By adopting a simulation platform and a margin-free closing process in the module structure of the ship pipeline, the problem of mismatch in the installation positioning of the module unit and the difficulty in controlling the accuracy is solved, and an efficient and accurate installation process is achieved, reducing costs and time and improving the product quality.
Patent Information
- Application Number
- CN202411205686.8
- Authority / Receiving Office
- CN · China
- Patent Type
- Applications(China)
- Current Assignee / Owner
- Filing Date
- 2024-08-30
- Publication Date
- 2024-11-12
AI Technical Summary
The existing ship pipeline module structure has problems such as modular units not without margin closing, large material cost and installation working hours, mismatch between modules, and difficult to control the docking accuracy of the cabin parts.
The design corresponding to the simulation platform and the hull bottom platform is adopted, and pre-simulated connection is carried out through the simulation cabin to ensure the precise docking of the module unit, and the use of the margin-free closing process in the module unit to reduce cutting and adjustment steps, improve installation efficiency and accuracy .
It improves the installation accuracy and efficiency of module units, reduces labor intensity and material consumption, shortens the ship cycle, and improves the quality and production efficiency of the final product.
Smart Images

Figure CN118928631A_ABST
Abstract
Description
Technical Field
[0001] The present invention relates to the technical field of ship piping modules, and in particular to a ship piping module structure and an installation method. Background Art
[0002] The ship piping module refers to the general term for the pipes, valves, accessories and equipment used to transport various liquids, gases, solid particles and other media on board. It is usually composed of basic components such as pipes, pipe fittings, valves, pumps, joints, etc. The main function of this module is to ensure that the ship can safely and reliably transport various media under various sea conditions and working conditions to meet the normal operation of ship power, auxiliary machinery, living facilities and other systems. When designing a ship piping module, it is necessary to meet the safety and reliability requirements of ship operation to ensure that the transportation, control and discharge of fluids are normal and reliable. On the premise of meeting safety and reliability, the design should minimize material and energy consumption and improve the operating efficiency of the ship. The design of the pipeline should take into account the convenience of maintenance and repair, so that maintenance personnel can easily inspect and maintain the pipeline system. However, in the existing ship piping module structure, the modular units cannot be closed without any margin, and the material cost and installation time are high. Moreover, the modules are assembled independently, and the installation positioning between the modules is not matched. At the same time, there is no simulation of the through-tank parts, and the docking accuracy with the pre-installed through-tank parts after on-site lifting is difficult to control. Summary of the invention
[0003] In order to solve the above technical problems, the technical solution of the present invention is as follows: An embodiment of the present invention provides a ship piping module structure and an installation method, including: Ship hull; characterized in that it also includes: A simulation platform, corresponding to the bottom platform of the ship hull, to facilitate welding of simulated pipeline through-tank parts; A first module unit is arranged on the simulation platform and is a module unit connected into one by complete pipeline parts; The first unit part is arranged on the simulation platform, connected to the first module unit through the first unit closing seam, and consists of two module units; The second unit part is arranged on the simulation platform, connected to the first unit part through the second unit closing seam, and is composed of two module units; The simulated cabin passage piece is arranged on the simulation platform to perform a pre-simulated connection; the simulated cabin passage piece includes: A first simulated cabin passage piece, one end of which is connected to the simulated platform, and the other end of which is connected to the unit pipeline flange, and the first simulated cabin passage piece is L-shaped; A second simulated cabin passage piece, one end of which is connected to the simulated platform, and the other end of which is connected to the unit pipeline flange, and the second simulated cabin passage piece is I-shaped; The third simulated cabin passage piece has one end connected to the simulated platform and the other end connected to the unit pipeline sleeve, and the third simulated cabin passage piece is I-shaped.
[0004] Furthermore, the first module unit includes: A first support plate, disposed on the top of the simulation platform; A flower steel plate, arranged on the first supporting plate; A cable flat iron is arranged under the flower steel plate; The first pipeline is arranged on and under the flower plate; Equipment, both ends of which are connected to the first pipeline; A valve member, both ends of which are connected to the first pipeline; The accessory has two ends connected to the first pipeline (106).
[0005] Furthermore, the first unit part includes: A second module unit is disposed on the simulation platform, and one end of the second module unit is connected to one end of the first module unit through a closure seam of the first unit; The third module unit is arranged on the simulation platform, and one end of the third module unit is connected to the other end of the first module unit through the closing seam of the first unit, and is located on a side of the ship hull away from the second module unit.
[0006] Furthermore, the second unit part includes: A fourth module unit is disposed on the simulation platform, and one end of the fourth module unit is connected to one end of the second module unit through a closure seam of the second unit; The fifth module unit is arranged on the simulation platform, and one end of the fifth module unit is connected to one end of the third module unit through the closing seam of the second unit, and is located on a side of the ship hull away from the third module unit.
[0007] Furthermore, the second unit closing seam includes: One end is the connecting pipe of the third module unit, and is connected to the connecting pipe of the fifth module unit at the other end without any margin; Wherein, the first unit closing seam and the second unit closing seam have the same structure and are provided with the connecting pipe.
[0008] Furthermore, the third module unit includes: A third support plate, disposed on the simulation platform; A third pipeline is arranged on the third supporting plate; The third pipe bracket is arranged on the third support plate and is provided in a plurality of groups to limit the position of the third pipeline.
[0009] Furthermore, the fifth module unit includes: a fifth support plate, disposed on the simulation platform; a fifth pipeline, disposed on the fifth supporting plate and connected to the third pipeline; The fifth pipe bracket is arranged on the fifth supporting plate and is provided in a plurality of groups to limit the position of the fifth pipeline.
[0010] A method for installing a ship piping module structure according to any one of claims 1 to 7, characterized in that the installation method comprises the following steps: S1, prefabricated pipeline; S2. Make a bottom segment simulation platform and set pipeline simulation cabin parts on the simulation platform; S3, assembling the module unit on the simulation platform, connecting the unit pipeline with the simulation cabin parts, and temporarily fixing it on the simulation platform; S4, assembling the module units one by one to realize multi-unit simulation pre-grouping; S5. After all the materials in the module unit are installed, check the dimensions and report them for inspection. Acceptance is done after confirmation. S6. Remove the connecting bolts along the connecting pipes between the module units, and at the same time remove the connecting bolts between the module units and the simulated cabin parts on the simulation platform, and move the module units out of the simulation platform in sequence; S7, the module unit is transported to the section, hoisted, docked with the through-cabin component arranged on the bottom platform of the ship hull, and locked; S8. Lift the regional module units in sequence to complete the reset and assembly of the module units on board.
[0011] Furthermore, the simulation platform is composed of one steel plate or a plurality of steel plates, and a simulation cabin passage is arranged on the simulation platform.
[0012] The above solution of the present invention includes at least the following beneficial effects: The present invention provides a simulation platform corresponding to the bottom platform of the ship hull, arranges the simulated cabin through-piece on the simulation platform, and pre-installs the simulated cabin through-piece with the pipelines on the module unit, thereby determining the position of the simulated cabin through-piece corresponding to the same module unit on the simulation platform, so that the cabin through-piece arranged on the bottom platform of the ship hull and distributed at the same position as the simulation platform are accurately connected with the pipelines on the module unit, thereby achieving better docking accuracy and higher connection efficiency with the pre-installed cabin through-piece during on-site lifting through the simulation of the cabin through-piece.
[0013] By using no-residue closing when connecting the pipes in the first module unit, the second module unit, the third module unit, the fourth module unit and the fifth module unit, through precise calculation and control, the module unit pipelines almost do not need additional cutting and adjustment when closing, thereby improving construction efficiency and accuracy. Among them, the use of the no-residue closing process method reduces the lifting time and the workload of the slipway assembly, thereby reducing labor intensity, improving production efficiency and the utilization rate of the slipway large crane. Secondly, since the steps of residual cutting and secondary closing positioning adjustment are reduced, the slipway cycle can be shortened and the enterprise efficiency can be improved. In addition, no-residue closing also helps to improve the quality of the final product because it reduces the errors caused by multiple adjustments and cutting. BRIEF DESCRIPTION OF THE DRAWINGS
[0014] Figure 1 is a stereoscopic diagram of the ship piping module structure of the present invention; Figure 2 is a stereoscopic view of the first module unit of the ship piping module structure of the present invention; Figure 3 It is a stereoscopic diagram of the ship piping module structure simulation platform of the present invention; Figure 4 This is an enlarged view of point B of the ship piping module structure of the present invention; Figure 5 It is a structural schematic diagram of the first unit of the ship piping module structure of the present invention; Figure 6 This is an enlarged view of point A of the ship piping module structure of the present invention; Figure 7 It is an installation connection diagram of the first module unit of the ship pipeline module structure of the present invention.
[0015] Description of reference numerals: 1. First module unit; 101. First support plate; 102. Flower steel plate; 103. Cable flat iron; 104. Valve; 105. Equipment; 106. First pipeline; 107. Accessories; 2. Second module unit; 3. Third module unit; 301. Third support plate; 302. Third pipe bracket; 303. Third pipeline; 4. Fourth module unit; 5. Fifth module unit; 501. Fifth support plate; 502. Fifth pipe bracket; 503. Fifth pipeline; 6. Ship hull; 601. First unit closing seam; 602. Second unit closing seam; 603. Bottom platform; 7. Simulation platform; 701. First simulated through-cabin component; 702. Second simulated through-cabin component; 703. Third simulated through-cabin component. DETAILED DESCRIPTION
[0016] The exemplary embodiments of the present invention will be described in more detail below with reference to the accompanying drawings. Although the exemplary embodiments of the present invention are shown in the accompanying drawings, it should be understood that the present invention can be implemented in various forms and should not be limited by the embodiments set forth herein. On the contrary, these embodiments are provided in order to enable a more thorough understanding of the present invention and to enable the scope of the present invention to be fully communicated to those skilled in the art.
[0017] like Figures 1 to 7 As shown, an embodiment of the present invention provides a ship pipeline module structure, including: a ship hull 6; also including: a simulation platform 7, corresponding to the bottom platform 603 of the ship hull 6, to facilitate the welding of pipeline simulation through-tank parts; a first module unit 1, arranged on the simulation platform 7, and connected into an integrated module unit by complete pipeline parts; a first unit part, arranged on the simulation platform 7, connected to the first module unit 1 through a first unit closing seam 601, and composed of two module units; a second unit part, arranged on the simulation platform 7, connected to the first unit part through a second unit closing seam 602, and composed of two module units; a simulated through-tank part, arranged On the simulation platform 7, a pre-simulation connection is performed; the simulation cabin passage parts include: a first simulation cabin passage part 701, one end of which is connected to the simulation platform 7, and the other end is connected to the unit pipeline flange, and the first simulation cabin passage part 701 is L-shaped; a second simulation cabin passage part 702, one end of which is connected to the simulation platform 7, and the other end is connected to the unit pipeline flange, and the second simulation cabin passage part 702 is I-shaped; a third simulation cabin passage part 703, one end of which is connected to the simulation platform 7, and the other end is connected to the unit pipeline sleeve, and the third simulation cabin passage part 703 is I-shaped.
[0018] In an embodiment of the present invention, a simulation platform 7 is provided to correspond to the bottom platform 603 of the ship hull 6, and a simulated through-tank component is provided on the simulation platform 7, so that the simulated through-tank component and the pipeline on the module unit are pre-installed, thereby determining the position of the simulated through-tank component corresponding to the same module unit on the simulation platform 7, so that the through-tank component distributed at the same position as the simulation platform 7 on the bottom platform 603 of the ship hull 6 is accurately connected with the pipeline on the module unit, thereby through the simulation of the through-tank component, the docking accuracy with the pre-installed through-tank component is better and the connection efficiency is higher during on-site lifting.
[0019] Among them, the simulation platform 7 does not contact the ship hull 6, but the bottom surface of the simulation platform 7 and the ship hull 6 are the same. The simulation platform 7 is arranged in the installation workshop to facilitate the installation of pipelines; the pre-installed pipeline interface below is preferably facing upward; if facing the side, the same direction should be considered to facilitate the unit lifting and docking with the through-cabin parts; thus, a first simulated through-cabin part 701 placed in an L shape and a second simulated through-cabin part 702 placed in an I shape are arranged to facilitate the connection of module units.
[0020] like Figures 1 to 7 As shown, the first module unit 1 includes: a first support plate 101, arranged at the top of the simulation platform 7; a flower plate 102, arranged on the first support plate 101; a cable flat iron 103, arranged under the flower plate 102; a first pipeline 106, arranged on or under the flower plate 102; a device 105, both ends of which are connected to the first pipeline 106; a valve 104, both ends of which are connected to the first pipeline 106; and an accessory 107, both ends of which are connected to the first pipeline (106).
[0021] In the embodiment of the present invention, the first pipeline 106, the support plate, the equipment 105, the equipment frame, the outfitting platform, the valve 104, the accessories 107 and the cable flat iron 103 form a complete module unit; wherein, no additional closing pipe is required in the two module units, and the two module units are directly connected without any margin through the connecting pipes provided in the module units, so as to reduce the material and design costs; if it is a flange connection, it is aligned in a line; if it is a sleeve connection, the sleeve is not welded, and a gap of 40 mm is left between the unit pipes. The sleeve is installed after the unit is closed to achieve a seamless closing.
[0022] Meanwhile, the first unit part and the second unit part also contain parts such as pipelines, brackets, equipment 105, equipment 105 mounts, outfitting platforms, valve accessories 107 and cable flat irons 103; and the size of the module unit depends on the lifting capacity of the crane, the width of the workshop door, and the size of the transport vehicle.
[0023] like Figures 1 to 7 As shown, the first unit part includes: a second module unit 2, which is arranged on the simulation platform 7, and one end of which is connected to one end of the first module unit 1 through the first unit closing seam 601; a third module unit 3, which is arranged on the simulation platform 7, and one end of which is connected to the other end of the first module unit 1 through the first unit closing seam 601, and is located on the side of the ship hull 6 away from the second module unit 2.
[0024] like Figures 1 to 7 As shown, the second unit part includes: a fourth module unit 4, which is arranged on the simulation platform 7, and one end of which is connected to one end of the second module unit 2 through the second unit closing seam 602; a fifth module unit 5, which is arranged on the simulation platform 7, and one end of which is connected to one end of the third module unit 3 through the second unit closing seam 602, and is located on the side of the ship hull 6 away from the third module unit 3.
[0025] In the embodiment of the present invention, the second module unit 2, the third module unit 3, the fourth module unit 4 and the fifth module unit 5 are respectively arranged at the four corners of the ship hull 6, and the corresponding module units are connected together through the first unit closing seam 601 and the second unit closing seam 602, so as to ensure the integrity of the hull pipeline. Among them, the first module unit 1, the second module unit 2, the third module unit 3, the fourth module unit 4 and the fifth module unit 5 are all connected by non-residue closing when connecting the pipelines therein. Through precise calculation and control, the module unit pipelines almost do not need additional cutting and adjustment when closing, thereby improving the construction efficiency and accuracy. Among them, the use of the non-residue closing process method reduces the hoisting time and the workload of the slipway assembly, thereby reducing the labor intensity, improving the production efficiency and the utilization rate of the slipway crane. Secondly, since the steps of excess cutting and secondary closing positioning adjustment are reduced, the slipway cycle can be shortened and the enterprise efficiency can be improved. In addition, the non-residue closing also helps to improve the quality of the final product because it reduces the errors caused by multiple adjustments and cutting.
[0026] like Figures 1 to 7 As shown, the second unit closing seam 602 includes: one end is the connecting pipe of the third module unit 3, and the other end is connected to the connecting pipe of the fifth module unit 5 without any remainder; wherein, the first unit closing seam 601 and the second unit closing seam 602 have the same structure and are provided with the connecting pipe.
[0027] In the embodiment of the present invention, no additional closing pipe is required when the third module unit 3 and the fifth module unit 5 are connected.
[0028] like Figures 1 to 7 As shown, the third module unit 3 includes: a third support plate 301, which is arranged on the simulation platform 7; a third pipeline 303, which is arranged on the third support plate 301; a third pipe bracket 302, which is arranged on the third support plate 301 and is provided with several groups to limit the position of the third pipeline 303.
[0029] like Figures 1 to 7 As shown, the fifth module unit 5 includes: a fifth support plate 501, which is arranged on the simulation platform 7; a fifth pipeline 503, which is arranged on the fifth support plate 501 and connected to the third pipeline 303; a fifth pipe bracket 502, which is arranged on the fifth support plate 501 and is provided with several groups to limit the position of the fifth pipeline 503.
[0030] In the embodiment of the present invention, the third pipeline 303 and the fifth pipeline 503 on the third module unit 3 and the fifth module unit 5 are connected together without any remainder.
[0031] When the module unit is hoisted and docked with the through-cabin parts set on the bottom platform 603 of the ship hull 6 and locked, the basin outfitting method is used, and the equipment and pipelines densely arranged above the inner bottom plate are installed completely through the main body outfitting on the basin-shaped area segments composed of the double bottom segments and the side segments of the engine room. Basin outfitting is a key stage in the transformation of the outfitting process in the bottom area of the engine room. In the basin outfitting process, the outfitting operation avoids the upper hull operation, so that a large number of pipelines and equipment can be constructed in a better environment, effectively improving the outfitting quality of this area.
[0032] A method for installing a ship pipeline module structure comprises the following steps: S1. Prefabricated pipelines, the pipeline manufacturing accuracy must comply with CSQS (GB / T 34000-2016); S2. Make the bottom segmented simulation platform 7, which is made of one or more steel plates, level the steel plates, and install them in the workshop. Set the simulation platform 7 in the workshop for easy installation; set the simulation cabin parts on the platform, and the coordinates of the cabin parts shall be based on the three-dimensional coordinates of the model design; the simulation cabin parts can be simplified, but it is necessary to ensure that the positioning dimensions are accurate and the terminal connection method is correct; the simulation cabin parts are spot welded so that the simulation cabin parts can be replaced when the remaining units are installed; S3, assembling the module unit on the simulation platform 7, connecting the unit pipeline with the through-chamber component, and temporarily fixing it on the simulation platform 7; S4, assembling the module units one by one to realize multi-unit simulation pre-grouping; S5. After all the materials in the module unit are installed, check the dimensions and report them for inspection. Acceptance is done after confirmation. S6, remove the connecting bolts along the connection between the module units, and at the same time remove the connecting bolts between the module units and the cabin parts on the simulation platform 7, and move the module units out of the simulation platform 7 in sequence; S7, the module unit is transported to the section, hoisted, docked with the through-cabin component arranged on the bottom platform 603 of the ship hull 6, and locked; S8. Lift the regional module units in sequence to complete the reset and assembly of the module units on board.
[0033] Among them, when the regional module units are hoisted one by one, there is no closing pipe between the module units, and there is no surplus closing, which is more convenient and quick.
[0034] The above is a preferred embodiment of the present invention. It should be pointed out that for ordinary technicians in this technical field, several improvements and modifications can be made without departing from the principles of the present invention. These improvements and modifications should also be regarded as the scope of protection of the present invention.
Claims
1. A ship piping module structure, comprising: A ship hull (6); characterized in that it also comprises: A simulation platform (7) corresponding to the bottom platform (603) of the ship hull (6) to facilitate the welding of pipeline simulation cabin parts; A first module unit (1) is arranged on the simulation platform (7) and is an integrated module unit connected by complete pipeline parts; A first unit part, which is arranged on the simulation platform (7), connected to the first module unit (1) via a first unit closing seam (601), and is composed of two module units; The second unit part is arranged on the simulation platform (7), connected to the first unit part via the second unit closing seam (602), and is composed of two module units; The simulated cabin passage piece is arranged on the simulation platform (7) to perform a pre-simulated connection; the simulated cabin passage piece comprises: A first simulated cabin passage member (701), one end of which is connected to the simulated platform (7), and the other end of which is connected to the unit pipeline flange, and the first simulated cabin passage member (701) is L-shaped; A second simulated cabin passage member (702), one end of which is connected to the simulated platform (7), and the other end of which is connected to the unit pipeline flange, and the second simulated cabin passage member (702) is I-shaped; The third simulated cabin passage member (703) has one end connected to the simulated platform (7) and the other end connected to the unit pipeline sleeve, and the third simulated cabin passage member (703) is I-shaped.
2. The ship piping module structure according to claim 1 is characterized in that: The first module unit (1) comprises: A first support plate (101) is arranged on the top of the simulation platform (7); A patterned steel plate (102) is disposed on the first supporting plate (101); A cable flat iron (103) is arranged under the flower steel plate (102); A first pipeline (106) is arranged on the patterned steel plate (102) and below the patterned steel plate (102); The device (105) has two ends connected to the first pipeline (106); A valve member (104), both ends of which are connected to the first pipeline (106); The accessory (107) has two ends connected to the first pipeline (106).
3. The ship piping module structure according to claim 2 is characterized in that: The first unit part comprises: A second module unit (2) is arranged on the simulation platform (7), and one end of the second module unit (2) is connected to one end of the first module unit (1) via the first unit closing seam (601); The third module unit (3) is arranged on the simulation platform (7), and one end of the third module unit (3) is connected to the other end of the first module unit (1) via the first unit closing seam (601), and is located on a side of the ship hull (6) away from the second module unit (2).
4. The ship piping module structure according to claim 3 is characterized in that: The second unit part includes: A fourth module unit (4) is arranged on the simulation platform (7), and one end of the fourth module unit (4) is connected to one end of the second module unit (2) via the second unit closing seam (602); The fifth module unit (5) is arranged on the simulation platform (7), and one end of the fifth module unit (5) is connected to one end of the third module unit (3) via the second unit closing seam (602), and is located on a side of the ship hull (6) away from the third module unit (3).
5. The ship piping module structure according to claim 4, characterized in that: The second unit closing seam (602) comprises: A connecting pipe (303) is provided on the third module unit (3) and is connected to a connecting pipe (503) provided on the fifth module unit (5); The first unit closing seam (601) and the second unit closing seam (602) have the same structure and are butt-jointed without any margin via the connecting pipe.
6. The ship piping module structure according to claim 5, characterized in that: The third module unit (3) comprises: A third support plate (301) is arranged on the simulation platform (7); A third pipeline (303) is arranged on the third support plate (301); The third pipe bracket (302) is arranged on the third support plate (301) and is provided in a plurality of groups to limit the position of the third pipeline (303).
7. The ship piping module structure according to claim 6, characterized in that: The fifth module unit (5) comprises: a fifth support plate (501), arranged on the simulation platform (7); a fifth pipeline (503), which is disposed on the fifth support plate (501) and connected to the third pipeline (303); The fifth pipe support (502) is arranged on the fifth support plate (501) and is provided in a plurality of groups to limit the position of the fifth pipeline (503).
8. A method for installing a ship piping module structure according to any one of claims 1 to 7, characterized in that: The installation method includes the following steps: S1, prefabricated pipeline; S2, manufacturing a bottom segment simulation platform (7), and setting pipeline simulation cabin components on the simulation platform (7); S3, assembling the module unit on the simulation platform (7), connecting the unit pipeline with the simulation cabin component, and temporarily fixing it on the simulation platform (7); S4, assembling the module units one by one to realize multi-unit simulation pre-grouping; S5. After all the materials in the module unit are installed, check the dimensions and report them for inspection. Acceptance is done after confirmation. S6, remove the connecting bolts along the connecting pipes between the module units, and at the same time remove the connecting bolts between the module units and the simulated cabin parts on the simulation platform (7), and move the module units out of the simulation platform (7) in sequence; S7, the module unit is transported to the section, hoisted, docked with the through-cabin component arranged on the bottom platform (603) of the ship hull (6), and locked; S8. Lift the regional module units in sequence to complete the reset and assembly of the module units on board.
9. The method for installing a ship piping module structure according to claim 8, characterized in that: The simulation platform (7) is composed of one steel plate or a plurality of steel plates spliced together, and a simulation cabin passage member is arranged on the simulation platform (7).