Construction method for crossed cantilever beam at high-altitude L-shaped structure based on assembly type steel platform

Through the construction method of cross-cantilever beams of high-altitude L-shaped structures based on prefabricated steel platforms, the problems of unsafe construction and difficulty in structural control in traditional steel platforms in high-altitude cantilever structures are solved, and efficient and safe construction of high-altitude cantilever structures are achieved. , avoiding the risks of external structure leakage and high-altitude operation.

CN118911427APending Publication Date: 2024-11-08CHONGQING CONSTR ENG FIRST MUNICIPAL ENG CO LTD

Patent Information

Application Number
CN202411305776.4
Authority / Receiving Office
CN · China
Patent Type
Applications(China)
Current Assignee / Owner
Filing Date
2024-09-14
Publication Date
2024-11-08

Smart Images

  • Figure CN118911427A_ABST
    Figure CN118911427A_ABST
Patent Text Reader

Abstract

The invention discloses a construction method for a crossed cantilever beam at a high-altitude L-shaped structure based on a fabricated steel platform, and belongs to the technical field of building construction. Comprising the steps of steel platform design, axis positioning, steel platform prefabricated embedded part construction, mounting position rechecking, embedded part reinforcing, rechecking before concrete pouring, formwork removal, steel platform machining and hoisting, steel platform mounting and connecting, sensor arrangement, plate opening supporting frame mounting, formwork mounting construction, steel bar construction and concrete pouring. The steel platform design comprises the steps of steel platform material selection, stress analysis and weld joint calculation according to SAP2000 three-dimensional software, and the positioning axis is based on the positioning axis and the horizontal elevation of a building; according to the method, SPA2000 finite element software is used for carrying out structural stress calculation on the steel platform, reasonable parameters are determined, safe stress of the platform is ensured, embedded bolts and anchor plates are reserved through a building main body structure, wall penetrating holes are prevented from being reserved, and the quality risk of leakage of an outer structure is avoided.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The invention belongs to the technical field of building construction, and particularly relates to a construction method for cross cantilever beams at a high-altitude L-shaped structure based on an assembled steel platform. Background Art

[0002] With the continuous development of the economy, high-rise buildings have become a beautiful landscape in the city. The appearance of buildings is changing more and more. In order to ensure the smooth progress of high-altitude cantilever structures, setting up steel platforms for the construction of high-altitude cantilever components should be a perfect and reliable solution.

[0003] Since conventional high-altitude cantilever steel platforms are laid with cantilevered steel sections on the floor level, they need to pass through shear walls or columns, increasing the risk of water seepage in the external structure; when welding the connecting beams and lower supports of the construction platform, it is necessary to stand on the external cantilevered steel sections to carry out operations, which is very dangerous; for special structures such as L-shaped structural outward-extending high-altitude cantilever components, traditional steel platform construction requires longer cantilevered main beams with larger cross-sectional heights, and it is difficult to control the position and angle of the cantilevered main beams, which is uneconomical and unsafe. In order to achieve the purpose of safe construction of high-altitude cantilever structures or special structures such as L-shaped / continuous L-shaped structures, it is necessary to solve the above problems based on the construction method of cross cantilever beams at the high-altitude L-shaped structure of the prefabricated steel platform. Summary of the invention

[0004] The purpose of the present invention is to provide a construction method for cross cantilever beams at a high-altitude L-shaped structure based on an assembled steel platform to solve the problems raised in the above-mentioned background technology.

[0005] To achieve the above-mentioned purpose, the present invention provides the following technical solutions: based on the construction method of the cross cantilever beam at the high-altitude L-shaped structure of the assembled steel platform, including steel platform design, positioning axis, construction of prefabricated embedded parts of the steel platform, verification of installation position, reinforcement of embedded parts, verification before pouring concrete, demolding, steel platform processing and hoisting, steel platform installation and connection, sensor arrangement, pan support frame installation, template installation construction, steel bar construction and concrete pouring, the steel platform design includes steel platform material selection, force analysis and weld calculation according to SAP2000 three-dimensional software;

[0006] The positioning axis is positioned according to the positioning axis and horizontal elevation of the building using CAD and Revit software, and the position of the embedded parts is confirmed on site using tools such as a steel tape measure, ink fountain, and paint brush;

[0007] The specific steps of the construction of the prefabricated embedded parts of the steel platform are as follows: the on-site construction workers use a laser line setting instrument to measure the control line, draw ink lines on the steel bars and mark the positions of the embedded parts with paint to control the axis deviation of the embedded parts; use the 1-meter line of the lower indoor structure to control the elevation of the embedded parts, and according to the positioning marks, the embedded parts are spot welded to the beam / shear wall steel bars after the steel bars are tied, and the anchor steel bars of the embedded parts must be placed inside the main steel bars;

[0008] The specific steps of checking the installation position are as follows: before fixing the embedded parts, it is necessary to check whether the position of the embedded parts is correct to ensure the construction quality of the embedded parts;

[0009] The specific steps of reinforcing the embedded parts are: after verification, reinforcing the embedded parts and welding them firmly to avoid vibration and falling off and shifting during concrete pouring;

[0010] The specific steps of the review before pouring concrete are: an on-site review needs to be carried out 1-2 hours before pouring concrete, and the offset embedded parts need to be corrected and fixed in time, and damaged embedded parts need to be replaced;

[0011] The specific steps of demoulding are as follows: after demoulding, the embedded parts of the template should be found and the surface should be cleaned within 2 days;

[0012] The steel platform processing and hoisting include platform welding and assembly on the ground and tower crane hoisting according to the design drawings;

[0013] The specific steps of installing and connecting the steel platform are as follows: before the steel platform is hoisted, four triangular supports are first installed, each support is connected with 2 / 4 M20 high-strength bolts, and a lower diagonal brace is set. The axis elevation of the triangular support must meet the construction requirements. Within the allowable deviation, the steel platform is hoisted onto the triangular support, and the two sides are pulled closer with a fall chain for adjustment. After the elevation and axis position are met, welding is performed, and the lower diagonal brace is welded using the lower scaffolding. After inspection to meet the design requirements and all welds are carefully inspected to meet the requirements, the platform can be separated from the tower crane wire rope;

[0014] The specific steps of arranging the sensors are as follows: according to the finite element calculation results, the maximum disturbance occurs at the end of the maximum cantilever, and considering the protection of the sensors, the sensors are installed at the position with greater load, that is, the end of the steel platform and the surface of the lower diagonal support;

[0015] The specific steps of the template installation construction are: first mark the +100cm elevation control line, then mark a template control line 10cm below the template based on this elevation line and check it;

[0016] Set up vertical poles and sweeping poles at the vertical pole plane position, set up horizontal connecting rods according to the step requirements, and set up longitudinal scissor braces according to the plan requirements;

[0017] The specific steps of the steel bar construction are: the cross beams at the cantilever structure are laid on the ground, tied and formed, and hoisted into the formwork as a whole by a tower crane;

[0018] The specific steps of pouring concrete are: first pouring concrete except for the concrete structure concrete, and finally pouring concrete for the cantilevered part.

[0019] This construction method avoids opening holes in external shear walls, columns, and beams, ensuring the waterproof quality of the structure; the lower diagonal brace is longer and is located on the outside of the L-shaped structure, and the steel section at the upper end of the diagonal brace is welded on the ground, ensuring the quality of welding; the positioning platform is installed on the floor level and the lower diagonal brace is welded, avoiding the time for workers to work at high altitudes, ensuring the safety of workers, and achieving significant social benefits.

[0020] As a preferred solution, the specific steps of selecting the steel platform material are: using 18# I-beam as the shelving triangular support, pre-embedded bolts above M20, and 12.6# / 14a# channel steel for the lower diagonal brace; 16# I-beam as the connecting beam, with a spacing of 500mm-600mm; 12.6# / 14a# channel steel for the lower diagonal brace, and the facade adopts 1.5m*1.8m steel protection net as a whole welded; 15mm composite wood formwork and 40*90 wood square are used as the main beam on the platform to close the operating platform;

[0021] The specific steps of stress analysis and weld calculation based on SAP2000 3D software are: using SAP2000 to establish a model consistent with the drawings and engineering practice, the model analysis and calculation simulation and the lower diagonal brace fillet weld calculation;

[0022] The steel platform's steel external protection is welded together with the ground and steel structure;

[0023] According to the actual working conditions, loading analysis is carried out based on the concentrated load of 1KN at each intersection of the platform steel to simulate the internal force of the entire construction platform component and the displacement of the end.

[0024] As a preferred solution, during the construction of the prefabricated embedded parts of the steel platform, the embedded parts are welded to the wall steel bars, which are prone to displacement due to concentrated vibration during concrete pouring, resulting in excessive deviations. Therefore, necessary reinforcement measures should be taken. When the embedded parts cannot be correctly installed at the embedded position due to excessive density of steel bars, consider burying them nearby with a height difference of no less than 5 cm.

[0025] As a preferred solution, during the process of reinforcing the embedded parts, it should be ensured that the verticality and flatness deviations of the embedded parts are no more than 3mm, the horizontal elevation deviation is no more than 10mm, and the position of the embedded parts deviates from the designed position by no more than 2mm.

[0026] As a preferred solution, during the demoulding process, a wooden broom is used for cleaning, and hard tools such as steel wire are not used to avoid scratching the surface anti-corrosion layer, and unqualified embedded parts should be replaced with additional post-embedded parts.

[0027] As a preferred solution, during the template installation construction process, horizontal steel pipes and wooden squares are installed, and after leveling, wooden templates are laid. Components with a span greater than 4 meters should be arched according to design requirements. If the design does not mention the arching requirements, it is advisable to arch at 1 / 1000-3 / 1000. The tightening torque of the fasteners should not be less than 40N·m and not more than 65N·m;

[0028] The distance between the wood pieces should not exceed 200mm, and they should be arranged neatly without any skewing, and the surface of the wood pieces should be planed;

[0029] A separate formwork design should be carried out for each span. Carpenters should not saw or splice the formwork randomly. The formwork should be laid on top of the wooden planks and the gap between the formworks should be adjusted. It is strictly forbidden to directly hit the edge of the formwork with a hammer. If necessary, use a wooden block to pad it for hitting.

[0030] As a preferred solution, when pouring the concrete in the cantilevered part of the concrete, it is first poured from the direction of the smaller cantilever span, and then poured from the cantilever root to the cantilever end using the "rushing slurry method", and the concrete discharge amount is controlled to avoid large impact force on the platform and the formwork due to large amount.

[0031] Compared with the prior art, the present invention has the following beneficial effects:

[0032] The present invention uses SPA2000 finite element software to calculate the structural stress of the steel platform, determine reasonable parameters, and ensure the safe stress of the platform;

[0033] The present invention utilizes the pre-buried bolts and anchor plates in the main structure of the building to avoid leaving through-wall holes and avoid the quality risk of leakage of the external structure.

[0034] The present invention manufactures a standardized triangular support (to place the main beam) and an assembled steel platform on the ground, thereby ensuring the welding construction quality of the platform;

[0035] The invention uses I-beams and channel steels to weld into a construction platform, uses a 1.5m*1.8m shaped steel protection net to make an external protection, is hoisted to the floor by a tower crane, and a fixed platform is installed on the floor and the lower end of the diagonal brace is welded, thus avoiding aerial welding work;

[0036] The present invention installs a DTSite intelligent monitoring system on the platform to monitor the stress of the cantilever structure at fixed points and irregular times to ensure the safety of the platform;

[0037] According to the present invention, beam reinforcement is tied on site and hoisted as a whole to an already erected formwork by a tower crane, thus reducing the time of workers' aerial work and the probability of accidents. BRIEF DESCRIPTION OF THE DRAWINGS

[0038] Figure 1 It is the construction flow chart of the present invention;

[0039] Figure 2 The flow chart of the steel platform design of the present invention is shown.

[0040] In the figure: 1. Steel platform design; 101. Steel platform material selection; 102. Force analysis and weld calculation according to SAP2000 3D software; 2. Positioning axis; 3. Construction of prefabricated embedded parts of steel platform; 4. Verification of installation position; 5. Reinforcement of embedded parts; 6. Verification before pouring concrete; 7. Formwork removal; 8. Steel platform processing and hoisting; 9. Steel platform installation and connection; 10. Arrangement of sensors; 11. Installation of pan support frame; 12. Formwork installation and construction; 13. Rebar construction; 14. Pouring concrete. DETAILED DESCRIPTION

[0041] The present invention will be further described below in conjunction with the embodiments.

[0042] The following examples are used to illustrate the present invention, but they cannot be used to limit the scope of protection of the present invention. The conditions in the examples can be further adjusted according to specific conditions. Simple improvements to the method of the present invention under the premise of the concept of the present invention belong to the scope of protection claimed in the present invention.

[0043] See also Figure 1-2 The present invention provides a construction method for a cross cantilever beam at a high altitude L-shaped structure of an assembled steel platform, including steel platform design 1, positioning axis 2, construction of prefabricated embedded parts of the steel platform 3, verification of installation position 4, reinforcement of embedded parts 5, verification before pouring concrete 6, demoulding 7, steel platform processing and hoisting 8, steel platform installation and connection 9, sensor arrangement 10, pan support frame installation 11, template installation construction 12, steel bar construction 13 and concrete pouring 14. The steel platform design 1 includes steel platform material selection 101, force analysis and weld calculation 102 according to SAP2000 three-dimensional software;

[0044] The specific steps of steel platform material selection 101 are: use 18# I-beam as the shelving triangle support, embed bolts above M20, and use 12.6# / 14a# channel steel for the lower diagonal support; 16# I-beam as the connecting beam, with a spacing of 500mm-600mm; use 12.6# / 14a# channel steel for the lower diagonal support, and use 1.5m*1.8m steel protection net for the facade as a whole welded; use 15mm composite wood formwork and 40*90 wood square as the main beam on the platform to close the operating platform;

[0045] The specific steps of carrying out stress analysis and weld calculation 102 according to SAP2000 three-dimensional software are: using SAP2000 to establish a model consistent with the drawings and the actual project, the model's analysis and calculation simulation and the lower diagonal brace fillet weld calculation;

[0046] The model is analyzed and calculated: Beam deadweight: G 梁 =0.2m*0.5m*3.4m*25.5KN / m 3 =8.7KN;

[0047] Platform weight: Steel platform 18# steel 6 meters, 16# I-beam 22 meters, 14a lower diagonal brace channel steel 15 meters, G 钢 =813.5kg;

[0048] The platform area is about 14.2m2 and the 15mm composite wood formwork and 40*90 wood squares are set at a spacing of 300mm. 2 , G 模板 =14.2*0.3=4.26KN=42.6kg;

[0049] The steel platform's steel external protection is welded together with the ground and steel structure;

[0050] G 防护 =200kg, G 平台 =813.5+42.6+200=936.1kg=1.336TFor specific calculation, please refer to platform hoisting;

[0051] Dynamic load of construction personnel and equipment: G 动载 =3KN / m 2 ;

[0052] G 动载 =3KN / m 2 =3*3.2*1.4+1.4*1.2=18.48KN Calculated according to the maximum dynamic load;

[0053] G 总 =8.7+1.34+18.48=28.52KN;

[0054] According to the actual working conditions, the loading analysis is carried out according to the concentrated load of 1KN at each intersection of the platform steel, simulating the internal force of the entire construction platform component and the displacement of the end;

[0055] Calculation of the lower diagonal support fillet weld: G 梁 =0.2m*0.5m*3.4m*25.5KN / m 3 =8.7KN;

[0056] G 平台=813.5+42.6+200=936.1kg=1.336T;

[0057] G 动载 =3KN / m 2 =3*3.2*1.4+1.4*1.2=18.48KN Calculated according to the maximum dynamic load;

[0058] G 斜撑受力 =8.7+1.34+18.48=28.52KN;

[0059] Positioning axis 2 Based on the positioning axis 2 and horizontal elevation of the building, CAD and Revit software are used to carry out layout and positioning, and steel tape measure, ink fountain, paint brush and other tools are used to confirm the position of embedded parts on site;

[0060] The specific steps of the construction of prefabricated embedded parts of the steel platform 3 are as follows: the on-site construction workers use the laser line setting instrument to measure the control line, draw ink lines on the steel bars and mark the positions of the embedded parts with paint to control the axis deviation of the embedded parts; use the 1-meter line of the lower indoor structure to control the elevation of the embedded parts, and according to the positioning marks, the embedded parts are spot welded to the beam / shear wall steel bars after the steel bars are tied, and the anchor steel bars of the embedded parts must be placed inside the main steel bars;

[0061] During the construction of the prefabricated embedded parts of the steel platform, the embedded parts are welded to the wall reinforcement, which is easy to be displaced due to concentrated vibration during concrete pouring, resulting in excessive deviation. Therefore, necessary reinforcement measures should be taken. When the embedded parts cannot be correctly installed to the buried position due to the dense reinforcement, consider burying them nearby with a height difference of no less than 5cm;

[0062] The specific steps of checking the installation position 4 are as follows: before fixing the embedded parts, it is necessary to check whether the position of the embedded parts is correct to ensure the construction quality of the embedded parts;

[0063] The specific steps of reinforcing the embedded parts 5 are: after verification, the embedded parts are reinforced and welded firmly to prevent them from falling off and shifting due to vibration when pouring concrete 14;

[0064] During the reinforcement of embedded parts 5, the verticality and flatness deviations of embedded parts should be no more than 3mm, the horizontal elevation deviation should be no more than 10mm, and the position of embedded parts should be no more than 2mm away from the designed position.

[0065] The specific steps of the review 6 before pouring concrete are as follows: since embedded parts in parts such as wall columns are prone to deviation when the civil engineering team sets up the side formwork or inserts the steel bars, and some embedded parts even have anchor bars bent or burned, it is necessary to conduct an on-site review 1-2 hours before pouring concrete 14, and promptly correct and fix the offset embedded parts and replace the damaged embedded parts;

[0066] The specific steps of demoulding 7 are as follows: after demoulding 7, the embedded parts of the template should be found out and the surface should be cleaned within 2 days;

[0067] During the process of removing the mold 7, use a wooden broom to clean, and do not use hard tools such as steel wire to avoid scratching the surface anti-corrosion layer. For unqualified embedded parts, add additional embedded parts to replace them.

[0068] Steel platform processing and hoisting 8 includes platform welding and assembly on the ground and tower crane hoisting according to the design drawings;

[0069] The main beam of the support is made of 18# I-steel, the connecting beam is made of 16# I-steel, and each lower diagonal brace is set with 12.6# / 14a# channel steel. The platform uses 15mm composite wood formwork and 40*90 wooden squares as the main beam spacing of 300mm, and a closed operating platform; a QTZ125 tower crane with a boom length of 60 meters is used. According to the on-site layout drawing, the steel platform construction is carried out within the 35-meter tower crane boom length. According to the analysis of the tower crane's hoisting capacity, the construction requirements are met.

[0070] The specific steps of steel platform installation and connection 9 are as follows: before the steel platform is hoisted, four triangular supports are installed first. Each support is connected with 2 / 4 M20 high-strength bolts, and a lower diagonal brace is set. The axis elevation of the triangular support must meet the construction requirements. Within the allowable deviation, the steel platform is hoisted onto the triangular support, and the two sides are pulled closer with a fall chain for adjustment. After the elevation and axis position are met, welding is performed, and the lower diagonal brace is welded using the lower scaffolding. After inspection to meet the design requirements and careful inspection of all welds to meet the requirements, the platform can be separated from the tower crane wire rope;

[0071] The specific steps of arranging the sensor 10 are as follows: according to the finite element calculation results, the maximum disturbance occurs at the end of the maximum cantilever, and considering the protection of the sensor, the sensor is installed at the position with a larger load, that is, the end of the steel platform and the surface of the lower diagonal support;

[0072] Installation of the buckle support frame: buckle vertical rod: Φ48*3.2Q345; horizontal rod and diagonal rod: Φ48*2.5Q235, adjustable top support force transmission;

[0073] Beam support design: beam side upright spacing 600mm, span direction 600mm / 900mm, step distance 1500mm;

[0074] The construction workers of the disc-type scaffolding must undergo professional safety and technical training and obtain the operation skills;

[0075] It is strictly forbidden to mix φ48×3.2mm vertical poles with φ48×2.5mm steel pipes in the process of setting up the disc-type scaffolding. One type of steel pipe should be used uniformly. The weight of the springboard used, whether it is a steel springboard, a bamboo springboard or a wooden springboard, cannot exceed 30kg, and the base should use a standard base or a welded base;

[0076] The specific steps of template installation construction 12 are: first mark the +100cm elevation control line, then mark a template control line 10cm below the bottom of the template based on this elevation line and check it;

[0077] Set up vertical poles and sweeping poles at the vertical pole plane position, set up horizontal connecting rods according to the step requirements, and set up longitudinal scissor braces according to the plan requirements;

[0078] During the formwork installation construction process, install horizontal steel pipes and wooden squares, level them, and lay wooden formwork. Components with a span greater than 4 meters should be arched according to the design requirements. If the design does not mention the arching requirements, it is advisable to arch at 1 / 1000-3 / 1000. The tightening torque of the fasteners should not be less than 40N·m and not more than 65N·m.

[0079] The distance between the wood pieces should not exceed 200mm, and they should be arranged neatly without any skewing, and the surface of the wood pieces should be planed;

[0080] A separate formwork design should be made for each span. When supporting the formwork, the woodwork should not be sawed or spliced ​​randomly. The formwork should be laid on top of the wood. The gap between the formwork should be adjusted. It is strictly forbidden to directly hit the edge of the formwork with a hammer. If necessary, it can be hit with a wooden block.

[0081] The specific steps of the steel bar construction 13 are as follows: the cross beams at the cantilever structure are laid on the ground, tied and formed, and hoisted into the formwork as a whole by a tower crane; the components are located at the outer end of the L-shaped structure, which reduces the time for workers to work at high altitudes, reduces the vibration impact caused by the plate-tied steel bars, and ensures the safety of workers during construction;

[0082] The specific steps of pouring concrete 14 are: first pouring concrete except for the concrete structure concrete, and finally pouring concrete for the cantilevered part;

[0083] When pouring concrete in the cantilevered part of the concrete 14, pour it first from the direction of the smaller cantilever span, and use the "rushing slurry method" to pour from the cantilever root to the cantilever end, and control the concrete discharge amount to avoid a large impact on the platform and the formwork due to a large amount.

[0084] This construction method avoids opening holes in external shear walls, columns, and beams, ensuring the waterproof quality of the structure; the lower diagonal brace is longer and is located on the outside of the L-shaped structure, and the steel section at the upper end of the diagonal brace is welded on the ground, ensuring the quality of welding; the positioning platform is installed on the floor level and the lower diagonal brace is welded, avoiding the time for workers to work at high altitudes, ensuring the safety of workers, and achieving significant social benefits.

[0085] The working principle and use process of the present invention are as follows: high-strength bolts are pre-buried in the main structure and triangular bracket supports are provided;

[0086] The steel platform is assembled on the ground, and the tower crane is hoisted onto the support as a whole, and then fixed by welding using the floor surface;

[0087] The formwork support system is set up on the steel platform, and the tower crane hoists the tied beam reinforcement into the formwork for subsequent concrete construction work;

[0088] During the construction process, each control point should be evenly distributed and re-measured regularly to ensure the accuracy of the control points; instruments should be inspected and calibrated regularly to ensure that the instruments are used within the validity period and that the measurement personnel are certified to work; a welding windproof shed should be set up before welding construction, flux-cored welding wire should be used for welding, and a large flow of CO2 gas should be used for welding protection to increase the stiffness of the CO2 protective gas column, improve wind resistance, and form a slag-gas combined protection for the welding pool; a temporary welding rainproof shed should be set up before welding construction to prevent rain from falling directly on the hot weld and causing cold brittle cracks; flash, burrs, and welding spatter should be removed before steel components are installed; calibration After correction, replace the temporary bolts with high-strength bolts and tighten the bolts with a manual wrench or electric wrench; when the high-strength bolts cannot be freely inserted into the bolt holes, they cannot be hard-punched in. Use an electric or manual hole milling device to correct the holes before inserting them. The maximum diameter of the bolt holes after repair and expansion should not be greater than 1.2 times the nominal diameter of the bolts, and the number of holes expanded should be subject to the consent of the design unit; torsion-shear type bolts are qualified if the plum head is twisted off, and large hexagon head bolts are qualified if the final torque is tightened; during the installation process, care should be taken to protect the bolts, and they must not be contaminated with mud, sand and other debris, or damage the threads; if any abnormality is found during use, construction should be stopped immediately, and construction can be resumed after inspection.

[0089] Although embodiments of the present invention have been shown and described, it will be appreciated by those skilled in the art that various changes, modifications, substitutions and variations may be made to the embodiments without departing from the principles and spirit of the present invention, and that the scope of the present invention is defined by the appended claims and their equivalents.

Claims

1. A construction method for a cross cantilever beam at a high altitude L-shaped structure of an assembled steel platform, comprising steel platform design (1), axis positioning (2), steel platform prefabricated embedded parts construction (3), verification of installation position (4), reinforcement of embedded parts (5), verification before pouring concrete (6), formwork removal (7), steel platform processing and hoisting (8), steel platform installation and connection (9), sensor arrangement (10), pan mouth support frame installation (11), template installation construction (12), steel bar construction (13) and concrete pouring (14), characterized in that: The steel platform design (1) includes steel platform material selection (101), force analysis and weld calculation (102) according to SAP2000 three-dimensional software; The positioning axis (2) is positioned according to the positioning axis (2) and the horizontal elevation of the building using CAD and Revit software, and the position of the embedded parts is confirmed on site using tools such as a steel tape measure, ink fountain, and paint brush; The specific steps of the construction of the prefabricated embedded parts of the steel platform (3) are as follows: the on-site construction worker uses a laser line setting instrument to measure the control line, draws ink lines on the steel bars and marks the positions of the embedded parts with paint to control the axis deviation of the embedded parts; uses the 1-meter line of the lower indoor structure to control the elevation of the embedded parts, and spot welds the embedded parts to the beam / shear wall steel bars according to the positioning marks after the steel bars are tied, and the anchor steel bars of the embedded parts must be placed inside the main steel bars; The specific steps of checking the installation position (4) are as follows: before fixing the embedded parts, it is necessary to check whether the position of the embedded parts is correct to ensure the construction quality of the embedded parts; The specific steps of reinforcing the embedded parts (5) are: after verification, reinforcing the embedded parts and welding them firmly to prevent them from falling off and shifting due to vibration when pouring concrete (14); The specific steps of the pre-concrete pouring review (6) are as follows: an on-site review needs to be conducted 1-2 hours before the concrete pouring (14), and the offset embedded parts need to be corrected and fixed in time, and damaged embedded parts need to be replaced; The specific steps of the demoulding (7) are as follows: after demoulding (7), the embedded parts in the template should be found and the surface should be cleaned within 2 days; The steel platform processing and hoisting (8) includes platform welding and assembly and tower crane hoisting on the ground according to the design drawings; The specific steps of the steel platform installation and connection (9) are as follows: before the steel platform is hoisted, four triangular supports are first installed, each support is connected by 2 / 4 M20 high-strength bolts, and a lower diagonal brace is set. The axis elevation of the triangular support must meet the construction requirements. Within the allowable deviation, the steel platform is hoisted onto the triangular support, and the two sides are pulled closer with a fall chain for adjustment. After the elevation and axis position are met, welding is performed, and the lower diagonal brace is welded using the lower scaffolding. After inspection to meet the design requirements and careful inspection of all welds to meet the requirements, the platform can be separated from the tower crane wire rope; The specific steps of arranging the sensor (10) are: according to the finite element calculation results, the maximum disturbance appears at the end of the maximum cantilever, and considering the protection of the sensor, the sensor is installed at the position with a larger load, that is, the end of the steel platform and the surface of the lower diagonal support; The specific steps of the template installation construction (12) are: first draw a +100cm elevation control line, then draw a template control line 10cm below the template based on this elevation line and check it; Set up vertical poles and sweeping poles at the vertical pole plane position, set up horizontal connecting rods according to the step requirements, and set up longitudinal scissor braces according to the plan requirements; The specific steps of the reinforcement construction (13) are: the cross beams at the cantilever structure are laid on the ground, tied and formed, and hoisted into the formwork as a whole by a tower crane; The specific steps of pouring concrete (14) are: first pouring concrete except for the concrete structure concrete, and finally pouring concrete for the cantilevered part.

2. The construction method of cross cantilever beams at the high altitude L-shaped structure based on the assembled steel platform according to claim 1 is characterized by: The specific steps of selecting the steel platform material (101) are: selecting 18# I-beam as the shelving triangular support, pre-embedded bolts above M20, and 12.6# / 14a# channel steel for the lower diagonal brace; 16# I-beam as the connecting beam, with a spacing of 500mm-600mm; 12.6# / 14a# channel steel for the lower diagonal brace, and the outer facade adopts a 1.5m*1.8m steel protection net that is integrally welded; 15mm composite wood formwork and 40*90 wood square are used as the main beam on the platform to close the operating platform; The specific steps of performing stress analysis and weld calculation (102) according to the SAP2000 three-dimensional software are: using SAP2000 to establish a model consistent with the drawings and the actual project, analysing and simulating the model, and calculating the weld of the lower diagonal brace.

3. The construction method of cross cantilever beams at a high altitude L-shaped structure based on an assembled steel platform according to claim 1 is characterized in that: During the construction (3) of the prefabricated embedded parts of the steel platform, the embedded parts are welded to the wall reinforcement, which is easy to be displaced due to concentrated vibration during concrete pouring, resulting in excessive deviation. Therefore, necessary reinforcement measures should be taken. When the embedded parts cannot be correctly installed at the embedded position due to the excessive density of reinforcement, consider burying them nearby with a height difference of not less than 5 cm.

4. The construction method of cross cantilever beams at a high altitude L-shaped structure based on an assembled steel platform according to claim 1 is characterized in that: During the process of reinforcing the embedded parts (5), it should be ensured that the verticality and flatness deviations of the embedded parts are no more than 3 mm, the horizontal elevation deviation is no more than 10 mm, and the position deviation of the embedded parts from the designed position is no more than 2 mm.

5. The construction method of cross cantilever beams at a high altitude L-shaped structure based on an assembled steel platform according to claim 1 is characterized in that: During the demoulding (7) process, a wooden broom should be used for cleaning, and hard tools such as steel wire should not be used to avoid scratching the surface anti-corrosion layer. In addition, unqualified embedded parts should be replaced with additional post-embedded parts.

6. The construction method of cross cantilever beams at a high altitude L-shaped structure based on an assembled steel platform according to claim 1 is characterized in that: During the template installation construction (12), horizontal steel pipes and wooden squares are installed. After leveling, wooden templates are laid. Components with a span greater than 4 meters should be arched according to design requirements. If the design does not mention the arching requirements, it is advisable to arch at 1 / 1000-3 / 1000. The tightening torque of the fasteners should not be less than 40N·m and not more than 65N·m. The distance between the wood pieces should not exceed 200mm, and they should be arranged neatly without any skewing, and the surface of the wood pieces should be planed; A separate formwork design should be carried out for each span. Carpenters should not saw or splice the formwork randomly. The formwork should be laid on top of the wooden planks and the gap between the formworks should be adjusted. It is strictly forbidden to directly hit the edge of the formwork with a hammer. If necessary, use a wooden block to pad it for hitting.

7. The construction method of cross cantilever beams at a high altitude L-shaped structure based on an assembled steel platform according to claim 1 is characterized in that: When pouring the concrete at the cantilevered part of the pouring concrete (14), the concrete is first poured from the direction of the smaller cantilever span, and then poured from the cantilever root to the cantilever end by using the "rushing slurry method", and the concrete discharge amount is well controlled to avoid a large amount of concrete causing a large impact force on the platform and the formwork.

Citation Information

Patent Citations

  • Large-sized overhang steel structure mounting method

    CN103388405A

  • Method for ensuring safety construction of large-size and cantilever concrete structure support system

    CN106193603A

  • Construction method of high altitude large-span overhanging steel platform formwork

    CN107165281A

  • Construction method for positioning stress steel beam on steel frame bearing platform

    CN114961260A

  • Assembly type triangular truss cantilever supporting frame system

    CN218990875U

Cited By

  • Steel structure davit and construction method thereof

    CN119914085A