Method and system for evaluating stability of hidden goaf roof of open pit coal mine
By identifying hidden empty areas of open-pit coal mines, obtaining their shape information, using the grid method to divide the roof area, calculate the evaluation coefficient, and evaluate the roof warning coefficient, the problem of poor accuracy of the stability evaluation of the roof panel in the existing technology is solved, and the problem of poor performance evaluation of the roof panel in hidden empty areas is realized. More accurate risk assessment.
Patent Information
- Application Number
- CN202410937137.3
- Authority / Receiving Office
- CN · China
- Patent Type
- Applications(China)
- Current Assignee / Owner
- Filing Date
- 2024-07-12
- Publication Date
- 2024-11-12
- Estimated Expiration
- 2044-07-12
AI Technical Summary
The prior art cannot accurately evaluate the stability of the roof panels of hidden empty areas of open-pit coal mines. The limited data obtained by a single monitoring equipment leads to poor accuracy of stability assessment.
By identifying hidden empty areas, obtaining their empty area shape information, using the grid method to divide the top plate areas, obtaining the stress and displacement information of each grid, calculating the roof evaluation coefficient, and then evaluating the roof warning coefficient to evaluate the roof stability.
The accuracy of the stability evaluation of the hidden empty ceiling roof is improved, and the stability of different areas of the roof can be analyzed in detail, and potential risks can be evaluated in real time.
Smart Images

Figure CN118940558A_ABST
Abstract
Description
Technical Field
[0001] The present invention relates to the technical field of stability assessment, and in particular to a method and system for assessing roof stability in a concealed empty area of an open-pit coal mine. Background Art
[0002] Concealed voids in open-pit coal mines refer to the large number of underground voids formed in the early stage of mining by open-pit mining methods such as room-and-pillar method. Due to incomplete or lost design data, many of these voids cannot be accurately located and bounded, leaving a large number of unknown voids inside and outside the open-pit coal mining boundary. The existence of concealed voids poses a serious threat to the safe production of open-pit coal mines, which may lead to a series of catastrophic events such as roof collapse, ground subsidence, pitting of mining equipment, and endangerment of the safety of personnel and equipment.
[0003] Although the existing technology can determine the location of hidden voids, the shape of voids, stress changes at the roof of voids, etc., due to the large area of the roof and the irregularity of the roof caused by mining operations, the data obtained by a single monitoring device is limited and cannot fully represent the stability information of the entire roof, resulting in poor accuracy of stability assessment. Summary of the invention
[0004] The present invention aims to solve one of the technical problems in the related art at least to a certain extent.
[0005] To this end, the first purpose of the present invention is to propose a method for evaluating the stability of the roof of a concealed empty area in an open-pit coal mine, so as to improve the accuracy of the evaluation of the stability of the roof of the concealed empty area.
[0006] The second object of the present invention is to provide a roof stability assessment system for concealed empty areas in open-pit coal mines.
[0007] A third objective of the present invention is to provide an electronic device.
[0008] A fourth object of the present invention is to provide a computer-readable storage medium.
[0009] To achieve the above-mentioned purpose, the first aspect of the present invention provides a method for evaluating the roof stability of a hidden empty area in an open-pit coal mine, comprising:
[0010] Identify hidden empty areas in open-pit coal mines and obtain empty area shape information of the hidden empty areas;
[0011] Dividing the roof area of the hidden empty area by a grid method to obtain stress information and displacement information of the roof rock layer of each grid;
[0012] Obtaining a roof evaluation coefficient of each grid based on the void shape information, the stress information, and the displacement information;
[0013] The roof warning coefficient is obtained based on the roof assessment coefficients of all grids to evaluate the stability of the empty area roof.
[0014] In the method of the first aspect of the present invention, the roof assessment coefficient of each grid is obtained based on the void shape information, the stress information and the displacement information, including: calculating the stress dynamic risk coefficient of each grid based on the stress information; calculating the displacement fluctuation coefficient of each grid based on the displacement information; calculating the spatial characteristic coefficient of the roof area based on the void shape information; obtaining the roof assessment coefficient of each grid based on the stress dynamic risk coefficient, the displacement fluctuation coefficient and the spatial characteristic coefficient.
[0015] In the method of the first aspect of the present invention, the roof evaluation coefficient of each grid satisfies:
[0016]
[0017] Where PG represents the roof assessment coefficient of any grid, α1, α2, and α3 are the proportional coefficients of the stress dynamic risk coefficient, displacement fluctuation coefficient, and spatial characteristic coefficient of the grid, respectively, and YL dt is the stress dynamic risk factor of the grid, WY bd is the displacement fluctuation coefficient of the grid, KJ tz is the spatial characteristic coefficient of the top plate area.
[0018] In the method of the first aspect of the present invention, the stress information includes horizontal stress and overlying stress per unit time, and the stress dynamic risk coefficient of each grid is calculated based on the stress information, including: based on the horizontal stress and overlying stress per unit time of each grid, respectively calculating the horizontal stress deviation coefficient and the overlying stress deviation coefficient, and then calculating the stress dynamic risk coefficient of the corresponding grid.
[0019] In the method of the first aspect of the present invention, the displacement information includes the initial position of the displacement sensor and the distance from the current position of the displacement sensor to the initial position per unit time, and the displacement fluctuation coefficient of each grid is calculated based on the displacement information, including: based on the initial position of the displacement sensor and the distance of each grid, obtaining the average value and standard deviation of the corresponding distance, and then calculating the displacement fluctuation coefficient of the corresponding grid.
[0020] In the method of the first aspect of the present invention, the empty area shape information includes the span, height and inclination angle of the hidden empty area, and the spatial characteristic coefficient of the top plate area is calculated based on the empty area shape information, including: obtaining the deviation corresponding to the span, height and inclination angle based on the span, height and inclination angle, and then calculating the spatial characteristic coefficient of the top plate area.
[0021] In the method of the first aspect of the present invention, the roof warning coefficient is obtained based on the roof assessment coefficient of all grids to evaluate the stability of the empty area roof, including: obtaining the roof warning coefficient by calculation based on the roof assessment coefficient of all grids and the roof assessment coefficient threshold, and determining the stability of the empty area roof based on the roof warning coefficient and the roof warning coefficient threshold.
[0022] To achieve the above-mentioned purpose, the second aspect of the present invention proposes a roof stability assessment system for a hidden empty area in an open-pit coal mine, comprising:
[0023] The first acquisition module is used to identify the hidden empty area of the open-pit coal mine and obtain the empty area shape information of the hidden empty area;
[0024] The second acquisition module is used to divide the roof area of the hidden empty area by a grid method to obtain stress information and displacement information of the roof rock layer of each grid;
[0025] A calculation module, used for obtaining a roof evaluation coefficient of each grid based on the void shape information, the stress information and the displacement information;
[0026] An evaluation module is used to obtain the roof warning coefficient based on the roof evaluation coefficients of all grids to evaluate the stability of the roof of the empty area.
[0027] To achieve the above-mentioned purpose, the third aspect of the present invention proposes an electronic device, comprising: a processor, and a memory communicatively connected to the processor; the memory stores computer-executable instructions; the processor executes the computer-executable instructions stored in the memory to implement the method proposed in the first aspect of the present invention.
[0028] To achieve the above-mentioned purpose, the fourth aspect of the present invention proposes a computer-readable storage medium, in which computer-executable instructions are stored. When the computer-executable instructions are executed by a processor, they are used to implement the method proposed in the first aspect of the present invention.
[0029] The method, system, electronic device and storage medium for evaluating the stability of the roof of a hidden empty area in an open-pit coal mine provided by the present invention obtain the shape information of the hidden empty area by identifying the hidden empty area of the open-pit coal mine; divide the roof area of the hidden empty area by the grid method to obtain the stress information and displacement information of the roof rock layer of each grid; obtain the roof evaluation coefficient of each grid based on the shape information, stress information and displacement information of the empty area; obtain the roof warning coefficient based on the roof evaluation coefficient of all grids to evaluate the stability of the roof of the empty area. In this case, the roof area is comprehensively divided into grids, and the shape information, stress information and displacement information of the empty area are comprehensively analyzed to determine the roof evaluation coefficient of the grid, and then the roof warning coefficient is obtained to evaluate the stability of the roof of the empty area, which is helpful for the stability of the roof of the empty area, thereby improving the accuracy of the evaluation of the stability of the roof of the hidden empty area.
[0030] Additional aspects and advantages of the present invention will be given in part in the following description and in part will be obvious from the following description, or will be learned through practice of the present invention. BRIEF DESCRIPTION OF THE DRAWINGS
[0031] The above and / or additional aspects and advantages of the present invention will become apparent and easily understood from the following description of the embodiments in conjunction with the accompanying drawings, in which:
[0032] Figure 1 A schematic flow chart of a method for evaluating roof stability of a concealed empty area in an open-pit coal mine provided by an embodiment of the present invention;
[0033] Figure 2 A block diagram of a roof stability assessment system for concealed empty areas in an open-pit coal mine provided by an embodiment of the present invention. DETAILED DESCRIPTION
[0034] Embodiments of the present invention are described in detail below, examples of which are shown in the accompanying drawings, wherein the same or similar reference numerals throughout represent the same or similar elements or elements having the same or similar functions. The embodiments described below with reference to the accompanying drawings are exemplary and are intended to be used to explain the present invention, and should not be construed as limiting the present invention.
[0035] The following describes a method and system for evaluating roof stability in a concealed empty area of an open-pit coal mine according to an embodiment of the present invention with reference to the accompanying drawings.
[0036] The embodiment of the present invention provides a method for evaluating the roof stability of a concealed empty area in an open-pit coal mine, so as to improve the accuracy of evaluating the roof stability of the concealed empty area.
[0037] Figure 1 A schematic flow chart of a method for evaluating roof stability in a concealed empty area of an open-pit coal mine provided in an embodiment of the present invention.
[0038] like Figure 1As shown, the method for evaluating roof stability of concealed empty area in open-pit coal mine includes the following steps:
[0039] Step S101, identifying hidden empty areas in an open-pit coal mine and obtaining empty area shape information of the hidden empty areas.
[0040] In step S101, the hidden empty areas of the open-pit coal mine are identified using geophysical exploration, three-dimensional laser scanning, sonar detection and other technologies.
[0041] In step S101, the acquired empty area shape information includes the span, height and inclination angle of the hidden empty area.
[0042] It is easy to understand that the span refers to the maximum width of the concealed empty area (hereinafter referred to as the empty area) in the horizontal direction. The inclination angle refers to the degree of inclination of the empty area relative to the horizontal plane, usually expressed as an angle. The height refers to the distance from the bottom plate of the empty area to the top plate of the empty area.
[0043] Step S102, dividing the roof area of the hidden empty area by a grid method to obtain stress information and displacement information of the roof rock layer of each grid.
[0044] In step S102, the step of dividing the top plate area of the hidden empty area by the grid method specifically includes:
[0045] 1) First, the area is divided into multiple small areas according to a certain scale, forming a grid-like division structure. The scale of the small area division can be determined according to the specific situation, usually based on the geological conditions, rock formation characteristics and the accuracy required for analysis.
[0046] 2) Then, a grid is established in each small area of the hidden space roof area, usually using a regular rectangular or orthogonal grid structure. The grids in each small area can be numbered by a coordinate system or other identifiers for subsequent analysis.
[0047] In step S102, after dividing the hidden empty space top plate area by the grid method, the monitoring equipment is reasonably distributed into each grid according to the divided grids, and the monitoring equipment includes stress sensors and displacement sensors.
[0048] In step S102, the stress information of the roof rock layer obtained includes the horizontal stress per unit time and the overlying stress at the roof rock layer. The stress information of the roof rock layer is collected by a stress sensor.
[0049] In step S102, the displacement information of the roof rock layer obtained includes the initial position of the displacement sensor and the distance from the current position of the displacement sensor to the initial position per unit time. The distance from the current position to the initial position is collected by the displacement sensor.
[0050] Step S103, obtaining the roof evaluation coefficient of each grid based on the void shape information, stress information and displacement information.
[0051] In step S103, since the void shape information, stress information and displacement information obtained in step S101 and step S102 are all major factors affecting the stability of the roof, this step combines the void shape information, stress information and displacement information to obtain the roof assessment coefficient of each grid, so as to assess the stability changes of different grids of the roof, and further determine the potential risks of different grids of the roof.
[0052] In step S103, the roof assessment coefficient of each grid is obtained based on the void shape information, stress information and displacement information, including: calculating the stress dynamic risk coefficient of each grid based on the stress information; calculating the displacement fluctuation coefficient of each grid based on the displacement information; calculating the spatial characteristic coefficient of the roof area based on the void shape information; and obtaining the roof assessment coefficient of each grid based on the stress dynamic risk coefficient, the displacement fluctuation coefficient and the spatial characteristic coefficient.
[0053] Among them, the stress dynamic risk coefficient of each grid is calculated based on the stress information, including: based on the horizontal stress and overburden stress per unit time of each grid, the horizontal stress deviation coefficient and the overburden stress deviation coefficient are calculated respectively, and then the stress dynamic risk coefficient of the corresponding grid is calculated. The displacement fluctuation coefficient of each grid is calculated based on the displacement information, including: based on the initial position and distance of the displacement sensor of each grid, the average value and standard deviation of the corresponding distance are obtained, and then the displacement fluctuation coefficient of the corresponding grid is calculated. The spatial characteristic coefficient of the roof area is calculated based on the shape information of the void area, including: based on the span, height and inclination angle, the deviation corresponding to the span, height and inclination angle is obtained, and then the spatial characteristic coefficient of the roof area is calculated.
[0054] Specifically, for the stress dynamic risk coefficient, the process of obtaining the stress dynamic risk coefficient of each grid includes:
[0055] Select a grid and determine the horizontal stress and overburden stress per unit time according to the stress sensors in the grid, and use SP n and SF n Represents, where n=1, 2, 3, ..., N, N represents the number of horizontal stresses and overburden stresses collected per unit time, N is a positive integer, and n is the number of horizontal stresses and overburden stresses collected per unit time;
[0056] Get the maximum horizontal stress threshold and the maximum overburden stress threshold, and use SP yz and SF yzIndicates that the horizontal stress and overburden stress greater than the maximum horizontal stress threshold and the maximum overburden stress threshold are obtained in unit time, and the horizontal stress greater than the maximum horizontal stress threshold and the overburden stress greater than the maximum overburden stress threshold are expressed as SP m and SF i Represents, where m=1, 2, 3, ..., M, M represents the number of horizontal stresses greater than the maximum horizontal stress threshold, M is a positive integer, m is the number of horizontal stresses greater than the maximum horizontal stress threshold, i=1, 2, 3, ..., I, I represents the number of overburden stresses greater than the maximum overburden stress threshold, I is a positive integer, i is the number of overburden stresses greater than the maximum overburden stress threshold;
[0057] Calculate the horizontal stress deviation coefficient using the following formula: Among them, PC sp is the horizontal stress deviation coefficient of the grid;
[0058] Calculate the overburden stress deviation coefficient using the following formula: Among them, PC sf is the overburden stress deviation coefficient of the grid;
[0059] Calculate the stress dynamic risk coefficient of the grid, the calculation formula is: Among them, YL dt is the stress dynamic risk factor of the grid.
[0060] The stress dynamic risk coefficients of the remaining grids are calculated by referring to the above calculation process in sequence, so as to obtain the stress dynamic risk coefficients of each grid.
[0061] For the displacement fluctuation coefficient, the process of obtaining the displacement fluctuation coefficient of each grid includes:
[0062] Select a grid, set the initial position of the corresponding displacement sensor according to the installation position of each displacement sensor in the grid, obtain the distance from the current position of the displacement sensor to the initial position of the displacement sensor per unit time, and use JL to calculate the distance from the current position of the displacement sensor to the initial position of the displacement sensor per unit time. n express;
[0063] The average value and standard deviation of the distance from the current position of the displacement sensor to the initial position of the displacement sensor in unit time are obtained, and the average value and standard deviation of the distance from the current position of the displacement sensor to the initial position of the displacement sensor in unit time are respectively expressed by JL avg and JL bzc It indicates that, N1 represents the number of displacement sensors, N1 is a positive integer, and n1 represents the serial number of the displacement sensor;
[0064] Calculate the displacement fluctuation coefficient using the following formula: Among them, WY bd is the displacement fluctuation coefficient of the grid.
[0065] The displacement fluctuation coefficients of the remaining grids are calculated by referring to the above calculation process in turn, so as to obtain the displacement fluctuation coefficients of each grid.
[0066] For the spatial characteristic coefficient, the process of obtaining the spatial characteristic coefficient of the roof area includes:
[0067] Collect the spatial characteristics of hidden voids in open-pit coal mines. The spatial characteristics of hidden voids in open-pit coal mines include the span, height and inclination angle of the voids. The span of the void is represented by KD, the height of the void is represented by GD, and the inclination angle of the void is represented by JD;
[0068] The standard thresholds of span, height and inclination angle of the empty area are obtained. The span, height and inclination angle of the hidden empty area in the open-pit coal mine are compared with the standard thresholds of span, height and inclination angle of the empty area to obtain the deviation of span, height and inclination angle of the empty area. The span deviation of the empty area is expressed as KD pc Indicates that the height deviation of the empty area is expressed as GD pc The tilt angle deviation of the empty area is expressed as JD pc express;
[0069] Calculate the spatial characteristic coefficient, the calculation formula is: Among them, KJ tz is the spatial characteristic coefficient of the top plate area.
[0070] After calculating the stress dynamic risk coefficient, displacement fluctuation coefficient and spatial characteristic coefficient of each grid, a data analysis model is established for the stress dynamic risk coefficient, displacement fluctuation coefficient and spatial characteristic coefficient to generate the roof assessment coefficient. The roof assessment coefficient of each grid satisfies:
[0071]
[0072] Where PG represents the roof assessment coefficient of any grid, α1, α2, and α3 are the proportional coefficients of the stress dynamic risk coefficient, displacement fluctuation coefficient, and spatial characteristic coefficient of the grid, respectively. If α1, α2, and α3 are greater than 0, YL dt is the stress dynamic risk factor of the grid, WY bd is the displacement fluctuation coefficient of the grid, KJ tz is the spatial characteristic coefficient of the top plate area.
[0073] In step S103, since each small area of the hidden empty area roof area includes multiple grids, each grid has a corresponding roof evaluation coefficient. For the convenience of subsequent description, the roof evaluation coefficient of the qth grid in the uth small area is represented by PG u, Indicates, where q = 1, 2, 3, ..., UQ, UQ is the number of grids in the u-th small area, UQ takes a positive integer, and q is the number of grids in the small area; u = 1, 2, 3, ..., U, U is the number of small areas, U takes a positive integer, and u is the number of small areas. The roof evaluation coefficient based on each grid can evaluate the stability changes of different grids.
[0074] In step S103, the roof evaluation coefficient threshold is obtained and the roof evaluation coefficient threshold is used as PG yz It means that the roof assessment coefficient of each grid is compared with the roof assessment coefficient threshold. If the roof assessment coefficient is greater than the roof assessment coefficient threshold, the grid is marked as a risk area. If the roof assessment coefficient is less than the roof assessment coefficient threshold, it will not be marked. In this way, the potential risks of different grids on the roof can be evaluated.
[0075] Step S104, obtaining a roof warning coefficient based on the roof assessment coefficients of all grids to assess the stability of the empty area roof.
[0076] In step S104, a roof warning coefficient is obtained based on the roof evaluation coefficients of all grids to evaluate the stability of the roof in the empty area, including: obtaining a roof warning coefficient based on the roof evaluation coefficients of all grids and the roof evaluation coefficient threshold, and determining the stability of the roof in the empty area based on the roof warning coefficient and the roof warning coefficient threshold. The various thresholds involved in the embodiments of the present invention are usually obtained through empirical values, numerical simulations, theoretical calculations, field data calibration and other methods or set by professional staff to ensure the accuracy and reliability of the evaluation results.
[0077] Specifically, the roof warning coefficient is used to quantify the risk level. The roof warning coefficients of different small areas meet the following requirements:
[0078]
[0079] In the formula, YJ db, is the roof warning coefficient of the u-th small area, PG u, is the roof evaluation coefficient of the qth grid in the uth small area, and UQ is the number of grids in the uth small area.
[0080] After calculating the roof warning coefficient of each area, the roof warning coefficient threshold is obtained, and each roof warning coefficient is compared with the roof warning coefficient threshold. If there is a roof warning coefficient greater than the roof warning coefficient threshold, a warning signal is generated, indicating that the stability of the roof in the hidden empty area of the open-pit coal mine is poor and there may be risks. The staff needs to be reminded to check in time. If all roof warning coefficients are less than the roof warning coefficient threshold, no warning signal is generated, indicating that the stability of the roof area is good and there is no risk for the time being.
[0081] In order to implement the above-mentioned embodiment, the present invention also proposes a roof stability assessment system for concealed empty areas in open-pit coal mines.
[0082] Figure 2 A block diagram of a roof stability assessment system for concealed empty areas in an open-pit coal mine provided by an embodiment of the present invention.
[0083] like Figure 2 As shown, the open-pit coal mine hidden empty area roof stability assessment system includes a first acquisition module 11, a second acquisition module 12, a calculation module 13 and an assessment module 14, wherein:
[0084] The first acquisition module 11 is used to identify the hidden empty area of the open-pit coal mine and obtain the empty area shape information of the hidden empty area;
[0085] The second acquisition module 12 is used to divide the roof area of the hidden empty area by a grid method to obtain stress information and displacement information of the roof rock layer of each grid;
[0086] A calculation module 13 is used to obtain a roof evaluation coefficient of each grid based on the void shape information, stress information and displacement information;
[0087] The evaluation module 14 is used to obtain a roof warning coefficient based on the roof evaluation coefficients of all grids to evaluate the stability of the empty area roof.
[0088] Furthermore, in a possible implementation of an embodiment of the present invention, the calculation module 13 is specifically used to: calculate the stress dynamic risk coefficient of each grid based on stress information; calculate the displacement fluctuation coefficient of each grid based on displacement information; calculate the spatial characteristic coefficient of the roof area based on the void shape information; and obtain the roof assessment coefficient of each grid based on the stress dynamic risk coefficient, the displacement fluctuation coefficient, and the spatial characteristic coefficient.
[0089] Further, in a possible implementation of the embodiment of the present invention, in the calculation module 13, the roof evaluation coefficient of each grid satisfies:
[0090]
[0091] Where PG represents the roof assessment coefficient of any grid, α1, α2, and α3 are the proportional coefficients of the stress dynamic risk coefficient, displacement fluctuation coefficient, and spatial characteristic coefficient of the grid, respectively, and YL dt is the stress dynamic risk factor of the grid, WY bd is the displacement fluctuation coefficient of the grid, KJ tz is the spatial characteristic coefficient of the top plate area.
[0092] Furthermore, in a possible implementation of an embodiment of the present invention, the stress information includes horizontal stress and overlying stress per unit time. In the calculation module 13, the stress dynamic risk coefficient of each grid is calculated based on the stress information, including: based on the horizontal stress and overlying stress per unit time of each grid, respectively calculating the horizontal stress deviation coefficient and the overlying stress deviation coefficient, and then calculating the stress dynamic risk coefficient of the corresponding grid.
[0093] Furthermore, in a possible implementation of an embodiment of the present invention, the displacement information includes an initial position of the displacement sensor and a distance from a current position of the displacement sensor to the initial position per unit time. In the calculation module 13, a displacement fluctuation coefficient of each grid is calculated based on the displacement information, including: based on the initial position and distance of the displacement sensor of each grid, an average value and a standard deviation of the corresponding distance are obtained, and then the displacement fluctuation coefficient of the corresponding grid is calculated.
[0094] Furthermore, in a possible implementation method of an embodiment of the present invention, the empty area shape information includes the span, height and inclination angle of the hidden empty area. In the calculation module 13, the spatial characteristic coefficient of the top plate area is calculated based on the empty area shape information, including: obtaining the deviation corresponding to the span, height and inclination angle based on the span, height and inclination angle, and then calculating the spatial characteristic coefficient of the top plate area.
[0095] Furthermore, in a possible implementation of an embodiment of the present invention, the evaluation module 14 is specifically used to: obtain a roof warning coefficient based on the roof evaluation coefficients and roof evaluation coefficient thresholds of all grids, and determine the stability of the empty area roof based on the roof warning coefficient and roof warning coefficient threshold.
[0096] It should be noted that the above explanation of the embodiment of the method for evaluating the roof stability of a hidden empty area in an open-pit coal mine is also applicable to the system for evaluating the roof stability of a hidden empty area in an open-pit coal mine of this embodiment, and will not be repeated here.
[0097] In the embodiment of the present invention, the hidden empty area of the open-pit coal mine is identified to obtain the empty area shape information of the hidden empty area; the roof area of the hidden empty area is divided by the grid method to obtain the stress information and displacement information of the roof rock layer of each grid; the roof evaluation coefficient of each grid is obtained based on the empty area shape information, stress information and displacement information; the roof warning coefficient is obtained based on the roof evaluation coefficient of all grids to evaluate the stability of the empty area roof. In this case, the roof area is divided into grids, and the empty area shape information, stress information and displacement information are comprehensively analyzed to determine the roof evaluation coefficient of the grid, and then the roof warning coefficient is obtained to evaluate the stability of the empty area roof, which is helpful for the stability of the empty area roof, thereby improving the accuracy of the hidden empty area roof stability evaluation.
[0098] The method and system of the present invention divide the roof area into grids, analyze the information in the grids separately, and determine the roof assessment coefficient of the grid area based on the stress information of the roof rock layer, the displacement information of the roof rock layer and the shape information of the empty area in the grid. The roof assessment coefficient of all the grids of the roof is used to measure the danger level of the roof stability, which is helpful for detailed analysis of the specific conditions of different areas of the roof and can accurately and real-timely assess the stability of the roof. The limitation problem of the existing roof stability assessment of hidden empty areas in open-pit coal mines is solved.
[0099] In order to implement the above embodiments, the present invention also proposes an electronic device, comprising: a processor, and a memory communicatively connected to the processor; the memory stores computer-executable instructions; the processor executes the computer-executable instructions stored in the memory to implement the method provided by the above embodiments.
[0100] In order to implement the above embodiments, the present invention further proposes a computer-readable storage medium, in which computer-executable instructions are stored. When the computer-executable instructions are executed by a processor, they are used to implement the methods provided by the above embodiments.
[0101] In order to implement the above embodiments, the present invention further provides a computer program product, including a computer program, which implements the methods provided by the above embodiments when executed by a processor.
[0102] In the description of the aforementioned embodiments, the description with reference to the terms "one embodiment", "some embodiments", "example", "specific example", or "some examples" etc. means that the specific features, structures, materials or characteristics described in conjunction with the embodiment or example are included in at least one embodiment or example of the present invention. In this specification, the schematic representations of the above terms do not necessarily refer to the same embodiment or example. Moreover, the specific features, structures, materials or characteristics described may be combined in any one or more embodiments or examples in a suitable manner. In addition, those skilled in the art may combine and combine the different embodiments or examples described in this specification and the features of the different embodiments or examples, unless they are contradictory.
[0103] In addition, the terms "first" and "second" are used for descriptive purposes only and should not be understood as indicating or implying relative importance or implicitly indicating the number of the indicated technical features. Therefore, the features defined as "first" and "second" may explicitly or implicitly include at least one of the features. In the description of the present invention, the meaning of "plurality" is at least two, such as two, three, etc., unless otherwise clearly and specifically defined.
[0104] Any process or method description in a flowchart or otherwise described herein may be understood to represent a module, segment or portion of code comprising one or more executable instructions for implementing the steps of a custom logical function or process, and the scope of the preferred embodiments of the present invention includes alternative implementations in which functions may not be performed in the order shown or discussed, including performing functions in a substantially simultaneous manner or in reverse order depending on the functions involved, which should be understood by technicians in the technical field to which the embodiments of the present invention belong.
[0105] The logic and / or steps represented in the flowchart or otherwise described herein, for example, can be considered as an ordered list of executable instructions for implementing logical functions, and can be embodied in any computer-readable medium for use by an instruction execution system, device or apparatus (such as a computer-based system, a system including a processor, or other system that can fetch instructions from an instruction execution system, device or apparatus and execute the instructions), or in combination with these instruction execution systems, devices or apparatuses. For the purpose of this specification, "computer-readable medium" can be any device that can contain, store, communicate, propagate or transmit a program for use by an instruction execution system, device or apparatus, or in combination with these instruction execution systems, devices or apparatuses. More specific examples of computer-readable media (a non-exhaustive list) include the following: an electrical connection with one or more wires (electronic device), a portable computer disk box (magnetic device), a random access memory (RAM), a read-only memory (ROM), an erasable and programmable read-only memory (EPROM or flash memory), a fiber optic device, and a portable compact disk read-only memory (CDROM). In addition, the computer-readable medium may even be paper or other suitable medium on which the program is printed, since the program may be obtained electronically, for example, by optically scanning the paper or other medium and then editing, interpreting or processing in other suitable ways if necessary, and then stored in a computer memory.
[0106] It should be understood that the various parts of the present invention can be implemented by hardware, software, firmware or a combination thereof. In the above-mentioned embodiments, a plurality of steps or methods can be implemented by software or firmware stored in a memory and executed by a suitable instruction execution system. For example, if implemented by hardware, as in another embodiment, it can be implemented by any one of the following technologies known in the art or their combination: a discrete logic circuit having a logic gate circuit for implementing a logic function for a data signal, a dedicated integrated circuit having a suitable combination of logic gate circuits, a programmable gate array (PGA), a field programmable gate array (FPGA), etc.
[0107] A person skilled in the art may understand that all or part of the steps in the method for implementing the above-mentioned embodiment may be completed by instructing related hardware through a program, and the program may be stored in a computer-readable storage medium, which, when executed, includes one or a combination of the steps of the method embodiment.
[0108] In addition, each functional unit in each embodiment of the present invention may be integrated into a processing module, or each unit may exist physically separately, or two or more units may be integrated into one module. The above-mentioned integrated module may be implemented in the form of hardware or in the form of a software functional module. If the integrated module is implemented in the form of a software functional module and sold or used as an independent product, it may also be stored in a computer-readable storage medium.
[0109] The storage medium mentioned above may be a read-only memory, a magnetic disk or an optical disk, etc. Although the embodiments of the present invention have been shown and described above, it can be understood that the above embodiments are exemplary and cannot be understood as limiting the present invention. A person of ordinary skill in the art may change, modify, replace and modify the above embodiments within the scope of the present invention.
Claims
1. A method for evaluating roof stability of concealed empty areas in open-pit coal mines, characterized in that: include: Identify hidden empty areas in open-pit coal mines and obtain empty area shape information of the hidden empty areas; Dividing the roof area of the hidden empty area by a grid method to obtain stress information and displacement information of the roof rock layer of each grid; Obtaining a roof evaluation coefficient of each grid based on the void shape information, the stress information, and the displacement information; The roof warning coefficient is obtained based on the roof assessment coefficients of all grids to evaluate the stability of the empty area roof.
2. The method for evaluating roof stability of a hidden empty area in an open-pit coal mine according to claim 1, characterized in that: The step of obtaining the roof evaluation coefficient of each grid based on the void shape information, the stress information and the displacement information includes: Calculating a stress dynamic risk coefficient of each grid based on the stress information; Calculating the displacement fluctuation coefficient of each grid based on the displacement information; Calculate the spatial characteristic coefficient of the top plate area based on the shape information of the empty area; The roof assessment coefficient of each grid is obtained based on the stress dynamic risk coefficient, the displacement fluctuation coefficient, and the spatial characteristic coefficient.
3. The method for evaluating roof stability of a hidden empty area in an open-pit coal mine according to claim 2, characterized in that: The roof evaluation coefficient of each grid satisfies: Where PG represents the roof assessment coefficient of any grid, α1, α2, and α3 are the proportional coefficients of the stress dynamic risk coefficient, displacement fluctuation coefficient, and spatial characteristic coefficient of the grid, respectively, and YL dt is the stress dynamic risk factor of the grid, WY bd is the displacement fluctuation coefficient of the grid, KJ tz is the spatial characteristic coefficient of the top plate area.
4. The method for evaluating roof stability of a hidden empty area in an open-pit coal mine according to claim 2, characterized in that: The stress information includes horizontal stress and overlying stress per unit time, and the stress dynamic risk coefficient of each grid is calculated based on the stress information, including: Based on the horizontal stress and overlying stress per unit time of each grid, the horizontal stress deviation coefficient and the overlying stress deviation coefficient are calculated respectively, and then the stress dynamic risk coefficient of the corresponding grid is calculated.
5. The method for evaluating roof stability of concealed empty areas in open-pit coal mines according to claim 2, characterized in that: The displacement information includes an initial position of the displacement sensor and a distance from a current position of the displacement sensor to the initial position per unit time. The displacement fluctuation coefficient of each grid is calculated based on the displacement information, including: Based on the initial position of the displacement sensor of each grid and the distance, the average value and standard deviation of the corresponding distance are obtained, and then the displacement fluctuation coefficient of the corresponding grid is calculated.
6. The method for evaluating roof stability of concealed empty areas in open-pit coal mines according to claim 2, characterized in that: The void area shape information includes the span, height and inclination angle of the hidden void area, and the spatial characteristic coefficient of the roof area calculated based on the void area shape information includes: Based on the span, height and inclination angle, the deviations corresponding to the span, height and inclination angle are obtained, and then the spatial characteristic coefficient of the top plate area is calculated.
7. The method for evaluating roof stability of concealed empty areas in open-pit coal mines according to claim 1, characterized in that: The roof assessment coefficient based on all grids is used to obtain the roof warning coefficient to assess the stability of the empty area roof, including: The roof warning coefficient is obtained by calculating the roof assessment coefficient and the roof assessment coefficient threshold of all grids. The stability of the roof of the empty area is determined based on the roof warning coefficient and the roof warning coefficient threshold.
8. A roof stability assessment system for concealed empty areas in open-pit coal mines, characterized in that: include: The first acquisition module is used to identify the hidden empty area of the open-pit coal mine and obtain the empty area shape information of the hidden empty area; The second acquisition module is used to divide the roof area of the hidden empty area by a grid method to obtain stress information and displacement information of the roof rock layer of each grid; A calculation module, used for obtaining a roof evaluation coefficient of each grid based on the void shape information, the stress information and the displacement information; An evaluation module is used to obtain the roof warning coefficient based on the roof evaluation coefficients of all grids to evaluate the stability of the roof of the empty area.
9. An electronic device, characterized in that: include: A processor, and a memory communicatively connected to the processor; The memory stores computer-executable instructions; The processor executes the computer-executable instructions stored in the memory to implement the method according to any one of claims 1 to 7.
10. A computer-readable storage medium, characterized in that: The computer-readable storage medium stores computer-executable instructions, which are used to implement the method according to any one of claims 1 to 7 when executed by a processor.
Citation Information
Patent Citations
Surrounding rock stability evaluation method for tunnel down-traversing goaf
CN110346213A
Coal mine underground reservoir environment risk assessment method
CN112560226A
Method, device and equipment for evaluating stability of goaf
CN115062449A
Method for evaluating monitoring and early warning capability of mine goaf micro-seismic monitoring and early warning system
CN115826037A
Construction method and system for expressway crossing coal seam goaf section
CN117127585A