Excavation method for asymmetric foundation pits on two sides of arc subway tunnel

By using a method of zoned and layered progressive excavation and step-by-step unloading, the deformation risk caused by uneven load in the asymmetric foundation pit excavation of curved subway tunnels was solved, enabling faster improvement of the stiffness and bearing capacity of the retaining structure and reducing the impact of construction dynamic disturbances on the tunnel.

CN118933015APending Publication Date: 2024-11-12THE FOURTH OF CHINA EIGHTH ENG BUREAU
View PDF 0 Cites 0 Cited by

Patent Information

Application Number
CN202411400514.6
Authority / Receiving Office
CN · China
Patent Type
Applications(China)
Current Assignee / Owner
Filing Date
2024-10-09
Publication Date
2024-11-12

AI Technical Summary

Technical Problem

Curved subway tunnels have low structural stiffness and poor resistance to external loads. Asymmetric excavation of the foundation pit leads to uneven load changes, increasing the risk of tunnel deformation and displacement, which is difficult to mitigate effectively with existing technologies.

Method used

The method of zoned and layered progressive excavation and step-by-step unloading was adopted. The earthwork construction sequence was set by simulation calculation, and the load was balanced by the reserved earthwork to avoid unilateral overload and mitigate the impact of construction dynamic disturbance on the operating subway tunnel.

Benefits of technology

It reduces the deformation risk of the foundation pit retaining structure and the operating subway tunnel, improves the overturning stiffness and axial bearing strength of the foundation pit retaining structure, reduces the exposure time without axial force support, and reduces the disaster-causing effect of construction dynamic disturbance on the tunnel.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN118933015A_ABST
    Figure CN118933015A_ABST
Patent Text Reader

Abstract

The invention discloses an excavation method for asymmetric foundation pits on the two sides of an arc subway tunnel. The excavation method comprises the steps that S100, a foundation pit is divided into a plurality of sections; s200, dividing the section into a plurality of running water construction areas; and S300, the running water construction area is divided into a plurality of running water construction sections. In the scheme, through zoning and layering recursive excavation and step-by-step unloading, the deformation risk of a foundation pit support structure and an operation subway tunnel caused by the influence of the space-time effect in the foundation pit soil body excavation construction process is reduced, the axial-force-free support exposure time of the foundation pit is shortened, and the construction efficiency is improved. The anti-overturning rigidity and the axial bearing strength of the foundation pit support structure can be improved more quickly; the earthwork construction sequence is set through simulation calculation, the area with unbalanced lateral pre-excavation loads is set as a post-excavation section, loads on the two sides are balanced through indwelling earthwork so as to balance unloading space-time responses on the two sides of a tunnel, displacement deformation disasters caused by single-side concentrated overload are avoided, and the construction efficiency is improved. And the disaster-causing effect of construction dynamic disturbance on an operation subway tunnel structure is relieved.