Building construction post-pouring hole template reinforcing structure and construction method thereof
By using empty mold pipes and water stop mold box structures in construction, the water seepage path is extended and the design of hanging rods and support rods is solved, and the leakage risk and construction efficiency problems after the holes in the laying of the floor slab are closed is achieved, thereby reducing seepage The effects of missing risks and saving resources.
Patent Information
- Application Number
- CN202411331088.5
- Authority / Receiving Office
- CN · China
- Patent Type
- Applications(China)
- Current Assignee / Owner
- Filing Date
- 2024-09-24
- Publication Date
- 2024-11-08
- Estimated Expiration
- 2044-09-24
AI Technical Summary
During construction, the risk of leakage after the laying holes on the floor slabs is sealed is high, and when the floor height is large, the support range of the frame needs to be increased, occupying the construction area, resulting in the process being easily lagged behind.
The structure of empty mold pipe and water stop mold box is adopted. By forming a water stop mold box in the middle of the empty mold pipe, concrete is poured on both sides of the mold box and the empty mold pipe, a water stop module is formed, and the water seepage path is extended, combining the boom and The design of the support rod realizes secondary pouring to cure the concrete and form an effective sealing structure.
It reduces the risk of later leakage of floor slabs, reduces the secondary steel pipe support form, avoids the impact of the process of separate support frames, and has the economic benefits of green and environmentally friendly, material-saving and low-carbon, and saving labor.
Smart Images

Figure CN118911416A_ABST
Abstract
Description
Technical Field
[0001] The invention relates to the technical field of building construction, and in particular to a building construction post-cast hole formwork reinforcement structure and a construction method thereof. Background Art
[0002] During construction, holes are often reserved on the floor for laying out lines. The holes are sealed with hanging formwork in the later stage. When the hanging formwork is used for support, if the screw holes are not sealed tightly enough, the risk of floor leakage in the later stage is high.
[0003] In addition, when using a separate support frame for support, when the floor height is large, it is necessary to increase the frame support range, occupying the remaining construction area, and the process is prone to delays. Summary of the invention
[0004] In order to overcome the defects of the prior art, a post-cast hole template reinforcement structure and a construction method thereof are provided to solve the problem of high leakage risk after the existing floor slab layout holes are sealed.
[0005] In order to achieve the above-mentioned purpose, a post-cast hole formwork reinforcement structure for building construction is provided, comprising:
[0006] A hollow mold tube is vertically arranged in the post-casting hole of the floor slab, the height of the hollow mold tube is adapted to the thickness of the floor slab, the middle part of the hollow mold tube protrudes outward to form a water-stop mold box, the inner cavity of the water-stop mold box is connected with the inner cavity of the hollow mold tube to form a first casting space, the bottom of the floor slab is attached with a template arranged below the post-casting hole, a second casting space is formed between the template and the inner wall of the hollow mold tube and the post-casting hole, and the template is provided with a through hole aligned with the lower pipe opening of the hollow mold tube;
[0007] A suspension rod is movably arranged in the hollow mold tube and the through hole, and a support member is detachably mounted on the lower end of the suspension rod, and the support member is supported on the template;
[0008] A reaction piece, two supporting rods are placed on the upper opening of the post-cast hole, the two supporting rods are arranged on opposite sides of the upper end of the hanger, the reaction piece is detachably installed on the upper end of the hanger, the two supporting rods are supported on the reaction piece, after the concrete poured in the second pouring space is solidified and the hanger is removed, concrete is poured in the first pouring space to consolidate and form a water-stop module.
[0009] Furthermore, the water-stop mold box includes a bottom plate, a top plate and side plates, the top plate and the bottom plate are annular and have matching shapes and sizes, the inner edges of the top plate and the bottom plate are connected to the empty mold tube, and the side plates are connected to the outer edges of the top plate and the bottom plate.
[0010] Furthermore, the top plate and the bottom plate are in an elliptical ring shape.
[0011] Furthermore, water-swellable water stop strips are respectively provided on the inner side of the junction between the upper part of the side plate and the top plate and on the inner side of the junction between the lower part of the side plate and the bottom plate.
[0012] Furthermore, the upper end and the lower end of the suspension rod are respectively formed with external threads, the reaction member and the support member are respectively provided with threaded holes, the reaction member is screwed into the upper end of the suspension rod, and the support member is screwed into the lower end of the suspension rod.
[0013] Furthermore, the concrete poured in the first pouring space is foamed concrete.
[0014] The present invention provides a construction method for a post-cast hole formwork reinforcement structure for building construction, comprising the following steps:
[0015] Fit the formwork to the bottom of the floor slab to seal the lower opening of the post-casting hole;
[0016] Vertically install the suspension rod in the post-casting hole so that the lower end of the suspension rod penetrates the through hole of the template;
[0017] Installing a support member at the lower end of the suspension rod so that the support member is supported on the template;
[0018] Sleeving the empty mold tube on the suspension rod so that the empty mold tube is vertically arranged in the post-casting hole;
[0019] Two support rods are placed on the upper openings of the post-casting holes, and the two support rods are arranged on opposite sides of the upper end of the suspension rod;
[0020] Installing a reaction piece at the upper end of the suspension rod so that the two support rods are supported on the reaction piece;
[0021] pouring concrete in a second pouring space formed between the template, the empty mold tube, and the inner wall of the post-casting hole;
[0022] After the concrete poured in the second pouring space is solidified, removing the suspension rod;
[0023] Concrete is poured into a first pouring space formed by the inner cavity of the water-stop mold box being connected with the inner cavity of the empty mold tube to solidify and form a water-stop module.
[0024] The beneficial effect of the present invention is that the post-cast hole formwork reinforcement structure of the present invention can reduce the risk of leakage of the floor slab in the later stage. Specifically, a water-stop mold box is formed through the middle part of the empty mold tube, and concrete is poured in the water-stop mold box and the empty mold tube to form a water-stop module. The water seepage path is extended on the inner and outer sides of the empty mold tube, respectively, reducing the risk of leakage caused by blocking the post-cast holes of the floor slab. The post-cast hole formwork reinforcement structure of the present invention reduces the secondary steel pipe formwork, and when the floor height is large, there is no need to use a separate support for support. It is green and environmentally friendly, saves materials and carbon, saves labor, and has strong economic benefits. BRIEF DESCRIPTION OF THE DRAWINGS
[0025] Other features, objects and advantages of the present application will become more apparent by reading the detailed description of non-limiting embodiments made with reference to the following drawings:
[0026] Figure 1 It is a structural schematic diagram of a post-cast hole formwork reinforcement structure for building construction according to an embodiment of the present invention.
[0027] Figure 2 It is a structural schematic diagram of the lower part of the post-cast hole formwork reinforcement structure for building construction according to an embodiment of the present invention.
[0028] Figure 3 It is a cross-sectional view of a post-cast hole formwork reinforcement structure for building construction according to an embodiment of the present invention.
[0029] Figure 4 The figure is a schematic diagram of the assembly state of the hollow mold tube and the suspension rod according to an embodiment of the present invention.
[0030] Figure 5 It is a schematic diagram of the state of the post-cast holes of the floor slab after pouring and sealing according to an embodiment of the present invention. DETAILED DESCRIPTION
[0031] The present application is further described in detail below in conjunction with the accompanying drawings and embodiments. It is to be understood that the specific embodiments described herein are only used to explain the relevant invention, rather than to limit the invention. It is also necessary to explain that, for ease of description, only the parts related to the invention are shown in the accompanying drawings.
[0032] It should be noted that, in the absence of conflict, the embodiments and features in the embodiments of the present application can be combined with each other. The present application will be described in detail below with reference to the accompanying drawings and in combination with the embodiments.
[0033] Reference Figures 1 to 5 As shown, the present invention provides a post-cast hole formwork reinforcement structure for building construction, comprising: an empty formwork tube 1, a hanger 2, and a reaction piece 3.
[0034] In this embodiment, the hollow mold pipe is a cast iron pipe. The hollow mold pipe 1 is vertically arranged in the post-casting hole 40 of the floor slab 4. The height of the hollow mold pipe 1 is adapted to the thickness of the floor slab 4.
[0035] The middle part of the hollow mold tube 1 bulges outward to form a water-stop mold box 11. The water-stop mold box and the hollow mold tube are integrally cast and formed. The inner cavity of the water-stop mold box 11 is connected with the inner cavity of the hollow mold tube 1 to form a first casting space.
[0036] See also Figure 1 and Figure 2 As shown, the bottom of the floor 4 is attached with a template 5 arranged below the post-casting hole 40. A second casting space is formed between the template 5 and the inner wall of the empty mold tube 1 and the post-casting hole 40. The template 5 is provided with a perforation aligned with the lower pipe opening of the empty mold tube 1.
[0037] The suspension rod 2 is movably arranged in the hollow mold tube 1 and the perforation. A support member 21 is detachably mounted on the lower end of the suspension rod 2. The support member 21 is supported on the template 5.
[0038] As a preferred embodiment, the outer diameter of the suspension rod is adapted to the inner diameter of the hollow mold tube. The hollow mold tube and the water stop mold box are integrally cast into a vertical pipe with a bulge in the middle.
[0039] Continue reading Figure 1 and Figure 2 As shown, two support rods 31 are placed on the upper opening of the post-casting hole 40. The two support rods 31 are arranged on opposite sides of the upper end of the suspension rod 2. The reaction member 3 is detachably mounted on the upper end of the suspension rod 2. The two support rods 31 are supported on the reaction member 3.
[0040] For the sealing of the post-cast holes, pouring is performed twice, that is, pouring concrete in the second pouring space first, and then pouring concrete in the first pouring space. After the concrete 6 poured in the second pouring space is solidified and the hanger 2 is removed, pouring concrete in the first pouring space to consolidate and form a water stop module 7.
[0041] As a preferred embodiment, the water stop mold box 11 includes a bottom plate 111, a top plate 112 and a side plate 113. The top plate 112 and the bottom plate 111 are annular. The shape and size of the top plate 112 are adapted to the shape and size of the bottom plate 111. The inner edges of the top plate 112 and the bottom plate 111 are connected to the hollow mold tube 1. The side plate 113 is connected to the outer edges of the top plate 112 and the bottom plate 111.
[0042] In this embodiment, the top plate 112 and the bottom plate 111 are in the shape of an elliptical ring. The overall shape of the water stop mold box is an elliptical shape.
[0043] A water-swelling water stop strip 114 is provided on the inner side of the junction between the upper part of the side plate 113 and the top plate 112. A water-swelling water stop strip 114 is provided on the inner side of the junction between the lower part of the side plate 113 and the bottom plate 111.
[0044] As a preferred embodiment, the upper and lower ends of the suspension rod 2 are respectively formed with external threads. The reaction member 3 and the support member 21 are respectively provided with threaded holes. The reaction member 3 is screwed to the upper end of the suspension rod 2. The support member 21 is screwed to the lower end of the suspension rod 2.
[0045] In this embodiment, the concrete poured in the first pouring space is foamed concrete.
[0046] The present invention provides a construction method for a post-cast hole formwork reinforcement structure for building construction, comprising the following steps:
[0047] S1. Attach the template 5 to the bottom of the floor slab 4 to seal the lower opening of the post-casting hole 40.
[0048] S2, vertically install the suspension rod 2 in the post-casting hole 40 so that the lower end of the suspension rod 2 passes through the through hole of the template 5.
[0049] S3. Install the support member 21 at the lower end of the suspension rod 2 so that the support member 21 is supported on the template 5.
[0050] S4, sleeve the empty mold tube 1 on the suspension rod 2, so that the empty mold tube 1 is vertically arranged in the post-casting hole 40.
[0051] S5. Two support rods 31 are placed on the upper opening of the post-casting hole 40 . The two support rods 31 are arranged on opposite sides of the upper end of the suspension rod 2 .
[0052] S6. Install the reaction piece 3 at the upper end of the suspension rod 2 so that the two support rods 31 are supported on the reaction piece 3.
[0053] S7, pouring concrete 6 in the second pouring space formed between the template 5 and the inner wall of the empty mold tube 1 and the post-casting hole 40.
[0054] S8. After the concrete 6 poured in the second pouring space is solidified, the hanger 2 is removed.
[0055] S9, pouring concrete into the first pouring space formed by the inner cavity of the waterproof mold box 11 communicating with the inner cavity of the hollow mold tube 1 to solidify and form the waterproof module 7.
[0056] The post-cast hole template reinforcement structure of the construction of the present invention can reduce the risk of floor leakage in the later stage. Specifically, a water-stopping mold box is formed in the middle of the empty mold tube, and concrete is poured in the water-stopping mold box and the empty mold tube to form a water-stopping module, and the water seepage path is extended on both sides of the empty mold tube, thereby reducing the risk of leakage caused by blocking the post-cast holes of the floor.
[0057] The post-cast hole formwork reinforcement structure for building construction of the present invention is simple to manufacture and flexible and convenient to operate.
[0058] The post-cast hole formwork reinforcement structure for building construction of the present invention is convenient to install and simple to disassemble, and can avoid the problem of a separate formwork frame affecting the interleaving of working procedures.
[0059] The post-cast hole formwork reinforcement structure for building construction of the present invention has simple constituent materials, simple design principle, low manufacturing cost and is not easy to damage.
[0060] The post-cast hole formwork reinforcement structure of the construction of the present invention reduces the secondary steel pipe formwork, and does not need to be supported by separate supporting members when the floor height is large. It is green and environmentally friendly, saves materials and carbon, saves labor, and has strong economic benefits.
[0061] The above description is only a preferred embodiment of the present application and an explanation of the technical principles used. Those skilled in the art should understand that the scope of the invention involved in the present application is not limited to the technical solution formed by a specific combination of the above technical features, but should also cover other technical solutions formed by any combination of the above technical features or their equivalent features without departing from the inventive concept. For example, the above features are replaced with (but not limited to) technical features with similar functions disclosed in the present application.
Claims
1. A post-cast hole formwork reinforcement structure for building construction. It is characterized in that include: A hollow mold tube is vertically arranged in the post-casting hole of the floor slab, the height of the hollow mold tube is adapted to the thickness of the floor slab, the middle part of the hollow mold tube protrudes outward to form a water-stop mold box, the inner cavity of the water-stop mold box is connected with the inner cavity of the hollow mold tube to form a first casting space, the bottom of the floor slab is attached with a template arranged below the post-casting hole, a second casting space is formed between the template and the inner wall of the hollow mold tube and the post-casting hole, and the template is provided with a through hole aligned with the lower pipe opening of the hollow mold tube; A suspension rod is movably arranged in the hollow mold tube and the through hole, and a support member is detachably mounted on the lower end of the suspension rod, and the support member is supported on the template; A reaction piece, two supporting rods are placed on the upper opening of the post-cast hole, the two supporting rods are arranged on opposite sides of the upper end of the hanger, the reaction piece is detachably installed on the upper end of the hanger, the two supporting rods are supported on the reaction piece, after the concrete poured in the second pouring space is solidified and the hanger is removed, concrete is poured in the first pouring space to consolidate and form a water-stop module.
2. The post-cast hole formwork reinforcement structure for building construction according to claim 1, It is characterized in that The water-stop mold box includes a bottom plate, a top plate and side plates. The top plate and the bottom plate are annular and have matching shapes and sizes. The inner edges of the top plate and the bottom plate are connected to the empty mold tube, and the side plates are connected to the outer edges of the top plate and the bottom plate.
3. The post-cast hole formwork reinforcement structure for building construction according to claim 2, It is characterized in that The top plate and the bottom plate are in an elliptical ring shape.
4. The post-cast hole formwork reinforcement structure for building construction according to claim 2, It is characterized in that Water-swellable water stop strips are respectively arranged on the inner side of the intersection of the upper part of the side plate and the top plate and on the inner side of the intersection of the lower part of the side plate and the bottom plate.
5. The post-cast hole formwork reinforcement structure for building construction according to claim 1, It is characterized in that The upper end and the lower end of the suspension rod are respectively formed with external threads, the reaction piece and the support piece are respectively provided with threaded holes, the reaction piece is screwed on the upper end of the suspension rod, and the support piece is screwed on the lower end of the suspension rod.
6. The post-cast hole formwork reinforcement structure for building construction according to claim 1, It is characterized in that The concrete poured in the first pouring space is foamed concrete.
7. A construction method for post-cast hole formwork reinforcement structure of building construction as claimed in any one of claims 1 to 6, It is characterized in that The following steps are involved: Fit the formwork to the bottom of the floor slab to seal the lower opening of the post-casting hole; Vertically install the suspension rod in the post-casting hole so that the lower end of the suspension rod penetrates the through hole of the template; Installing a support member at the lower end of the suspension rod so that the support member is supported on the template; Sleeving the empty mold tube on the suspension rod so that the empty mold tube is vertically arranged in the post-casting hole; Two support rods are placed on the upper openings of the post-casting holes, and the two support rods are arranged on opposite sides of the upper end of the suspension rod; Installing a reaction piece at the upper end of the suspension rod so that the two support rods are supported on the reaction piece; pouring concrete in a second pouring space formed between the template, the empty mold tube, and the inner wall of the post-casting hole; After the concrete poured in the second pouring space is solidified, removing the suspension rod; Concrete is poured into a first pouring space formed by the inner cavity of the water-stop mold box being connected with the inner cavity of the empty mold tube to solidify and form a water-stop module.
Citation Information
Patent Citations
Roof reserved opening concrete sealing and blocking device and fabrication method thereof
CN109322505A
Plugging device and plugging method for floor reserved hole
CN110939268A
Composite floor slab post-pouring slab strip formwork structure
CN217998565U
Concrete placing construction method
JP2001098760A