On-load vector check test method used before starting of relay protection of newly-built and rebuilt and expanded transformer substations
By integrating the current source module, voltage source module and clamp phase meter module in the test equipment, the problem that traditional equipment cannot verify the polarity relationship of voltage sensors is solved, the power and volume of the equipment are reduced, and the relay protection of the substation is achieved. Efficient inspection, suitable for load vector inspection of new and expanded substations.
Patent Information
- Application Number
- CN202410954390.X
- Authority / Receiving Office
- CN · China
- Patent Type
- Applications(China)
- Current Assignee / Owner
- Filing Date
- 2024-07-17
- Publication Date
- 2024-11-08
AI Technical Summary
Traditional load vector testers cannot verify the polarity relationship between the first and second times of the voltage sensor, and the equipment is large in power, weight and volume, which is inconvenient for operation and cannot support the optimization of the substation startup test process.
A test equipment including a current source module, a voltage source module and a clamp phase meter module was designed. Through the separate operation of these modules, they can be used separately to verify the wiring accuracy of voltage and current transformers and through a clamp phase meter Verify the voltage phase relationship between the primary and secondary sides of the voltage transformer, reduce the power and volume of the equipment, and improve operational convenience.
It realizes independent verification of the correctness of the secondary circuit wiring of voltage and current transformers, reduces the power and weight of the equipment, improves operating efficiency, and is suitable for the relay protection before starting of new and expanded substations.
Smart Images

Figure CN118914697A_ABST
Abstract
Description
Technical Field
[0001] The present invention relates to the technical field of power system detection, and in particular to a load vector inspection test method before relay protection is started for a newly built or expanded substation. Background Art
[0002] The substation relay protection load vector check test technology is mainly used to check the correctness of the relay protection vector, and is also used to check the correctness of the vector of secondary equipment such as measuring instruments, meters, and control systems. The correctness of the vector of secondary equipment in the power system generally includes the correctness of the current and voltage secondary circuits, the correctness of the phase angle access between current and voltage, and the correctness of the corresponding relationship between the current and voltage transformer ratios; the traditional vector check method uses the method of pressurizing the secondary circuit of the voltage sensor and passing the current on the primary side of the current sensor to simultaneously pressurize and pass the current of the subcomponents, check the wiring of the voltage and current secondary circuits, and can also perform vector checks, but cannot verify the polarity relationship between the primary and secondary of the voltage sensor, and cannot support the optimization of the substation startup test process. Therefore, we have developed a load vector check test method for the start-up of relay protection in new and expanded substations.
[0003] Patent number CN201810406805.4 is a Chinese invention patent, which discloses a wireless load vector tester for the field of power measurement, including a voltage reference and a measuring host, and wireless communication is adopted between the two. The voltage reference and the measuring host each have a power supply, and the synchronous measurement and calculation of the voltage, current frequency, amplitude, phase and other electrical parameters of different measurement points based on the voltage reference are realized by using synchronization instructions; the measuring host can not only work independently and complete the measurement and calculation of various electrical parameters of three-phase voltage and three-phase current signals; it can also use the voltage reference as a reference, perform multiple separate measurements, save data, and synthesize all input measurement results with the voltage reference, and then directly display them on the display in a vector diagram, so as to perform PT phase nuclear and load vector tests; it is a convenient and fast handheld instrument suitable for smart substations, which can measure the amplitude and phase of signals between multiple different locations, perform load vector tests, and directly display hexagonal diagrams, but the invention has the following problems: first, it cannot verify the polarity relationship between the primary and secondary of the voltage sensor, and secondly, the use of the load vector tester has high power, large weight and volume, which is not convenient for test personnel to operate. Summary of the invention
[0004] The purpose of the present invention is to address the deficiencies of the prior art. By setting a current source module, a voltage source module, and a clamp phase meter module, the present invention solves the technical problems that the method of pressurizing and passing current through the sub-components used in the traditional vector inspection method can check the wiring of the voltage and current secondary circuits and can also perform vector inspection, but cannot verify the polarity relationship between the primary and secondary of the PT, and the traditional loaded vector tester has high power, large size and weight, and is not convenient for test personnel to operate.
[0005] To achieve the above object, the present invention provides the following technical solutions:
[0006] A load vector inspection test method for newly built and expanded substation relay protection before starting, comprising a test equipment module and a substation module to be inspected and verified, the test equipment module comprising a current source module, a voltage source module, and a clamp phase meter module, the upper end of the current source module is provided with a small voltage output port module, the output current of the current source module, the output voltage of the small voltage output port module, and the output voltage of the voltage source module use the same phase reference, the substation module to be inspected and verified comprises a newly built substation module and a expanded substation module, the newly built substation module uses the test equipment module to perform a full-station voltage test, a current test of each voltage level, a main transformer differential protection test, and a longitudinal differential protection test before being put into operation when the primary and secondary sides of the substation are delivered and the secondary side equipment is configured, and the expanded substation module needs to use the test equipment module to perform a relay protection vector inspection test before being put into operation.
[0007] As a preferred embodiment, the full-station pressure test includes the following steps:
[0008] Step 1: When the bus voltage transformer of the whole station of the newly built substation module is in operation state and the voltage secondary circuit is in normal operation state, an access interval is selected from the lower voltage level (110kV) of the star side of the main transformer of the newly built substation module, and the voltage source module is connected to the substation primary equipment in this interval, and the voltage flows to other voltage level lines (220kV, 35kV) through the access interval, bus, transformer interval, and transformer;
[0009] Step 2: By changing the state of the primary equipment, all the busbars and busbar voltage transformers of the newly built substation module have voltage. If the test is carried out with only one transformer, there is no need to consider the state of the busbar except for the interval voltage level (220kV, 35kV). If the test is carried out with two or more transformers, it is necessary to clarify which busbar each transformer of other voltage levels (220kV, 35kV) carries, and the busbars between the busbars of each transformer of other voltage levels (220kV, 35kV) except for the interval voltage level are disconnected;
[0010] Step 3: In addition to the conventional vector check of each voltage transformer, use a special clamp phase meter to check the phase relationship between the primary and secondary voltages;
[0011] Step 4: After checking that the voltage transformers and their secondary circuits of the newly built substation module are normal, close each bus tie and verify the correctness of the parallel connection between the bus voltage transformers. If the access interval is not connected, select the bushing as the access point of the voltage source module. If the access interval is connected, select the grounding copper busbar on the line side of the switch in this interval as the access position of the voltage source module.
[0012] As a preferred embodiment, the current flow test of each voltage level includes the following steps:
[0013] Step 1: Select an interval within the test voltage level in the newly built substation module as the entry interval of the current source module, and other intervals as the current outflow intervals. If the entry interval is not connected, the bushing is selected as the entry point of the current source module. If the entry interval is connected, the grounding copper busbar of the switch line side of this interval is selected as the access position of the current source module;
[0014] Step 2: The busbar side switch, switch, and switch line side grounding switch of the outflow interval switch are closed, and the current flows in the direction that the current source module enters the interval, the busbar flows out of the interval, and finally the ground network flows back to the equipment to form a loop;
[0015] Step three: insert the small voltage output port module into the secondary side of the voltage transformer to provide a phase reference sense for the relay protection device; if the inflow and outflow intervals are not on the same bus, the bus-coupler interval can be brought in between to complete the verification of the bus-coupler interval current transformer and its secondary circuit.
[0016] As a preferred embodiment, the main transformer differential protection test includes the following steps:
[0017] Step 1: Place two currents on both sides of the transformer in the newly built substation module, with the current on one side flowing into the transformer and the current on the other side flowing out of the transformer;
[0018] Step 2: Calculate the output current values of the two current source modules according to the rated power of the transformer at different voltage levels. After the current is passed through both sides, check whether the differential protection of the main transformer meets expectations.
[0019] Step 3: If the main transformer has three voltage levels, you can choose to test the high and medium voltage sides and the medium and low voltage sides separately, or you can choose to apply current to the three sides at the same time.
[0020] As a preferred embodiment, the longitudinal differential protection test comprises the following steps:
[0021] Step 1: Place two current source modules at the substations at both ends of the line respectively, and after determining the current flow direction, apply currents of the same amplitude on both sides. The current application method is the same as the current flow test of each voltage level;
[0022] Step 2: After current is passed through both sides, check whether the longitudinal differential protection meets expectations.
[0023] As a preferred embodiment, the relay protection vector inspection test includes the inspection of the single-outlet interval expansion and reconstruction of the current transformer and its secondary circuit, and the relay protection vector inspection of the bus voltage transformer replacement, and the inspection of the single-outlet interval expansion and reconstruction of the current transformer and its secondary circuit includes the following steps:
[0024] Step 1: Connect the current module to the busbar of the modified and expanded substation module. The connection method is the same as the current flow test of each voltage level. If the busbar is not within the scope of the modification and expansion, the current flows into the grounding grid from the grounding knife switch on the busbar side of the switch through the switch, and a current loop is formed through the grounding grid. If the busbar is within the scope of the modification and expansion, the current can flow out from the grounding knife switch on the line side of other interval switches, and a loop is formed through the grounding grid;
[0025] Step 2: Connect the secondary small voltage output on the current source module to the line protection device to provide a phase reference;
[0026] Step 3: In addition to the routine vector check, use a dedicated clamp phase meter to measure the secondary current to confirm that the wiring is correct.
[0027] As a preferred embodiment, the relay protection vector check for replacing the bus voltage transformer includes the following steps:
[0028] Step 1: Connect the voltage source module to the primary side of the voltage transformer through the bus voltage transformer grounding switch, and perform a conventional vector check after the device outputs;
[0029] Step 2: In addition to the routine vector check, use a dedicated clamp phase meter to measure the secondary voltage to confirm that the wiring is correct.
[0030] As a preferred embodiment, the grounding copper busbar needs to be removed in advance before the full-station voltage test and the current test of each voltage level.
[0031] Beneficial effects of the present invention:
[0032] (1) In the present invention, a test equipment module is provided, wherein the current source module, the voltage source module, and the clamp phase meter module included therein work independently and separately. The current source module, the voltage source module, or the clamp phase meter module can be used alone to test the voltage transformer and the current transformer. Compared with the conventional load vector tester, the power consumption is greatly reduced, and the weight and volume are also reduced, which is convenient for the test personnel to operate and improves the work efficiency.
[0033] (2) The correctness test of the installation of the voltage transformer and the wiring of the AC voltage sampling system composed of its secondary circuit in the present invention is carried out. The phase sequence, phase and amplitude of the primary test voltage are used as a reference. A small signal reference voltage is obtained by an external independent standard voltage transformer or an independent method such as a source sampling output built into the test device, and is used as a standard reference phasor for phase verification (phase sequence, transformation ratio, polarity) of the correctness of the installation and wiring of the voltage transformer. The test principle does not involve other equipment. Whether the wiring of other equipment is correct or not will not affect the correctness of the wiring itself. The verification can be carried out independently, and can also be used in conjunction with a special clamp phase meter to check the phase relationship between the primary and secondary voltages of the voltage transformer.
[0034] (3) The correctness test of the installation of the current transformer and the wiring of the AC current sampling system composed of its secondary circuit in the present invention is to obtain a small signal reference (which can be in the form of a small current or a small current converted into a voltage) through an external independent standard current transformer or a built-in source sampling output of the test device, etc., as a standard reference phasor for verifying the correctness of the installation and wiring of the current transformer (phase sequence, transformation ratio, polarity). The test principle does not involve other equipment, and whether the wiring of other equipment is correct or not will not affect the correctness of the wiring itself. It can be verified independently without paying attention to the phase relationship between the output phase of the current source module and the operating voltage (interval current).
[0035] To sum up, the invention has the advantages of being able to independently verify the correctness of the installation and wiring of the AC sampling system composed of current and voltage transformers and their secondary circuits, and being able to check the phase relationship between the primary and secondary voltages of the voltage transformer, and is particularly suitable for the field of power system detection technology. BRIEF DESCRIPTION OF THE DRAWINGS
[0036] In order to more clearly illustrate the technical solutions of the embodiments of the present invention, the accompanying drawings required for use in the description of the embodiments will be briefly introduced below. Obviously, the accompanying drawings described below are only some embodiments of the present invention. For ordinary technicians in this field, other accompanying drawings can be obtained based on these accompanying drawings without paying creative work.
[0037] Figure 1 The figure is a schematic diagram of the overall step structure of the substation module to be tested.
[0038] Figure 2 This is a schematic diagram of the structure of the test equipment module.
[0039] Figure 3 This is a schematic diagram of the step structure of the full-station pressure test.
[0040] Figure 4 This is a schematic diagram of the circuit structure of the full-station pressure test part.
[0041] Figure 5 It is a schematic diagram of the step structure of the current-through test part for each voltage level.
[0042] Figure 6 It is a schematic diagram of the circuit structure of the current-through test part of each voltage level.
[0043] Figure 7 Schematic diagram of the step structure of the main transformer differential protection test part.
[0044] Figure 8 This is the circuit structure diagram of the main transformer differential protection test part.
[0045] Fig. 9 This is a schematic diagram of the step structure of the longitudinal differential protection test part.
[0046] Fig.10 This is a schematic diagram of the circuit structure of the longitudinal differential protection test part.
[0047] Fig.11 Schematic diagram of the step structure of the relay protection vector check test part.
[0048] Fig.12 This is a schematic diagram of the circuit structure of the single-outlet bay expansion test section.
[0049] Fig.13 Schematic diagram of the circuit structure of the relay protection vector inspection test part for replacing the bus voltage transformer. DETAILED DESCRIPTION
[0050] The technical solutions in the embodiments of the present invention are clearly and completely described below in conjunction with the accompanying drawings.
[0051] Embodiment 1
[0052] like Figures 1 to 13As shown, the present invention provides a load vector inspection test method before the relay protection of a newly built or expanded substation is started, including a test equipment module and a substation module to be inspected and verified. The test equipment module includes a current source module, a voltage source module, and a clamp phase meter module. The three modules contained in the test equipment module exist independently and can be used separately and independently. Compared with a conventional load vector tester, the volume, weight, and power are reduced, which is convenient for test personnel to carry and operate, and improves work efficiency. A small voltage output port module is provided at the upper end of the current source module. In a current flow test, only the current source module needs to be connected to obtain a small voltage without connecting another voltage source module. The output current of the current source module, the output voltage of the small voltage output port module, and the output voltage of the voltage source module use the same phase reference, and a wireless or wired synchronization signal is used to form a phase. The same fragrance reference can be regarded as the same source, and the clamp phase meter module can use the output phase of the current source module and the voltage source module as the reference to measure the current and voltage. The substation modules to be inspected and verified include new substation modules and modified and expanded substation modules. For different substation types, relevant load vector inspection tests are carried out before the start of relay protection. When the primary and secondary sides of the substation are delivered and the secondary side equipment is configured, the new substation module uses the test equipment module to carry out full-station voltage test, current test of each voltage level, main transformer differential protection test, and longitudinal differential protection test before commissioning. The modified and expanded substation module needs to use the test equipment module to carry out relay protection vector inspection test before commissioning. The following test steps are all tested by taking 220kV substation and substation with 220kV, 110kV, and 35kV voltage levels as examples.
[0053] Further, if Figure 3 As shown, the full-station pressure test includes the following steps:
[0054] Step 1: When the bus voltage transformer of the whole station of the newly built substation module is in operation state and the voltage secondary circuit is in normal operation state, an access interval is selected from the lower voltage level (110kV) of the star side of the main transformer of the newly built substation module, and the voltage source module is connected to the substation primary equipment in this interval, and the voltage flows to other voltage level lines (220kV, 35kV) through the access interval, bus, transformer interval, and transformer;
[0055] Step 2: By changing the state of the primary equipment, all the busbars and busbar voltage transformers of the newly built substation module are voltage-free. If the test is carried out with only one transformer, there is no need to consider the state of the busbar except for the interval voltage level (220kV, 35kV). If the test is carried out with two or more transformers, it is necessary to clarify which busbar each transformer of other voltage levels (220kV, 35kV) carries, and the busbars of each transformer of other voltage levels (220kV, 35kV) except the interval voltage level are disconnected to prevent the voltage difference between the transformers from forming a circulating current due to inconsistent gears between the transformers;
[0056] Step 3: In addition to the conventional vector check of each voltage transformer, use a special clamp phase meter to check the phase relationship between the primary and secondary voltages;
[0057] Step 4: After checking that the voltage transformers and their secondary circuits of the new substation module are normal, close each bus tie and verify the correctness of the parallel connection between the bus voltage transformers. If the access interval is not connected, select the bushing as the access point of the voltage source module. If the access interval is connected, select the grounding copper busbar on the line side of the switch in this interval as the access position of the voltage source module. The new substation module is subjected to a full-station voltage test to verify the accuracy of the voltage transformers and their secondary circuits and the vectors on the relay protection device of the whole station.
[0058] Further, if Figure 5 As shown, the current-through test of each voltage level includes the following steps:
[0059] Step 1: Select an interval within the test voltage level in the newly built substation module as the entry interval of the current source module, and other intervals as the current outflow intervals. If the entry interval is not connected, the bushing is selected as the entry point of the current source module. If the entry interval is connected, the grounding copper busbar of the switch line side of this interval is selected as the access position of the current source module;
[0060] Step 2: The busbar side switch, switch, and switch line side grounding switch of the outflow interval switch are closed, and the current flows in the direction that the current source module enters the interval, the busbar flows out of the interval, and finally the ground network flows back to the equipment to form a loop;
[0061] Step three: insert the small voltage output port module into the secondary side of the voltage transformer to provide a phase reference sense for the relay protection device; if the inflow and outflow intervals are not on the same bus, the bus-tie interval can be brought in between to complete the verification of the current transformer and its secondary circuit in the bus-tie interval. The new substation module is tested for current flow at various voltage levels to check the correctness of the vectors on the current transformers and their secondary circuits and relay protection devices of the entire station, and the bus differential protection can be verified at the same time.
[0062] Further, if Figure 7 As shown, the main transformer differential protection test includes the following steps:
[0063] Step 1: Place two currents on both sides of the transformer in the newly built substation module, with the current on one side flowing into the transformer and the current on the other side flowing out of the transformer;
[0064] Step 2: Calculate the output current values of the two current source modules according to the rated power of the transformer at different voltage levels. After the current is passed through both sides, check whether the differential protection of the main transformer meets expectations.
[0065] Step 3: If the main transformer has three voltage levels, you can choose to test the high and medium voltage sides and the medium and low voltage sides separately, or you can choose to apply current on the three sides at the same time. The main transformer differential protection test is carried out on the newly built substation module in order to test the wiring and the current flow test of each voltage level.
[0066] Further, if Fig. 9 As shown, the longitudinal differential protection test includes the following steps:
[0067] Step 1: Place two current source modules at the substations at both ends of the line respectively, and after determining the current flow direction, apply currents of the same amplitude on both sides. The current application method is the same as the current flow test of each voltage level;
[0068] Step 2: After current is passed through both sides, check whether the longitudinal differential protection meets expectations. The longitudinal differential protection test is carried out on the newly built substation module to check whether the longitudinal differential protection meets expectations.
[0069] Further, if Fig.11 As shown, the relay protection vector inspection test includes the inspection of the single-outlet interval expansion current transformer and its secondary circuit, and the relay protection vector inspection of the bus voltage transformer replacement. The inspection of the single-outlet interval expansion current transformer and its secondary circuit includes the following steps:
[0070] Step 1: Connect the current module to the busbar of the modified and expanded substation module. The connection method is the same as the current flow test of each voltage level. If the busbar is not within the scope of the modification and expansion, the current flows into the grounding grid from the grounding knife switch on the busbar side of the switch through the switch, and a current loop is formed through the grounding grid. If the busbar is within the scope of the modification and expansion, the current can flow out from the grounding knife on the line side of other interval switches, and a loop is formed through the grounding grid. While verifying the correctness of the CT and its secondary circuit, the correctness of the bus differential protection is verified;
[0071] Step 2: Connect the secondary small voltage output on the current source module to the line protection device to provide a phase reference;
[0072] Step 3: In addition to the routine vector check, use a dedicated clamp phase meter to measure the secondary current to confirm that the wiring is correct.
[0073] Further, the relay protection vector check for replacing the bus voltage transformer includes the following steps:
[0074] Step 1: Connect the voltage source module to the primary side of the voltage transformer through the bus voltage transformer grounding switch, and perform a conventional vector check after the device outputs;
[0075] Step 2: In addition to the routine vector check, use a dedicated clamp phase meter to measure the secondary voltage to confirm that the wiring is correct.
[0076] Further, if Fig.13 As shown, the grounding copper busbar needs to be removed in advance before the full-station voltage test and the current test of each voltage level, which will affect the accuracy of the test, resulting in errors in the test data, and may cause arcing in the equipment, resulting in electrical accidents.
[0077] Working process: First determine the type of substation. If it is a newly built substation module, it is necessary to conduct full-station voltage test, current test of each voltage level, main transformer differential protection test, and longitudinal differential protection test;
[0078] The whole station voltage test is carried out. First, an access interval is selected within the lower voltage level (110kV) of the main transformer star side of the newly built substation module. The voltage source module is connected to the substation primary equipment in this interval, and the voltage flows to other voltage level lines (220kV, 35kV) through the access interval, bus, transformer interval, and transformer; further, by changing the state of the primary equipment, the whole station bus and bus voltage transformer of the newly built substation module are all voltage. If the test is carried out with only one transformer, there is no need to consider the state of the bus coupling except the access interval voltage level (220kV, 35kV). If the test is carried out with two or more transformers, it is necessary to clarify which bus each transformer of other voltage levels (220kV, 35kV) carries, and the voltage level of each transformer other than the access interval voltage level (220kV, 35kV) The busbars of the transformers are disconnected to prevent the voltage difference between the transformers from forming a circulating current due to the inconsistency of the gears between the transformers; further, in addition to the conventional vector check, each voltage transformer uses a special clamp phase meter to check the phase relationship between the primary and secondary voltages; further, after checking that the voltage transformers of the entire station and their secondary circuits of the newly built substation module are normal, close each busbar, and verify the correctness of the parallel connection between the bus voltage transformers. If the access interval is not connected, the bushing is selected as the access point of the voltage source module. If the access interval is connected, the grounding copper busbar on the switch line side of this interval is selected as the access position of the voltage source module. The new substation module is subjected to a full-station voltage test to verify the accuracy of the vectors of the voltage transformers and their secondary circuits and relay protection devices of the entire station;
[0079] The current flow test of each voltage level is carried out. First, a gap is selected within the test voltage level in the newly built substation module as the entry gap of the current source module, and other gaps are used as current outflow gaps. If the entry gap is not connected, the bushing is selected as the entry point of the current source module. If the entry gap is connected, the grounding copper busbar on the line side of the switch in this gap is selected as the access position of the current source module. Furthermore, the busbar side switch, switch, and line side grounding knife of the switch in the outflow gap are closed, and the current flows in the direction of the current source. The module enters the interval, the busbar flows out of the interval, and finally the ground network flows back to the equipment to form a loop; further, the small voltage output port module is inserted into the secondary side of the voltage transformer to provide a phase reference sense for the relay protection device; if the inflow and outflow intervals are not on the same bus, the busbar interval can be brought in in the middle to complete the verification of the busbar interval current transformer and its secondary circuit. The new substation module is tested for current flow at various voltage levels in order to check the correctness of the vectors on the current transformer and its secondary circuit and relay protection device of the entire station, and the busbar differential protection can be verified at the same time;
[0080] Main transformer differential protection test: To conduct this test, first place two current sources on both sides of the transformer in the newly built substation module, with the current on one side flowing into the transformer and the current on the other side flowing out of the transformer; further, calculate the output current value of the two current source modules according to the rated power of the transformer at different voltage levels. After the current is passed through both sides, check whether the main transformer differential protection meets expectations. If the main transformer has three voltage levels, you can choose to test the high and medium voltage sides and the medium and low voltage sides separately, or you can choose to apply current on the three sides at the same time. The purpose of conducting a main transformer differential protection test on the newly built substation module is to test the wiring and the current flow test of each voltage level;
[0081] Longitudinal differential protection test: To conduct this test, firstly, two current source modules are placed at the substations at both ends of the line, and after the current flow direction is determined, currents of the same amplitude are applied on both sides. The current application method is the same as the current flow test of each voltage level. Furthermore, after the current is passed through both sides, it is checked whether the longitudinal differential protection meets expectations. The longitudinal differential protection test is conducted on the newly built substation module to check whether the longitudinal differential protection meets expectations.
[0082] If the substation is judged to be a modified or expanded substation module, it is necessary to check the single-outlet bay modified or expanded current transformer and its secondary circuit, and replace the relay protection vector of the busbar voltage transformer;
[0083] Inspection of the current transformer and its secondary circuit of the single-outlet interval expansion and reconstruction. For this test, first connect the current module to the bus of the expanded and reconstructed substation module. The connection method is the same as the current flow test of each voltage level. If the bus is not within the scope of expansion and reconstruction, the current flows into the earth grid through the switch from the grounding knife on the bus side of the switch, and forms a current loop through the earth grid. If the bus is within the scope of expansion and reconstruction, the current can flow out from the grounding knife on the line side of other interval switches, and form a loop through the earth grid. While verifying the correctness of the CT and its secondary circuit, the correctness of the bus differential protection is verified; further, the secondary small voltage output on the current source module is connected to the line protection device to provide a phase reference; further, in addition to the conventional vector inspection, a special clamp phase meter module is used to measure the secondary side current to confirm that the wiring is correct.
[0084] Replace the relay protection vector check of the bus voltage transformer. For this test, first connect the voltage source module to the primary side of the voltage transformer through the bus voltage transformer grounding switch, and perform a conventional vector check after the device outputs. Furthermore, in addition to the conventional vector check, use a dedicated clamp phase meter module to measure the secondary side voltage to confirm that the wiring is correct.
[0085] In the description of the present invention, it is necessary to understand that the directions or positional relationships indicated by the terms "front and back", "left and right", etc. are based on the directions or positional relationships shown in the accompanying drawings, and are only for the convenience of describing the present invention and simplifying the description, rather than indicating or implying that the device or component referred to must have a specific direction, be constructed and operated in a specific direction, and therefore cannot be understood as a limitation on the invention.
[0086] Of course, in the present technical solution, those skilled in the art should understand that the term "one" should be understood as "at least one" or "one or more", that is, in one embodiment, the number of an element may be one, while in another embodiment, the number of the element may be multiple, and the term "one" should not be understood as a limitation on the quantity.
[0087] The above is only a preferred specific embodiment of the present invention, but the protection scope of the present invention is not limited thereto. Any changes or substitutions that can be easily thought of by a person skilled in the art under the technical guidance of the present invention should be included in the protection scope of the present invention. Therefore, the protection scope of the present invention should be based on the protection scope of the claims.
Claims
1. A load vector inspection test method for relay protection before starting a new or expanded substation, characterized in that: It includes a test equipment module and a substation module to be inspected and verified. The test equipment module includes a current source module, a voltage source module, and a clamp phase meter module. A small voltage output port module is provided at the upper end of the current source module. The output current of the current source module, the output voltage of the small voltage output port module, and the output voltage of the voltage source module use the same phase reference. The substation module to be inspected and verified includes a newly built substation module and a modified and expanded substation module. When the primary and secondary sides of the substation are delivered and the secondary side equipment is configured, the newly built substation module uses the test equipment module to perform a full-station voltage test, a current test of each voltage level, a main transformer differential protection test, and a longitudinal differential protection test before being put into operation. The modified and expanded substation module needs to use the test equipment module to perform a relay protection vector inspection test before being put into operation.
2. A load vector inspection test method for newly built and expanded substation relay protection before starting according to claim 1, characterized in that: The full-station pressure test comprises the following steps: Step 1: When the bus voltage transformer of the whole station of the newly built substation module is in operation state and the voltage secondary circuit is in normal operation state, an access interval is selected from the lower voltage level (110kV) of the star side of the main transformer of the newly built substation module, and the voltage source module is connected to the substation primary equipment in this interval, and the voltage flows to other voltage level lines (220kV, 35kV) through the access interval, bus, transformer interval, and transformer; Step 2: By changing the state of the primary equipment, all the busbars and busbar voltage transformers of the newly built substation module have voltage. If the test is carried out with only one transformer, there is no need to consider the state of the busbar except for the interval voltage level (220kV, 35kV). If the test is carried out with two or more transformers, it is necessary to clarify which busbar each transformer of other voltage levels (220kV, 35kV) carries, and the busbars between the busbars of each transformer of other voltage levels (220kV, 35kV) except for the interval voltage level are disconnected; Step 3: In addition to the conventional vector check of each voltage transformer, use a special clamp phase meter to check the phase relationship between the primary and secondary voltages; Step 4: After checking that the voltage transformers and their secondary circuits of the newly built substation module are normal, close each bus tie and verify the correctness of the parallel connection between the bus voltage transformers. If the access interval is not connected, select the bushing as the access point of the voltage source module. If the access interval is connected, select the grounding copper busbar on the line side of the switch in this interval as the access position of the voltage source module.
3. A load vector inspection test method for relay protection before starting a new or expanded substation according to claim 1, characterized in that: The current-through test of each voltage level comprises the following steps: Step 1: Select an interval within the test voltage level in the newly built substation module as the entry interval of the current source module, and other intervals as the current outflow intervals. If the entry interval is not connected, the bushing is selected as the entry point of the current source module. If the entry interval is connected, the grounding copper busbar of the switch line side of this interval is selected as the access position of the current source module; Step 2: The busbar side switch, switch, and switch line side grounding switch of the outgoing interval switch are closed, and the current flows in the direction that the current source module enters the interval, the busbar flows out of the interval, and finally the ground network flows back to the equipment to form a loop; Step three: insert the small voltage output port module into the secondary side of the voltage transformer to provide a phase reference sense for the relay protection device; if the inflow and outflow intervals are not on the same bus, the bus-coupler interval can be brought in between to complete the verification of the bus-coupler interval current transformer and its secondary circuit.
4. A load vector inspection test method for relay protection before starting a new or expanded substation according to claim 1, characterized in that: The main transformer differential protection test comprises the following steps: Step 1: Place two currents on both sides of the transformer in the newly built substation module, with the current on one side flowing into the transformer and the current on the other side flowing out of the transformer; Step 2: Calculate the output current values of the two current source modules according to the rated power of the transformer at different voltage levels. After the current is passed through both sides, check whether the differential protection of the main transformer meets expectations. Step 3: If the main transformer has three voltage levels, you can choose to test the high and medium voltage sides and the medium and low voltage sides separately, or you can choose to apply current to the three sides at the same time.
5. A load vector inspection test method for newly built and expanded substation relay protection before starting according to claim 3, characterized in that: The longitudinal differential protection test comprises the following steps: Step 1: Place two current source modules at the substations at both ends of the line respectively, and after determining the current flow direction, apply currents of the same amplitude on both sides, and the current application method is the same as the current flow test of each voltage level; Step 2: After current is passed through both sides, check whether the longitudinal differential protection meets expectations.
6. A load vector inspection test method for relay protection before starting a new or expanded substation according to claim 1, characterized in that: The relay protection vector inspection test includes the inspection of the single-outlet interval expansion current transformer and its secondary circuit, and the relay protection vector inspection of the bus voltage transformer replacement. The inspection of the single-outlet interval expansion current transformer and its secondary circuit includes the following steps: Step 1: Connect the current module to the busbar of the modified and expanded substation module. The connection method is the same as the current flow test of each voltage level. If the busbar is not within the scope of the modification and expansion, the current flows into the grounding grid from the grounding knife switch on the busbar side of the switch through the switch, and a current loop is formed through the grounding grid. If the busbar is within the scope of the modification and expansion, the current can flow out from the grounding knife switch on the line side of other interval switches, and a loop is formed through the grounding grid; Step 2: Connect the secondary small voltage output on the current source module to the line protection device to provide a phase reference; Step 3: In addition to the conventional vector check, use a dedicated clamp phase meter module to measure the secondary current to confirm that the wiring is correct.
7. A load vector inspection test method for newly built and expanded substation relay protection before starting according to claim 6, characterized in that: The relay protection vector check for replacing the bus voltage transformer comprises the following steps: Step 1: Connect the voltage source module to the primary side of the voltage transformer through the bus voltage transformer grounding switch, and perform a conventional vector check after the device outputs; Step 2: In addition to the conventional vector check, use a dedicated clamp phase meter module to measure the secondary voltage to confirm that the wiring is correct.
8. A load vector inspection test method for relay protection before starting a new or expanded substation according to claim 1, characterized in that: The grounding copper busbar must be removed in advance before the full-station voltage test and the current test of each voltage level.
Citation Information
Patent Citations
Method for checking and testing relay protection vector before operation of newly-built transformer station
CN102510010A
Method for checking and testing relay protection vectors before commissioning of capacitance-compensated transformer substation
CN102593737A
Measuring and testing method for relay protection vector based on synchronous trigger pressurized flow technology
CN109212360A
Three-phase current and voltage application comprehensive test system
CN111122959A
On-load test system before starting relay protection of transformer substation
CN115248353A