Truss bearing type composite floor slab
Through the design of truss support type overlapping floor slabs, the truss stressed frame and prefabricated overlapping boards are used to form a truss stressed structure, which solves the problem of lower support in the existing technology, achieves high stiffness and convenient construction, and adapts to different Requirements for floor design thickness.
Patent Information
- Application Number
- CN202411158920.6
- Authority / Receiving Office
- CN · China
- Patent Type
- Applications(China)
- Current Assignee / Owner
- Filing Date
- 2024-08-22
- Publication Date
- 2024-11-12
AI Technical Summary
The existing truss-supported laminated plate construction method requires lower support, and due to the inconsistent floor size and thickness of floor slabs in the building, each prefabricated floor slab needs to be customized to support truss, resulting in component transportation and on-site assembly organization problems, and the degree of standardization is low. .
The truss-resisted overlapping floor slab is adopted, and the bottom surface is supported by a prefabricated beam body, including a prefabricated overlapping board, a truss-resisted frame and a concrete cast-in-place layer. The truss-resisted structure is formed through the chord and abdomen connecting the support on the truss, so as to achieve no The construction mode of lower support improves stiffness and saves construction materials.
The high stiffness and deformation resistance of the laminated plate are achieved, the construction process is simplified, the construction time is saved for more than 10 working hours, and the load-bearing capacity and standardization are improved by adjusting the truss structure to adapt to the design thickness of different floor slabs.
Smart Images

Figure CN118933248A_ABST
Abstract
Description
Technical Field
[0001] The present invention relates to the field of prefabricated building construction, and more specifically, to a truss-supported composite floor slab. Background Art
[0002] With the continuous development of social economy and the continuous improvement of urbanization level, prefabricated buildings are widely used in various engineering structures due to their characteristics of rapid construction. In prefabricated building systems, composite floor slabs are widely used as the most commonly used prefabricated slab components. The thickness of composite floor slabs is generally 80-120mm. During the construction process, they are hoisted on the completed beams or columns. After temporary support is made under the slab, the steel bars of the slab are tied and the water and electricity pipes are laid. Then, the concrete of the cast-in-place layer of the slab is poured. In this process, the composite floor slab can be regarded as the bottom formwork of the cast-in-place layer, which saves the time of supporting the slab formwork and has the characteristics of convenient construction.
[0003] After years of development, the support system of the composite plate has developed a truss support in addition to the conventional lower steel pipe support. Since the truss system has good bearing capacity and anti-deformation ability when supported at both ends, it is currently used in some projects. The patent application number CN117702976A discloses a detachable composite plate with a support truss, which is composed of a prefabricated composite plate and a support truss. The support truss and the composite plate are detachably connected by high-strength bolts to form a temporary support structure. This type of composite plate is connected to the truss by high-strength bolts through embedded parts with inner thread sleeves set in the plate, which can be disassembled and used. However, the number of embedded parts used in this scheme is large. Considering that the current prefabricated component factory will produce an embedded error of about 4mm in the positioning control of embedded parts, in order to achieve the expected effect of high-strength bolt threaded connection between the truss and the embedded parts, the horizontal and vertical positioning accuracy of the embedded parts is very high and the implementation is extremely difficult. In addition, the steel truss needs to be customized according to the span of the composite plate, and the degree of standardization is low.
[0004] For the composite floor system, since the composite floor is designed to be thin, in order to prevent the composite floor from deflecting during the pouring process, a support frame must be set up under the composite floor in the case of a larger span. At present, all conventional support systems are about how to support the hoisted composite floor by setting up supports below. If the existing truss-supported composite floor construction method is adopted, it also faces many technical difficulties. In actual projects, since the size and thickness of the floor in the building are not uniform, it is necessary to customize the support truss for each prefabricated floor. Although the support truss can be used in a cyclical manner, since the support truss corresponds to each composite board one by one and cannot be simply disassembled, it causes great organizational problems for the transportation of components and on-site assembly. Therefore, it is necessary to propose a composite floor with a unique support mode, which can have good deformation resistance when pouring the cast-in-place concrete layer without lower support, and is easy to construct and assemble. Summary of the invention
[0005] One object of the present invention is to provide a truss-supported composite floor slab, which has greatly improved rigidity compared to conventional prefabricated composite slabs, fundamentally solves the construction mode of the composite slab requiring lower support, and saves construction materials.
[0006] In order to achieve these purposes and other advantages according to the present invention, according to one aspect of the present invention, the present invention provides a truss-supported composite floor, the bottom surface of which is supported by a prefabricated beam body, comprising:
[0007] A prefabricated composite slab, which is a rectangular concrete slab; a truss load-bearing frame, which includes at least one truss upper chord higher than the prefabricated composite slab, a plurality of web connecting supports and a plurality of truss webs, wherein a plurality of rows of spaced web connecting supports are fixed to the upper surface of the prefabricated composite slab, and one or more truss webs are detachably fixedly connected to each web connecting support and the truss upper chord, wherein the truss load-bearing frame and the prefabricated composite slab together form a truss load-bearing structure; a cast-in-place concrete layer, which is formed above the prefabricated composite slab, and the top surface of the cast-in-place concrete layer is not higher than the connection between the web connecting supports and the truss webs.
[0008] Preferably, both side edges of the upper surface of the prefabricated composite panel are each provided with a row of spaced-apart web connecting supports along the length direction, and a truss upper chord is horizontally provided above the prefabricated composite panel along the length direction, wherein the truss upper chord is located above the center axis of the row of web connecting supports, and at least one truss web is detachably fixedly connected between each web connecting support and the truss upper chord.
[0009] Preferably, the web connecting support includes a support fixing plate and two first sleeves, the support fixing plate is fixed to the upper surface of the prefabricated composite plate, the two first sleeves are symmetrically welded to the support fixing plate, the truss upper chord includes a plurality of groups of second sleeves obliquely downward, the second sleeves are coaxially opposite to the first sleeves one by one, both ends of the truss web are provided with external threads, the second sleeve and the first sleeve are provided with internal threads matching the truss web, the two ends of the truss web are matched and screwed into the corresponding second sleeve and the first sleeve, wherein, when the truss web is screwed to the top in the direction of the corresponding first sleeve or the second sleeve, one end of the truss web is in a disengaged state.
[0010] Preferably, the truss upper chord and truss web are both steel tubular structures.
[0011] Preferably, the upper chord of the truss includes a chord main tube and a chord connecting tube which are alternately threadedly connected, and matching threads are provided at both ends of the chord main tube and the chord connecting tube. Four second sleeves are connected obliquely downward to the middle of the tube body of the chord main tube, wherein each chord main tube is located directly above the center position of four adjacent web connecting supports that form the vertices of a rectangle, and the four second sleeves on the chord main tube are all screwed together with the corresponding first sleeves to have the truss webs.
[0012] Preferably, the construction method of the truss-supported composite floor slab comprises the following steps:
[0013] S1. Design the dimensions of the prefabricated composite slab according to the beam and column arrangement of the building, the on-site hoisting capacity, and the force calculation results. After all components are processed in the prefabricated component processing plant, they will be sent to the construction site;
[0014] S2. At the construction site, according to the design requirements, the chord main tube and the chord connecting tube are screwed in sequence to form a single integral truss upper chord and temporarily supported. After the corresponding number of web connecting supports are stacked in place, the corresponding number of truss webs are connected between the web connecting supports and the truss upper chord to form a truss force frame;
[0015] S3, manually fix the bottom surface of the web connecting support in the truss force frame to the matching prefabricated composite plate, and then hoist the prefabricated composite plate as a whole onto the fixed prefabricated beam body in sequence;
[0016] S4, repeat step S3 until all prefabricated composite slabs on the same floor are in place, and then proceed with the construction of slab surface reinforcement and water and electricity pipelines;
[0017] S5, sealing the joints between any two adjacent prefabricated composite panels and pouring a cast-in-place concrete layer;
[0018] S6. Cure the cast-in-place concrete layer until it reaches the design strength requirement, and then remove all truss upper chords and truss webs;
[0019] S7. Fill the first sleeve with grouting material for sealing, and complete the construction of the floor slab of this layer.
[0020] Preferably, in step S3, the bottom surface of the support fixing plate is coated with steel glue so as to fix it to the upper surface of the prefabricated composite plate.
[0021] The present invention has at least the following beneficial effects:
[0022] First, the prefabricated composite slab used in the present invention cooperates with the upper truss load-bearing frame to form a truss load-bearing structure in actual stress. The weight of the cast-in-place concrete layer is distributed to the truss load-bearing frame connected to the prefabricated composite slab and transmitted to the prefabricated beam body that has been fixed. The rigidity of this prefabricated composite slab is greatly improved compared with the conventional prefabricated composite slab, which fundamentally solves the construction mode of the composite slab requiring lower support.
[0023] Second, the truss upper chord and truss web in the present invention are assembled on site and completed before the prefabricated composite slab is hoisted. When the floor slab is constructed, it can be directly hoisted to the designated position and then the steel bar binding and water and electricity pipe laying can be carried out, which saves a support process and saves more than 10 working hours for each floor slab construction.
[0024] Third, the present invention uses a truss load-bearing structure formed by a truss upper chord, a truss web and a prefabricated composite slab to bear the load of the cast-in-place concrete layer and the construction load, wherein the height of the truss upper chord determines the stiffness of the overall load-bearing structure, so prefabricated composite slabs of the same thickness can be used in different floor slab design thicknesses, and when the thickness or load of the cast-in-place concrete layer increases, the purpose of improving the stiffness of the truss load-bearing system and the bearing capacity of the prefabricated composite slab can be achieved by adjusting the setting height of the truss upper chord, the length of the truss web and the spacing of the web connection supports.
[0025] Fourthly, the web connecting support of the present invention is detachably connected to the truss web, and the connection portion is higher than the cast-in-place concrete layer. After the cast-in-place concrete layer reaches a certain strength, the truss web and truss main chord can be manually removed, saving construction materials.
[0026] Other advantages, objectives and features of the present invention will be embodied in part through the following description, and in part will be understood by those skilled in the art through study and practice of the present invention. BRIEF DESCRIPTION OF THE DRAWINGS
[0027] Figure 1 It is a schematic diagram of placing a truss-supported composite floor slab on a prefabricated beam body in a technical solution of the present invention;
[0028] Figure 2 A side view of the construction process of a truss-supported composite floor in a technical solution of the present invention;
[0029] Figure 3 It is a schematic diagram of the construction process of a truss-supported composite floor in a technical solution of the present invention;
[0030] Figure 4 It is a schematic diagram of the removal of the cast-in-place concrete layer of the truss-supported composite floor slab in one technical solution of the present invention;
[0031] Figure 5 It is a schematic diagram of a web connecting support in a technical solution of the present invention;
[0032] Figure 6 It is a schematic diagram of the installation of a truss web member in a technical solution of the present invention;
[0033] Figure 7 It is a schematic diagram of the installation of the upper chord of the truss in a technical solution of the present invention;
[0034] Figure 8 It is a schematic diagram of prefabricated composite panels of the same size cooperating with truss upper chords of different heights in a technical solution of the present invention.
[0035] Legend: 1-precast composite slab, 2-web connecting support, 21-first sleeve, 22-support fixing plate, 3-truss web, 31-web threaded section, 4-truss upper chord, 40-second sleeve, 41-chord main tube, 42-chord connecting tube, 5-cast-in-place concrete layer, 6-precast beam. DETAILED DESCRIPTION
[0036] The present invention is further described in detail below in conjunction with the accompanying drawings and specific embodiments so that those skilled in the art can implement the invention with reference to the description.
[0037] It should be understood that the terms such as “having”, “including” and “comprising” used herein do not exclude the existence or addition of one or more other elements or combinations thereof.
[0038] It should be noted that the experimental methods described in the following embodiments are conventional methods unless otherwise specified, and the reagents and materials can be obtained from commercial sources unless otherwise specified; in the description of the present invention, it should be noted that, unless otherwise clearly specified and limited, the terms "installed", "connected", and "set" should be understood in a broad sense, for example, they can be fixedly connected, set, or detachably connected, set, or connected and set in one piece. For ordinary technicians in this field, the specific meanings of the above terms in the present invention can be understood in specific circumstances. The orientation or position relationship indicated by the terms "lateral", "longitudinal", "upper", "lower", "front", "back", "left", "right", "vertical", "horizontal", "top", "bottom", "inside", "outside", etc. is based on the orientation or position relationship shown in the accompanying drawings, which is only for the convenience of describing the present invention and simplifying the description, and does not indicate or imply that the device or element referred to must have a specific orientation, be constructed and operated in a specific orientation, and therefore cannot be understood as a limitation of the present invention.
[0039] like Figures 1 to 8 As shown, the present invention provides a truss-supported composite floor, the bottom surface of which is supported by a precast beam body 6, comprising: a precast composite panel 1, which is a rectangular concrete panel; a truss load-bearing frame, which comprises at least one truss upper chord 4 higher than the precast composite panel 1, a plurality of web connecting supports 2 and a plurality of truss webs 3, wherein a plurality of rows of web connecting supports 2 arranged at intervals are fixed to the upper surface of the precast composite panel 1, and more than one truss web 3 is detachably fixedly connected between each web connecting support 2 and the truss upper chord 4, wherein the truss load-bearing frame and the precast composite panel 1 together form a truss load-bearing structure; a cast-in-place concrete layer 5, which is formed above the precast composite panel 1, and the top surface of the cast-in-place concrete layer 5 is not higher than the connection between the web connecting supports 2 and the truss web 3.
[0040] In the present technical scheme, the precast beam body 6 is a precast beam component with bearing capacity, and its strength and fixing means are sufficient to bear the loads of the precast composite slab 1, the cast-in-place concrete layer 5 and the supporting steel bars and other related equipment allocated to it. The precast composite slab 1 is an internally reinforced long strip concrete slab, and additional reinforcement can be made inside for the subsequent fixing position of the web connecting support 2. The two short sides of the precast composite slab 1 are placed on two precast beam bodies 6. If there is no protruding steel bar on the long side of the precast composite slab 1, the adjacent slab bodies are tightly spliced. If the long side of the precast composite slab 1 is designed as an protruding steel bar, there is a certain gap between the adjacent precast composite slabs 1 to form a post-casting strip, and the protruding steel bar is 100% overlapped. The upper surface of the precast composite slab 1 is roughened to better combine with the cast-in-place concrete layer 5. Optionally, in addition to the two short side ends of the precast composite slab 1 being placed on the precast beam body 6, the bottom of the slab body can also be fixed to other precast beam bodies 6.
[0041] In the present technical solution, the truss upper chord 4 and the truss web 3 are made of finished steel pipes or steel sections, wherein the truss web 3 and the truss upper chord 4 can be connected by bolt connection or threaded sleeve, and the connection form is similar to the steel structure truss node form, the web connecting support 2 is a component made of steel plate or steel pipe, and the end of the truss web 3 can be connected by bolt connection or threaded sleeve, and the web connecting support 20 and the top surface of the prefabricated composite plate 1 can be connected by anchor glue or bolts. In terms of force considerations, the truss force structure composed of a single truss upper chord 4 and the connected truss webs 3 can be regarded as a steel truss with a simplified lower chord. Since the prefabricated composite slab 1 can be regarded as a lower chord structure, when the slab surface reinforcement construction and the cast-in-place concrete layer 5 are constructed, the prefabricated composite slab 1 and its upper truss upper chord 4 and truss webs 3 are combined to bear force, and the stiffness and bearing capacity are greatly improved compared to conventional composite floors. Optionally, a rod structure can be added between any two web connection supports 2 to further enhance the overall strength.
[0042] Rigidity refers to the ability of an object to not easily deform when subjected to external forces. The rigidity of a truss load-bearing structure is closely related to its load-bearing capacity. In the present technical solution, the relative height of the truss upper chord 4 above the prefabricated composite plate 1 determines the rigidity of the truss load-bearing structure composed of the prefabricated composite plate 1, the truss upper chord 4, and the truss web 3 in the present solution. Since the web connecting support 2 and the truss web 3 in the present solution are components that are assembled with the prefabricated composite plate 1 later, the rigidity of the truss load-bearing structure can be adjusted more conveniently, such as Figure 8 As shown, for floor slabs of different design thicknesses, prefabricated composite panels 1 of the same size specifications can be used. By adjusting the setting height of the truss upper chord 4, the length of the truss web 3 and the spacing of the web connecting supports 2, the purpose of adjusting the stiffness and bearing capacity of the truss load-bearing structure can be achieved.
[0043] In the present technical solution, since the web connecting support 2 and the truss web 3 are detachably connected, the connection between the web connecting support 2 and the truss web 3 is flush with or higher than the top surface elevation of the cast-in-place concrete layer 5. Therefore, except for the connection between the web connecting support 2 and the truss web 3, the other parts are cast inside the cast-in-place concrete layer 5. Before the cast-in-place concrete layer 5 solidifies and reaches the demolding strength, the truss upper chord 4 and the truss web 3 cooperate with the prefabricated composite plate 1 to bear the load together. When the cast-in-place concrete layer 5 reaches the demolding strength, the connection between the web connecting support 2 and the truss web 3 is released. The self-weight and the load on it are instead borne by the cast-in-place concrete layer 5 and the prefabricated composite slab 1 cast integrally therewith. The prefabricated composite slab 1 adopted in the present invention is in the form of an upper truss chord 4 and a truss web 3 above, and can be regarded as a truss load-bearing structure in actual stress. The rigidity of the prefabricated composite slab 2 after the addition of the truss upper chord 4 and the truss web 3 is greatly improved compared with the conventional composite slab, and can effectively bear the construction load and the load of the cast-in-place concrete layer 5. The present invention combines the advantages of the composite slab system and the truss load-bearing system to achieve the construction of the floor slab without lower support.
[0044] In another technical scheme, the two side edges of the upper surface of the prefabricated composite panel 1 are each provided with a row of spaced-apart web connecting supports 2 along the length direction, and a truss upper chord 4 is horizontally provided above the prefabricated composite panel 1 along the length direction, wherein the truss upper chord 4 is located above the central axis of the row of web connecting supports 2, and at least one truss web 3 is detachably fixedly connected between each web connecting support 2 and the truss upper chord 4. In the present technical scheme, each truss upper chord 4 corresponds to a prefabricated composite panel 1. In the vertical and top views, the prefabricated composite panel 1, the truss upper chord 4 and any two adjacent truss webs 3 form an isosceles triangle, and the overall structure can be regarded as a triangular truss load-bearing structure. For the working condition where the thickness of the cast-in-place concrete layer 5 changes, the prefabricated composite panel 1 of the same specification can be used, and the height of the truss upper chord 4 and the spacing of the web connecting supports 2 can be adjusted, and the length of the truss web 3 can also be adjusted in advance or on-site to meet the purpose of stiffness and bearing capacity.
[0045] In another technical solution, the web connecting support 2 includes a support fixing plate 22 and two first sleeves 21, the support fixing plate 22 is fixed to the upper surface of the prefabricated composite plate 1, and the two first sleeves 21 are symmetrically welded to the support fixing plate 22, and the truss upper chord 4 includes a plurality of groups of second sleeves 40 obliquely downward, and the second sleeves 40 are coaxially opposite to the first sleeves 21 one by one, and the two ends of the truss web 3 are provided with external threads, and the second sleeve 40 and the first sleeve 21 are provided with internal threads matching the truss web 3, and the two ends of the truss web 3 are matched and screwed into the corresponding second sleeves 40 and the first sleeve 21, when the truss web 3 is screwed to the top in the direction of the corresponding first sleeve 21 or the second sleeve 40, one end of the truss web 3 is in a disengaged state, and in this technical solution, the support fixing plate 22 is a finished steel plate The truss web 3 is cut and the first sleeve 21 and the second sleeve 40 are both finished steel pipe segments with internal threads. The truss web 3 is a round rod or round tube structure. Both ends of the truss web 3 are provided with external threads matching the first sleeve 21 and the second sleeve 40 respectively, wherein the direction in which one end of the truss web 3 is screwed into the first sleeve 21 is opposite to the direction in which the other end is screwed into the second sleeve 40. After one end of the truss web 3 is screwed into the bottom of the second sleeve 21 in the positive direction, the first sleeve 21 of the web connecting support 2 is aligned with the other end of the truss web 3. At this time, the truss web 3 is screwed in the opposite direction, and the two ends of the truss web 3 are respectively screwed out of the second sleeve 40 and screwed into the first sleeve 21. For the distance that the truss web 3 is screwed into the second sleeve 40 and the first sleeve 21, force calculation is required to avoid the sliding sleeve from coming out under the load-bearing state.
[0046] In another technical solution, the truss upper chord 4 and the truss web 3 are both steel tubular structures. Compared with a rod body with a smaller diameter, the steel tube has better bending and torsion resistance.
[0047] In another technical solution, the truss upper chord 4 includes a chord main tube 41 and a chord connecting tube 42 that are alternately threadedly connected, and matching threads are provided at both ends of the chord main tube 41 and the chord connecting tube 42. Four second sleeves 40 are connected obliquely downward to the middle of the tube body of the chord main tube 41, wherein each chord main tube 41 is located directly above the center position of four adjacent web connecting supports 2 that form the vertices of a rectangle, and the four second sleeves 40 on the chord main tube 41 are all screwed together with the relative first sleeve 21 to have the truss web 3. The chord main tube 41 and the chord connecting tube 42 are connected by threads, which is convenient for adapting to prefabricated composite panels of various lengths and convenient for rapid installation and transportation. When the setting height of the truss upper chord 4 is adjusted while keeping the fixed positions and angles of the first sleeve 21 and the second sleeve 40 on the support fixing plate 22 and the chord main tube 41 unchanged, the chord connecting tubes 42 of different lengths can be replaced according to actual conditions.
[0048] In another technical solution, the construction method of the truss-supported composite floor slab comprises the following steps:
[0049] S1. The size of the prefabricated composite slab 1 is designed according to the beam and column arrangement of the building, the on-site hoisting capacity, and the force calculation results. After all the components are processed in the prefabricated component processing plant, they are sent to the construction site. Specifically, in the concrete component processing plant, the prefabricated composite slab 1 is constructed according to the designed size and the designed reinforcement scheme, and after maintenance, it is sent to the construction site. In the steel component processing plant, the commercial steel plates and steel pipes are cut by a laser cutting machine, and the steel plates are processed into support fixing plates 22 that meet the size, and the steel pipes are processed into chord main tubes 41, chord connecting tubes 42, truss webs 4, first sleeves 21, and second sleeves 40 that meet the size and length requirements, and the internal and external threaded sections of the above components are processed by tapping and threading equipment, four second sleeves 40 are welded to the same chord main tube 41 according to the designed angle, and two first sleeves 21 are welded to the support fixing plates 22 cut from the finished steel plates to form a web connecting support 2. After the components are processed, they are uniformly loaded and sent to the construction site.
[0050] S2. At the construction site, according to the design requirements, the chord main tube 41 and the chord connecting tube 42 are screwed in sequence at intervals to form a single integral truss upper chord 4 and provide temporary support. After a corresponding number of web connecting supports 2 are put in place, a corresponding number of truss webs 3 are connected between the web connecting supports 2 and the truss upper chord 4 to form a truss force-bearing frame. Specifically, at the construction site, the assembly of the truss upper chord 4 is completed, a corresponding number of truss webs 3 are screwed into the top of the second sleeve 40, and then the truss upper chord 4 is erected by a bracket. After a corresponding number of web connecting supports 2 are put in place, the truss webs 3 are screwed in the opposite direction so that they are partially out of the second sleeve 40 and partially screwed into the first sleeve 21.
[0051] S3. Manually fix the bottom surface of the web connecting support 2 in the truss load-bearing frame to the matching prefabricated composite panel 1, and then hoist the prefabricated composite panel 1 as a whole to the fixed prefabricated beam body 6 in turn. Specifically, the support fixing plate 22 can be fixed to the prefabricated composite panel 1 by screws or steel glue, and the connected prefabricated composite panels 1 are hoisted one by one using on-site hoisting equipment so that both short sides are placed on the prefabricated beam body 6. The long sides of the prefabricated composite panels 1 at the edge or special position can also be placed on the prefabricated beam body 6.
[0052] S4, repeat step S3 until all prefabricated composite slabs 1 on the same floor are in place, and then carry out the construction of the slab surface reinforcement and water and electricity pipelines. Specifically, the slab surface reinforcement can be tied to the web connecting support 2.
[0053] S5. Seal the joints between any two adjacent prefabricated composite panels 1 and pour the cast-in-place concrete layer 5. Specifically, after the construction of steel bars, water and electricity pipes on all prefabricated composite panels 1 is completed, use sponge strips and other sealing materials to seal the joints below the prefabricated composite panels 1, and use polyurethane coating or other colloidal sealing materials to apply the connection between the web connecting support 2 and the truss web 3 to avoid concrete slurry contaminating the connection. Concrete pouring can be carried out only after inspection.
[0054] S6. Cure the cast-in-place concrete layer 5 until the design strength requirement is reached, and then remove all the truss upper chords 4 and truss webs 3. Specifically, after the strength of the cast-in-place concrete layer 5 reaches 100%, a person goes up to remove the truss upper chords 4 and truss webs 3, first cleaning the sealing material at the connection between the web connecting support 2 and the truss web 3, and then screwing the truss web 3 out of the first sleeve 21.
[0055] S7. Fill the first sleeve 21 with grouting material to seal it and complete the construction of the floor slab of this layer. Specifically, high-strength cement slurry or other forms of grouting materials are uniformly poured into the first sleeve 21 to complete the sealing of the first sleeve 21. The portion of the first sleeve 21 that is higher than the structural elevation of the floor of this layer will be buried in the mortar layer or other filling layer process in the subsequent construction method, and does not need to be cut or sawed.
[0056] In this technical solution, all components are processed outside the construction site. The truss upper chord 4 and truss web 3 on the prefabricated composite panels 1 with different loads need to be calculated according to the load conditions to obtain the setting height of the truss upper chord 4, the number of web connection supports 2 required, and other information;
[0057] During the construction of floor beams and columns, construction workers can assemble them simultaneously at the component yard. Only after the lifting is correct can the construction of reinforcement and water and electricity be carried out, which greatly saves the on-site construction time. After the cast-in-place concrete layer 5 reaches the demolding strength, the truss upper chord 4 and truss web 3 are both removable and circulated components, which also reduces the construction cost.
[0058] In another technical solution, in step S4, the bottom surface of the support fixing plate 22 is coated with steel adhesive to fix it to the upper surface of the prefabricated composite board 1. In this technical solution, the main component of the steel adhesive is A, B two-component bisphenol A modified epoxy resin structural adhesive, which can be cured at room temperature and has little shrinkage during the curing process. Before applying the steel adhesive, the bottom surface of the support fixing plate 22 and the surface of the prefabricated composite board 1 at the bonding point need to be cleaned with sandpaper and a spray bottle.
[0059] Although the embodiments of the present invention have been disclosed as above, they are not limited to the applications listed in the specification and the implementation modes, and they can be fully applied to various fields suitable for the present invention. For those familiar with the art, additional modifications can be easily implemented. Therefore, without departing from the general concept defined by the claims and the scope of equivalents, the present invention is not limited to the specific details and the illustrations shown and described herein.
Claims
1. Truss-supported composite floor, the bottom surface of which is supported by prefabricated beams, characterized in that: include: Prefabricated composite slab, which is a rectangular concrete slab; A truss stress-bearing frame, comprising at least one truss upper chord higher than the prefabricated composite plate, a plurality of web connecting supports and a plurality of truss webs, wherein a plurality of rows of web connecting supports arranged at intervals are fixed on the upper surface of the prefabricated composite plate, and more than one truss web is detachably fixedly connected between each web connecting support and the truss upper chord, wherein the truss stress-bearing frame and the prefabricated composite plate together form a truss stress-bearing structure; A cast-in-place concrete layer is formed above the prefabricated composite slab, and the top surface of the cast-in-place concrete layer is not higher than the connection between the web member connecting support and the truss web member.
2. The truss-supported composite floor slab according to claim 1, characterized in that: The two side edges of the upper surface of the prefabricated composite panel are each provided with a row of spaced-apart web connecting supports along the length direction, and a truss upper chord is horizontally provided above the prefabricated composite panel along the length direction, wherein the truss upper chord is located above the central axis of the row of web connecting supports, and at least one truss web is detachably fixedly connected between each web connecting support and the truss upper chord.
3. The truss-supported composite floor slab according to claim 2, characterized in that: The web connecting support includes a support fixing plate and two first sleeves, the support fixing plate is fixed to the upper surface of the prefabricated composite plate, the two first sleeves are symmetrically welded to the support fixing plate, the truss upper chord includes a plurality of groups of second sleeves obliquely downward, the second sleeves are coaxially opposite to the first sleeves one by one, both ends of the truss web are provided with external threads, the second sleeve and the first sleeve are provided with internal threads matching the truss web, the two ends of the truss web are matched and screwed into the corresponding second sleeve and the first sleeve, wherein, when the truss web is screwed to the top in the direction of the corresponding first sleeve or the second sleeve, one end of the truss web is in a disengaged state.
4. The truss-supported composite floor slab according to claim 3, characterized in that: The truss upper chord and truss web are both steel tubular structures.
5. The truss-supported composite floor slab according to claim 4, characterized in that: The upper chord of the truss includes a chord main tube and a chord connecting tube which are alternately threadedly connected, and matching threads are provided at both ends of the chord main tube and the chord connecting tube. Four second sleeves are connected obliquely downward to the middle of the tube body of the chord main tube, wherein each chord main tube is located directly above the center position of four adjacent web connecting supports that form the vertices of a rectangle, and the four second sleeves on the chord main tube are all screwed together with the corresponding first sleeves to have the truss web.
6. The construction method of the truss-supported composite floor slab according to claim 5, characterized in that: The following steps are involved: S1. Design the dimensions of the prefabricated composite slab according to the beam and column arrangement of the building, the on-site hoisting capacity, and the force calculation results. After all components are processed in the prefabricated component processing plant, they will be sent to the construction site; S2. At the construction site, according to the design requirements, the chord main tube and the chord connecting tube are screwed in sequence to form a single integral truss upper chord and temporarily supported. After the corresponding number of web connecting supports are stacked in place, the corresponding number of truss webs are connected between the web connecting supports and the truss upper chord to form a truss force frame; S3, manually fix the bottom surface of the web connecting support in the truss force frame to the matching prefabricated composite plate, and then hoist the prefabricated composite plate as a whole onto the fixed prefabricated beam body in sequence; S4, repeat step S3 until all prefabricated composite panels on the same floor are in place, and then proceed with the construction of panel reinforcement and water and electricity pipelines; S5, sealing the joints between any two adjacent prefabricated composite slabs and pouring a cast-in-place concrete layer; S6. Cure the cast-in-place concrete layer until it reaches the design strength requirement, and then remove all truss upper chords and truss webs; S7. Fill the first sleeve with grouting material for sealing, and complete the construction of the floor slab of this layer.
7. The construction method of the truss-supported composite floor slab according to claim 6, characterized in that: In the step S5, steel adhesive is applied to the bottom surface of the support fixing plate so that the support fixing plate is fixed to the upper surface of the prefabricated composite plate.
Citation Information
Patent Citations
Pre-stressed concrete truss composite slab and manufacturing method thereof
CN105756252A
Concrete laminated slab, manufacturing method and construction process
CN113863551A
Steel pipe truss concrete laminated slab
CN115341705A
Fabricated laminated slab
CN116677118A
Coincide floor prefabricated plate
CN207878747U