Tower crane foundation construction and dismantling method
By setting up a support platform, cross support beam and connecting short columns on the basement floor, dispersing the tower crane load and laying protective plates on the basement floor, the problem of insufficient bearing capacity of the tower crane foundation in the basement floor is solved, and the stable construction and demolition of the tower crane is achieved. Improve construction efficiency and structural recovery capabilities.
Patent Information
- Application Number
- CN202411157906.4
- Authority / Receiving Office
- CN · China
- Patent Type
- Applications(China)
- Current Assignee / Owner
- Filing Date
- 2024-08-22
- Publication Date
- 2024-11-08
AI Technical Summary
During construction, when the tower crane foundation is directly installed on the basement floor, the basement bottom plate has insufficient bearing capacity and cannot meet the load needs of the tower crane. Moreover, the basement structure is easily damaged during construction and demolition, affecting construction efficiency and structural recovery.
By setting up a support platform, cross support beam and connecting short columns on the basement floor, the load of the tower crane is dispersed, and protective plates are laid on the basement floor to protect the structure. A layered casting method is used to form a stable tower crane foundation to ensure structural strength and construction convenience .
Effectively meet the load bearing needs of tower cranes, avoid the impact on the basement floor, improve construction efficiency, and easily restore the original structure after demolition, ensuring the stability of the tower crane foundation and the convenience of construction.
Smart Images

Figure CN118911188A_ABST
Abstract
Description
Technical Field
[0001] The invention relates to the technical field of building construction, and in particular to a tower crane foundation construction and dismantling method. Background Art
[0002] Tower cranes are important equipment for lifting and transportation in the construction industry. Most of the vertical transportation of building materials is completed by tower cranes. In order to ensure the smooth operation of tower cranes, tower cranes are installed on tower crane foundations. The tower crane foundation must meet two requirements: one is to evenly transfer the upper load of the tower crane to the foundation and not exceed the ground endurance; the other is to ensure that the tower crane can maintain overall stability and not tip over under various adverse working conditions. Therefore, the tower crane foundation is usually composed of a larger size concrete cap.
[0003] In engineering construction, in order to facilitate the hoisting of construction materials and save hoisting costs, multiple construction buildings share the same tower crane. Due to the different construction periods between the construction buildings, the tower crane attached to the building that was completed first needs to be dismantled due to delivery time constraints after the topping-out, which limits the construction progress of the unfinished buildings. Therefore, the tower crane needs to be reinstalled. Due to construction site restrictions, the tower crane foundation needs to be set up based on the completed basement. If the tower crane foundation is directly set on the basement floor, the basement floor has insufficient bearing capacity to meet the needs of bearing the tower crane. Summary of the invention
[0004] The purpose of the present invention is to provide a tower crane foundation construction and dismantling method, which can rely on the existing structure of the basement for construction, ensure that the tower crane foundation has good structural strength, meet the tower crane bearing requirements, avoid affecting the basement floor, be easy to construct, improve construction efficiency, facilitate the subsequent tower crane foundation dismantling, and restore the original structure of the basement.
[0005] In order to achieve the above object, the present invention provides a tower crane foundation construction method, comprising the following steps:
[0006] S1. Openings are set on the top plate of the basement;
[0007] S2. Setting a cap dimension line on the basement floor, and chiseling the basement floor within the cap dimension line;
[0008] S3. Lay a protective plate on the basement floor outside the dimension line of the said cap;
[0009] S4. Perform steel bar binding construction of the cross support beam and the connecting short column on the protective plate; the dimension line of the cap is located at the intersection of the cross support beam, one end of the connecting short column abuts against the other end of the cross support beam, and the other end abuts against the side wall of the basement wall or the second frame column;
[0010] S5. Pre-embedded tower crane fixing bolts;
[0011] S6, construction of pouring formwork for caps, cross support beams and connecting short columns;
[0012] S7. Pouring of concrete for tower crane foundation.
[0013] Furthermore, the step S1 includes the following steps:
[0014] S11, laying out the opening on the basement roof;
[0015] S12, erecting a return support frame: setting a return support frame at the opening, wherein the bottom of the return support frame abuts against the basement floor, and the top of the return support frame abuts against the basement roof;
[0016] S13, providing a material receiving plate in the return support frame, wherein the material receiving plate is located directly below the opening;
[0017] S13, drilling holes within the layout range using a water drill, and then cutting the basement top plate along the layout using a rope saw;
[0018] S14, dismantling the partial structure of the return support frame directly below the opening.
[0019] Furthermore, the step S2 further includes: breaking the first frame column located within the dimension line of the cap, and retaining the vertical longitudinal reinforcement;
[0020] Furthermore, the step S6 further includes:
[0021] S61. An oblique brace is provided on the outside of the casting formwork, one end of the oblique brace is fixed to the basement floor, and the other end is in contact with the casting formwork.
[0022] Furthermore, the step S4 comprises:
[0023] S41, opening a first anchor hole in the basement floor along the vertical direction, and inserting a first anchor in the first anchor hole;
[0024] A second anchor hole is provided on the side wall of the basement wall facing the cross support beam, the axis of the second anchor hole is perpendicular to the axis of the first anchor hole, a second anchor is passed through the second anchor hole, one end of the second anchor is provided outside the basement wall, and the other end passes through the second anchor hole and the connecting short column in sequence and extends into the cross support beam;
[0025] A third anchor hole is opened on the side wall of the second frame column facing the cross support beam, the axis of the third anchor hole is perpendicular to the axis of the first anchor hole, a third anchor bar is passed through the third anchor hole, one end of the third anchor bar is located outside the second frame column, and the other end passes through the third anchor hole and the connecting short column to extend into the cross support beam.
[0026] Furthermore, the step S41 further includes:
[0027] S411. Roughen the side wall of the second frame column facing the cross support beam to expose the internal stirrups of the second frame column, and weld and fix the stirrups of the connecting column to the internal stirrups.
[0028] Furthermore, the first rebar embedding hole, the second rebar embedding hole, and the third rebar embedding hole are filled with structural adhesive.
[0029] Furthermore, the second anchor bar includes a first straight segment and a second straight segment vertically arranged, the first straight segment is arranged in the second anchor bar hole, the second straight segment is arranged on the outside of the basement wall and arranged along the vertical direction, and the two second anchor bars are relatively arranged and fixed by welding.
[0030] Furthermore, the step S7 comprises:
[0031] S71. When pouring concrete, adopt the layered pouring method. The thickness of each layer shall not exceed 500mm and shall be vibrated and compacted.
[0032] The present invention also provides a tower crane foundation dismantling method, based on any of the tower crane foundation construction methods described above, comprising the following steps:
[0033] S110, cutting off the tower crane foundation, retaining the first frame column, and removing the protective plate;
[0034] S120: Reconstruct the first frame column and fill the opening.
[0035] Compared with the prior art, the tower crane foundation construction and dismantling method of the embodiment of the present invention has the following beneficial effects: the pedestal is arranged on the basement floor, and a cross support beam is arranged for reinforcement, and a connecting short column is arranged, one end of the connecting short column is abutted against the end of the cross support beam, and the other end is respectively abutted against the side wall of the basement wall or the second frame column, so that the load on the tower crane foundation can be dispersed to meet the tower crane bearing requirements, avoid affecting the basement floor, facilitate construction, and improve construction efficiency. In addition, laying a protective plate on the basement floor can avoid damage to the basement floor, facilitate the subsequent dismantling of the tower crane foundation, and restore the original structure of the basement. In addition, the pedestal, cross support beam, and connecting short column are integrally cast to form the tower crane foundation, and the overall casting makes the structure stable and reliable. BRIEF DESCRIPTION OF THE DRAWINGS
[0036] Figure 1 is a plan view of a tower crane foundation according to an embodiment of the present invention;
[0037] Figure 2 It is a schematic diagram of the structure of the opening of the basement top plate according to an embodiment of the present invention;
[0038] Figure 3 is a distribution diagram of connecting short columns of a tower crane foundation according to an embodiment of the present invention;
[0039] Figure 4 It is a schematic diagram of the connection between the connecting short column of the tower crane foundation and the basement wall according to an embodiment of the present invention;
[0040] Figure 5 It is a schematic diagram of the connection between the connecting short column of the tower crane foundation and the second frame column of the basement according to an embodiment of the present invention;
[0041] Figure 6 It is a reinforcement plan view of a casting template of a tower crane foundation according to an embodiment of the present invention;
[0042] Figure 7 is a cross-sectional view of a cross-support beam of a tower crane foundation according to an embodiment of the present invention;
[0043] Figure 8 It is a reconstruction construction drawing of the first frame column of the basement in an embodiment of the present invention;
[0044] Fig. 9 It is a schematic diagram of filling a hole in a basement roof according to an embodiment of the present invention.
[0045] In the figure, a1, basement roof; a10, opening; a2, basement floor; a3, basement wall; a4, first frame column; a41, longitudinal reinforcement; a5, second frame column; b, pedestal dimension line; 1, protective plate; 2, cross support beam; 3, connecting short column; 4, tower crane fixing bolts; 5, casting formwork; 6, return top support frame; 7, diagonal brace; 8, second embedded reinforcement; 81, first straight line segment; 82, second straight line segment; 9, third embedded reinforcement. DETAILED DESCRIPTION
[0046] The specific implementation of the present invention is further described in detail below in conjunction with the accompanying drawings and examples. The following examples are used to illustrate the present invention, but are not intended to limit the scope of the present invention.
[0047] In the description of the present invention, it should be understood that the terms "upper", "lower", "front", "back", "inside", "outside", etc. used in the present invention to indicate the orientation or positional relationship are based on the positional relationship shown in the drawings, and are only for the convenience of describing the present invention and simplifying the description, rather than indicating or implying that the referred devices and elements must have a specific orientation, be constructed and operated in a specific orientation, and therefore cannot be understood as a limitation on the present invention.
[0048] In the description of the present invention, it should be understood that the present invention uses the terms "first", "second", etc. to describe various information, but these information should not be limited to these terms, and these terms are only used to distinguish the same type of information from each other. For example, without departing from the scope of the present invention, "first" information may also be referred to as "second" information, and similarly, "second" information may also be referred to as "first" information.
[0049] See also Figures 1 to 7 , as shown, a tower crane foundation construction method of a preferred embodiment of the present invention, relying on a completed basement to carry out tower crane construction, which includes the following steps:
[0050] S1, the basement top plate a1 is provided with an opening a10;
[0051] S2, setting a cap dimension line on the basement floor a2, and chiseling the basement floor a2 within the cap dimension line;
[0052] S3, laying a protective plate 1 on the basement floor a2 outside the said platform dimension line;
[0053] S4, perform steel bar binding construction of the cross support beam and the connecting short column 3 on the protective plate 1; the dimension line of the cap is located at the intersection of the cross support beam, one end of the connecting short column 3 abuts against the other end of the cross support beam 2, and the other end abuts against the side wall of the basement wall a3 or the second frame column a5;
[0054] S5, tower crane fixing bolts 4 are embedded;
[0055] S6, construction of cross support beam 2, connecting short column 3 casting formwork 5;
[0056] S7. Pouring of foundation concrete.
[0057] Among them, see Figure 1 , Figure 2 , Figure 3 , step S1 specifically includes the following steps:
[0058] S11, laying out the opening a10 on the basement top plate a1; before laying out the opening, the material above the basement top plate a1 needs to be cleaned;
[0059] S12, setting up the top-returning support frame 6: setting up the top-returning support frame 6 at the opening a10, the bottom of the top-returning support frame 6 abuts against the basement floor a2, and the top of the top-returning support frame 6 abuts against the basement ceiling a1; when the top-returning support frame 6 is used for the opening a10, it supports the periphery of the opening a10, and in order to prevent the entire cut floor slab at the opening a10 from falling during the cutting process, the top-returning support frame 6 also needs to support the opening a10;
[0060] S13, a receiving plate is arranged in the return support frame 6, and the receiving plate is located directly below the opening a10; the function of the receiving plate is to prevent concrete debris from falling to the ground during the opening of the hole a10, thereby damaging the ground or equipment in the basement, and to avoid cleaning the ground before pouring the foundation concrete, thereby improving construction efficiency;
[0061] S13, drilling holes within the layout range using a water drill, and then cutting the basement top plate a1 along the layout using a rope saw;
[0062] S14, dismantling a portion of the structure of the return support frame 6 directly below the opening a10 is to avoid interference with the return support frame 6 during the subsequent installation of the tower crane.
[0063] In some embodiments, since the basement is provided with a first frame column a4 within the foundation dimension line, in step S2, the first frame column a4 needs to be demolished at the same time, and the vertical longitudinal reinforcement a41 of the first frame column a4 is retained; the longitudinal reinforcement a41 is retained to facilitate the reconstruction of the first frame column a4 after the subsequent demolition of the tower crane foundation.
[0064] Further, in this embodiment, refer to Figure 7 The protective plate 1 includes a foam plate and a template stacked from bottom to top, and its overall thickness is 100 mm.
[0065] Furthermore, in some embodiments, in order to improve the connection strength between the short column 3 and the basement wall a3 and the cross support beam 2, and the connection strength between the short column 3 and the second frame column a5 and the cross support beam 2, refer to Figure 4 , Figure 5 , the step S4 comprises:
[0066] S41, opening a first anchor hole in the basement floor a2 along the vertical direction, and inserting a first anchor in the first anchor hole;
[0067] A second anchor hole is provided on the side wall of the basement wall a3 facing the cross support beam 2, the axis of the second anchor hole is perpendicular to the axis of the first anchor hole, a second anchor 8 is passed through the second anchor hole, one end of the second anchor 8 is provided outside the basement wall a3, and the other end passes through the second anchor hole and the connecting short column 3 in sequence and extends into the cross support beam 2;
[0068] A third anchor hole is opened on the side wall of the second frame column a5 facing the cross support beam 2, the axis of the third anchor hole is perpendicular to the axis of the first anchor hole, a third anchor 9 is passed through the third anchor hole, one end of the third anchor 9 is located outside the second frame column a5, and the other end passes through the third anchor hole and the connecting short column 3 to extend into the cross support beam 2.
[0069] Among them, in step S41, the aperture of the first anchor hole, the second anchor hole, and the third anchor hole is d, and the aperture when drilling is not less than d+4mm. The implantation depth of the first anchor, the second anchor 8, and the third anchor 9 must meet the relevant provisions of 12.2.1-12.2.6 in "GB50367-2013", and shall not be greater than the size of the implanted component along the implantation direction minus 30mm.
[0070] Furthermore, when inserting the rebars in each rebar hole, the dust in the hole needs to be cleaned. At the same time, the first rebar hole, the second rebar hole, and the third rebar hole are filled with structural adhesive to strengthen the connection strength with the rebar. In this embodiment, the structural adhesive is required to use Class A adhesive, and its safety performance indicators must meet the relevant requirements of Section 4.5 of the "Specification for Reinforcement Design of Concrete Structures" (GB50367-2006), and must pass the wet heat aging test. The center distance between each rebar should be no less than 4d, that is, the center distance between adjacent rebars is no less than 4d. Furthermore, in this embodiment, in order to improve the direct connection strength between the second frame column a5 and the connecting short column 3, the step S41 also includes: S411, the side wall of the second frame column a5 facing the cross support beam 2 is roughened to expose the internal stirrups of the second frame column a5, and the stirrups of the connecting column and the internal stirrups are welded and fixed.
[0071] Furthermore, in some embodiments, in order to enhance the connection strength of adjacent second anchor bars 8, the second anchor bars 8 include a first straight segment 81 and a second straight segment 82 arranged vertically, the first straight segment 81 is arranged in the second anchor hole, the second straight segment 82 is arranged on the outside of the basement wall a3, and arranged in the vertical direction, and the second straight segments 82 of the two second anchor bars 8 are arranged opposite to each other and are welded and fixed. For the parts that need to be welded, the structural adhesive in the second anchor hole should preferably use fireproof anchor glue. If ordinary anchor glue is used, the distance between the welding position and the second anchor hole shall not be less than 500mm, and heat insulation measures shall be taken to avoid heat damage to the anchor glue, which will affect the connection strength of the second anchor and the second anchor hole.
[0072] Furthermore, in step S5, refer to Figure 1 The tower crane fixing bolts 4 include four groups of anchor bolts, each group of anchor bolts has four bolts, and the relative positions of the anchor bolts must be accurate. After assembly, the diagonal error of the anchor bolt holes must be no more than 2 mm, so as to ensure the installation of the fixed base section. The anchor bolts are not allowed to be welded or knocked, and the pre-tightening force of the M48-5.8 anchor bolts is 295 kN. The tower crane foundation in the present invention is used for the W6513-6B tower crane with a standard independent height of 51 m.
[0073] Furthermore, in step S6, refer to Figure 6 , Figure 7 The pouring formwork 5 of the cap is made of 1830*915*15mm plywood, the inner keel is made of 40*90 wood square, and the spacing is 200mm; the outer keel is made of 48*3.0 double steel pipe, and the spacing of the tension screw beam in the span direction is 800mm, and the beam height direction is arranged at a starting distance of 100mm and then at a spacing of 400. Furthermore, in order to ensure that the pouring formwork 5 is not deformed during the concrete pouring of the tower crane foundation, which affects the overall strength of the tower crane foundation, therefore, step S6 also includes:
[0074] S61, an inclined brace 7 is arranged outside the casting formwork 5, one end of the inclined brace 7 is fixed to the basement floor a2, and the other end is in contact with the casting formwork 5. Further, in order to improve the supporting strength of the inclined brace, refer to Figure 7 The angle between the axis of the inclined support and the horizontal plane ranges from 45° to 60°.
[0075] Furthermore, step S7 includes: S71, adopting the layered pouring method when pouring concrete, the pouring thickness of each layer shall not exceed 500mm, and vibrating and compacting shall be carried out. Pay close attention to avoid collision with steel bars and embedded parts during vibration. During the pouring process, no less than two groups of test blocks shall be taken for testing to ensure that the concrete strength grade of the tower crane foundation meets the requirements. Before installing the tower crane, it is necessary to ensure that the concrete strength reaches more than 80% of the design strength. At the same time, the tower crane foundation shall be subjected to balanced settlement observation, and the specific method is as follows: 4 16mm steel bar heads are embedded in the 4 corners of the foundation surface of the pedestal as observation points, and observed once before installation, once after installation is completed, once a day in the early stage, and once a week after stabilization. In case of special circumstances, the number of observations shall be increased, and the data shall be summarized for future reference.
[0076] The present invention also provides a tower crane foundation dismantling method, based on any of the tower crane foundation construction methods described above, referring to Figure 8 , Fig. 9 , including the following steps:
[0077] S110, cutting off the tower crane foundation, retaining the first frame column a4, and removing the protective plate 1;
[0078] S120, rebuilding the first frame column a4 and filling the opening a10.
[0079] Among them, see Figure 8 , step S110 is specifically as follows: using a rope saw to cut and chisel the tower crane foundation, retaining the first frame column a4 during the cutting process, modifying and leveling the damaged basement floor a2 with mortar of the same grade, and if the floor reinforcement is damaged and exposed, the reinforcement must be restored and anti-rusted first, and then repaired and leveled, and handed over to the floor unit to restore the original use function. At the same time, the cross support beam and the connecting short column 3 are cut off, and when the connection between the connecting short column 3 and the basement wall a3 and the second frame column a5 is chiseled, the chiseling depth in the side wall of the basement wall a3 or the second frame column a5 is 30mm, avoiding secondary damage to the original wall and column structure, and using a hand grinder to cut the reinforcement exposed outside the wall or frame column; anti-rust treatment is performed on the column reinforcement exposed after the basement wall a3 or the second frame column a5 is chiseled; after the anti-rust treatment is completed, the same grade of mortar is used for repair.
[0080] In step S120, refer to Fig. 9 The specific process of rebuilding the first frame column a4 is as follows: when the tower crane foundation is cut off, the first frame column a4 is cut out with a rope saw, and the longitudinal reinforcement a41 and the newly tied steel bars are welded, and the stirrups are tied according to the original reinforcement. Then the frame column formwork is installed and reinforced, and the same grade of concrete is used to cast it densely.
[0081] The specific process of filling the opening a10 is as follows: after the tower crane is dismantled, a formwork support frame needs to be set up at the opening a10, and the return support frame 6 is re-erected according to the part of the structure directly below the original opening a10. After the erection is completed, the construction joints around the opening a10 are roughened, and the plate reinforcement is chiseled out for at least 15d and cleaned;
[0082] After the roughening is completed, the steel bars are tied. The reserved steel bars at the opening a10 are connected with the later tied steel bars by welding. The welding is single-sided and the welding length is not less than 10d. The steel bar reinforcement is implemented according to the original slab surface reinforcement. After the steel bars are tied, a higher level of expansive anti-seepage concrete is used for pouring and compaction (to reduce the risk of leakage) and cured for 14 days.
[0083] In summary, the embodiment of the present invention provides a tower crane foundation construction and dismantling method, in which the pedestal is arranged on the basement floor a2, and a cross support beam 2 is arranged for reinforcement, and a connecting short column 3 is arranged, one end of the connecting short column 3 is abutted against the end of the cross support beam, and the other end is respectively abutted against the side wall of the basement wall a3 or the second frame column a5, so that the load on the tower crane foundation can be dispersed to meet the tower crane bearing requirements, avoid affecting the basement floor a2, facilitate construction, and improve construction efficiency. In addition, laying a protective plate 1 on the basement floor a2 can avoid damage to the basement floor, facilitate the subsequent dismantling of the tower crane foundation, and restore the original structure of the basement. In addition, the pedestal, the cross support beam 2, and the connecting short column 3 are integrally cast to form the tower crane foundation, which is integrally cast and has a stable and reliable structure.
[0084] The above is only a preferred embodiment of the present invention. It should be pointed out that for ordinary technicians in this technical field, several improvements and substitutions can be made without departing from the technical principles of the present invention. These improvements and substitutions should also be regarded as the scope of protection of the present invention.
Claims
1. A tower crane foundation construction method, It is characterized in that The following steps are involved: S1. Openings are set on the top plate of the basement; S2. Setting a cap dimension line on the basement floor, and chiseling the basement floor within the cap dimension line; S3. Lay a protective plate on the basement floor outside the dimension line of the said cap; S4. Perform steel bar binding construction of the cross support beam and the connecting short column on the protective plate; the dimension line of the cap is located at the intersection of the cross support beam, one end of the connecting short column abuts against the other end of the cross support beam, and the other end abuts against the side wall of the basement wall or the second frame column; S5. Pre-embedded tower crane fixing bolts; S6, construction of pouring formwork for caps, cross support beams and connecting short columns; S7. Pouring of concrete for tower crane foundation.
2. The tower crane foundation construction method according to claim 1, It is characterized in that The step S1 comprises the following steps: S11, laying out the opening on the basement roof; S12, erecting a return support frame: setting a return support frame at the opening, wherein the bottom of the return support frame abuts against the basement floor, and the top of the return support frame abuts against the basement roof; S13, providing a material receiving plate in the return support frame, wherein the material receiving plate is located directly below the opening; S13, drilling holes within the layout range using a water drill, and then cutting the basement top plate along the layout using a rope saw; S14, dismantling the partial structure of the return support frame directly below the opening.
3. The tower crane foundation construction method according to claim 1, It is characterized in that The step S2 further includes: breaking the first frame column located within the dimension line of the cap, and retaining the vertical longitudinal reinforcement; 4. The tower crane foundation construction method according to claim 1, It is characterized in that The step S6 further comprises: S61. An oblique brace is provided on the outside of the casting formwork, one end of the oblique brace is fixed to the basement floor, and the other end is in contact with the casting formwork.
5. The tower crane foundation construction method according to claim 1, It is characterized in that The step S4 comprises: S41, opening a first anchor hole in the basement floor along the vertical direction, and inserting a first anchor in the first anchor hole; A second anchor hole is provided on the side wall of the basement wall facing the cross support beam, the axis of the second anchor hole is perpendicular to the axis of the first anchor hole, a second anchor is passed through the second anchor hole, one end of the second anchor is provided outside the basement wall, and the other end passes through the second anchor hole and the connecting short column in sequence and extends into the cross support beam; A third anchor hole is opened on the side wall of the second frame column facing the cross support beam, the axis of the third anchor hole is perpendicular to the axis of the first anchor hole, a third anchor bar is passed through the third anchor hole, one end of the third anchor bar is located outside the second frame column, and the other end passes through the third anchor hole and the connecting short column to extend into the cross support beam.
6. The tower crane foundation construction method according to claim 5, It is characterized in that The step S41 further includes: S411. Roughen the side wall of the second frame column facing the cross support beam to expose the internal stirrups of the second frame column, and weld and fix the stirrups of the connecting column to the internal stirrups.
7. The tower crane foundation construction method according to claim 5, Features: The first rebar embedding hole, the second rebar embedding hole, and the third rebar embedding hole are filled with structural adhesive.
8. The tower crane foundation construction method according to claim 5, Features: The second anchor bar includes a first straight segment and a second straight segment vertically arranged, the first straight segment is arranged in the second anchor bar hole, the second straight segment is arranged on the outside of the basement wall and arranged along the vertical direction, and the two second anchor bars are relatively arranged and fixed by welding.
9. The tower crane foundation construction method according to claim 1, It is characterized in that The step S7 comprises: S71. When pouring concrete, adopt the layered pouring method. The thickness of each layer shall not exceed 500mm and shall be vibrated and compacted.
10. A tower crane foundation dismantling method, based on the tower crane foundation construction method according to any one of claims 1 to 9, Features , including the following steps: S110, cutting off the tower crane foundation, retaining the first frame column, and removing the protective plate; S120: Reconstruct the first frame column and fill the opening.