Dynamic optimization construction method for tamping side ditch
Through dynamic construction methods optimized by numerical simulation analysis and real-time monitoring, the problems of uneven compaction effect and poor slope stability in traditional side ditch construction are solved, and the efficient stability of side ditch compaction and the improvement of backfill soil quality are achieved. Construction under complex geological conditions.
Patent Information
- Application Number
- CN202411001764.2
- Authority / Receiving Office
- CN · China
- Patent Type
- Applications(China)
- Current Assignee / Owner
- Filing Date
- 2024-07-25
- Publication Date
- 2024-11-12
- Estimated Expiration
- Not applicable · inactive patent
AI Technical Summary
Traditional side ditch construction methods have problems such as uneven compaction effect, poor slope stability, and lateral loss of backfill soil, which is difficult to meet the requirements of modern projects for high quality and high efficiency, especially in complex geological conditions, which is difficult to achieve stable side ditch compaction. .
Using a dynamic optimization construction method based on numerical simulation analysis, by predicting the mutual influence of slope and backfill soil under vibration compaction, multiple partitions and layers are divided, vibration energy and process parameters are adjusted, and the compaction parameters are monitored and dynamically optimized to ensure that Stability and compactness of slopes and backfill soil.
It achieves efficient and stable trench compaction, ensures slope safety and backfill quality, improves construction quality and efficiency, and is suitable for construction under complex geological conditions.
Smart Images

Figure CN118932972A_ABST
Abstract
Description
Technical Field
[0001] The present application relates to the technical field of ditch compaction, and more specifically, to a dynamic optimization construction method for ditch compaction. Background Art
[0002] In civil engineering and infrastructure construction, side ditches are important structures for drainage and prevention of soil erosion. The quality and stability of side ditches directly affect the overall performance of roads, dams and other projects. Traditional side ditch construction methods often rely on experience and simple engineering calculations, and there are problems such as uneven compaction effect, poor slope stability, and lateral loss of backfill soil, which are difficult to meet the requirements of modern engineering for high quality and high efficiency.
[0003] In recent years, vibration compaction technology has been gradually applied in ditch construction because it can significantly improve the density and stability of backfill soil. However, the slope and backfill soil affect each other during the vibration compaction process, and the vibration energy is unevenly distributed, resulting in differences in compaction effects in different areas. In particular, the compaction of the slope area is more difficult and prone to deformation and loss. In addition, there is a lack of real-time monitoring and dynamic adjustment methods for slope stability and backfill soil density during the construction process, making it difficult to discover and solve construction problems in a timely manner, affecting construction quality and efficiency.
[0004] To sum up, how to solve many problems in traditional construction methods and achieve efficient and stable ditch tamping construction under complex geological conditions provides a new technical approach for civil engineering construction and has become a technical problem that needs to be solved urgently. Summary of the invention
[0005] In order to overcome a series of defects in the prior art, the purpose of this application is to provide a dynamic optimization construction method for ditch compaction in view of the above problems, comprising the following steps:
[0006] Step 1: Based on numerical simulation analysis, predict the mutual influence between the slope and backfill soil under vibration compaction, evaluate the possible deformation of the slope and the lateral loss of backfill soil, and divide the ditch area into multiple zones and layers accordingly;
[0007] Step 2: First, high-energy vibration compaction is performed in the central bottom area to form a compacted base, and then the compaction range is gradually expanded to the slope areas on both sides, and the compaction energy and process parameters are adjusted according to the characteristics of each partition;
[0008] Step 3: In the slope areas on both sides of the ditch, the direction and strength of the impact force are controlled so that the compaction energy is effectively transferred to the slope area to ensure the compaction quality of the backfill soil in the slope area;
[0009] Step 4: Real-time monitoring of slope stability and lateral loss of backfill material, dynamic optimization and adjustment of compaction parameters of each partition based on the monitoring data, and implementation of adaptive partition and layered control;
[0010] Step 5: After completing the vibration compaction work in each zone and layer, conduct a comprehensive assessment of the compaction quality of the ditch backfill soil.
[0011] Furthermore, step 1 includes the following steps:
[0012] Step 1.1, based on the finite element numerical calculation method, taking into account the influence factors of soil layer distribution, slope shape and groundwater level, the geometric model of the slope and backfill soil is established;
[0013] Step 1.2, introduce the dynamic characteristics of the vibration compaction load into the geometric model to simulate the effect of vibration on the slope and backfill soil;
[0014] Step 1.3, conduct in-depth analysis of the output results of the numerical simulation to predict the deformation and stability changes of the slope under vibration, and evaluate the lateral loss tendency of the backfill soil under vibration;
[0015] Step 1.4: Based on the prediction results, the ditch area is divided into several zones according to the size of deformation and loss tendency. The geological conditions and expected responses within each zone are relatively uniform, and each zone is layered according to depth.
[0016] Furthermore, the deformation of the slope under vibration is expressed by the following formula: u = K -1 F, where u is the displacement vector, i.e., the deformation of the slope under vibration; K is the stiffness matrix; and F is the vibration load;
[0017] The stability change of the slope is evaluated by calculating the safety factor FOS, the specific formula is: Where c′ is the effective cohesion; σ is the normal stress; φ′ is the effective internal friction angle; τ is the shear stress acting on the sliding surface;
[0018] The lateral loss of backfill soil under vibration is evaluated by lateral deformation and shear stress. The specific formula is: τ x =G·γ x , where δ x is the lateral deformation; v x (t′) is the lateral velocity that changes with time; the variable of t′ integration represents the time point from the initial time 0 to a certain time; dt′ represents the small time change at time t′; τ x is the lateral shear stress; G is the shear modulus; γ x is the lateral shear strain.
[0019] Further, step 1.4 includes the following steps:
[0020] Based on the spatial distribution characteristics of deformation and loss tendency, combined with cluster analysis method, the ditch is divided into several main zones;
[0021] Taking into account the geological conditions and expected response characteristics, the sub-areas are optimized and adjusted to ensure that the conditions within each sub-area are relatively uniform;
[0022] For each zone, depth stratification is performed based on soil quality changes and compaction difficulty factors;
[0023] Develop a complete zoning and stratification scheme, assign unique identifiers to each zone and stratum, and summarize their key characteristics;
[0024] Establish a dynamic adjustment mechanism to optimize the plan in a timely manner according to actual conditions during the construction process.
[0025] Furthermore, based on the spatial distribution characteristics of deformation and loss tendency, combined with the cluster analysis method, the ditch is divided into several main zones, including the following steps:
[0026] The deformation and loss tendency data of the ditch area are collected to form a data set. Each data point contains two features: deformation feature X i and the churn tendency characteristic Y i ;
[0027] K-means clustering was selected as the clustering algorithm, and the goal of clustering was defined as dividing the data points into several groups so that the data points within each group are similar to each other, that is, the ditch areas are similar in deformation and loss tendency, while the similarity of data points between groups is low;
[0028] Using Euclidean distance as a metric for similarity between data points, the clustering process is represented by the following objective function: Among them, X i is the feature vector of the i-th data point, including the deformation feature X i and the churn tendency characteristic Y i ;μ j is the eigenvector of the jth cluster center; C is the set of clusters, including all cluster centers μ j ;
[0029] After clustering is completed, each ditch area data point is assigned to a cluster center μ j The partition represented by it realizes the partition of the ditch area.
[0030] Furthermore, the depth-wise layering method includes the following steps:
[0031] Divide the soil into layers based on depth, each with similar compaction characteristics and vibration response;
[0032] Quantitatively describe the characteristics of each layer, including factors related to compaction difficulty;
[0033] An optimization model is established to determine the best stratification scheme. The optimization model is described by the following objective function: Where d represents the depth, that is, the range from the surface to the depth d; X k (d) is the characteristic vector of the k-th layer of soil at depth d, including the index of the compaction difficulty factor; X target is the ideal value of the target compaction characteristic; L is the variable used to minimize the objective; Layer(d) represents the set of selected soil layers at depth d;
[0034] By solving the above optimization problem, the best layering scheme Layer(d) is determined.
[0035] Furthermore, step 2 includes the following steps:
[0036] Arrange a number of vibrating compaction machines in the central bottom area of the side ditch and adjust them to a high vibration energy level to perform compaction operations to form a central base layer;
[0037] After the central base layer is compacted, the compaction range is gradually expanded outward along the slope areas on both sides of the ditch;
[0038] According to the results of numerical simulation analysis, differentiated compaction strategies are adopted for different partitions: for partitions with large deformation and loss tendency, the vibration energy is appropriately reduced to reduce the adverse impact on the slope; for relatively stable partitions, the vibration energy is appropriately increased to improve the compaction effect;
[0039] Adjust the layout and operation mode parameters of compaction machinery to ensure the compaction quality of each zone;
[0040] When working in the outermost areas of the slopes on both sides of the ditch, use a layered and phased compaction method, pay close attention to the stability of the slope, and adjust parameters in time to avoid instability.
[0041] Further, step 3 includes the following steps:
[0042] Arrange vibrating compaction equipment with adjustable vibration parameters in the slope area, and effectively transmit the impact force to the backfill soil layer inside the slope by changing the arrangement angle, vibration frequency and vibration force parameters of the equipment;
[0043] According to the geological conditions and compaction requirements of each zone, the size and direction of the impact force should be reasonably set: in the steep slope area, the horizontal component of the impact force should be appropriately increased to transfer more energy to the inside of the slope; in the flat area, the vertical component should be appropriately increased to improve the compaction effect of the surface layer;
[0044] For some slope areas that are difficult to act directly on, reflective devices are arranged to use the reflection effect of the impact force to indirectly guide the vibration energy to the target area for compaction;
[0045] Through on-site detection feedback, the compaction quality of the backfill soil in the slope area is monitored in real time, and the impact force parameters are adjusted in time to ensure that the compaction quality of the entire slope area meets the design requirements.
[0046] Further, step 4 includes the following steps:
[0047] Adopting an automated monitoring system to collect data from each monitoring point in real time and summarize it to the control center;
[0048] According to the monitoring data analysis results, the slope stability and backfill loss of each sub-area are judged, and the compaction parameters of the sub-area with abnormalities are automatically adjusted;
[0049] For normal partitions, the compaction parameters are fine-tuned according to slight changes in monitoring data to optimize the compaction effect;
[0050] Feed the monitoring data to the numerical analysis model to correct the model parameters, continuously improve the accuracy of the numerical simulation, and provide a more reliable basis for the pre-determination of the compaction parameters;
[0051] Through closed-loop feedback of monitoring data, adaptive zoning and stratification intelligent control of the entire process is achieved to maximize the effectiveness of vibration compaction and ensure slope safety and backfill compaction quality.
[0052] Further, step 5 includes the following steps:
[0053] Use in-situ testing methods to test the density of each partition and each layer to ensure that the design requirements are met;
[0054] Use dynamic penetration method to detect whether the bearing capacity of backfill soil meets the design standards;
[0055] Use settlement observation points to continuously monitor the deformation of slopes and backfill soil and assess their long-term stability;
[0056] Compare the actual compaction effect with the predicted result in step 1 and analyze the reasons for the difference;
[0057] Based on the quality acceptance results and data analysis, the compaction process parameters and zoning and stratification schemes are optimized and adjusted to form a more accurate construction guidance plan.
[0058] Compared with the prior art, this application has the following beneficial effects:
[0059] This application proposes a dynamic optimization ditch compaction construction method based on numerical simulation and real-time monitoring. Through zoning and stratification strategy, adjustment of vibration parameters, real-time monitoring and adaptive adjustment, the high efficiency and stability of ditch compaction are achieved, ensuring the safety of the slope and the quality of backfill soil. BRIEF DESCRIPTION OF THE DRAWINGS
[0060] Figure 1 A schematic flow chart of a dynamically optimized construction method for ditch compaction disclosed in an embodiment of the present application. DETAILED DESCRIPTION
[0061] In order to make the purpose, technical scheme and advantages of the implementation of the present invention clearer, the technical scheme in the embodiment of the present invention will be described in more detail below in conjunction with the drawings in the embodiment of the present invention. In the drawings, the same or similar reference numerals throughout represent the same or similar elements or elements with the same or similar functions. The described embodiments are part of the embodiments of the present invention, not all of the embodiments.
[0062] Based on the embodiments of the present invention, all other embodiments obtained by ordinary technicians in the field without making any creative work shall fall within the scope of protection of the present invention.
[0063] The embodiments and directional terms described below with reference to the accompanying drawings are exemplary and intended to be used to explain the present invention, but should not be construed as limiting the present invention.
[0064] like Figure 1 As shown, a dynamic optimization construction method for ditch compaction includes the following steps:
[0065] Step 1: Based on numerical simulation analysis, predict the mutual influence between the slope and backfill soil under vibration compaction, evaluate the possible deformation of the slope and the lateral loss of backfill soil, and divide the ditch area into multiple zones and layers accordingly;
[0066] Step 2: First, high-energy vibration compaction is performed in the central bottom area to form a compacted base, and then the compaction range is gradually expanded to the slope areas on both sides, and the compaction energy and process parameters are adjusted according to the characteristics of each partition;
[0067] Step 3: In the slope areas on both sides of the ditch, the direction and strength of the impact force are controlled so that the compaction energy is effectively transferred to the slope area to ensure the compaction quality of the backfill soil in the slope area;
[0068] Step 4: Real-time monitoring of slope stability and lateral loss of backfill material, dynamic optimization and adjustment of compaction parameters of each partition based on the monitoring data, and implementation of adaptive partition and layered control;
[0069] Step 5: After completing the vibration compaction work in each zone and layer, conduct a comprehensive assessment of the compaction quality of the ditch backfill soil.
[0070] In step 1, numerical simulation analysis is the basis of the entire ditch compaction dynamic optimization construction method. Through numerical simulation, the mutual influence between the slope and backfill under vibration compaction can be predicted. Specifically, this process includes establishing numerical models of the slope and backfill, setting relevant parameters for vibration compaction, and then simulating the compaction process by computer to predict the deformation of the slope under different conditions and the degree of lateral loss of the backfill. The advantages of this step are mainly reflected in three aspects: first, it can provide detailed prediction data to help understand the response characteristics of different areas during the compaction process; second, it helps to identify the weak areas of the slope and provide key areas for subsequent construction; finally, the ditch area is divided into multiple partitions and layers according to the simulation results, which provides a scientific basis for the next step of compaction work, ensuring that the compaction parameters of each area can accurately match its specific conditions and optimize the compaction effect.
[0071] In step 2, the construction starts with high-energy vibration compaction from the central bottom area to form a compacted base, and then gradually expands the compaction range to the slope areas on both sides. Through this gradually expanding compaction method, the distribution of compaction energy can be effectively controlled to ensure that each area can obtain sufficient compaction effect. First, the high-energy compaction of the central bottom area can form a stable base, providing strong support for the backfill of the entire ditch. Then, in the process of gradually expanding to both sides, the compaction energy and process parameters are adjusted according to the characteristics of each partition, which can make the compaction process more uniform and efficient, avoiding the problems of energy dispersion and uneven effect caused by one-time large-area compaction. The advantage of this step is that it improves the efficiency and quality of the compaction operation, makes the foundation of the entire ditch compaction more stable, and lays a good foundation for the construction of subsequent steps.
[0072] In step 3, in the slope areas on both sides of the ditch, it is necessary to control the direction and strength of the impact force so that the compaction energy is effectively transferred to the slope area to ensure the compaction quality of the backfill soil in the slope area. The key to this process is to accurately control the operating parameters of the compaction equipment to achieve effective transfer and uniform distribution of energy. In this way, the compaction density of the slope area can be improved without destroying the stability of the slope, and the problems of looseness and lateral loss of the slope backfill soil can be prevented. In addition, by controlling the direction of the impact force, directional compaction can be performed for different slope shapes and backfill soil characteristics, further improving the compaction effect and slope stability. The advantage of this step is that through precise compaction control, the construction quality and stability of the slope area are ensured, thereby providing a guarantee for the long-term stability of the entire ditch.
[0073] The core of step 4 is to monitor the slope stability and lateral loss of backfill in real time, and dynamically optimize and adjust the compaction parameters of each partition according to the monitoring data to achieve adaptive partition and layered control. By deploying sensors and monitoring equipment, the deformation data of the slope and the loss of backfill can be obtained in real time, and problems can be discovered and adjusted in time. The dynamic optimization process includes adjusting the compaction energy, changing the compaction time, modifying the compaction path and other means to adapt to the actual situation on site. The advantage of this step is mainly reflected in improving the flexibility and response speed of construction. Through real-time monitoring and dynamic adjustment, it can effectively deal with various uncertainties that arise during the construction process, ensure the quality of compaction, minimize construction risks and costs, and improve construction efficiency and safety.
[0074] In step 5, after completing the vibration compaction work of each partition and layer, the construction team needs to conduct a comprehensive assessment of the compaction quality of the ditch backfill. The assessment includes the density, uniformity, stability of the slope, and possible lateral loss of the backfill. Through this assessment, we can fully understand the compaction effect, find and solve existing problems, and ensure that the overall quality of the ditch meets the design requirements. This evaluation process is not only a verification of the previous construction effect, but also an important link to provide data support and technical feedback for subsequent construction. Through scientific and systematic evaluation, we can summarize construction experience, optimize construction technology, and improve the quality and efficiency of future construction. The advantage of this step is to ensure the reliability of the compaction quality and the long-term stability of the ditch, providing a solid guarantee for the successful implementation of the entire project.
[0075] In summary, this dynamic optimization construction method for ditch compaction systematically improves the quality and efficiency of ditch compaction construction through numerical simulation analysis, zoned and layered high-energy compaction, real-time monitoring and dynamic adjustment, and comprehensive evaluation of compaction quality, ensuring the stability of the slope and the density of backfill soil, and providing all-round technical guarantee for the successful implementation of the project.
[0076] Furthermore, step 1 includes the following steps:
[0077] Step 1.1, based on the finite element numerical calculation method, taking into account the influence factors of soil layer distribution, slope shape and groundwater level, the geometric model of the slope and backfill soil is established;
[0078] Step 1.2, introduce the dynamic characteristics of the vibration compaction load into the geometric model to simulate the effect of vibration on the slope and backfill soil;
[0079] Step 1.3, conduct in-depth analysis of the output results of the numerical simulation to predict the deformation and stability changes of the slope under vibration, and evaluate the lateral loss tendency of the backfill soil under vibration;
[0080] Step 1.4: Based on the prediction results, the ditch area is divided into several zones according to the size of deformation and loss tendency. The geological conditions and expected responses within each zone are relatively uniform, and each zone is layered according to depth.
[0081] In step 1.1, based on the finite element numerical calculation method, the geometric model of the slope and backfill soil is established while considering multiple influencing factors such as soil layer distribution, slope morphology and groundwater level. This process is the basis of numerical simulation analysis. The distribution and properties of each geological layer are determined through detailed geological exploration data and field mapping of slope morphology. The groundwater level is an important factor affecting the stability of the slope, so its position and change trend need to be accurately reflected during modeling. By establishing a geometric model, the actual geological conditions of the construction area can be fully and accurately reflected, providing a reliable basis for subsequent numerical calculations. The advantage of this step is to ensure the accuracy and completeness of the model, provide a scientific basis for simulating the mechanical behavior during vibration compaction, make subsequent simulations and analyses closer to the actual situation, and improve the reliability and accuracy of the prediction results.
[0082] In step 1.2, the dynamic characteristics of the vibration compaction load are introduced into the geometric model to simulate the effect of vibration on the slope and backfill soil. The vibration compaction load is periodic and dynamic, and its effect on the soil is significantly different from that of the static load. Therefore, during the simulation process, the dynamic characteristics of the vibration compaction equipment, including parameters such as frequency, amplitude, and force, need to be accurately input into the geometric model. Through this simulation, the propagation path and attenuation characteristics of the vibration load in the soil can be observed, and its impact on the stability of the slope and the density of the backfill soil can be evaluated. The advantage of this step is that it truly reproduces the impact of vibration compaction on the soil during the construction process, so that the construction effect under different vibration parameters can be evaluated in a virtual environment, the compaction process parameters can be optimized, and the construction quality and efficiency can be improved.
[0083] In step 1.3, the output results of the numerical simulation are analyzed in depth to predict the deformation of the slope under vibration and its stability changes, and to evaluate the lateral loss tendency of the backfill soil under vibration. By analyzing the simulation results, the deformation mode and failure mechanism that may occur in the slope during vibration compaction can be identified, and the stability changes of the slope under different construction conditions can be predicted. At the same time, the evaluation of the lateral loss tendency of the backfill soil under vibration can provide important early warning information for construction. During the analysis process, charts, animations, and data reports can be used to intuitively display the response characteristics of the slope and backfill soil under vibration. The advantage of this step is that it provides detailed analysis results, helps to fully understand the risks and challenges that may be faced during the construction process, and provides data support and decision-making basis for formulating scientific construction plans.
[0084] In step 1.4, based on the prediction results, the ditch area is divided into several zones according to the size of deformation and loss tendency. The geological conditions and expected responses within each zone are relatively uniform, and each zone is layered according to depth. This process aims to achieve refined construction management, and optimize the compaction effect by adopting differentiated construction strategies for different zones and layers. The basis for the division of each zone includes factors such as geological conditions, slope morphology, groundwater level, and response characteristics of vibration compaction. Through zoning and layering treatment, targeted compaction methods and parameter settings can be adopted for specific problems in different areas to ensure that the compaction quality of each zone meets the expected standards. The advantage of this step is to improve the accuracy and effectiveness of construction. Through scientific zoning and layering management, the stability and density of the slope and backfill soil are ensured, laying a solid foundation for the smooth progress of subsequent construction.
[0085] In summary, step 1 systematically predicts and evaluates the mutual influence between the slope and backfill during the vibration compaction process by establishing a detailed geometric model, introducing the dynamic characteristics of the vibration compaction load, deeply analyzing the numerical simulation results, and scientifically processing the partitions and layers. This process provides comprehensive technical support and decision-making basis for subsequent construction, ensures the safety and efficiency of construction, and improves the overall quality and stability of slope compaction.
[0086] Furthermore, the deformation of the slope under vibration is expressed by the following formula: u = K -1 F, where u is the displacement vector, i.e., the deformation of the slope under vibration; K is the stiffness matrix; and F is the vibration load;
[0087] The stability change of the slope is evaluated by calculating the safety factor FOS, the specific formula is: Where c′ is the effective cohesion; σ is the normal stress; φ′ is the effective internal friction angle; τ is the shear stress acting on the sliding surface;
[0088] The lateral loss of backfill soil under vibration is evaluated by lateral deformation and shear stress. The specific formula is: τ x =G·γ x , where δ x is the lateral deformation; v x (t′) is the lateral velocity that changes with time; the variable of t′ integration represents the time point from the initial time 0 to a certain time; dt′ represents the small time change at time t′; γ x is the lateral shear stress; G is the shear modulus; γ x is the lateral shear strain.
[0089] Further, step 1.4 includes the following steps:
[0090] Based on the spatial distribution characteristics of deformation and loss tendency, combined with cluster analysis method, the ditch is divided into several main zones;
[0091] Taking into account the geological conditions and expected response characteristics, the sub-areas are optimized and adjusted to ensure that the conditions within each sub-area are relatively uniform;
[0092] For each zone, depth stratification is performed based on soil quality changes and compaction difficulty factors;
[0093] Develop a complete zoning and stratification scheme, assign unique identifiers to each zone and stratum, and summarize their key characteristics;
[0094] Establish a dynamic adjustment mechanism to optimize the plan in a timely manner according to actual conditions during the construction process.
[0095] Furthermore, based on the spatial distribution characteristics of deformation and loss tendency, combined with the cluster analysis method, the ditch is divided into several main zones, including the following steps:
[0096] The deformation and loss tendency data of the ditch area are collected to form a data set. Each data point contains two features: deformation feature X i and the churn tendency characteristic Y i ;
[0097] K-means clustering was selected as the clustering algorithm, and the goal of clustering was defined as dividing the data points into several groups so that the data points within each group are similar to each other, that is, the ditch areas are similar in deformation and loss tendency, while the similarity of data points between groups is low;
[0098] Using Euclidean distance as a metric for similarity between data points, the clustering process is represented by the following objective function: Among them, X i is the feature vector of the i-th data point, including the deformation feature X i and the churn tendency characteristic Yi ;μ j is the eigenvector of the jth cluster center; C is the set of clusters, including all cluster centers μ j ;
[0099] After clustering is completed, each ditch area data point is assigned to a cluster center μ j The partition represented by it realizes the partition of the ditch area.
[0100] Furthermore, the depth-wise layering method includes the following steps:
[0101] Divide the soil into layers based on depth, each with similar compaction characteristics and vibration response;
[0102] Quantitatively describe the characteristics of each layer, including factors related to compaction difficulty;
[0103] An optimization model is established to determine the best stratification scheme. The optimization model is described by the following objective function: Where d represents the depth, that is, the range from the surface to the depth d; X k (d) is the characteristic vector of the k-th layer of soil at depth d, including the index of the compaction difficulty factor; X target is the ideal value of the target compaction characteristic; L is the variable used to minimize the objective; Layer(d) represents the set of selected soil layers at depth d;
[0104] By solving the above optimization problem, the best layering scheme Layer(d) is determined.
[0105] Furthermore, step 2 includes the following steps:
[0106] Step 2.1, arranging a number of vibrating compaction machines in the central bottom area of the side ditch and adjusting them to a high vibration energy level for compaction to form a central base layer;
[0107] Step 2.2, after the central base layer is compacted, the compaction range is gradually expanded outward along the slope areas on both sides of the side ditch;
[0108] Step 2.3, based on the results of numerical simulation analysis, adopt differentiated compaction strategies for different partitions: for partitions with large deformation and loss tendency, appropriately reduce the vibration energy to reduce the adverse impact on the slope; for relatively stable partitions, moderately increase the vibration energy to improve the compaction effect;
[0109] Step 2.4, adjust the layout and operation mode parameters of the compaction machinery to ensure the compaction quality of each partition;
[0110] Step 2.5: When working in the outermost area of the slope on both sides of the ditch, use a layered and phased compaction method, pay close attention to the stability of the slope, and adjust parameters in time to avoid instability.
[0111] In step 2.1, several vibration compaction machines are arranged in the central bottom area of the ditch and adjusted to high vibration energy level for compaction operation, with the aim of forming a solid central base layer. Compaction with high vibration energy level can significantly increase the density of the soil, improve its bearing capacity and anti-deformation ability, and provide a stable foundation for subsequent compaction operations. The technical effects of this measure are reflected in several aspects: first, high-energy vibration compaction can minimize the soil pores in the central bottom area, so that it can reach an ideal dense state and enhance the overall strength of the soil; second, by compacting the central base layer first, a stable "core" can be provided for the entire ditch, effectively dispersing and supporting the stress in the slope areas on both sides, and reducing the risk of large-scale deformation and sliding of the slopes during the subsequent compaction process; finally, the formation of the central base layer provides a reliable reference and support for the subsequent partition compaction operation, which helps to improve the efficiency and quality of the compaction construction.
[0112] In step 2.2, after the compaction of the central base layer is completed, the construction gradually expands the compaction range outward. This construction strategy of gradually expanding from the center to the two sides can effectively control and guide the transfer of compaction energy to ensure that each area can be fully compacted. Its technical effects are manifested in several aspects: first, the gradually expanded compaction method can avoid the energy dispersion problem caused by one-time large-area compaction, so that the energy is concentrated in a small range, ensuring that each layer of soil can be fully compacted; second, this method can gradually adjust and optimize the construction parameters during the compaction process, and flexibly adjust the compaction energy and method according to the geological conditions and compaction effects of each expanded area, so as to improve the accuracy and effect of the construction; in addition, the gradually expanded compaction process can timely discover and deal with unstable factors in the construction, reduce the impact on the stability of the slope, and ensure the safety and stability of the entire ditch.
[0113] In step 2.3, differentiated compaction strategies are adopted for different partitions based on the results of numerical simulation analysis. The technical effect of this step is significantly reflected in its targeting and optimization. Through numerical simulation, it is possible to understand the geological conditions, deformation and loss tendency of each partition in detail, so as to formulate the most appropriate compaction plan for each partition. For partitions with large deformation and loss tendency, the vibration energy is appropriately reduced to reduce the adverse effects on the slope, so as to avoid the instability of the slope and lateral loss of backfill soil caused by excessive vibration energy; while for relatively stable partitions, moderately increasing the vibration energy can further improve the compaction effect and make the soil in these areas more compact and stable. The application of this differentiated strategy can not only maximize the overall compaction quality, but also effectively reduce construction risks and improve the overall stability and safety of the ditch slope.
[0114] In step 2.4, adjusting the layout and operation mode parameters of the compaction machinery according to the specific conditions of different partitions is an important means to ensure the compaction quality of each partition. The technical effect of this step is to optimize the use efficiency and effect of the compaction equipment. By adjusting the mechanical layout, it can be ensured that each partition can be fully affected by vibration compaction to avoid dead corners and insufficient compaction problems; by adjusting the operation mode parameters, such as vibration frequency, amplitude and compaction duration, the compaction effect can be optimized for different soil types and geological conditions. Specifically, in loose or soft areas, it may be necessary to reduce the vibration frequency and increase the amplitude to enhance the compaction effect; in harder areas, it may be necessary to increase the vibration frequency and reduce the amplitude to avoid damage to the soil. This targeted adjustment can not only ensure the compaction quality of each partition, but also improve the efficiency and safety of construction.
[0115] In step 2.5, when working in the outermost area of the slopes on both sides of the ditch, the layered and phased compaction method is adopted, and the slope stability is closely monitored. The parameters are adjusted in time to avoid instability, which is a key measure to ensure the safety and stability of the slope. Layered and phased compaction can gradually enhance the density and stability of the soil and prevent the risk of slope collapse or large-scale sliding caused by one-time large-energy compaction. The technical effect of this step is reflected in the following aspects: First, layered compaction can reinforce the soil layer by layer, gradually improve the overall stability and shear strength of the slope, and reduce the possibility of large-scale instability; second, phased compaction can monitor and evaluate after each compaction, dynamically adjust the compaction parameters according to real-time data, ensure that each layer of compaction achieves the expected effect, and timely discover and deal with potential problems; finally, pay close attention to the stability of the slope, monitor the deformation and stress changes of the slope in real time through sensors and monitoring systems, and timely warn and respond to emergencies to ensure construction safety and long-term stability of the slope. The refined management and real-time adjustment in this process not only improve the safety and stability of the slope, but also provide reliable guarantees for the successful implementation of the entire ditch project.
[0116] Further, step 3 includes the following steps:
[0117] Step 3.1, arranging a vibration compaction device with adjustable vibration parameters in the slope area, and effectively transmitting the impact force to the backfill soil layer inside the slope by changing the arrangement angle, vibration frequency and vibration force parameters of the device;
[0118] Step 3.2, according to the geological conditions and compaction requirements of each zone, reasonably set the size and direction of the impact force: in the steep slope area, appropriately increase the horizontal component of the impact force so that more energy is transferred to the inside of the slope; in the flat area, appropriately increase the vertical component to improve the compaction effect of the surface layer;
[0119] Step 3.3: For some slope areas that are difficult to act directly on, reflective devices are arranged to use the reflection effect of the impact force to indirectly guide the vibration energy to the target area for compaction;
[0120] Step 3.4: Monitor the compaction quality of the backfill soil in the slope area in real time through on-site detection feedback, and adjust the impact force parameters in a timely manner to ensure that the compaction quality of the entire slope area meets the design requirements.
[0121] In step 3.1, a vibration compaction device with adjustable vibration parameters is arranged in the slope area. By changing the arrangement angle, vibration frequency and vibration force parameters of the equipment, the impact force is effectively transmitted to the backfill soil layer inside the slope. The technical effects of this process are mainly reflected in the following aspects: first, through the vibration compaction device with adjustable parameters, the geological conditions and compaction requirements of different slope areas can be flexibly responded to, ensuring that the compaction energy can be accurately transmitted to the target area; second, by changing the arrangement angle and vibration parameters of the equipment, the impact force can effectively penetrate into the slope, improving the density and stability of the backfill soil layer; third, this flexible equipment arrangement and parameter adjustment method can reduce the damage to the slope surface during the compaction process and protect the overall structure and morphology of the slope; finally, by optimizing the transmission path of the vibration force, the construction efficiency and quality can be effectively improved, and the construction time and cost can be reduced. The technical effect of this step is to ensure that the backfill soil layer inside the slope can be fully and evenly compacted by accurately controlling the parameters and arrangement of the compaction equipment, thereby enhancing the overall stability and safety of the slope.
[0122] The core of step 3.2 is to reasonably set the size and direction of the impact force according to the geological conditions and compaction requirements of each partition. The technical effect of this step is to achieve targeted compaction control to adapt to different slope areas. Specifically, in steep slope areas, by appropriately increasing the horizontal component of the impact force, more energy can be transferred to the inside of the slope, enhancing the internal structural stability of the slope; while in flat areas, by increasing the vertical component, the compaction effect of the surface layer can be improved, making the surface backfill soil more compact. This differentiated impact force setting method can be flexibly adjusted according to actual needs to ensure that the compaction effect of each area can reach the best state. In addition, by reasonably controlling the direction of the impact force, the adverse effects on the slope structure can be reduced, the construction risk can be reduced, and the overall safety of the slope can be improved. The technical effect is to improve the accuracy and effectiveness of the construction, so that each partition of the slope can receive the most appropriate compaction treatment, ensuring the long-term stability and safety of the slope.
[0123] In step 3.3, for some slope areas that are difficult to act directly, by arranging a reflector and utilizing the reflection effect of the impact force, the vibration energy is indirectly guided to the target area for compaction. The effect of this innovative technology is significantly reflected in solving the "dead corner" problem that is difficult to cover with traditional compaction methods. Through the reflector, the vibration energy can be effectively guided to those internal areas of the slope that are difficult to directly contact, so that the backfill soil in these areas can also be fully compacted. In addition, the use of the reflector can reduce the interference with the surrounding soil and structure, and maintain the overall shape and stability of the slope. The technical effect is to expand the coverage of vibration compaction, improve the comprehensiveness and uniformity of construction, and ensure that each part of the backfill soil can achieve the density and stability required by the design. This indirect compaction method not only improves the construction quality, but also improves the flexibility and adaptability of construction, so that the slope compaction under complex terrain conditions can also be carried out smoothly.
[0124] In step 3.4, the compaction quality of the backfill soil in the slope area is monitored in real time through on-site detection feedback, and the parameters of the impact force are adjusted in time to ensure that the compaction quality of the entire slope area can meet the design requirements. The technical effects of this process are mainly reflected in the following aspects: First, the on-site detection feedback system can provide various data in the compaction process in real time, including the density of the backfill soil, the deformation of the slope, etc., so as to provide construction personnel with immediate construction quality evaluation; secondly, the real-time monitoring and feedback mechanism enables construction personnel to dynamically adjust the compaction parameters according to the actual situation to ensure that the compaction effect of each area can meet the expected standards; in addition, timely adjustment of the impact force parameters can avoid construction quality problems caused by excessive or insufficient compaction, and improve the overall stability and safety of the slope; finally, through this real-time monitoring and adjustment method, the efficiency and quality of construction can be greatly improved, and the cost of rework and repair can be reduced. The technical effect is to ensure that the compaction quality of the backfill soil in the slope area meets the design requirements through efficient and accurate construction quality control, improve the long-term stability and safety of the slope, and provide reliable guarantee for the successful implementation of the entire project.
[0125] Further, step 4 includes the following steps:
[0126] Step 4.1, using an automated monitoring system to collect data from each monitoring point in real time and aggregate it to the control center;
[0127] Step 4.2, based on the monitoring data analysis results, determine the slope stability and backfill loss of each partition, and automatically adjust the compaction parameters of the partition with abnormalities;
[0128] Step 4.3: For normal partitions, fine-tune the compaction parameters according to the slight changes in the monitoring data to optimize the compaction effect;
[0129] Step 4.4, feed the monitoring data to the numerical analysis model to calibrate the model parameters, continuously improve the accuracy of the numerical simulation, and provide a more reliable basis for the pre-determination of the compaction parameters;
[0130] Step 4.5, through the closed-loop feedback of monitoring data, realize adaptive zoning and stratification intelligent control of the whole process, maximize the efficiency of vibration compaction, and ensure the safety of slope and the compaction quality of backfill.
[0131] In step 4.1, an automated monitoring system is used to collect data from each monitoring point in real time and summarize it to the control center. The technical effects of this step are mainly reflected in the following aspects: First, through the automated monitoring system, all-weather monitoring of the construction area can be achieved, and data on key parameters such as slope stability, backfill density, and surface deformation can be obtained in real time to ensure that every detail in the construction process is under control; secondly, real-time data collection and transmission can greatly improve the efficiency of information transmission and reduce the risks caused by data delays; thirdly, after the data is summarized to the control center, it can be centrally processed and analyzed to provide comprehensive and accurate information support for subsequent decision-making. In addition, this real-time monitoring and data aggregation method can significantly improve the level of intelligent construction, and improve the accuracy and response speed of construction through data-driven methods. In general, the application of the automated monitoring system not only improves the efficiency of data collection and processing, but also lays the foundation for real-time control and adjustment of construction parameters, and improves the overall safety and construction quality of the slope compaction project.
[0132] In step 4.2, the slope stability and backfill loss of each partition are determined based on the monitoring data analysis results. For the partition with abnormalities, the compaction parameters of the partition are automatically adjusted. The technical effect is to achieve dynamic and precise construction control. Through real-time data analysis, abnormal conditions of slope stability and backfill loss can be discovered in time, such as excessive displacement of the slope or insufficient density of the backfill. This abnormality detection and early warning mechanism can greatly reduce the risk of slope instability or substandard construction quality. The function of automatically adjusting compaction parameters integrates intelligent and automated technologies into the construction process, realizes instant adjustment of parameters such as compaction energy and vibration frequency, and ensures that the construction parameters of each partition are always in the best state. In this way, not only can we quickly respond to and solve sudden problems in construction, but we can also optimize the compaction effect and improve construction quality and safety.
[0133] In step 4.3, for normal partitions, the compaction parameters are fine-tuned according to the slight changes in the monitoring data to optimize the compaction effect. The technical effects of this process are mainly reflected in the following aspects: First, by analyzing the slight changes in the monitoring data of normal partitions, potential slight change trends can be discovered, and adjustments can be made in advance to prevent the accumulation and expansion of problems; second, by fine-tuning the compaction parameters, the compaction effect can be continuously optimized, so that the density and stability of the backfill soil can reach the optimal state, further improving the construction quality; in addition, this meticulous adjustment method can significantly improve the accuracy and reliability of the construction, ensuring that the compaction effect of each partition can meet the design requirements. The process of fine-tuning parameters can also accumulate a large amount of construction experience data, providing valuable reference and reference for subsequent similar projects. In general, through the monitoring and fine-tuning of slight changes, the continuous optimization of construction quality can be achieved, ensuring that the compaction quality of the backfill soil in the entire slope area is uniform and stable.
[0134] In step 4.4, the monitoring data is fed to the numerical analysis model to correct the model parameters, continuously improve the accuracy of the numerical simulation, and provide a more reliable basis for the pre-determination of the compaction parameters. The technical effect of this process is reflected in the accuracy of data-driven model optimization and parameter preset. Through the feedback of real-time monitoring data, the numerical analysis model can continuously perform parameter correction and optimization, so that the model can more accurately reflect the geological and mechanical characteristics of the actual construction process. After the accuracy of the model is improved, it can provide more reliable compaction parameter presets for subsequent construction, reduce trial and error costs and time, and improve construction efficiency and quality. In addition, through this two-way interaction between data and models, a closed-loop optimization system can be formed, so that every link in the construction process can obtain the most optimized parameter support and decision-making basis, and improve the scientificity and intelligence level of the entire construction project.
[0135] In step 4.5, the closed-loop feedback of monitoring data is used to realize the adaptive partition and layered intelligent control of the whole process, maximize the efficiency of vibration compaction, and ensure the safety of slopes and the compaction quality of backfill. The technical effect is to comprehensively improve the intelligence and automation level of the construction process. The closed-loop feedback system can collect and analyze monitoring data in real time, dynamically adjust construction parameters according to the analysis results, and realize adaptive control of the whole process. This intelligent control system can significantly improve construction efficiency and quality, and reduce the possibility of manual intervention and operational errors. Through the adaptive control of partition and layer, the optimal compaction strategy can be implemented according to the specific conditions of different regions to ensure that the compaction effect of each partition meets the design requirements. In addition, the closed-loop feedback system can also continuously monitor the stability of the slope and the density of the backfill, timely warn and deal with potential risks, and ensure the long-term safety and stability of the slope. In general, through the closed-loop feedback of monitoring data, the intelligent control of the whole process can be realized, which can maximize the efficiency of vibration compaction, improve construction quality, ensure slope safety, and provide solid technical support for the successful implementation of engineering projects.
[0136] Further, step 5 includes the following steps:
[0137] Step 5.1: Use in-situ testing methods to conduct density tests in each partition and each layer to ensure that the design requirements are met;
[0138] Step 5.2, using the dynamic penetration method to detect whether the bearing capacity of the backfill soil meets the design standards;
[0139] Step 5.3, using settlement observation points to continuously monitor the deformation of the slope and backfill soil and assess their long-term stability;
[0140] Step 5.4, compare the actual compaction effect with the predicted result in step 1 and analyze the reasons for the difference;
[0141] Step 5.5: Based on the quality acceptance results and data analysis, optimize and adjust the compaction process parameters and zoning and stratification scheme to form a more accurate construction guidance plan.
[0142] In step 5.1, the in-situ test method is used to test the density of each partition and each layer to ensure that the design requirements are met. The technical effects of this process are mainly reflected in the following aspects: First, the in-situ test method can directly reflect the density of the construction area, provide accurate field data, and avoid errors caused by sampling tests; second, by performing density tests in each partition and each layer, the density of the entire slope and backfill soil can be fully understood to ensure that each area and layer meets the design requirements. In-situ test methods such as nuclear densitometers and sand injection methods can quickly and accurately detect the density of backfill soil, provide instant test results, and facilitate instant adjustment and optimization during the construction process. Overall, the application of in-situ test methods ensures the quality of backfill soil and the stability of the slope, provides reliable data support for subsequent construction and acceptance, and improves the accuracy and reliability of construction.
[0143] In step 5.2, the dynamic penetration method is used to detect whether the bearing capacity of the backfill soil meets the design standards. The technical effects of this method are mainly reflected in the following aspects: First, the dynamic penetration method is an in-situ test method widely used in geotechnical testing. It directly reflects the bearing capacity and density of the soil layer by measuring the resistance of the cone head penetrating into the soil layer. Secondly, by testing the bearing capacity of the backfill soil, the compaction effect during the construction process can be verified to ensure that the backfill soil has sufficient bearing capacity and meets the design standard requirements. The dynamic penetration method can also provide a continuous profile of the soil layer to help construction personnel understand the layered structure and density distribution of the backfill soil, providing detailed data support for the comprehensive evaluation of the construction quality. In addition, through the detection of this method, deficiencies in the construction can be discovered and corrected in a timely manner, and the compaction process and parameters can be optimized to ensure the construction quality and the long-term stability of the slope.
[0144] In step 5.3, the deformation of the slope and backfill soil is continuously monitored by using the settlement observation points to evaluate their long-term stability. The technical effects of this step are mainly reflected in the following aspects: First, through the layout and continuous monitoring of the settlement observation points, the deformation of the slope and backfill soil can be understood in real time, and potential stability problems can be discovered in time. Secondly, the settlement observation data can provide the settlement changes of the slope and backfill soil in different time periods, providing reliable data support for the evaluation of their long-term stability. Through this continuous monitoring, the abnormal settlement trend of the slope or backfill soil can be discovered early, and corresponding remedial measures can be taken to prevent potential instability risks. In addition, the settlement observation data can also be used to verify and optimize the numerical model and improve the accuracy and reliability of the numerical simulation. In general, the use of settlement observation points for continuous monitoring helps to ensure the long-term stability of the slope and backfill soil, and provide protection for the safety and stability of the entire project.
[0145] In step 5.4, the actual compaction effect is compared with the predicted result in step 1, and the reasons for the difference are analyzed. The technical effects of this step are mainly reflected in the following aspects: First, by comparing the actual compaction effect with the predicted results of numerical simulation, the accuracy and reliability of the numerical simulation can be evaluated, and the differences between the actual construction and the predicted results can be found. Secondly, analyzing the reasons for the difference can help construction personnel understand the possible problems and deficiencies in the construction process, such as insufficient compaction energy and improper construction technology. Through this analysis, improvement suggestions and optimization directions can be provided for subsequent construction, and the accuracy and quality of construction can be improved. In addition, through comparison and analysis, rich construction data and experience can be accumulated, providing valuable reference and reference for numerical simulation and construction guidance of similar projects. Overall, this step improves the scientificity and accuracy of construction through comparison and analysis, and provides reliable guarantee for project quality and safety.
[0146] In step 5.5, based on the quality acceptance results and data analysis, the compaction process parameters and the partition and layering scheme are optimized and adjusted to form a more accurate construction guidance plan. The technical effects of this step are mainly reflected in the following aspects: First, through the quality acceptance results and data analysis, the construction effect can be comprehensively evaluated and the links that need to be improved and optimized can be found. Secondly, based on these analysis results, the compaction process parameters and the partition and layering scheme are optimized and adjusted to improve the scientificity and rationality of the construction and ensure that each partition and layer can achieve the best compaction effect. Through this optimization and adjustment, the construction quality and efficiency can be effectively improved, and the problems and rework that may occur during the construction process can be reduced. In addition, the formation of a more accurate construction guidance plan can provide detailed operation guidance and technical support for subsequent similar projects, and improve the overall construction level and project quality. In general, through optimization and adjustment, the accuracy and reliability of the construction are ensured, providing a solid technical guarantee for the successful implementation of the project.
[0147] Finally, it should be pointed out that the above embodiments are only used to illustrate the technical solutions of the present invention, rather than to limit them. Although the present invention has been described in detail with reference to the above embodiments, a person skilled in the art should understand that the technical solutions described in the above embodiments can still be modified, or some of the technical features can be replaced by equivalents; and these modifications or replacements do not make the essence of the corresponding technical solutions deviate from the spirit and scope of the technical solutions of the embodiments of the present invention.
Claims
1. A dynamic optimization construction method for ditch compaction, characterized in that: The following steps are involved: Step 1: Based on numerical simulation analysis, the interaction between the slope and backfill under vibration compaction is predicted, and the potential deformation of the slope and the degree of lateral loss of backfill are evaluated. Based on this, the ditch area is divided into multiple zones and layers. Step 2: First, perform high-energy vibration compaction in the central bottom area to form a compacted base, then gradually expand the compaction range to the slope areas on both sides, adjusting the compaction energy and process parameters according to the characteristics of each zone; Step 3: In the slope areas on both sides of the ditch, the direction and intensity of the impact force are controlled to effectively transfer the compaction energy to the slope area, thereby ensuring the compaction quality of the backfill soil in the slope area; Step 4: Real-time monitoring of slope stability and lateral loss of backfill material, and dynamic optimization and adjustment of compaction parameters for each zone based on the monitoring data to achieve adaptive zone and layer control; Step 5: After completing the vibration compaction work in each zone and layer, conduct a comprehensive assessment of the compaction quality of the ditch backfill soil.
2. A dynamic optimization construction method for ditch compaction according to claim 1, characterized in that: Step 1 includes the following steps: Step 1.1: Based on the finite element numerical calculation method, the geometric model of the slope and backfill soil is established by considering the influence of soil layer distribution, slope morphology and groundwater level; Step 1.2: Introduce the dynamic characteristics of the vibration compaction load into the geometric model to simulate the effect of vibration on the slope and backfill soil; Step 1.3: Conduct in-depth analysis of the numerical simulation output to predict slope deformation and stability changes under vibration, and assess the lateral loss tendency of backfill soil under vibration; In step 1.4, based on the prediction results, the ditch area is divided into several zones according to the magnitude of deformation and loss tendency. The geological conditions and expected responses within each zone are relatively uniform, and each zone is layered according to depth.
3. A dynamic optimization construction method for ditch compaction according to claim 2, characterized in that: The deformation of the slope under vibration is expressed by the following formula: u = K -1 F, where u is the displacement vector, i.e., the deformation of the slope under vibration; K is the stiffness matrix; and F is the vibration load. The stability change of the slope is evaluated by calculating the safety factor FOS, the specific formula is: Where c′ is the effective cohesion; σ is the normal stress; φ′ is the effective internal friction angle; τ is the shear stress acting on the sliding surface; The lateral loss of backfill soil under vibration is evaluated by lateral deformation and shear stress. The specific formula is: τ x =G·γ x , where δ x is the lateral deformation; u x (t′) is the lateral velocity that changes with time; the variable of t′ integration represents the time point from the initial time 0 to a certain time; dt′ represents the small time change at time t′; τ x is the lateral shear stress; G is the shear modulus; γ x is the lateral shear strain.
4. A dynamic optimization construction method for ditch compaction according to claim 2, characterized in that: Step 1.4 includes the following steps: Based on the spatial distribution characteristics of deformation and loss tendency, combined with cluster analysis method, the ditch is divided into several major zones; Taking into account the geological conditions and expected response characteristics, the zones are optimized and adjusted to ensure that the conditions within each zone are relatively uniform; For each zone, depth stratification is performed based on soil quality changes and compaction difficulty factors; Develop a complete zoning and stratification scheme, assign unique identifiers to each zone and layer, and summarize their key characteristics; Establish a dynamic adjustment mechanism to optimize the plan in a timely manner according to actual conditions during the construction process.
5. A dynamic optimization construction method for ditch compaction according to claim 4, characterized in that: Based on the spatial distribution characteristics of deformation and loss tendency, combined with cluster analysis methods, the ditch is divided into several major zones, including the following steps: The deformation and loss tendency data of the ditch area are collected to form a data set. Each data point contains two features: deformation feature X i and churn propensity characteristic Y i ; K-means clustering was selected as the clustering algorithm. The goal of clustering was to divide the data points into several groups so that the data points within each group are similar to each other, that is, the ditch areas are similar in deformation and loss tendency, while the similarity of data points between groups is low. Using Euclidean distance as a measure of similarity between data points, the clustering process is expressed as the following objective function: Among them, X i is the feature vector of the i-th data point, including the deformation feature X i and churn propensity characteristic Y i ;μ j is the eigenvector of the jth cluster center; C is the set of clusters, including all cluster centers μ j ; After clustering is completed, each ditch area data point is assigned to a cluster center μ j The partition represented by it realizes the partition of the ditch area.
6. A dynamic optimization construction method for ditch compaction according to claim 4, characterized in that: The depth-wise layering approach includes the following steps: Divide the soil into layers based on depth, each layer having similar compaction characteristics and vibration response; Quantitatively describe the characteristics of each layer, including factors related to compaction difficulty; An optimization model is established to determine the best stratification scheme. The optimization model is described by the following objective function: Where d represents the depth, that is, the range from the surface to the depth d; X k (d) is the characteristic vector of the kth layer of soil at depth d, including the index of the compaction difficulty factor; X target is the ideal value of the target compaction characteristic; L is the variable used to minimize the objective; Layer(d) represents the set of selected soil layers at depth d; By solving the above optimization problem, the best layering scheme Layer(d) is determined.
7. A dynamic optimization construction method for ditch compaction according to claim 1, characterized in that: Step 2 includes the following steps: Arrange several vibrating compactors in the central bottom area of the side ditch and adjust them to high vibration energy levels to perform compaction operations to form a central base layer; After the central base layer is compacted, the compaction range is gradually expanded outward along the slope areas on both sides of the ditch; Based on the results of numerical simulation analysis, differentiated compaction strategies are adopted for different zones: for zones with high deformation and loss tendency, the vibration energy is appropriately reduced to reduce the adverse impact on the slope; for relatively stable zones, the vibration energy is moderately increased to improve the compaction effect; Adjust the layout and operating mode parameters of the compaction machinery to ensure the compaction quality of each zone; When working in the outermost areas of the slopes on both sides of the ditch, adopt a layered and staged compaction method, pay close attention to the stability of the slope, and adjust parameters in time to avoid instability.
8. A dynamic optimization construction method for ditch compaction according to claim 1, characterized in that: Step 3 includes the following steps: Arrange vibrating compaction equipment with adjustable vibration parameters in the slope area. By changing the arrangement angle, vibration frequency and vibration force parameters of the equipment, the impact force is effectively transmitted to the backfill soil layer inside the slope. The magnitude and direction of the impact force should be reasonably set according to the geological conditions and compaction requirements of each zone: in steep slope areas, the horizontal component of the impact force should be appropriately increased to transfer more energy to the interior of the slope; in flat areas, the vertical component should be appropriately increased to improve the surface compaction effect; For some slope areas that are difficult to act directly on, reflective devices are arranged to utilize the reflection effect of the impact force to indirectly guide the vibration energy to the target area for compaction; Through on-site inspection feedback, the compaction quality of the backfill soil in the slope area is monitored in real time, and the impact force parameters are adjusted in a timely manner to ensure that the compaction quality of the entire slope area meets the design requirements.
9. A dynamic optimization construction method for ditch compaction according to claim 1, characterized in that: Step 4 includes the following steps: Adopting an automated monitoring system to collect data from each monitoring point in real time and aggregate it to the control center; Based on the monitoring data analysis results, the slope stability and backfill loss of each zone are judged, and the compaction parameters of the zone with abnormalities are automatically adjusted; For normal partitions, fine-tune the compaction parameters based on slight changes in monitoring data to optimize the compaction effect; Feeding monitoring data into the numerical analysis model to calibrate model parameters, continuously improving the accuracy of numerical simulations and providing a more reliable basis for pre-determining consolidation parameters; Through closed-loop feedback of monitoring data, adaptive zoning and layered intelligent control of the entire process is achieved, maximizing the effectiveness of vibration compaction and ensuring slope safety and backfill compaction quality.
10. A dynamic optimization construction method for ditch compaction according to claim 1, characterized in that: Step 5 includes the following steps: Use in-situ testing methods to conduct density tests in each partition and each layer to ensure that the design requirements are met; Use dynamic penetration method to test whether the bearing capacity of backfill soil meets the design standards; Use settlement observation points to continuously monitor the deformation of slopes and backfill soil and assess their long-term stability; Compare the actual compaction effect with the predicted result in step 1 and analyze the reasons for the difference; Based on the quality acceptance results and data analysis, the compaction process parameters and zoning and stratification plans are optimized and adjusted to form a more accurate construction guidance plan.
Citation Information
Cited By
Variable resonant frequency hydraulic vibration control system and method based on DSP
CN119247858A
Stirring method and system for TRD
CN119784308A
Statistical analysis method and system for civil engineering test data of hydropower engineering
CN120235363A
Rectangular pipe gallery layered backfill soil monitoring method and monitoring system
CN120719645A
Rectangular pipe gallery layered backfill soil monitoring method and monitoring system
CN120719645B