Offshore wind turbine tower connecting structure, wind generating set and construction method
By adopting a combined structure of connection mechanism, prestressed cable and anchor bolt in offshore wind power, the problem that the connection between concrete tower and pipe pile structure is difficult to meet the complex wind conditions and high tower height at the sea, and the stable connection of the tower is achieved and the improvement of structural strength reduces construction difficulty and operating costs.
Patent Information
- Application Number
- CN202411050685.0
- Authority / Receiving Office
- CN · China
- Patent Type
- Applications(China)
- Current Assignee / Owner
- Filing Date
- 2024-08-01
- Publication Date
- 2024-11-15
- Estimated Expiration
- 2044-08-01
AI Technical Summary
The connection method of the existing concrete tower and pipe pile structure is difficult to meet the complex wind conditions at sea and the requirements of higher tower heights, resulting in safety and economic problems of prestressed concrete towers in offshore wind power applications.
Using a combined structure of connecting mechanism, prestressed cable and anchor bolt, the concrete tower is initially fixed through anchor bolts, and the prestressed cable is tensile to improve the structural strength and connection strength of the tower. Combined with the design of support components and flange, the connection is enhanced. Stability and force conduction.
Ensure a stable connection between concrete towers and connection mechanisms in harsh marine environments, reduce construction difficulty, improve the structural strength and connection strength of the tower, meet the application needs of higher tower heights, and enhance the safety and economicality of wind turbines .
Smart Images

Figure CN118959233A_ABST
Abstract
Description
Technical Field
[0001] The present invention relates to the technical field of wind power generation, and in particular to an offshore wind turbine tower connection structure, a wind turbine generator set and a construction method. Background Art
[0002] With the support of relevant policies, the construction of offshore wind power projects has maintained rapid development in the direction of large-scale and deep sea. At the same time, with the leapfrog increase in the capacity of wind turbines and the diameter of impellers, the height of wind turbine towers is also constantly being refreshed. More complex offshore working conditions have also put forward higher requirements for the safety of towers, but as the height of traditional steel towers continues to increase, their safety and economic issues have gradually become prominent.
[0003] As a solution for ultra-high towers in recent years, prestressed concrete towers have been tested in a large number of onshore wind power projects and have broad application prospects at sea. However, the existing connection method between concrete towers and pipe pile structures is still difficult to cope with complex offshore wind conditions and meet the requirements for higher tower heights, making it difficult to use prestressed concrete towers in offshore wind power. Summary of the invention
[0004] In view of this, the present invention provides an offshore wind turbine tower connection structure, a wind turbine generator set and a construction method to solve the problem that the existing connection method between concrete towers and pipe pile structures is difficult to cope with complex wind conditions at sea and meet higher tower height requirements.
[0005] In a first aspect, the present invention provides an offshore wind turbine tower connection structure for connecting a concrete tower and a pipe pile structure, characterized in that it comprises:
[0006] A connecting mechanism, used to connect the concrete tower and the pipe pile structure, one end of the connecting mechanism is connected to the concrete tower, and the other end is connected to the pipe pile structure;
[0007] A plurality of prestressed cables, one end of which is connected to the top of the concrete tower frame and the other end of which is anchored to the connecting mechanism, wherein the plurality of prestressed cables are arranged at intervals along the circumference of the concrete tower frame;
[0008] A plurality of anchor bolts have one end embedded in the concrete tower and the other end anchored to the connection mechanism, and a plurality of the anchor bolts are arranged between adjacent prestressed cables.
[0009] Beneficial effects: The offshore wind turbine tower connection structure utilizes a connection mechanism, a prestressed cable and an anchor bolt to connect the concrete tower and the pipe pile structure. The anchor bolt can be used to initially fix the concrete tower when the concrete tower is hoisted onto the connection mechanism, so that the concrete tower can maintain a stable connection with the connection mechanism in the harsh environment at sea, thereby enabling the prestressed cable tensioning construction to be carried out smoothly and safely. By connecting one end of the prestressed cable to the top of the concrete tower and anchoring the other end to the connection mechanism, the tensioned prestressed cable can change the stress state of the concrete tower and improve the structural strength of the concrete tower and the connection strength with the connection mechanism. By connecting the concrete tower and the pipe pile structure by means of a connection mechanism, a prestressed cable and an anchor bolt, not only can the structural strength of the concrete tower and the connection strength with the connection mechanism be improved by the prestressed cable, but also the connection strength of the concrete tower during the construction of the prestressed cable can be improved by the anchor bolt, which reduces the construction difficulty and is sufficient to meet the requirements of a higher tower height under the conditions of complex wind conditions at sea, so that the construction and use of the concrete tower at sea are guaranteed.
[0010] In an optional embodiment, the connecting mechanism includes a connecting flange and a supporting assembly, one end of the supporting assembly is sleeved on the circumference of the connecting flange, and the other end is supported on the pipe pile structure, one end of the connecting flange is connected to the concrete tower frame, one end of the prestressed cable close to the connecting mechanism is connected to an end of the connecting flange away from the concrete tower frame, and one end of the anchor bolt away from the concrete tower frame is connected to the connecting flange.
[0011] Beneficial effects: The connection mechanism connects one end of the support assembly to the connecting flange and supports the other end on the pipe pile structure, so that the connecting flange can remain stable and can effectively transmit force to the pipe pile structure. The connecting flange provides an anchoring end for the anchor bolts and prestressed cables, making the anchoring of the anchor bolts and prestressed cables more secure, thereby improving the gain in the structural strength of the concrete tower.
[0012] In an optional embodiment, the connecting flange includes a top flange, an anchoring flange, a rib plate and an anchoring plate, one end of the top flange is connected to the concrete tower, and the peripheral side of the top flange is connected to the support assembly, the top flange and the anchoring flange are coaxially arranged, the rib plates are spaced around the axis of the top flange, the anchoring plate is arranged between the top flange and the anchoring flange, the connecting flange is provided with a first channel and a second channel, the connecting flange is also provided with a first through hole and a second through hole, the first through hole is connected to the first channel, and the second through hole is connected to the second channel, one end of the prestressed cable is connected to the anchoring flange through the first through hole, and one end of the anchor bolt is connected to the anchoring plate through the second through hole.
[0013] Beneficial effects: The anchor flange is used for anchoring the prestressed cable, and the anchor plate is used for anchoring the anchor bolt. By setting the anchor plate, the engineering workload of anchoring the anchor bolt can be reduced. By setting the rib plate between the top flange and the anchor flange, the top flange and the anchor flange can be connected and supported, thereby greatly enhancing the structural strength of the connecting flange. By setting the first channel and the second channel on the connecting flange, the prestressed cable and the anchor bolt do not interfere with each other, and the positioning engineering workload of the prestressed cable and the anchor bolt is reduced, thereby enhancing the connection strength of the prestressed cable and the anchor bolt to the concrete tower.
[0014] In an optional embodiment, the side wall of the concrete tower is provided with a channel, the prestressed cable is inserted into the channel, the first channel or the second channel is formed between adjacent rib plates, the first channel and the second channel are staggered, the top flange and the anchor flange are both provided with the first through hole, the second through hole is provided in the top flange and the anchor plate, the anchor plate is provided in the second channel, one end of the prestressed cable is anchored to the anchor flange through the first through hole, and one end of the anchor bolt is anchored to the anchor plate through the second through hole.
[0015] Beneficial effect: By setting a hole in the concrete tower frame, the prestressed cable can be inserted into the hole, so that the prestressed cable is in the side wall of the concrete tower frame, and a first channel or a second channel is formed between the ribs, so that the prestressed cable in the side wall can be inserted into the first channel and connected to the anchor flange, and the anchor bolt passes through the second channel and is anchored to the anchor plate. The arrangement of the prestressed cable makes the prestressed cable and the concrete tower frame form a structural integration, which reduces the design difficulty of the construction plan and can also reduce the construction difficulty
[0016] In an optional embodiment, the connecting mechanism also includes a cylinder and a base plate, one end of the cylinder is arranged between the connecting flange and one end of the supporting assembly, the other end of the cylinder and the other end of the supporting assembly are connected to one side of the base plate, and the other side of the base plate is connected to the pipe pile structure.
[0017] Beneficial effect: The bottom plate can strengthen the connection strength and stability between the supporting components, the connecting flange and the pipe pile structure, and the cylinder can further provide support for the connecting flange.
[0018] In an optional embodiment, the prestressed cable is passed through the inner side of the concrete tower frame, the first channel is formed between adjacent rib plates, the second channel is formed between the outer wall of the cylinder and the inner side of the support assembly, the top flange and the anchor flange are both provided with the first through hole, the second through hole is provided in the top flange and the anchor plate, the anchor plate is provided in the second channel, one end of the prestressed cable is anchored to the anchor flange through the first through hole, and one end of the anchor bolt is anchored to the anchor plate through the second through hole.
[0019] Beneficial effect: Since the prestressed cable is passed through the inner side of the concrete tower frame, the setting position of the anchor bolt is farther away from the axis of the concrete tower frame than the prestressed cable. Therefore, the first channel for passing the prestressed cable is formed between the ribs, and the second channel for passing the anchor bolt is formed on the inner side of the cylinder and the support assembly, so that the second channel is farther away from the axis of the concrete tower frame than the first channel, and thus can correspond to the position of the anchor bolt. The above-mentioned setting method of the prestressed cable is easy to check, and the stress changes can be grasped regularly, which can effectively extend the life of the concrete tower frame and ensure the stable and safe connection of the concrete tower frame.
[0020] In an optional embodiment, the rib plate further includes an extension section, which extends toward the pipe pile structure and is connected to the inner side wall of the cylinder.
[0021] Beneficial effect: The extension section can further strengthen the connection strength between the cylinder and the connecting flange, and can strengthen the structural strength of the cylinder, thereby preventing the cylinder from deforming and causing the supporting force of the connecting flange to decrease, and ensuring that the connecting flange is firmly set.
[0022] In an optional embodiment, the support assembly includes an annular box girder and a support box girder, the annular box girder is arranged around the circumference of the connecting flange, one end of the support box girder is connected to the annular box girder, and the other end of the support box girder is connected to the base plate.
[0023] Beneficial effects: The annular box girder can exert supporting force on the peripheral sides of the top flange and the anchor flange, strengthen the supporting strength of the top flange and the anchor flange, avoid deformation of the top flange and the anchor flange, and the supporting box girder can support the annular box girder to ensure the stability of the annular box girder and the connecting flange.
[0024] In a second aspect, the present invention further provides a wind turbine generator set, comprising the concrete tower, the pipe pile structure and the above-mentioned offshore wind turbine tower connection structure, wherein the concrete tower and the pipe pile structure are connected via the offshore wind turbine tower connection structure.
[0025] Beneficial effects: The wind turbine generator set connects the concrete tower and the pipe pile structure through the offshore wind turbine tower connection structure, which can strengthen the connection strength between the concrete tower and the pipe pile structure, enable the wind turbine generator set to adapt to complex wind conditions at sea and higher tower height requirements, and reduce the construction difficulty during the construction of the wind turbine generator set.
[0026] In a third aspect, the present invention further provides a wind turbine generator construction method for constructing the above-mentioned wind turbine generator, comprising:
[0027] Install pipe pile structure and connection mechanism;
[0028] Hoisting the first section of the concrete tower frame to connect the first section of the concrete tower frame with the connecting mechanism;
[0029] Anchor the anchor bolts to the connection mechanism, tighten the anchor bolts and perform tension pre-tightening;
[0030] Hoist other sections of concrete tower until the hoisting is completed;
[0031] One end of the prestressed cable is lifted to the top of the concrete tower and connected, and the other end of the prestressed cable is anchored to the connecting mechanism to tension the prestressed cable.
[0032] Beneficial effects: When hoisting the first section of the concrete tower, the wind turbine construction method anchors it with the connecting mechanism through anchor bolts, so that the first section of the concrete tower can be stably set on the connecting mechanism, thereby ensuring that when hoisting other sections of the concrete tower, the first section of the concrete tower can remain stable, ensuring construction safety and reducing construction difficulty. After the concrete tower is completely hoisted, prestress is applied to the concrete tower by tensioning the prestressed cables, so that the structural strength of the concrete tower and the connection strength between the concrete tower and the connecting mechanism are effectively improved. BRIEF DESCRIPTION OF THE DRAWINGS
[0033] In order to more clearly illustrate the specific implementation methods of the present invention or the technical solutions in the prior art, the drawings required for use in the specific implementation methods or the description of the prior art will be briefly introduced below. Obviously, the drawings described below are some implementation methods of the present invention. For ordinary technicians in this field, other drawings can be obtained based on these drawings without paying creative work.
[0034] Figure 1 A schematic structural diagram of a wind turbine generator set according to an embodiment of the present invention;
[0035] Figure 2 A schematic diagram of a connection between a pipe pile structure and an offshore wind turbine tower connection structure according to an embodiment of the present invention;
[0036] Figure 3This is a schematic structural diagram of an offshore wind turbine tower connection structure according to an embodiment of the present invention;
[0037] Figure 4 A schematic diagram of a partial structure of a concrete tower according to an embodiment of the present invention;
[0038] Figure 5 A schematic diagram of a connection structure between a concrete tower and an offshore wind turbine tower according to an embodiment of the present invention;
[0039] Figure 6 The present invention is a schematic diagram of another connection structure between a concrete tower and an offshore wind turbine tower according to an embodiment of the present invention.
[0040] Description of reference numerals:
[0041] 100, concrete tower; 101, channel; 200, pipe pile structure; 300, wind turbine host; 400, steel tower;
[0042] 1. Connecting mechanism; 11. Connecting flange; 111. Top flange; 112. Anchor flange; 113. Rib plate; 1131. Extension section; 114. Anchor plate; 115. First passage; 116. Second passage; 117. First through hole; 118. Second through hole; 12. Support assembly; 121. Annular box beam; 122. Support box beam; 13. Cylinder; 131. Door opening; 14. Bottom plate;
[0043] 2. Prestressed cables;
[0044] 3. Anchor bolt. DETAILED DESCRIPTION
[0045] In order to make the purpose, technical solution and advantages of the embodiments of the present invention clearer, the technical solution in the embodiments of the present invention will be clearly and completely described below in conjunction with the drawings in the embodiments of the present invention. Obviously, the described embodiments are part of the embodiments of the present invention, not all of the embodiments. Based on the embodiments of the present invention, all other embodiments obtained by those skilled in the art without creative work are within the scope of protection of the present invention.
[0046] Combine the following Figures 1 to 6 , describing an embodiment of the present invention.
[0047] According to an embodiment of the present invention, on the one hand, there is provided an offshore wind turbine tower connection structure for connecting a concrete tower 100 and a pipe pile structure 200, comprising a connection mechanism 1, a plurality of prestressed cables 2 and a plurality of anchor bolts 3. The connection mechanism 1 is used to connect the concrete tower 100 and the pipe pile structure 200, one end of the connection mechanism 1 is connected to the concrete tower 100, and the other end is connected to the pipe pile structure 200; one end of the prestressed cable 2 is connected to the top of the concrete tower 100, and the other end is anchored to the connection mechanism 1, and a plurality of prestressed cables 2 are arranged at intervals along the circumference of the concrete tower 100; one end of the anchor bolt 3 is pre-buried in the concrete tower 100, and the other end is anchored to the connection mechanism 1, and a plurality of anchor bolts 3 are arranged between adjacent prestressed cables 2.
[0048] The offshore wind turbine tower connection structure provided in this embodiment utilizes a connection mechanism 1, a prestressed cable 2 and an anchor bolt 3 to connect a concrete tower 100 and a pipe pile structure 200. When the concrete tower 100 is hoisted onto the connection mechanism 1, the anchor bolt 3 can be used to preliminarily fix the concrete tower 100, so that the concrete tower 100 can maintain a stable connection with the connection mechanism 1 in the harsh environment at sea, thereby enabling the prestressed cable 2 to be tensioned smoothly and safely. By connecting one end of the prestressed cable 2 to the top of the concrete tower 100 and anchoring the other end to the connection mechanism 1, the tensioned prestressed cable 2 can change the stress state of the concrete tower 100, thereby improving the structural strength of the concrete tower 100 and the connection strength with the connection mechanism 1. The concrete tower 100 and the pipe pile structure 200 are connected by means of a connecting mechanism 1, a prestressed cable 2 and an anchor bolt 3. Not only can the structural strength of the concrete tower 100 and the connection strength with the connecting mechanism 1 be improved by the prestressed cable 2, but the connection strength of the concrete tower 100 during the construction of the prestressed cable 2 can also be improved by the anchor bolt 3, thereby reducing the construction difficulty and being sufficient to meet the requirements of a higher tower height under complex wind conditions at sea, thereby ensuring the construction and use of the concrete tower 100 at sea.
[0049] Specifically, the concrete tower 100 is made of concrete, and prestress can be applied thereto to increase the structural strength of the concrete tower 100, thereby improving the safety of the concrete tower 100 when used at sea, and can also reduce the manufacturing cost of the wind turbine generator set and improve economic efficiency. Since the pipe pile structure 200 does not have sufficient space for tensioning the prestressed cable 2, the concrete tower 100 and the pipe pile structure 200 are connected by a connecting mechanism 1, which provides a platform for the construction of the prestressed cable 2 and improves the connection strength between the concrete tower 100 and the pipe pile structure 200.
[0050] Specifically, the connection mechanism 1 includes a connection flange 11 and a support assembly 12, one end of the support assembly 12 is sleeved on the peripheral side of the connection flange 11, and the other end is supported on the pipe pile structure 200, one end of the connection flange 11 is connected to the concrete tower 100, one end of the prestressed cable 2 close to the connection mechanism 1 is connected to the end of the connection flange 11 away from the concrete tower 100, and one end of the anchor bolt 3 away from the concrete tower 100 is connected to the connection flange 11. The connection mechanism 1 enables the connection flange 11 to remain stable and effectively transmit force to the pipe pile structure 200 by connecting one end of the support assembly 12 to the connection flange 11 and supporting the other end on the pipe pile structure 200, while the connection flange 11 provides an anchoring end for the anchor bolt 3 and the prestressed cable 2, so that the anchoring of the anchor bolt 3 and the prestressed cable 2 is more firmly, and the gain of the structural strength of the concrete tower 100 is improved.
[0051] Specifically, the connecting flange 11 includes a top flange 111, an anchoring flange 112, a rib plate 113 and an anchoring plate 114. One end of the top flange 111 is connected to the concrete tower 100, and the peripheral side of the top flange 111 is connected to the support assembly 12. The top flange 111 and the anchoring flange 112 are coaxially arranged, the rib plates 113 are spaced around the axis of the top flange 111, and the anchoring plate 114 is arranged between the top flange 111 and the anchoring flange 112. The connecting flange 11 is provided with a first channel 115 and a second channel 116. The connecting flange 11 is also provided with a first through hole 117 and a second through hole 118. The first through hole 117 is communicated with the first channel 115, and the second through hole 118 is communicated with the second channel 116. One end of the prestressed cable 2 is connected to the anchoring flange 112 through the first through hole 117, and one end of the anchor bolt 3 is connected to the anchoring plate 114 through the second through hole 118. The anchor flange 112 is used for anchoring the prestressed cable 2, and the anchor plate 114 is used for anchoring the anchor bolt 3. By setting the anchor plate 114, the engineering workload for anchoring the anchor bolt 3 can be reduced. By setting the rib plate 113 between the top flange 111 and the anchor flange 112, the top flange 111 and the anchor flange 112 can be connected and supported, thereby greatly enhancing the structural strength of the connecting flange 11. By setting the first channel 115 and the second channel 116 on the connecting flange 11, the prestressed cable 2 and the anchor bolt 3 do not interfere with each other, and the positioning engineering workload of the prestressed cable 2 and the anchor bolt 3 is reduced, thereby enhancing the connection strength of the prestressed cable 2 and the anchor bolt 3 to the concrete tower 100.
[0052] Specifically, the axis of the first through hole 117 is parallel to the extension direction of the first channel 115, and the axis of the second through hole 118 is parallel to the extension direction of the second channel 116, thereby avoiding friction or interference between the prestressed cable 2 and / or the anchor bolt 3 and the connecting flange 11, thereby extending the service life of the prestressed cable 2 and the anchor bolt 3.
[0053] There is no restriction on the number of prestressed cables 2, anchor bolts 3 and ribs 113. The number of prestressed cables 2, anchor bolts 3 and ribs 113 should be set according to the design requirements of the concrete tower 100 to ensure that the structural strength of the concrete tower 100 meets the design requirements.
[0054] In this embodiment, every two anchor bolts 3 form an anchor bolt group 3. When viewed along the circumference of the concrete tower 100, the prestressed cables 2 and the anchor bolt groups 3 are staggered, so that the anchor bolts 3 do not affect the arrangement of the prestressed cables 2 after being anchored.
[0055] In one embodiment, Figure 5 As shown, a channel 101 is provided on the side wall of the concrete tower 100, and the prestressed cable 2 is inserted into the channel 101. A first channel 115 or a second channel 116 is formed between adjacent ribs 113. The first channel 115 and the second channel 116 are alternately arranged. The top flange 111 and the anchor flange 112 are both provided with a first through hole 117. The second through hole 118 is provided on the top flange 111 and the anchor plate 114. The anchor plate 114 is provided in the second channel 116. One end of the prestressed cable 2 is anchored to the anchor flange 112 through the first through hole 117, and one end of the anchor bolt 3 is anchored to the anchor plate 114 through the second through hole 118. By setting the hole 101 in the concrete tower 100, the prestressed cable 2 can be inserted into the hole 101, so that the prestressed cable 2 is located in the side wall of the concrete tower 100, and the first channel 115 or the second channel 116 is formed between the ribs 113, so that the prestressed cable 2 in the side wall can be inserted into the first channel 115 and connected to the anchor flange 112, and the anchor bolt 3 passes through the second channel 116 and is anchored to the anchor plate 114. The arrangement of the prestressed cable 2 enables the prestressed cable 2 and the concrete tower 100 to form a structural integration, which reduces the design difficulty of the construction plan and can also reduce the construction difficulty.
[0056] Specifically, the connection mechanism 1 further includes a cylinder 13 and a bottom plate 14, one end of the cylinder 13 is disposed between the connection flange 11 and one end of the support assembly 12, the other end of the cylinder 13 and the other end of the support assembly 12 are both connected to one side of the bottom plate 14, and the other side of the bottom plate 14 is connected to the pipe pile structure 200. The bottom plate 14 can enhance the connection strength and connection stability between the support assembly 12, the connection flange 11 and the pipe pile structure 200, and the cylinder 13 can further provide support force for the connection flange 11.
[0057] Furthermore, the cylinder 13 is provided with a door opening 131, and a climbing device is provided inside the cylinder 13. The door opening 131 allows construction personnel to enter and exit the cylinder 13 to perform construction or maintenance on the connection mechanism 1, and the climbing device can facilitate the construction personnel to perform maintenance and other operations on the anchor points of the prestressed cable 2 and the anchor flange 112 and the anchor points of the anchor bolt 3 and the anchor plate 114, which is convenient for future maintenance. The connection mechanism 1 forms a hollow structure through the above-mentioned setting, which further facilitates the operation of personnel and tools during prestressed construction, and effectively reduces the difficulty of prestressed construction.
[0058] In another embodiment, Figure 6 As shown, the prestressed cable 2 is passed through the inner side of the concrete tower 100, a first channel 115 is formed between adjacent ribs 113, a second channel 116 is formed between the outer wall of the cylinder 13 and the inner side of the support assembly 12, the top flange 111 and the anchor flange 112 are both provided with a first through hole 117, a second through hole 118 is provided on the top flange 111 and the anchor plates 114 114, the anchor plate 114 is provided in the second channel 116, one end of the prestressed cable 2 is anchored to the anchor flange 112 through the first through hole 117, and one end of the anchor bolt 3 is anchored to the anchor plate 114 through the second through hole 118. Since the prestressed cable 2 is passed through the inner side of the concrete tower 100, the setting position of the anchor bolt 3 is farther away from the axis of the concrete tower 100 than the prestressed cable 2. Therefore, the first channel 115 for passing the prestressed cable 2 is formed between the ribs 113, and the second channel 116 for passing the anchor bolt 3 is formed on the inner side of the cylinder 13 and the support assembly 12, so that the second channel 116 is farther away from the axis of the concrete tower 100 than the first channel 115, and thus can correspond to the position of the anchor bolt 3. The above-mentioned setting method of the prestressed cable 2 is convenient for inspection, and stress changes can be regularly grasped, which can effectively extend the service life of the concrete tower 100 and ensure the stable and safe connection of the concrete tower 100.
[0059] Furthermore, in the embodiment where the prestressed cable 2 is passed through the inner side of the concrete tower 100, the circumferential side of the top flange 111 extends to fully support the concrete tower 100, thereby preventing the bottom area of the concrete tower 100 from being larger than the area of the top flange 111, thereby effectively supporting the concrete tower 100.
[0060] Specifically, the cylinder 13 is welded to the top flange 111 , the anchor flange 112 , the ribs 113 and the anchor plates 114 , and the connection is firm and stable, thereby enhancing the structural strength in offshore application scenarios.
[0061] Furthermore, the rib plate 113 further includes an extension section 1131, which extends toward the pipe pile structure 200 and is connected to the inner wall of the cylinder 13. The extension section 1131 can further strengthen the connection strength between the cylinder 13 and the connecting flange 11, and can strengthen the structural strength of the cylinder 13, thereby preventing the cylinder 13 from deforming and causing the supporting force of the connecting flange 11 to decrease, and ensuring that the connecting flange 11 is arranged firmly.
[0062] Furthermore, the support assembly 12 includes an annular box beam 121 and a support box beam 122. The annular box beam 121 is disposed around the peripheral side of the connecting flange 11. One end of the support box beam 122 is connected to the annular box beam 121, and the other end of the support box beam 122 is connected to the bottom plate 14. The annular box beam 121 can exert a supporting force on the peripheral side of the top flange 111 and the anchoring flange 112, strengthen the supporting strength of the top flange 111 and the anchoring flange 112, and avoid deformation of the top flange 111 and the anchoring flange 112. The support box beam 122 can support the annular box beam 121 to ensure the stability of the annular box beam 121 and the connecting flange 11.
[0063] In this embodiment, four supporting box beams 122 are provided, and four supporting points are formed at the top of the pipe pile structure 200. One end of the supporting box beam 122 is evenly spaced around the annular box beam 121, and the other end is respectively provided at the positions where the four supporting points are projected onto the bottom plate 14, so that the weight of the concrete tower 100 can be directly transferred to the pipe pile structure 200 through the supporting box beam 122.
[0064] According to an embodiment of the present invention, on the other hand, a wind turbine generator set is provided, including a concrete tower 100, a pipe pile structure 200 and the above-mentioned offshore wind turbine tower connection structure, wherein the concrete tower 100 and the pipe pile structure 200 are connected via the offshore wind turbine tower connection structure.
[0065] The wind turbine generator set provided in this embodiment connects the concrete tower 100 and the pipe pile structure 200 through the offshore wind turbine tower connection structure, which can strengthen the connection strength between the concrete tower 100 and the pipe pile structure 200, so that the wind turbine generator set can adapt to complex wind conditions at sea and higher tower height requirements and can reduce the construction difficulty during the construction of the wind turbine generator set.
[0066] Furthermore, the wind turbine generator set further includes a wind turbine main unit 300 and a steel tower 400 , and the wind turbine main unit 300 is connected to the concrete tower 100 via the steel tower 400 .
[0067] According to an embodiment of the present invention, on the other hand, a wind turbine generator set construction method is provided, which is used to construct the above-mentioned wind turbine generator set, comprising:
[0068] Install the pipe pile structure 200 and the connecting mechanism 1;
[0069] Hoisting the first section of the concrete tower 100, so that the first section of the concrete tower 100 is connected to the connecting mechanism 1;
[0070] Anchor the anchor bolt 3 to the connection mechanism 1, tighten the anchor bolt 3 and perform tension pre-tightening;
[0071] Hoisting other sections of concrete tower 100 until the hoisting is completed;
[0072] One end of the prestressed cable 2 is lifted to the top of the concrete tower 100 and connected, and the other end of the prestressed cable 2 is anchored to the connecting mechanism 1 to tension the prestressed cable 2 .
[0073] The wind turbine generator construction method provided in the present embodiment anchors the first section of the concrete tower 100 to the connecting mechanism 1 through the anchor bolts 3 when hoisting the first section of the concrete tower 100, so that the first section of the concrete tower 100 can be stably arranged on the connecting mechanism 1, thereby ensuring that when hoisting other sections of the concrete tower 100, the first section of the concrete tower 100 can remain stable, ensuring construction safety and reducing construction difficulty. After the concrete tower 100 is completely hoisted, prestress is applied to the concrete tower 100 by tensioning the prestressed cables 2, so that the structural strength of the concrete tower 100 and the connection strength between the concrete tower 100 and the connecting mechanism 1 are effectively improved.
[0074] Specifically, after the pipe pile structure 200 and the connecting mechanism 1 are connected to form a whole on land, they are floated to the machine site at sea and then sunk and fixed. It is simpler and more convenient to connect the pipe pile structure 200 and the connecting mechanism 1 on land, and transporting the connected pipe pile structure 200 and the connecting structure at sea also reduces the difficulty of transportation.
[0075] The specific connection method between the pipe pile structure 200 and the connection mechanism 1 is not limited here. In this embodiment, the pipe pile structure 200 and the connection mechanism 1 are connected by welding, and the connection is firm and reliable.
[0076] Specifically, hoisting the first section of the concrete tower 100 and connecting the first section of the concrete tower 100 with the connecting mechanism 1 includes: after connecting the concrete tower barrel with the top flange 111, applying sealing structural adhesive on the joint surface between the top flange 111 and the first section of the concrete tower 100, thereby filling the small gap caused by the precision error of the joint surface and playing a sealing role.
[0077] In the embodiment where the prestressed cable 2 is arranged on the inner side of the side wall of the concrete tower 100, after completing the anchoring and anti-corrosion operations of the anchor bolt 3, the annular box girder 121 needs to be sealed to prevent the anchor bolt 3 from being directly exposed to the marine environment, thereby extending the service life of the anchor bolt 3.
[0078] Specifically, anchoring the anchor bolt 3 to the connection mechanism 1, and tightening the anchor bolt 3 and performing tension pre-tightening include:
[0079] Install the anchor bolt 3 in the conventional manner, tighten and pre-tension it, mark the anchor bolt 3 with an anti-loosening marking line with a striking color, and after acceptance, clean the dirt and debris on the bolt surface of the anchor bolt 3, and then apply a wax film rust inhibitor with a wool brush or other brushing tool for anti-corrosion treatment to extend the service life.
[0080] Specifically, one end of the prestressed cable 2 is lifted to the top of the concrete tower 100 and connected, and the other end of the prestressed cable 2 is anchored to the connecting mechanism 1. The prestressed cable 2 is tensioned including: after all sections of the concrete tower 100 are hoisted, the prestressed cable 2 is lifted and tensioned.
[0081] After the prestressed cable 2 is made on land, the whole roll of prestressed cable 2 is transported into the cylinder 13 for hoisting and tensioning. The prestressed cable 2 tooling is hoisted to the top surface of the concrete tower 100, and the prestressed cable 2 is lifted using the winch and rope on the tooling.
[0082] After the prestressed cable 2 is lifted, the prestressed cable 2 is tensioned. The upper end of the prestressed cable 2 is anchored to the upper end of the concrete tower 100 , and the lower end is anchored to the anchor flange 112 . The hydraulic tensioning and anti-corrosion operation of the prestressed cable 2 is completed in the cylinder 13 .
[0083] Further, one end of the prestressed cable 2 is lifted to the top of the concrete tower 100 and connected, and the other end of the prestressed cable 2 is anchored to the connecting mechanism 1. After the prestressed cable 2 is tensioned, the following steps are further included:
[0084] The steel tower frame 400 is hoisted on the upper end of the concrete tower frame 100. When the steel tower frame 400 is hoisted completely, the wind turbine main unit 300 is hoisted to complete the entire construction of the wind turbine generator set.
[0085] Although the embodiments of the present invention have been described in conjunction with the accompanying drawings, those skilled in the art may make various modifications and variations without departing from the spirit and scope of the present invention, and such modifications and variations are all within the scope defined by the appended claims.
Claims
1. An offshore wind turbine tower connection structure, used to connect a concrete tower (100) and a pipe pile structure (200), characterized in that: include: A connecting mechanism (1) is used to connect the concrete tower (100) and the pipe pile structure (200), one end of the connecting mechanism (1) being connected to the concrete tower (100) and the other end being connected to the pipe pile structure (200); A plurality of prestressed cables (2), one end of which is connected to the top of the concrete tower (100) and the other end of which is anchored to the connection mechanism (1), and the plurality of prestressed cables (2) are arranged at intervals along the circumference of the concrete tower (100); A plurality of anchor bolts (3) have one end embedded in the concrete tower (100) and the other end anchored to the connection mechanism (1), and a plurality of the anchor bolts (3) are arranged between adjacent prestressed cables (2).
2. The offshore wind turbine tower connection structure according to claim 1, characterized in that: The connection mechanism (1) comprises a connection flange (11) and a support assembly (12); one end of the support assembly (12) is sleeved on the peripheral side of the connection flange (11), and the other end is supported on the pipe pile structure (200); one end of the connection flange (11) is connected to the concrete tower (100); one end of the prestressed cable (2) close to the connection mechanism (1) is connected to one end of the connection flange (11) away from the concrete tower (100); and one end of the anchor bolt (3) away from the concrete tower (100) is connected to the connection flange (11).
3. The offshore wind turbine tower connection structure according to claim 2, characterized in that: The connecting flange (11) comprises a top flange (111), an anchor flange (112), a rib plate (113) and an anchor plate (114); one end of the top flange (111) is connected to the concrete tower (100), and the circumferential side of the top flange (111) is connected to the support assembly (12); the top flange (111) and the anchor flange (112) are coaxially arranged; the rib plates (113) are spaced around the axis of the top flange (111); and the anchor plate (114) is arranged between the top flange (111) and the anchor flange (112). The connecting flange (11) is provided with a first channel (115) and a second channel (116), and the connecting flange (11) is also provided with a first through hole (117) and a second through hole (118), the first through hole (117) is connected to the first channel (115), and the second through hole (118) is connected to the second channel (116), one end of the prestressed cable (2) is connected to the anchor flange (112) through the first through hole (117), and one end of the anchor bolt (3) is connected to the anchor plate (114) through the second through hole (118).
4. The offshore wind turbine tower connection structure according to claim 3, characterized in that: The side wall of the concrete tower (100) is provided with a hole (101), the prestressed cable (2) is inserted into the hole (101), the first channel (115) or the second channel (116) is formed between adjacent ribs (113), the first channel (115) and the second channel (116) are arranged alternately, the top flange (111) and the anchor flange (112) are both provided with the first through hole (117), the second through hole (118) is provided on the top flange (111) and the anchor plate (114), the anchor plate (114) is provided on the second channel (116), one end of the prestressed cable (2) is anchored to the anchor flange (112) through the first through hole (117), and one end of the anchor bolt (3) is anchored to the anchor plate (114) through the second through hole (118).
5. The offshore wind turbine tower connection structure according to claim 3, characterized in that: The connecting mechanism (1) further comprises a cylinder (13) and a base plate (14); one end of the cylinder (13) is arranged between the connecting flange (11) and one end of the supporting assembly (12); the other end of the cylinder (13) and the other end of the supporting assembly (12) are both connected to one side of the base plate (14); and the other side of the base plate (14) is connected to the pipe pile structure (200).
6. The offshore wind turbine tower connection structure according to claim 5, characterized in that: The prestressed cable (2) is passed through the inner side of the concrete tower (100), the first channel (115) is formed between adjacent ribs (113), the second channel (116) is formed between the outer wall of the cylinder (13) and the inner side of the support assembly (12), the top flange (111) and the anchor flange (112) are both provided with the first through hole (117), the second through hole (118) is provided on the top flange (111) and the anchor plate (114), the anchor plate (114) is provided on the second channel (116), one end of the prestressed cable (2) is anchored to the anchor flange (112) through the first through hole (117), and one end of the anchor bolt (3) is anchored to the anchor plate (114) through the second through hole (118).
7. The offshore wind turbine tower connection structure according to claim 5, characterized in that: The rib plate (113) further comprises an extension section (1131), wherein the extension section (1131) extends toward the pipe pile structure (200) and is connected to the inner side wall of the cylinder (13).
8. The offshore wind turbine tower connection structure according to claim 5, characterized in that: The support assembly (12) comprises an annular box beam (121) and a support box beam (122); the annular box beam (121) is arranged around the peripheral side of the connecting flange (11); one end of the support box beam (122) is connected to the annular box beam (121); and the other end of the support box beam (122) is connected to the bottom plate (14).
9. A wind turbine generator set, comprising the concrete tower (100), the pipe pile structure (200) and the offshore wind turbine tower connection structure according to any one of claims 1 to 8, characterized in that: The concrete tower (100) and the pipe pile structure (200) are connected via the offshore wind turbine tower connection structure.
10. A method for constructing a wind turbine generator set, used for constructing the wind turbine generator set according to claim 9, characterized in that: include: Installing the pipe pile structure (200) and the connecting mechanism (1); Hoisting the first section of the concrete tower (100) so that the first section of the concrete tower (100) is connected to the connection mechanism (1); Anchoring the anchor bolt (3) to the connection mechanism (1), tightening the anchor bolt (3) and performing tension pre-tightening; Hoisting other sections of the concrete tower (100) until the hoisting is completed; One end of the prestressed cable (2) is lifted to the top of the concrete tower (100) and connected, and the other end of the prestressed cable (2) is anchored to the connection mechanism (1), and the prestressed cable (2) is tensioned.
Citation Information
Patent Citations
Fan base with pressure dispersed type arrangement high-strength pre-stressed anchor rods (cables)
CN104110039A
Mixing tower drum connecting structure
CN107859600A
Prefabricated prestress plate type wind power generation tower base
CN108755736A
Wind turbine generator system, tower and infrastructure thereof
CN109681390A
VB language-based wind power steel-concrete tower design tool and parameterized three-dimensional design method
CN113408025A
Cited By
Concrete tower drum connecting device and fan supporting structure
CN119288772A
Concrete tower connection device and wind turbine support structure
CN119288772B