paint spraying of the single pile is completed can be avoided; a spraying device is arranged, the spraying device is provided with a first arc-shaped plate and a second arc-shaped plate, a plurality of nozzles are arranged in the first arc-shaped plate, and a plurality of air outlet holes are formed in the second arc-shaped plate, so that dust and impurities on the surface of the single pile are blown off before the single pile is sprayed, and it is guaranteed as much as possible that the surface of the single pile is kept clean during paint spraying; and spraying operation can be carried out on the single pile more uniformly and comprehensively.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The invention relates to the technical field of long pipe preparation and processing, and in particular to a large-diameter ultra-long pipe preparation and overall spraying construction method. Background Art

[0002] Large diameter long pipe refers to a pipe with a larger diameter and a longer length. This kind of pipe is widely used in many fields such as hydraulics, construction, and industry, and plays an important role.

[0003] Due to the large diameter and long length, the preparation and subsequent processing and construction are relatively difficult. Due to some environmental requirements, it is necessary to spray paint on the surface of the long tube to improve corrosion resistance. Then the length and volume of the entire single pile are too large, so it is necessary to use a support frame to support the single pile and then spray the single pile manually. However, this spraying method has serious defects. Not only is the manual spraying uneven, but after the spraying is completed, the contact part between the support frame and the single pile cannot be effectively sprayed, and there is a spraying gap. When the support frame is separated from the single pile, there will be warping of the sprayed paint, which requires multiple reworks and is very inefficient. Summary of the invention

[0004] The main purpose of the present invention is to provide a method for preparing and integrally spraying large-diameter and ultra-long pipes, aiming to solve the problems of the above background technology.

[0005] To achieve the above-mentioned purpose, the present invention proposes a method for preparing a large-diameter ultra-long pipe and spraying the entire pipe, comprising the following steps:

[0006] S1. Prepare several short pipes of different lengths and weld them in sections in the workshop;

[0007] S2, transporting the pipes welded in step S1 to the assembly workshop by a module vehicle for overall assembly and welding;

[0008] S3, place the whole monopile assembled in step S2, place three roller racks in the spray room, place the whole monopile on the three roller racks, and after placing them, withdraw the module car behind;

[0009] S4. After the module vehicle is withdrawn, the two rear roller frames are lifted up, the front roller frame is moved to a suitable position, the two roller frames on both sides are lifted up, and the middle roller frame is moved to a suitable position to fully support the single pile;

[0010] S5, after the last three roller frames are positioned, the first two roller frames are moved to the top of the single pile and placed by the joint lifting of the roller frames and the module car, and after the placement, the remaining module car is removed;

[0011] S6. Sandblast the entire single pile;

[0012] S7, after completing the sandblasting of step S6, use a spraying device to spray the entire monopile, the contact area between the roller frame and the monopile is the paint damage zone area, and the paint damage zone area is not sprayed first;

[0013] S8. Perform secondary sandblasting in the paint damaged zone area, and protect the adjacent area of ​​the damaged zone before sandblasting to prevent the paint coating in the adjacent area from being damaged during sandblasting;

[0014] S9, moving the roller frame in the paint damaged zone area to the paint zone, and after the roller frame position is moved, manually spraying the paint damaged zone area;

[0015] The spraying device includes a vehicle body, a sprayer and a nozzle structure. The sprayer is located on the vehicle body. The output end of the sprayer is connected to a conical barrel, the conical barrel is connected to a guide pipe, and the nozzle structure is connected to the end of the guide pipe. The nozzle structure surrounds the single pile to spray it.

[0016] Optionally, a cylinder is provided on the vehicle body, a lifting platform is provided at the output end of the cylinder, the sprayer is mounted on the lifting platform, and the cylinder drives the lifting platform to change the longitudinal height of the sprayer.

[0017] Optionally, the nozzle structure includes a first arc-shaped plate and a plurality of nozzles, the first arc-shaped plate is connected to the guide pipe, and each nozzle is arranged at intervals along the inner wall of the first arc-shaped plate.

[0018] Optionally, a storage box is provided on the lifting platform, and the storage box is connected to the sprayer for storing paint.

[0019] Optionally, a straight rod is provided on the first curved plate, a micro fan is provided on the straight rod, and a mobile power source for providing power to the micro fan is provided on the vehicle body.

[0020] Optionally, the output end of the micro fan is connected to a second arc-shaped plate, and the inner wall of the second arc-shaped plate is provided with a plurality of air outlet holes.

[0021] Optionally, the modular vehicle is a SPMT modular vehicle.

[0022] Compared with the prior art, the present invention has the following beneficial effects:

[0023] 1. Through the cooperation of the roller frame and the module vehicle, the single pile is sprayed in stages and layers, so that the paint on the overall surface of the single pile is more complete and smooth, which can avoid the phenomenon of paint gaps or paint falling after the single pile is painted.

[0024] 2. The spraying device is provided with a first arc plate, and the nozzles are arranged at intervals along the inner wall of the first arc plate, thereby increasing the spraying area and being able to more fully fit the arc surface of the single pile, so that the single pile can be sprayed more evenly.

[0025] 3. The spraying device is provided with a second curved plate, the inner wall of which is provided with a plurality of air outlets. Wind is transmitted to the second curved plate through a micro fan, and the wind is blown out from the air outlets to blow off dust and impurities on the surface of the single pile, so as to ensure that the surface of the single pile remains clean when spraying paint. BRIEF DESCRIPTION OF THE DRAWINGS

[0026] In order to more clearly illustrate the embodiments of the present invention or the technical solutions in the prior art, the drawings required for use in the embodiments or the description of the prior art will be briefly introduced below. Obviously, the drawings described below are only some embodiments of the present invention. For ordinary technicians in this field, other drawings can be obtained based on the structures shown in these drawings without paying creative work.

[0027] Figure 1 is a flow chart of the construction method of the present invention;

[0028] Figure 2 This is a schematic diagram of the transportation of a whole single pile;

[0029] Figure 3 This is a schematic diagram of placing a monopile on a roller frame when transporting the monopile to the whole-pile coating room;

[0030] Figure 4 This is a schematic diagram of removing one of the module vehicles;

[0031] Figure 5 A schematic diagram showing the removal of the remaining module vehicle;

[0032] Figure 6 Schematic diagram of the roller frame being adjusted to support the single pile;

[0033] Figure 7 This is a schematic diagram of a single pile after sandblasting;

[0034] Figure 8 Schematic diagram of spraying operation for a single pile;

[0035] Fig. 9 Schematic diagram of a monopile with partial spraying completed;

[0036] Fig.10 It is a schematic diagram of spraying paint on the paint damage zone after the roller frame is moved;

[0037] Fig.11 It is a structural schematic diagram of a spraying device.

[0038] Description of Figure Numbers:

[0039] Label name Label name 10 Body 20 Lifting platform 21 cylinder 22 Storage Box 30 Spraying Machine 31 Conical barrel 32 Flow guide tube 33 Straight 40 Nozzle structure 41 The first curved plate 42 nozzle 50 Micro fan 60 The second curved plate 61 Air outlet

[0040] The realization of the purpose, functional features and advantages of the present invention will be further explained in conjunction with embodiments and with reference to the accompanying drawings. DETAILED DESCRIPTION

[0041] The following will be combined with the drawings in the embodiments of the present invention to clearly and completely describe the technical solutions in the embodiments of the present invention. Obviously, the described embodiments are only part of the embodiments of the present invention, not all of the embodiments. Based on the embodiments of the present invention, all other embodiments obtained by ordinary technicians in this field without creative work are within the scope of protection of the present invention.

[0042] It should be noted that all directional indications in the embodiments of the present invention (such as up, down, left, right, front, back, etc.) are only used to explain the relative position relationship, movement status, etc. between the components under a certain specific posture (as shown in the accompanying drawings). If the specific posture changes, the directional indication will also change accordingly.

[0043] In addition, the descriptions of "first", "second", etc. in the present invention are only used for descriptive purposes and cannot be understood as indicating or implying their relative importance or implicitly indicating the number of the indicated technical features. Therefore, the features defined as "first" and "second" may explicitly or implicitly include at least one of the features. In addition, the technical solutions between the various embodiments can be combined with each other, but they must be based on the ability of ordinary technicians in the field to implement them. When the combination of technical solutions is contradictory or cannot be implemented, it should be deemed that such a combination of technical solutions does not exist and is not within the scope of protection required by the present invention.

[0044] The present invention provides a method for preparing a large-diameter ultra-long pipe and spraying the entire pipe, comprising the following steps:

[0045] S1. Prepare several short pipes of different lengths and weld them in sections in the workshop;

[0046] S2, transporting the pipes welded in step S1 to the assembly workshop by a module vehicle for overall assembly and welding;

[0047] S3, placing the whole monopile assembled in step S2 on two module vehicles, transporting them to the spraying room by the two module vehicles, placing three roller racks in the spraying room, placing the whole monopile on the three roller racks, and after placing them, withdrawing the module vehicle behind;

[0048] S4. After the module vehicle is withdrawn, the two rear roller frames are lifted up, the front roller frame is moved to a suitable position, the two roller frames on both sides are lifted up, and the middle roller frame is moved to a suitable position to fully support the single pile;

[0049] S5, after the last three roller frames are positioned, the first two roller frames are moved to the top of the single pile and placed by the joint lifting of the roller frames and the module car, and after the placement, the remaining module car is removed;

[0050] S6. Sandblast the entire single pile;

[0051] S7, after completing the sandblasting of step S6, use a spraying device to spray the entire monopile, the contact area between the roller frame and the monopile is the paint damage zone area, and the paint damage zone area is not sprayed first;

[0052] S8. Perform secondary sandblasting in the paint damaged zone area, and protect the adjacent area of ​​the damaged zone before sandblasting to prevent the paint coating in the adjacent area from being damaged during sandblasting;

[0053] S9, moving the roller frame in the paint damaged zone area to the paint zone, and after the roller frame position is moved, manually spraying the paint damaged zone area.

[0054] Please refer to Figure 2-Figure 3 Further, in step S1, before preparing several short pipes of different lengths for segmented welding, the outer surface of the short pipes is first derusted, and then step S2 is performed, the welded pipes are transported to the assembly workshop by a module car for overall assembly welding, wherein the module car is an SPMT module car, and the roller frame is a prior art that can rotate the single pile, which will not be described in detail here; after the overall assembly welding is completed, the solder at the welding point is polished and smoothed with a grinder, and then the entire single pile is placed on two module cars, and the two module cars are transported to the spray room; when the entire single pile is transported to the whole pile painting room, the single pile is placed in the three roller frames in the painting room, and after it is placed, the rear module car can be withdrawn.

[0055] Please refer to Figure 4 After the module car is withdrawn, lift up the two rear roller frames, so that the front roller frame can be moved to the position shown in the figure. The same is true for the middle roller frame. First lift up the two roller frames and move the middle roller frame to the position shown in the figure.

[0056] Please refer to Figure 5 and Figure 6 After the last three roller frames are placed, the first two roller frames can be moved to the top of the single pile and placed after the roller frames and the module car are lifted together. After the placement, the remaining module car can be removed. Figure 5 shown.

[0057] Please refer to Figure 7 After the roller frame is placed in the right position, the sandblasting machine can be used to sandblast the single pile.

[0058] Please refer to Figure 8 , painting is carried out according to the painting construction process, wherein the unpainted area in contact with the roller frame is the paint damage zone area, and the paint damage zone area is not painted first. During painting, the roller frame rotates to make the single pile rotate, so as to spray the surface of the single pile in all directions.

[0059] Please refer to Fig. 9 , perform secondary sandblasting in the paint damaged zone area, where the adjacent area of ​​the paint damaged zone needs to be protected before sandblasting to prevent damage to the paint coating in the adjacent area during sandblasting. Before this process, the paint in the painted area has been completely solidified.

[0060] Please refer to Fig.10 To move any of the roller frames in the first three positions, the other four roller frames need to cooperate with the lifting before they can move. The moving principle is the same as that of step S3. Before the roller frame completes the movement, a quilt needs to be placed above the moving roller frame to avoid crushing and damaging the coating of the adjacent pipe section. After the roller frame position is moved, the paint damage zone area is manually sprayed, which can spray the paint damage zone area more accurately.

[0061] In the implementation process of this embodiment, the single pile is sprayed in stages and layers through the cooperation between the module vehicle and the roller frame, so that the paint on the overall surface of the single pile is more complete and smooth, and the phenomenon of paint gaps or paint peeling after the single pile is painted can be avoided.

[0062] This embodiment also provides a spraying device for implementing the spraying operation of step S7.

[0063] Please refer to Fig.11 The spraying device includes a vehicle body 10, a sprayer 30 and a nozzle structure 40. The sprayer 30 is located on the vehicle body 10. The output end of the sprayer 30 is connected to a conical barrel 31. The conical barrel 31 is connected to a guide pipe 32. The conical barrel 31 gathers the paint and then converges it to the guide pipe 32. The nozzle structure 40 is connected to the end of the guide pipe 32. The nozzle structure 40 surrounds the single pile to spray it.

[0064] In this embodiment, the vehicle body 10 can be an AGV vehicle, and a cylinder 21 is provided on the vehicle body 10. A lifting platform 20 is provided at the output end of the cylinder 21. The sprayer 30 is installed on the lifting platform 20. The cylinder 21 drives the lifting platform 20 to change the longitudinal height of the sprayer 30 to adapt to the spraying of single piles of different sizes. A storage box 22 is provided on the lifting platform 20, and the storage box 22 is connected to the sprayer 30 for storing paint.

[0065] In this embodiment, the nozzle structure 40 includes a first curved plate 41 and a plurality of nozzles 42. The first curved plate 41 is connected to the guide tube 32. Each nozzle 42 is arranged at intervals along the inner wall of the first curved plate 41, so that the surface of the single pile can be sprayed with paint from different directions. The rotation of the single pile on the roller frame can make the painting more uniform.

[0066] In this embodiment, a straight rod 33 is provided on the first curved plate 41, and the straight rod 33 is a solid cylindrical rod, and paint will not enter the straight rod 33; a micro fan 50 is provided on the straight rod 33, and a mobile power supply for providing power to the micro fan 50 is provided on the vehicle body, and the output end of the micro fan 50 is connected to a second curved plate 60, and a plurality of air outlet holes 61 are provided on the inner wall of the second curved plate 60, and each air outlet hole is provided along the inner wall of the second curved plate 60, and the second curved plate 60 is hollow, so as to ensure that the wind blown by the micro fan 50 to the second curved plate 60 can be blown out from the air outlet holes 61. The mobile power supply and the micro fan 60 are both prior art, and will not be described in detail here.

[0067] It is understandable that before painting the single pile, the micro fan 60 is started to blow air, and the wind is blown out through the air outlet 61 to blow off the dust and impurities on the surface of the single pile, so as to ensure that the surface of the single pile remains clean during painting.

[0068] The device is moved to one side of the single pile so that the first arc plate 41 and the second arc plate 60 surround the top of the single pile. The device moves along the length direction of the single pile and cooperates with the roller frame to rotate the single pile to make the spraying more uniform and comprehensive.

[0069] The above description is only a preferred embodiment of the present invention, and does not limit the patent scope of the present invention. All equivalent structural changes made by using the contents of the present invention specification and drawings under the inventive concept of the present invention, or directly / indirectly applied in other related technical fields are included in the patent protection scope of the present invention.

Claims

1. A method for preparing and spraying large-diameter and ultra-long pipes. It is characterized in that The steps include: S1. Prepare several short pipes of different lengths and weld them in sections in the workshop; S2, transporting the pipes welded in step S1 to the assembly workshop by a module vehicle for overall assembly and welding; S3, placing the whole monopile assembled in step S2 on two module vehicles, transporting them to the spraying room by the two module vehicles, placing three roller racks in the spraying room, placing the whole monopile on the three roller racks, and after placing them, withdrawing the module vehicle behind; S4. After the module vehicle is withdrawn, the two rear roller frames are lifted up, the front roller frame is moved to a suitable position, the two roller frames on both sides are lifted up, and the middle roller frame is moved to a suitable position to fully support the single pile; S5, after the last three roller frames are positioned, the first two roller frames are moved to the top of the single pile and placed by the joint lifting of the roller frames and the module car, and after the placement, the remaining module car is removed; S6. Sandblast the entire single pile; S7, after completing the sandblasting of step S6, use a spraying device to spray the entire monopile, the contact area between the roller frame and the monopile is the paint damage zone area, and the paint damage zone area is not sprayed first; S8. Perform secondary sandblasting in the paint damaged zone area, and protect the adjacent area of ​​the damaged zone before sandblasting to prevent the paint coating in the adjacent area from being damaged during sandblasting; S9, moving the roller frame in the paint damaged zone area to the paint zone, and after the roller frame position is moved, manually spraying the paint damaged zone area; The spraying device includes a vehicle body, a sprayer and a nozzle structure. The sprayer is located on the vehicle body. The output end of the sprayer is connected to a conical barrel, the conical barrel is connected to a guide pipe, and the nozzle structure is connected to the end of the guide pipe. The nozzle structure surrounds the single pile to spray it.

2. The method for preparing and spraying a large-diameter ultra-long pipe as claimed in claim 1, Features: The vehicle body is provided with a cylinder, the output end of the cylinder is provided with a lifting platform, the sprayer is mounted on the lifting platform, and the cylinder drives the lifting platform to change the longitudinal height of the sprayer.

3. The method for preparing and spraying a large-diameter ultra-long pipe as claimed in claim 1, Features: The nozzle structure comprises a first arc plate and a plurality of nozzles. The first arc plate is communicated with the flow guide pipe, and each nozzle is arranged at intervals along the inner wall of the first arc plate.

4. The method for preparing and integrally spraying a large-diameter ultra-long pipe as claimed in claim 2, Features: The lifting platform is provided with a storage box, which is connected to the spraying machine and is used for storing paint.

5. The method for preparing and integrally spraying a large-diameter ultra-long pipe as claimed in claim 3, Features: A straight rod is disposed on the first arc-shaped plate, a micro fan is disposed on the straight rod, and a mobile power source for providing power to the micro fan is disposed on the vehicle body.

6. The method for preparing and integrally spraying a large-diameter ultra-long pipe as claimed in claim 5, Features: The output end of the micro fan is connected to a second arc plate, and the inner wall of the second arc plate is provided with a plurality of air outlet holes.

7. The method for preparing and integrally spraying a large-diameter ultra-long pipe as claimed in claim 1, Features: The module vehicle is a SPMT module vehicle.