Reinforcing steel bar integral manufacturing jig frame for polygonal variable cross-section inclined tower column component
Through the combined system of the middle bracket, inner cavity bracket and movable bracket, the simultaneous construction and precise adjustment of polygonal deformation cross-section tower columns is achieved, solving the problems of large consumables and low industrial efficiency of double column construction in the existing technology, and improving construction efficiency and structural stability ensure the positioning and installation accuracy of the tower columns.
Patent Information
- Application Number
- CN202411258608.4
- Authority / Receiving Office
- CN · China
- Patent Type
- Applications(China)
- Current Assignee / Owner
- Filing Date
- 2024-09-09
- Publication Date
- 2024-11-12
AI Technical Summary
In the overall production and hoisting construction of inclined tower column reinforcement parts, the consumables are large, the working efficiency is low, the construction period is long, and the single column lacks mutual support, which affects structural stability and installation accuracy.
The central bracket working platform, inner cavity bracket working platform, movable bracket working platform, plate and positioning system are adopted to achieve simultaneous construction and precise adjustment of polygonal deformed cross-section tower columns through adjustable struts and walking systems to ensure structural stability and construction. efficiency.
Improve work efficiency and construction quality, reduce material waste, enhance the overall stability and construction safety of the structure, ensure the positioning and installation accuracy of tower columns, reduce construction risks, improve the overall construction efficiency and structure quality and life.
Smart Images

Figure CN118932875A_ABST
Abstract
Description
Technical Field
[0001] The invention relates to the technical field of bridge engineering, and in particular to a tire frame used for integrally manufacturing steel bars of polygonal variable-section inclined tower column components. Background Art
[0002] With the continuous improvement of bridge construction technology, in the process of super-high bridge tower construction, the overall production and hoisting construction of tower column steel bars have become a trend in the field of bridge construction technology. The overall production and hoisting construction of tower column steel bars can transform the high-altitude steel bar binding operation to the ground operation, reduce the construction risk of high-altitude steel bar binding operation, improve construction efficiency and construction quality, and provide a safer, more efficient and high-quality construction method for bridge tower construction.
[0003] In the prior art, when constructing a cradle for an inclined tower column, single columns are used to construct them one by one. When constructing double columns, this method not only consumes a lot of materials, has low work efficiency and a long construction period, but also the single columns lack mutual support during the construction process, which may affect the overall stability of the structure and increase construction risks. The positioning and installation accuracy of the cradle are relatively difficult to control, which affects the subsequent tower column installation accuracy and overall line shape.
[0004] The object of the present invention is to provide a frame for integrally manufacturing steel bars of polygonal variable-section inclined tower column components, so as to solve the problems mentioned in the above-mentioned background technology. Summary of the invention
[0005] To achieve the above-mentioned purpose, the present invention provides a frame for integrally manufacturing steel bars of polygonal variable-section inclined tower column parts, comprising a middle support work platform, an inner cavity support work platform, a plurality of movable support work platforms, a slat, and a positioning system;
[0006] The middle support work platform is arranged at the center of the relative inclined surfaces of the two columns of the inclined tower column, and is arranged along the outer contour of the center of the inclined surface of the inclined tower column;
[0007] A plurality of movable support work platforms are arranged along the outer contour of the inclined tower column from both sides of the middle support work platform, and are surrounded by the middle support work platform to form a polygonal structure of the inclined tower column. Adjacent movable support work platforms and the joints with the middle support platform are connected by a slatted plate. Any movable support work platform can be moved by a walking system to adjust the outer cross-sectional size of the inclined tower column.
[0008] The inner cavity support work platform is arranged along the inner cavity contour of the inclined tower column, the inner cavity support work platform and the middle support work platform are both connected to a rigid frame through adjustable struts, the vertical main reinforcement of the inclined tower column is connected and fixed to the rigid frame, the adjustable struts are used to adjust the size of the inner contour and the outer contour of the inclined tower column, and the inner cavity support work platform and the middle support work platform are respectively provided with a herringbone staircase and a ladder cage;
[0009] The positioning system is used to install the vertical main reinforcement.
[0010] As a further improvement of the present invention, the walking system includes walking wheels, and the bottom of each movable support working platform is provided with the walking wheels. The movable support working platform is pushed by the walking wheels to move along the outer contour of the inclined tower column to adapt to the changes in the cross-sectional size of the inclined tower column.
[0011] As a further improvement of the present invention, the heights of the middle support working platform, the inner cavity support working platform and the movable support working platform are relatively flush with the height of the vertical steel bars, and are each provided with upper, middle and lower three-layer operating platforms. The upper and middle operating platforms on the middle support working platform and the inner cavity support working platform are each provided with the adjustable support rod connected to the rigid frame.
[0012] As a further improvement of the present invention, the adjustable support rod is a threaded telescopic rod and a sleeve, the threaded telescopic rod is movably inserted into the interior of the sleeve, the threaded telescopic rod is threadedly connected to an adjustment handle, the adjustment handle is rotatably connected to the end of the threaded telescopic rod mounted on the sleeve, the sleeve is connected and fixed to the upper and middle operating platforms on the inner cavity support working platform or the middle support working platform via a U-shaped clamp, and the threaded telescopic rod is connected to the rigid skeleton.
[0013] As a further improvement of the present invention, each operating platform on the middle support working platform, the inner cavity support working platform and the movable support working platform is provided with a corresponding extension platform according to the inclination of the vertical main reinforcement.
[0014] As a further improvement of the present invention, the positioning system includes a bottom positioning comb plate, a middle support frame steel bar, and a top positioning comb plate. The bottom of the bottom positioning comb plate is provided with a channel steel, and the channel steel is supported by the ground. The bottom of the vertical main reinforcement is connected to the bottom positioning comb plate, the middle support frame steel bar is connected and fixed to the center position of both sides of the rigid frame, the top positioning comb plate is connected and fixed to the top of the rigid frame, and the top of the vertical main reinforcement is connected to the top positioning comb plate.
[0015] As a further improvement of the present invention, a plurality of circular positioning holes are provided on the bottom positioning comb plate, and the circular positioning holes are distributed on the bottom positioning comb plate according to the spacing between each steel bar of the vertical main reinforcement, and each steel bar of the vertical main reinforcement is plugged and fixed with the circular positioning hole, and a semicircular positioning hole matching the outer wall of the top end of the vertical main reinforcement is provided on the top positioning comb plate, and the inclination of the vertical main reinforcement is adjusted through the semicircular positioning hole.
[0016] As a further improvement of the present invention, a guardrail is provided on the outer side of the top of each movable supporting work platform, and a plurality of positioning hoops are fixedly installed on the ground around the outer periphery of the movable supporting work platform. The outer periphery of the movable supporting work platform frame is connected and fixed to the positioning hoops by steel wire ropes.
[0017] Compared with the prior art, the present invention has the following beneficial effects:
[0018] The present invention is provided with a middle support working platform, which can operate on the two columns of the inclined tower column at the same time, thereby improving work efficiency. The middle support working platform connects the movable support working platforms of the two columns together, which is beneficial to saving tire frame construction materials, and can also reduce the error caused by the construction of a single column, thereby ensuring the accuracy of the two relative columns during construction, improving work efficiency and work quality. Furthermore, a walking system is provided at the bottom of the movable support working platform, which is convenient for movement and thus adjusting the outer cross-sectional size of the tower column. The position of the inner cavity support working platform and the rigid skeleton is adjusted by an adjustable strut, which is beneficial for adjusting to the shape change of the inclined tower column, thereby improving the accuracy of the steel bar construction of the inclined tower column components, and constructing the two columns at the same time, which can make full use of construction resources, reduce the construction period, and thus improve the overall construction efficiency. They can also support each other during the construction process, enhance the overall stability of the structure, and reduce construction risks. The two columns are constructed at the same time, which can better control the positioning and installation accuracy of the tire frame, ensure the tensioning of the prestress and the later stress conditions, thereby improving the quality and life of the structure. BRIEF DESCRIPTION OF THE DRAWINGS
[0019] Figure 1 It is a front view of the present invention;
[0020] Figure 2 A top view of the present invention;
[0021] Figure 3 It is a schematic plan view of the bottom positioning comb plate of the present invention;
[0022] Figure 4 This is a schematic diagram of the top opening positioning comb plate structure of the present invention;
[0023] Figure 5It is a top view, AA cross-sectional view and BB cross-sectional view of the inner cavity support work platform of the present invention;
[0024] Figure 6 It is a top view, CC cross-sectional view and DD cross-sectional view of the middle supporting working platform of the present invention.
[0025] In the figure: 1. Middle support working platform; 2. Inner cavity support working platform; 3. Movable support working platform; 4. Ladder; 5. Channel steel; 6. Bottom positioning comb plate; 601. Circular positioning hole; 7. Herringbone staircase; 8. Ladder cage; 9. Adjustable support rod; 901. Threaded telescopic rod; 902. Casing; 903. Adjustment handle; 904. U-shaped clamp; 10. Rigid skeleton; 11. Vertical main reinforcement; 12. Middle support frame reinforcement; 13. Top positioning comb plate; 14. Semicircular positioning hole; 15. Guardrail. DETAILED DESCRIPTION
[0026] To facilitate understanding of the present invention, the present invention will be described more comprehensively below with reference to the relevant drawings. Several embodiments of the present invention are given in the drawings, but the present invention can be implemented in different forms and is not limited to the embodiments described in the text. On the contrary, these embodiments are provided to make the content disclosed in the present invention more thorough and comprehensive.
[0027] It should be noted that when an element is referred to as being "fixed on" another element, it may be directly on the other element or there may be a central element. When an element is considered to be "connected to" another element, it may be directly connected to the other element or there may be a central element at the same time. The terms "vertical", "horizontal", "left", "right" and similar expressions used in this article are for illustrative purposes only.
[0028] Unless otherwise defined, all technical and scientific terms used herein have the same meaning as commonly connected by technicians in the technical field to which the present invention belongs. The terms used in the specification of the present invention are only for the purpose of describing specific embodiments and are not intended to limit the present invention. The term "and / or" used in this article includes any and all combinations of one or more related listed items.
[0029] The present invention is further described in detail below in conjunction with the accompanying drawings.
[0030] Embodiment 1:
[0031] See also Figure 1-6 The present invention provides a tire frame for integrally manufacturing steel bars of polygonal variable-section inclined tower column parts, including a middle bracket work platform 1, an inner cavity bracket work platform 2, a plurality of movable bracket work platforms 3, a slat 4, and a positioning system;
[0032] The middle support work platform 1 is arranged at the center of the relative inclined surfaces of the two columns of the inclined tower column, and is arranged along the outer contour of the center of the inclined surface of the inclined tower column;
[0033] A plurality of movable support work platforms 3 are arranged along the outer contour of the inclined tower column from both sides of the middle support work platform 1, and are arranged together with the middle support work platform 1 to form a polygonal structure of the inclined tower column. Adjacent movable support work platforms 3 and the joints with the middle support platform are connected by a slat 4. Any movable support work platform 3 can be moved by a walking system to adjust the outer cross-sectional size of the inclined tower column.
[0034] The inner cavity support work platform 2 is arranged along the inner cavity contour of the inclined tower column. The inner cavity support work platform 2 and the middle support work platform 1 are both connected to a rigid frame 10 through an adjustable support rod 9. The vertical main reinforcement 11 of the inclined tower column is connected and fixed to the rigid frame 10. The adjustable support rod 9 is used to adjust the size of the inner contour and the outer contour of the inclined tower column. The inner cavity support work platform 2 and the middle support work platform 1 are respectively provided with a herringbone staircase 7 and a ladder cage 8;
[0035] The positioning system is used to install the vertical main reinforcement 11.
[0036] The walking system includes walking wheels, and the bottom of each movable support work platform 3 is provided with the walking wheels, and the movable support work platform 3 is pushed by the walking wheels to move along the outer contour of the inclined tower column to adapt to the change of the cross-sectional size of the inclined tower column.
[0037] The heights of the middle support working platform 1, the inner cavity support working platform 2 and the movable support working platform 3 are relatively flush with the height of the vertical steel bars, and are each provided with upper, middle and lower three-layer operating platforms. The upper and middle operating platforms on the middle support working platform 1 and the inner cavity support working platform 2 are each provided with the adjustable support rod 9 connected to the rigid frame 10.
[0038] The adjustable support rod 9 consists of a threaded telescopic rod 901 and a sleeve 902. The threaded telescopic rod 901 is movably inserted into the interior of the sleeve 902. The threaded telescopic rod 901 is threadedly connected to an adjustment handle 903. The adjustment handle 903 is rotatably connected to the end of the threaded telescopic rod 901 sleeved on the sleeve 902. The sleeve 902 is connected and fixed to the upper and middle operating platforms on the inner cavity support working platform 2 or the middle support working platform 1 through a U-shaped clamp 904. The threaded telescopic rod 901 is connected to the rigid skeleton 10.
[0039] Each operating platform on the middle support operating platform 1 , the inner cavity support operating platform 2 and the movable support operating platform 3 is provided with a corresponding extension platform according to the inclination of the vertical main reinforcement 11 .
[0040] The present embodiment, during the construction, firstly installs the middle support work platform 1 between the two columns of the inclined tower column, and then extends the movable support work platform 3 from both sides of the central support work platform according to the outer contour of the inclined tower column, until it is consistent with the column shape of the inclined tower column. Through the set middle support work platform 1, the two columns of the inclined tower column can be operated at the same time, thereby improving the work efficiency. The middle support work platform 1 connects the movable support work platforms 3 of the two columns together, which is beneficial to saving the materials for the construction of the tire frame, and can also reduce the error caused by the construction of a single column, thereby ensuring the accuracy of the two relative columns during construction, improving the work efficiency and work quality, and constructing the two columns at the same time, which can make full use of construction resources, reduce the construction period, and thus improve the overall construction efficiency. They can also support each other during the construction process, enhance the overall stability of the structure, and reduce the construction risk. The simultaneous construction of the two columns can better control the positioning and installation accuracy of the tire frame, ensure the tensioning of the prestress and the later stress conditions, thereby improving the quality and life of the structure. Furthermore, a walking platform is provided at the bottom of the movable support work platform 3. The system is convenient for moving and adjusting the outer cross-sectional size of the tower column. The position of the inner cavity support work platform 2 and the rigid frame 10 is adjusted by the adjustable support rod 9, which is conducive to adapting to the shape change of the inclined tower column for adjustment, thereby improving the accuracy of the reinforcement of the inclined tower column parts. In this embodiment, the adjustable support rod 9 adopts a threaded telescopic rod 901, a sleeve 902 and an adjusting handle 903 to achieve telescoping. The adjusting handle 903 is rotated to adjust its horizontal position on the threaded extension rod. Since the adjusting handle 903 is movably connected to the sleeve 902, when the adjusting handle 903 is moved When it moves, it will push the sleeve 902 to move on the threaded telescopic rod 901, thereby achieving telescopic movement, which is convenient for adjusting the distance between the inner cavity support or the middle support and the rigid skeleton 10, and can better adapt to steel segments of different sizes and shapes, ensure the accurate docking and fixation of the steel segments, thereby improving the accuracy and efficiency of construction, and helping to optimize the arrangement of the steel segments, making the structure of the tower column more stable, and enhancing the overall bearing capacity and weathering and earthquake resistance of the tower column. In addition, appropriate distance adjustment can also reduce errors in the construction process and reduce safety hazards caused by inaccurate docking.
[0041] Embodiment 2:
[0042] See also Figure 1 , Figure 3 , Figure 4The positioning system includes a bottom positioning comb plate 6, a middle support frame steel bar 12, and a top positioning comb plate 13. The bottom of the bottom positioning comb plate 6 is provided with a channel steel 5, and the channel steel 5 is supported by the ground. The bottom of the vertical main reinforcement 11 is connected to the bottom positioning comb plate 6, the middle support frame steel bar 12 is connected and fixed to the center position of both sides of the rigid frame 10, the top positioning comb plate 13 is connected and fixed to the top of the rigid frame 10, and the top of the vertical main reinforcement 11 is connected to the top positioning comb plate 13.
[0043] The bottom positioning comb plate 6 is provided with a plurality of circular positioning holes 601, and the circular positioning holes 601 are distributed on the bottom positioning comb plate 6 according to the spacing between each steel bar of the vertical main reinforcement 11, and each steel bar of the vertical main reinforcement 11 is plugged and fixed with the circular positioning hole 601, and the top positioning comb plate 13 is provided with a semicircular positioning hole 14 matching the outer wall of the top end of the vertical main reinforcement 11, and the inclination of the vertical main reinforcement 11 is adjusted through the semicircular positioning hole 14.
[0044] When in use and during construction, the position of the movable working support platform is adjusted according to the contour of the polygonal variable-section inclined tower column component steel bars, the position of the bottom positioning comb plate 6 is measured and laid out, and adjusted and fixed, and then the position of the rigid skeleton 10 of the component steel bars is measured and laid out, and the rigid skeleton 10 is installed, and the adjustable struts 9 on the inner cavity support working platform 2 and the middle support working platform 1 are connected and supported and fixed with the rigid skeleton 10, and then the top positioning comb plate 13 is measured and laid out, and the top end of the rigid skeleton 10 is connected and fixed, and the position of the middle support frame steel bars 12 is released according to the top positioning comb plate 13 and the bottom positioning comb plate 6, and fixed on the rigid skeleton 10, and finally the vertical main reinforcement 11 is installed according to the semicircular positioning holes 14 and the circular positioning holes 601 set on the top positioning comb plate 13 and the bottom positioning comb plate 6. After the vertical main reinforcement 11 steel bars and other steel bars are tied, the adjustable struts are removed, and the constructed component steel bars are directly lifted vertically.
[0045] Embodiment three:
[0046] See also Figure 1 A guardrail 15 is provided on the outer side of the top of each movable support work platform, and a plurality of positioning hoops are fixedly installed on the ground around the movable support work platform. The outer periphery of the movable support work platform frame is connected and fixed to the positioning hoops by steel wire ropes.
[0047] When in use, by setting a guardrail 15 on the top outer side of the movable support work platform, the safety of workers during construction can be ensured and construction workers can be prevented from falling from the frame. Multiple steel wire ropes are set on the frame of the movable support work platform and connected and fixed with positioning hoops set on the ground, which can prevent the frame from moving on the ground, further ensuring the safety and accuracy of construction.
[0048] The above is an exemplary description of the present invention in combination with the accompanying drawings. It is obvious that the specific implementation of the present invention is not limited to the above-mentioned method. As long as such non-substantial improvements are made by adopting the method concept and technical solution of the present invention, or the concept and technical solution of the present invention are directly applied to other occasions without improvement, they are all within the protection scope of the present invention.
Claims
1. A frame for integrally manufacturing steel bars of polygonal variable-section inclined tower columns. Features: It comprises a middle support working platform (1), an inner cavity support working platform (2), a plurality of movable support working platforms (3), a scaffolding plate (4), and a positioning system; The middle support working platform (1) is arranged at the center of the relative inclined surfaces of the two columns of the inclined tower column, and is arranged along the outer contour of the center of the inclined surface of the inclined tower column; A plurality of movable support work platforms (3) are arranged along the outer contour of the inclined tower column from both sides of the middle support work platform (1), and are arranged together with the middle support work platform (1) to form a polygonal structure of the inclined tower column. Adjacent movable support work platforms (3) and the joints with the middle support platform are connected by a bridging plate (4). Any movable support work platform (3) can be moved by a walking system to adjust the outer cross-sectional size of the inclined tower column. The inner cavity support work platform (2) is arranged along the inner cavity contour of the inclined tower column. The inner cavity support work platform (2) and the middle support work platform (1) are both connected to a rigid frame (10) via an adjustable support rod (9). The vertical main reinforcement (11) of the inclined tower column is connected and fixed to the rigid frame (10). The adjustable support rod (9) is used to adjust the size of the inner contour and the outer contour of the inclined tower column. The inner cavity support work platform (2) and the middle support work platform (1) are respectively provided with a herringbone staircase (7) and a ladder cage (8); The positioning system is used to install the vertical main reinforcement (11).
2. A tire frame for integrally manufacturing steel bars of polygonal variable-section inclined tower column parts according to claim 1, Features: The walking system comprises walking wheels, and the bottom of each movable support working platform (3) is provided with the walking wheels, and the movable support working platform (3) is pushed by the walking wheels to move along the outer contour of the inclined tower column to adapt to the change of the cross-sectional size of the inclined tower column.
3. A tire frame for integrally manufacturing steel bars of polygonal variable-section inclined tower column parts according to claim 1, Features: The heights of the middle support working platform (1), the inner cavity support working platform (2) and the movable support working platform (3) are relatively flush with the height of the vertical steel bars, and are all provided with upper, middle and lower three-layer operating platforms. The upper and middle operating platforms on the middle support working platform (1) and the inner cavity support working platform (2) are both provided with the adjustable support rods (9) connected to the rigid frame (10).
4. A tire frame for integrally manufacturing steel bars of polygonal variable-section inclined tower column parts according to claim 3, Features: The adjustable support rod (9) comprises a threaded telescopic rod (901) and a sleeve (902); the threaded telescopic rod (901) is movably inserted into the interior of the sleeve (902); the threaded telescopic rod (901) is threadedly connected to an adjustment handle (903); the adjustment handle (903) is rotatably connected to the end of the sleeve (902) on which the threaded telescopic rod (901) is sleeved; the sleeve (902) is connected and fixed to the upper and middle operating platforms on the inner cavity support working platform (2) or the middle support working platform (1) via a U-shaped clamp (904); and the threaded telescopic rod (901) is connected to the rigid skeleton (10).
5. A tire frame for integrally manufacturing steel bars of polygonal variable-section inclined tower column parts according to claim 3, Features: Each operating platform on the middle support operating platform (1), the inner cavity support operating platform (2) and the movable support operating platform (3) is provided with a corresponding extension platform according to the inclination of the vertical main reinforcement (11).
6. A tire frame for integrally manufacturing steel bars of polygonal variable-section inclined tower column parts according to claim 1, Features: The positioning system comprises a bottom positioning comb plate (6), a middle support frame steel bar (12), and a top positioning comb plate (13); a channel steel (5) is provided at the bottom of the bottom positioning comb plate (6); the channel steel (5) is supported by the ground; the bottom of the vertical main reinforcement (11) is connected to the bottom positioning comb plate (6); the middle support frame steel bar (12) is connected and fixed to the center positions of both sides of the rigid frame (10); the top positioning comb plate (13) is connected and fixed to the top of the rigid frame (10); and the top of the vertical main reinforcement (11) is connected to the top positioning comb plate (13).
7. A tire frame for integrally manufacturing steel bars of polygonal variable-section inclined tower column parts according to claim 6, Features: The bottom positioning comb plate (6) is provided with a plurality of circular positioning holes (601), the circular positioning holes (601) being distributed on the bottom positioning comb plate (6) according to the spacing between each steel bar of the vertical main reinforcement (11), each steel bar of the vertical main reinforcement (11) being plugged and fixed to the circular positioning hole (601), the top positioning comb plate (13) being provided with a semicircular positioning hole (14) matching the outer wall of the top end of the vertical main reinforcement (11), the inclination of the vertical main reinforcement (11) being adjusted through the semicircular positioning hole (14).
8. A tire frame for integrally manufacturing steel bars of polygonal variable-section inclined tower column parts according to claim 1, Features: A guardrail (15) is provided on the outer side of the top of each movable support work platform, and a plurality of positioning hoops are fixedly installed on the ground around the outer periphery of the movable support work platform. The outer periphery of the movable support work platform frame is connected and fixed to the positioning hoops via steel wire ropes.
Citation Information
Cited By
Construction method for block prefabrication of curve variable cross-section bridge tower steel reinforcement framework
CN119824803A