Preparation method of concrete module and concrete module

By using recyclable polystyrene foam board molds and optimized material ratios, the problems of single shape and high manufacturing cost in existing concrete modules in outdoor applications are solved, and the precise molding and structural stability of complex shapes are achieved, which improves the art Effects and economic benefits.

CN118952444APending Publication Date: 2024-11-15BEIJING JIAOTONG UNIV +1
View PDF 0 Cites 2 Cited by

Patent Information

Application Number
CN202411025916.2
Authority / Receiving Office
CN · China
Patent Type
Applications(China)
Current Assignee / Owner
Filing Date
2024-07-29
Publication Date
2024-11-15

AI Technical Summary

Technical Problem

The existing concrete modules have a single shape and low integration in outdoor applications, making it difficult to meet the needs of large-scale assembled and combined outdoor rest landscape kiosks, and the manufacturing process is high and cannot take into account both artistic effects and economic benefits.

Method used

The concrete module is prepared by recyclable polystyrene foam board molds for back-beating one-molding process, combining optimized material ratios and process flow, including jetting and casting processes, to form decorative and structural layers, and to reinforce rib ingredients and anti-corrosion Processing to ensure the artistic effect and structural strength of the module.

Benefits of technology

The precise molding of complex shapes is achieved, which reduces manufacturing costs, improves the fluidity and strength of materials, enhances the structural stability and aesthetics of the module, and reduces the cost of later maintenance.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN118952444A_ABST
    Figure CN118952444A_ABST
Patent Text Reader

Abstract

The invention discloses a preparation method of a concrete module. The preparation method comprises the following steps: forming a mold for preparing the concrete module; the mold is made of a recyclable material; preparing a concrete module based on the mold; and post-processing the concrete module to obtain a final concrete module. The invention further discloses the prepared concrete module. The polystyrene foam boards with the volume weight of 14-16 kilograms are used as the inner mold and the outer mold, cost is low, ductility and plasticity are high, numerical control carving can be achieved, and manual cutting and splicing manufacturing can also be achieved. And the mold can be recycled after being demolded and is green and environment-friendly. Adjustment changes of the shape and the structure of the arching pavilion can be quickly adapted; the mix proportion design is optimized, and the fluidity of the material is fully improved on the premise of ensuring the mechanical strength of the arch-shaped module. The operation process decorative surface adopts a spraying process to ensure the color and texture, and the structural layer is manufactured by adopting a pouring process to ensure the strength. The material can also adopt high-strength concrete (UHPC) so as to further reduce the size, thickness and weight of the component and remarkably enhance the mechanical property.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The invention relates to the technical fields of buildings, building prefabricated parts, and in particular to a preparation method of a concrete module and the concrete module. Background Art

[0002] Modular construction (Prefabricated Prefinished Volumetric Construction, PPVC for short) refers to a building divided into several space modules. All equipment, pipelines, decoration, etc. in the module have been completed, and the facade decoration can also be completed. The modular components are transported to the construction site and assembled together like building blocks. It is a high-end product of building industrialization and has its own high integrity. Among them, the frameless system is generally made of concrete casting. The integral casting method makes the rigidity particularly large. The frame system usually uses steel, aluminum, wood, and reinforced concrete as the frame, and uses light profile panels to enclose to form a box. However, the concrete modules in the prior art have the following structural and application defects:

[0003] First, currently in the construction field, precast concrete modules are mainly used in engineering structure facilities, such as pipelines, roads, walls, floor slabs, etc. They have a single shape rule, simple process, low integration, and are rarely used in outdoor landscape facilities.

[0004] Second, there are few large-scale assembled and combined outdoor rest landscape pavilions in the current existing technology. Most outdoor rest landscape pavilions are made of wood, metal, plastic and other materials, which require regular maintenance and updating, which increases the manufacturing cost and the subsequent maintenance cost.

[0005] Third, the current manufacturing process of prefabricated concrete modules is outdated, the processing time and cost are high, and it is impossible to ensure that the prefabricated concrete modules have artistic effects and improve economic benefits when used outdoors. Summary of the invention

[0006] In order to solve the problems existing in the prior art, the present invention provides the following technical solutions, a method for preparing a concrete module and a concrete module.

[0007] In one aspect, the present invention provides a method for preparing a concrete module, comprising:

[0008] S1, forming a mold for preparing a concrete module; the mold is made of recyclable materials;

[0009] S2, preparing a concrete module based on the mold;

[0010] S3, post-processing the concrete module to obtain a final concrete module.

[0011] Preferably, the S1 comprises:

[0012] S11, perform plate design;

[0013] S12, according to the board design, mold materials are used to perform mold processing to form multiple mold pieces; wherein the multiple mold pieces are inner and outer molds formed by polystyrene foam boards with a bulk density of 14-16 kg; the mold processing adopts a reverse one-time molding process, that is, a negative mold technology, with the decorative surface bottom mold at the bottom and the concrete material at the top;

[0014] S13, assembling a plurality of the mold pieces to form a processing mold;

[0015] S14, demoulding the processing mold with a release agent for subsequent decorative layer molding and structural layer molding.

[0016] Preferably, S2 includes:

[0017] S21, determining the materials of the concrete module; the materials include decorative layer ingredients, structural layer ingredients and reinforcing rib ingredients;

[0018] S22, respectively stirring the decorative layer ingredients and the structural layer ingredients, and forming the decorative layer by using a first operating process under a first pressure, and forming the structural layer by using a second operating process under a second pressure;

[0019] S23, connecting the decorative layer and the structural layer.

[0020] Preferably, the ingredients of the decorative layer are 1 part of cement, 3 parts of waste rock and auxiliary materials; the ingredients of the structural layer are 1 part of cement, 3 parts of waste rock and auxiliary materials; wherein 1 part of cement is 100KG of 425 or 525 grade cement; 3 parts of waste rock are 100KG of aggregate with a diameter of 20-30mm, 100KG of aggregate with a diameter of 5-10mm, and 100KG of fine powder with a diameter of less than 5mm; the auxiliary materials are 7KG of steel fiber, 250 grams of sodium citrate high-efficiency water reducer and 32KG of water.

[0021] Preferably, the 1 part of cement can also be recycled concrete, ordinary concrete or high-strength concrete UHPC.

[0022] Preferably, the first operation process is a spraying process to ensure the color and texture of the decorative surface; the second operation process is a pouring process to ensure the strength of the structural layer.

[0023] Preferably, the first pressure and the second pressure are 6 MPa and 8 MPa respectively.

[0024] Preferably, S2 further includes:

[0025] S24, determine the reinforcement rib ingredients and mix them to form a back-supporting steel frame; after the decorative layer and the structural layer are connected, embedding and reinforcement operations are performed, and they are assembled with the formed back-supporting steel frame and anti-corrosion treatment is performed to form a concrete module.

[0026] Preferably, the post-processing includes:

[0027] S31, after a period of static rest, perform maintenance for 800 hours at 40-50 degrees Celsius;

[0028] S32, performing demoulding process;

[0029] S33, performing stone-like treatment on the decorative layer, and then inspecting and packaging it for shipment.

[0030] The second aspect of the present invention is to provide a concrete module, which is prepared by the preparation method of the concrete module according to the first aspect, comprising:

[0031] Concrete submodule A and concrete submodule B, wherein the top of the concrete submodule A and the top of the concrete submodule B are fixedly connected to each other in a mortise and tenon manner through an adapting connection member and then used in conjunction to form the outdoor rest landscape pavilion;

[0032] The top and back of the concrete submodule A are provided with a plurality of first pipeline integrated holes (11), a plurality of first foundation connection holes (12) and a first text hole or integrated facility (13);

[0033] The top and back of the concrete submodule B are provided with a plurality of second pipeline integrated holes (21), a plurality of second basic connection holes (22) and a second text hole or integrated facility (23); the plurality of second pipeline integrated holes (21), the plurality of second basic connection holes (22) and the second text hole or integrated facility (23) are respectively provided corresponding to the plurality of first pipeline integrated holes (11), the plurality of first basic connection holes (12) and the first text hole or integrated facility (13);

[0034] Counterweights are symmetrically arranged at the bottom of the concrete submodule A and the concrete submodule B.

[0035] The preparation method provided by the present invention and the concrete module prepared thereby have the following beneficial effects:

[0036] 1. Mould:

[0037] Different from traditional mold process technology, a mold material with extremely strong plasticity is used, which can bear weight without deformation, so that the complex shape of the arch module can be accurately formed, while also taking into account the smooth demoulding of different holes and details of the arch module.

[0038] Mould features: Use polystyrene foam board with a bulk density of 14-16 kg as internal and external moulds, which are low-cost, highly ductile and plastic, can be CNC engraved, or manually cut and spliced. It can be recycled after demoulding, which is green and environmentally friendly. It can quickly adapt to the adjustment and changes of the shape and structure of the arch pavilion. The mould adopts a reverse one-time forming process, that is, negative mould technology, with the bottom mould of the decorative surface at the bottom and the concrete material at the top. This process is convenient for perfectly expressing the details of the texture, pattern and layer of the decorative surface, eliminating the time and cost of reprocessing after demoulding, ensuring the artistic effect while improving economic benefits.

[0039] 2. Materials:

[0040] Optimize the mix design to fully improve the fluidity of the material while ensuring the mechanical strength of the arch module. Rationally use aggregate grading to find the best ratio between strength, fluidity and texture. Material ratio: 100KG of 425 or 525 grade cement, 100KG of aggregate with a diameter of 20-30mm, 100KG of aggregate with a diameter of 5-10mm, 100KG of fine powder with a diameter of less than 5mm, 7KG of steel fiber, 250 grams of sodium citrate high-efficiency water reducer, and 32KG of water. Operation process The decorative surface adopts the spraying process to ensure the color and texture, and the structural layer is made by pouring technology to ensure strength.

[0041] The materials can be not only recycled concrete and ordinary concrete, but also ultra-high-strength concrete (UHPC), which can further reduce the size, thickness and weight of the components and significantly enhance the mechanical properties.

[0042] 3. Structure:

[0043] The arched module itself has structural strength and stability. The bottom of the module is an integrated seat to enhance the stability of the bottom weight of the module. Holes of different sizes and shapes are reserved on the top and back to reduce the weight of the top while reserving space for integrating other functional facilities.

[0044] 4. Connection details:

[0045] The arched modules are connected to the pre-buried steel nails on the ground through the reserved holes at the bottom, which is convenient to connect and ensures the stability of the connection with the ground. The connection combination between the arched modules is to connect the modules to each other in a mortise and tenon manner through dovetail-shaped connection components, and the overall stability will be further enhanced after the connection.

[0046] 5. Shape and texture:

[0047] The shape of the arched module is controlled by the golden ratio to ensure the harmony and beauty of the shape. Its surface texture treatment technology can adopt the production process of plain concrete, or it can adopt a special treatment method to form exposed aggregate to form a stone-like texture, achieving a special decorative effect different from concrete and stone. BRIEF DESCRIPTION OF THE DRAWINGS

[0048] Figure 1 The figure is a schematic flow chart of a method for preparing a concrete module according to a preferred embodiment of the present invention.

[0049] Figure 2 The present invention is a specific process flow chart of the preferred embodiment of the present invention.

[0050] Figure 3 This is a schematic diagram of a concrete module structure for an outdoor rest landscape pavilion according to a preferred embodiment of the present invention. DETAILED DESCRIPTION

[0051] In order to better understand the above technical solution, the above technical solution will be described in detail below in conjunction with the accompanying drawings and specific implementation methods.

[0052] Embodiment 1

[0053] like Figure 1 As shown, the present invention provides a method for preparing a concrete module, comprising:

[0054] S1, forming a mold for preparing a concrete module;

[0055] As a preferred embodiment, the S1 includes:

[0056] S11, perform plate design;

[0057] S12, performing mold processing using mold materials according to the plate design to form a plurality of mold pieces;

[0058] S13, assembling a plurality of the mold pieces to form a processing mold;

[0059] S14, demoulding the processing mold with a release agent for subsequent decorative layer molding and structural layer molding.

[0060] In this embodiment, different from the traditional mold process technology, the mold material is a mold material with extremely strong plasticity, which can bear weight without deformation, so that the complex shape of the arch module can be accurately formed, while also taking into account the smooth demoulding of different holes and details of the arch module.

[0061] In this embodiment, the multiple molds are formed of inner and outer molds of polystyrene foam boards with a bulk density of 14-16 kg, which are low-cost, highly ductile and plastic, can be numerically carved, or manually cut and spliced. After demoulding, they can be recycled, are green and environmentally friendly, and can quickly adapt to the adjustment and changes of the shape and structure of the arch pavilion.

[0062] As a preferred embodiment, the mold processing of S12 adopts a reverse one-time molding process, that is, a negative mold technology, with the decorative surface bottom mold at the bottom and the concrete material at the top. This process is convenient for perfectly expressing the details such as the texture, pattern and layer of the decorative surface, eliminating the time and cost of post-demolding reprocessing, ensuring the artistic effect while improving economic benefits.

[0063] S2, preparing a concrete module based on the mold;

[0064] As a preferred embodiment, S2 includes:

[0065] S21, determining the materials of the concrete module; the materials include decorative layer ingredients, structural layer ingredients and reinforcing rib ingredients;

[0066] Among them, in this embodiment, the ingredients of the decorative layer are 1 part of cement, 3 parts of waste rock and auxiliary materials; the ingredients of the structural layer are 1 part of cement, 3 parts of waste rock and auxiliary materials.

[0067] Optimize the mix design to fully improve the fluidity of the material while ensuring the mechanical strength of the arch module. Rationally use aggregate grading to find the best ratio between strength, fluidity and texture. Material ratio:

[0068] One part of cement is 100KG of 425 or 525 grade cement; three parts of waste rock are 100KG of aggregate with a diameter of 20-30mm, 100KG of aggregate with a diameter of 5-10mm, and 100KG of fine powder with a diameter of less than 5mm; the auxiliary materials are 7KG of steel fiber, 250 grams of sodium citrate high-efficiency water reducer, and 32KG of water.

[0069] As an alternative embodiment, the 1 part of cement can also be made of recycled concrete, ordinary concrete or ultra-high-strength concrete (UHPC), wherein the ultra-high-strength concrete (UHPC) can further reduce the size, thickness and weight of the component and significantly enhance the mechanical properties.

[0070] S22, respectively stirring the decorative layer ingredients and the structural layer ingredients, and forming the decorative layer by using a first operating process under a first pressure, and forming the structural layer by using a second operating process under a second pressure;

[0071] In this embodiment, the first operation process is a spraying process to ensure the color and texture of the process decorative surface; the second operation process is a pouring process to ensure the strength of the structural layer.

[0072] S23, connecting the decorative layer and the structural layer.

[0073] In this embodiment, the first pressure and the second pressure are 6 MPa and 8 MPa respectively. Of course, those skilled in the art may also use other pressure values, which are all within the protection scope of the present invention.

[0074] As a preferred embodiment, the S2 further includes:

[0075] S24, determine the reinforcement rib ingredients and mix them to form a back-supporting steel frame; after the decorative layer and the structural layer are connected, embedding and reinforcement operations are performed, and they are assembled with the formed back-supporting steel frame and anti-corrosion treatment is performed to form a concrete module.

[0076] S3, post-processing the concrete module;

[0077] As a preferred embodiment, the post-processing includes:

[0078] S31, after a period of static rest, perform maintenance for 800 hours at 40-50 degrees Celsius;

[0079] S32, demoulding process:

[0080] S33, performing stone-like treatment on the decorative layer, and then inspecting and packaging it for shipment.

[0081] The specific process flow chart of this embodiment is as follows Figure 2 As shown:

[0082] 1. Process: Plate design, structural design Personnel: Designer

[0083] Process responsibilities: 1. Plate type decomposition design and statistics; 2. Reinforcement and steel structure design and calculation; 3. Design of embedded parts and mounting parts.

[0084] Technical indicators: 1. The board specifications are accurately counted; 2. The board structure meets the mechanical properties; 3. The allowable tolerance requirements of the board specifications are clear.

[0085] Process requirements: 1. The board type has few block specifications and strong replaceability; 2. The drawing design is accurate and rigorous;

[0086] 2. Process name: bottom mold and enclosure personnel: mold personnel

[0087] Process responsibilities: 1. Responsible for the processing of mold enclosures; 2. Responsible for the initial debugging of mold assembly; 3. Responsible for the processing and production of embedded parts, reinforcement, and steel structures; 4. Responsible for the maintenance of equipment and facilities.

[0088] Process requirements: 1. The bottom mold and the support plate meet the flatness tolerance of the product; 2. The enclosure meets the product specification requirements and facilitates the installation of embedded parts; 3. The reinforcement, embedded parts, and steel structure meet the welding process requirements; 4. The operation rate of equipment and facilities meets the process requirements, and monthly maintenance work is done well.

[0089] 3. Process name: mold making, assembly personnel: mold maker

[0090] Process responsibilities: 1. Responsible for the production of molds (polystyrene board, gypsum, silicone rubber, fiberglass); 2. Responsible for guiding production personnel to assemble molds; 3. Responsible for the debugging and positioning of the initial assembly of molds.

[0091] Technical indicators: 1. Spare parts meet production requirements; 2. The initial assembly pass rate of molds is 98%; 3. The size status of the mold is recorded after each shift.

[0092] Process requirements: 1. Number the molds; 2. The molds should be easy to disassemble and assemble; 3. Provide production molds in a timely manner; 4. Fill out the mold assembly record form carefully; 5. During the vibration molding process of the decorative layer, the mold must not be displaced.

[0093] 4. Process name: Brushing release agent Personnel: Molding personnel

[0094] Process responsibilities: 1. Responsible for coating mold release agent; 2. Preparation of special mold release agent.

[0095] Index indicators: 1. 100% coating area; 2. Strictly follow the instructions for use; 3. Record the brand of release agent used.

[0096] Process requirements: 1. Apply evenly without local accumulation of liquid; 2. Keep the mold clean and free of debris; 3. A dedicated person should be responsible for the adjustment, preparation and melting of special release agents.

[0097] 5. Process name: mix ratio design

[0098] Process responsibilities: 1. Responsible for the design of the proportion of molding materials; 2. Supervise the quality status control of raw and auxiliary materials; 3. Responsible for the supervision and guidance of material proportions.

[0099] Technical indicators: 1. The efficiency of the ratio notification form is 100%; 2. The quality certification of raw and auxiliary materials is 100%.

[0100] Process requirements: 1. Separate design for different products; 2. Separate design for different structures of the same product; 3. Strong operability.

[0101] 6. Process name: Batching personnel: Batching worker

[0102] Process responsibilities: 1. Responsible for the preparation of materials; 2. Responsible for the record of materials used in material preparation; 3. Responsible for the maintenance and inspection of metering facilities.

[0103] Technical indicators: 1. Material weighing accuracy <2%; 2. Material collection accuracy 100%.

[0104] Process requirements: 1. Carefully understand the proportion notice, and prepare materials separately for different proportion designs; 2. Special materials are measured separately and mixed and prepared centrally; 3. The preparation base is based on 50kg of cement; 4. Liquid materials are weighed based on volume and converted to solid content when necessary; 5. Use metering equipment correctly; 6. Carefully keep records of material preparation.

[0105] 7. Process name: Mixing personnel: Mixing worker

[0106] Process responsibilities: 1. Responsible for mixing materials and conveying them to the next process; 2. Responsible for the cleaning and maintenance of mixing equipment; 3. Responsible for the supervision of material ratio; 4. Adjust the consistency of slurry under the guidance of the Quality Inspection Department.

[0107] Technical indicators: 1. Each batch of materials is mixed with 50kg cement as the base material; 2. Mixing time is 3~5 minutes; 3. Equipment operation rate ≥90%.

[0108] Process requirements: 1. Material addition order:

[0109] 80% of design water → aggregate → admixture → cement —— → 20% of design water (adjustment water)

[0110] 2. Stir as the molding progresses. Stirring in advance and standing by for a long time is strictly prohibited;

[0111] 3. Correctly select the mixing equipment according to the material forming method;

[0112] 4. Carefully record the relevant parameters of equipment operation and material mixing.

[0113] 8. Process name: Decorative layer molding

[0114] Process responsibilities: 1. Responsible for the debugging of molding equipment parameters; 2. Responsible for the daily maintenance and repair of molding equipment.

[0115] Technical indicators: 1. When the decorative layer is formed by injection molding, the material thickness is 3-5mm; when the decorative layer is vibrated, the thickness is not less than 15mm; 2. The injection surface is perpendicular to the molding plane; 3. The dead corners of the mold should be filled with material in place, and the required filling density is ∑4. The vibration molding time is ≤30 seconds.

[0116] Process requirements: 1. Record the equipment operating parameter adjustment and molding technical parameters; 2. The injection speed should be uniform and sand splashing should be prevented; 3. Start the vibrator after the material is evenly spread; 4. Avoid frequent displacement of the mold during vibration molding; 5. When using the vibrating facility to vibrate, it is strictly forbidden to damage the lining mold.

[0117] Safety measures: 1. The mold assembly is firmly and stably positioned without displacement; 2. Frequent motor start-up is strictly prohibited during vibration molding; 3. Avoid pointing the gun at people during injection molding; 4. Operate in strict accordance with the equipment operating procedures.

[0118] 9. Process name: Structural layer forming Personnel: Forming worker

[0119] Process responsibilities: 1. Responsible for the molding of structural layer materials; 2. Responsible for parameter adjustment and maintenance of molding equipment.

[0120] Technical indicators: 1. The thickness of each spraying is 3-4m until it meets the design requirements; 2. The content of glass fiber roving reaches 4±0.5%; 3. The mesh cloth covers 100% of the mold cavity, with an overlap of not less than 20cm, and the contact surface is paved with cement mortar; 4. The rolling method is longitudinal and transverse rolling.

[0121] Process requirements: 1. After the decorative layer is formed, the structural layer should be sprayed in time; 2. Ensure that the content of glass fiber in the slurry is not less than the design requirements; 3. The fiber mesh cloth should be rolled into the slurry and the thickness of the plain mortar should be sprayed once before and after laying the mesh with a thickness of 1-2mm; 4. The two sprayings should be carried out in a way of superimposing peaks and troughs; 5. Record the molding and production parameter status.

[0122] 10. Process name: Strengthening rib forming

[0123] Process responsibilities: 1. Responsible for the molding and production of reinforcing ribs; 2. Responsible for the positioning of embedded parts reinforcement and lifting hooks; 3. Responsible for the management of the molding molds for reinforcing ribs.

[0124] Technical indicators: 1. The reinforcement is welded as a whole; 2. The displacement deviation of the center line under the embedded parts is <3mm; 3. The tolerance of the reinforcing rib width is allowed to be ±3mm; 4. The content of untwisted glass fiber during injection molding is ≥2.5%.

[0125] Process requirements: 1. After the initial setting of the structural layer, the reinforcing ribs shall be made; 2. Select an appropriate rib-raising mold and position it accurately; 3. The reinforcement and embedded parts shall be treated with anti-corrosion and there shall be sufficient protective layer thickness in the ribs. ∑4. During vibration molding, the corners shall be strengthened to promote compaction; 5. After the rib slurry has finally set, lift the reinforcing rib mold and immediately use a spatula to smooth it; 6. Ensure that the exposed embedded parts are free of pollution; 7. Record the molding process parameters.

[0126] 11. Process name: Steel structure connection forming

[0127] Process responsibilities: Responsible for the forming and production of steel structure connections.

[0128] Technical indicators: 1. Steel structure connection; 2. The content of untwisted glass fiber during injection molding is ≥2.5%.

[0129] Process requirements: 1. The steel structure connection should be made after the initial setting of the structural layer; 2. The steel structure should be treated with anti-corrosion, and there should be sufficient protective layer thickness on the embedded parts; 3. Ensure that the exposed embedded parts are free of pollution; 4. Record the molding process parameters.

[0130] 12. Process name: Static stop and maintenance personnel: maintenance worker

[0131] Process responsibilities: Responsible for the maintenance of products after final setting.

[0132] Technical indicators: 1. Static time: 1.5 hours for sulphoaluminate cement, no less than 4 hours for other types of cement, and 100% film coverage; 2. Curing age ≥ 7 days, 3 days of heat preservation and curing after molding, and 4 days of natural curing; 3. Steam curing should be adopted when the room temperature is <5℃, and the maximum temperature is <60℃.

[0133] Process requirements: 1. Avoid frequent shifting during static periods; 2. After removing the frame, the products must be numbered in time. The numbering method refers to the design number, and the numbering area is on the side of the product; 3. Do not spray the products with sewage.

[0134] 13. Process Name: Demoulding Personnel: Demoulding Worker

[0135] Process responsibilities: 1. Responsible for the disassembly of the frame; 2. Responsible for the separation of the product and the bottom mold.

[0136] Technical indicators: 1. The control rate of mold parts is 100%; 2. The intact rate of products is 100%; 3. The utilization rate of bottom mold and lining mold is ≥95%; 4. The products are generally demoulded after 48 hours of curing. For special products, please refer to the process requirements for details.

[0137] Process requirements: 1. Use demoulding facilities reasonably and correctly; 2. It is strictly forbidden to carry it flat after demoulding; 3. Demolded products should be stacked on the curing rack according to specifications and numbers.

[0138] 14. Process name: Decorative layer processing personnel: Renovation worker

[0139] Process responsibilities: 1. Responsible for the artistic reprocessing of the decorative layer; 2. Responsible for the renovation of the edges and corners of the product.

[0140] Technical indicators: 1. The chopping depth of axe products is 5-10mm and the chopping texture is consistent; 2. The corners of special products are chamfered to 5×45° and are neat; 3. The color difference of bumps and repairs is consistent when visually inspected from 3 meters away; 4. The stone output rate is consistent when visually inspected.

[0141] Process requirements: 1. Chiseling operations can only be carried out when the product strength is greater than C30; 2. Operations can only be carried out when the plate is placed stably, and it is forbidden to hit the plate surface with a heavy hammer; 3. When repairing the surface layer, materials with the same ratio should be used; 4. It is strictly forbidden to lift and transport products flatly.

[0142] 15. Process name: Inspection and storage Personnel: Inspector

[0143] Process responsibilities: 1. Responsible for the inspection of product appearance quality and specifications and dimensions; 2. Responsible for checking the numbering status of products.

[0144] Technical indicators: 1. Enterprise standard Q / CPBGS002-2007; 2. Customer requirements.

[0145] Process requirements: 1. Use quality inspection equipment correctly; 2. Perform inspection operations strictly and seriously; 3. Keep complete inspection records.

[0146] Embodiment 2

[0147] This embodiment provides a concrete module, which is prepared by the preparation method of the concrete module of the first embodiment.

[0148] like Figure 3 As shown, the concrete modules are used for outdoor rest landscape pavilions, including:

[0149] Concrete submodule A and concrete submodule B, wherein the top of the concrete submodule A and the top of the concrete submodule B are fixedly connected to each other in a mortise and tenon manner through an adapting connecting member and then used together to form the outdoor rest landscape pavilion∑

[0150] The top and back of the concrete submodule A are provided with a plurality of first pipeline integration holes 11, a plurality of first foundation connection holes 12 and a first text hole or integration facility 13;

[0151] The top and back of the concrete submodule B are provided with a plurality of second pipeline integrated holes 21, a plurality of second basic connection holes 22, and a second text hole or integrated facility 23; the plurality of second pipeline integrated holes 21, the plurality of second basic connection holes 22, and the second text hole or integrated facility 23 are respectively provided corresponding to the plurality of first pipeline integrated holes 11, the plurality of first basic connection holes 12, and the first text hole or integrated facility 13;

[0152] Counterweights are symmetrically arranged at the bottom of the concrete submodule A and the concrete submodule B.

[0153] Its structural details have the following advantages:

[0154] 1. Structure:

[0155] The arched module itself has structural strength and stability. The bottom of the module is an integrated seat to enhance the stability of the bottom weight of the module. Holes of different sizes and shapes are reserved on the top and back to reduce the weight of the top while reserving space for integrating other functional facilities.

[0156] 2. Connection details:

[0157] The arched modules are connected to the pre-buried steel nails on the ground through the reserved holes at the bottom, which is convenient to connect and ensures the stability of the connection with the ground. The connection combination between the arched modules is to connect the modules to each other in a mortise and tenon manner through dovetail-shaped connection components, and the overall stability will be further enhanced after the connection.

[0158] 3. Shape and texture:

[0159] The shape of the arched module is controlled by the golden ratio to ensure the harmony and beauty of the shape. Its surface texture treatment technology can adopt the production process of plain concrete, or it can adopt a special treatment method to form exposed aggregate to form a stone-like texture, achieving a special decorative effect different from concrete and stone.

[0160] Although preferred embodiments of the present invention have been described, additional changes and modifications may be made to these embodiments by those skilled in the art once the basic inventive concepts are known. Therefore, the appended claims are intended to be interpreted as including the preferred embodiments and all changes and modifications that fall within the scope of the present invention. Obviously, those skilled in the art may make various changes and modifications to the present invention without departing from the spirit and scope of the present invention. Thus, if these modifications and variations of the present invention fall within the scope of the claims of the present invention and their equivalents, the present invention is also intended to include these modifications and variations.

Claims

1. A method for preparing a concrete module, characterized in that: include: S1, forming a mold for preparing a concrete module; the mold is made of recyclable materials; S2, preparing a concrete module based on the mold; S3, post-processing the concrete module to obtain a final concrete module.

2. The method for preparing a concrete module according to claim 1, characterized in that: The S1 includes: S11, perform plate design; S12, according to the board design, mold materials are used to perform mold processing to form multiple mold pieces; wherein the multiple mold pieces are inner and outer molds formed by polystyrene foam boards with a bulk density of 14-16 kg; the mold processing adopts a reverse one-time molding process, that is, a negative mold technology, with the decorative surface bottom mold at the bottom and the concrete material at the top; S13, assembling a plurality of the mold pieces to form a processing mold; S14, demoulding the processing mold with a release agent for subsequent decorative layer molding and structural layer molding.

3. The method for preparing a concrete module according to claim 2, characterized in that: The S2 includes: S21, determining the materials of the concrete module; the materials include decorative layer ingredients, structural layer ingredients and reinforcing rib ingredients; S22, respectively stirring the decorative layer ingredients and the structural layer ingredients, and forming the decorative layer by using a first operating process under a first pressure, and forming the structural layer by using a second operating process under a second pressure; S23, connecting the decorative layer and the structural layer.

4. The method for preparing a concrete module according to claim 3, characterized in that: The ingredients of the decorative layer are 1 part of cement, 3 parts of waste stone and auxiliary materials; the ingredients of the structural layer are 1 part of cement, 3 parts of waste stone and auxiliary materials; among them, 1 part of cement is 100KG of 425 or 525 grade cement; 3 parts of waste stone are 100KG of aggregate with a diameter of 20-30mm, 100KG of aggregate with a diameter of 5-10mm, and 100KG of fine powder with a diameter of less than 5mm; the auxiliary materials are 7KG of steel fiber, 250 grams of sodium citrate high-efficiency water reducer and 32KG of water.

5. The method for preparing a concrete module according to claim 3, characterized in that: The 1 part of cement can also be recycled concrete, ordinary concrete or high-strength concrete UHPC.

6. The method for preparing a concrete module according to claim 3, characterized in that: The first operation process is a spraying process to ensure the color and texture of the decorative surface; the second operation process is a pouring process to ensure the strength of the structural layer.

7. The method for preparing a concrete module according to claim 3, characterized in that: The first pressure and the second pressure are 6 MPa and 8 MPa respectively.

8. The method for preparing a concrete module according to claim 3, characterized in that: The S2 further includes: S24, determine the reinforcement rib ingredients and mix them to form a back-supporting steel frame; after the decorative layer and the structural layer are connected, embedding and reinforcement operations are performed, and they are assembled with the formed back-supporting steel frame and anti-corrosion treatment is performed to form a concrete module.

9. The method for preparing a concrete module according to claim 1, characterized in that: The post-processing includes: S31, after a period of static rest, perform maintenance for 800 hours at 40-50 degrees Celsius; S32, demoulding process: S33, performing stone-like treatment on the decorative layer, and then inspecting and packaging it for shipment.

10. A concrete module, prepared by the method for preparing a concrete module according to any one of claims 1 to 9, comprising: Concrete submodule A and concrete submodule B, wherein the top of the concrete submodule A and the top of the concrete submodule B are fixedly connected to each other in a mortise and tenon manner through an adapting connection member and then used in conjunction to form the outdoor rest landscape pavilion; The top and back of the concrete submodule A are provided with a plurality of first pipeline integrated holes (11), a plurality of first foundation connection holes (12) and a first text hole or integrated facility (13); The top and back of the concrete submodule B are provided with a plurality of second pipeline integrated holes (21), a plurality of second basic connection holes (22) and a second text hole or integrated facility (23); the plurality of second pipeline integrated holes (21), the plurality of second basic connection holes (22) and the second text hole or integrated facility (23) are respectively provided corresponding to the plurality of first pipeline integrated holes (11), the plurality of first basic connection holes (12) and the first text hole or integrated facility (13); Counterweights are symmetrically arranged at the bottom of the concrete submodule A and the concrete submodule B.

Citation Information

Cited By

  • Special-shaped curved surface floor support plate concrete spray forming method and system

    CN120401804A

  • Concrete spraying method and system for special-shaped curved floor slabs

    CN120401804B