Train coupling de-compiling working diagram generation method, system and equipment and storage medium
By automatically generating train joint hanging uncompilation operation diagrams, the problems of high labor costs and low efficiency in the existing technology are solved, and automated operation diagram drawing is realized, and efficiency is improved.
Patent Information
- Application Number
- CN202411111704.6
- Authority / Receiving Office
- CN · China
- Patent Type
- Applications(China)
- Current Assignee / Owner
- Filing Date
- 2024-08-14
- Publication Date
- 2024-11-12
AI Technical Summary
The existing technology lacks the function of automatically generating the train joint unwrapping and unwrapping operation line, resulting in high labor costs and low efficiency.
By determining the train operation parameters and joint or uncompilation information within the target time period, the joint uncompilation operation diagram is automatically generated, including acquisition modules and generation modules, and the automatic drawing is achieved using processors and memory.
It reduces labor costs, improves the efficiency of drawing of train joint hanging and uncompilation operation diagrams, and realizes automatic generation.
Smart Images

Figure CN118928504A_ABST
Abstract
Description
Background Art
[0002] The train operation diagram is a technical document used to show the operation of trains in railway sections and the arrival, departure or passing times at stations. It stipulates the procedures for each train to occupy the section, the arrival and departure (or passing) times of trains at each station, the operation time of trains in the section and the stop time. It is the basis for organizing train operations on the entire railway. The operation diagram is a graphic illustration of the time and space relationship of train operation, and is a two-dimensional line diagram.
[0003] At present, each signal system manufacturer has its own operation diagram compilation system, and the operation diagram compilation has become relatively mature. Some manufacturers have been able to compile the main line coupling and uncoupling operation diagram. However, there is currently a lack of the function of automatically generating the operation line for coupling and uncoupling trains.
[0004] Therefore, it is urgent to provide a technical solution to solve the above problems. Summary of the invention
[0005] In order to solve the above technical problems, the present invention provides a method, system, device and storage medium for generating a train coupling and disassembly operation diagram.
[0006] In a first aspect, the present invention provides a method for generating a train coupling and disassembly diagram, and the technical solution of the method is as follows:
[0007] Determine the train operation parameters of each section within the target time period, as well as the coupling information and / or decoupling information corresponding to each section;
[0008] According to the train operation parameters of each section within the target time period, and the coupling information and / or decoupling information corresponding to each section, a coupling and decoupling operation diagram for the target time period is drawn and generated.
[0009] The beneficial effects of the train coupling and uncoupling operation diagram generation method of the present invention are as follows:
[0010] The method of the present invention can automatically generate drawing parameters of a train coupling and disassembly plan, thereby automatically generating a train coupling and disassembly operation diagram, reducing labor costs and improving the efficiency of drawing the train coupling and disassembly operation diagram.
[0011] On the basis of the above scheme, the train coupling and disassembly operation diagram generation method of the present invention can also be improved as follows.
[0012] In an optional manner, the train operation parameters of any segment include: the number of trains, the running interval, the segment start and end time points, the segment identification and the segment preset route;
[0013] When the segment identifier of any of the segments is a pre-coupling identifier or a post-coupling identifier, the coupling information corresponding to the segment includes: the coupling point position and the coupling start and end time points; when the segment identifier of any of the segments is a pre-decoupling identifier or a post-decoupling identifier, the decoupling information corresponding to the segment includes: the decoupling point position and the decoupling start and end time points.
[0014] In an optional manner, the step of determining the train operation parameters of the first segment within the target time period, and the coupling information or decoupling information corresponding to the first segment, includes:
[0015] Setting a segment identification, a preset segment duration and a preset segment route for each segment, and setting the segment start and end time points of the first segment, as well as the number of trains and / or the running interval;
[0016] When only the number of trains is set for the first segment, the train interval of the first segment is calculated based on the number of trains in the first segment and the length of the route cycle in the preset route of the segment; or, when only the train interval is set for the first segment, the number of trains in the first segment is calculated based on the train interval of the first segment and the length of the route cycle in the preset route of the segment.
[0017] In an optional manner, the step of determining the train operation parameters of the first segment within the target time period, and the coupling information or decoupling information corresponding to the first segment, further includes:
[0018] When the segment identifier of the first segment is the pre-coupling identifier, determine whether the number of trains in the first segment is an even number. If not, correct the number of trains in the first segment to obtain and determine the corrected number of trains and the corrected train interval as the number of trains and the train interval of the first segment.
[0019] In an optional manner, the step of determining the train operation parameters of any segment other than the first segment within the target time period, and the coupling information or decoupling information corresponding to the segment, includes:
[0020] Determine the number of trains in the segment according to the number of trains in the previous segment of any segment other than the first segment and the segment identifier of the segment;
[0021] If the previous segment of any segment other than the first segment is coupled or uncoupled, the time point of the first coupling or uncoupling of the previous segment of the segment is determined as the starting time point of the segment, and the end time point of the segment is determined according to the starting time point of the segment and the preset segment duration, and the segment start and end time points of the segment are obtained;
[0022] The train interval of any segment other than the first segment is calculated according to the number of trains in the segment and the length of the route cycle in the preset route of the segment.
[0023] In a second aspect, the present invention provides a train coupling and disassembly operation diagram generation system, the technical solution of the system is as follows:
[0024] Includes: acquisition module and generation module;
[0025] The acquisition module is used to: determine the train operation parameters of each segment within the target time period, and the coupling information and / or decoupling information corresponding to each segment;
[0026] The generating module is used to draw and generate a coupling and uncoupling operation diagram for the target time period according to the train operation parameters of each section within the target time period, and the coupling information and / or uncoupling information corresponding to each section.
[0027] The beneficial effects of the train coupling and disassembly operation diagram generation system of the present invention are as follows:
[0028] The system of the present invention can automatically generate drawing parameters of a train coupling and disassembly plan, thereby automatically generating a train coupling and disassembly operation diagram, reducing labor costs and improving the efficiency of drawing the train coupling and disassembly operation diagram.
[0029] On the basis of the above scheme, the train coupling and disassembly operation diagram generation system of the present invention can also be improved as follows.
[0030] In an optional manner, the train operation parameters of any segment include: the number of trains, the running interval, the segment start and end time points, the segment identification and the segment preset route;
[0031] When the segment identifier of any of the segments is a pre-coupling identifier or a post-coupling identifier, the coupling information corresponding to the segment includes: the coupling point position and the coupling start and end time points; when the segment identifier of any of the segments is a pre-decoupling identifier or a post-decoupling identifier, the decoupling information corresponding to the segment includes: the decoupling point position and the decoupling start and end time points.
[0032] In an optional manner, the acquisition module is specifically used to:
[0033] Setting a segment identification, a preset segment duration and a preset segment route for each segment, and setting the segment start and end time points of the first segment, as well as the number of trains and / or the running interval;
[0034] When only the number of trains is set for the first segment, the train interval of the first segment is calculated based on the number of trains in the first segment and the length of the route cycle in the preset route of the segment; or, when only the train interval is set for the first segment, the number of trains in the first segment is calculated based on the train interval of the first segment and the length of the route cycle in the preset route of the segment.
[0035] In a third aspect, a technical solution of an electronic device of the present invention is as follows:
[0036] It includes a memory, a processor, and a program stored in the memory and running on the processor. When the processor executes the program, the steps of the train coupling and disassembly operation diagram generation method of the present invention are implemented.
[0037] In a fourth aspect, the present invention provides a computer-readable storage medium having the following technical solution:
[0038] Instructions are stored in the computer-readable storage medium. When the computer-readable storage medium reads the instructions, the computer-readable storage medium executes the steps of the train coupling and disassembly operation diagram generation method of the present invention.
[0039] The above description is only an overview of the technical solution of the present invention. In order to more clearly understand the technical means of the present invention, it can be implemented according to the contents of the specification. In order to make the above and other purposes, features and advantages of the present invention more obvious and easy to understand, the specific implementation methods of the present invention are listed below. BRIEF DESCRIPTION OF THE DRAWINGS
[0040] The accompanying drawings are only used to illustrate the embodiments and are not to be considered as limiting the present invention. In addition, the same reference symbols are used to represent the same components throughout the accompanying drawings. In the accompanying drawings:
[0041] Figure 1 A schematic flow chart of an embodiment of a method for generating a train coupling and uncoupling operation diagram of the present invention;
[0042] Figure 2 It is a schematic diagram of the coupling and uncoupling operation diagram;
[0043] Figure 3 It is a structural schematic diagram of an embodiment of a train coupling and disassembly operation diagram generation system of the present invention;
[0044] Figure 4 The figure is a schematic structural diagram of an embodiment of an electronic device of the present invention. DETAILED DESCRIPTION
[0045] Exemplary embodiments of the present invention will be described in more detail below with reference to the accompanying drawings. Although exemplary embodiments of the present invention are shown in the drawings, it should be understood that the present invention can be implemented in various forms and should not be limited to the embodiments set forth herein.
[0046] Figure 1A flow chart of an embodiment of a method for generating a train coupling and disassembly diagram provided by the present invention is shown. The method for generating a train coupling and disassembly diagram can be executed by an electronic device such as a terminal device or a server. The terminal device can be any fixed or mobile terminal such as a user equipment (UE), a mobile device, a user terminal, a terminal, a cellular phone, a cordless phone, a personal digital assistant (PDA), a handheld device, a computing device, a vehicle-mounted device, a wearable device, etc. The server can be a single server or a server cluster composed of multiple servers. Any electronic device can implement the method for generating a train coupling and disassembly diagram by means of a processor calling computer-readable instructions stored in a memory. Figure 1 As shown, the following steps are included:
[0047] S1. Determine the train operation parameters of each segment within the target time period, as well as the coupling information and / or decoupling information corresponding to each segment.
[0048] The target time period is set according to actual needs, such as 5:00-8:00, and there is no limit here. There are multiple segments within the target time period, which are divided by coupling points or decoupling points. Train operation parameters include but are not limited to: number of trains, driving intervals, segment start and end time points, segment identification and segment preset routes. Segment identification includes: before coupling, before decoupling, after coupling, after decoupling and none. A segment identification can contain multiple, such as after decoupling and before coupling.
[0049] Among them, when the segment identifier of any segment is a pre-coupling identifier or a post-coupling identifier, the coupling information corresponding to the segment includes: the coupling point position and the coupling start and end time points; when the segment identifier of any segment is a pre-decoupling identifier or a post-decoupling identifier, the decoupling information corresponding to the segment includes: the decoupling point position and the decoupling start and end time points.
[0050] In S1, specifically:
[0051] 1) The step of determining the train operation parameters of the first segment within the target time period and the coupling information or decoupling information corresponding to the first segment comprises:
[0052] The segment identification, preset segment duration and segment preset route of each segment are set, and the segment start and end time points of the first segment, as well as the number of trains and / or the running interval are set.
[0053] The segmented preset routes include but are not limited to: route cycle duration, number of route cycles and return duration.
[0054] When the first segment is only set with the number of trains, the train interval of the first segment is calculated according to the number of trains in the first segment and the length of the route cycle in the segment preset route. Or, when the first segment is only set with the train interval, the train number of the first segment is calculated according to the train interval of the first segment and the length of the route cycle in the segment preset route.
[0055] According to the formula TrainTime = t x / TrainNum calculates the train interval; TrainNum is the number of trains, t x is the duration of the route cycle of the xth segment, and TrainTime is the driving interval. According to the formula TrainNum = t x / TrainTime calculates the number of trains.
[0056] 2) The step of determining the train operation parameters of the first segment within the target time period, and the coupling information or decoupling information corresponding to the first segment, further includes:
[0057] When the segment identifier of the first segment is the pre-coupling identifier, determine whether the number of trains in the first segment is an even number; if not, correct the number of trains in the first segment to obtain the corrected number of trains and the corrected train interval as the number of trains and the train interval in the first segment.
[0058] When the number of trains in the first segment is an odd number, the number of trains is corrected by subtracting one from the number of trains to obtain the corrected number of trains, and the formula TrainTime = t x / TrainNum gets the corrected train interval.
[0059] 3) The step of determining the train operation parameters of any segment other than the first segment within the target time period, and the coupling information or decoupling information corresponding to the segment, comprises:
[0060] The number of trains in any segment other than the first segment is determined according to the number of trains in the previous segment and the segment identifier of the segment.
[0061] Among them, if the segment mark is a post-disassembly mark, the number of trains in this segment is twice the number of trains in the previous segment of this segment; if the segment mark is a post-coupling mark, the number of trains in this segment is half the number of trains in the previous segment of this segment.
[0062] If the previous segment of any segment other than the first segment is coupled or decoupled, the time point of the first coupling or decoupling of the previous segment of the segment is determined as the starting time point of the segment, and based on the starting time point of the segment and the preset segment duration, the end time point of the segment is determined and the segment start and end time points of the segment are obtained.
[0063] The train interval of any segment other than the first segment is calculated according to the number of trains in the segment and the length of the route cycle in the preset route of the segment.
[0064] S2. Draw and generate a coupling and uncoupling operation diagram for the target time period according to the train operation parameters of each segment within the target time period, and the coupling and uncoupling information and / or uncoupling information corresponding to each segment.
[0065] Among them, the QT drawing framework is used to realize the display and drawing of the coupling and uncoupling operation diagram. Specifically, according to the number of trains TrainNum, the train interval TrainTime, the coupling and uncoupling point location, and the coupling and uncoupling start and end time points of each segment in the target time period, the coupling and uncoupling operation diagram of the target time period is drawn according to the logic of drawing the coupling and uncoupling points from front to back.
[0066] like Figure 2 As shown in the figure, the target time period is 5:00-7:41, with 2 sections. The number of trains in the first section is 4. The first section is: 5:00-6:20, and the other section is: 6:00-7:41. The starting point of the coupling and uncoupling point of the first section is 6:00. After setting the input, the system will automatically calculate the train data of each section. Use QT to draw the framework. Figure 2 Draw as shown, and set the connection and release relationship.
[0067] The technical solution of this embodiment can automatically generate the drawing parameters of the train coupling and disassembly plan, thereby automatically generating the train coupling and disassembly operation diagram, reducing labor costs and improving the efficiency of drawing the train coupling and disassembly operation diagram.
[0068] Figure 3 FIG. 2 is a schematic diagram showing a structure of an embodiment of a train coupling and disassembly operation diagram generation system 200 provided by the present invention. Figure 3 As shown, the system 200 includes: an acquisition module 210 and a generation module 220;
[0069] The acquisition module 210 is used to: determine the train operation parameters of each segment within the target time period, and the coupling information and / or decoupling information corresponding to each segment;
[0070] The generating module 220 is used to draw and generate a coupling and uncoupling operation diagram for the target time period according to the train operation parameters of each segment within the target time period, and the coupling information and / or uncoupling information corresponding to each segment.
[0071] In an optional manner, the train operation parameters of any segment include: the number of trains, the running interval, the segment start and end time points, the segment identification and the segment preset route;
[0072] When the segment identifier of any of the segments is a pre-coupling identifier or a post-coupling identifier, the coupling information corresponding to the segment includes: the coupling point position and the coupling start and end time points; when the segment identifier of any of the segments is a pre-decoupling identifier or a post-decoupling identifier, the decoupling information corresponding to the segment includes: the decoupling point position and the decoupling start and end time points.
[0073] In an optional manner, the acquisition module is specifically used to:
[0074] Setting a segment identification, a preset segment duration and a preset segment route for each segment, and setting the segment start and end time points of the first segment, as well as the number of trains and / or the running interval;
[0075] When only the number of trains is set for the first segment, the train interval of the first segment is calculated based on the number of trains in the first segment and the length of the route cycle in the preset route of the segment; or, when only the train interval is set for the first segment, the number of trains in the first segment is calculated based on the train interval of the first segment and the length of the route cycle in the preset route of the segment.
[0076] In an optional manner, the acquisition module is further configured to:
[0077] When the segment identifier of the first segment is the pre-coupling identifier, determine whether the number of trains in the first segment is an even number. If not, correct the number of trains in the first segment to obtain and determine the corrected number of trains and the corrected train interval as the number of trains and the train interval of the first segment.
[0078] In an optional manner, the acquisition module is further configured to:
[0079] Determine the number of trains in the segment according to the number of trains in the previous segment of any segment other than the first segment and the segment identifier of the segment;
[0080] If the previous segment of any segment other than the first segment is coupled or uncoupled, the time point of the first coupling or uncoupling of the previous segment of the segment is determined as the starting time point of the segment, and the end time point of the segment is determined according to the starting time point of the segment and the preset segment duration, and the segment start and end time points of the segment are obtained;
[0081] The train interval of any segment other than the first segment is calculated according to the number of trains in the segment and the length of the route cycle in the preset route of the segment.
[0082] The technical solution of this embodiment can automatically generate the drawing parameters of the train coupling and disassembly plan, thereby automatically generating the train coupling and disassembly operation diagram, reducing labor costs and improving the efficiency of drawing the train coupling and disassembly operation diagram.
[0083] The above-mentioned parameters and steps for each module to implement corresponding functions in the train coupling and disassembly operation diagram generation system 200 of this embodiment can refer to the parameters and steps in the embodiment of the train coupling and disassembly operation diagram generation method mentioned above, and will not be repeated here.
[0084] like Figure 4 As shown, an electronic device 300 according to an embodiment of the present invention includes a processor 320, the processor 320 is coupled to a memory 310, and the memory 310 stores at least one computer program 330, and the at least one computer program 330 is loaded and executed by the processor 320, so that the electronic device 300 implements any of the above-mentioned train coupling and decoupling operation diagram generation methods, specifically:
[0085] The electronic device 300 may have relatively large differences due to different configurations or performances, and may include one or more processors 320 (Central Processing Units, CPU) and one or more memories 310, wherein the one or more memories 310 store at least one computer program 330, and the at least one computer program 330 is loaded and executed by the one or more processors 320, so that the electronic device 300 implements any of the train coupling and disassembly operation diagram generation methods provided in the above embodiments. Of course, the electronic device 300 may also have components such as a wired or wireless network interface, a keyboard, and an input and output interface for input and output, and the electronic device 300 may also include other components for realizing device functions, which will not be repeated here.
[0086] A computer-readable storage medium according to an embodiment of the present invention stores at least one computer program, and the at least one computer program is loaded and executed by a processor so that the computer implements any of the above-mentioned train coupling and disassembly operation diagram generation methods.
[0087] Optionally, the computer-readable storage medium may be a read-only memory (ROM), a random access memory (RAM), a compact disc (CD-ROM), a magnetic tape, a floppy disk, an optical data storage device, and the like.
[0088] In an exemplary embodiment, a computer program product or a computer program is also provided, the computer program product or the computer program comprising computer instructions, the computer instructions being stored in a computer-readable storage medium. A processor of an electronic device reads the computer instructions from the computer-readable storage medium, and the processor executes the computer instructions, so that the electronic device executes any of the above-mentioned train coupling and disassembly operation diagram generation methods.
[0089] It should be noted that the terms "first", "second", etc. in the specification and claims of the present application are used to distinguish similar objects and represent the definition of a specific order or sequence. The order of use of similar objects can be interchanged where appropriate, so that the embodiments of the present application described herein can be implemented in an order other than the order shown or described.
[0090] Those skilled in the art know that the present invention can be implemented as a system, method or computer program product. Therefore, the present disclosure can be specifically implemented in the following forms, namely: it can be complete hardware, it can be complete software (including firmware, resident software, microcode, etc.), or it can be a combination of hardware and software, which is generally referred to as "circuit", "module" or "system" herein. In addition, in some embodiments, the present invention can also be implemented in the form of a computer program product in one or more computer-readable media, and the computer-readable medium contains computer-readable program code.
[0091] Any combination of one or more computer-readable media can be used. Computer-readable media can be computer-readable signal media or computer-readable storage media. Computer-readable storage media can be, for example, but not limited to, electrical, magnetic, optical, electromagnetic, infrared, or semiconductor systems, devices or devices, or any combination of the above. More specific examples of computer-readable storage media (a non-exhaustive list) include: an electrical connection with one or more wires, a portable computer disk, a hard disk, a random access memory (RAM), a read-only memory (ROM), an erasable programmable read-only memory (EPROM or flash memory), an optical fiber, a portable compact disk read-only memory (CD-ROM), an optical storage device, a magnetic storage device, or any suitable combination of the above. In the present application, a computer-readable storage medium can be any tangible medium containing or storing a program, which can be used by an instruction execution system, device or device or used in combination with it.
[0092] Although the embodiments of the present invention have been shown and described above, it is to be understood that the above embodiments are exemplary and are not to be construed as limitations of the present invention. A person skilled in the art may change, modify, replace and vary the above embodiments within the scope of the present invention.
Claims
1. A method for generating a train coupling and uncoupling operation diagram, characterized in that: include: Determine the train operation parameters of each section within the target time period, as well as the coupling information and / or decoupling information corresponding to each section; According to the train operation parameters of each section within the target time period, and the coupling information and / or decoupling information corresponding to each section, a coupling and decoupling operation diagram for the target time period is drawn and generated.
2. The train coupling and disassembly operation diagram generation method according to claim 1, characterized in that: The train operation parameters of any section include: number of trains, running interval, section start and end time points, section identification and section preset route; When the segment identifier of any of the segments is a pre-coupling identifier or a post-coupling identifier, the coupling information corresponding to the segment includes: the coupling point position and the coupling start and end time points; when the segment identifier of any of the segments is a pre-decoupling identifier or a post-decoupling identifier, the decoupling information corresponding to the segment includes: the decoupling point position and the decoupling start and end time points.
3. The train coupling and disassembly operation diagram generation method according to claim 2, characterized in that: The step of determining the train operation parameters of the first segment within the target time period, and the coupling information or decoupling information corresponding to the first segment, comprises: Setting a segment identification, a preset segment duration and a preset segment route for each segment, and setting the segment start and end time points of the first segment, as well as the number of trains and / or the running interval; When only the number of trains is set for the first segment, the train interval of the first segment is calculated based on the number of trains in the first segment and the length of the route cycle in the preset route of the segment; or, when only the train interval is set for the first segment, the number of trains in the first segment is calculated based on the train interval of the first segment and the length of the route cycle in the preset route of the segment.
4. The train coupling and disassembly operation diagram generation method according to claim 3 is characterized in that: The step of determining the train operation parameters of the first segment within the target time period, and the coupling information or decoupling information corresponding to the first segment, further includes: When the segment identifier of the first segment is the pre-coupling identifier, determine whether the number of trains in the first segment is an even number. If not, correct the number of trains in the first segment to obtain and determine the corrected number of trains and the corrected train interval as the number of trains and the train interval of the first segment.
5. The train coupling and disassembly diagram generation method according to claim 3 or 4, characterized in that: The step of determining the train operation parameters of any segment other than the first segment within the target time period, and the coupling information or uncoupling information corresponding to the segment, comprises: Determine the number of trains in the segment according to the number of trains in the previous segment of any segment other than the first segment and the segment identifier of the segment; If the previous segment of any segment other than the first segment is coupled or uncoupled, the time point of the first coupling or uncoupling of the previous segment of the segment is determined as the starting time point of the segment, and the end time point of the segment is determined according to the starting time point of the segment and the preset segment duration, and the segment start and end time points of the segment are obtained; The train interval of any segment other than the first segment is calculated according to the number of trains in the segment and the length of the route cycle in the preset route of the segment.
6. A train coupling and uncoupling operation diagram generation system, characterized in that: include: Get modules and generate modules; The acquisition module is used to: determine the train operation parameters of each segment within the target time period, and the coupling information and / or decoupling information corresponding to each segment; The generating module is used to draw and generate a coupling and uncoupling operation diagram for the target time period according to the train operation parameters of each section within the target time period, and the coupling information and / or uncoupling information corresponding to each section.
7. The train coupling and disassembly operation diagram generation system according to claim 6, characterized in that: The train operation parameters of any section include: number of trains, running interval, section start and end time points, section identification and section preset route; When the segment identifier of any of the segments is a pre-coupling identifier or a post-coupling identifier, the coupling information corresponding to the segment includes: the coupling point position and the coupling start and end time points; when the segment identifier of any of the segments is a pre-decoupling identifier or a post-decoupling identifier, the decoupling information corresponding to the segment includes: the decoupling point position and the decoupling start and end time points.
8. The train coupling and disassembly operation diagram generation system according to claim 7, characterized in that: The acquisition module is specifically used for: Setting a segment identification, a preset segment duration and a preset segment route for each segment, and setting the segment start and end time points of the first segment, as well as the number of trains and / or the running interval; When only the number of trains is set for the first segment, the train interval of the first segment is calculated based on the number of trains in the first segment and the length of the route cycle in the preset route of the segment; or, when only the train interval is set for the first segment, the number of trains in the first segment is calculated based on the train interval of the first segment and the length of the route cycle in the preset route of the segment.
9. An electronic device, characterized in that: The electronic device includes a processor, the processor is coupled to a memory, at least one computer program is stored in the memory, and the at least one computer program is loaded and executed by the processor so that the electronic device implements the train coupling and disassembly operation diagram generation method as described in any one of claims 1 to 5.
10. A computer-readable storage medium, characterized in that: At least one computer program is stored in the computer-readable storage medium, and the at least one computer program is loaded and executed by the processor so that the computer-readable storage medium implements the train coupling and disassembly operation diagram generation method as described in any one of claims 1 to 5.