Ground surface settlement real-time monitoring system for subway construction tunnel

By using a real-time monitoring system for surface settlement during subway construction tunnel construction, real-time monitoring of surface settlement is achieved using adjustable measuring rods and laser ranging sensors, solving the problem of real-time and accurate monitoring in the existing technology, and improving the Monitor efficiency and resource utilization.

CN118913207APending Publication Date: 2024-11-08SINOHYRDO ENG BUREAU 3 CO LTD
View PDF 0 Cites 3 Cited by

Patent Information

Application Number
CN202410972236.5
Authority / Receiving Office
CN · China
Patent Type
Applications(China)
Current Assignee / Owner
Filing Date
2024-07-19
Publication Date
2024-11-08

AI Technical Summary

Technical Problem

The prior art cannot provide continuous and real-time monitoring of surface settlement during subway construction tunnel construction, and the accuracy of monitoring data is affected by human operation and environmental factors, making it difficult to capture small settlement changes, and the monitoring equipment is usually discarded after construction is completed, resulting in Waste of resources.

Method used

A real-time monitoring system for surface settlement including a monitoring module with a measurement module and a wireless communication connection is designed. By setting an adjustable measuring rod and laser ranging sensor in the monitoring hole, surface settlement is measured in real time and data is transmitted through wireless communication. Reduce manual intervention and improve monitoring efficiency and data reliability.

Benefits of technology

Real-time and accurate monitoring of surface settlement, reduce data gaps, improve monitoring efficiency and data reliability, provide strong support for subway construction safety and quality assurance, and improve system use by simplifying the installation and maintenance process. Convenience and practicality.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN118913207A_ABST
    Figure CN118913207A_ABST
Patent Text Reader

Abstract

The invention discloses a ground surface settlement real-time monitoring system for a subway construction tunnel, which comprises a measuring module and a monitoring module in wireless communication connection with the measuring module, the monitoring module comprises a plurality of measuring units, and each measuring unit comprises a plurality of monitoring holes, a plurality of monitoring terminals and a plurality of monitoring terminals, the device comprises a monitoring hole, a measuring rod which is located in the monitoring hole, hollow inside and adjustable in length, an expansion positioning mechanism arranged at the bottom of the measuring rod, a monitoring box installed on the ground above the monitoring hole, and an adjusting mechanism which is arranged in the monitoring box and used for adjusting the length of the measuring rod. The driving mechanism is arranged on the monitoring box and used for driving the expansion positioning mechanism, the laser distance measuring sensor is arranged on the monitoring box, and laser of the laser distance measuring sensor is vertically projected on the inner bottom wall of the measuring rod; the system has the advantages of real-time performance, high precision, automation, resource saving and the like, and the ground surface settlement monitoring level in the subway construction process can be remarkably improved.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The invention belongs to the technical field of subway construction, and in particular relates to a real-time monitoring system for surface settlement of a subway construction tunnel. Background Art

[0002] With the rapid development of cities and population growth, urban traffic is becoming more and more congested. Traditional ground transportation can no longer meet the travel needs of citizens. As a large-capacity, fast and punctual public transportation method, the subway can save ground space, effectively alleviate urban traffic pressure, and improve travel efficiency. It plays an important role in improving the urban transportation network. The subway has developed into one of the main modes of transportation in the city.

[0003] Subway tunnel construction involves large-scale soil excavation and underground operations. These activities will have a significant impact on the stress state of the surrounding rock and soil, the movement of groundwater, etc. If the construction is not well controlled or the geological conditions are complex, it may cause safety hazards such as surface subsidence and building cracks. Surface subsidence monitoring is an important measure to ensure the smooth progress of subway tunnel construction and the safety of the surrounding environment. By monitoring surface subsidence data, the deformation of the soil during the excavation of the subway tunnel can be evaluated, the impact of the construction on the surrounding environment can be understood, potential problems can be discovered and dealt with in a timely manner, and the construction plan can be adjusted in a timely manner to provide strong guarantees for construction safety and project quality.

[0004] The existing technology usually monitors the degree of surface settlement by setting up settlement monitoring points. This method requires first setting a hole of specific depth and width on the road surface, and then burying a settlement rod of sufficient length in the hole, pouring concrete at the bottom, and filling the upper part with fine sand. With the help of measuring instruments (such as levels, total stations, etc.), the changes in the elevation of the settlement rod in the monitoring hole are observed to obtain the surface settlement data of the monitoring point; however, this method relies on regular manual observation and cannot provide continuous and real-time surface settlement monitoring data. In addition, it is affected by human operation and environmental factors, resulting in limited accuracy of monitoring data and difficulty in capturing tiny settlement changes; and when the ground or foundation pit is restored, the surface settlement monitoring points are usually directly abandoned underground, resulting in a waste of resources. Summary of the invention

[0005] The purpose of the present invention is to provide a real-time monitoring system for ground subsidence in subway tunnel construction to solve the above-mentioned problems in the prior art.

[0006] In order to achieve the above object, the technical solution adopted by the present invention is:

[0007] A real-time monitoring system for surface settlement of a subway construction tunnel comprises a measuring module and a monitoring module wirelessly connected to the measuring module, wherein the monitoring module comprises a plurality of measuring units, and the measuring units comprise: a plurality of monitoring holes vertically drilled from the ground to an original soil layer, a hollow measuring rod located inside the monitoring holes and having an adjustable length, an expansion positioning mechanism arranged at the bottom of the measuring rod, a monitoring box installed on the ground above the monitoring holes, an adjustment mechanism arranged in the monitoring box for adjusting the length of the measuring rod, a driving mechanism arranged on the monitoring box for driving the expansion positioning mechanism, and a laser ranging sensor arranged in the monitoring box, wherein the laser of the laser ranging sensor is vertically projected onto an inner bottom wall of the measuring rod.

[0008] Preferably, a mounting seat is provided on the ground above the monitoring hole, a mounting opening adapted to the size of the monitoring box is provided through the center of the mounting seat, a positioning ring adapted to the size of the measuring rod is provided in the monitoring hole, the positioning ring is connected to the inner wall of the mounting seat through a connecting frame, and the monitoring box is installed in the mounting opening of the mounting seat through a plug-in assembly.

[0009] Preferably, the plug-in assembly includes: a groove arranged on the inner wall of the mounting seat, a plug-in plate slidably arranged in the groove, a compression spring connected to the plug-in plate at one end and connected to the inner wall of the groove at the other end, a plug-in hole arranged on the side wall of the monitoring box, and a movable rod connected to the plug-in plate at one end and movable through the groove wall at the other end, and the plug-in block has a downwardly inclined slope on one side facing the plug-in hole.

[0010] Preferably, the measuring rod comprises: an insertion rod with an opening at the top and a hollow interior, and an adjusting rod with openings at both ends and a hollow interior, the insertion rod is threadedly connected to the interior of the adjusting rod, a conical head is provided at the bottom of the insertion rod, a first limit strip is provided on the inner side wall of the insertion rod along its length direction, and a second limit strip is provided on the outer side wall of the adjusting rod along its length direction.

[0011] Preferably, a through hole is provided through the bottom of the monitoring box, and the adjusting mechanism includes: a driving cylinder with openings at both ends and a hollow interior, a limiting cylinder with openings at both ends and a hollow interior, and a power component arranged in the monitoring box for driving the driving cylinder to rotate, a second limiting groove matched with the second limiting strip is provided on the inner wall of the driving cylinder, and a first limiting groove matched with the first limiting strip is provided on the outer wall of the limiting cylinder, the bottom end of the driving cylinder passes through the through hole and is sleeved on the top of the adjusting rod, the upper end of the limiting cylinder is fixedly connected to the monitoring box, and the lower end passes through the through hole and is inserted into the insertion rod.

[0012] Preferably, the power assembly includes: a gear ring fixedly sleeved on the outer side of the top end of the driving cylinder, a gear meshing with the gear ring, and a power member arranged on the monitoring box and connected to the gear to drive the gear to rotate.

[0013] Preferably, the expansion positioning mechanism includes: a plurality of through holes arranged through the side wall of the lower end of the insertion rod, the through holes are distributed in a circular array around the central axis of the insertion rod, an expansion rod with one end arranged in the through hole, a slider connected to the other end of the expansion rod and the bottom end of which is slidably connected to the bottom wall of the insertion rod, an end hinged to the upper end connecting rod of the slider, a moving rod arranged on the central axis of the insertion rod and hinged to the connecting rod, a sleeve threadedly connected to the upper end of the moving rod, and a square rod fixedly connected to the top end of the sleeve, the moving rod being slidably connected to the inner side wall of the insertion rod via a connecting rod.

[0014] Preferably, the driving mechanism includes: a mounting tube with a square cavity inside, an opening at the bottom and sleeved on the outer end of the square rod, a rotating shaft that rotates through the monitoring box and is fixedly connected to the top of the mounting tube, and a handle arranged at the top of the rotating shaft.

[0015] Compared with the prior art, the advantages of the present invention are:

[0016] 1. The monitoring system of the present invention adjusts the length of the measuring rod through an adjusting mechanism, so that the bottom end of the measuring rod can penetrate into the original soil layer, and then the bottom end of the measuring rod will drop with the settlement of the original soil layer. A laser distance measuring sensor is arranged in the measuring box to measure the distance change between the bottom wall of the measuring rod and the sensor in real time, and transmit it to the monitoring module through wireless communication, so as to accurately reflect the settlement of the surface in real time, realize the real-time monitoring of the surface settlement, can continuously collect data, reduce manual intervention, avoid the data blank period caused by manual observation interval, improve the monitoring efficiency and data reliability, and provide strong support for the safety and quality assurance of subway construction;

[0017] 2. The present invention ensures that the measuring rod remains vertical and stable in the monitoring hole by arranging a positioning ring in the mounting seat, thereby preventing it from deflecting or shaking during the monitoring process. The monitoring box is connected to the mounting seat by using a plug-in assembly, so that the installation process of the monitoring box becomes simple and quick, without the need for additional tools or complicated operating steps, thereby improving the installation efficiency and stability of the monitoring system and facilitating subsequent maintenance and replacement work;

[0018] 3. The present invention drives the transmission of the gear and the gear ring through the power part, combined with the cooperation of the second limit groove and the second limit strip, so that the adjusting rod is driven to rotate synchronously when the driving cylinder rotates. The cooperation of the first limit groove and the first limit strip ensures that the insertion rod will not rotate with the adjusting rod during the adjustment process, but remains relatively still and only moves up and down in the adjusting rod, thereby finally realizing the adjustment of the length of the measuring rod. The overall structure is compact, and the installation and adjustment process is simple and quick. After the measurement is completed, it is also convenient to pull the measuring rod out of the original soil layer for recycling and reuse, which not only improves the measurement accuracy and stability, but also further improves the convenience and practicality of the system. BRIEF DESCRIPTION OF THE DRAWINGS

[0019] In order to more clearly illustrate the technical solutions of the embodiments of the present invention, the drawings required for use in the embodiments will be briefly introduced below. It should be understood that the following drawings only show certain embodiments of the present invention and therefore should not be regarded as limiting the scope. For ordinary technicians in this field, other related drawings can be obtained based on these drawings without paying creative work.

[0020] Figure 1 It is a schematic diagram of the structure of a measurement unit of a real-time monitoring system for ground settlement in a subway construction tunnel;

[0021] Figure 2 A cross-sectional view of a mounting base for a real-time monitoring system for ground subsidence in a subway tunnel construction;

[0022] Figure 3 The structure of a monitoring box for a real-time monitoring system of ground settlement in a subway tunnel under construction is shown in FIG.

[0023] Figure 4 This is a schematic diagram of the internal structure of a monitoring box for a real-time monitoring system of ground settlement in a subway construction tunnel;

[0024] Figure 5 A cross-sectional view of a monitoring box for a real-time monitoring system of ground subsidence in a subway tunnel under construction;

[0025] Figure 6 A schematic diagram of the structure of a measuring rod for a real-time monitoring system of ground settlement in a subway construction tunnel;

[0026] Figure 7 A cross-sectional view of the bottom end of an insertion rod of a real-time monitoring system for ground settlement in a subway tunnel construction;

[0027] Figure markings: 1-measuring rod, 2-expansion positioning mechanism, 3-monitoring box, 4-laser ranging sensor, 5-mounting seat, 6-mounting port, 7-positioning ring, 8-connecting frame, 9-groove, 10-plug-in board, 11-compression spring, 12-plug-in hole, 13-movable rod, 14-insertion rod, 15-adjusting rod, 16-first limit strip, 17-second limit strip, 18-through hole, 19-driving cylinder, 20-limiting cylinder, 21-first limit groove, 22-second limit groove, 23-gear ring, 24-gear, 25-power part, 26-perforation, 27-expansion rod, 28-slider, 29-connecting rod, 30-moving rod, 31-sleeve, 32-square rod, 33-mounting cylinder, 34-rotating shaft, 35-handle. DETAILED DESCRIPTION

[0028] In order to make the purpose, technical solution and advantages of the embodiments of the present invention clearer, the technical solution in the embodiments of the present invention will be clearly and completely described below in conjunction with the drawings in the embodiments of the present invention. Obviously, the described embodiments are part of the embodiments of the present invention, not all of the embodiments. Based on the embodiments of the present invention, all other embodiments obtained by ordinary technicians in this field without creative work are within the scope of protection of the present invention.

[0029] It should be noted that similar reference numerals and letters denote similar items in the following drawings, and therefore, once an item is defined in one drawing, further definition and explanation thereof is not required in subsequent drawings.

[0030] In the description of the present invention, it should be noted that if the terms "center", "up", "down", "left", "right", "vertical", "horizontal", "inside", "outside" and the like appear, the orientation or position relationship indicated is based on the orientation or position relationship shown in the accompanying drawings, or is the orientation or position relationship in which the product of the invention is usually placed when used. It is only for the convenience of describing the present invention and simplifying the description, and does not indicate or imply that the device or element referred to must have a specific orientation, be constructed and operated in a specific orientation, and therefore cannot be understood as a limitation on the present invention.

[0031] In addition, the terms “first”, “second”, “third”, etc., if used, are merely used to distinguish between the descriptions and should not be understood as indicating or implying relative importance.

[0032] In addition, the terms "horizontal", "vertical", "overhanging", etc. do not mean that the components are required to be absolutely horizontal or overhanging, but can be slightly tilted. For example, "horizontal" only means that its direction is more horizontal than "vertical", and does not mean that the structure must be completely horizontal, but can be slightly tilted.

[0033] In the description of the present invention, it is also necessary to explain that, unless otherwise clearly specified and limited, the terms "set", "install", "connect", "connection", etc. should be understood in a broad sense, for example, it can be a fixed connection, a detachable connection, or an integral connection; it can be a mechanical connection or an electrical connection; it can be a direct connection, or it can be indirectly connected through an intermediate medium, or it can be the internal communication of two components. For ordinary technicians in this field, the specific meanings of the above terms in the present invention can be understood according to specific circumstances.

[0034] It should be noted that, in the absence of conflict, the features in the embodiments of the present invention may be combined with each other.

[0035] Example 1

[0036] like Figure 1-Figure 6 As shown, a real-time monitoring system for surface settlement of subway construction tunnels includes a measuring module and a monitoring module wirelessly connected to the measuring module, the monitoring module includes a plurality of measuring units, and the measuring units include: a plurality of monitoring holes vertically drilled from the ground to the original soil layer, a hollow measuring rod 1 located inside the monitoring holes and having an adjustable length, an expansion positioning mechanism 2 arranged at the bottom of the measuring rod 1, a monitoring box 3 installed on the ground above the monitoring holes, an adjustment mechanism arranged in the monitoring box 3 for adjusting the length of the measuring rod 1, a driving mechanism arranged on the monitoring box 3 for driving the expansion positioning mechanism 2, and a laser ranging sensor 4 arranged on the monitoring box 3, the laser of the laser ranging sensor 4 being projected vertically onto the inner bottom wall of the measuring rod 1.

[0037] It should be noted that: the monitoring module is an existing technology. The measuring module transmits the monitored surface settlement data to the monitoring module through wireless communication. The monitoring module analyzes and processes the data collection to generate a surface settlement curve and report for evaluating the impact of subway tunnel construction on the surrounding environment and timely discovering and handling potential problems. A plurality of monitoring holes are arranged at equal distances along the length direction of the subway main excavation. In actual operation, a measurement section can be marked at a certain distance along the length direction of the subway main excavation. A certain number of monitoring points are marked on each measurement section. Then, a drilling device is used to drill monitoring holes at the monitoring point ground with a depth directly reaching the original soil layer. The spacing between the monitoring holes and the diameter of the monitoring holes themselves are set according to the actual project conditions.

[0038] When installing the measuring unit, first place the measuring rod 1 in the monitoring hole, making sure that its bottom is inserted into the surface of the original soil layer and the top is lower than the opening of the monitoring hole, and then install the monitoring box 3 on the ground above the monitoring hole, so that the adjustment mechanism in the monitoring box 3 is movably connected to the measuring rod 1. After connecting all electronic equipment and sensors, start the adjustment mechanism to adjust the length of the measuring rod 1 so that the bottom end of the measuring rod 1 can penetrate into the original soil layer, and then start the expansion positioning mechanism 2 through the driving mechanism to increase the contact area between the bottom of the measuring rod 1 and the original soil layer, thereby improving the stability and sensitivity of the measuring rod 1 during the surface settlement monitoring process, and further improving the accuracy of the monitoring data;

[0039] After the system is started, the bottom end of the measuring rod 1 will drop as the original soil layer settles. The relative position between the laser ranging sensor 4 installed on the monitoring box 3 and the inner bottom wall of the measuring rod 1 will change, so that the value measured by the laser ranging sensor 4 will change. The sensor transmits the value to the monitoring module through wireless communication. The monitoring module collects, processes and analyzes these data to generate surface settlement curves and reports to determine whether the surface settlement during subway construction is within the normal range, thereby realizing real-time monitoring of surface settlement, being able to continuously collect data, reducing manual intervention, avoiding data blank periods caused by manual observation intervals, and improving monitoring efficiency and data reliability.

[0040] Example 2

[0041] On the basis of Example 1, Figure 2 As shown, a mounting seat 5 is provided on the ground above the monitoring hole, a mounting opening 6 which is adapted to the size of the monitoring box 3 is provided through the center of the mounting seat 5, a positioning ring 7 which is adapted to the size of the measuring rod 1 is provided in the monitoring hole, the positioning ring 7 is connected to the inner wall of the mounting seat 5 through a connecting frame 8, and the monitoring box 3 is installed in the mounting opening 6 of the mounting seat 5 through a plug-in assembly.

[0042] Among them, the plug-in assembly includes: a groove 9 arranged on the inner wall of the mounting base 5, a plug-in plate 10 slidably arranged in the groove 9, a compression spring 11 connected to the plug-in plate 10 at one end and connected to the inner wall of the groove 9 at the other end, a plug-in hole 12 arranged on the side wall of the monitoring box 3, and a movable rod 13 connected to the plug-in plate 10 at one end and movable through the wall of the groove 9 at the other end, and the side of the plug-in block facing the plug-in hole 12 is a downward inclined surface.

[0043] It should be noted that: the mounting base 5 can be fixed on the ground by expansion screws, and a level gauge can also be provided on the mounting base 5 to ensure that the mounting base 5 can be installed horizontally on the ground;

[0044] In this embodiment, a positioning ring 7 located inside the monitoring hole and matched with the size of the measuring rod 1 is provided on the mounting base 5 to facilitate the installation of the measuring rod 1 and to keep the measuring rod 1 vertical and stable in the monitoring hole to prevent it from shifting or shaking during the monitoring process; after the mounting base 5 is installed, the monitoring box 3 is aligned with the mounting port 6 of the mounting base 5 and gently pushed in. During the pushing process, the inclined surface of the plug-in block will guide the monitoring box 3 to slide in smoothly, and the compression spring 11 will be compressed. When the plug-in hole 12 of the monitoring box 3 is aligned with the plug-in block, the elastic force of the compression spring 11 will push the plug-in board 10 to move outward, so that the plug-in block is automatically inserted into the plug-in hole 12, thereby realizing the fixed connection between the monitoring box 3 and the mounting base 5; the setting of the plug-in component makes the installation process of the monitoring box 3 simple and quick, and further facilitates the subsequent maintenance and replacement of the monitoring system.

[0045] Example 3

[0046] On the basis of Example 1, Figure 2-Figure 6 As shown: the measuring rod 1 includes: an insertion rod 14 with an open top and a hollow interior, and an adjusting rod 15 with open ends and a hollow interior, the insertion rod 14 is threadedly connected to the interior of the adjusting rod 15, a conical head is provided at the bottom of the insertion rod 14, a first limit strip 16 is provided on the inner side wall of the insertion rod 14 along its length direction, and a second limit strip 17 is provided on the outer side wall of the adjusting rod 15 along its length direction.

[0047] A through hole 18 is provided through the bottom of the monitoring box 3, and the adjusting mechanism includes: a driving cylinder 19 which is open at both ends and hollow inside, a limiting cylinder 20 which is open at both ends and hollow inside, and a power component arranged in the monitoring box 3 for driving the driving cylinder 19 to rotate, a second limiting groove 22 which is adapted to the second limiting strip 17 is provided on the inner wall of the driving cylinder 19, and a first limiting groove 21 which is adapted to the first limiting strip 16 is provided on the outer wall of the limiting cylinder 20, the bottom end of the driving cylinder 19 passes through the through hole 18 and is sleeved on the top of the adjusting rod 15, the upper end of the limiting cylinder 20 is fixedly connected to the monitoring box 3, and the lower end passes through the through hole 18 and is inserted into the inside of the insertion rod 14.

[0048] The power assembly includes: a gear 24 ring 23 fixedly sleeved on the outer side of the top end of the driving cylinder 19, a gear 24 meshing with the gear 24 ring 23, and a power part 25 arranged on the monitoring box 3 and connected to the gear 24 to drive the gear 24 to rotate.

[0049] It should be noted that the power member 25 can be a manually driven rotating rod, or can be set as a driving motor commonly used in the prior art; before the measuring rod 1 is placed in the monitoring hole, the adjusting rod 15 and the inserting rod 14 can be rotated as needed to preliminarily adjust the length of the measuring rod 1.

[0050] In this embodiment, the insertion rod 14 can be quickly and stably inserted into the surface of the original soil layer through the bottom conical head to ensure initial stability. When installing the detection box, it should be ensured that the driving cylinder 19 is sleeved on the outside of the adjusting rod 15 through the second limiting groove 22 and the second limiting strip 17, and the limiting cylinder 20 is inserted into the inside of the insertion rod 14 through the first limiting groove 21 and the first limiting strip 16. The first limiting strip 16 is used to cooperate with the limiting cylinder 20. The power part 25 drives the gear 24 to rotate, thereby driving the gear 24 ring 23 meshing with the gear 24 to rotate, and then the driving cylinder 19 fixedly connected to the inner side of the gear 24 ring 23 rotates. Due to the second limiting groove 22 and the first limiting strip 17, the limiting cylinder 20 is inserted into the inside of the insertion rod 14 through the first limiting groove 21 and the first limiting strip 16. The first limiting strip 16 is used to cooperate with the limiting cylinder 20. The power part 25 drives the gear 24 to rotate, thereby driving the gear 24 ring 23 meshing with the gear 24 to rotate, and then the driving cylinder 19 fixedly connected to the inner side of the gear 24 ring 23 rotates. With the cooperation of the second limit strip 17, the driving cylinder 19 will drive the adjusting rod 15 to rotate synchronously when it rotates. At the same time, since the adjusting rod 15 and the insertion rod 14 are connected by threads, and the first limit groove 21 cooperates with the first limit strip 16, the insertion rod 14 will not rotate with the adjusting rod 15. The insertion rod 14 will move up and down in the adjusting rod 15, thereby adjusting the length of the measuring rod 1 so that its bottom can be stably inserted deep into the original soil layer. After the system is used, it is also convenient to pull the measuring rod 1 out of the original soil layer, which further improves the measurement accuracy and stability of the system, simplifies the installation and adjustment steps, and makes the entire monitoring system more efficient and practical.

[0051] Example 4

[0052] On the basis of Example 3, Figure 5 and Figure 7 As shown, the expansion positioning mechanism 2 includes: a plurality of through holes 26 penetrating the side wall of the lower end of the insertion rod 14, the through holes 26 are distributed in a circular array around the central axis of the insertion rod 14, an expansion rod 27 with one end arranged in the through hole 26, a slider 28 connected to the other end of the expansion rod 27 and the bottom end of which is slidably connected to the bottom wall of the insertion rod 14, an end of which is hinged to the upper end connecting rod 29 of the slider 28, a moving rod 30 arranged on the central axis of the insertion rod 14 and hinged to the connecting rod 29, a sleeve 31 threadedly connected to the upper end of the moving rod 30, and a square rod 32 fixedly connected to the top end of the sleeve 31, and the moving rod 30 is slidably connected to the inner wall of the insertion rod 14 through a connecting rod.

[0053] The driving mechanism includes: a mounting tube 33 with a square cavity inside, an opening at the bottom and sleeved on the outer end of the square rod 32, a rotating shaft 34 that rotates through the monitoring box 3 and is fixedly connected to the top of the mounting tube 33, and a handle 35 arranged at the top of the rotating shaft 34.

[0054] The expansion rod 27 is extended out of the through hole 26 to extend the expansion rod 27, thereby expanding the lower end of the insertion rod 14 and forming a closer contact with the original soil layer.

[0055] Finally, it should be noted that the above embodiments are only used to illustrate the technical solutions of the present invention rather than to limit it. Although the present invention has been described with reference to the preferred embodiments of the present invention, it should be understood by those skilled in the art that various changes may be made in form and details without departing from the spirit and scope of the present invention as defined in the appended claims.

Claims

1. A real-time monitoring system for ground subsidence in subway tunnel construction, characterized in that: The invention comprises a measuring module and a monitoring module wirelessly connected to the measuring module, wherein the monitoring module comprises a plurality of measuring units, wherein the measuring units comprise: a plurality of monitoring holes vertically drilled from the ground to the original soil layer, a measuring rod (1) located in the monitoring holes and having a hollow interior and adjustable length, an expansion positioning mechanism (2) arranged at the bottom of the measuring rod (1), a monitoring box (3) installed on the ground above the monitoring holes, an adjustment mechanism arranged in the monitoring box (3) for adjusting the length of the measuring rod (1), a driving mechanism arranged on the monitoring box (3) for driving the expansion positioning mechanism (2), and a laser ranging sensor (4) arranged in the monitoring box (3), wherein the laser of the laser ranging sensor (4) is vertically projected onto the inner bottom wall of the measuring rod (1).

2. A real-time monitoring system for ground subsidence in subway tunnel construction according to claim 1, characterized in that: A mounting seat (5) is provided on the ground above the monitoring hole. A mounting opening (6) matching the size of the monitoring box (3) is provided through the center of the mounting seat (5). A positioning ring (7) matching the size of the measuring rod (1) is provided in the monitoring hole. The positioning ring (7) is connected to the inner wall of the mounting seat (5) through a connecting frame (8). The monitoring box (3) is installed in the mounting opening (6) of the mounting seat (5) through a plug-in assembly.

3. A real-time monitoring system for ground subsidence in subway tunnel construction according to claim 2, characterized in that: The plug-in assembly comprises: a groove (9) arranged on the inner wall of the mounting seat (5), a plug-in plate (10) slidably arranged in the groove (9), a compression spring (11) having one end connected to the plug-in plate (10) and the other end connected to the inner wall of the groove (9), a plug-in hole (12) penetrating the side wall of the monitoring box (3), and a movable rod (13) having one end connected to the plug-in plate (10) and the other end movably penetrating the wall of the groove (9), and the plug-in block has a side surface facing the plug-in hole (12) that is inclined downward.

4. The real-time monitoring system for ground subsidence in subway tunnel construction according to claim 1 is characterized by: The measuring rod (1) comprises: an insertion rod (14) with an open top and a hollow interior, and an adjustment rod (15) with open ends and a hollow interior, the insertion rod (14) being threadedly connected to the interior of the adjustment rod (15), a conical head being provided at the bottom of the insertion rod (14), a first limiting strip (16) being provided along the length direction of the insertion rod (14) being provided on the inner side wall thereof, and a second limiting strip (17) being provided along the length direction of the adjustment rod (15) being provided on the outer side wall thereof.

5. A real-time monitoring system for ground subsidence in subway tunnel construction according to claim 4, characterized in that: The bottom of the monitoring box (3) is provided with a through hole (18), and the adjustment mechanism comprises: a driving cylinder (19) with openings at both ends and a hollow interior, a limiting cylinder (20) with openings at both ends and a hollow interior, and a power assembly arranged in the monitoring box (3) for driving the driving cylinder (19) to rotate, the inner wall of the driving cylinder (19) is provided with a second limiting groove (22) adapted to the second limiting strip (17), and the outer wall of the limiting cylinder (20) is provided with a first limiting groove (21) adapted to the first limiting strip (16), the bottom end of the driving cylinder (19) passes through the through hole (18) and is sleeved on the top of the adjustment rod (15), the upper end of the limiting cylinder (20) is fixedly connected to the monitoring box (3), and the lower end passes through the through hole (18) and is inserted into the inside of the insertion rod (14).

6. A real-time monitoring system for ground subsidence in subway tunnel construction according to claim 5, characterized in that: The power assembly comprises: a gear (24) ring (23) fixedly sleeved on the outer side of the top end of the driving cylinder (19), a gear (24) meshing with the gear (24) ring (23), and a power member (25) arranged on the monitoring box (3) and connected to the gear (24) to drive the gear (24) to rotate.

7. The real-time monitoring system for ground subsidence in subway tunnel construction according to claim 4 is characterized by: The expansion positioning mechanism (2) comprises: a plurality of through holes (26) penetrating the side wall of the lower end of the insertion rod (14), the through holes (26) being distributed in a circular array around the central axis of the insertion rod (14), an expansion rod (27) with one end disposed in the through hole (26), a slider (28) connected to the other end of the expansion rod (27) and having its bottom end slidably connected to the bottom wall of the insertion rod (14), an end hinged to a connecting rod (29) at the upper end of the slider (28), a moving rod (30) disposed on the central axis of the insertion rod (14) and hinged to the connecting rod (29), a sleeve (31) threadedly connected to the upper end of the moving rod (30), and a square rod (32) fixedly connected to the top end of the sleeve (31), the moving rod (30) being slidably connected to the inner side wall of the insertion rod (14) via a connecting rod.

8. A real-time monitoring system for ground subsidence in subway tunnel construction according to claim 7, characterized in that: The driving mechanism comprises: a mounting tube (33) having a square cavity inside and an opening at the bottom end and being sleeved on the outer end of the square rod (32); a rotating shaft (34) rotatably passing through the monitoring box (3) and fixedly connected to the top end of the mounting tube (33); and a handle (35) arranged at the top end of the rotating shaft (34).

Citation Information

Cited By

  • Highway tunnel construction settlement measuring equipment and measuring method

    CN120778072A

  • Roadbed upwarp deformation alarm device and alarm method thereof

    CN122106043A

  • Subgrade camber deformation alarm device and alarm method thereof