Excavation method for asymmetric foundation pits on two sides of arc subway tunnel
By using a method of zoned and layered progressive excavation and step-by-step unloading, the deformation risk caused by uneven load in the asymmetric foundation pit excavation of curved subway tunnels was solved, enabling faster improvement of the stiffness and bearing capacity of the retaining structure and reducing the impact of construction dynamic disturbances on the tunnel.
Patent Information
- Application Number
- CN202411400514.6
- Authority / Receiving Office
- CN · China
- Patent Type
- Applications(China)
- Current Assignee / Owner
- Filing Date
- 2024-10-09
- Publication Date
- 2024-11-12
AI Technical Summary
Curved subway tunnels have low structural stiffness and poor resistance to external loads. Asymmetric excavation of the foundation pit leads to uneven load changes, increasing the risk of tunnel deformation and displacement, which is difficult to mitigate effectively with existing technologies.
The method of zoned and layered progressive excavation and step-by-step unloading was adopted. The earthwork construction sequence was set by simulation calculation, and the load was balanced by the reserved earthwork to avoid unilateral overload and mitigate the impact of construction dynamic disturbance on the operating subway tunnel.
It reduces the deformation risk of the foundation pit retaining structure and the operating subway tunnel, improves the overturning stiffness and axial bearing strength of the foundation pit retaining structure, reduces the exposure time without axial force support, and reduces the disaster-causing effect of construction dynamic disturbance on the tunnel.
Smart Images

Figure CN118933015A_ABST