Pile foundation detection equipment and method based on unloading point method

By designing a pile foundation detection equipment for unloading point method including support, lifting, loading, guidance and detection mechanisms, the accuracy problem of detecting pile foundations of different depths and sizes in the prior art is solved, and the pile foundations in clay are realized and effective detection of medium and long pile foundations provides more accurate bearing capacity analysis.

CN118933096APending Publication Date: 2024-11-12NINGBO SANJIANG TESTING CO LTD
View PDF 0 Cites 0 Cited by

Patent Information

Application Number
CN202411286500.6
Authority / Receiving Office
CN · China
Patent Type
Applications(China)
Current Assignee / Owner
Filing Date
2024-09-13
Publication Date
2024-11-12

AI Technical Summary

Technical Problem

The existing unloading point method pile foundation detection method is difficult to provide accurate results when detecting pile foundations of different depths and sizes, and the pile foundation bearing capacity detection and medium-length pile foundation detection in clay are poor, and there is no detection result. Determinism.

Method used

A pile foundation detection equipment based on the unloading point method is designed, including a support mechanism, a lifting mechanism, a load mechanism, a guide mechanism, a switching mechanism and a detection mechanism. Through the cooperation of the switching parts and a buffer mechanism, it can be based on the depth and size of the pile foundation. Adjust the position of the load part, form instantaneous pressure and repeatedly impact the pile foundation to obtain pile foundation change data.

Benefits of technology

It improves the detection adaptability of pile foundations of different types, depths and sizes, ensures the accuracy and stability of the detection results, and can more accurately analyze the disease location and bearing capacity of pile foundations.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN118933096A_ABST
    Figure CN118933096A_ABST
Patent Text Reader

Abstract

The invention relates to the field of pile foundation detection, and provides pile foundation detection equipment based on an unloading point method, which comprises a support mechanism, a lifting mechanism, a loading mechanism, a guide mechanism, a switching mechanism, a buffer mechanism and a detection mechanism, the supporting mechanism is arranged in the vertical direction, the lifting mechanism is installed on one side of the supporting mechanism, and the lifting end is located at the top of the supporting mechanism; a guiding space is formed in the middle of the guiding mechanism, and the two sides of the guiding mechanism are connected with the supporting mechanism. The switching mechanism is connected with the top of the supporting mechanism; the loading mechanism is connected with the switching mechanism in a sliding manner; the buffering mechanism is located in the guiding mechanism, slides along the guiding space and is connected with the top of the pile foundation. The detection mechanism is installed on the supporting mechanism and is aligned with the pile foundation. The method has the effects that adaptive detection is provided for different pile foundations, and the accuracy of detection data is improved. In addition, the invention further provides a detection method.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The present application relates to the field of pile foundation detection, and in particular to a pile foundation detection device and a detection method based on an unloading point method. Background Art

[0002] Pile foundation is one of the most important foundation forms in bridge engineering. Whether the bearing capacity of pile foundation meets the design requirements is related to the safety of bridge structure. At present, the bearing capacity detection of pile foundation mainly includes two main methods: static load test method and high strain dynamic test method.

[0003] At present, the unloading point method of pile foundation detection is an analysis method in the static and dynamic pile foundation detection technology based on explosives. This method is often used in static and dynamic pile foundation detection because of its concise and clear theory. Due to the high degree of danger of explosive technology, static and dynamic pile foundation detection technology has not been used on a large scale in my country. The unloading point method of pile foundation detection technology of static and dynamic pile foundation detection equipment is more suitable for the detection of medium and short pile foundations in sand. For the bearing capacity detection of pile foundations in clay or the detection of medium and long pile foundations, it is still necessary to make a comprehensive judgment based on the soil environment and accumulated experience to test the bearing capacity of the pile foundation and apply it to the unloading point method.

[0004] The unloading point pile foundation detection method uses rapid load detection equipment. When this equipment detects pile foundations of different depths and sizes, it is difficult to provide pile foundations that are suitable for the corresponding depths and sizes, and the accuracy of the detection results cannot be guaranteed. Summary of the invention

[0005] In order to improve the above-mentioned problems, the present application provides a pile foundation detection device and a detection method based on the unloading point method.

[0006] The present application provides a pile foundation detection device and detection method based on the unloading point method, which adopts the following technical solutions: A pile foundation detection device based on an unloading point method comprises a supporting mechanism, a lifting mechanism, a load-bearing mechanism, a guiding mechanism, a switching mechanism, a buffer mechanism and a detecting mechanism; the supporting mechanism is arranged in a vertical direction, the lifting mechanism is installed on one side of the supporting mechanism, and the lifting end is located at the top of the supporting mechanism; a guiding space is formed in the middle of the guiding mechanism, and both sides are connected to the supporting mechanism; the switching mechanism is connected to the top of the supporting mechanism; the load-bearing mechanism is slidably connected to the switching mechanism; the buffer mechanism is located in the guiding mechanism, slides along the guiding space, and is connected to the top of the pile foundation; the detecting mechanism is installed on the supporting mechanism and is aligned with the pile foundation; the switching mechanism comprises a first switching member and a second switching member, the first switching member is installed on the top of the supporting mechanism, and the first switching member is provided with a first switching groove; the second switching member is connected to the lifting end, and the second switching member is provided with a second switching groove; when the first switching member and the second switching member are docked, the first switching groove and the second switching groove are docked; the second switching member is slidably connected to the guiding mechanism; the load-bearing mechanism comprises a plurality of load-bearing members, and the plurality of load-bearing members slide along the first switching groove and the second switching groove.

[0007] By adopting the above technical solution, the lifting mechanism drives the second switching member to the top of the supporting mechanism, so that the first switching groove is connected with the second switching groove. According to the depth, size and style of the pile foundation on site, the corresponding load-bearing member is switched to the second switching groove, and the other load-bearing members are located in the first switching groove. Then, under the lifting mechanism, the load-bearing member drives the second switching member to descend rapidly, and the second switching member descends along the guide mechanism to ensure the accurate descending position of the load-bearing member. The load-bearing member collides with the buffer mechanism to form instantaneous pressure, and the buffer mechanism transmits the pressure to the top of the pile foundation. This is repeated, and the pile foundation is detected by the detection mechanism to obtain the pile foundation change data after the collision.

[0008] Optionally, the second switching member is also provided with two fixing openings, which are connected to the second switching groove; the second switching member is also provided with a fixing portion; the fixing portion is provided with two fixing ends, which pass through the fixing openings and extend to the second switching groove; the fixing portion is also provided with a fastening portion, which is screwed to the second switching member.

[0009] By adopting the above technical solution, the fixed end of the fixing part passes through the fixing mouth and closes the slot of the second switching slot. After the fastening part is screwed together with the second switching member, the load-bearing member located on the second switching member is fixed in the second switching slot and cannot be detached, thereby further ensuring the stability of the position of the load-bearing member during the detection process.

[0010] Optionally, the lifting mechanism includes a lifting drive member, a pulling member and a plurality of guide wheels; the lifting drive member and the plurality of guide wheels are both installed on the supporting mechanism; the pulling member is wound around the lifting drive member, and after passing around the plurality of guide wheels in turn, is connected to the second switching member.

[0011] By adopting the above technical solution, the pulling member is wrapped around the lifting drive member, and the lifting drive member drives the pulling member to be continuously wrapped, so that the pulling member changes the lifting path along the guide wheel, and pulls the second switching member close to the top of the supporting mechanism, while keeping the first switching groove and the second switching groove in a docking state. When the load-bearing member of the required weight moves into the second switching groove, the pulling member under the lifting drive member is lifted, so that the load-bearing member loses the pulling of the pulling member and drives the second switching member to descend, thereby entering the guide space to collide with the buffer mechanism.

[0012] Optionally, the support mechanism is further provided with a positioning member, a positioning groove is formed on a side of the second switching member close to the positioning member, and the positioning member is plugged into the positioning groove.

[0013] By adopting the above technical solution, when the second switching member is driven by the pulling member to rise, the positioning groove on the second switching member is plugged into the positioning member to ensure that the rising position of the second switching member is accurate, so that the first switching groove and the second flower cutting groove can be accurately connected.

[0014] Optionally, the support mechanism includes a first support member, a second support member and a load-bearing member; the first support member and the second support member are connected to the ground in a vertical direction; and the load-bearing member is installed on the top of the first support member and the second support member.

[0015] By adopting the above technical solution, the first support member and the second support member are used to provide support by contacting the ground, and then the load-bearing member is used to provide installation space for the guide wheels of the lifting mechanism and the switching mechanism and other structures, so as to ensure the stable operation of each mechanism during the detection process.

[0016] Optionally, both the first supporting member and the second supporting member are slidably connected with a stabilizing member, and the stabilizing member is inserted into the ground along the vertical direction.

[0017] By adopting the above technical solution, the overall support area of ​​the support mechanism can be increased by using the stabilizing member, thereby improving the overall stability of the support mechanism and avoiding the position deviation of the support mechanism during the detection process.

[0018] Optionally, the first support member and the second support member are both divided into the first telescopic section and the second telescopic section along the vertical direction; the second telescopic section is slidably connected to the first telescopic section; a locking member is provided between the first telescopic section and the second telescopic end; and the load-bearing member is installed on the top of the second telescopic section.

[0019] By adopting the above technical solution, the overall height of the first support member and the second support member is adjusted by sliding the second telescopic section along the first telescopic section, so that the height of the load-bearing member is adjusted. After the adjustment, the positions of the first telescopic section and the second telescopic section are fixed by the locking member to achieve the fixed height. The gravitational potential energy of load-bearing members at different heights is different. Therefore, the height of the load-bearing member can be adjusted to further adapt to pile foundations of different depths, sizes or styles.

[0020] Optionally, the guide mechanism includes a guide cylinder and a connecting piece; one end of the connecting piece is connected to the outer wall of the guide cylinder, and the other end is connected to the supporting mechanism, and the guide cylinder contains a guide space.

[0021] By adopting the above technical solution, the connecting piece connects the guide cylinder with the supporting mechanism, so that the position of the guide cylinder is fixed. When the second switching piece descends, it enters the guide cylinder and moves along the guide space in the guide cylinder, ensuring the accuracy of the lifting and lowering path of the second switching piece.

[0022] Optionally, the guide cylinder is composed of a plurality of first guide plates and a plurality of second guide plates, and the first guide plates and the second guide plates are arranged at intervals; a first fixing ring is arranged at the bottom of the plurality of first guide plates, and the first fixing ring connects all the first guide plates as a whole; a second fixing ring is arranged at the top of the second guide plate, and the second fixing ring connects all the second guide plates as a whole; the first guide plate is connected to the first telescopic section through the connecting member; and the second guide plate is connected to the second telescopic section through the connecting member.

[0023] By adopting the above technical solution, when the second telescopic section drives the second guide plate and the second fixed ring to rise through the connecting piece, the first telescopic section drives the first guide plate and the first fixed ring to remain in position through the connecting piece, so that the second guide plate and the first guide plate are staggered in rising and falling, extending the guide length and adapting to load-bearing parts of different heights without affecting the guiding effect.

[0024] A detection method comprises the following steps: Collect on-site pile foundation and soil information, and check building, design, and construction information to ensure that the survey data is accurate; Move the testing equipment to the pile foundation to be tested and adjust the testing equipment according to the survey data; According to the depth, size or style of the pile foundation, the corresponding load-bearing member is switched along the first switching groove and the second switching groove to the second switching groove, and the other load-bearing members are pushed into the first switching groove; Start the testing agency to test the pile foundation; The lifting mechanism is started, the lifting mechanism lowers the second switching member, the second switching member and the load-bearing member hit the buffer mechanism along the guide mechanism, and the buffer mechanism hits the pile foundation synchronously; According to the impact of the pile foundation, the testing agency conducts data testing and collects data information on the pile foundation; Repeat the above steps several times to obtain multiple groups of control data, and the testing agency collects and draws data curves; Based on the data information from the testing agency’s mobile testing equipment and the pile foundation after it is installed, data integration and calculation are performed to comprehensively analyze the location of the pile foundation defects and the specific types of defects, and obtain comprehensive performance data on the integrity and bearing capacity of the pile foundation.

[0025] By adopting the above technical solution, the detection equipment is used to detect pile foundations of different types, depths and sizes, which has strong adaptability and the obtained data information is more accurate.

[0026] In summary, the present application includes at least one of the following beneficial technical effects: 1. The lifting mechanism drives the second switching member to the top of the supporting mechanism, so that the first switching slot is connected to the second switching slot. According to the depth, size and style of the on-site pile foundation, the corresponding load-bearing member is switched to the second switching slot, and other load-bearing members are located in the first switching slot. Then, the load-bearing member drives the second switching member to descend rapidly under the lifting mechanism. The second switching member descends along the guide mechanism to ensure the accurate descending position of the load-bearing member. The load-bearing member collides with the buffer mechanism to form instantaneous pressure, and the buffer mechanism transmits the pressure to the top of the pile foundation. This is repeated, and the pile foundation is inspected by the detection mechanism to obtain the pile foundation change data after the collision; 2. The fixed end of the fixing part passes through the fixing opening and closes the notch of the second switching slot. The fastening part is screwed with the second switching member so that the load-bearing member on the second switching member is fixed in the second switching slot and cannot be separated, thereby further ensuring the stability of the position of the load-bearing member during the detection process; 3. The pulling member is wound around the lifting driving member, and the lifting driving member drives the pulling member to be wound continuously, so that the pulling member changes the lifting path along the guide wheel, and pulls the second switching member to be close to the top of the supporting mechanism, while keeping the first switching groove and the second switching groove in a docking state. When the load-bearing member of the required weight moves into the second switching groove, the pulling member under the lifting driving member is lifted, so that the load-bearing member loses the pulling of the pulling member and drives the second switching member to descend, thereby entering the guide space to collide with the buffer mechanism; 4. When the second switching member is driven by the pulling member to rise, the positioning groove on the second switching member is plugged into the positioning member to ensure that the rising position of the second switching member is accurate, so that the first switching groove and the second flower cutting groove can be accurately docked. BRIEF DESCRIPTION OF THE DRAWINGS

[0027] Figure 1This is a schematic diagram of the first structure of a detection device in one embodiment of the present application; Figure 2 is a schematic diagram of the structure of the second switching member in some embodiments of the present application; Figure 3 is a second structural schematic diagram of a detection device in some embodiments of the present application; Figure 4 is a third structural schematic diagram of the detection device in some embodiments of the present application; Figure 5 is a schematic diagram of a three-dimensional structure of a first guide plate and a second guide plate in a separated state in some embodiments of the present application; 1. The markings in the accompanying drawings are: 1. supporting mechanism, 11. first supporting member, 12. second supporting member, 13. load-bearing member, 14. stabilizing member, 15. first telescopic section, 16. second telescopic section, 17. locking member, 18. locking hole, 2. lifting mechanism, 21. lifting drive member, 22. pulling member, 23. guide wheel, 24. positioning member, 3. load-bearing mechanism, 31. load-bearing member, 4. guiding mechanism, 41. guide cylinder, 411. first guide plate, 412. second guide plate, 413. first fixing ring, 414. second fixing ring, 42. connecting member, 5. switching mechanism, 51. first switching member, 511. first switching groove, 52. second switching member, 521. second switching groove, 522. fixing port, 523. fixing part, 524. fastening part, 525. positioning groove, 6. buffer mechanism, 7. detection mechanism. DETAILED DESCRIPTION

[0028] The following is an explanation of the implementation of the present application by specific examples, and those skilled in the art can easily understand other advantages and effects of the present application from the information disclosed in the present application. The present application can also be implemented or applied through other different specific implementations, and the details in the present application can also be modified or changed in various ways according to different viewpoints and application systems without departing from the spirit of the present application. It should be noted that the embodiments in the present application and the features in the embodiments can be combined with each other without conflict.

[0029] The following is a detailed description of the embodiments of the present application with reference to the accompanying drawings so that those skilled in the art can easily implement the present application. The present application can be embodied in a variety of different forms and is not limited to the embodiments described herein.

[0030] In the representations of the present application, the representations with reference to the terms "one embodiment", "some embodiments", "examples", "specific examples", or "some examples" etc. mean that the specific features, structures, materials or characteristics represented in conjunction with the embodiment or example are included in at least one embodiment or example of the present application. Moreover, the represented specific features, structures, materials or characteristics may be combined in any one or more embodiments or examples in a suitable manner. In addition, those skilled in the art may combine and combine the different embodiments or examples represented in the present application and the features of the different embodiments or examples, unless they contradict each other.

[0031] In addition, the terms "first" and "second" are only used to indicate the target, and cannot be understood as indicating or implying relative importance or implicitly indicating the number of the indicated technical features. Therefore, the features defined as "first" and "second" may explicitly or implicitly include at least one of the features. In the representation of this application, the meaning of "plurality" is two or more, unless otherwise clearly and specifically defined.

[0032] Throughout the specification, when a device is said to be "connected" to another device, this includes not only the case of "direct connection" but also the case of "indirect connection" by placing other elements therebetween. In addition, when a device is said to "include" a certain component, unless otherwise stated, it does not exclude other components, but means that other components may be included.

[0033] The following is combined with Figure 1 -Attached Figure 5 , further details of this application are given.

[0034] The embodiments of the present application disclose a pile foundation detection device and a detection method based on the unloading point method.

[0035] A pile foundation detection equipment based on the unloading point method. The unloading point method pile foundation detection technology is to obtain a second py curve of the inspected pile foundation through a displacement time-history curve, an acceleration time-history curve, and a force time-history curve, and compare the two py curves to comprehensively obtain the bearing capacity of the inspected pile foundation. Then, combined with the disease position determined after the inspected pile foundation is detected by the low-strain pile foundation detection technology and the displacement time-history curve, the acceleration time-history curve, the force time-history curve, and the force traveling wave curve, the disease type at the disease position can be analyzed and the corresponding comprehensive evaluation of the integrity and bearing capacity of the inspected pile foundation can be output.

[0036] It is necessary to obtain these displacement time-history curves, acceleration time-history curves, and force time-history curves in order to perform pile foundation testing using the unloading point method, and it is necessary to use the pile foundation testing equipment in this application to provide testing to obtain data.

[0037] refer to Figure 1As shown, the pile foundation detection equipment of the present application includes a supporting mechanism 1, a lifting mechanism 2, a load-bearing mechanism 3, a guiding mechanism 4, a switching mechanism 5, a buffer mechanism 6 and a detection mechanism 7; the supporting mechanism 1 is arranged in a vertical direction, and the supporting mechanism 1 is used to provide stable load-bearing and support. The supporting mechanism 1 is in contact with the ground, wherein detachable moving wheels can be provided at the bottom of the supporting mechanism 1 for easy transportation. After the transportation arrives at the location, the moving wheels are disassembled to avoid the position displacement of the supporting mechanism 1 during data detection.

[0038] The lifting mechanism 2 is installed on one side of the supporting mechanism 1, and the lifting end is located at the top of the supporting mechanism 1. The lifting mechanism 2 provides a lifting effect. The driving end of the lifting mechanism 2 is located on the side of the bottom of the supporting mechanism 1, and the lifting end is located at the top of the supporting mechanism 1 to ensure the lifting height.

[0039] A guiding space is formed in the middle of the guiding mechanism 4, and both sides are connected to the supporting mechanism 1. The switching mechanism 5 is connected to the top of the supporting mechanism 1, and the load-bearing mechanism 3 is slidably connected to the switching mechanism 5. The load-bearing mechanism 3 is used to impact the pile foundation to apply pressure. The guiding mechanism 4 is used to provide guidance for the lifting path of the load-bearing mechanism 3. The switching mechanism 5 can switch the load-bearing end of the load-bearing mechanism 3 so that different load-bearing ends can adapt to pile foundations of different depths and sizes.

[0040] The buffer mechanism 6 is located in the guide mechanism 4, slides along the guide space, and is connected to the top of the pile foundation. The buffer mechanism 6 is used to adapt to pile foundations at different heights above the ground. The buffer mechanism 6 can slide along the guide space of the guide mechanism 4. If it contacts a pile foundation with a lower height above the ground, the buffer mechanism 6 extends longer from the guide space to fit the top of the pile foundation. If it contacts a pile foundation with a higher height above the ground, the buffer mechanism 6 extends further into the guide space.

[0041] The detection mechanism 7 is installed on the supporting mechanism 1 and is aligned with the pile foundation. The detection mechanism 7 can adopt a quick-load pile foundation detection signal system, including a controller, a force sensor, an acceleration sensor, a displacement sensor, a photoelectric sensor, etc. After being aligned with the pile foundation, the detection ends of the force sensor and the acceleration sensor can be set on the buffer mechanism 6 to perform force transmission detection by pulling with a data line or by means of a wireless signal, and the displacement and settlement of the pile foundation caused by the load-bearing mechanism 3 can be detected and data collected.

[0042] Among them, the switching mechanism 5 includes a first switching member 51 and a second switching member 52. The first switching member 51 is installed on the top of the supporting mechanism 1. The first switching member 51 is provided with a first switching groove 511. The first switching member 51 can adopt two first switching rails. The second switching member 52 is connected to the lifting end. The second switching member 52 is provided with a second switching groove 521. The second switching member 52 can adopt a second switching rail. The two first switching rails are located on both sides of the second switching rail. The first switching groove 511 on the two first switching rails and the second switching groove 521 on the second switching rail can be connected to each other. When the first switching groove 511 and the second switching groove 521 are connected, the load-bearing mechanism 3 can slide freely along the two first switching grooves 511 and the second switching groove 521 to switch the installation position.

[0043] The load-bearing mechanism 3 includes a plurality of load-bearing members 31, and the plurality of load-bearing members 31 slide along the first switching groove 511 and the second switching groove 521, so that different load-bearing members 31 can enter the first switching groove 511 or the second switching groove 521 to switch different load-bearing members 31, wherein different load-bearing members 31 have different weights to adapt to pile foundations of different depths and sizes.

[0044] After the second switching member 52 is affected by the gravity of the load-bearing member 31, the lifting end of the lifting mechanism 2 is lowered, so that the second switching member 52 drives the load-bearing member 31 to descend, and the load-bearing member 31 enters the guide space. At the same time, the second switching member 52 is slidingly connected to the inner wall of the guide mechanism 4, so that the position of the second switching member 52 will not be offset, ensuring that the load-bearing member 31 can descend and collide with the buffer mechanism 6 stably.

[0045] Specifically, the lifting mechanism 2 drives the second switching member 52 to the top of the supporting mechanism 1, so that the first switching groove 511 is docked with the second switching groove 521. According to the depth, size and style of the pile foundation on site, the corresponding load-bearing member 31 is switched to the second switching groove 521, and the other load-bearing members 31 are located in the first switching groove 511. Then, under the lifting mechanism 2, the load-bearing member 31 drives the second switching member 52 to descend rapidly, and the second switching member 52 descends along the guide mechanism 4 to ensure that the load-bearing member 31 descends accurately. The load-bearing member 31 collides with the buffer mechanism 6 to form instantaneous pressure, and the buffer mechanism 6 transmits the pressure to the top of the pile foundation. This is repeated, and the pile foundation is detected by the detection mechanism 7 to obtain the pile foundation change data after the collision.

[0046] For further reference, Figure 2 As shown, the second switching member 52 is further provided with two fixing openings 522 , which are communicated with the second switching slot 521 , and the two fixing openings 522 are respectively located at the slot openings of the second switching slot 521 .

[0047] The second switching member 52 is also provided with a fixing portion 523, and the fixing portion 523 is provided with two fixing ends, and the two fixing ends extend through the fixing opening 522 to extend toward the second switching slot 521. The fixing portion 523 can adopt a door-shaped fixing frame, and the two fixing ends of the fixing frame extend downward, which can be respectively inserted into the fixing opening 522, so as to block and fix the slot of the second switching slot 521.

[0048] A fastening portion 524 is also provided on the fixing portion 523, and the fastening portion 524 is threadedly connected to the second switching member 52. The fastening portion 524 can be a bolt, and a threaded hole can be set on the surface of the second switching member 52. When the fixing portion 523 moves downward to insert the fixed end into the fixing port 522, the bolt is screwed into the threaded hole and tightened, so that the fixed end of the fixing portion 523 stably blocks the second switching groove 521, so that the load-bearing member 31 located on the second switching groove 521 cannot be separated from the second switching groove 521, further avoiding the load-bearing member 31 from being offset during the collision with the buffer mechanism 6.

[0049] In some embodiments, reference Figure 3 As shown, the lifting mechanism 2 includes a lifting drive member 21, a pulling member 22 and a plurality of guide wheels 23; the lifting drive member 21 and the plurality of guide wheels 23 are both installed on the supporting mechanism 1, the lifting drive member 21 can adopt a driving element such as a winch, a crane, etc., and the guide wheel 23 can adopt a fixed pulley. The lifting drive member 21 is mainly installed on the side wall of the supporting mechanism 1 near the lower position, and the number of guide wheels 23 is several, which are installed on the side wall and the top of the supporting mechanism 1 in sequence to form a lifting path.

[0050] The pulling member 22 is wound around the lifting driving member 21 and passes through a plurality of guide wheels 23 in sequence before being connected to the second switching member 52 . The pulling member 22 can be made of components such as a steel wire rope and a traction rope.

[0051] Specifically, the pulling member 22 is wrapped around the lifting drive member 21, and the lifting drive member 21 drives the pulling member 22 to be continuously wrapped, so that the pulling member 22 changes the lifting path along the guide wheel 23, and pulls the second switching member 52 close to the top of the support mechanism 1, while keeping the first switching groove 511 and the second switching groove 521 in a docking state. When the load-bearing member 31 of the required weight moves into the second switching groove 521, the pulling member 22 under the lifting drive member 21 is lifted, so that the load-bearing member 31 loses the pull of the pulling member 22 and drives the second switching member 52 to descend, thereby entering the guide space to collide with the buffer mechanism 6.

[0052] For further reference, Figure 4As shown, the support mechanism 1 is also provided with a positioning member 24, and a positioning groove 525 is provided on a side of the second switching member 52 close to the positioning member 24, and the positioning member 24 is plugged into the positioning groove 525. The positioning member 24 can adopt a positioning plate, and a positioning protrusion is provided on the positioning plate, and the second switching member 52 is provided with a positioning groove 525 corresponding to the positioning protrusion on a side close to the positioning member 24, so that when the second switching member 52 is driven by the pulling member 22 to rise, the positioning groove 525 on the second switching member 52 is plugged into the positioning protrusion to ensure that the rising position of the second switching member 52 is accurate, so that the first switching groove 511 and the second flower cutting groove can be accurately connected.

[0053] In some embodiments, reference Figure 3 As shown, the support mechanism 1 includes a first support member 11, a second support member 12 and a load-bearing member 13; the first support member 11 and the second support member 12 are connected to the ground in the vertical direction, and the first support member 11 and the second support member 12 can both adopt support frames made of alloy materials, and the bottom of the first support member 11 and the second support member 12 can be provided with detachable moving wheels to facilitate the movement of the overall detection equipment. When it arrives at the pile foundation to be detected, the moving wheels can be removed to fix the position.

[0054] The load-bearing member 13 is installed on the top of the first support member 11 and the second support member 12. The load-bearing member 13 can be a load-bearing frame or a load-bearing beam made of alloy material, providing installation space for structures such as the guide wheel 23 of the lifting mechanism 2 and the switching mechanism 5, and providing load-bearing.

[0055] Specifically, the first support member 11 and the second support member 12 are used to provide support by contacting the ground, and the load-bearing member 13 is used to provide installation space for the guide wheel 23 of the lifting mechanism 2 and the switching mechanism 5, so as to ensure the stable operation of each mechanism during the detection process.

[0056] For further reference, Figure 4 As shown, the first support member 11 and the second support member 12 are both slidably connected with a stabilizing member 14, and the stabilizing member 14 is inserted into the ground along the vertical direction. The stabilizing member 14 can adopt a stabilizing ring and a stabilizing nail. The stabilizing ring is ring-shaped and slidably connected to the side wall of the first support member 11 or the second support member 12. A number of stabilizing nails can be provided. The stabilizing ring moves downward along the first support member 11 or the second support member 12 so that the stabilizing nails are inserted into the ground. The stabilizing nails are used to increase the support area, improve the overall stability of the support mechanism 1, and avoid the position displacement of the support mechanism 1 during the detection process.

[0057] Further, refer to Figure 4As shown, the first support member 11 and the second support member 12 are divided into a first telescopic section 15 and a second telescopic section 16 along the vertical direction. The second telescopic section 16 is slidably connected to the first telescopic section 15. The first telescopic section 15 and the second telescopic section 16 are respectively a telescopic cylinder and a telescopic frame. The telescopic frame is inserted into the telescopic cylinder and can slide along the telescopic cylinder to extend from or into the telescopic cylinder to adjust the height of the overall first support member 11 or the second support member 12.

[0058] A locking piece 17 is provided between the first telescopic section 15 and the second telescopic end, and the load-bearing member 13 is installed on the top of the second telescopic section 16. After the height of the first support member 11 and the second support member 12 is adjusted, the height of the load-bearing member 13 is simultaneously increased, and the locking piece 17 can be a locking column or a locking rod made of a metal material. The first telescopic section 15 and the second telescopic section 16 are both separated by a plurality of locking holes 18. When the first telescopic section 15 and the second telescopic section 16 are adjusted to a suitable position, the two locking holes 18 are butted, and then the locking piece 17 is inserted into the locking hole 18 to lock the position of the first telescopic section 15 and the second telescopic section 16. The first telescopic section 15 and the second telescopic section 16 cannot continue to telescope, and the selected height is fixed.

[0059] Specifically, the second telescopic section 16 is used to slide along the first telescopic section 15 to adjust the overall height of the first support member 11 and the second support member 12, so that the height of the load-bearing member 13 is adjusted. After the adjustment, the positions of the first telescopic section 15 and the second telescopic section 16 are fixed by the locking member 17 to achieve a fixed height. The gravitational potential energy of load-bearing members 31 at different heights is different. Therefore, the height of the load-bearing member 13 can be adjusted to further adapt to pile foundations of different depths, sizes or styles.

[0060] In some embodiments, reference Figure 3 or Figure 4 As shown, the guide mechanism 4 includes a guide cylinder 41 and a connecting member 42; one end of the connecting member 42 is connected to the outer wall of the guide cylinder 41, and the other end is connected to the support mechanism 1. The guide cylinder 41 has a guide space. The connecting member 42 can adopt a connecting frame, which connects the guide cylinder 41 to the support mechanism 1 so that the position of the guide cylinder 41 is fixed. When the second switching member 52 descends, it enters the guide cylinder 41 and moves along the guide space in the guide cylinder 41.

[0061] Among them, reference Figure 5As shown, only part of the length of the guide protrusion is shown in the figure. A guide rail can be set on the top of the guide cylinder 41, and the guide rail is a guide protrusion. The second switching member 52 is provided with a guide groove, and the guide protrusion is plugged into the guide groove. At the same time, the second switching member 52 can move into the guide cylinder 41 along the guide protrusion through the guide groove. There are two guide rails, which are respectively located on both sides of the guide cylinder 41, and the interval width between the two guide rails is greater than the width of the load-bearing member 31, so that when the load-bearing member 31 moves along the first switching groove 511 and the second switching groove 521, it will not be blocked by the guide rails. The guide rails can provide preliminary guiding effect when the second switching member 52 has not entered the guide cylinder 41, so as to avoid the position deviation of the second switching member 52 and ensure that the second switching groove 521 and the first switching groove 511 can be accurately docked.

[0062] For further reference, Figure 4 and Figure 5 As shown, the guide cylinder 41 is composed of a plurality of first guide plates 411 and a plurality of second guide plates 412, and the first guide plates 411 and the second guide plates 412 are arranged at intervals, so that all the second guide plates 412 are staggered with the first guide plates 411 when they are lifted or lowered in the vertical direction.

[0063] A first fixing ring 413 is provided at the bottom of several first guide plates 411, and the first fixing ring 413 connects all the first guide plates 411 as a whole. A second fixing ring 414 is provided on the top of the second guide plate 412, and the second fixing ring 414 connects all the second guide plates 412 as a whole. All the first guide plates 411 can be moved in the vertical direction uniformly through the first fixing ring 413, and the position of all the second guide plates 412 is fixed by the second fixing ring 414 and will not rise synchronously with the first guide plates 411. The first guide plates 411 are connected to the first telescopic section 15 through the connecting member 42, and the second guide plates 412 are connected to the second telescopic section 16 through the connecting member 42.

[0064] When the second telescopic section 16 drives the second guide piece 412 and the second fixed ring 414 to rise through the connecting piece 42, the first telescopic section 15 drives the first guide piece 411 and the first fixed ring 413 to remain in position through the connecting piece 42, so that the second guide piece 412 and the first guide piece 411 are staggered in rising and falling, extending the guiding length and adapting to the load-bearing parts 13 of different heights without affecting the guiding effect.

[0065] The present application also provides a detection method, which is applied to the detection device in the above embodiment, comprising the following steps: S1. Collect on-site pile foundation and soil information, and check the building, design and construction information to ensure the accuracy of the survey data.

[0066] S2. Move the detection equipment to the pile foundation to be detected, and adjust the detection equipment according to the survey data: 21. According to the depth, size or style of the pile foundation, move and switch the corresponding load-bearing member 31 along the first switching groove 511 and the second switching groove 521 to the second switching groove 521, and push other load-bearing members 31 into the first switching groove 511; 22. Start the detection mechanism 7, and the detection mechanism 7 detects the pile foundation; 23. Start the lifting mechanism 2, and the lifting mechanism 2 lowers the second switching member 52. The second switching member 52 and the load-bearing member 31 collide with the buffer mechanism 6 along the guide mechanism 4, and the buffer mechanism 6 synchronously collide with the pile foundation; 24. According to the impact of the pile foundation, the detection mechanism 7 performs data detection and data information collection on the pile foundation; 25. Repeat steps S21-S24 several times to obtain multiple groups of control data, and the detection mechanism 7 collects and draws data curves.

[0067] S3. According to the data information of the mobile detection equipment of the detection mechanism 7 and the pile foundation, data integration and calculation are performed to comprehensively analyze the location of the pile foundation defects and the specific types of defects to obtain comprehensive performance data on the integrity and bearing capacity of the pile foundation.

[0068] When the fixing portion 523 is provided, step S211 is added in S21.

[0069] S211, after the corresponding load-bearing member 31 moves to the second switching groove 521, move the fixing part 523 toward the fixing opening 522 so that the fixing part 523 is stuck in the notch of the second switching groove 521, and then tighten the fastening part 524 and the second switching member 52 to fasten the fixing part 523 to the second switching member 52 to prevent the load-bearing member 31 from detaching.

[0070] When a stabilizing member 14 is provided, the following contents are added in step S2: the detection device is moved to the pile foundation to be detected, and the stabilizing member 14 is inserted into the ground to fix the supporting mechanism 1 .

[0071] Wherein, when the first telescopic section 15 and the second telescopic section 16 are provided, in step S21 , step S212 is added.

[0072] S212, synchronously pull the second telescopic section 16 of the first support member 11 and the second support member 12. After the second telescopic section 16 is pulled out of the first telescopic section 15, the first guide piece 411 and the second guide piece 412 are synchronously separated, and the first telescopic section 15 and the second telescopic section 16 are locked and fixed by the locking member 17 to increase the adapted height. The gravitational potential energy of the load-bearing member 31 is increased by the adjusted height, and the impact force is increased. Different data change curves can be obtained through different height data.

[0073] The embodiments of this specific implementation are all preferred embodiments of the present application, and are not intended to limit the protection scope of the present application. The same components are represented by the same figure marks. Therefore, any equivalent changes made based on the structure, shape, and principle of the present application should be included in the protection scope of the present application.

Claims

1. A pile foundation detection device based on the unloading point method, characterized in that: The invention comprises a supporting mechanism (1), a lifting mechanism (2), a load-bearing mechanism (3), a guiding mechanism (4), a switching mechanism (5), a buffer mechanism (6) and a detection mechanism (7); the supporting mechanism (1) is arranged in a vertical direction, the lifting mechanism (2) is installed on one side of the supporting mechanism (1), and the lifting end is located at the top of the supporting mechanism (1); a guiding space is formed in the middle of the guiding mechanism (4), and both sides are connected to the supporting mechanism (1); the switching mechanism (5) is connected to the top of the supporting mechanism (1); the load-bearing mechanism (3) is slidably connected to the switching mechanism (5); the buffer mechanism (6) is located in the guiding mechanism (4), slides along the guiding space, and is connected to the top of the pile foundation; the detection mechanism (7) is installed on the supporting mechanism (1), and is aligned with the pile foundation. The switching mechanism (5) comprises a first switching member (51) and a second switching member (52), wherein the first switching member (51) is mounted on the top of the supporting mechanism (1), and the first switching member (51) is provided with a first switching groove (511); the second switching member (52) is connected to the lifting end, and the second switching member (52) is provided with a second switching groove (521); when the first switching member (51) and the second switching member (52) are docked, the first switching groove (511) and the second switching groove (521) are docked; the second switching member (52) is slidably connected to the guide mechanism (4); the load-bearing mechanism (3) comprises a plurality of load-bearing members (31), and the plurality of load-bearing members (31) slide along the first switching groove (511) and the second switching groove (521).

2. The pile foundation detection device based on the unloading point method according to claim 1 is characterized in that: The second switching member (52) is further provided with two fixing openings (522), the two fixing openings (522) being in communication with the second switching slot (521); the second switching member (52) is further provided with a fixing portion (523); the fixing portion (523) is provided with two fixing ends, the two fixing ends pass through the fixing openings (522) and extend toward the second switching slot (521); the fixing portion (523) is further provided with a fastening portion (524), the fastening portion (524) being screwed to the second switching member (52).

3. The pile foundation detection device based on the unloading point method according to claim 1 is characterized in that: The lifting mechanism (2) comprises a lifting drive member (21), a pulling member (22) and a plurality of guide wheels (23); the lifting drive member (21) and the plurality of guide wheels (23) are both mounted on the supporting mechanism (1); the pulling member (22) is wound around the lifting drive member (21), and after passing around the plurality of guide wheels (23) in sequence, is connected to the second switching member (52).

4. The pile foundation detection device based on the unloading point method according to claim 3 is characterized in that: The support mechanism (1) is further provided with a positioning member (24); a positioning groove (525) is provided on a side of the second switching member (52) close to the positioning member (24); and the positioning member (24) is plugged into the positioning groove (525).

5. The pile foundation detection equipment based on the unloading point method according to claim 1 is characterized in that: The support mechanism (1) comprises a first support member (11), a second support member (12) and a load-bearing member (13); the first support member (11) and the second support member (12) are connected to the ground in a vertical direction; and the load-bearing member (13) is mounted on the top of the first support member (11) and the second support member (12).

6. The pile foundation detection device based on the unloading point method according to claim 5 is characterized in that: The first support member (11) and the second support member (12) are both slidably connected with a stabilizing member (14), and the stabilizing member (14) is inserted into the ground in a vertical direction.

7. The pile foundation detection device based on the unloading point method according to claim 5 is characterized in that: The first support member (11) and the second support member (12) are both divided into the first telescopic section (15) and the second telescopic section (16) along the vertical direction; the second telescopic section (16) is slidably connected to the first telescopic section (15); a locking member (17) is provided between the first telescopic section (15) and the second telescopic end; and the load-bearing member (13) is mounted on the top of the second telescopic section (16).

8. The pile foundation detection device based on the unloading point method according to claim 5 is characterized in that: The guide mechanism (4) comprises a guide cylinder (41) and a connecting piece (42); one end of the connecting piece (42) is connected to the outer wall of the guide cylinder (41), and the other end is connected to the support mechanism (1); the guide cylinder (41) contains a guide space.

9. The pile foundation detection device based on the unloading point method according to claim 8, characterized in that: The guide cylinder (41) is composed of a plurality of first guide pieces (411) and a plurality of second guide pieces (412), and the first guide pieces (411) and the second guide pieces (412) are arranged at intervals; a first fixing ring (413) is arranged at the bottom of the plurality of first guide pieces (411), and the first fixing ring (413) connects all the first guide pieces (411) as a whole; a second fixing ring (414) is arranged at the top of the second guide piece (412), and the second fixing ring (414) connects all the second guide pieces (412) as a whole; the first guide piece (411) is connected to the first telescopic section (15) through the connecting piece (42); and the second guide piece (412) is connected to the second telescopic section (16) through the connecting piece (42).

10. A detection method, characterized in that: The pile foundation detection equipment based on the unloading point method as described in claim 1 includes the following steps: collecting on-site pile foundation and soil information, and checking the building, design, and construction information to ensure that the survey data is accurate; Move the testing equipment to the pile foundation to be tested and adjust the testing equipment according to the survey data; According to the depth, size or style of the pile foundation, the corresponding load-bearing member (31) is switched along the first switching groove (511) and the second switching groove (521) to the second switching groove (521), and the other load-bearing members (31) are pushed into the first switching groove (511); Starting the detection mechanism (7), the detection mechanism (7) detects the pile foundation; The lifting mechanism (2) is started, the lifting mechanism (2) lowers the second switching member (52), the second switching member (52) and the load-bearing member (31) collide with the buffer mechanism (6) along the guide mechanism (4), and the buffer mechanism (6) synchronously collide with the pile foundation; According to the impact condition of the pile foundation, the detection mechanism (7) performs data detection and data information collection on the pile foundation; Repeat the above steps several times to obtain multiple groups of control data, and the detection agency (7) collects and draws a data curve; According to the data information of the mobile detection equipment of the detection agency (7) and the pile foundation, data integration and calculation are carried out to comprehensively analyze the location of the pile foundation defects and the specific types of defects, and obtain the comprehensive performance data of the integrity and bearing capacity of the pile foundation.