Power grid equipment verification method, device, equipment and medium

By sorting the configuration data of power grid equipment and querying the template library, automatic verification of power grid equipment is realized, the problem of low human verification accuracy is solved, the accuracy and efficiency of calibration is improved, and the safety of power grid equipment is ensured. run.

CN118941240APending Publication Date: 2024-11-12GUANGDONG POWER GRID CO LTD +1
View PDF 0 Cites 1 Cited by

Patent Information

Application Number
CN202411023711.0
Authority / Receiving Office
CN · China
Patent Type
Applications(China)
Current Assignee / Owner
Filing Date
2024-07-29
Publication Date
2024-11-12

AI Technical Summary

Technical Problem

In the prior art, the verification of power grid equipment depends on manpower, resulting in low accuracy and easy to cause unsafe accidents, especially when there are many types and large quantities of power grid files.

Method used

By obtaining the configuration data of the power grid equipment, classifying it according to the functions to be checked, using the detection templates in the power grid template library for comparison, obtaining the verification results, and improving the accuracy of the verification and resource utilization rate.

Benefits of technology

It improves the accuracy and efficiency of power grid equipment verification, reduces human errors, and improves the safety of power grid equipment.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN118941240A_ABST
    Figure CN118941240A_ABST
Patent Text Reader

Abstract

The invention discloses a power grid equipment verification method and device, equipment and a medium. The method comprises the following steps: acquiring configuration data of power grid equipment; according to at least one to-be-verified function, classifying the configuration data to obtain a to-be-verified data set corresponding to each to-be-verified function; querying in a power grid template library to obtain a detection template corresponding to the power grid equipment; and aiming at each to-be-verified function, comparing the to-be-verified function with the template data set corresponding to the corresponding template element in the detection template to obtain a verification result of the power grid equipment aiming at each to-be-verified function. According to the embodiment of the invention, the accuracy and efficiency of power grid equipment verification can be improved.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The present invention relates to the field of data detection technology, and in particular to a method, device, equipment and medium for verifying power grid equipment. Background Art

[0002] With the rapid development of science and technology, the types of power equipment are gradually increasing. In order to ensure the normal operation of power equipment, operation and maintenance personnel need to regularly check the power grid files of power equipment during the construction, transformation, expansion and troubleshooting of power equipment to ensure the safety of equipment.

[0003] Currently, the contents of power grid documents are verified item by item through manual verification.

[0004] However, there are many types of power grid documents and their number is large, and the accuracy of manual verification is low, which can easily lead to unsafe accidents. Summary of the invention

[0005] The present invention provides a method, device, equipment and medium for verifying power grid equipment, so as to improve the accuracy of verifying power grid equipment.

[0006] In a first aspect, an embodiment of the present invention provides a method for verifying power grid equipment, the method comprising:

[0007] Obtain configuration data of power grid equipment;

[0008] Classifying the configuration data according to at least one function to be verified to obtain a data set to be verified corresponding to each function to be verified;

[0009] Query the power grid template library to obtain the detection template corresponding to the power grid equipment;

[0010] For each function to be verified, a comparison is made with the template data set corresponding to the corresponding template element in the detection template to obtain the verification result of the power grid equipment for each function to be verified.

[0011] In a second aspect, an embodiment of the present invention further provides a power grid equipment verification device, the device comprising:

[0012] A data acquisition module, used to acquire configuration data of power grid equipment;

[0013] A data set acquisition module, used to classify the configuration data according to at least one function to be verified, and obtain a data set to be verified corresponding to each function to be verified;

[0014] The template query module is used to query the power grid template library to obtain the detection template corresponding to the power grid equipment;

[0015] The result acquisition module is used to compare each function to be verified with the template data set corresponding to the corresponding template element in the detection template to obtain the verification result of the power grid equipment for each function to be verified.

[0016] In a third aspect, an embodiment of the present invention further provides a power grid equipment verification device, the power grid equipment verification device comprising:

[0017] at least one processor; and

[0018] a memory communicatively connected to at least one processor; wherein,

[0019] The memory stores a computer program that can be executed by at least one processor. The computer program is executed by at least one processor so that the at least one processor can execute the power grid equipment verification method of any embodiment of the present invention.

[0020] According to another aspect of the present invention, a computer-readable storage medium is provided, wherein the computer-readable storage medium stores computer instructions, and the computer instructions are used to enable a processor to implement the power grid equipment verification method of any embodiment of the present invention when executed.

[0021] The technical solution of the embodiment of the present invention obtains the configuration data of the power grid equipment; classifies the configuration data according to at least one function to be verified, obtains the data set to be verified corresponding to each function to be verified, refines the classification of the configuration data, and improves the accuracy of verification. The detection template corresponding to the power grid equipment is queried in the power grid template library, and the detection template can be reused, which improves resource utilization. For each function to be verified, the template data set corresponding to the corresponding template element in the detection template is compared to obtain the verification result of the power grid equipment for each function to be verified. The data set to be verified corresponding to different functions to be verified is compared with the corresponding template data set, and the comparison operation is more refined, which improves the accuracy of power grid equipment verification.

[0022] It should be understood that the contents described in this section are not intended to identify the key or important features of the embodiments of the present invention, nor are they intended to limit the scope of the present invention. Other features of the present invention will become easily understood through the following description. BRIEF DESCRIPTION OF THE DRAWINGS

[0023] In order to more clearly illustrate the technical solutions in the embodiments of the present invention, the following briefly introduces the drawings required for use in the description of the embodiments. Obviously, the drawings described below are only some embodiments of the present invention. For ordinary technicians in this field, other drawings can be obtained based on these drawings without creative work.

[0024] Figure 1 is a flow chart of a power grid equipment verification method provided according to Embodiment 1 of the present invention;

[0025] Figure 2 is a flow chart of a power grid equipment verification method provided according to Embodiment 2 of the present invention;

[0026] Figure 3 is a structural diagram of a power grid equipment verification device provided according to an embodiment of the present invention;

[0027] Figure 4 It is a structural schematic diagram of a power grid equipment verification device provided by an embodiment of the present invention. DETAILED DESCRIPTION

[0028] In order to enable those skilled in the art to better understand the scheme of the present invention, the technical scheme in the embodiments of the present invention will be clearly and completely described below in conjunction with the drawings in the embodiments of the present invention. Obviously, the described embodiments are only part of the embodiments of the present invention, not all of the embodiments. Based on the embodiments of the present invention, all other embodiments obtained by ordinary technicians in this field without creative work should fall within the scope of protection of the present invention.

[0029] It should be noted that the terms "first", "second", etc. in the specification and claims of the present invention and the above-mentioned drawings are used to distinguish similar objects, and are not necessarily used to describe a specific order or sequence. It should be understood that the data used in this way can be interchanged where appropriate, so that the embodiments of the present invention described herein can be implemented in an order other than those illustrated or described herein. In addition, the terms "including" and "having" and any variations thereof are intended to cover non-exclusive inclusions, for example, a process, method, system, product or device that includes a series of steps or units is not necessarily limited to those steps or units that are clearly listed, but may include other steps or units that are not clearly listed or inherent to these processes, methods, products or devices.

[0030] In the technical solution of the embodiment of the present invention, the acquisition, storage and application of the current operation ticket instructions, etc. are in compliance with the provisions of relevant laws and regulations and do not violate public order and good morals.

[0031] Embodiment 1

[0032] Figure 1 This is a flow chart of a power grid equipment verification method provided in Embodiment 1 of the present invention. The embodiment of the present invention is applicable to power grid equipment verification, and the method can be executed by a power grid equipment verification device, which can be implemented in the form of hardware and / or software.

[0033] See also Figure 1 The power grid equipment verification method shown includes:

[0034] S101. Obtain configuration data of power grid equipment.

[0035] The power grid equipment may be equipment in a smart substation that can manage power resources in a digital manner. The configuration data may be data pre-configured for the power grid equipment to ensure normal operation of the power grid equipment.

[0036] Specifically, a smart substation is a substation that uses reliable, economical, integrated, low-carbon and environmentally friendly equipment, with the basic requirements of digitalization of the entire station information, networking of the communication platform, standardization of information sharing, integration of system functions, compact structure design, intelligence of high-voltage equipment and visualization of operation status, so as to realize real-time online analysis and control decision-making of the power grid, thereby improving the reliability and economy of the entire power grid operation. A smart substation can automatically complete basic functions such as information collection, measurement, control, protection, metering and detection, and at the same time, it has the ability to support real-time automatic control, intelligent regulation, online analysis and decision-making, and collaborative interaction of the power grid. Configuration data can be data containing basic functions such as automatic completion of information collection, measurement, control, protection, metering and detection, and has information that supports real-time automatic control, intelligent regulation, and online analysis and decision-making of the power grid. The configuration data of the power grid equipment is obtained, and the acquisition method includes but is not limited to: sequential search algorithm, binary search algorithm, tree table search algorithm or hash search algorithm, etc., which is not limited in the embodiment of the present invention.

[0037] In an example, the configuration data of the power grid device 1 obtained by the sequential search algorithm is file identification: file identification 1; line: bus, circuit breaker, switch and transformer; device model: model 1; data: received data set 1 received data set 2 received data set 3.

[0038] S102: Classify the configuration data according to at least one function to be verified, and obtain a set of data to be verified corresponding to each function to be verified.

[0039] The function to be verified may be a function to be verified on the configuration data, and the data set to be verified may be a data set after the configuration data is classified according to the function to be verified.

[0040] Specifically, different configuration data can verify different functions of power grid equipment. According to the indicators of the configuration data to be verified corresponding to the verification function, the configuration data is classified to obtain the data set to be verified corresponding to each verification function. The data set to be verified includes at least one indicator of the configuration data and the value of the configuration data corresponding to the indicator.

[0041] In one example, the function to be verified is a file verification function, and the corresponding data set to be verified is file identification: file identification 1. The function to be verified is a line verification function, and the corresponding data set to be verified is line: bus, measurement and control, and intelligent terminal.

[0042] S103: Query and obtain a detection template corresponding to the power grid equipment in the power grid template library.

[0043] The detection template may be a template for detecting configuration data of a power grid device. The power grid template library may be a collection of detection templates for power grid devices.

[0044] Specifically, different power grid devices correspond to different configuration data, and therefore, different power grid devices correspond to different detection templates. The detection templates corresponding to each power grid device are stored in a power grid template library. Different power grid devices have different identifiers, and different detection templates have different identifiers. Power grid devices correspond to detection templates one by one, and the detection template corresponding to the identifier of the power grid device can be queried in the power grid template library according to the identifier of the power grid device.

[0045] In one example, the identification of the power grid equipment is 500KV_transformer_version 2A10-35_measurement and control device B2A10-35. The identification of the detection template 1 corresponding to the power grid equipment obtained by querying the power grid template library is 500KV_transformer_version 2A10-35_measurement and control device B2A10-35 and 500KV_transformer_version 2A10-35_measurement and control device B2A10-36. The detection template corresponding to the identification 500KV_transformer_version 2A10-35_measurement and control device B2A10-35 is queried in the power grid template library through a sequential search algorithm.

[0046] S104 . For each function to be verified, compare the template data set corresponding to the corresponding template element in the detection template to obtain a verification result of the power grid device for each function to be verified.

[0047] The template element may be an identifier of a data set corresponding to the function to be verified in the detection template. The template data set may be a set of data for verifying the configuration data corresponding to the function to be verified in the detection template.

[0048] Specifically, different functions to be verified correspond to different configuration data to be verified, so different functions to be verified correspond to different template data in the detection template. The detection template contains at least one template element, and the template element corresponds to the function to be verified one by one. One template element corresponds to one template data set. The configuration data corresponding to each function to be verified is compared with the data in the template data set of the template element corresponding to each function to be verified, and the verification result of the power grid equipment for each function to be verified is obtained.

[0049] In one example, the function to be verified is file verification, and the data set to be verified corresponding to the function to be verified is file identification: file identification 1. When the function to be verified is file verification, the template data set corresponding to the template element corresponding to the function to be verified in the detection template is file identification: file identification 1. The data set to be verified corresponding to the function to be verified is compared with the template data set corresponding to the template element corresponding to the function to be verified, and the verification result of the power grid device for each function to be verified is passed verification.

[0050] The technical solution of the embodiment of the present invention obtains the configuration data of the power grid equipment; classifies the configuration data according to at least one function to be verified, obtains the data set to be verified corresponding to each function to be verified, refines the classification of the configuration data, and improves the accuracy of verification. The detection template corresponding to the power grid equipment is queried in the power grid template library, and the detection template can be reused, which improves resource utilization. For each function to be verified, the template data set corresponding to the corresponding template element in the detection template is compared to obtain the verification result of the power grid equipment for each function to be verified. The data set to be verified corresponding to different functions to be verified is compared with the corresponding template data set, and the comparison operation is more refined, which improves the accuracy of power grid equipment verification.

[0051] Optionally, after comparing each function to be verified with the template data set corresponding to the corresponding template element in the detection template to obtain the verification result of the power grid equipment for each function to be verified, it also includes: matching the data set to be verified corresponding to each function to be verified with the configuration data of the power grid equipment to obtain the number of matching items; identifying the configuration data of the power grid equipment to obtain the number of configuration items; and calculating the classification accuracy based on the number of matching items and the number of configuration items.

[0052] The number of matching items may be the cumulative number of the same number of indicators in the to-be-verified data set corresponding to each to-be-verified function and the indicators in the configuration data of the power grid device. The number of configuration items may be the number of indicators in the configuration data. The classification accuracy may be the accuracy of classifying the configuration data according to the to-be-verified function.

[0053] Specifically, the configuration data corresponding to the power grid equipment includes at least one indicator. Different functions to be verified have different corresponding indicators. The indicators corresponding to the classified verification functions can be matched with the indicators in the configuration data to obtain the number of matching items in which the indicators corresponding to the verification functions are the same as the indicators in the configuration data. The configuration data can be identified to obtain the number of original indicators in the configuration data and the number of configuration items. The ratio of the number of matching items to the number of configuration items is calculated to obtain the classification accuracy.

[0054] In one example, the configuration data of the power grid equipment is identified, and the indicators in the configuration data are file identification, device identification and device model, and the number of configuration items is 3. The indicators of the data set to be verified corresponding to the verification function 1 are device identification and device model. The data set to be verified corresponding to the function to be verified is matched with the configuration data of the power grid equipment, and the number of matching items is 2. The ratio of the number of matching items to the number of configuration items is calculated, and the classification accuracy is 66.7%.

[0055] The number of matching items is obtained by matching the data sets to be verified corresponding to each function to be verified with the configuration data of the power grid equipment; the configuration data of the power grid equipment is identified to obtain the number of configuration items; the classification accuracy is calculated based on the number of matching items and the number of configuration items, the classification algorithm can be tested to obtain the accuracy of the classification algorithm detection, and the classification algorithm can be adjusted according to the calculation results to improve the accuracy of power grid equipment verification.

[0056] Optionally, configuration data, including: secondary loop instance configuration file data.

[0057] Among them, the secondary circuit instance configuration file data can be data for automatically completing basic functions such as information collection, measurement, control, protection, metering and detection of power equipment configuration.

[0058] Specifically, the secondary circuit is an electrical circuit formed by interconnecting secondary devices in the power system, which is used to monitor, control, adjust and protect the primary equipment. The secondary circuit includes all low-voltage circuits such as measurement circuits, relay protection circuits, switch control and signal circuits, operating power circuits, and electrical interlocking circuits of circuit breakers and disconnectors. Electrical equipment for power generation, transmission, distribution or other production processes is called primary equipment. Secondary equipment refers to low-voltage electrical equipment required to monitor, control, adjust, protect the operation of primary equipment and provide operating conditions or production command signals for operation and maintenance personnel, such as fuses, control switches, relays and control cables. In the electrical system, the secondary circuit is a circuit connected by the secondary winding of the mutual inductor, measuring and monitoring instruments, relays and automatic devices through control cables to control, protect, adjust, measure and monitor the working conditions of various parameters and components in the primary circuit. Secondary circuit instance configuration file data can be a collection of data configured for equipment in the secondary circuit to ensure the normal operation of power grid equipment.

[0059] In one example, secondary circuit instance configuration file data of a power grid device is obtained, and the secondary circuit instance configuration file data is classified according to at least one function to be verified to obtain a data set to be verified corresponding to each function to be verified, and a detection template corresponding to the power grid device is queried in a power grid template library; for each function to be verified, a comparison is made with a template data set corresponding to a corresponding template element in the detection template to obtain a verification result of the power grid device for each function to be verified.

[0060] By acquiring the secondary circuit instance configuration file data of the power grid equipment and detecting the secondary circuit instance configuration file data of the power grid equipment, the configuration result of the configuration information of the secondary circuit power grid equipment can be automatically detected without manual detection, thereby improving the efficiency of power grid equipment verification.

[0061] Embodiment 2

[0062] Figure 2 This is a flow chart of a power grid equipment verification method provided by Embodiment 2 of the present invention. Based on the above embodiments, this embodiment of the present invention optimizes and improves the power grid equipment verification operation.

[0063] Further, "for each function to be verified, compare the template data set corresponding to the corresponding template element in the detection template to obtain the verification result of the power grid equipment for each function to be verified" is refined into "obtaining the position order between the corresponding template elements in the detection template; for each function to be verified, sort the data sets to be verified corresponding to each function to be verified according to the position order between the corresponding template elements to obtain the sorting result; according to the sorting result, select the current data set from each data set to be verified; compare the current data set with the template data set of the corresponding template element to obtain the comparison result of the current data set; when the comparison result is that the verification is passed, return to execute according to the sorting result, select the current data set from each data set to be verified, until all data sets to be verified are selected; when the comparison result is that the verification is not passed, determine the fault detection result of the power grid equipment according to the comparison result", so as to improve the operation of power grid equipment verification.

[0064] It should be noted that for parts not described in detail in the embodiments of the present invention, reference may be made to descriptions of other embodiments.

[0065] See also Figure 2 The power grid equipment verification method shown includes:

[0066] S201. Obtain configuration data of power grid equipment.

[0067] S202: Classify the configuration data according to at least one function to be verified, and obtain a set of data to be verified corresponding to each function to be verified.

[0068] S203: Query the power grid template library to obtain a detection template corresponding to the power grid equipment.

[0069] S204: Obtain the position sequence between corresponding template elements in the detection template.

[0070] The position order may be used to describe the order of physical addresses stored in each template element in the detection template.

[0071] Specifically, at least one template element is stored in the detection template. Each template element is stored at a different physical address. There is a sequential position relationship between each template element. The position order between each corresponding template element in the detection template can be obtained by a search algorithm, and the search method includes but is not limited to: breadth-first traversal and depth-first traversal, etc., which is not limited in the embodiment of the present invention.

[0072] In one example, the search is performed in a depth-first traversal manner, and the position order between the template elements in the detection template is obtained as the file check element and the line check element.

[0073] S205 , for each function to be verified, sort the data sets to be verified corresponding to each function to be verified according to the position sequence between the corresponding template elements to obtain a sorting result.

[0074] The sorting result may be a result of sorting the data sets to be verified corresponding to the functions to be verified in order of position.

[0075] Specifically, the configuration data of the power grid device includes at least one data set to be verified corresponding to a function to be verified. According to the position order between the template elements in the detection template corresponding to the power grid device, the data set to be verified corresponding to the template element is searched in each data set to be verified, and the found data sets to be verified are arranged in sequence to obtain the sorting results of each data set to be verified. The search method includes but is not limited to: binary search algorithm, hash search algorithm, tree table search algorithm or sequential search algorithm, etc., which is not limited in the embodiment of the present invention.

[0076] In one example, the position order between the template elements of the detection template corresponding to the power grid device 1 is the file verification element and the line verification element. The configuration data of the power grid device includes a data set 2 to be verified corresponding to the line verification function and a data set 1 to be verified corresponding to the file verification function. According to the position order between the template elements of the detection template corresponding to the power grid device 1, the data sets to be verified corresponding to each function to be verified are sorted, and the sorting results are data set 1 to be verified and data set 2 to be verified.

[0077] S206 . According to the sorting result, select a current data set from each data set to be verified; compare the current data set with the template data set of the corresponding template element to obtain a comparison result of the current data set.

[0078] The current data set may be a data set to be compared with the template data set at the current time, and the comparison result of the current data set may be the result of comparing the current data set with the template data set at the current time.

[0079] Specifically, different functions to be verified correspond to different data sets to be compared. According to the function to be verified, a current data set is selected from each data set to be verified, and the current data set is compared with the template data set of the corresponding template element to obtain a comparison result of the current data set. The data set to be verified corresponding to the function to be verified includes at least one indicator to be verified. The template data set corresponding to the template element corresponding to the function to be verified includes at least one preset indicator. The positional order between the indicators in the data set to be verified corresponding to the function to be verified is the same as the positional order between the indicators in the template data set corresponding to the template element corresponding to the function to be verified. According to the sorting result, the current data set is selected from each data set to be verified, and the value of the indicator in the current data set is compared with the value of the corresponding indicator in the template data set of the corresponding template element to obtain a comparison result of the current data set.

[0080] In one example, as shown in the previous example, the sorting results are data set 1 to be verified and data set 2 to be verified. The function to be verified is a file verification function, and the indicator included in data set 1 to be verified is a file identifier, and the value corresponding to the indicator is file identifier 1. The template element corresponding to the function to be verified is a file verification element. The indicator included in the template data set corresponding to the file verification element is a file identifier, and the value corresponding to the indicator is file identifier 1. Data set 1 to be verified is selected as the current data set. File identifier 1 in data set 1 to be verified is compared with file identifier 1 in the template data set corresponding to the file verification element, and the comparison result of the current data set is passed verification.

[0081] S207 , when the comparison result is that the verification fails, returning to the execution, selecting the current data set from each of the to-be-verified data sets according to the sorting result, until all of the to-be-verified data sets have been selected.

[0082] Specifically, different data sets to be verified have different verification functions, and different functions of the configuration data of the power grid equipment can be verified. In the process of verifying the power grid equipment, not all data sets to be verified may be verified, and it may be determined whether to continue to compare the next data set to be verified based on the comparison result of the current data set. When the comparison result is that the verification fails, the execution returns to select the current data set from each data set to be verified according to the sorting result, and compares the current data set with the template data set of the corresponding template element to obtain the comparison result of the current data set. Until all data sets to be verified are selected, the fault location can be performed to obtain the data set to be verified corresponding to the fault, the indicators in the data set, and the values ​​of the indicators.

[0083] In one example, the sorting results are data set 1 to be verified and data set 2 to be verified. The function to be verified is a file verification function, and the indicator included in data set 1 to be verified is a file identification, and the value corresponding to the indicator is file identification 1. The template element corresponding to the function to be verified is a file verification element. The indicator included in the template data set corresponding to the file verification element is a file identification, and the value corresponding to the indicator is file identification 2. Data set 1 to be verified is selected as the current data set. File identification 1 in data set 1 to be verified is compared with file identification 2 in the template data set corresponding to the file verification element, and the comparison result of the current data set is that the verification fails. Data set 2 to be verified is obtained, the indicator in data set 2 to be verified is the line, and the value corresponding to the line is the bus, measurement and control, and intelligent terminal, the indicator in the template data set corresponding to data set 2 to be verified is the line, and the value corresponding to the line is the bus,, measurement and control, and intelligent terminal, the value corresponding to the indicator in data set 2 to be verified is compared with the value of the indicator in the template data set corresponding to data set 2 to be verified, and the comparison result is that the verification passes.

[0084] S208. When the comparison result is that the verification is passed, determine the verification result of the power grid equipment according to the comparison result.

[0085] The verification result may be the result of the verification of the power grid equipment by the function to be verified.

[0086] Specifically, for each function to be verified, the data sets to be verified corresponding to each function to be verified are sorted according to the position order between the corresponding template elements to obtain the sorting result. According to the sorting result, the current data set is selected from each data set to be verified, and the current data set is compared with the template data set of the corresponding template element. When the comparison result is a pass-verification, the verification result of the power grid device is determined according to the comparison result. When the data set to be verified is a data set corresponding to the file verification function, the data set is compared with the data set corresponding to the file verification element (CRC check code). If the comparison result is a pass-verification, it means that the configuration data corresponding to the power grid device is consistent with the configuration file corresponding to the template data set corresponding to the file verification element, and the verification is no longer continued. It is determined that the verification result corresponding to the power grid device is consistent with the file verification. For example, the file can be a CCD file. If the comparison result is that the verification fails, the next data set to be verified is compared. When the data set to be verified is the data set corresponding to the line verification function, the data set is compared with the data set corresponding to the line verification element (IED element). If the comparison result is that the verification fails, the verification is no longer continued, indicating that the configuration data corresponding to the power grid equipment and the line corresponding to the template data set corresponding to the line verification element are inconsistent. If the comparison result is that the verification passes, it is determined that the verification result corresponding to the power grid equipment is consistent with the line verification, and then the next data set to be verified is compared. When the data set to be verified is the data set corresponding to the model verification function, the data set is compared with the data set corresponding to the model verification element (GOOSEPUB element). If the comparison result is that the verification fails, the verification is no longer continued, indicating that the configuration data corresponding to the power grid equipment and the line corresponding to the template data set corresponding to the line verification element are inconsistent. If the verification fails, the verification will not be continued. If the comparison result is that the verification is passed, it means that the configuration data corresponding to the power grid device and the model corresponding to the template data set corresponding to the model verification element are consistent, then the next data set to be verified is compared. When the data set to be verified is the data set corresponding to the data verification function, the data set is compared with the data set corresponding to the data verification element (GOOSESUB element). If the comparison result is that the verification is passed, it means that the configuration data corresponding to the power grid device and the model corresponding to the template data set corresponding to the data verification element are consistent. If the comparison result is that the verification is not passed, it means that the configuration data corresponding to the power grid device and the model corresponding to the template data set corresponding to the data verification element are inconsistent. At this point, all data verification is completed.

[0087] In one example, the function to be verified is a file verification function, the indicator included in the data set 1 to be verified is a file identifier, and the value corresponding to the indicator is file identifier 1. The template element corresponding to the function to be verified is a file verification element. The indicator included in the template data set corresponding to the file verification element is a file identifier, and the value corresponding to the indicator is file identifier 1. Data set 1 to be verified is selected as the current data set. File identifier 1 in data set 1 to be verified is compared with file identifier 1 in the template data set corresponding to the file verification element. If the comparison result of the current data set is that the verification is passed, the verification is no longer continued, and it is determined that the verification result corresponding to the power grid equipment is consistent with the file verification.

[0088] The embodiment of the present invention obtains the position sequence between each corresponding template element in the detection template, and for each function to be verified, sorts the data sets to be verified corresponding to each function to be verified according to the position sequence between each corresponding template element to obtain a sorting result, selects the current data set from each data set to be verified according to the sorting result, compares the current data set with the template data set of the corresponding template element to obtain a comparison result of the current data set, and when the comparison result is that the verification is passed, returns to execute the selection of the current data set from each data set to be verified according to the sorting result until all the data sets to be verified are selected, and when the comparison result is that the verification is not passed, determines the fault detection result of the power grid equipment according to the comparison result, and performs different operations according to the comparison result, and does not need to compare all the data sets to be verified, thereby improving the efficiency of power grid equipment verification.

[0089] Optional template elements include: file verification elements, line verification elements, equipment verification elements and data verification elements.

[0090] Among them, the file verification element may be the identifier of the template data set, which is used to verify whether the data of the data set to be verified is the same as the file to which the template data set corresponding to the data set to be verified belongs. The line verification element may be the identifier of the template data set, which is used to verify whether the device line corresponding to the data of the data set to be verified is the same as the line of the device corresponding to the template data set corresponding to the data set to be verified. The device verification element may be the identifier of the template data set, which is used to verify whether the device model corresponding to the data of the data set to be verified is the same as the model of the device corresponding to the template data set corresponding to the data set to be verified. The data verification element may be the identifier of the template data set, which is used to verify whether the data arrangement of the data set to be verified is the same as the data arrangement of the template data set corresponding to the data set to be verified.

[0091] Specifically, the file check element may be a CRC check code, the line check element may be an IED element, the device check element may be a GOOSEPUB element, and the data check element may be a GOOSESUB element.

[0092] Through template elements, including: file verification elements, line verification elements, equipment verification elements and data verification elements, the data in the detection template are classified through different template elements, and different operations are performed according to different classifications, which refines the power grid equipment verification operation and improves the accuracy of power grid equipment verification.

[0093] Optionally, a power grid template library includes: obtaining at least one operating voltage data, at least one device type, at least one device version number and at least one device measurement and control device; arranging and combining each operating voltage data, each device type, each device version number and each device measurement and control device to generate at least one file identification group; according to each file identification group, querying the loop configuration file, preset parameter file and historical fault data file corresponding to each file identification group; fusing the loop configuration data, preset parameter data and historical fault data corresponding to each file identification group to obtain the power grid template library.

[0094] Among them, the operating voltage data can be the actual working voltage of the power grid equipment. The equipment type can be the type of the power grid equipment. The equipment version number can be the identifier of the updated version of the power grid equipment. The equipment measurement and control device can be the identifier of the measurement and control device of the power grid equipment. The file identification group can be a string generated by the arrangement and combination of each operating voltage data, each equipment type, each equipment version number and each equipment measurement and control device. The loop configuration file can be a collection of configuration indicators of the power grid equipment and the values ​​corresponding to the indicators. The preset parameter file can be a collection of configuration indicators of the power grid equipment preset according to industry experience and the values ​​corresponding to the indicators. The historical fault data file can be a collection of fault indicators of power grid equipment that have failed in a historical time period and the values ​​corresponding to the indicators.

[0095] Specifically, at least one operating voltage data, at least one device type, at least one device version number and at least one device measurement and control device are obtained, and each operating voltage data, each device type, each device version number and each device measurement and control device are arranged and combined to generate at least one file identification group. According to each file identification group, the loop configuration file, preset parameter file and historical fault data file corresponding to each file identification group are queried, and the loop configuration data, preset parameter data and historical fault data corresponding to each file identification group are merged to obtain a power grid template library, and the file name of the detection template in the power grid template library is the same as the corresponding file identification group. The file identification group corresponds to the detection template one by one.

[0096] In an example, the operating voltage data of 500KV and 1000KV, the equipment types of transformer and lightning arrester, the equipment version numbers of 2.1 and 2.2, and the equipment measurement and control devices of CE1 and CE2 are obtained, and the operating voltage data, equipment types, equipment version numbers and equipment measurement and control devices are arranged and combined to generate file identification groups of 500KV_transformer_version 2.1_measurement and control device CE1 and 1000KV_transformer_version 2.2_measurement and control device CE2, and according to each file identification group, the loop configuration file, preset parameter file and historical fault data file corresponding to each file identification group are queried, and the loop configuration data, preset parameter data and historical fault data corresponding to each file identification group are merged to obtain a power grid template library, which includes detection templates identified as 500KV_transformer_version 2.1_measurement and control device CE1 and 1000KV_transformer_version 2.2_measurement and control device CE2.

[0097] By acquiring at least one operating voltage data, at least one device type, at least one device version number and at least one device measurement and control device; arranging and combining each operating voltage data, each device type, each device version number and each device measurement and control device to generate at least one file identification group; according to each file identification group, querying the loop configuration file, preset parameter file and historical fault data file corresponding to each file identification group; fusing the loop configuration data, preset parameter data and historical fault data corresponding to each file identification group to obtain a power grid template library, generating the power grid template library through multi-dimensional data, the data in the power grid template library is more comprehensive, which is convenient for power grid equipment verification and improves the accuracy of power grid equipment verification.

[0098] Optionally, a detection template corresponding to the power grid equipment is queried in the power grid template library, including: obtaining the identifier to be checked corresponding to the power grid equipment; performing string segmentation processing on the identifier to be checked to obtain at least one segmentation identifier; arranging and combining each segmentation identifier to obtain at least one segmentation identifier group; and screening in the power grid template library according to each segmentation identifier group to obtain a detection template.

[0099] The identifier to be verified may be the identifier of the power grid device to be verified. The segmented identifier may be a character string obtained by segmenting the identifier to be verified. The segmented identifier group may be a character string formed by arranging and combining the segmented identifiers.

[0100] Specifically, obtain the identification to be verified corresponding to the power grid equipment. The identification to be verified is composed of multiple character strings with identification functions, and different character strings identify different information of the power grid equipment. For example, the character string can be a device identification, a device model, or a measurement and control device. Perform character string segmentation processing on the identification to be verified to obtain at least one segmentation identification, arrange and combine the separation identifications to obtain at least one segmentation identification group, and screen in the power grid template library according to the segmentation identification groups, screen the identification that is the same as any segmentation identification group in each segmentation identification group, and determine the detection template corresponding to the identification as the detection template corresponding to the power grid equipment.

[0101] In one example, the identification of the power grid equipment is 500KV_transformer_version 2A10-35_measurement and control device B2A10-35. The identification to be checked is subjected to string segmentation processing, and the segmentation identification is obtained as 500KV, transformer, version 2A10-35 and measurement and control device B2A10-35. Each separation identification is arranged and combined to obtain a segmentation identification group of 500KV_transformer_version 2A10-35_measurement and control device B2A10-35, transformer_500KV_version 2A10-35_measurement and control device B2A10-35, 500KV_transformer_measurement and control device B2A10-35_version 2A10-35, etc. According to each segmentation identification group, screening is performed in the power grid template library to find the detection template identified as transformer_500KV_version 2A10-35_measurement and control device B2A10-35, and the detection template is used as the detection template corresponding to the power grid equipment.

[0102] pass.

[0103] Embodiment 3

[0104] Figure 3 The present invention is a schematic diagram of a structure of a power grid equipment verification device provided in Embodiment 3 of the present invention. The present invention is applicable to the situation of power grid equipment verification, the device can execute the power grid equipment verification method, and the device can be implemented in the form of hardware and / or software.

[0105] See also Figure 3 The power grid equipment verification device shown includes: a data acquisition module 301, a data set acquisition module 302, a template query module 303 and a result acquisition module 304, wherein:

[0106] The data acquisition module 301 is used to acquire the configuration data of the power grid equipment;

[0107] The data set acquisition module 302 is used to classify the configuration data according to at least one function to be verified, and obtain a data set to be verified corresponding to each function to be verified;

[0108] The template query module 303 is used to query the power grid template library to obtain the detection template corresponding to the power grid equipment;

[0109] The result acquisition module 304 is used to compare each function to be verified with the template data set corresponding to the corresponding template element in the detection template to obtain the verification result of the power grid device for each function to be verified.

[0110] The technical solution of the embodiment of the present invention obtains the configuration data of the power grid equipment; classifies the configuration data according to at least one function to be verified, obtains the data set to be verified corresponding to each function to be verified, refines the classification of the configuration data, and improves the accuracy of verification. The detection template corresponding to the power grid equipment is queried in the power grid template library, and the detection template can be reused, which improves resource utilization. For each function to be verified, the template data set corresponding to the corresponding template element in the detection template is compared to obtain the verification result of the power grid equipment for each function to be verified. The data set to be verified corresponding to different functions to be verified is compared with the corresponding template data set, and the comparison operation is more refined, which improves the accuracy of power grid equipment verification.

[0111] Optionally, the result acquisition module 304 includes:

[0112] A sequence detection unit, used to obtain the position sequence between corresponding template elements in the detection template;

[0113] A data sorting unit is used to sort the to-be-checked data sets corresponding to each to-be-checked function according to the position order between the corresponding template elements, and obtain a sorting result;

[0114] A data comparison unit is used to select a current data set from each data set to be verified according to the sorting result; compare the current data set with the template data set of the corresponding template element to obtain a comparison result of the current data set;

[0115] The data set selection unit is used to return to the execution of selecting the current data set from each data set to be verified according to the sorting result when the comparison result is that the verification fails, until all the data sets to be verified are selected;

[0116] The detection data acquisition unit is used to determine the verification result of the power grid equipment according to the comparison result when the comparison result is that the verification is passed.

[0117] Optional template elements, including:

[0118] File check elements, line check elements, equipment check elements and data check elements.

[0119] Optional, grid template library, specifically used for:

[0120] Obtain at least one operating voltage data, at least one device type, at least one device version number, and at least one device measurement and control device;

[0121] Arrange and combine the operating voltage data, the device types, the device version numbers and the device measurement and control devices to generate at least one file identification group;

[0122] According to each file identification group, query the loop configuration file, preset parameter file and historical fault data file corresponding to each file identification group;

[0123] The loop configuration data, preset parameter data and historical fault data corresponding to each file identification group are integrated to obtain a power grid template library.

[0124] Optionally, the template query module 303 is specifically used for:

[0125] Obtain the identification to be verified corresponding to the power grid equipment;

[0126] Performing character string segmentation processing on the mark to be checked to obtain at least one segmentation mark;

[0127] Arrange and combine the separation marks to obtain at least one segmentation representation group;

[0128] According to each segmentation representation group, a detection template is obtained by screening in the power grid template library.

[0129] Optionally, the power grid equipment verification device further includes:

[0130] A matching item number acquisition module is used to compare each function to be verified with a template data set corresponding to a corresponding template element in a detection template, obtain a verification result of the power grid device for each function to be verified, and then match the data set to be verified corresponding to each function to be verified with the configuration data of the power grid device to obtain the number of matching items;

[0131] A configuration item number acquisition module is used to identify the configuration data of the power grid equipment and obtain the number of configuration items;

[0132] The accuracy acquisition module is used to calculate the classification accuracy based on the number of matching items and the number of configuration items.

[0133] Optionally, the power grid file to be detected includes: a secondary circuit instance configuration file.

[0134] The power grid equipment verification device provided in the embodiment of the present invention can execute the power grid equipment verification method provided in any embodiment of the present invention, and has the corresponding functional modules and beneficial effects for executing the power grid equipment verification method.

[0135] Embodiment 4

[0136] Figure 4A schematic structural diagram of a power grid equipment verification device 400 that can be used to implement an embodiment of the present invention is shown.

[0137] like Figure 4 As shown, the power grid equipment verification device 400 includes at least one processor 401, and a memory connected to the at least one processor 401 in communication, such as a read-only memory (ROM) 402, a random access memory (RAM) 403, etc., wherein the memory stores a computer program that can be executed by at least one processor, and the processor 401 can perform various appropriate actions and processes according to the computer program stored in the read-only memory (ROM) 402 or the computer program loaded from the storage unit 408 to the random access memory (RAM) 403. In RAM403, various programs and data required for the operation of the power grid equipment verification device 400 can also be stored. The processor 401, ROM402 and RAM403 are connected to each other through a bus 404. An input / output (I / O) interface 405 is also connected to the bus 404.

[0138] Multiple components in the power grid equipment verification device 400 are connected to the I / O interface 405, including: an input unit 406, such as a keyboard, a mouse, etc.; an output unit 407, such as various types of displays, speakers, etc.; a storage unit 408, such as a disk, an optical disk, etc.; and a communication unit 409, such as a network card, a modem, a wireless communication transceiver, etc. The communication unit 409 allows the power grid equipment verification device 400 to exchange information / data with other devices through a computer network such as the Internet and / or various telecommunication networks.

[0139] Processor 401 may be a variety of general and / or special processing components with processing and computing capabilities. Some examples of processor 401 include, but are not limited to, a central processing unit (CPU), a graphics processing unit (GPU), various dedicated artificial intelligence (AI) computing chips, various processors running machine learning model algorithms, digital signal processors (DSPs), and any appropriate processors, controllers, microcontrollers, etc. Processor 501 executes the various methods and processes described above, such as a power grid equipment verification method.

[0140] In some embodiments, the power grid device verification method may be implemented as a computer program, which is tangibly contained in a computer-readable storage medium, such as a storage unit 408. In some embodiments, part or all of the computer program may be loaded and / or installed on the power grid device verification device 400 via the ROM 402 and / or the communication unit 409. When the computer program is loaded into the RAM 403 and executed by the processor 401, one or more steps of the power grid device verification method described above may be performed. Alternatively, in other embodiments, the processor 401 may be configured to execute the power grid device verification method in any other appropriate manner (e.g., by means of firmware).

[0141] Various implementations of the systems and techniques described above herein can be implemented in digital electronic circuit systems, integrated circuit systems, field programmable gate arrays (FPGAs), application specific integrated circuits (ASICs), application specific standard products (ASSPs), systems on chips (SOCs), complex programmable logic devices (CPLDs), computer hardware, firmware, software, and / or combinations thereof. These various implementations can include: being implemented in one or more computer programs that can be executed and / or interpreted on a programmable system including at least one programmable processor, which can be a special purpose or general purpose programmable processor that can receive data and instructions from a storage system, at least one input device, and at least one output device, and transmit data and instructions to the storage system, the at least one input device, and the at least one output device.

[0142] Computer programs for implementing the methods of the present invention may be written in any combination of one or more programming languages. These computer programs may be provided to a processor of a general-purpose computer, a special-purpose computer, or other programmable data processing device, so that when the computer program is executed by the processor, the functions / operations specified in the flow chart and / or block diagram are implemented. The computer program may be executed entirely on the machine, partially on the machine, partially on the machine and partially on a remote machine as a stand-alone software package, or entirely on a remote machine or server.

[0143] In the context of the present invention, a computer-readable storage medium may be a tangible medium that may contain or store a computer program for use by or in combination with an instruction execution system, device or equipment. A computer-readable storage medium may include, but is not limited to, electronic, magnetic, optical, electromagnetic, infrared, or semiconductor systems, devices or equipment, or any suitable combination of the foregoing. Alternatively, a computer-readable storage medium may be a machine-readable signal medium. A more specific example of a machine-readable storage medium may include an electrical connection based on one or more lines, a portable computer disk, a hard disk, a random access memory (RAM), a read-only memory (ROM), an erasable programmable read-only memory (EPROM or flash memory), an optical fiber, a portable compact disk read-only memory (CD-ROM), an optical storage device, a magnetic storage device, or any suitable combination of the foregoing.

[0144] In order to provide interaction with a user, the systems and techniques described herein may be implemented on an operation detection device, which has: a display device (e.g., a CRT (cathode ray tube) or LCD (liquid crystal display) monitor) for displaying information to a user; and a keyboard and a pointing device (e.g., a mouse or a trackball), through which a user can provide input to the power grid equipment verification device. Other types of devices may also be used to provide interaction with a user; for example, the feedback provided to the user may be any form of sensory feedback (e.g., visual feedback, auditory feedback, or tactile feedback); and input from the user may be received in any form (including acoustic input, voice input, or tactile input).

[0145] The systems and techniques described herein may be implemented in a computing system that includes backend components (e.g., as a data server), or a computing system that includes middleware components (e.g., an application server), or a computing system that includes frontend components (e.g., a user computer with a graphical user interface or a web browser through which a user can interact with implementations of the systems and techniques described herein), or a computing system that includes any combination of such backend components, middleware components, or frontend components. The components of the system may be interconnected by any form or medium of digital data communication (e.g., a communication network). Examples of communication networks include: a local area network (LAN), a wide area network (WAN), a blockchain network, and the Internet.

[0146] A computing system may include a client and a server. The client and the server are generally remote from each other and usually interact through a communication network. The relationship between the client and the server is generated by computer programs running on the corresponding computers and having a client-server relationship with each other. The server may be a cloud server, also known as a cloud computing server or a cloud host, which is a host product in the cloud computing service system to solve the defects of difficult management and weak business scalability in traditional physical hosts and VPS (Virtual Private Server) services.

[0147] It should be understood that the various forms of processes shown above can be used to reorder, add or delete steps. For example, the steps described in the present invention can be executed in parallel, sequentially or in different orders, as long as the desired results of the technical solution of the present invention can be achieved, and this document does not limit this.

[0148] The above specific implementations do not constitute a limitation on the protection scope of the present invention. It should be understood by those skilled in the art that various modifications, combinations, sub-combinations and substitutions can be made according to design requirements and other factors. Any modification, equivalent substitution and improvement made within the spirit and principle of the present invention should be included in the protection scope of the present invention.

Claims

1. A method for verifying power grid equipment, characterized in that: The method comprises: Obtain configuration data of power grid equipment; Classifying the configuration data according to at least one function to be verified to obtain a data set to be verified corresponding to each function to be verified; Querying a power grid template library to obtain a detection template corresponding to the power grid device; For each of the functions to be verified, a comparison is made with the template data set corresponding to the corresponding template element in the detection template to obtain a verification result of the power grid device for each of the functions to be verified.

2. The method according to claim 1, characterized in that The comparing, for each of the functions to be verified, with the template data set corresponding to the corresponding template element in the detection template to obtain the verification result of the power grid device for each of the functions to be verified, includes: Obtaining the position order between the corresponding template elements in the detection template; For each of the functions to be verified, sorting the data sets to be verified corresponding to each of the functions to be verified according to the position order between the corresponding template elements to obtain a sorting result; According to the sorting result, a current data set is selected from each of the to-be-verified data sets; the current data set is compared with a template data set of a corresponding template element to obtain a comparison result of the current data set; When the comparison result is failure to pass the verification, returning to the execution of selecting the current data set from each of the to-be-verified data sets according to the sorting result, until all of the to-be-verified data sets have been selected; When the comparison result is that the verification is passed, the verification result of the power grid device is determined according to the comparison result.

3. The method according to claim 2, characterized in that The template elements include: File check elements, line check elements, equipment check elements and data check elements.

4. The method according to claim 1, characterized in that: The power grid template library comprises: Obtain at least one operating voltage data, at least one device type, at least one device version number, and at least one device measurement and control device; Arrange and combine the operating voltage data, the device types, the device version numbers and the device measurement and control devices to generate at least one file identification group; According to each of the file identification groups, query the loop configuration files, preset parameter files and historical fault data files corresponding to each of the file identification groups; The loop configuration data, preset parameter data and historical fault data corresponding to each of the file identification groups are merged to obtain a power grid template library.

5. The method according to claim 1, characterized in that The step of querying a power grid template library to obtain a detection template corresponding to the power grid device includes: Obtaining an identification to be verified corresponding to the power grid device; Performing character string segmentation processing on the identifier to be verified to obtain at least one segmented identifier; Arrange and combine the partition marks to obtain at least one partition mark group; According to each of the segmentation identification groups, a screening is performed in the power grid template library to obtain a detection template.

6. The method according to claim 1, characterized in that After comparing the functions to be verified with the template data sets corresponding to the corresponding template elements in the detection template to obtain the verification results of the power grid equipment for the functions to be verified, the method further includes: Matching the to-be-verified data set corresponding to each of the to-be-verified functions with the configuration data of the power grid device to obtain the number of matching items; Identifying the configuration data of the power grid device to obtain the number of configuration items; The classification accuracy is calculated based on the number of matching items and the number of configuration items.

7. The method according to claim 1, characterized in that The configuration data includes: secondary loop instance configuration file data.

8. A power grid equipment calibration device, characterized in that: The device comprises: A data acquisition module, used to acquire configuration data of power grid equipment; A data set acquisition module, used to classify the configuration data according to at least one function to be verified, and obtain a data set to be verified corresponding to each function to be verified; A template query module, used to query the power grid template library to obtain the detection template corresponding to the power grid equipment; The result acquisition module is used to compare the template data set corresponding to the corresponding template element in the detection template with each of the functions to be verified, so as to obtain the verification result of the power grid equipment for each of the functions to be verified.

9. A power grid equipment calibration device, characterized in that: The power grid equipment verification device comprises: at least one processor; and a memory communicatively connected to the at least one processor; wherein, The memory stores a computer program executable by the at least one processor, and the computer program is executed by the at least one processor so that the at least one processor can execute the power grid equipment verification method according to any one of claims 1 to 7.

10. A computer-readable storage medium, characterized in that: The computer-readable storage medium stores computer instructions, and the computer instructions are used to enable a processor to implement the power grid equipment verification method according to any one of claims 1 to 7 when executed.