Scheduling method and system for intelligent charging of new energy electric vehicle

By optimizing charging scheduling based on the expected pick-up time and parking time of the electric vehicle, determining the target charging volume and power, and using shared charging piles, the problems of unstable voltage and low charging efficiency of the electric vehicle are solved, and more efficient grid utilization and Improved user experience.

CN118928120AActive Publication Date: 2024-11-12SOUTH CHINA UNIV OF TECH
View PDF 2 Cites 0 Cited by

Patent Information

Application Number
CN202411245662.5
Authority / Receiving Office
CN · China
Patent Type
Applications(China)
Current Assignee / Owner
Filing Date
2024-09-06
Publication Date
2024-11-12
Estimated Expiration
2044-09-06

AI Technical Summary

Technical Problem

In the centralized dispatch mode of electric vehicles, the voltage is unstable and the utilization efficiency of charging piles is low, resulting in a large peak-to-valley difference in the grid load, affecting the safety of the grid and the user's charging experience.

Method used

By obtaining the expected pick-up time and parking time of the electric vehicle to be charged, sorting and filtering out vehicles of the same level, determining the target charging amount and charging power, scheduling the charging sequence and power, optimizing the charging scheduling, and using shared charging piles for charging.

Benefits of technology

Maintain the stability of the charging voltage, reduce the impact of excessive charging vehicles on electricity consumption, improve the efficiency of charging time, and reduce the inconvenience of users due to inability to charge in time.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN118928120A_ABST
    Figure CN118928120A_ABST
Patent Text Reader

Abstract

The invention relates to the technical field of electric vehicle charging, in particular to a new energy electric vehicle intelligent charging scheduling method and system, and the method comprises the following steps: obtaining the expected vehicle taking time of a to-be-charged electric vehicle, and determining the expected parking time of the to-be-charged electric vehicle based on the expected vehicle taking time and the current moment; performing preliminary sorting on the to-be-charged electric vehicles based on the expected vehicle taking time to obtain a first charging sequence; the expected parking time of the to-be-charged electric vehicles is determined according to the expected vehicle taking time and the current moment, the to-be-charged electric vehicles with the same expected parking time are screened out based on the first charging sequence, and a first same-level electric vehicle set is obtained; obtaining the target charging amount of each to-be-charged electric vehicle in the first same-level electric vehicle set; the stability of the charging voltage can be maintained, the influence of too many charged vehicles on electricity utilization is reduced, and the utilization efficiency of the charging time is improved.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The present invention relates to the technical field of electric vehicle charging, and in particular to a scheduling method and system for intelligent charging of new energy electric vehicles. Background Art

[0002] Electric vehicles are gaining more and more attention from various countries in terms of energy conservation, emission reduction and environmental improvement, and are being actively promoted and applied in many fields. With the increasing number of electric vehicles, the disorderly charging of a large number of electric vehicles will increase the peak-to-valley difference of the power grid load, causing increased network losses, affecting the power quality of the distribution network system, and posing a threat to the safe and stable operation of the power grid. Reasonable optimization and scheduling strategies can effectively limit the negative impact of disorderly charging of electric vehicles on the power system, reduce the peak-to-valley difference of the load of the distribution system, improve the safety and economy of the power grid, enrich the means of power grid operation, regulation and control, improve the charging experience of users, and promote the healthy and rapid development of the electric vehicle industry.

[0003] The existing centralized dispatching mode of electric vehicles will cause voltage instability when multiple electric vehicles are charging at the same time. After charging is completed, the idle charging piles must wait for the previous vehicle to leave in time before they can continue to serve the vehicles waiting behind. This fails to give full play to the efficiency of equipment utilization and results in low efficiency in charging time.

[0004] To this end, we propose a scheduling method and system for intelligent charging of new energy electric vehicles to solve the above problems. Summary of the invention

[0005] The purpose of the present invention is to provide a scheduling method and system for intelligent charging of new energy electric vehicles to solve the problems raised in the above background technology.

[0006] To achieve the above object, the present invention provides the following technical solution: a scheduling method and system for intelligent charging of new energy electric vehicles, the method comprising the following steps:

[0007] S1: Obtaining an expected pick-up time for the electric vehicle to be charged, and determining an expected parking time for the electric vehicle to be charged based on the expected pick-up time and the current time;

[0008] Preliminarily sorting the electric vehicles to be charged based on the expected pick-up time to obtain a first charging sequence;

[0009] S2: determining the expected parking time of the electric vehicle to be charged according to the expected pick-up time and the current time, and filtering out the electric vehicles to be charged with the same expected parking time based on the first charging sequence to obtain a first set of electric vehicles of the same level;

[0010] Obtaining target charging amounts of each to-be-charged electric vehicle in a first electric vehicle set of the same level, and sorting the first electric vehicles of the same level in ascending order based on the target charging amounts to obtain a second charging sequence;

[0011] S3: extracting electric vehicles to be charged with the same target charging amount based on the first set of electric vehicles of the same level to obtain a second set of electric vehicles of the same level;

[0012] Acquiring a charging power of the electric vehicle to be charged to obtain a first charging power;

[0013] determining a target charging sequence based on the first charging sequence, the second charging sequence, and the first charging power;

[0014] Determine a target charging power based on the target charging time and the expected parking time, wherein the target charging power is the first charging power or the second charging power;

[0015] S4: Scheduling the electric vehicles to be charged based on the target charging sequence and the target charging power to obtain a scheduling result;

[0016] S5: Based on the scheduling result, the electric vehicles to be charged are charged through the shared charging piles.

[0017] By adopting the above technical scheme, the charging power of the electric vehicle to be charged is determined according to the expected pick-up time, the expected parking time and the target charging amount of the electric vehicle to be charged, the charging power is adjusted according to the pick-up time, and the number of electric vehicles to be charged is adjusted according to the available power. The charging of the electric vehicle to be charged is scheduled according to the pick-up time, the charging power and the number of electric vehicles to be charged, the stability of the charging voltage is maintained, the impact of too many charging vehicles on electricity consumption is reduced, and the utilization efficiency of the charging time is improved.

[0018] Preferably, the step of determining the target charging power based on the target charging time and the expected parking time, wherein the charging power is the first charging power or the second charging power, comprises:

[0019] determining a target charging time based on the first charging power and the target charging amount;

[0020] Compare the target charging time with the expected parking time to determine whether the expected parking time is consistent with the target charging time;

[0021] If it is determined that the expected parking time is consistent with the target charging time, the first charging power is used as the target charging power;

[0022] If it is determined that the expected parking time is inconsistent with the target charging time, the second charging power is used as the target charging power.

[0023] Preferably, the step of determining the target charging sequence based on the first charging sequence, the second charging sequence and the first charging power includes:

[0024] Acquire electric vehicles to be charged within the same expected vehicle pickup time based on the first charging sequence, acquire target charging amounts corresponding to the electric vehicles to be charged within the same expected vehicle pickup time based on the second charging sequence; determine a second charging power for the electric vehicles to be charged based on the expected parking time and the target charging amount; and count the number of electric vehicles to be charged within the same expected vehicle pickup time;

[0025] When the target charging time is equal to the expected parking time, the second charging sequence is directly used as the target charging sequence;

[0026] When the target charging time is less than the expected parking time, the electric vehicle to be charged within the expected pickup time is taken as the target charging vehicle, and it is determined whether the number of electric vehicles to be charged within the same expected pickup time is greater than 1. If it is less than or equal to 1, the electric vehicle to be charged within the next expected pickup time is taken as the second charging vehicle to obtain the target charging sequence; if it is greater than 1, the other electric vehicles to be charged within the same expected pickup time are taken as the second charging vehicle to obtain the target charging sequence;

[0027] When the target charging time is greater than the expected parking time, the overall required power within the same expected car pick-up time is obtained, and it is determined whether the overall required power exceeds the preset power threshold, and a judgment result is obtained. The target charging sequence is determined based on the judgment result, and the judgment result is that the overall required power exceeds the preset power threshold or the overall required power does not exceed the preset power threshold.

[0028] Preferably, the step of determining the second charging power of the electric vehicle to be charged based on the expected parking time, the target charging amount and the charging start time includes: obtaining the charging start time of the electric vehicle to be charged; obtaining the target charging amount of the electric vehicle to be charged and the expected pick-up time; determining the target charging time based on the charging start time and the expected pick-up time, and determining the target required charging power based on the target charging time and the target charging amount to obtain the second charging power.

[0029] Preferably, the step of determining the target charging sequence based on the judgment result includes:

[0030] When the judgment result is that the overall required power does not exceed the preset power threshold, the overall required power is used as the overall charging power;

[0031] When the judgment result is that the overall required power exceeds the preset power threshold, the maximum power value in the preset power threshold is used as the overall charging power; the overall charging power is divided and rounded based on the second charging power, and the electric vehicles to be charged that meet the rounded charging power are used as target charging vehicles, and the users corresponding to the remaining electric vehicles to be charged that cannot complete the full charging are reminded to modify the expected pick-up time, and the electric vehicles to be charged within the next expected pick-up time are used as the second charging vehicles to obtain the target charging sequence.

[0032] Preferably, the step of reminding the users corresponding to the remaining electric vehicles to be charged that cannot be fully charged to modify the expected vehicle pickup time includes: counting the number of electric vehicles to be charged within the same expected vehicle pickup time based on the second electric vehicle set of the same level, obtaining a target simultaneous charging vehicle value, and recording the electric vehicles to be charged corresponding to the target number of simultaneous charging vehicles as target simultaneous charging vehicles;

[0033] Determine whether the number of target vehicles charging simultaneously exceeds the preset vehicle quantity threshold;

[0034] If it is determined that the number of target vehicles being charged simultaneously does not exceed the preset vehicle number threshold, the electric vehicles to be charged are charged in sequence according to the target charging sequence;

[0035] If it is determined that the target number of simultaneously charged vehicles exceeds the preset vehicle number threshold, the number of to-be-charged electric vehicles exceeding the threshold is calculated based on the target number of simultaneously charged vehicles and the preset vehicle number threshold to obtain the excess number; a reminder is sent to the user corresponding to the target simultaneously charged vehicle to modify the expected vehicle pickup time and a new expected vehicle pickup time is recommended to the user as the recommended vehicle pickup time; user feedback and user feedback time are obtained, and the user feedback includes user refusal to modify and user successful modification; based on the user feedback time sequence, the to-be-charged electric vehicles that have been successfully modified by the user are obtained to obtain the target modified vehicle, and the number of the target modified vehicles is counted until it is consistent with the excess number; the expected vehicle pickup time updated by the user corresponding to the target modified vehicle is obtained to obtain the target vehicle pickup time; the difference between the target vehicle pickup time and the recommended vehicle pickup time is calculated to obtain the modification time difference; the difference between the target vehicle pickup time and the expected vehicle pickup time is calculated to obtain the actual impact time difference; a priority index is determined based on the modification time difference and the actual impact time difference, the target modified vehicle is prioritized for the next time based on the priority index, and the target modified vehicle is charged according to the priority ranking.

[0036] Preferably, the step of charging the electric vehicle to be charged through the shared charging pile based on the scheduling result includes:

[0037] Obtaining relevant information about shared charging piles, where the relevant information includes the number and location of shared charging piles, and each shared charging pile corresponds to a unique identifier;

[0038] The parking area is divided into regions based on the locations of the shared charging piles to obtain target charging areas, each of which corresponds to at least one shared charging pile;

[0039] Obtaining electric vehicles to be charged in a target charging area, dividing the number of electric vehicles to be charged based on the number of shared charging piles in the target charging area, and matching the electric vehicles to be charged with corresponding shared charging piles based on unique identifiers to obtain target shared charging piles;

[0040] Based on the scheduling result, the electric vehicle to be charged is matched with the target shared charging pile in the corresponding target charging area, and the electric vehicle to be charged is charged based on the target shared charging pile.

[0041] A scheduling system for intelligent charging of new energy electric vehicles, applied to any of the scheduling methods for intelligent charging of new energy electric vehicles as described above, comprising:

[0042] A first data acquisition module is used to obtain an expected pick-up time of the electric vehicle to be charged, and determine an expected parking time of the electric vehicle to be charged based on the expected pick-up time and the current time;

[0043] Preliminarily sorting the electric vehicles to be charged based on the expected pick-up time to obtain a first charging sequence;

[0044] A second data acquisition module is used to determine the expected parking time of the electric vehicle to be charged according to the expected pick-up time and the current time, and to filter out the electric vehicles to be charged with the same expected parking time based on the first charging sequence to obtain a first set of electric vehicles of the same level;

[0045] Obtaining target charging amounts of each to-be-charged electric vehicle in a first electric vehicle set of the same level, and sorting the first electric vehicles of the same level in ascending order based on the target charging amounts to obtain a second charging sequence;

[0046] A charging sequence determination module, configured to extract electric vehicles to be charged with the same target charging amount based on the first set of electric vehicles of the same level, to obtain a second set of electric vehicles of the same level;

[0047] Acquiring a charging power of the electric vehicle to be charged to obtain a first charging power;

[0048] determining a target charging sequence based on the first charging sequence, the second charging sequence, and the first charging power;

[0049] Determine a target charging power based on the target charging time and the expected parking time, wherein the target charging power is the first charging power or the second charging power;

[0050] The charging module is used to schedule the electric vehicles to be charged based on the target charging sequence and the target charging power to obtain a scheduling result; and to charge the electric vehicles to be charged based on the scheduling result.

[0051] Compared with the prior art, the present invention has the following beneficial effects:

[0052] 1. Determine the charging power of the electric vehicle to be charged according to the expected pick-up time, expected parking time and target charging amount of the electric vehicle to be charged, adjust the charging power according to the pick-up time, and adjust the number of electric vehicles to be charged at the same time according to the available power. Schedule the charging of the electric vehicle to be charged according to the pick-up time, charging power and the number of electric vehicles to be charged, maintain the stability of the charging voltage, reduce the impact of too many charging vehicles on electricity consumption, and improve the utilization efficiency of charging time;

[0053] 2. Through the relationship between the target charging time and the expected parking time, the charging of the electric vehicles to be charged is scheduled, and the users of the electric vehicles to be charged who cannot complete the charging in time are reminded and the charging data is modified, thereby reducing unnecessary troubles caused to users due to the failure to charge in time. BRIEF DESCRIPTION OF THE DRAWINGS

[0054] In order to more clearly illustrate the technical solutions of the embodiments of the present invention, the drawings required for describing the embodiments are briefly introduced below. Obviously, the drawings described below are only some embodiments of the present invention. For ordinary technicians in this field, other drawings can be obtained based on these drawings without creative work.

[0055] Figure 1 It is a schematic diagram of the method flow of the present invention;

[0056] Figure 2 It is a system structure block diagram of the present invention.

[0057] In the accompanying drawings, the components represented by the reference numerals are listed as follows:

[0058] 1. First data acquisition module; 2. Second data acquisition module; 3. Charging sequence determination module; 4. Charging module. DETAILED DESCRIPTION

[0059] The following will be combined with the drawings in the embodiments of the present invention to clearly and completely describe the technical solutions in the embodiments of the present invention. Obviously, the described embodiments are only part of the embodiments of the present invention, not all of the embodiments. Based on the embodiments of the present invention, all other embodiments obtained by ordinary technicians in this field without creative work are within the scope of protection of the present invention.

[0060] Example 1

[0061] See also Figure 1 to Figure 2 The present invention provides a scheduling method and system technical solution for intelligent charging of new energy electric vehicles: A scheduling method for intelligent charging of new energy electric vehicles, comprising the following steps:

[0062] S1: Obtaining an expected pick-up time for the electric vehicle to be charged, and determining an expected parking time for the electric vehicle to be charged based on the expected pick-up time and the current time;

[0063] Preliminarily sorting the electric vehicles to be charged based on the expected pick-up time to obtain a first charging sequence;

[0064] S2: determining the expected parking time of the electric vehicle to be charged according to the expected pick-up time and the current time, and filtering out the electric vehicles to be charged with the same expected parking time based on the first charging sequence to obtain a first set of electric vehicles of the same level;

[0065] Obtaining target charging amounts of each to-be-charged electric vehicle in a first electric vehicle set of the same level, and sorting the first electric vehicles of the same level in ascending order based on the target charging amounts to obtain a second charging sequence;

[0066] S3: extracting electric vehicles to be charged with the same target charging amount based on the first set of electric vehicles of the same level to obtain a second set of electric vehicles of the same level;

[0067] Acquiring a charging power of the electric vehicle to be charged to obtain a first charging power;

[0068] determining a target charging sequence based on the first charging sequence, the second charging sequence, and the first charging power;

[0069] Determine a target charging power based on the target charging time and the expected parking time, wherein the target charging power is the first charging power or the second charging power;

[0070] S4: Dispatching the electric vehicles to be charged based on the target charging sequence and the target charging power to obtain a dispatch result;

[0071] S5: charging the electric vehicle to be charged through the shared charging pile based on the scheduling result;

[0072] It should be noted that sorting the electric vehicles to be charged based on the expected pick-up time means that the later the pick-up time is, the further back the electric vehicles to be charged are placed, and the earlier the pick-up time is, the further forward the electric vehicles to be charged are placed; for example, if the charging queue starts at 11 a.m., and the pick-up time of one electric vehicle is set at 3 p.m., and the pick-up time of another electric vehicle is set at 6 p.m., then the charging priority of the electric vehicle with the expected pick-up time at 3 p.m. is higher than the charging priority of the electric vehicle with the expected pick-up time at 6 p.m.; the target charging amount is determined according to the current battery power and the total battery power, and the total power is the maximum power that the battery of the electric vehicle to be charged can store;

[0073] Preset the target battery power. For example, if the current power of an electric vehicle to be charged is 30%, and its battery capacity is 30 kWh, and it is ready to be charged to 50%, then the target charging amount required is 20% of the battery capacity, that is, 6 kW is required. Users can preset the target battery power according to their needs, and determine the target charging amount based on the target battery power and battery capacity, so as to better determine the charging time required for the electric vehicle.

[0074] The step of determining the target charging power based on the target charging time and the expected parking time, wherein the charging power is the first charging power or the second charging power, comprises:

[0075] determining a target charging time based on the first charging power and the target charging amount;

[0076] Compare the target charging time with the expected parking time to determine whether the expected parking time is consistent with the target charging time;

[0077] If it is determined that the expected parking time is consistent with the target charging time, the first charging power is used as the target charging power;

[0078] If it is determined that the expected parking time is inconsistent with the target charging time, the second charging power is used as the target charging power;

[0079] The step of determining a target charging sequence based on the first charging sequence, the second charging sequence, and the first charging power includes:

[0080] Acquire electric vehicles to be charged within the same expected vehicle pickup time based on the first charging sequence, acquire target charging amounts corresponding to the electric vehicles to be charged within the same expected vehicle pickup time based on the second charging sequence; determine a second charging power for the electric vehicles to be charged based on the expected parking time and the target charging amount; and count the number of electric vehicles to be charged within the same expected vehicle pickup time;

[0081] When the target charging time is equal to the expected parking time, the second charging sequence is directly used as the target charging sequence;

[0082] When the target charging time is less than the expected parking time, the electric vehicle to be charged within the expected pickup time is taken as the target charging vehicle, and it is determined whether the number of electric vehicles to be charged within the same expected pickup time is greater than 1. If it is less than or equal to 1, the electric vehicle to be charged within the next expected pickup time is taken as the second charging vehicle to obtain the target charging sequence; if it is greater than 1, the other electric vehicles to be charged within the same expected pickup time are taken as the second charging vehicle to obtain the target charging sequence;

[0083] When the target charging time is greater than the expected parking time, the overall power demand within the same expected vehicle pickup time is obtained to determine whether the overall power demand exceeds the preset power threshold. If not, the overall power demand is used as the overall charging power; if exceeded, the maximum power value in the preset power threshold is used as the overall charging power; the overall charging power is divided and rounded based on the second charging power, and the electric vehicle to be charged that meets the rounded charging power is used as the target charging vehicle, and the users corresponding to the remaining electric vehicles to be charged that cannot complete the full charging are reminded to modify the expected vehicle pickup time, and the electric vehicle to be charged within the next expected vehicle pickup time is used as the second charging vehicle to obtain the target charging sequence;

[0084] It should be noted that the meaning of rounding is that when the total power is 3 kilowatts, the charging power of one electric vehicle is 1, and the charging power of the other electric vehicle is 1.3. After being divided between the two electric vehicles, 0.7 is left. At this time, the charging power of the other electric vehicle is 0.8. This situation means that only two electric vehicles can be charged. The third vehicle is not within the rounding range. The result of rounding is 2 electric vehicles to be charged; the second charging power refers to the charging power after adjusting the first charging power when the target charging time is inconsistent with the expected parking time;

[0085] Specifically, when the target charging time is less than the expected parking time, assuming that the target charging time required to charge to the target charging amount under normal power is 2 hours, and the expected parking time is 3 hours, then the charging power can be reduced, and the number of vehicles within the same expected pickup time is counted, and the charging power is distributed to other electric vehicles within the same expected pickup time. If there is only one electric vehicle, the excess charging power is used to charge the next batch of electric vehicles within the expected pickup time to obtain the target charging sequence;

[0086] When the target charging time is greater than the expected parking time, assuming that the target charging time to reach the target charging amount under normal power is 3 hours and the expected parking time is 2 hours, the charging power can be increased at this time, and the number of vehicles within the same expected time can be counted, and the charging power of the overall charging pile can be judged to meet the number of electric vehicles that can be fully charged at the same time, and a modification reminder is issued to the users of the remaining electric vehicles that cannot be fully charged, and the reservation charging data is recommended, and the remaining scattered charging power is used to charge the next batch of electric vehicles with the expected pick-up time, and the target charging sequence is obtained;

[0087] Determine the number of electric vehicles that can be fully charged at the same time with the charging power of the overall charging pile, and send modification reminders to the users of the remaining electric vehicles that cannot be fully charged and recommend appointment charging data. At the same time, the remaining scattered charging power is used to charge the electric vehicles of the next batch expected to pick up the car at the time. If there is enough time, the charging power is distributed, and if there is not enough time, the charging power is distributed.

[0088] During the vehicle pickup time, the power is adjusted so that the target charging amount can be completed just in time for the vehicle pickup, and the excess power can be used to charge another electric vehicle; assuming that during A's vehicle pickup time, A's target charging time is sufficient, and A is the electric vehicle with the earliest vehicle pickup time, and E's situation is the same as A, but C's vehicle pickup time is longer, then A and C can be charged at the same time, and the user of E is reminded to modify the scheduled charging first, because the remaining charging power is not enough to meet E's usage, but C can be charged in advance, so that when CD is charging at the same time, C is charged in advance, and the extra charging power can speed up the charging of D, thereby completing the charging of other subsequent vehicles in advance and improving the charging efficiency.

[0089] On one hand, high power is used to charge vehicles with short pick-up time, and on the other hand, low power is used to charge vehicles with long pick-up time. If there is surplus power, charging is started in sequence according to different pick-up times. The time when the first batch of vehicles is fully charged is predicted. The pick-up time of the second batch of vehicles is used as the charging time for the second batch of vehicles. It is judged whether the target charging time is sufficient. If it is sufficient, normal power is used for charging. If it is not sufficient, the power is adjusted for charging. The remaining power is used to charge the third batch of vehicles, and so on. The charging is carried out in sequence; the vehicles with sufficient time are matched with those with insufficient time. For example, if the time of A is insufficient and the time of D is sufficient, A and D can be charged at the same time, with less power given to D and more power given to A. For vehicles with short pick-up time, fast charging is used, and the surplus power is distributed to vehicles with long pick-up time for slow charging. According to the number of vehicles charged at the same time, the charging scheduling is completed in conjunction with the pick-up time, which can improve the charging efficiency and enable more vehicles to complete charging at the pick-up time.

[0090] The step of determining the second charging power of the electric vehicle to be charged based on the expected parking time, the target charging amount and the charging start time includes: obtaining the charging start time of the electric vehicle to be charged; obtaining the target charging amount of the electric vehicle to be charged and the expected vehicle pick-up time; determining the target charging time based on the charging start time and the expected vehicle pick-up time, determining the target required charging power based on the target charging time and the target charging amount, and obtaining the second charging power;

[0091] Specifically, assuming that the charging start time is 1 p.m., the expected pick-up time is 5 p.m., and the target charging amount is 2 kilowatts, the charging power at this time is 0.5 kilowatts per hour. If the first charging power is kilowatts per hour, the first charging power needs to be reduced, and the reduced first charging power is used as the second charging power of the electric vehicle to be charged.

[0092] The step of reminding users corresponding to the remaining electric vehicles to be charged that cannot be fully charged to modify the expected vehicle pickup time includes: counting the number of electric vehicles to be charged within the same expected vehicle pickup time based on the second electric vehicle set of the same level, obtaining a target simultaneous charging vehicle value, and recording the electric vehicles to be charged corresponding to the target simultaneous charging vehicle number as target simultaneous charging vehicles;

[0093] Determine whether the number of target vehicles charging simultaneously exceeds the preset vehicle quantity threshold;

[0094] If it is determined that the number of target vehicles being charged simultaneously does not exceed the preset vehicle number threshold, the electric vehicles to be charged are charged in sequence according to the target charging sequence;

[0095] If it is determined that the target number of simultaneously charged vehicles exceeds the preset vehicle number threshold, the number of to-be-charged electric vehicles exceeding the threshold is calculated based on the target number of simultaneously charged vehicles and the preset vehicle number threshold to obtain the excess number; a reminder is sent to the user corresponding to the target simultaneously charged vehicle to modify the expected vehicle pickup time and a new expected vehicle pickup time is recommended to the user as the recommended vehicle pickup time; user feedback and user feedback time are obtained, and the user feedback includes user refusal to modify and user successful modification; based on the user feedback time sequence, the to-be-charged electric vehicles that have been successfully modified by the user are obtained to obtain the target modified vehicle, and the number of the target modified vehicles is counted until it is consistent with the excess number; the expected vehicle pickup time updated by the user corresponding to the target modified vehicle is obtained to obtain the target vehicle pickup time; the difference between the target vehicle pickup time and the recommended vehicle pickup time is calculated to obtain the modification time difference; the difference between the target vehicle pickup time and the expected vehicle pickup time is calculated to obtain the actual impact time difference; a priority index is determined based on the modification time difference and the actual impact time difference, the target modified vehicle is prioritized for the next time based on the priority index, and the target modified vehicle is charged according to the priority ranking;

[0096] Specifically, assuming that there are 5 target vehicles charging at the same time, and the preset vehicle number threshold is 3, there will be 2 extra electric vehicles that cannot be charged at this time, then a reminder to modify the scheduled charging data is sent to the users of the 5 electric vehicles, and recommended scheduled charging data is provided, and the first two users who give feedback and agree to modify are obtained, and the corresponding numbers of the electric vehicles that meet the number are determined, and they are charged; and the modified data of the first two users who give feedback are obtained, and the difference between the modified data and the recommended data is calculated, and the modified data is arranged in descending order according to the modified difference. The arrangement order is used as the priority of the next charging, and the priority index of the next charging is determined in combination with the data difference. For example, the pick-up time of the first car is 3 o'clock, and the recommended time is 5 o'clock in the afternoon. The user changes it to 4 o'clock in the afternoon; the pick-up time of the second car is 3 o'clock, and the recommended time is 5 o'clock. The user changes it to 6 o'clock in the afternoon, which means that the priority of the second car is greater than the first car at the next charging; and the actual impact time difference of the first car is calculated to be 1 hour, and the actual impact time difference of the second car is three hours. According to the actual impact time difference and the modification time difference, based on the association function Calculate the priority index, where Ts represents the actual impact time difference and Tx represents the modification time difference, and sort the electric vehicles in descending order according to the priority index as the priority for the next charging;

[0097] It should be noted that the first charging power refers to the charging power most suitable for the electric vehicle to be charged, and the most suitable refers to the charging power that protects the battery life and improves the charging efficiency; the preset vehicle quantity threshold refers to the number of electric vehicles that can be charged normally at the same time by the pre-set charging pile within the target charging amount and the time period;

[0098] The modification time difference means that when the expected pick-up time is 3 pm, the user is recommended to modify the expected pick-up time to 6 pm, and the expected pick-up time actually modified by the user is 5 pm, which is used as the first modified target charging data. At this time, the closeness of the two data is the difference of minus 1 hour. When the user actually modifies the expected pick-up time to 5:30 pm, which is used as the second modified target charging data, the closeness of the two data is minus 0.5 hours. It can be seen that the modification difference between the first modified target charging data and the recommended scheduled charging data is smaller than the modification difference between the second modified target charging data and the recommended scheduled charging data. Therefore, the priority of the next charging of the electric vehicle corresponding to the second modified target charging data is greater than that of the electric vehicle corresponding to the first modified target charging data.

[0099] Specifically, assume that there are five electric vehicles A, B, C, D, and E in the charging sequence, among which A, B, and E have the same pick-up time, and the target charging amount of A and E is the same. The pick-up time of C and D is longer than that of A, B, and E. At this time, A and E need to be charged at the same time to obtain the number of charging piles that can be charged at the same time. If the available power of the charging pile at this time can only charge one vehicle normally, determine whether the pick-up time is greater than the target charging time. If it is greater, the charging power of the two electric vehicles will be lowered and they will be charged at the same time. If it is less than, send a message to the user to remind the user to modify the scheduled charging data. According to the feedback time, determine who to charge first. If the user of A gives feedback first, E will be charged first. If the user of E gives feedback first, A will be charged first. According to the scheduled charging data, give the user a certain priority for the next charging.

[0100] By determining the charging power of the electric vehicle to be charged according to the expected pick-up time, expected parking time and target charging amount of the electric vehicle to be charged, adjusting the charging power according to the pick-up time, and adjusting the number of electric vehicles to be charged at the same time according to the available power, and scheduling the charging of the electric vehicle to be charged according to the pick-up time, the charging power and the number of electric vehicles to be charged, the stability of the charging voltage is maintained, the impact of too many charging vehicles on electricity consumption is reduced, and the utilization efficiency of the charging time is improved;

[0101] Through the relationship between the target charging time and the expected parking time, the charging of the electric vehicles to be charged is scheduled, and the users of the electric vehicles to be charged who cannot complete the charging in time are reminded and the charging data is modified, thereby reducing unnecessary troubles caused to users due to the failure to charge in time.

[0102] The steps of charging the electric vehicle to be charged through the shared charging pile based on the scheduling result include:

[0103] Obtaining relevant information about shared charging piles, where the relevant information includes the number and location of shared charging piles, and each shared charging pile corresponds to a unique identifier;

[0104] The parking area is divided into regions based on the locations of the shared charging piles to obtain target charging areas, each of which corresponds to at least one shared charging pile;

[0105] Obtaining electric vehicles to be charged in a target charging area, dividing the number of electric vehicles to be charged based on the number of shared charging piles in the target charging area, and matching the electric vehicles to be charged with corresponding shared charging piles based on unique identifiers to obtain target shared charging piles;

[0106] Based on the scheduling result, the electric vehicle to be charged is matched with the target shared charging pile in the corresponding target charging area, and the electric vehicle to be charged is charged based on the target shared charging pile.

[0107] A scheduling system for intelligent charging of new energy electric vehicles, applied to any of the scheduling methods for intelligent charging of new energy electric vehicles as described above, comprising:

[0108] A first data acquisition module is used to obtain an expected pick-up time of the electric vehicle to be charged, and determine an expected parking time of the electric vehicle to be charged based on the expected pick-up time and the current time;

[0109] Preliminarily sorting the electric vehicles to be charged based on the expected pick-up time to obtain a first charging sequence;

[0110] A second data acquisition module is used to determine the expected parking time of the electric vehicle to be charged according to the expected pick-up time and the current time, and to filter out the electric vehicles to be charged with the same expected parking time based on the first charging sequence to obtain a first set of electric vehicles of the same level;

[0111] Obtaining target charging amounts of each to-be-charged electric vehicle in a first electric vehicle set of the same level, and sorting the first electric vehicles of the same level in ascending order based on the target charging amounts to obtain a second charging sequence;

[0112] A charging sequence determination module, configured to extract electric vehicles to be charged with the same target charging amount based on the first set of electric vehicles of the same level, to obtain a second set of electric vehicles of the same level;

[0113] Acquiring a charging power of the electric vehicle to be charged to obtain a first charging power;

[0114] determining a target charging sequence based on the first charging sequence, the second charging sequence, and the first charging power;

[0115] Determine a target charging power based on the target charging time and the expected parking time, wherein the target charging power is the first charging power or the second charging power;

[0116] The charging module is used to schedule the electric vehicles to be charged based on the target charging sequence and the target charging power to obtain a scheduling result; and to charge the electric vehicles to be charged based on the scheduling result.

[0117] In actual use, each household has an independent charging pile for charging electric vehicles. During the peak period of electricity consumption at night, it is easy to cause voltage instability. The present invention can schedule the electric vehicles that need to be charged according to the charging time by using shared charging piles, and maintain the stability of electricity consumption at night without affecting the charging of electric vehicles. Suppose in a certain community, each household originally had an independent charging pile, and there were 100 residents in total. If a shared charging pile is built, one can be shared by every 5 households, then there will be 20 shared charging piles in this community, and there is no need to build a charging pile for each household separately. In the case of shared charging piles, 80% of the charging pile construction can be reduced; in the case of 100 households, each resident's charging pile needs to be connected to the bus line in the community, while the shared charging pile can be connected in a centralized manner, reducing a lot of repeated wiring costs. In addition, shared charging piles can also save the investment in charging pile equipment required by each user.

[0118] The present invention determines the expected parking time of the user's electric vehicle according to the pick-up time of the user's electric vehicle and the current time, judges whether it is necessary to adjust the charging parameters according to the expected parking time and the target charging amount, judges the relationship between the time required for normal power charging (the time period from the expected time formulated according to the charging sequence to the pick-up time) and the expected parking time, and if it is greater than, it needs to be adjusted, and if it is less than, it does not need to be adjusted, and the electric vehicle is charged according to the adjusted power and charging sequence; if the expected parking time is not enough, several vehicles with the same target charging amount are judged to be able to be charged at the same time, and it is judged whether the expected parking time is sufficient in the case of simultaneous charging. If it is sufficient, it is directly charged, if not, a modification suggestion is sent to the user, and a modification discount and a scheduled time are given. The charging time selected by the user is closer to the scheduled time, the greater the discount. Under the same charging time, different charging quantities correspond to different charging powers. Under the same charging power, if the charging time is sufficient, it corresponds to different charging times. According to the target charging amount, the power is determined. For example, if the target charging amount is low, two vehicles can be charged at the same time with low power. If the target charging amount is large, one vehicle needs to be charged with high power at the same time, so as to maintain the stability of the overall voltage.

[0119] According to the overall charging power and the power demand of the electric vehicles to be charged, it is determined that several vehicles can be charged together, and the total power remains unchanged. When a vehicle has a high power demand, the charging power of other vehicles is automatically reduced. When the parking time of the vehicles is similar, the charging power of the same level is adjusted to meet the maximum charging power of the target vehicle. It is determined whether other electric vehicles can still be charged. If the time to pick up the vehicle is long, the charging power given is low; if the time to pick up the vehicle is short, the power given is high. The charging of each electric vehicle is optimized and scheduled to stagger the peak charging period, reduce the impact of too many charging vehicles on electricity consumption, and improve the utilization efficiency of charging time.

[0120] In the description of this specification, the description with reference to the terms "one embodiment", "example", "specific example", etc. means that the specific features, structures, materials or characteristics described in conjunction with the embodiment or example are included in at least one embodiment or example of the present invention. In this specification, the schematic representation of the above terms does not necessarily refer to the same embodiment or example. Moreover, the specific features, structures, materials or characteristics described can be combined in any one or more embodiments or examples in a suitable manner.

[0121] Although embodiments of the present invention have been shown and described, it will be appreciated by those skilled in the art that various changes, modifications, substitutions and variations may be made to the embodiments without departing from the principles and spirit of the present invention, and that the scope of the present invention is defined by the appended claims and their equivalents.

Claims

1. A scheduling method for intelligent charging of new energy electric vehicles, characterized in that: The following steps are involved: S1: Obtaining an expected pick-up time for the electric vehicle to be charged, and determining an expected parking time for the electric vehicle to be charged based on the expected pick-up time and the current time; Preliminarily sorting the electric vehicles to be charged based on the expected pick-up time to obtain a first charging sequence; S2: determining the expected parking time of the electric vehicle to be charged according to the expected pick-up time and the current time, and filtering out the electric vehicles to be charged with the same expected parking time based on the first charging sequence to obtain a first set of electric vehicles of the same level; Obtaining target charging amounts of each to-be-charged electric vehicle in a first electric vehicle set of the same level, and sorting the first electric vehicles of the same level in ascending order based on the target charging amounts to obtain a second charging sequence; S3: extracting electric vehicles to be charged with the same target charging amount based on the first set of electric vehicles of the same level to obtain a second set of electric vehicles of the same level; Acquiring a charging power of the electric vehicle to be charged to obtain a first charging power; determining a target charging sequence based on the first charging sequence, the second charging sequence, and the first charging power; Determine a target charging power based on the target charging time and the expected parking time, wherein the target charging power is the first charging power or the second charging power; S4: Dispatching the electric vehicles to be charged based on the target charging sequence and the target charging power to obtain a dispatch result; S5: Based on the scheduling result, the electric vehicles to be charged are charged through the shared charging piles.

2. The method for scheduling intelligent charging of new energy electric vehicles according to claim 1, characterized in that: The step of determining the target charging power based on the target charging time and the expected parking time, wherein the charging power is the first charging power or the second charging power, comprises: determining a target charging time based on the first charging power and the target charging amount; Compare the target charging time with the expected parking time to determine whether the expected parking time is consistent with the target charging time; If it is determined that the expected parking time is consistent with the target charging time, the first charging power is used as the target charging power; If it is determined that the expected parking time is inconsistent with the target charging time, the second charging power is used as the target charging power.

3. The method for scheduling intelligent charging of new energy electric vehicles according to claim 1, characterized in that: The step of determining a target charging sequence based on the first charging sequence, the second charging sequence and the first charging power comprises: Acquire electric vehicles to be charged within the same expected vehicle pickup time based on the first charging sequence, acquire target charging amounts corresponding to the electric vehicles to be charged within the same expected vehicle pickup time based on the second charging sequence; determine a second charging power for the electric vehicles to be charged based on the expected parking time and the target charging amount; and count the number of electric vehicles to be charged within the same expected vehicle pickup time; When the target charging time is equal to the expected parking time, the second charging sequence is directly used as the target charging sequence; When the target charging time is less than the expected parking time, the electric vehicle to be charged within the expected pickup time is taken as the target charging vehicle, and it is determined whether the number of electric vehicles to be charged within the same expected pickup time is greater than 1. If it is less than or equal to 1, the electric vehicle to be charged within the next expected pickup time is taken as the second charging vehicle to obtain the target charging sequence; if it is greater than 1, the other electric vehicles to be charged within the same expected pickup time are taken as the second charging vehicle to obtain the target charging sequence; When the target charging time is greater than the expected parking time, the overall required power within the same expected car pick-up time is obtained, and it is determined whether the overall required power exceeds the preset power threshold, and a judgment result is obtained. The target charging sequence is determined based on the judgment result, and the judgment result is that the overall required power exceeds the preset power threshold or the overall required power does not exceed the preset power threshold.

4. The method for scheduling intelligent charging of new energy electric vehicles according to claim 3 is characterized in that: The step of determining the second charging power of the electric vehicle to be charged based on the expected parking time, the target charging amount and the charging start time includes: obtaining the charging start time of the electric vehicle to be charged; obtaining the target charging amount of the electric vehicle to be charged and the expected pick-up time; determining the target charging time based on the charging start time and the expected pick-up time, and determining the target required charging power based on the target charging time and the target charging amount to obtain the second charging power.

5. The method for scheduling intelligent charging of new energy electric vehicles according to claim 3 is characterized in that: The step of determining the target charging sequence based on the judgment result comprises: When the judgment result is that the overall required power does not exceed the preset power threshold, the overall required power is used as the overall charging power; When the judgment result is that the overall required power exceeds the preset power threshold, the maximum power value in the preset power threshold is used as the overall charging power; the overall charging power is divided and rounded based on the second charging power, and the electric vehicles to be charged that meet the rounded charging power are used as target charging vehicles, and the users corresponding to the remaining electric vehicles to be charged that cannot complete the full charging are reminded to modify the expected pick-up time, and the electric vehicles to be charged within the next expected pick-up time are used as the second charging vehicles to obtain the target charging sequence.

6. The method for scheduling intelligent charging of new energy electric vehicles according to claim 5 is characterized in that: The step of reminding the users corresponding to the remaining electric vehicles to be charged that cannot be fully charged to modify the expected vehicle pickup time includes: counting the number of electric vehicles to be charged within the same expected vehicle pickup time based on the second electric vehicle set of the same level, obtaining a target simultaneous charging vehicle value, and recording the electric vehicles to be charged corresponding to the target simultaneous charging vehicle number as target simultaneous charging vehicles; Determine whether the number of target vehicles charging simultaneously exceeds the preset vehicle quantity threshold; If it is determined that the number of target vehicles being charged simultaneously does not exceed the preset vehicle number threshold, the electric vehicles to be charged are charged in sequence according to the target charging sequence; If it is determined that the target number of simultaneously charged vehicles exceeds the preset vehicle number threshold, the number of to-be-charged electric vehicles exceeding the threshold is calculated based on the target number of simultaneously charged vehicles and the preset vehicle number threshold to obtain the excess number; a reminder is sent to the user corresponding to the target simultaneously charged vehicle to modify the expected vehicle pickup time and a new expected vehicle pickup time is recommended to the user as the recommended vehicle pickup time; user feedback and user feedback time are obtained, and the user feedback includes user refusal to modify and user successful modification; based on the user feedback time sequence, the to-be-charged electric vehicles that have been successfully modified by the user are obtained to obtain the target modified vehicle, and the number of the target modified vehicles is counted until it is consistent with the excess number; the expected vehicle pickup time updated by the user corresponding to the target modified vehicle is obtained to obtain the target vehicle pickup time; the difference between the target vehicle pickup time and the recommended vehicle pickup time is calculated to obtain the modification time difference; the difference between the target vehicle pickup time and the expected vehicle pickup time is calculated to obtain the actual impact time difference; a priority index is determined based on the modification time difference and the actual impact time difference, the target modified vehicle is prioritized for the next time based on the priority index, and the target modified vehicle is charged according to the priority ranking.

7. The method for scheduling intelligent charging of new energy electric vehicles according to claim 1, characterized in that: The steps of charging the electric vehicle to be charged through the shared charging pile based on the scheduling result include: Obtaining relevant information about shared charging piles, where the relevant information includes the number and location of shared charging piles, and each shared charging pile corresponds to a unique identifier; The parking area is divided into regions based on the locations of the shared charging piles to obtain target charging areas, each of which corresponds to at least one shared charging pile; Obtaining electric vehicles to be charged in a target charging area, dividing the number of electric vehicles to be charged based on the number of shared charging piles in the target charging area, and matching the electric vehicles to be charged with corresponding shared charging piles based on unique identifiers to obtain target shared charging piles; Based on the scheduling result, the electric vehicle to be charged is matched with the target shared charging pile in the corresponding target charging area, and the electric vehicle to be charged is charged based on the target shared charging pile.

8. A scheduling system for intelligent charging of new energy electric vehicles, applied to the scheduling method for intelligent charging of new energy electric vehicles as claimed in any one of claims 1 to 7, characterized in that: include: A first data acquisition module is used to obtain an expected pick-up time of the electric vehicle to be charged, and determine an expected parking time of the electric vehicle to be charged based on the expected pick-up time and the current time; Preliminarily sorting the electric vehicles to be charged based on the expected pick-up time to obtain a first charging sequence; A second data acquisition module is used to determine the expected parking time of the electric vehicle to be charged according to the expected pick-up time and the current time, and to filter out the electric vehicles to be charged with the same expected parking time based on the first charging sequence to obtain a first set of electric vehicles of the same level; Obtaining target charging amounts of each to-be-charged electric vehicle in a first electric vehicle set of the same level, and sorting the first electric vehicles of the same level in ascending order based on the target charging amounts to obtain a second charging sequence; A charging sequence determination module, configured to extract electric vehicles to be charged with the same target charging amount based on the first set of electric vehicles of the same level, to obtain a second set of electric vehicles of the same level; Acquiring a charging power of the electric vehicle to be charged to obtain a first charging power; determining a target charging sequence based on the first charging sequence, the second charging sequence, and the first charging power; Determine a target charging power based on the target charging time and the expected parking time, wherein the target charging power is the first charging power or the second charging power; A charging module, used to schedule the electric vehicles to be charged based on the target charging sequence and the target charging power, and obtain a scheduling result; The electric vehicles to be charged are charged based on the scheduling results.

Citation Information

Patent Citations

  • Scheduling method and system for automatic charging piles of electric vehicles

    CN112297930A

  • Electric vehicle charging pile control system capable of performing peak shifting charging

    CN115366728A