Construction method for reinforcing existing railroad bed based on pressure balance type grouting

By implanting the capsules in the railway subgrade and performing different grouting, the roadbed is reinforced, which solves the problem of existing grouting and reinforcement technology affecting railway operations, and realizes a disturbance-free roadbed reinforcement and safe construction process, reducing operating costs .

CN118911216APending Publication Date: 2024-11-08BEIJING ZHONGYAN DADI TECH CO LTD
View PDF 0 Cites 0 Cited by

Patent Information

Application Number
CN202411288115.5
Authority / Receiving Office
CN · China
Patent Type
Applications(China)
Current Assignee / Owner
Filing Date
2024-09-14
Publication Date
2024-11-08

AI Technical Summary

Technical Problem

The existing grouting and reinforcement technology needs to occupy construction space during the construction process, affecting the normal operation of the railway. The new construction section is highly sensitive, affecting the safety of railway operation, and it is difficult to achieve disturbance-free roadbed reinforcement.

Method used

The pressure-balanced grouting method is used to implant the capsule in the railway subgrade, and the road subgrade is reinforced through differentiated grouting. The side construction avoids the impact on railway operations. The capsule is always in a support or disturbance state during the construction process. , different grouting pressure control is carried out according to the settlement amount.

Benefits of technology

The reinforcement of the roadbed under normal operation conditions of the railway is achieved, the impact of construction on railway operation is avoided, the safety of the construction process and the uniform settlement of the roadbed are ensured, and the operation cost of railways is reduced.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN118911216A_ABST
    Figure CN118911216A_ABST
Patent Text Reader

Abstract

The invention discloses a construction method for reinforcing an existing railroad bed based on pressure balance type grouting, and belongs to the technical field of foundation treatment.The construction method comprises the following specific construction steps that a bag body is implanted into the railroad bed, differential grouting is conducted on the bag body, and then the railroad bed is reinforced. Forming holes in the roadbed; implanting a capsule body; grouting for the first time; performing differential grouting; and supplementing slurry and maintaining. The influence on normal operation of the railway is avoided through side construction, differentiated jacking is achieved through the arrangement of the bag body, different heights are jacked according to different settling volumes, in the construction process, a supporting stage or an undisturbed state is always in the construction process, and the safety of railway operation is not influenced.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The invention relates to the technical field of foundation treatment, and in particular to a construction method for reinforcing an existing railway roadbed based on pressure-balanced grouting. Background Art

[0002] With the acceleration of urbanization, the rapid layout of the railway network has also become a major problem at present. With the construction of the railway network and the speed-up of traditional subways, differences in soil quality, density, moisture content, etc. in different strata will lead to different settlement rates in different parts. Long-term vehicle operation will exert load on the roadbed. Different vehicle types, speeds and other factors will also affect the settlement of the roadbed. Changes in groundwater levels, precipitation and other factors will also affect the settlement of the roadbed. All these factors will lead to uneven settlement of the roadbed.

[0003] When uneven settlement occurs on the high-speed railway subgrade, it may cause the track line to become uneven, increase the vibration and noise during train operation, and affect operational safety; it may cause the track to deform, increase the friction of the vehicle on the track, and accelerate vehicle wear, which in turn leads to frequent maintenance of the track and vehicles, and increase railway operating costs; uneven tracks may cause bumps during train operation, affecting passenger comfort and may even cause passenger discomfort or accidents.

[0004] At present, grouting reinforcement is a commonly used technology for treating uneven settlement. Its principle is to improve the physical and mechanical properties of the soil by injecting specific materials (such as cement slurry, polymer slurry, etc.) into the roadbed soil, thereby improving the bearing capacity and stability of the soil and reducing the unevenness of settlement. However, conventional grouting reinforcement requires a certain amount of construction space, affecting the normal operation of the railway line, and requiring traffic control and safety assurance during construction. In addition, the sensitivity of the new construction section is relatively high, and it needs to be maintained and consolidated before it can be put into normal operation. Therefore, it has a greater impact on the operation of the railway. Summary of the invention

[0005] In view of the above technical problems existing in the prior art, the present invention proposes a construction method for reinforcing the existing railway subgrade based on pressure-balanced grouting, which overcomes the shortcomings of the prior art. The construction on the side avoids affecting the normal operation of the railway, and the setting of the bladder realizes differentiated jacking, jacking different heights according to different settlement amounts, and is always in the support stage or undisturbed state during the construction process, which does not affect the safety of railway operation.

[0006] In order to achieve the above object, the present invention adopts the following technical solution: A construction method for reinforcing an existing railway subgrade based on pressure-balanced grouting, wherein a bladder is implanted in the railway subgrade, and differential grouting is performed on the bladder to reinforce the subgrade. The specific construction steps are as follows: Step 1: Determine the location of railway settlement By observing and measuring the railway subgrade surface, the settlement of the settlement point or settlement area is determined, and the settlement contour lines are drawn based on the measurement data; Step 2: Roadbed opening The hole positions are set according to the settlement contour lines. The hole positions are designed to be on the side of the roadbed. According to the size and distribution of the settlement area, the first hole is set at the maximum settlement position. The second and third holes are set on both sides with the first hole as the center. The distance between the first and second holes is controlled according to the settlement amount. If the settlement area is large, the fourth and fifth holes are set on both sides. The distance between the two holes is set according to the settlement amount. If the settlement area is too large, more symmetrically distributed holes are set by analogy. The holes are opened by spiral drilling in combination with full casing construction. The holes are opened horizontally from one side of the roadbed. The length of the horizontal hole is less than the width of the roadbed of the section. Step 3: Implant the capsule After each hole is opened, the bladder is placed in the set position from the casing, and the bladder grouting pipe and the bladder grouting pipe are inserted into the bladder until the deepest bladder is placed; Step 4: Primary Grouting After the bladder is arranged in the same opening, the hole is immediately injected with non-bleeding cement slurry through the grouting pipe. As the casing is pulled out, the space in the opening is gradually grouted and the grouting pipe is pulled out. Step 5: Differential Grouting When the non-bleeding cement slurry in the opening space begins to solidify, start injecting quick-setting cement slurry into the bladder. The grouting flow rate is kept constant at 3L / min-5L / min, and the grouting pressure is injected at 0.1MPa. When the grouting flow rate remains unchanged and the grouting pressure suddenly increases, stop grouting, and seal the bladder grouting pipe port with a grout stopper. When multiple bladders are set in the opening, follow the above process until all bladders are grouted; After the quick-setting cement slurry in the bladder is initially set, different grouting pressures are used to perform differential grouting on the bladder according to different settlement conditions. The grouting pressure is related to the ground settlement. When the settlement is between 0 and 10 mm, the grouting pressure of the bladder in this area is 1.5 MPa to 2.5 MPa. When the settlement is between 10 and 20 mm, the grouting pressure of the bladder in this area is 2.0 MPa to 3.0 MPa. When the settlement is greater than 20 mm, the grouting pressure of the bladder in this area is 2.5 MPa to 3.5 MPa. Step 6: Grouting and maintenance Repeat grouting of the bladder every 10 minutes to 30 minutes, with the grouting pressure being the same as the first grouting pressure to ensure that the bladder expands to the designed extent.

[0007] Preferably, in step 2, a hole is opened in the roadbed, and the diameter of the hole is 110mm~250mm, and the distance between the two holes is controlled according to the settlement: when the settlement is between 0-10mm, the distance between the two holes is 900mm-1200mm; when the settlement is between 10mm-20mm, the distance between the two holes is 700mm-1000mm; when the settlement is greater than 20mm, the distance between the two holes is 500mm-800mm.

[0008] Preferably, the capsule has a cylindrical structure when expanded, and is made of a soft composite film or steel. The thickness of the soft composite film is 1.0 mm-3.0 mm, and the thickness of the steel is 0.1 mm-1.0 mm.

[0009] Preferably, in step 3, the distance between adjacent capsules is at least 10 cm and at most 500 cm.

[0010] Preferably, the water-cement ratio of the quick-setting cement slurry in the capsule to the non-bleeding cement slurry in the opening is 0.6-1.0.

[0011] Beneficial technical effects brought by the present invention: By constructing on the side, the impact on the normal operation of the railway is avoided. The differentiated jacking is achieved through the setting of the bladder. Different heights are lifted according to different settlement amounts. During the construction process, it is always in the support stage or undisturbed state, which does not affect the safety of railway operation. BRIEF DESCRIPTION OF THE DRAWINGS

[0012] Figure 1 The present invention is a schematic diagram of a railway subgrade section involved in a construction method for reinforcing an existing railway subgrade based on pressure-balanced grouting.

[0013] Figure 2 The diagram is a schematic diagram of the positional relationship between the deepest bladder implanted into the opening in a construction method for reinforcing an existing railway subgrade based on pressure-balanced grouting according to the present invention.

[0014] Figure 3 The present invention is a schematic structural diagram of the expansion of a bladder in a construction method for reinforcing an existing railway subgrade based on pressure-balanced grouting.

[0015] Among them, 1-railway; 2-ballast bed; 3-railway roadbed; 4-roadbed opening; 5-bladder; 6-bladder grouting pipe; 7-grouting pipe; 8-return grouting pipe; 9-casing. DETAILED DESCRIPTION

[0016] Unless otherwise specified, the positional relationships of up, down, left, and right described herein correspond to the up, down, left, and right in real life. The present invention is further described in detail below in conjunction with the accompanying drawings and specific embodiments: Embodiment 1:

[0017] like Figures 1 to 3 As shown, a construction method for reinforcing an existing railway subgrade based on pressure-balanced grouting is shown, wherein a bladder 5 is implanted in a railway subgrade 3, and differential grouting is performed on the bladder 5 to reinforce the subgrade. The specific construction steps are as follows: Step 1: Determine the location of railway settlement By observing and measuring the surface of the railway embankment 3, the settlement of the settlement point or settlement area is determined, and the settlement contour lines are drawn according to the measurement data; Step 2: Roadbed opening 4 The hole positions are set according to the settlement contour lines. The hole positions are designed to be on the side of the roadbed. According to the size and distribution of the settlement area, the first hole is set at the maximum settlement position. The second and third holes are set on both sides with the first hole as the center. The distance between the first and second holes is controlled according to the settlement amount. If the settlement area is large, the fourth and fifth holes are set on both sides. The distance between the two holes is set according to the settlement amount. If the settlement area is too large, more symmetrically distributed holes are set by analogy. The holes are opened by using a spiral drill in combination with a full casing 9. The holes are opened horizontally from one side of the roadbed. The length of the horizontal hole is less than the width of the roadbed of the section. Step 3: Implantation of capsule 5 After each hole is opened, the bladder 5 is placed in the set position from the casing 9, and the bladder grouting pipe 6 and the bladder grouting pipe 8 are inserted into the bladder 5 until the deepest bladder 5 is placed; Step 4: Primary Grouting After the bladder 5 in the same opening is arranged, the hole is immediately injected with non-bleeding cement slurry through the grouting pipe 7. As the casing 9 is pulled out, the space in the opening is gradually grouted and the grouting pipe 7 is pulled out. Step 5: Differential Grouting When the non-bleeding cement slurry in the opening space begins to solidify, start injecting quick-setting cement slurry into the capsule 5, the grouting flow rate remains constant at 3L / min-5L / min, and the grouting pressure begins to be injected at 0.1MPa. When the grouting flow rate remains constant and the grouting pressure suddenly increases, stop grouting, and use a stop plug to seal the capsule grouting pipe 6. When multiple capsules 5 are arranged in the opening, follow the above process until all capsules 5 are grouted; After the quick-setting cement slurry in the capsule 5 is initially set, different grouting pressures are used to perform differential grouting on the capsule according to different settlement conditions. The grouting pressure is related to the ground settlement. When the settlement is between 0 and 10 mm, the grouting pressure of the capsule 5 in this area is 1.5 MPa to 2.5 MPa. When the settlement is between 10 and 20 mm, the grouting pressure of the capsule 5 in this area is 2.0 MPa to 3.0 MPa. When the settlement is greater than 20 mm, the grouting pressure of the capsule 5 in this area is 2.5 MPa to 3.5 MPa. Step 6: Grouting and maintenance The bladder 5 is repeatedly grouted every 10-30 minutes, and the grouting pressure is the same as the first grouting pressure to ensure that the bladder 5 expands to the designed degree.

[0018] Preferably, in the step 2, the roadbed hole 4 has a diameter of 110 mm to 250 mm, and the distance between the two holes is controlled according to the settlement: when the settlement is between 0 and 10 mm, the distance between the two holes is 900 mm to 1200 mm; when the settlement is between 10 mm and 20 mm, the distance between the two holes is 700 mm to 1000 mm; when the settlement is greater than 20 mm, the distance between the two holes is 500 mm to 800 mm.

[0019] Preferably, the capsule 5 has a cylindrical structure when expanded, and is made of a soft composite film or steel. The thickness of the soft composite film is 1.0 mm-3.0 mm, and the thickness of the steel is 0.1 mm-1.0 mm.

[0020] Preferably, in step 3, the distance between adjacent capsules 5 is at least 10 cm and at most 500 cm.

[0021] Preferably, the water-cement ratio of the quick-setting cement slurry in the bladder 5 to the non-bleeding cement slurry in the opening is 0.6-1.0. Embodiment 2:

[0022] The roadbed of a railway section is reinforced, and the railway line is operating normally during the reinforcement process. The specific construction measures are as follows: like Figures 1 to 3 As shown, a construction method for reinforcing an existing railway subgrade based on pressure-balanced grouting is shown, wherein a bladder 5 is implanted in a railway subgrade 3, and differential grouting is performed on the bladder 5 to reinforce the subgrade. The specific construction steps are as follows: Step 1: Determine the location of railway settlement By observing and measuring the surface of the railway embankment 3, the settlement of the settlement point or settlement area is determined, and the settlement contour lines are drawn according to the measurement data; the maximum settlement of the embankment in this project is 27mm, and the maximum settlement contour line range is about 1.53 square meters. The location of the railway is the maximum settlement point, the area with settlement in the range of 10mm-20mm is about 9.38 square meters, and the area with settlement in the range of 0-10mm is about 15.17 square meters.

[0023] Step 2: Roadbed opening 4 The hole positions are set according to the settlement contour lines. The hole positions are designed on the sides of the roadbed. According to the size and distribution of the settlement area, the first hole is set at the maximum settlement position, and the second and third holes are set on both sides with the first hole as the center. The distance between the first and second holes is controlled according to the settlement amount. If the settlement area is large, the fourth and fifth holes are set on both sides. The distance between the two holes is set according to the settlement amount. If the settlement area is too large, more symmetrically distributed holes are set by analogy. According to the settlement distribution, a total of 11 hole positions are set, symmetrically distributed on both sides with the deepest settlement point as the center, among which the three middle hole positions are located at the position where the settlement exceeds 20mm, two hole positions on both sides are located at the position where the settlement is 10mm-20mm, and the two outer hole positions are located at the position where the settlement is 0mm-10mm. The hole is drilled horizontally from one side of the roadbed using a spiral drill in conjunction with full casing 9. The length of the horizontal hole is less than the width of the roadbed in this section. The hole length for this project is 10m, passing through the entire sinking area, and the hole diameter is 127mm.

[0024] Step 3: Implantation of capsule 5 After each hole is opened, the bladder 5 is placed at the set position from the casing 9, and the bladder grouting pipe 6 and the bladder grouting pipe 8 are inserted into the bladder 5 until the deepest bladder 5 is placed. The deepest settlement in the same hole is 30 cm away from the nearest adjacent bladder 5, and 50 cm away from the adjacent one further away. Four bladders 5 are arranged in one hole, and a total of 44 bladders 5 are arranged in the whole project.

[0025] Step 4: Primary Grouting After the bladder 5 in the same opening is arranged, the hole is immediately injected with non-bleeding cement slurry through the grouting pipe 7. As the casing 9 is pulled out, the space in the opening is gradually grouted and the grouting pipe 7 is pulled out. Step 5: Differential Grouting When the non-bleeding cement slurry in the opening space begins to solidify, start injecting quick-setting cement slurry into the capsule 5, the grouting flow rate remains constant at 3L / min-5L / min, and the grouting pressure begins to be injected at 0.1MPa. When the grouting flow rate remains constant and the grouting pressure suddenly increases, stop grouting, and use a stop plug to seal the capsule grouting pipe 6. When multiple capsules 5 are arranged in the opening, follow the above process until all capsules 5 are grouted; After the quick-setting cement slurry in the bladder 5 is initially set, different grouting pressures are used to perform differential grouting on the bladder according to different settlement conditions. The differential grouting mainly involves different grouting pressures, which are related to the ground settlement. When the settlement is between 0 and 10 mm, the grouting pressure of the bladder 5 in this area is 1.5 MPa. When the settlement is between 10 and 20 mm, the grouting pressure of the bladder 5 in this area is 2.0 MPa. When the settlement is greater than 20 mm, the grouting pressure of the bladder 5 in this area is 2.5 MPa. The distance between the opening and the rail is generally 3 m to 5 m. If the pressure of conventional soil at a depth of 5 m is about 0.9 MPa, Step 6: Grouting and maintenance The bladder 5 is repeatedly grouted every 20 minutes, and the grouting pressure is the same as the first grouting pressure to ensure that the bladder 5 expands to the designed degree.

[0026] Preferably, the capsule 5 has a cylindrical structure when expanded, and is made of a soft composite film or steel. The thickness of the soft composite film is 1.0 mm-3.0 mm, and the thickness of the steel is 0.1 mm-1.0 mm.

[0027] Preferably, the water-cement ratio of the quick-setting cement slurry in the bladder 5 to the non-bleeding cement slurry in the opening is 0.6.

[0028] Of course, the above description is not a limitation of the present invention, and the present invention is not limited to the above examples. Changes, modifications, additions or substitutions made by technicians in this technical field within the essential scope of the present invention also fall within the protection scope of the present invention.

Claims

1. A construction method for reinforcing an existing railway subgrade based on pressure-balanced grouting, characterized in that: The bladder is implanted in the railway roadbed, and differential grouting is performed on the bladder to reinforce the roadbed. The specific construction steps are as follows: Step 1: Determine the location of railway settlement By observing and measuring the railway subgrade surface, the settlement of the settlement point or settlement area is determined, and the settlement contour lines are drawn based on the measurement data; Step 2: Roadbed opening The hole positions are set according to the settlement contour lines. The hole positions are designed to be on the side of the roadbed. According to the size and distribution of the settlement area, the first hole is set at the maximum settlement position. The second and third holes are set on both sides with the first hole as the center. The distance between the first and second holes is controlled according to the settlement amount. If the settlement area is large, the fourth and fifth holes are set on both sides. The distance between the two holes is set according to the settlement amount. If the settlement area is too large, more symmetrically distributed holes are set by analogy. The holes are opened by spiral drilling in combination with full casing construction. The holes are opened horizontally from one side of the roadbed. The length of the horizontal hole is less than the width of the roadbed of the section. Step 3: Implant the capsule After each hole is opened, the bladder is placed in the set position from the casing, and the bladder grouting pipe and the bladder grouting pipe are inserted into the bladder until the deepest bladder is placed; Step 4: Primary Grouting After the bladder is arranged in the same opening, the hole is immediately injected with non-bleeding cement slurry through the grouting pipe. As the casing is pulled out, the space in the opening is gradually grouted and the grouting pipe is pulled out. Step 5: Differential Grouting When the non-bleeding cement slurry in the opening space begins to solidify, start injecting quick-setting cement slurry into the bladder. The grouting flow rate is kept constant at 3L / min-5L / min, and the grouting pressure is injected at 0.1MPa. When the grouting flow rate remains unchanged and the grouting pressure suddenly increases, stop grouting, and seal the bladder grouting pipe port with a grout stopper. When multiple bladders are set in the opening, follow the above process until all bladders are grouted; After the quick-setting cement slurry in the bladder is initially set, different grouting pressures are used to perform differential grouting on the bladder according to different settlement conditions. The grouting pressure is related to the ground settlement. When the settlement is between 0 and 10 mm, the grouting pressure of the bladder in this area is 1.5 MPa to 2.5 MPa. When the settlement is between 10 and 20 mm, the grouting pressure of the bladder in this area is 2.0 MPa to 3.0 MPa. When the settlement is greater than 20 mm, the grouting pressure of the bladder in this area is 2.5 MPa to 3.5 MPa. Step 6: Grouting and maintenance Repeat grouting of the bladder every 10 minutes to 30 minutes, with the grouting pressure being the same as the first grouting pressure to ensure that the bladder expands to the designed extent.

2. A construction method for reinforcing an existing railway subgrade based on pressure-balanced grouting according to claim 1, characterized in that: In the step 2, a hole is opened in the roadbed, and the diameter of the hole is 110mm-250mm. The distance between the two holes is controlled according to the settlement: when the settlement is between 0-10mm, the distance between the two holes is 900mm-1200mm; when the settlement is between 10mm-20mm, the distance between the two holes is 700mm-1000mm; when the settlement is greater than 20mm, the distance between the two holes is 500mm-800mm.

3. The construction method for reinforcing an existing railway subgrade based on pressure-balanced grouting according to claim 1 is characterized in that: The bladder has a cylindrical structure when expanded. The bladder is made of a soft composite film or steel. The thickness of the soft composite film is 1.0mm-3.0mm, and the thickness of the steel is 0.1mm-1.0mm.

4. The construction method for reinforcing an existing railway subgrade based on pressure-balanced grouting according to claim 1 is characterized in that: In step 3, the minimum distance between adjacent capsules is 10 cm and the maximum is 500 cm.

5. The construction method for reinforcing an existing railway subgrade based on pressure-balanced grouting according to claim 1 is characterized in that: The water-cement ratio of the quick-setting cement slurry in the capsule to the non-bleeding cement slurry in the opening is 0.6-1.0.