Intelligent identification method and system for construction progress of steel-concrete combined bridge tower
Through the intelligent identification system combined with equipment information and reasoning rule database, the problem of inefficient monitoring of bridge tower construction progress is solved, efficient and accurate construction progress management is achieved, and refined management needs are met.
Patent Information
- Application Number
- CN202411105946.4
- Authority / Receiving Office
- CN · China
- Patent Type
- Applications(China)
- Current Assignee / Owner
- Filing Date
- 2024-08-13
- Publication Date
- 2024-11-15
AI Technical Summary
The construction progress monitoring of existing bridge towers relies on manual methods, which is inefficient and lagging in information, making it difficult to achieve accurate and efficient construction progress management.
Using an intelligent identification method and system for the construction progress of steel-concrete bridge towers, the construction progress reasoning rules database is constructed by obtaining information on climbing frames, tower cranes, vehicles, concrete tankers and other equipment, combining video image acquisition and data collectors, and real-time judgment is made Construction progress.
It improves the accuracy and efficiency of the construction progress monitoring of steel-concrete combination bridge towers, meets the needs of refined construction management, and realizes intelligent identification of construction progress.
Smart Images

Figure CN118958145A_ABST
Abstract
Description
Technical Field
[0001] The present invention relates to the technical field of bridge tower construction, and in particular to a method and system for intelligently identifying the construction progress of a steel-concrete composite bridge tower. Background Art
[0002] Bridge pylons (bridge towers for short) refer to tower-shaped structures that support the main cables of suspension bridges or cable-stayed bridges. Steel-concrete composite structures are widely used in bridge pylon structures because they can give full play to the material properties of steel and concrete. Construction progress monitoring is a key link in bridge engineering construction management. Bridge towers are an important part of bridge construction. On the premise of ensuring project quality and construction safety, it is of practical significance to monitor the construction progress of bridge towers efficiently and accurately, which can help project leaders understand the construction progress in a timely manner and make scientific and reasonable construction decisions.
[0003] At present, the construction progress monitoring and progress data recording of bridge towers are mostly carried out manually. This traditional construction progress management mode has problems such as low efficiency, large workload of manual filling and information lag, and requires relevant construction management personnel to have relatively comprehensive knowledge of bridge construction. In recent years, with the rise and development of artificial intelligence technology, some new information and intelligent technologies have emerged, providing ideas for solving the problems existing in the traditional construction progress management mode. This patent aims to provide a method and system for intelligent identification of the construction progress of steel-concrete composite bridge towers that integrates traditional construction knowledge and multi-source heterogeneous data. Summary of the invention
[0004] The purpose of the present invention is to address the defects of the prior art and provide a method and system for intelligently identifying the construction progress of a steel-concrete composite bridge tower, thereby realizing intelligent identification of the construction progress of a steel-concrete composite bridge tower, effectively improving the accuracy and efficiency of monitoring the construction progress of the steel-concrete composite bridge tower, and meeting the needs of refined management of the construction of steel-concrete composite bridge towers.
[0005] In order to solve the above technical problems, in a first aspect, the present invention provides a method for intelligently identifying the construction progress of a steel-concrete composite bridge tower, comprising:
[0006] The steel-concrete composite bridge tower includes n groups of bridge tower segments, and the construction process of each group of bridge tower segments includes at least one tower column steel segment hoisting construction process and one tower column concrete pouring construction process. Each group of bridge tower segments includes at least one sub-segment, and each sub-segment corresponds to one tower column steel segment hoisting construction process.
[0007] The tower column steel segment hoisting construction process includes the hoisting construction preparation sub-process, steel segment hoisting and positioning sub-process, steel segment connection sub-process, and reinforcement construction sub-process. The tower column concrete pouring construction process includes the pouring construction preparation sub-process, concrete pouring sub-process, and concrete curing sub-process.
[0008] Obtain information on climbing frames, screw force monitoring equipment, flatbed trucks, concrete tankers, truck pumps, tower cranes, concrete pouring platforms, and construction personnel to identify construction progress.
[0009] Furthermore, the method for identifying the construction progress includes:
[0010] S1. Obtain the current constructed tower top height, compare the current constructed tower top height with the top elevation of each sub-segment in each group of bridge tower segments, and determine that the current constructed tower top height is equal to the top elevation of the j-th sub-segment in the i-th group of bridge tower segments;
[0011] S2, determining whether the operation state of the climbing frame is climbing, if so, executing step S21;
[0012] S21. Determine whether the j-th sub-segment in the i-th group of bridge tower segments is the last sub-segment of the i-th group of bridge tower segments. If so, confirm that the current sub-process is in the casting construction preparation sub-process of the i-th group of bridge tower segments; otherwise, confirm that the current sub-process is in the hoisting construction preparation sub-process of the j+1-th sub-segment in the i-th group of bridge tower segments.
[0013] Further, in step S2, if the operating state of the climbing frame is not climbing, step S22 is executed, and step S22 includes:
[0014] Determine whether the top elevation of the climbing frame is greater than the current height of the tower top that has been constructed. If not, execute step S3, which includes: determining the current construction progress based on the tower crane and construction personnel information;
[0015] The top elevation of the climbing frame is the height of the top of the guardrail of the uppermost construction platform of the climbing frame.
[0016] Further, step S3 includes:
[0017] S31, obtaining the lifting weight information of the tower crane and the image information of the lifting object of the tower crane;
[0018] S32, judging whether the temporary construction passage is being hoisted on site, if the hoisting weight of the tower crane is equal to the weight of the temporary construction passage and the hoisted object is identified as a temporary construction passage according to the hoisting object image information, it is determined that the temporary construction passage is being hoisted on site, and the current process is the steel segment connection sub-process of the j-th sub-segment in the i-th group of bridge tower segments, otherwise, executing step S33;
[0019] S33, obtaining image information of the inside and outside of the j-th sub-segment in the i-th group of bridge tower segments, and determining whether there are construction workers performing construction inside or outside the j-th sub-segment in the i-th group of bridge tower segments;
[0020] If there are construction workers on the construction platform outside the j-th sub-segment in the i-th group of bridge tower segments, then the current step is the steel segment connection sub-process of the j-th sub-segment in the i-th group of bridge tower segments;
[0021] If there are construction workers inside the steel pipe of the j-th sub-segment in the i-th group of bridge tower segments, then the current sub-process is the steel bar construction sub-process of the j-th sub-segment in the i-th group of bridge tower segments;
[0022] Otherwise, it is determined that the current state is down.
[0023] Further, in step S22, if the top elevation of the climbing frame is greater than the current constructed tower top height, step S4 is executed, and step S4 includes: determining whether the jth sub-segment in the i-th group of bridge tower segments is the last sub-segment, if not, executing step S5: determining the current construction progress based on the tower crane information and the flatbed transport vehicle information.
[0024] Further, step S5 includes:
[0025] S51, obtaining the lifting weight information of the tower crane and the image information of the lifting object of the tower crane;
[0026] S52, judging whether the steel segment is being hoisted on site, if the hoisting weight of the tower crane is equal to the weight of the steel segment and the hoisted object is identified as a steel segment according to the hoisting object image information, it is determined that the steel segment is being hoisted on site, and the steel segment hoisting and positioning sub-process of the j+1th sub-segment in the i-th group of bridge tower segments is currently in progress, otherwise, executing step S53;
[0027] S53. Obtain the driving track, current position and image information of the load of the flatbed transport vehicle, and determine whether there is a flatbed transport vehicle traveling from the steel structure processing plant to the construction site or is located within the construction site, and whether the load of the flatbed transport vehicle is steel segments. If so, the current construction process is the hoisting construction preparation sub-process of the j+1th sub-segment of the i-th group of bridge tower segments; otherwise, it is determined that the current construction process is in a stopped state.
[0028] Further, in step S4, if the jth sub-segment in the i-th group of bridge tower segments is the last sub-segment, step S6 is executed, and step S6 includes: judging the current construction progress based on information from the screw force monitoring equipment, flatbed transport vehicles, concrete tank trucks, truck pumps, tower cranes, concrete pouring platforms and construction personnel.
[0029] Further, step S6 includes:
[0030] S61, obtaining image information of the currently constructed tower top, determining whether the concrete pouring platform is located at the top of the currently constructed bridge tower, and if so, obtaining the location information of the truck pump and the driving track and current location of the concrete tank truck;
[0031] S62, determining whether the truck pump is located within the scope of the construction site and whether there are concrete tank trucks traveling between the construction site and the concrete processing plant; if so, determining the concrete pouring sub-process currently in the i-th group of bridge tower segments; otherwise, executing step S63;
[0032] S63. Obtain image information of the working surface above the j-th sub-segment in the i-th group of bridge tower segments and the interior of the concrete pouring platform to determine whether there are construction workers inside the concrete pouring platform who are installing pump pipes. If so, determine that the current process is in the pouring construction preparation sub-process of the i-th group of bridge tower segments; otherwise, determine that the current process is in a shutdown state.
[0033] Furthermore, in step S61, if the concrete pouring platform is not located at the top of the currently constructed bridge tower, step S7 is executed:
[0034] S71, obtaining and analyzing the monitoring data of the screw force monitoring device to determine whether the concrete pouring of the i-th group of bridge tower segments is completed, if so, executing step S72, otherwise, executing step S74;
[0035] S72, obtaining the lifting weight information of the tower crane and the image information of the lifting object of the tower crane, and judging whether the lifting of the steel segment is being carried out on site; if the lifting weight of the tower crane is equal to the weight of the steel segment and the lifting object is identified as a steel segment according to the image information of the lifting object, it is determined that the lifting of the steel segment is being carried out on site, and the steel segment lifting and positioning sub-process of the first sub-segment in the i+1th group of bridge tower segments is determined; otherwise, executing step S73;
[0036] S73, obtaining the driving track, current position and image information of the load of the flatbed transport vehicle, determining whether there is a flatbed transport vehicle traveling from the steel structure processing plant to the construction site or located within the scope of the construction site, and whether the load of the flatbed transport vehicle is a steel segment; if so, the current construction process is the hoisting construction preparation sub-process of the first sub-segment in the i+1th group of bridge tower segments; otherwise, according to the completion time of the concrete pouring sub-process of the i-th bridge tower segment, determining whether the current construction process is the concrete curing sub-process of the i-th group of bridge tower segments;
[0037] S74, obtaining the lifting weight information of the tower crane and the image information of the lifting object of the tower crane, and determining whether the concrete pouring platform is being hoisted on site; if the lifting weight of the tower crane is equal to the weight of the concrete pouring platform and the lifting object is identified as the concrete pouring platform according to the image information of the lifting object, then the concrete pouring platform is currently being hoisted, and it is determined that the pouring construction preparation sub-process of the i-th group of bridge tower segments is currently in progress; otherwise, executing step S75;
[0038] S75. Obtain the driving track, current position and image information of the flatbed transport vehicle, and determine whether there is a flatbed transport vehicle traveling from the steel structure processing plant to the construction site or is located within the construction site, and whether the load of the flatbed transport vehicle is a concrete casting platform. If so, the current process is in the casting construction preparation sub-process of the i-th group of bridge tower segments; otherwise, it is determined that the current process is in a shutdown state.
[0039] In a second aspect, the present invention provides a steel-concrete composite bridge tower construction progress intelligent identification system, including a cloud server, a video image acquisition device, a vehicle data collector, a tower crane data collector, a climbing frame data collector, and a screw force monitoring device;
[0040] The video image acquisition device is used to collect video image information within the construction site and upload it to the cloud server;
[0041] The vehicle data collector is used to collect the driving data of the flatbed transport truck and the concrete tank truck and the image data of the load of the flatbed transport truck and upload them to the cloud server;
[0042] The tower crane data collector is used to collect lifting weight information and lifting object image information and upload them to the cloud server;
[0043] The climbing frame data collector is used to collect the operating status of the climbing frame and the top height of the climbing frame and upload them to the cloud server;
[0044] The screw force monitoring device is used to monitor the screw force of the screws at the four corner points of the tower limb during the entire process of the tower construction and upload it to the cloud server;
[0045] The cloud server is used to determine the construction progress based on various types of information obtained.
[0046] The beneficial effects of the present invention are as follows: the present invention uses the completion of concrete maintenance as the dividing point of the construction stage, divides the steel-concrete composite bridge tower into n groups of bridge tower segments, and the construction process of each group of bridge tower segments includes at least one tower column steel segment hoisting construction process and one tower column concrete pouring construction process. By sorting out the construction entities such as bridge components, mechanical equipment, staff and temporary facilities in the construction scene, the relevant information that can be used to judge the construction progress is determined, and the intelligent identification of the construction progress of the steel-concrete composite bridge tower is realized, which effectively improves the accuracy and efficiency of the construction progress monitoring of the steel-concrete composite bridge tower and meets the needs of refined management of the construction of the steel-concrete composite bridge tower. BRIEF DESCRIPTION OF THE DRAWINGS
[0047] Figure 1 is a flow chart of steps S1 to S5 of the present invention;
[0048] Figure 2 is a flow chart of steps S6 to S7 of the present invention;
[0049] Figure 3 This is a construction process diagram of Example 1 of the present invention. DETAILED DESCRIPTION
[0050] In order to make the technical problems, technical solutions and beneficial effects to be solved by the present application more clearly understood, the present application is further described in detail below in conjunction with the accompanying drawings and embodiments. It should be understood that the specific embodiments described herein are only used to explain the present application and are not used to limit the present application.
[0051] Example 1
[0052] This embodiment provides a method for intelligently identifying the construction progress of a steel-concrete composite bridge tower, comprising:
[0053] Based on the construction plan of the steel-concrete composite bridge tower and combined with the knowledge of bridge tower construction, the specific construction content of each construction process of the steel-concrete composite bridge tower is sorted out.
[0054] The steel-concrete composite bridge tower includes n groups of bridge tower segments. The construction process of each group of bridge tower segments includes at least one tower column steel segment hoisting construction process and one tower column concrete pouring construction process. Each group of bridge tower segments includes at least one sub-segment, and each sub-segment corresponds to one tower column steel segment hoisting construction process.
[0055] In this embodiment, the steel segments of each sub-segment are transported to the site after being processed in the steel structure processing plant and then hoisted by a tower crane. The first group of bridge tower segments includes one sub-segment. Starting from the second group of bridge tower segments, each group of bridge tower segments includes three sub-segments. The concrete inside the tower column of each group of bridge tower segments is poured centrally, such as Figure 3 As shown, taking the second group of bridge tower segments as an example, the second group of bridge tower segments includes T2, T3, and T4 segments. First, the steel segments of T2, T3, and T4 segments are hoisted, and then the concrete of T2, T3, and T4 segments is poured centrally, thus completing the construction of the second group of bridge tower segments.
[0056] The construction procedures for hoisting tower steel segments of the three sub-segments T2, T3 and T4 include the hoisting construction preparation sub-process, steel segment hoisting and positioning sub-process, steel segment connection sub-process and reinforcement construction sub-process. The construction procedures for pouring concrete inside the tower columns of the second group of bridge tower segments include the pouring construction preparation sub-process, concrete pouring sub-process and concrete curing sub-process.
[0057] Combined with the specific construction content of each process of the steel-concrete composite bridge tower and the knowledge of bridge tower construction, the construction entities such as bridge components, mechanical equipment, staff and temporary facilities in the construction scene are sorted out, and the connotation of construction entity-relationship-attribute is further analyzed and summarized to construct the construction progress reasoning rule base of the steel-concrete composite bridge tower, as shown in Table 1.
[0058] Table 1 Entity-Relationship-Attribute Table
[0059]
[0060]
[0061] The various construction processes of the steel-concrete composite bridge tower are carried out in a fixed construction sequence and cannot be carried out simultaneously or in reverse order. For example, the lifting of the steel segment of the T2 segment must be carried out after the climbing frame has been raised to the specified position, and the lifting of the steel segment of the next group of bridge tower segments can only be carried out after the concrete has reached the required design strength. In this way, a sequential reasoning rule for the construction progress can be constructed.
[0062] Intelligent reasoning of the construction progress is performed based on the construction process, progress reasoning rule library and data collected on site, which is divided into two steps: feature entity and feature attribute identification and extraction, and construction progress reasoning.
[0063] (1) Feature entity and feature attribute identification and extraction
[0064] After the field data collection is completed, the collected data needs to be processed separately to extract the characteristic construction entities and their characteristic attributes associated with the process. The corresponding relationship between various characteristic entities and characteristic attributes and field data is shown in Table 2.
[0065] Table 2 Entity-attribute-data source table
[0066] Serial number Feature Entity Type Feature attributes Data Source 1 Bridge tower structure Spatial location Image Video 2 Tower Crane Lifting weight Tower crane data 3 Construction machinery Spatial location Image Video 4 Engineering vehicles Spatial position and driving trajectory Image video, vehicle driving data 5 Construction workers Spatial location, behavioral characteristics Image Video 6 Construction monitoring equipment Monitoring parameters Monitoring data
[0067] (2) Intelligent reasoning and identification of construction progress
[0068] like Figure 1 As shown, the methods for identifying construction progress include:
[0069] S1. Obtain the currently constructed tower top height, compare the currently constructed tower top height with the top elevation of each sub-segment in each group of bridge tower segments, and determine that the currently constructed tower top height is equal to the top elevation of the j-th sub-segment in the i-th group of bridge tower segments; it should be noted that the currently constructed tower top height is the highest height of the currently constructed steel segment;
[0070] S2, determining whether the operation state of the climbing frame is climbing, if so, executing step S21;
[0071] S21. Determine whether the j-th sub-segment in the i-th group of bridge tower segments is the last sub-segment of the i-th group of bridge tower segments. If so, confirm that the current sub-process is in the casting construction preparation sub-process of the i-th group of bridge tower segments; otherwise, confirm that the current sub-process is in the hoisting construction preparation sub-process of the j+1-th sub-segment in the i-th group of bridge tower segments.
[0072] It is understandable that if Figure 3 As shown in the figure, if the current constructed tower top height is equal to the top elevation of the T4 segment in the second group of bridge tower segments, since the T4 segment is the last sub-segment of the second group of bridge tower segments, the next construction process is the pouring of tower column concrete of the second group of bridge tower segments, and since the operating state of the climbing frame is climbing, the construction progress at this time must be the pouring construction preparation sub-process of the second group of bridge tower segments; if the current constructed tower top height is equal to the top elevation of the T3 segment in the second group of bridge tower segments, the next construction process is the hoisting of the tower column steel segment of the T4 segment, and since the operating state of the climbing frame is climbing, the construction progress at this time must be the hoisting construction preparation sub-process of the T4 segment.
[0073] If the running state of the climbing frame is not climbing, step S22 is executed, and step S22 includes:
[0074] Determine whether the top elevation of the climbing frame is greater than the current height of the tower top that has been constructed. If not, execute step S3, which includes: determining the current construction progress based on the tower crane and construction personnel information;
[0075] The top elevation of the climbing frame is the height of the top of the guardrail of the uppermost construction platform of the climbing frame.
[0076] Step S3 specifically includes:
[0077] S31, obtaining the lifting weight information of the tower crane and the image information of the lifting object of the tower crane;
[0078] S32, judging whether the temporary construction passage is being hoisted on site, if the hoisting weight of the tower crane is equal to the weight of the temporary construction passage and the hoisted object is identified as a temporary construction passage according to the hoisting object image information, it is determined that the temporary construction passage is being hoisted on site, and the current process is the steel segment connection sub-process of the j-th sub-segment in the i-th group of bridge tower segments, otherwise, executing step S33;
[0079] S33, obtaining image information of the inside and outside of the j-th sub-segment in the i-th group of bridge tower segments, and determining whether there are construction workers performing construction inside or outside the j-th sub-segment in the i-th group of bridge tower segments;
[0080] If there are construction workers on the construction platform outside the j-th sub-segment in the i-th group of bridge tower segments, then the current step is the steel segment connection sub-process of the j-th sub-segment in the i-th group of bridge tower segments;
[0081] If there are construction workers inside the steel pipe of the j-th sub-segment in the i-th group of bridge tower segments, then the current sub-process is the steel bar construction sub-process of the j-th sub-segment in the i-th group of bridge tower segments;
[0082] Otherwise, it is determined that the current state is down.
[0083] It is understandable that if Figure 3 As shown, if the current constructed tower top height is equal to the top elevation of the T2 segment in the second group of bridge tower segments, the operating status of the climbing frame is not climbing, and the top elevation of the climbing frame is not greater than the current constructed tower top height, then the T2 segment may be in the steel segment connection or reinforcement construction sub-process at this time, and the construction progress can be judged through the information of the tower crane and construction personnel (the positions of the construction personnel are different, the welding work is located on the construction platform outside the steel tower segment, and the reinforcement connection work is located inside the steel pipe of the steel tower segment).
[0084] In step S22, if the top elevation of the climbing frame is greater than the current constructed tower top height, step S4 is executed. Step S4 includes: determining whether the jth sub-segment in the i-th group of bridge tower segments is the last sub-segment. If not, step S5 is executed: determining the current construction progress based on the tower crane information and the flatbed transport vehicle information.
[0085] Step S5 specifically includes:
[0086] S51, obtaining the lifting weight information of the tower crane and the image information of the lifting object of the tower crane;
[0087] S52, judging whether the steel segment is being hoisted on site, if the hoisting weight of the tower crane is equal to the weight of the steel segment and the hoisted object is identified as a steel segment according to the hoisting object image information, it is determined that the steel segment is being hoisted on site, and the steel segment hoisting and positioning sub-process of the j+1th sub-segment in the i-th group of bridge tower segments is currently in progress, otherwise, executing step S53;
[0088] S53. Obtain the driving track, current position and image information of the load of the flatbed transport vehicle, and determine whether there is a flatbed transport vehicle traveling from the steel structure processing plant to the construction site or is located within the construction site, and whether the load of the flatbed transport vehicle is steel segments. If so, the current construction process is the hoisting construction preparation sub-process of the j+1th sub-segment of the i-th group of bridge tower segments; otherwise, it is determined that the current construction process is in a stopped state.
[0089] It can be understood that if the current constructed tower top height is equal to the top elevation of the T3 segment in the second group of bridge tower segments, the operating status of the climbing frame is not climbing, and the top elevation of the climbing frame is greater than the current constructed tower top height, then it means that all sub-processes of hoisting the tower column steel segment of the T3 segment have been completed, and the current process is the hoisting construction process of the tower column steel segment of the T4 segment. At this time, the current construction sub-process can be further judged based on the information of the tower crane and the flatbed transport vehicle.
[0090] like Figure 2As shown, in step S4, if the jth sub-segment in the i-th group of bridge tower segments is the last sub-segment, step S6 is executed. It can be understood that if the jth sub-segment in the i-th group of bridge tower segments is the last sub-segment, it means that the top elevation of the climbing frame is greater than the top elevation of the T4 segment. At this time, it may be in the tower column concrete pouring construction process of the second group of bridge tower segments, or it may be in the tower column steel segment hoisting construction process of the first sub-segment T5 segment in the third group of bridge tower segments.
[0091] Step S6 includes: judging the current construction progress according to the information of the screw force monitoring equipment, the flatbed transport vehicle, the concrete tanker, the truck pump, the tower crane, the concrete pouring platform and the construction personnel.
[0092] Further, step S6 includes:
[0093] S61, obtaining image information of the currently constructed tower top, determining whether the concrete pouring platform is located at the top of the currently constructed bridge tower, and if so, obtaining the location information of the truck pump and the driving track and current location of the concrete tank truck;
[0094] S62, determining whether the truck pump is located within the scope of the construction site and whether there are concrete tank trucks traveling between the construction site and the concrete processing plant; if so, determining the concrete pouring sub-process currently in the i-th group of bridge tower segments; otherwise, executing step S63;
[0095] S63. Obtain image information of the working surface above the j-th sub-segment in the i-th group of bridge tower segments and the interior of the concrete pouring platform to determine whether there are construction workers inside the concrete pouring platform who are installing pump pipes. If so, determine that the current process is in the pouring construction preparation sub-process of the i-th group of bridge tower segments; otherwise, determine that the current process is in a shutdown state.
[0096] It should be noted that the pump pipes are divided into horizontal pump pipes and vertical pump pipes. The vertical pump pipes are connected from the ground to the top surface of the current steel tower segment, and the horizontal pump pipes are led from the vertical pump pipes to the top of the area to be poured. Therefore, the construction workers will install the pump pipes on the outside and top of the segment and inside the concrete pouring platform.
[0097] In step S61, if the concrete pouring platform is not located at the top of the currently constructed bridge tower, step S7 is executed:
[0098] S71, obtaining and analyzing the monitoring data of the screw force monitoring device to determine whether the concrete pouring of the i-th group of bridge tower segments is completed, if so, executing step S72, otherwise, executing step S74;
[0099] It should be noted that the screw force monitoring equipment is arranged at the screws at the four corner points of the tower limbs, and real-time monitoring and early warning are carried out during the entire process of tower construction. The screw force monitoring equipment monitors the tension of the screw. As the tower limbs tilt inward, with the hoisting of the steel tower segments and the pouring of concrete, the pressure on the inside of the tower limbs increases and the tension on the outside increases, which causes the screw force on the inside to decrease and the screw force on the outside to increase. The total height of each group of tower segments is about 40m. The screw force at the four corner points will change significantly before and after the concrete is poured. This change can be used to determine whether the concrete inside the group of tower segments has been poured.
[0100] S72, obtaining the lifting weight information of the tower crane and the image information of the lifting object of the tower crane, and judging whether the lifting of the steel segment is being carried out on site; if the lifting weight of the tower crane is equal to the weight of the steel segment and the lifting object is identified as a steel segment according to the image information of the lifting object, it is determined that the lifting of the steel segment is being carried out on site, and the steel segment lifting and positioning sub-process of the first sub-segment in the i+1th group of bridge tower segments is determined; otherwise, executing step S73;
[0101] S73, obtaining the driving track, current position and image information of the load of the flatbed transport vehicle, and determining whether there is a flatbed transport vehicle traveling from the steel structure processing plant to the construction site or located within the scope of the construction site, and whether the load of the flatbed transport vehicle is a steel segment. If so, the current construction process is the hoisting construction preparation sub-process of the first sub-segment in the i+1th group of bridge tower segments. Otherwise, according to the completion time of the concrete pouring sub-process of the i-th bridge tower segment, determine whether the current construction process is the concrete curing sub-process of the i-th group of bridge tower segments. For example, the concrete curing time can be set to 28 days. If the current time is within 28 days after the completion of the concrete pouring sub-process, it is determined that the current process is the concrete curing sub-process of the i-th group of bridge tower segments. Otherwise, it is determined that the current process is in a shutdown state.
[0102] S74, obtaining the lifting weight information of the tower crane and the image information of the lifting object of the tower crane, and determining whether the concrete pouring platform is being hoisted on site; if the lifting weight of the tower crane is equal to the weight of the concrete pouring platform and the lifting object is identified as the concrete pouring platform according to the image information of the lifting object, then the concrete pouring platform is currently being hoisted, and it is determined that the pouring construction preparation sub-process of the i-th group of bridge tower segments is currently in progress; otherwise, executing step S75;
[0103] S75. Obtain the driving track, current position and image information of the flatbed transport vehicle, and determine whether there is a flatbed transport vehicle traveling from the steel structure processing plant to the construction site or is located within the construction site, and whether the load of the flatbed transport vehicle is a concrete casting platform. If so, the current process is in the casting construction preparation sub-process of the i-th group of bridge tower segments; otherwise, it is determined that the current process is in a shutdown state.
[0104] Example 2
[0105] Based on Example 1, this embodiment provides an intelligent identification system for the construction progress of a steel-concrete composite bridge tower, including a cloud server, a video image acquisition device, a vehicle data collector, a tower crane data collector, a climbing frame data collector, and a screw force monitoring device.
[0106] There are multiple video image acquisition devices that can be installed at key locations around the bridge tower to collect video image information within the construction site and upload it to the cloud server. The video image acquisition devices can collect image information of the current bridge tower, image information inside the steel segment, image information on the concrete pouring platform, etc. The cloud server can calculate the current height of the tower top based on the image information of the current bridge tower, and determine whether there are construction workers working based on the image information inside the steel segment and the image information on the concrete pouring platform.
[0107] The vehicle data collector is used to collect the driving data of flatbed trucks and concrete tank trucks, as well as the image data of the load of the flatbed truck and upload it to the cloud server; the vehicle data collector includes a positioning device and a vehicle-mounted camera. The cloud server can obtain the driving trajectory of the vehicle based on the positioning device, and combine it with the load captured by the vehicle-mounted camera to determine the current process. In addition, by installing RFID tags on the vehicle and setting up card readers in the corresponding construction area, combined with the video image data collected by the camera, the vehicle's position and driving trajectory can be accurately tracked.
[0108] The tower crane data collector is used to collect lifting weight information and lifting object image information and upload it to the cloud server. The tower crane data collector includes a gravity sensor and a tower crane camera. The gravity sensor is used to detect the weight of the lifting object, and the tower crane camera is used to photograph the lifting object. The cloud server can judge the type of the lifting object based on the weight of the lifting object and the image information of the lifting object, thereby determining the current process.
[0109] The climbing frame data collector is used to collect the operating status of the climbing frame and the top height of the climbing frame and upload them to the cloud server. The climbing frame data collector includes a distance sensor, which is used to measure the height between the top of the climbing frame and the ground. At the same time, it can judge the operating status of the climbing frame. If the height between the top of the climbing frame and the ground obtained by the cloud server remains unchanged, it means that the operating status of the climbing frame is stopped.
[0110] The screw force monitoring equipment is used to monitor the screw force of the four corner points of the bridge tower limbs during the entire process of bridge tower construction and upload it to the cloud server.
[0111] The above-described embodiments are only used to illustrate the technical solutions of the present application, rather than to limit them. Although the present application is described in detail with reference to the above-mentioned embodiments, a person skilled in the art should understand that the technical solutions described in the above-mentioned embodiments can still be modified, or some of the technical features can be replaced by equivalents; and these modifications or replacements do not make the essence of the corresponding technical solutions deviate from the spirit and scope of the technical solutions of the embodiments of the present application, and should be included in the protection scope of the present application.
Claims
1. A method for intelligently identifying the construction progress of a steel-concrete composite bridge tower, characterized in that: include: The steel-concrete composite bridge tower includes n groups of bridge tower segments, and the construction process of each group of bridge tower segments includes at least one tower column steel segment hoisting construction process and one tower column concrete pouring construction process. Each group of bridge tower segments includes at least one sub-segment, and each sub-segment corresponds to one tower column steel segment hoisting construction process. The tower column steel segment hoisting construction process includes the hoisting construction preparation sub-process, steel segment hoisting and positioning sub-process, steel segment connection sub-process, and reinforcement construction sub-process. The tower column concrete pouring construction process includes the pouring construction preparation sub-process, concrete pouring sub-process, and concrete curing sub-process. Obtain information on climbing frames, screw force monitoring equipment, flatbed trucks, concrete tankers, truck pumps, tower cranes, concrete pouring platforms, and construction personnel to identify construction progress.
2. The method for intelligently identifying the construction progress of a steel-concrete composite bridge tower according to claim 1 is characterized in that: Methods for identifying construction progress include: S1. Obtain the current constructed tower top height, compare the current constructed tower top height with the top elevation of each sub-segment in each group of bridge tower segments, and determine that the current constructed tower top height is equal to the top elevation of the j-th sub-segment in the i-th group of bridge tower segments; S2, determining whether the operation state of the climbing frame is climbing, if so, executing step S21; S21. Determine whether the j-th sub-segment in the i-th group of bridge tower segments is the last sub-segment of the i-th group of bridge tower segments. If so, confirm that the current sub-process is in the casting construction preparation sub-process of the i-th group of bridge tower segments; otherwise, confirm that the current sub-process is in the hoisting construction preparation sub-process of the j+1-th sub-segment in the i-th group of bridge tower segments.
3. The method for intelligently identifying the construction progress of a steel-concrete composite bridge tower according to claim 2 is characterized in that: In step S2, if the running state of the climbing frame is not climbing, step S22 is executed, and step S22 includes: Determine whether the top elevation of the climbing frame is greater than the current height of the tower top that has been constructed. If not, execute step S3, which includes: determining the current construction progress based on the tower crane and construction personnel information; The top elevation of the climbing frame is the height of the top of the guardrail of the uppermost construction platform of the climbing frame.
4. The method for intelligently identifying the construction progress of a steel-concrete composite bridge tower according to claim 3 is characterized in that: Step S3 includes: S31, obtaining the lifting weight information of the tower crane and the image information of the lifting object of the tower crane; S32, judging whether the temporary construction passage is being hoisted on site, if the hoisting weight of the tower crane is equal to the weight of the temporary construction passage and the hoisted object is identified as a temporary construction passage according to the hoisting object image information, it is determined that the temporary construction passage is being hoisted on site, and the current process is the steel segment connection sub-process of the j-th sub-segment in the i-th group of bridge tower segments, otherwise, executing step S33; S33, obtaining image information of the inside and outside of the j-th sub-segment in the i-th group of bridge tower segments, and determining whether there are construction workers performing construction inside or outside the j-th sub-segment in the i-th group of bridge tower segments; If there are construction workers on the construction platform outside the j-th sub-segment in the i-th group of bridge tower segments, then the current step is the steel segment connection sub-process of the j-th sub-segment in the i-th group of bridge tower segments; If there are construction workers inside the steel pipe of the j-th sub-segment in the i-th group of bridge tower segments, then the current sub-process is the steel bar construction sub-process of the j-th sub-segment in the i-th group of bridge tower segments; Otherwise, it is determined that the current state is down.
5. The method for intelligently identifying the construction progress of a steel-concrete composite bridge tower according to claim 3 is characterized in that: In step S22, if the top elevation of the climbing frame is greater than the current constructed tower top height, step S4 is executed. Step S4 includes: determining whether the jth sub-segment in the i-th group of bridge tower segments is the last sub-segment. If not, step S5 is executed: determining the current construction progress based on the tower crane information and the flatbed transport vehicle information.
6. The method for intelligently identifying the construction progress of a steel-concrete composite bridge tower according to claim 5 is characterized in that: Step S5 includes: S51, obtaining the lifting weight information of the tower crane and the image information of the lifting object of the tower crane; S52, judging whether the steel segment is being hoisted on site, if the hoisting weight of the tower crane is equal to the weight of the steel segment and the hoisted object is identified as a steel segment according to the hoisting object image information, it is determined that the steel segment is being hoisted on site, and the steel segment hoisting and positioning sub-process of the j+1th sub-segment in the i-th group of bridge tower segments is currently in progress, otherwise, executing step S53; S53. Obtain the driving track, current position and image information of the load of the flatbed transport vehicle, and determine whether there is a flatbed transport vehicle traveling from the steel structure processing plant to the construction site or is located within the construction site, and whether the load of the flatbed transport vehicle is steel segments. If so, the current construction process is the hoisting construction preparation sub-process of the j+1th sub-segment of the i-th group of bridge tower segments; otherwise, it is determined that the current construction process is in a stopped state.
7. The method for intelligently identifying the construction progress of a steel-concrete composite bridge tower according to claim 5 is characterized in that: In step S4, if the jth sub-segment in the i-th group of bridge tower segments is the last sub-segment, step S6 is executed, and step S6 includes: judging the current construction progress based on the information of the screw force monitoring equipment, flatbed transport vehicle, concrete tanker, truck pump, tower crane, concrete pouring platform and construction personnel.
8. The method for intelligently identifying the construction progress of a steel-concrete composite bridge tower according to claim 7 is characterized in that: Step S6 includes: S61, obtaining image information of the currently constructed tower top, determining whether the concrete pouring platform is located at the top of the currently constructed bridge tower, and if so, obtaining the location information of the truck pump and the driving track and current location of the concrete tank truck; S62, determining whether the truck pump is located within the scope of the construction site and whether there are concrete tank trucks traveling between the construction site and the concrete processing plant; if so, determining the concrete pouring sub-process currently in the i-th group of bridge tower segments; otherwise, executing step S63; S63. Obtain image information of the working surface above the j-th sub-segment in the i-th group of bridge tower segments and the interior of the concrete pouring platform to determine whether there are construction workers performing pump pipe installation construction. If so, determine that the current process is in the pouring construction preparation sub-process of the i-th group of bridge tower segments; otherwise, determine that the current process is in a shutdown state.
9. The method for intelligently identifying the construction progress of a steel-concrete composite bridge tower according to claim 8 is characterized in that: In step S61, if the concrete pouring platform is not located at the top of the currently constructed bridge tower, step S7 is executed: S71, obtaining and analyzing the monitoring data of the screw force monitoring device to determine whether the concrete pouring of the i-th group of bridge tower segments is completed, if so, executing step S72, otherwise, executing step S74; S72, obtaining the lifting weight information of the tower crane and the image information of the lifting object of the tower crane, and judging whether the lifting of the steel segment is being carried out on site; if the lifting weight of the tower crane is equal to the weight of the steel segment and the lifting object is identified as a steel segment according to the image information of the lifting object, it is determined that the lifting of the steel segment is being carried out on site, and the steel segment lifting and positioning sub-process of the first sub-segment in the i+1th group of bridge tower segments is determined; otherwise, executing step S73; S73, obtaining the driving track, current position and image information of the load of the flatbed transport vehicle, determining whether there is a flatbed transport vehicle traveling from the steel structure processing plant to the construction site or located within the scope of the construction site, and whether the load of the flatbed transport vehicle is a steel segment; if so, the current construction process is the hoisting construction preparation sub-process of the first sub-segment in the i+1th group of bridge tower segments; otherwise, according to the completion time of the concrete pouring sub-process of the i-th bridge tower segment, determining whether the current construction process is the concrete curing sub-process of the i-th group of bridge tower segments; S74, obtaining the lifting weight information of the tower crane and the image information of the lifting object of the tower crane, and determining whether the concrete pouring platform is being hoisted on site; if the lifting weight of the tower crane is equal to the weight of the concrete pouring platform and the lifting object is identified as the concrete pouring platform according to the image information of the lifting object, then the concrete pouring platform is currently being hoisted, and it is determined that the pouring construction preparation sub-process of the i-th group of bridge tower segments is currently in progress; otherwise, executing step S75; S75. Obtain the driving track, current position and image information of the flatbed transport vehicle, and determine whether there is a flatbed transport vehicle traveling from the steel structure processing plant to the construction site or is located within the construction site, and whether the load of the flatbed transport vehicle is a concrete casting platform. If so, the current process is in the casting construction preparation sub-process of the i-th group of bridge tower segments; otherwise, it is determined that the current process is in a shutdown state.
10. An intelligent identification system for the construction progress of a steel-concrete composite bridge tower, characterized in that: Including cloud servers, video image acquisition equipment, vehicle data collectors, tower crane data collectors, climbing frame data collectors, and screw force monitoring equipment; The video image acquisition device is used to collect video image information within the construction site and upload it to the cloud server; The vehicle data collector is used to collect the driving data of the flatbed transport truck and the concrete tank truck and the image data of the load of the flatbed transport truck and upload them to the cloud server; The tower crane data collector is used to collect lifting weight information and lifting object image information and upload them to the cloud server; The climbing frame data collector is used to collect the operating status of the climbing frame and the top height of the climbing frame and upload them to the cloud server; The screw force monitoring device is used to monitor the screw force of the screws at the four corner points of the tower limb during the entire process of the tower construction and upload it to the cloud server; The cloud server is used to determine the construction progress based on various types of information obtained.