Soft foundation replacement and filling construction method
Through the construction of weak foundation replacement, including stone throwing, silting and reinforced concrete replacement, large raft foundations are formed, which solves the construction difficulty and safety risks of traditional pile foundations under complex geological conditions, and achieves construction efficiency and safety. promote.
Patent Information
- Application Number
- CN202411371321.2
- Authority / Receiving Office
- CN · China
- Patent Type
- Applications(China)
- Current Assignee / Owner
- Filing Date
- 2024-09-29
- Publication Date
- 2024-11-15
AI Technical Summary
In deep foundation pits, areas with complex geological conditions and abundant groundwater, traditional pile foundation construction has problems such as high difficulty, high safety hazards and long cycles, especially the serious hole collapse within the cave area, high concrete consumption and difficult sewage treatment.
Weak foundation replacement construction methods are adopted, including foundation excavation, stone throwing and silting, preset holding layer construction, reinforced concrete replacement and high-pressure grouting, to form a large raft foundation, and solve the problem of pile foundation in Construction difficulty and safety hazards under complex geological conditions.
The construction difficulty and construction period are reduced, construction safety is improved, and the compression and shear resistance of the foundation is enhanced through reinforcement bridge formation and high-pressure grouting, solving the impact of groundwater and sewage treatment problems.
Smart Images

Figure CN118958261A_ABST
Abstract
Description
Technical Field
[0001] The invention relates to the technical field of foundation construction, and in particular to a soft foundation replacement construction method. Background Art
[0002] In the construction field, pile foundation construction is generally used in restricted areas such as deep foundation pits, complex geological conditions and large groundwater areas. However, for areas with complex geological conditions, especially those with underground caves and abundant groundwater, pile foundation construction will cause serious hole collapse in the cave during the drilling and backfilling process, which requires repeated backfilling of concrete. The consumption of concrete is huge, and many construction areas are located in the central urban areas of the city with high requirements for sewage discharge. How to deal with the large amount of mud generated during pile foundation construction has also become a difficulty in pile foundation construction. Static load tests can only be carried out after the pile foundation reaches the design strength of 28 days, which delays the construction period. Therefore, for construction sites with deep foundation pits, complex geological conditions, large groundwater and complex cave distribution, traditional pile foundation construction is difficult, has great safety hazards and a long construction period. Summary of the invention
[0003] In view of the above-mentioned deficiencies in the prior art, the object of the present invention is to provide a soft foundation replacement construction method to solve the problems of great difficulty, great safety hazards and long construction period of the existing pile foundation.
[0004] In order to solve the above technical problems, the technical solution adopted by the present invention is as follows: a soft foundation replacement construction method, comprising the following steps: a) Foundation excavation; Within the preset range, the soft foundation at the preset bearing layer depth is excavated to expose the rock layer around the soft foundation area to form a replacement pit; b) Throwing stones to squeeze out silt; Throwing blocks of preset grade into the replacement pit, so that the blocks are densely piled below the preset bearing layer, and digging out the water, soil and / or silt squeezed out by the blocks in the replacement pit; c) Construction of pre-set bearing layer; Rebars are planted at the preset elevation of the rock layer exposed in the replacement pit, and a steel mesh is laid horizontally to connect the surrounding sides of the steel mesh with the planted bars on the rock layer; concrete is poured into the replacement pit to the preset elevation, and after maintenance, a preset bearing layer raft foundation is formed, completing the replacement construction of the soft foundation.
[0005] As an optimization, in step a, when the inclination angle of the exposed rock layer exceeds a preset angle, the surface of the exposed rock layer is processed to form a step structure on the surface.
[0006] As an optimization, in step b, before throwing the stone blocks, a groundwater drainage pipe is pre-buried in the replacement pit, the lower end of the drainage pipe extends below the preset bearing layer, and the upper end extends out of the replacement pit.
[0007] As an optimization, the steel mesh is arranged in multiple layers along the depth direction of the replacement pit, and there are spacings and support members between adjacent steel meshes and between the steel meshes and the bottom of the replacement pit.
[0008] As an optimization, the concrete is self-compacting concrete.
[0009] As an optimization, condensation pipes are buried in the raft foundation.
[0010] As an optimization, in step c, after the concrete is cured to a preset strength, grouting holes are drilled on the raft foundation, the grouting holes penetrate the raft foundation, and concrete repair mortar is injected into the grouting holes.
[0011] As an optimization, the concrete repair mortar is a cement-water glass double liquid slurry.
[0012] Compared with the prior art, the present invention has the following advantages: by treating the soft foundation with "stone throwing to squeeze out silt + organized drainage + rock reinforcement bridging + reinforced concrete replacement + high-pressure grouting", the foundation form is changed from "raft foundation + pile foundation" to a large raft foundation, which solves the problems of difficult or high-cost construction of pile foundations due to complex geological conditions, large groundwater, and restricted construction environment, reduces the construction difficulty, saves construction period, and improves construction safety. BRIEF DESCRIPTION OF THE DRAWINGS
[0013] Figure 1 It is a schematic diagram of the construction process of the present invention; In the figure: 1 rock layer, 2 stones, 3 steel mesh, 4 raft foundation, 5 drainage pipe, 6 condenser pipe. DETAILED DESCRIPTION
[0014] The present invention will be further described below in conjunction with the accompanying drawings and embodiments.
[0015] In order to make the purpose, technical solutions and advantages of the embodiments of the present invention clearer, the technical solutions in the embodiments of the present invention will be clearly and completely described below in conjunction with the drawings in the embodiments of the present invention. Obviously, the described embodiments are part of the embodiments of the present invention, not all of the embodiments. Therefore, the following detailed description of the embodiments of the present invention provided in the drawings is not intended to limit the scope of the claimed invention, but merely represents the selected embodiments of the present invention. Based on the embodiments of the present invention, all other embodiments obtained by ordinary technicians in this field without creative work are within the scope of protection of the present invention.
[0016] It should be noted that similar numbers and letters represent similar items in the following drawings, so once an item is defined in one drawing, it does not need to be further defined and explained in the subsequent drawings. In the description of the present invention, it should be noted that the orientation or position relationship indicated by the terms "center", "upper", "lower", "left", "right", "vertical", "horizontal", "inside", "outside", etc. is based on the orientation or position relationship shown in the drawings, or the orientation or position relationship in which the invention product is usually placed when used, which is only for the convenience of describing the present invention and simplifying the description, rather than indicating or implying that the device or element referred to must have a specific orientation, be constructed and operated in a specific orientation, and therefore cannot be understood as a limitation of the present invention. In addition, the terms "first", "second", "third", etc. are only used to distinguish the description, and cannot be understood as indicating or implying relative importance. In addition, the terms "horizontal", "vertical", etc. do not mean that the components are absolutely horizontal or suspended, but can be slightly tilted. For example, "horizontal" only means that its direction is more horizontal than "vertical", and does not mean that the structure must be completely horizontal, but can be slightly tilted. In the description of the present invention, it is also necessary to explain that, unless otherwise clearly specified and limited, the terms "set", "install", "connect", and "connect" should be understood in a broad sense, for example, it can be a fixed connection, a detachable connection, or an integral connection; it can be a mechanical connection or an electrical connection; it can be a direct connection, or it can be indirectly connected through an intermediate medium, or it can be the internal communication of two elements. For ordinary technicians in this field, the specific meanings of the above terms in the present invention can be understood according to specific circumstances.
[0017] Example: See Figure 1 A soft foundation replacement construction method comprises the following steps: a) Foundation excavation; Within the preset range, the weak foundation at the preset bearing layer depth is excavated to expose the medium-weathered rock layer 1 around the weak foundation area to form a replacement pit. Specifically, for areas with complex geological conditions, the weak foundation is generally unevenly distributed and is mainly filled between rock layers with complex shapes. During the foundation excavation process, the weak foundation between the rock layers is excavated, and considering that the exposed rock layers need to bear the load, after the rock layer 1 is exposed, the inclination angle of the rock wall of each rock layer 1 is checked. When the inclination angle of the exposed rock layer 1 is large, the surface of the exposed rock layer 1 is processed to form a step structure on its surface, so that the foundation structure formed after pouring can better transfer the load to the rock layer 1 and improve the stability of the foundation.
[0018] b) Throwing stones to squeeze out silt; Throw blocks 2 of preset gradation into the replacement pit, so that the blocks 2 are piled up and compacted to a preset elevation below the preset bearing layer, thereby squeezing out the soft plastic soil, mud, water or silt in the cave that cannot be cleaned below the preset bearing layer, and digging out the water, soil and / or silt squeezed out by the blocks 2 in the replacement pit. Specifically, the replacement blocks are made from local materials, with a strength of not less than 30Mpa, and the particle size of the blocks 2 is not less than 300mm. The replaced mud is turned over and dried, and then abandoned to the designated dumping point with the earth and stone. In order to ensure the quality of the replacement, the replacement area is cleaned with a high-pressure water gun after the excavation of soft soil, local rock mass and the squeezing of silt by throwing stones in the cave is completed.
[0019] Centralized drainage (pre-buried drainage pipe 5); At the groundwater outlet point in the project replacement area, one or more drainage pipes 5 made of DN300 seamless cast iron steel pipes are pre-buried to below the preset bearing layer depth of the base, and the ends of the steel pipes are welded in advance with reserved flanges for later plugging. Its main function is to dredge the groundwater here, reduce the head pressure, and reduce the impact of groundwater on the quality of concrete pouring. At the same time, groundwater can be reused for surface water storage and maintenance after large-volume concrete pouring and cooling pipe circulation water source.
[0020] c) Raft foundation construction; Along the contour of the replacement pit, at the preset elevation of the rock layer 1 exposed in the replacement pit, reinforced steel bars are planted to build bridges, and steel meshes 3 are horizontally laid in layers, so that the surrounding sides of the steel meshes 3 are connected to the planted steel bars on the rock layer. Specifically, the steel meshes 3 are arranged in three layers along the depth direction of the replacement pit, and there are spacings and supports between adjacent steel meshes 3 and between the steel meshes 3 and the bottom of the replacement pit. Among them, concrete pads are used as supports between the steel meshes 3 and the bottom of the replacement pit, and finished steel bar horse stools are used between adjacent steel meshes 3 to ensure that the multi-layer steel meshes 3 form a whole. The concrete pads are processed into grooves during production, so that the steel bars and pads are better combined together to ensure that they are not offset or shifted. In this embodiment, the steel mesh is made of criss-crossed steel bars, the planted bars are arranged in φ25@250, and the depth of the rock layer is not less than 500mm, and the steel bars of the steel mesh are arranged in φ14@500. After the steel mesh is erected, concrete is poured into the replacement pit until the concrete completely covers the steel mesh and is poured to the preset elevation. After the maintenance is completed, the preset bearing layer raft foundation 4 is formed, and the replacement construction of the weak foundation is completed. The additional steel mesh and embedded steel bars in this range allow the raft foundation 4 to transfer force to the surrounding medium-weathered rock layer in the form of a bridge and pour the original groove, so that the concrete and the medium-weathered rock layer form a whole, and improve the mechanical properties of the bearing layer such as compression and shear resistance. Specifically, since the poured concrete belongs to the large-volume concrete pouring construction, in order to reduce the risk of concrete cracking, reduce the internal temperature peak of the concrete and the temperature difference between the inside and the outside, multi-layer condenser pipes 6 are arranged inside the large-volume concrete to dissipate heat inside the concrete. The condenser pipe 6 is arranged using a steel support, and the circulating cooling water pipe adopts a thin-walled steel pipe with a diameter of 50 mm and a wall thickness of 2.5 mm, and the end is tapped and connected with a bend pipe joint and a straight pipe joint. The pipe joint is connected with a straight pipe joint. The connection should be firm and the cold tape should be wrapped to prevent water leakage. The condenser pipe 6 should be firmly fixed to the steel bar to prevent failure caused by the influence of concrete pouring and tamping. A valve is set at the inlet and outlet of the condenser pipe 6 to control the direction and flow of water inlet. In this embodiment, the horizontal spacing of the condenser pipes is 1.0m and the layer spacing is 0.9m. The specific construction can be appropriately adjusted according to the size of the large volume concrete.
[0021] When pouring concrete, the concrete should be poured in layers, and there should be no construction joints between the upper and lower layers, that is, the upper layer of concrete must be continuously constructed before the lower layer of concrete begins to set. The thickness of each layer of concrete is 300 to 500 mm. The pouring sequence of each layer should start from the bottom and pour from one end to the other along the long side.
[0022] The concrete adopts C30P10 self-compacting commercial concrete. The concrete is pumped to the pouring site by a concrete tank truck. A boom pump is used to pour the concrete in layers from low to high. The pouring process of "partitioning and fixing points, one slope, pouring thin layers, step by step, and reaching the top at one time" is adopted when pouring concrete. The specifications of the pump truck are determined according to the pouring area. After the concrete pouring is completed, the concrete surface is stored with water for maintenance, and the outlet of the cooling water pipe is used for water storage and maintenance. Temporary small embankments are built around to store water for maintenance. The water height is maintained at 40-60mm, and it is replenished in time after evaporation.
[0023] High pressure grouting; After pouring, since groundwater may corrode concrete, each water outlet and gap is measured and positioned before pouring concrete. After the concrete strength reaches 70%, a grouting hole is drilled on the raft foundation. The grouting hole runs through the raft foundation, and concrete repair mortar is injected into the grouting hole under high pressure for drilling and grouting reinforcement. The grouting hole diameter is 20mm, the hole depth is not less than the replacement concrete thickness + 500mm, and the hole spacing is 1000mm in a plum blossom shape. In this embodiment, the concrete repair mortar is cement-water glass double liquid slurry, PO42.5 cement is selected, the cement slurry water-cement ratio is 0.8:1~1:1, the cement slurry and water glass volume ratio is 1:0.5~1:0.8, the water glass modulus is 2.4~3.4, and the Baume degree is 22~40°. Grouting is injected using a special high-pressure grouting pump, with a grouting pipe pressure of 1.5~3.0Mpa, an initial grouting pressure of 1.0~1.5Mpa, a normal grouting pressure of 0.8~1.8Mpa, and a final hole grouting pressure of 1.5~2.0Mpa. Boring grouting allows the slurry to penetrate into the gaps between the blocks and rocks in the cave, forming high-strength concrete. As the amount of grouting increases, the cement slurry continues to penetrate into the soft rock and soil due to groundwater immersion, increasing the bearing area of the replacement concrete, which is equivalent to reinforcing the base of the replacement area. When the permeability of the cement slurry is limited by the gaps in the surrounding rock formations, the pressure continues to rise, and the replacement concrete and blocks are squeezed, compacted, filled, consolidated, and infiltrated, which will effectively reinforce or compact the disturbed bearing layer of the base, improve the connection between the replacement material and the rock formation, and improve the bearing capacity of the reinforced concrete. Finally, after the concrete reaches the design strength, the foundation bearing capacity is tested and a report is issued, and the drainage pipe is blocked. After the construction of the present invention is completed, the final foundation structure is formed. The raft foundation is bridged by planting reinforcement to cross the soft foundation area. The load can be well transferred to the rock layer, and in conjunction with the replacement structure layer in the soft foundation area, the load is further transferred to the surrounding rock layer, thereby ensuring the strength and stability of the entire foundation structure.
[0024] In summary, the present invention changes the foundation form from "raft foundation + pile foundation" to a large raft foundation by treating the soft foundation with "stone throwing + organized drainage + rock reinforcement bridge + reinforced concrete replacement + high-pressure grouting", thereby solving the problems caused by complex geological conditions, large groundwater, and restricted construction environment, reducing the construction difficulty, saving construction time, and improving construction safety.
[0025] Finally, it should be noted that the above embodiments are only used to illustrate the technical solution of the present invention rather than to limit the technical solution. Those skilled in the art should understand that those modifications or equivalent substitutions of the technical solution of the present invention that do not depart from the purpose and scope of the technical solution should be included in the scope of the claims of the present invention.
Claims
1. A soft foundation replacement construction method, characterized by: The following steps are included: a) Foundation excavation; Within the preset range, the soft foundation at the preset bearing layer depth is excavated to expose the rock layer around the soft foundation area to form a replacement pit; b) Throwing stones to squeeze out silt; Throwing stones of a preset grade into the replacement pit, so that the stones are densely piled below the preset bearing layer, and digging out the water, soil and / or silt squeezed out by the stones in the replacement pit; c) Construction of pre-set bearing layer; Rebars are planted at the preset elevation of the rock layer exposed in the replacement pit, and a steel mesh is laid horizontally to connect the surrounding sides of the steel mesh with the planted bars on the rock layer; concrete is poured into the replacement pit to the preset elevation, and after maintenance, a preset bearing layer raft foundation is formed, completing the replacement construction of the soft foundation.
2. A soft foundation replacement construction method according to claim 1, characterized in that: In step a, when the inclination angle of the exposed rock layer exceeds a preset angle, the surface of the exposed rock layer is processed to form a step structure on the surface.
3. A soft foundation replacement construction method according to claim 1, characterized in that: In step b, before throwing the stone blocks, a groundwater drainage pipe is pre-buried in the replacement pit, the lower end of the drainage pipe extends below the preset bearing layer, and the upper end extends out of the replacement pit.
4. A soft foundation replacement construction method according to claim 1, characterized in that: The steel mesh is arranged in multiple layers along the depth direction of the replacement pit, and there are spacings between adjacent steel meshes and between the steel meshes and the bottom of the replacement pit, and support members are provided.
5. A soft foundation replacement construction method according to claim 1, characterized in that: The concrete is self-compacting concrete.
6. A soft foundation replacement construction method according to claim 1, characterized in that: Condensation pipes are buried in the raft foundation.
7. A soft foundation replacement construction method according to claim 1, characterized in that: In step c, after the concrete is cured to a preset strength, grouting holes are drilled on the raft foundation, the grouting holes penetrate the raft foundation, and concrete repair mortar is injected into the grouting holes.
8. A soft foundation replacement construction method according to claim 7, characterized in that: The concrete repair mortar is a cement-water glass double liquid slurry.
Citation Information
Cited By
Contaminated soil replacement method and light replacement structure
CN121250870A
Method for replacing contaminated soil and light replacement structure
CN121250870B