Method for testing stability of circular underground diaphragm wall structure model

By applying uniform confining pressure in the circular underground continuous wall structure model, using steel strand hydraulic jack and force gauge to measure strain gauge data, the problem of lack of complex scene experiments in circular foundation pit research is solved, and the problem of achieving the goal of achieving The safety and economic cost of circular underground continuous wall structure are optimized.

CN118961439APending Publication Date: 2024-11-15SOUTH CHINA AGRICULTURAL UNIVERSITY
View PDF 0 Cites 0 Cited by

Patent Information

Application Number
CN202411260930.0
Authority / Receiving Office
CN · China
Patent Type
Applications(China)
Current Assignee / Owner
Filing Date
2024-09-10
Publication Date
2024-11-15

AI Technical Summary

Technical Problem

The prior art lacks comprehensiveness in the research of circular foundation pits, especially indoor model experiments in complex scenarios are rare, making it difficult to ensure safety and economic cost optimization of circular underground continuous wall structures.

Method used

A stability test method for circular underground continuous wall structure model is adopted, by welding circular steel ring beams, laying uniform confining loading device, installing strain gauge and displacement meter, and applying pressure using a steel strand hydraulic jack to simulate uniform soil Pressure, obtain the stress and deformation characteristics data of the structural model.

Benefits of technology

It provides a scientific experimental basis to ensure the construction and operation safety of circular underground continuous walls, improves the reliability of design and construction efficiency, and is suitable for the experiments of most circular underground continuous wall structure models.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN118961439A_ABST
    Figure CN118961439A_ABST
Patent Text Reader

Abstract

The invention discloses a stability testing method of a circular underground diaphragm wall structure model, and relates to the technical field of indoor simulation methods of circular underground diaphragm wall structures. Comprising the following steps: A, welding a circular steel ring beam on the inner side of a structure model; b, the structural model is horizontally placed on the ground, a hoop steel strand penetrates through an anchoring plate to be anchored, the other end of the hoop steel strand is fixed to a steel strand hydraulic jack after winding the structural model by a circle, and a dynamometer is connected to the hoop steel strand in series; c, a strain gauge is attached to the structural model, and a displacement meter is installed on the structural model; d, the steel strand hydraulic jack pulls the hoop steel strand to apply pressure to the structure model, and data of the strain gauges and the displacement meter are obtained and sent to a computer to be processed. According to the invention, the simulation of the wall front and back side soil pressure borne by the circular underground diaphragm wall structure model is realized, a test basis is provided for researching the stress and deformation characteristics of the circular underground diaphragm wall under the condition of uniform confining pressure, and the construction and operation safety of the circular underground diaphragm wall is ensured.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The invention relates to the technical field of indoor simulation methods for circular underground continuous wall structures, and in particular to a stability testing method for a circular underground continuous wall structure model. Background Art

[0002] LNG, or liquefied natural gas, is a clean energy with a wide range of uses. It not only has energy properties, but is also a very important chemical raw material with broad development prospects. The International Energy Agency (IEA) predicts that in the global energy structure from 2030 to 2035, LNG will replace coal as the world's second largest energy source, and the global demand for LNG will continue to grow. It is expected that by 2026, my country's LNG supply will increase by about 40% compared with 2022.

[0003] my country is a major producer of liquefied natural gas, but it is also the largest consumer of liquefied natural gas. Domestic liquefied natural gas production is far from meeting domestic consumption needs, so my country still needs to import a large amount of liquefied natural gas every year. As an important structure for liquefied natural gas storage, the number of LNG storage tanks built is increasing year by year, and my country's LNG storage tanks are basically above-ground tanks. The safety of above-ground LNG storage tanks is easily affected by human factors, and there are fewer and fewer sites with high-quality geological conditions along the coast and rivers, so the demand for the construction of LNG underground storage tanks is increasing. Compared with above-ground tanks, the advantages of LNG underground tanks are mainly: 1) saving land space, solving the problem of difficult site selection and limited scale of roadbed LNG receiving stations; 2) having stronger explosion-proof, impact-resistant and earthquake-resistant performance, which can reduce the impact on the surrounding environment and improve the safety of storage tanks.

[0004] At present, China has fully mastered the full set of technologies for LNG ground tanks, but for underground tanks, relevant units have only conducted preliminary research. The current research on circular foundation pits is mainly based on the analysis of actual engineering data, and the research on special or complex engineering situations is not comprehensive enough; in addition, indoor model experiments on circular foundation pits are relatively rare. In order to more comprehensively understand the stress and deformation characteristics of the circular foundation pit structure system in specific and complex scenarios, and optimize the design of the circular ground-connected wall structure, it is necessary to carry out indoor model experiments on circular foundation pits for specific and complex scenarios. This model test can help researchers clarify the stress and deformation laws of the circular foundation pit retaining structure, and play an important guiding role in strengthening relevant theoretical research, making full use of the advantages of underground storage tanks, designing more reasonable structural forms, and optimizing construction processes, thereby improving the safety of circular foundation pits for LNG underground storage tanks while reducing economic costs.

[0005] Based on the above problems existing in the prior art, there is a need for a stability testing method for a circular underground continuous wall structure model. Summary of the invention

[0006] The main purpose of the present invention is to provide a stability testing method for a circular underground continuous wall structure model, which realizes the simulation of the soil pressure on the front and rear sides of the circular underground continuous wall structure model, provides a scientific experimental basis for studying the stress and deformation characteristics of the circular underground continuous wall under uniform confining pressure, ensures the construction and operation safety of the circular underground continuous wall, and solves the problems existing in the prior art.

[0007] In order to solve the above technical problems, the present invention adopts the following technical solutions:

[0008] A method for testing the stability of a circular underground continuous wall structure model comprises the following steps:

[0009] A. Welding circular steel ring beams: Place the structural model of the circular underground continuous wall horizontally on the ground, and weld multiple circular steel ring beams inside the structural model of the circular underground continuous wall;

[0010] B. Arrange uniform confining pressure loading device: Place the structural model of the circular underground continuous wall horizontally on the ground, pass one end of multiple hoop steel strands through the anchor plate and anchor them with steel strand anchors, and fix the other end on the steel strand hydraulic jack after wrapping around the outer surface of the structural model. Connect a dynamometer in series on the hoop steel strands;

[0011] C. Arrangement of the test instruments: multiple strain gauges are placed on the inner and outer surfaces of the structural model of the circular underground continuous wall, and multiple displacement meters are installed on the outer surface of the structural model of the circular underground continuous wall;

[0012] D. Pressure loading: Apply pressure to the structural model by tightening the hoop steel strands with the steel strand hydraulic jack, obtain the data of the strain gauge and displacement meter, and send them to the computer for processing.

[0013] Furthermore, in step A, seven circular steel ring beams are welded inside the structural model of the circular underground continuous wall.

[0014] Furthermore, when the uniform confining pressure loading device is arranged in step B, a positioning slot is provided on the outer surface of the structural model, the hoop steel strand passes through the positioning slot, the anchor plate is provided with a slot, and one end of the hoop steel strand passes through the slot and is anchored with a steel strand anchor.

[0015] Furthermore, the density of the hoop steel strands increases as the depth of the structural model of the circular underground continuous wall increases.

[0016] Compared with the prior art, the present invention has the following beneficial effects:

[0017] It can apply uniform confining pressure to the structural model of the circular underground continuous wall, and more realistically test and measure the effect and influence of the uniform confining pressure on the structural model of the circular underground continuous wall, thereby providing a more scientific and reliable test basis for the design and construction of the circular underground continuous wall structure, so as to ensure the construction and operation safety of the circular underground continuous wall.

[0018] By adjusting the tension of the hoop steel hinge wire, the contact pressure and its changes are adjusted, and then the loading value of the structural model is controlled, and the effect and influence of the uniform confining pressure on the structural model under different soil pressure conditions are simulated, making the test method of the present invention more applicable and can be used for the test of most circular underground continuous wall structure models.

[0019] When arranging the uniform pressure loading device, a positioning slot is also provided on the outer surface of the structural model. The fixed hoop steel strands pass through the positioning slots, so that each hoop steel strand can be positioned in the slot of the positioning rod. The hoop steel strands are distributed in an orderly manner to avoid the hoop steel strands being entangled with each other during the test, affecting the application of the load and making the test difficult to conduct. BRIEF DESCRIPTION OF THE DRAWINGS

[0020] Figure 1 It is a front view of the uniform confining pressure loading method of the present invention.

[0021] Figure 2 It is a rear view of the uniform confining pressure loading method according to an example of the present invention.

[0022] Figure 3 It is a top view of the uniform confining pressure loading method according to an example of the present invention.

[0023] Figure 4 It is a schematic diagram of the internal steel ring beam of the uniform confining pressure loading method of the present invention.

[0024] Among them, 1-structural model; 2-anchor plate; 3-positioning slot; 4-circular steel ring beam; 5-steel strand anchor; 6-strain gauge; 7-hoop steel strand; 8-dynamometer; 9-displacement meter. DETAILED DESCRIPTION

[0025] The technical solution of the present invention is further described below through the accompanying drawings and embodiments.

[0026] Embodiment 1

[0027] Combination Figure 1 The present invention provides a method for testing the stability of a circular underground continuous wall structure model, comprising the following steps:

[0028] A. Welded circular steel ring beam: Figure 3 As shown, the structural model 1 of the circular underground continuous wall is horizontally placed on the ground, and seven circular steel ring beams 4 are welded inside the structural model 1 of the circular underground continuous wall.

[0029] B. Arrange uniform confining pressure loading device: Figure 1 As shown, the structural model 1 of the circular underground continuous wall is placed horizontally on the ground. In this embodiment, twelve hoop steel strands 7 are arranged on the periphery of the structural model 1. One end of the twelve hoop steel strands 7 passes through the anchor plate 2 and is anchored by the steel strand anchor 5. The other end is fixed on the steel strand hydraulic jack after being wrapped around the outer surface of the structural model 1 for one circle. The hoop steel strands 7 are connected in series with a dynamometer 8.

[0030] C. Arrangement of test instruments: Figure 1 , Figure 4 As shown, 120 strain gauges 6 are placed on the inner and outer surfaces of the structural model 1 of the circular underground continuous wall, 16 strain gauges 6 are placed on the upper surface of the circular steel ring beam 4, and 24 displacement meters 9 are installed on the outer surface of the structural model 1 of the circular underground continuous wall;

[0031] D. Pressure loading: Apply pressure to the structural model 1 by tightening the hoop steel strand 7 with the steel strand hydraulic jack, obtain the data of the strain gauge 6 and displacement meter 9, and send them to the computer for processing.

[0032] like Figure 1 As shown, when the uniform confining pressure loading device is arranged in step B, a positioning slot 3 is also provided on the outer surface of the structural model 1, and the hoop steel strand 7 passes through the positioning slot 3. The anchor plate 2 has a slot, and one end of the hoop steel strand 7 passes through the slot and is anchored by the steel strand anchor 5.

[0033] The working principle and working process of the present invention are as follows: a plurality of groups of hoop steel strands 7 are arranged along the outer surface of the circular underground continuous wall structure model 1, and the hoop steel strands 7 are tightened by the steel strand hydraulic jack, and contact pressure is applied to the outer surface of the structure model 1. Since the hoop steel strands 7 are evenly distributed on the outer surface of the structure model 1 at the same height along the circumferential surface, a uniform confining pressure is generated on the structure model 1. At the same time, the hoop steel strands 7 are arranged sparsely at the top and densely at the bottom. This loading method can form a uniform confining pressure in the horizontal position, that is, the density of the hoop steel strands 7 increases with the depth of the circular underground continuous wall structure model 1. The vertical force is triangular along the depth direction. The deeper the position, the denser the hoop steel strands 7 are arranged, and the greater the confining pressure. This arrangement method can better simulate the change of soil pressure to a certain extent. The magnitude of the applied force can be read out through the dynamometer 8 connected in series to the steel strand jack and the tensioning hoop steel strand 7; the pressure and related mechanical parameters of various parts of the structural model 1 are measured by the strain gauge 6 and displacement meter 9 arranged on the surface of the structural model 1 to measure the internal force and deformation of the structural model respectively; these data are then sent to the computer for processing, and the mechanical performance parameter values ​​of the circular underground continuous wall structural model 1 under the action of uniform confining pressure are obtained.

[0034] Embodiment 2

[0035] Figure 1 What is drawn is the uniform confining pressure loading. In this embodiment, the twelve hoop steel strands 7 used in the first embodiment are replaced by seven hoop steel strands 7 of three sizes. The two hoop steel strands 7 at the bottom are anchored after spirally wrapping around the structure model 1 for three times. The third hoop steel strand 7 from the bottom is anchored after spirally wrapping around the structure model for two times. The last four hoop steel strands are anchored after wrapping around the structure model for one time. This improved method has the same number of turns of the hoop steel strands 7 as the original solution, which is twelve turns.

[0036] The second embodiment is applied in actual operation. Because of the shortage of hydraulic jack equipment for steel strands, the same number of hoops is achieved by increasing the number of turns of the hoop steel strands 7.

[0037] The above description is only a preferred embodiment of the present invention and does not limit the technical scope of the present invention. Therefore, any slight modifications, equivalent changes and modifications made to the above embodiments based on the technical essence of the present invention still fall within the scope of the technical solution of the present invention.

Claims

1. A method for testing the stability of a circular underground continuous wall structure model, characterized in that: The following steps are involved: A. Welding a circular steel ring beam: placing a structural model (1) of a circular underground continuous wall horizontally on the ground, and welding a plurality of circular steel ring beams (4) inside the structural model (1) of the circular underground continuous wall; B. Arrange a uniform confining pressure loading device: Place the circular underground continuous wall structure model (1) horizontally on the ground, pass one end of a plurality of hoop steel strands (7) through the anchor plate (2), and anchor them with a steel strand anchor (5), and then wrap the other end around the outer surface of the structure model (1) and fix it on the steel strand hydraulic jack, and connect a dynamometer (8) in series to the hoop steel strands (7); C. Arrangement of the testing instrument: a plurality of strain gauges (6) are attached to the inner and outer surfaces of the structural model (1) of the circular underground continuous wall, and a plurality of displacement meters (9) are installed on the outer surface of the structural model (1) of the circular underground continuous wall; D. Pressure loading: The steel strand hydraulic jack is used to tighten the hoop steel strand (7) to apply pressure to the structural model (1), and the data of the strain gauge (6) and displacement meter (9) are obtained and sent to the computer for processing.

2. The method for testing the stability of a circular underground continuous wall structure model according to claim 1, characterized in that: In step A, seven circular steel ring beams (4) are welded inside the structural model (1) of the circular underground continuous wall.

3. The method for testing the stability of a circular underground continuous wall structure model according to claim 1, characterized in that: When the uniform confining pressure loading device is arranged in step B, a positioning slot (3) is also provided on the outer surface of the structural model (1), the hoop steel strand (7) passes through the positioning slot (3), and a slot is provided on the anchor plate (2), and one end of the hoop steel strand (7) passes through the slot and is anchored by a steel strand anchor (5).

4. The method for testing the stability of a circular underground continuous wall structure model according to claim 1, characterized in that: The density of the hoop steel strands (7) increases as the depth of the circular underground continuous wall structural model (1) increases.