Peak clipping control method and device for wind driven generator

By combining dynamic working conditions and steady-state working conditions control, the torque management of wind turbines is managed by using PD and PI control, the service life problem caused by wind turbine fluctuations is solved, and more stable operation and longer equipment life is achieved.

CN118959222APending Publication Date: 2024-11-15XJ GRP CORP +1
View PDF 0 Cites 0 Cited by

Patent Information

Application Number
CN202411286928.0
Authority / Receiving Office
CN · China
Patent Type
Applications(China)
Current Assignee / Owner
Filing Date
2024-09-13
Publication Date
2024-11-15

AI Technical Summary

Technical Problem

The existing peak-cutting control strategy of wind turbines leads to a reduction in system stability, and frequent long-term periodic fluctuations in wind turbine power and speed, resulting in increased fatigue load and reduced service life.

Method used

Using a combination of dynamic operating condition control and steady-state operating condition control, the torque control of the wind turbine under dynamic operating conditions and steady-state operating conditions is carried out through PD control and PI control respectively, taking into account the change of speed and rotational acceleration. To suppress power and speed fluctuations.

Benefits of technology

Effectively suppress the fluctuations in wind turbine power and speed, extend the service life, improve system stability, and avoid long-term periodic fluctuations.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN118959222A_ABST
    Figure CN118959222A_ABST
Patent Text Reader

Abstract

The invention relates to a peak clipping control method and device for a wind driven generator, and belongs to the technical field of wind power generation. The method comprises the steps that if the output power of the wind driven generator meets the dynamic working condition, the torque output by the wind driven generator is controlled through dynamic working condition control; the control quantity of the dynamic working condition control is obtained by PD control, the increment of a proportional link in the PD control is determined according to the variation of the deviation between the actual value and the target value of the rotating speed of the generator, and the increment of a differential link is determined according to the variation of the rotating acceleration of the generator and the control period. The dynamic working condition control obtained through PD control considers the two factors of the rotation acceleration and the rotation speed of the wind driven generator at the same time, the consideration range is more comprehensive, and the dynamic working condition control takes the variable quantity of the rotation acceleration of the wind driven generator as the factor for determining the control quantity, so that the wind driven generator is controlled in advance, and the control accuracy is improved. Therefore, fluctuation of power and rotating speed of the wind driven generator can be inhibited in advance.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The invention belongs to the technical field of wind power generation, and in particular relates to a peak shaving control method and equipment for a wind generator. Background Art

[0002] As environmental pollution becomes increasingly serious, countries are paying more and more attention to and developing clean and renewable energy. Wind power is an important component of clean and renewable energy. As wind power generation technology becomes increasingly mature, wind turbine power generation is distributed in wider and wider areas. However, there are also problems with wind power generation technology. For example, the operation of wind turbines will be affected by wind speed. When the wind speed continues to rise and exceeds a certain value, the load on the wind turbine will increase rapidly. Excessive load on the wind turbine will affect the normal operation of the wind turbine.

[0003] Geng Lihong, Wang Chaodong, Xie Jinjuan and others proposed a wind turbine peak shaving control strategy in a paper titled "Optimal Control Technology of Wind Turbine Load Based on Peak Shaving Regulation" published in the Journal of Solar Energy in February 2020. The wind turbine peak shaving control strategy can effectively solve the problem of excessive load on wind turbines, but it was found during operation that after the peak shaving control strategy is put into use, the system stability will be reduced, and the power and speed of wind turbines will frequently fluctuate for a long time. Even after the wind speed is stable, the power and speed of wind turbines will continue to fluctuate for a period of time, resulting in an increase in the fatigue load of the wind turbine and a reduction in the service life of the wind turbine. Summary of the invention

[0004] The purpose of the present invention is to provide a wind turbine peak shaving control method and device to solve the problem in the prior art that the periodic fluctuations in wind turbine power and speed caused by the peak shaving control strategy reduce the service life of the wind turbine.

[0005] In order to solve the above technical problems, the present invention provides a wind turbine peak shaving control method, the method comprising:

[0006] If the output power of the wind turbine generator meets the dynamic operating conditions, the torque output by the wind turbine generator is controlled through dynamic operating condition control; the control quantity of the dynamic operating condition control is obtained by PD control, and the increment of the proportional link in the PD control is determined according to the change in the deviation between the actual value and the target value of the generator speed, and the increment of the differential link is determined according to the change in the generator rotation acceleration and the control period.

[0007] Furthermore, if the output power of the wind turbine generator meets the steady-state operating conditions but does not meet the dynamic operating conditions, the torque output by the wind turbine generator is controlled through steady-state operating condition control; if the output power of the wind turbine generator does not meet the dynamic operating conditions and does not meet the steady-state operating conditions, the current control method is used for control; the control quantity of the steady-state operating condition control is obtained by PI control, and the increment of the proportional link in the PI control is determined according to the change in the actual speed of the generator, and the increment of the integral link is determined according to the deviation between the actual value of the generator speed and the target value.

[0008] Further, the method of determining the differential link of the PD control according to the change amount of the generator rotation acceleration and the control period includes: determining the increment of the differential link of the PD control according to the ratio of the change amount of the generator rotation acceleration determined by the difference between the generator rotation acceleration limit values ​​of the current control period and the previous control period to the control period; the generator rotation acceleration limit value is obtained by the generator rotation acceleration after acceleration limit;

[0009] The generator rotation acceleration is limited by the acceleration amplitude to obtain the generator rotation acceleration amplitude limit value, including:

[0010] If the generator rotation acceleration is greater than the upper threshold of the normal fluctuation range, the generator rotation acceleration limit value is obtained from the upper threshold of the normal fluctuation range; if the generator rotation acceleration is less than the lower threshold of the normal fluctuation range, the generator rotation acceleration limit value is obtained from the lower threshold of the normal fluctuation range; otherwise, the generator rotation acceleration limit value is obtained from the current generator rotation acceleration.

[0011] Furthermore, the increment of the differential link of the PD control determined by the ratio of the change in the generator rotation acceleration determined by the difference between the generator rotation acceleration limit values ​​of the current control cycle and the previous control cycle to the control cycle is:

[0012]

[0013] Among them, △y d is the incremental value of the differential link, K d is the differential coefficient, T is the control period, They are the generator rotation acceleration limit values ​​of the nth control cycle and the n-1th control cycle respectively.

[0014] Furthermore, the control quantity of dynamic condition control obtained by PD control is:

[0015]

[0016] In the formula, y PD (n), y PD(n-1) are the control quantities of the dynamic working condition control in the nth and n-1th control cycles respectively, K p is the proportional coefficient, e(n) and e(n-1) are the deviations between the actual value of the generator speed and the target value of the generator speed in the nth control cycle and the n-1th control cycle.

[0017] Furthermore, the control quantity of steady-state operating condition control obtained by PI control is:

[0018] y PI (n) = y PI (n-1)+K p [e(n)-e(n-1)]+K i e(n)

[0019] In the formula, y PI (n), y PI (n-1) are the control quantities of steady-state control in the nth and n-1th control cycles, respectively. K p is the proportionality coefficient, K i is the integral coefficient, T is the control period, e(n) and e(n-1) are the deviations between the actual value of the generator speed and the target value of the generator speed in the nth control period and the n-1th control period.

[0020] Furthermore, it is determined whether the working condition of the wind turbine generator satisfies a steady-state working condition or a dynamic working condition according to the change of the power output by the wind turbine generator.

[0021] Furthermore, the method of judging whether the operating condition of the wind turbine generator meets the dynamic operating condition according to the change of the power output by the wind turbine generator includes: if the output power of the wind turbine generator satisfies that the absolute value of the slope of the power fitting curve is greater than the set slope threshold, then it is judged that the operating condition of the wind turbine generator meets the dynamic operating condition; otherwise, it is judged that it does not meet the condition.

[0022] Furthermore, the method of judging whether the working condition of the wind turbine generator meets the steady-state working condition according to the change of the power output by the wind turbine generator includes:

[0023] If the maximum power change within the set time period satisfied by the wind turbine output power is less than the set change threshold, it is determined that the working condition of the wind turbine meets the steady-state working condition; otherwise, it is determined that it does not meet the condition.

[0024] In order to solve the above technical problems, the present invention further provides a wind turbine peak clipping control device, comprising a processor, wherein the processor is used to execute a computer program to implement the steps of a wind turbine peak clipping control method.

[0025] The beneficial effects of the above technical solution are as follows: the present invention provides a new peak shaving control method for wind turbines, which controls the torque output by the wind turbine in dynamic conditions by using the dynamic condition control obtained by PD control. The dynamic condition control obtained by PD control takes into account both the rotational acceleration of the wind turbine and the speed of the wind turbine, and has a more comprehensive consideration scope. Moreover, since the dynamic condition control takes the change in the rotational acceleration of the wind turbine as a factor in determining the control amount, the wind turbine is controlled in advance, thereby suppressing the fluctuation of the power and speed of the wind turbine in advance. BRIEF DESCRIPTION OF THE DRAWINGS

[0026] Figure 1 is an example diagram of the operation flow of the wind turbine peak shaving control method according to an embodiment of the wind turbine peak shaving control method of the present invention;

[0027] Figure 2 It is a comparison diagram of the operating effects before and after the application of the wind turbine peak shaving control method in the embodiment of the wind turbine peak shaving control method of the present invention. DETAILED DESCRIPTION

[0028] In order to make the purpose, technical solutions and advantages of the present invention more clear, the present invention is further described in detail below with reference to the accompanying drawings and embodiments.

[0029] Wind turbine peak shaving control method embodiment

[0030] A wind turbine peak shaving control method according to the present embodiment is specifically to timely determine the working condition (i.e., dynamic working condition) of the wind turbine having or about to have a large fluctuation according to the change of the output power of the wind turbine, and for the dynamic working condition, use PD control to obtain the control amount based on the change of the speed deviation of the wind turbine and the change of the speed acceleration to control the output torque of the wind turbine, so as to reduce the amplitude of the power fluctuation of the wind turbine and try to stabilize it quickly, and ensure that when the power fluctuation of the wind turbine is large, the power fluctuation of the wind turbine is suppressed as much as possible; and for the steady-state working condition, use PI control based on the change of the speed deviation of the wind turbine and the speed deviation of the wind turbine itself to control the output torque of the wind turbine, so as to ensure that when the power fluctuation of the wind turbine is small, the speed deviation of the wind turbine is eliminated as much as possible.

[0031] The wind turbine generator peak shaving control method specifically includes:

[0032] If the output power of the wind turbine generator meets the dynamic operating conditions, the torque output by the wind turbine generator is controlled through dynamic operating condition control; the control quantity of the dynamic operating condition control is obtained by PD control, and the increment of the proportional link in the PD control is determined according to the change in the deviation between the actual value and the target value of the generator speed, and the increment of the differential link is determined according to the change in the generator rotation acceleration and the control period.

[0033] The present invention controls the torque output by the wind turbine in a dynamic working condition by using the dynamic working condition control obtained by PD control. The dynamic working condition control obtained by PD control considers two factors, namely, the rotational acceleration of the wind turbine and the rotational speed of the wind turbine, and has a more comprehensive consideration scope. Moreover, since the dynamic working condition control takes the change in the rotational acceleration of the wind turbine as a factor for determining the control amount, the wind turbine is controlled in advance, thereby being able to suppress the fluctuation of the power and rotational speed of the wind turbine in advance.

[0034] Specifically, the control quantity of dynamic working condition control obtained by PD control is:

[0035]

[0036] In the formula, y PD (n), y PD (n-1) are the control quantities of the dynamic working condition control in the nth and n-1th control cycles respectively, K p is the proportionality coefficient, K d is the differential coefficient, e(n) and e(n-1) are the deviations between the actual value of the generator speed and the target value of the generator speed in the nth control cycle and the n-1th control cycle.

[0037] In this embodiment, the method of determining the differential link of the PD control according to the change amount of the generator rotation acceleration and the control period includes: determining the increment of the differential link of the PD control according to the ratio of the change amount of the generator rotation acceleration determined by the difference between the generator rotation acceleration limit values ​​of the current control period and the previous control period to the control period; the generator rotation acceleration limit value is obtained by the generator rotation acceleration after acceleration limit;

[0038] The generator rotation acceleration is limited by the acceleration amplitude to obtain the generator rotation acceleration amplitude limit value, including:

[0039] If the generator rotation acceleration is greater than the upper threshold of the normal fluctuation range, the generator rotation acceleration limit value is obtained from the upper threshold of the normal fluctuation range; if the generator rotation acceleration is less than the lower threshold of the normal fluctuation range, the generator rotation acceleration limit value is obtained from the lower threshold of the normal fluctuation range; otherwise, the generator rotation acceleration limit value is obtained from the current generator rotation acceleration.

[0040] Specifically, the process of obtaining the generator rotation acceleration limit value through acceleration limit is as follows: the original control parameters of the wind turbine remain unchanged, the wind turbine speed data is collected, and the normal fluctuation range of the wind turbine rotation acceleration a is counted between the starting wind speed and the rated wind speed, which is recorded as [-L, L]. The acceleration ramp limit is set to filter out the noise interference in the acceleration signal. The acceleration ramp limit expression is as follows:

[0041]

[0042]

[0043] Where a is the generator rotation acceleration, is the generator rotation acceleration limit, L is the generator rotation acceleration upper limit, and -L is the generator rotation acceleration lower limit.

[0044] The increment of the differential link of the PD control determined by the ratio of the change in the generator rotation acceleration determined by the difference between the generator rotation acceleration limit value of the current control cycle and the previous control cycle to the control cycle is:

[0045]

[0046] Among them, △y d is the incremental value of the differential link, K d is the differential coefficient, T is the control period, They are the generator rotation acceleration limit values ​​of the nth control cycle and the n-1th control cycle respectively.

[0047] In addition, if the output power of the wind turbine generator meets the steady-state operating conditions but does not meet the dynamic operating conditions, the torque output by the wind turbine generator is controlled through steady-state operating condition control; if the output power of the wind turbine generator does not meet the dynamic operating conditions and does not meet the steady-state operating conditions, the current control method is used for control (that is, it is selected between steady-state operating condition control and dynamic operating condition control); the control quantity of steady-state operating condition control is obtained by PI control, and the increment of the proportional link in the PI control is determined according to the change in the actual speed of the generator, and the increment of the integral link is determined according to the deviation between the actual value of the generator speed and the target value.

[0048] The wind turbine is divided into dynamic working condition and steady-state working condition according to the change of output power of the wind turbine, and different control means are used to control it because of the different problems under different working conditions. Under dynamic working condition, the wind turbine has or is about to have large fluctuations. For dynamic working condition, PD control is used to obtain the control amount based on the change of speed deviation of the wind turbine and the change of speed acceleration at the same time to control the output torque of the wind turbine, so as to reduce the amplitude of power fluctuation of the wind turbine and try to stabilize it quickly, so as to ensure that the power fluctuation of the wind turbine is suppressed as much as possible in case of large power fluctuation of the wind turbine. Under steady-state working condition, PI control is used to control the output torque of the wind turbine based on the change of speed deviation of the wind turbine and the speed deviation of the wind turbine itself, so as to ensure that the speed deviation of the wind turbine is eliminated as much as possible in case of small power fluctuation of the wind turbine. Specifically, Figure 1 shown.

[0049] In this embodiment, the output of the integral link of the PI control determined according to the deviation between the actual value and the target value of the generator speed is:

[0050] y i =K i e(n)(K i ≠0)

[0051] Among them, y i The output value of the integral link, K i is the integral coefficient, and e(n) is the deviation between the actual value of the generator speed and the target value of the generator speed in the nth control cycle.

[0052] The control quantity of steady-state operating condition control obtained by PI control is:

[0053] y PI (n) = y PI (n-1)+K p [e(n)-e(n-1)]+K i e(n)

[0054] In the formula, y PI (n), y PI (n-1) are the control quantities of steady-state control in the nth and n-1th control cycles, respectively. K p is the proportionality coefficient, K i is the integral coefficient, T is the control period, e(n) and e(n-1) are the deviations between the actual value of the generator speed and the target value of the generator speed in the nth control period and the n-1th control period.

[0055] At this time, the control quantity of the steady-state working condition control is the torque control method under all working conditions used in the prior art.

[0056] In this embodiment, it is determined whether the working condition of the wind turbine generator satisfies the steady-state working condition or the dynamic working condition according to the change of the power output by the wind turbine generator.

[0057] The method of judging whether the working condition of the wind turbine generator meets the dynamic working condition according to the change of the power output of the wind turbine generator includes: if the absolute value of the slope of the power fitting curve satisfied by the output power of the wind turbine generator is greater than the set slope threshold, then it is judged that the working condition of the wind turbine generator meets the dynamic working condition; otherwise, it is judged that it does not meet the dynamic working condition.

[0058] Methods for judging whether the working condition of the wind turbine generator meets the steady-state working condition according to the change of the power output of the wind turbine generator include:

[0059] If the maximum power change within the set time period satisfied by the wind turbine output power is less than the set change threshold, it is determined that the working condition of the wind turbine meets the steady-state working condition; otherwise, it is determined that it does not meet the condition.

[0060] Specifically, the dynamic working condition is met in the following manner: the wind turbine output power satisfies that the absolute value of the slope of the power fitting curve is greater than a set slope threshold. In this embodiment, the slope threshold is set to 100 kW.

[0061] The slope of the power fitting curve is calculated as follows:

[0062] Assume y(n) is the n-second average of the generator output power, and use the following formula to calculate the power variation characteristic data P:

[0063]

[0064]

[0065] In the formula, k1 is the slope of the power fitting curve, and k2 is the second-order differential value of the power fitting curve.

[0066] The conditions for satisfying the steady-state operating condition include: the wind turbine output power satisfies that the maximum power change within a set time period is less than a set change threshold. In this embodiment, the wind turbine output power satisfies that the maximum power change within 20 seconds is less than 300kW, which is a steady-state operating condition.

[0067] The calculation method for the wind turbine output power to meet the maximum power change within 20 seconds is as follows:

[0068] h=y max -y min

[0069] y max=max[y(n),y(n-1),…y(n-19)]

[0070] y min =min[y(n),y(n-1),…y(n-19)]

[0071] Where h is the maximum power change of the wind turbine within 20 seconds, y max is the maximum power of the wind turbine within 20 seconds, y min It is the minimum power of the wind turbine within 20 seconds.

[0072] The present invention uses the above technical means to quickly stabilize the power and speed of the wind turbine generator in a short time. Compared with the prior art, it can suppress the fluctuation amplitude of the power and speed of the wind turbine generator in advance and avoid the subsequent long-term periodic fluctuation of the wind turbine generator power. The specific effects are as follows: Figure 2 shown.

[0073] Wind turbine peak shaving control device embodiment

[0074] The present invention also provides a wind turbine peak clipping control device, comprising a processor, the processor being used to execute a computer program to implement the steps of the wind turbine peak clipping control method. The specific process, principle and effect of the wind turbine peak clipping control device have been described in detail in the embodiment of the wind turbine peak clipping control method, and will not be repeated here.

[0075] Specific implementation methods are given above, but the present invention is not limited to the described implementation methods. The basic idea of ​​the present invention lies in the above basic scheme. For ordinary technicians in this field, it does not take creative work to design various deformed models, formulas, and parameters according to the teachings of the present invention. Changes, modifications, substitutions, and variations of the implementation methods without departing from the principles and spirit of the present invention still fall within the scope of protection of the present invention.

Claims

1. A wind turbine peak shaving control method, characterized in that: The method includes: If the output power of the wind turbine generator meets the dynamic operating conditions, the torque output by the wind turbine generator is controlled by dynamic operating condition control; the control quantity of the dynamic operating condition control is obtained by PD control, and the increment of the proportional link in the PD control is determined according to the change in the deviation between the actual value and the target value of the generator speed, and the increment of the differential link is determined according to the change in the generator rotation acceleration and the control period.

2. The wind turbine peak shaving control method according to claim 1, characterized in that: If the output power of the wind turbine generator meets the steady-state operating conditions but does not meet the dynamic operating conditions, the torque output by the wind turbine generator is controlled through steady-state operating condition control. If the output power of the wind turbine generator does not meet the dynamic operating conditions and does not meet the steady-state operating conditions, the current control method is used for control. The control quantity of the steady-state operating condition control is obtained by PI control. The increment of the proportional link in the PI control is determined according to the change in the actual speed of the generator, and the increment of the integral link is determined according to the deviation between the actual value of the generator speed and the target value.

3. The wind turbine peak shaving control method according to claim 1, characterized in that: The method of determining the differential link of the PD control according to the change of the generator rotation acceleration and the control period includes: determining the increment of the differential link of the PD control according to the ratio of the change of the generator rotation acceleration determined by the difference between the generator rotation acceleration limit values ​​of the current control period and the previous control period to the control period; the generator rotation acceleration limit value is obtained by the generator rotation acceleration through acceleration limit; The generator rotation acceleration is limited by the acceleration amplitude to obtain the generator rotation acceleration amplitude limit value, including: If the generator rotation acceleration is greater than the upper threshold of the normal fluctuation range, the generator rotation acceleration limit value is obtained from the upper threshold of the normal fluctuation range; if the generator rotation acceleration is less than the lower threshold of the normal fluctuation range, the generator rotation acceleration limit value is obtained from the lower threshold of the normal fluctuation range; otherwise, the generator rotation acceleration limit value is obtained from the current generator rotation acceleration.

4. The wind turbine peak shaving control method according to claim 3, characterized in that: The increment of the differential link of the PD control determined by the ratio of the change in the generator rotation acceleration determined by the difference between the generator rotation acceleration limit value of the current control cycle and the previous control cycle to the control cycle is: Among them, △y d is the incremental value of the differential link, K d is the differential coefficient, T is the control period, They are the generator rotation acceleration limit values ​​of the nth control cycle and the n-1th control cycle respectively.

5. The wind turbine peak shaving control method according to claim 4, characterized in that: The control quantity of dynamic working condition control obtained by PD control is: In the formula, y PD (n), y PD (n-1) are the control quantities of the dynamic working condition control in the nth and n-1th control cycles respectively, K p is the proportional coefficient, e(n) and e(n-1) are the deviations between the actual value of the generator speed and the target value of the generator speed in the nth control cycle and the n-1th control cycle.

6. The wind turbine peak shaving control method according to claim 3, characterized in that: The control quantity of steady-state operating condition control obtained by PI control is: y PI (n)=y PI (n-1)+K p [e(n)-e(n-1)]+K i e(n) In the formula, y PI (n), y PI (n-1) are the control quantities of steady-state control in the nth and n-1th control cycles, respectively. K p is the proportionality coefficient, K i is the integral coefficient, T is the control period, e(n) and e(n-1) are the deviations between the actual value of the generator speed and the target value of the generator speed in the nth control period and the n-1th control period.

7. The wind turbine peak shaving control method according to any one of claims 1 to 6, characterized in that: Whether the working condition of the wind turbine generator satisfies the steady-state working condition or the dynamic working condition is determined according to the change of the power output by the wind turbine generator.

8. The wind turbine peak shaving control method according to claim 7, characterized in that: The method of judging whether the working condition of the wind turbine generator meets the dynamic working condition according to the change of the power output of the wind turbine generator includes: if the absolute value of the slope of the power fitting curve satisfied by the output power of the wind turbine generator is greater than the set slope threshold, then it is judged that the working condition of the wind turbine generator meets the dynamic working condition; otherwise, it is judged that it does not meet the dynamic working condition.

9. The wind turbine peak shaving control method according to claim 7, characterized in that: Methods for judging whether the working condition of the wind turbine generator meets the steady-state working condition according to the change of the power output of the wind turbine generator include: If the maximum power change within the set time period satisfied by the wind turbine output power is less than the set change threshold, it is determined that the working condition of the wind turbine meets the steady-state working condition; otherwise, it is determined that it does not meet the condition.

10. A wind turbine peak shaving control device, comprising a processor, characterized in that: The processor is used to execute a computer program to implement the steps of the wind turbine peak shaving control method according to any one of claims 1 to 9.