Operation strategy determination method and device, equipment and storage medium
By predicting the target power value and evaluating different strategies using hierarchical analysis method and entropy weight method, the problem of insufficient efficiency of fixed strategies in the photoreservation and load energy management system is solved, the system is maximized and optimal operation is achieved, and the adaptability is improved and efficiency.
Patent Information
- Application Number
- CN202411023655.0
- Authority / Receiving Office
- CN · China
- Patent Type
- Applications(China)
- Current Assignee / Owner
- Filing Date
- 2024-07-26
- Publication Date
- 2024-11-15
AI Technical Summary
The existing optical load storage energy management system usually adopts a fixed strategy before project construction, ignoring the additional benefits and efficiency improvements that may be brought about by strategy adjustments in different periods, resulting in limited accuracy of user return on investment prediction.
By obtaining power generation related data, including actual power generation data and weather data, predicting the target power value, and using hierarchical analysis method and entropy weight method to determine the evaluation value of different operating strategies, we can select the optimal operating strategy.
A comprehensive evaluation of different strategies is achieved, and the optimal operation strategy for each preset period is identified and selected, which significantly improves the adaptability and efficiency of the system, reduces operational risks, and brings a high return on investment to users. Market competitiveness.
Smart Images

Figure CN118970905A_ABST
Abstract
Description
Technical Field
[0001] The present invention relates to the field of microgrid control technology, and in particular to a method, device, equipment and storage medium for determining an operation strategy. Background Art
[0002] At present, the existing solar-to-load energy management systems on the market usually set fixed strategies based on user needs before project construction. Before project construction, traditional measurement schemes usually estimate indicators based on the general effect of a single control target.
[0003] However, these systems ignore the additional benefits and efficiency gains that may be brought about by adjusting strategies at different times. Fixed strategies may not maximize economic benefits during peak hours, resulting in limited accuracy in predicting users' return on investment. These systems ignore the variability in actual operations, resulting in users facing accuracy limitations when predicting return on investment. Summary of the invention
[0004] The present invention provides a method, device, equipment and storage medium for determining an operation strategy to solve the problem of poor efficiency of the control strategy.
[0005] In a first aspect, the present invention provides a method for determining an operation strategy, comprising:
[0006] Acquire power generation related data, and use the power generation related data to determine a target power forecast value for a preset future date, wherein the power generation related data includes actual power generation data and weather data affecting power generation, and the target power forecast value includes a light power forecast value and a load power forecast value;
[0007] Determine the operation result information under different preset operation strategies in each preset time period by using the target power prediction value, and determine the evaluation value of the preset operation strategy by using the hierarchical analysis method and the entropy weight method for each operation result information;
[0008] An operation strategy for each preset time period in the preset future date is determined according to the evaluation value.
[0009] In a second aspect, the present invention provides a device for determining an operation strategy, comprising:
[0010] A power prediction module, used to obtain power generation related data, and use the power generation related data to determine a target power prediction value for a preset future date, wherein the power generation related data includes actual power generation data and weather data affecting power generation, and the target power prediction value includes a light power prediction value and a load power prediction value;
[0011] An operation strategy evaluation module, used to determine the operation result information under different preset operation strategies in each preset time period by using the target power prediction value, and determine the evaluation value of the preset operation strategy by using the hierarchical analysis method and the entropy weight method for each of the operation result information;
[0012] An operation strategy determination module is used to determine the operation strategy for each preset time period in the preset future date according to the evaluation value.
[0013] In a third aspect, the present invention provides an electronic device, the electronic device comprising:
[0014] at least one processor;
[0015] and a memory communicatively coupled to the at least one processor;
[0016] The memory stores a computer program that can be executed by at least one processor, and the computer program is executed by at least one processor so that the at least one processor can execute the method for determining the operating strategy of the first aspect mentioned above.
[0017] In a fourth aspect, the present invention provides a computer-readable storage medium storing computer instructions, wherein the computer instructions are used to enable a processor to implement the method for determining the operating strategy of the first aspect when executing the computer instructions.
[0018] The scheme for determining the operation strategy provided by the present invention uses the predicted target power to predict each preset operation strategy, the operation result information of each preset time period at a preset future date, and uses the hierarchical analysis method and the entropy weight method to determine the evaluation value of the preset operation strategy, thereby achieving a comprehensive evaluation of different strategies, so as to identify and select the optimal operation strategy for each preset time period, ensuring that the system operates in a maximized benefit and optimal manner, significantly improving the adaptability and efficiency of the system, while reducing operational risks, and bringing users a higher rate of return on investment and market competitiveness.
[0019] It should be understood that the content described in this section is not intended to identify the key or important features of the present invention, nor is it intended to limit the scope of the present invention. Other features of the present invention will become easily understood through the following description. BRIEF DESCRIPTION OF THE DRAWINGS
[0020] In order to more clearly illustrate the technical solutions in the embodiments of the present invention, the following briefly introduces the drawings required for use in the description of the embodiments. Obviously, the drawings described below are only some embodiments of the present invention. For ordinary technicians in this field, other drawings can be obtained based on these drawings without creative work.
[0021] Figure 1is a flow chart of a method for determining an operation strategy provided according to Embodiment 1 of the present invention;
[0022] Figure 2 is a flow chart of a method for determining an operation strategy provided according to Embodiment 2 of the present invention;
[0023] Figure 3 is a structural schematic diagram of a device for determining an operation strategy provided according to Embodiment 3 of the present invention;
[0024] Figure 4 It is a schematic diagram of the structure of an electronic device provided according to Embodiment 4 of the present invention. DETAILED DESCRIPTION
[0025] In order to enable those skilled in the art to better understand the scheme of the present invention, the technical scheme in the embodiments of the present invention will be clearly and completely described below in conjunction with the drawings in the embodiments of the present invention. Obviously, the described embodiments are only part of the embodiments of the present invention, not all of the embodiments. Based on the embodiments of the present invention, all other embodiments obtained by ordinary technicians in this field without creative work should fall within the scope of protection of the present invention.
[0026] It should be noted that the terms "first", "second", etc. in the specification and claims of the present invention and the above-mentioned drawings are used to distinguish similar objects, and are not necessarily used to describe a specific order or sequence. It should be understood that the data used in this way can be interchanged where appropriate, so that the embodiments of the present invention described herein can be implemented in an order other than those illustrated or described herein. In the description of the present invention, unless otherwise specified, "multiple" refers to two or more. "And / or" describes the association relationship of associated objects, indicating that three relationships may exist, for example, A and / or B can represent: A exists alone, A and B exist at the same time, and B exists alone. The character " / " generally indicates that the objects associated before and after are an "or" relationship. In addition, the terms "including" and "having" and any of their variations are intended to cover non-exclusive inclusions, for example, a process, method, system, product or device that includes a series of steps or units is not necessarily limited to those steps or units that are clearly listed, but may include other steps or units that are not clearly listed or inherent to these processes, methods, products or devices.
[0027] Embodiment 1
[0028] Figure 1A flowchart of a method for determining an operating strategy is provided for Embodiment 1 of the present invention. This embodiment can be applicable to situations where a control strategy of an energy system, such as a photovoltaic load-storage system, is determined. The method can be executed by an operating strategy determination device. The operating strategy determination device can be implemented in the form of hardware and / or software. The operating strategy determination device can be configured in an electronic device. The electronic device can be composed of two or more physical entities or one physical entity.
[0029] like Figure 1 As shown, the method for determining an operation strategy provided by the first embodiment of the present invention specifically includes the following steps:
[0030] S101. Acquire power generation related data, and use the power generation related data to determine a target power forecast value for a preset future date, wherein the power generation related data includes actual power generation data and weather data affecting power generation, and the target power forecast value includes a light power forecast value and a load power forecast value.
[0031] In this embodiment, if the application scenario is a photovoltaic-storage-load system, the power generation-related data may include photovoltaic and energy storage installed capacity data, historical and real-time active power, load power and electricity price, etc., as well as meteorological data of the location of the photovoltaic-storage-load system, such as hourly irradiance and hourly temperature, etc. A power prediction model may be pre-built, and the power generation-related data may be input into the model to obtain a target power prediction value for a preset future date.
[0032] S102, using the target power prediction value to determine the operation result information under different preset operation strategies in each preset time period, and for each of the operation result information, using the hierarchical analysis method and the entropy weight method to determine the evaluation value of the preset operation strategy.
[0033] In this embodiment, a serial number can be assigned in advance to each control strategy in the control strategy set to form an execution plan for strategy 1 to strategy n. These strategies may include peak shaving and valley filling, peak-valley arbitrage, and demand optimization, etc., to meet different control needs. Simulation software can be used to predict the operation result information corresponding to different preset operation strategies for each preset period in the preset future date according to the target power prediction value, wherein the operation result information includes economic benefit indicators and environmental benefit indicators, etc. For each operation result information, the hierarchical analysis method can be used to determine the indicator weight of each indicator, and the entropy weight method can be used to determine the entropy weight of each indicator. By performing preset mathematical operations on the operation result information, the indicator weight and the entropy weight, the evaluation value of each preset operation strategy can be obtained.
[0034] S103: Determine an operation strategy for each preset time period in the preset future date according to the evaluation value.
[0035] In this embodiment, the preset operation strategy corresponding to the evaluation value that meets the preset requirements in each preset time period can be determined as the operation strategy of the preset time period.
[0036] The method for determining the operation strategy provided by the embodiment of the present invention obtains power generation-related data, and uses the power generation-related data to determine the target power prediction value of the preset future date, wherein the power generation-related data includes actual power generation data and weather data affecting power generation, and the target power prediction value includes the optical power prediction value and the load power prediction value, and uses the target power prediction value to determine the operation result information under different preset operation strategies in each preset time period, and for each of the operation result information, uses the hierarchical analysis method and the entropy weight method to determine the evaluation value of the preset operation strategy, and determines the operation strategy of each preset time period in the preset future date according to the evaluation value. The technical solution of the embodiment of the present invention predicts each preset operation strategy using the predicted target power, the operation result information of each preset time period in the preset future date, and uses the hierarchical analysis method and the entropy weight method to determine the evaluation value of the preset operation strategy, so as to achieve a comprehensive evaluation of different strategies, so as to identify and select the optimal operation strategy for each preset time period, ensure that the system operates in a maximized benefit and optimal manner, significantly improve the adaptability and efficiency of the system, and reduce the operation risk at the same time, bringing users a higher return on investment and market competitiveness.
[0037] Optionally, for each of the operation result information, the evaluation value of the preset operation strategy is determined by using the hierarchical analysis method and the entropy weight method, including: for each of the operation result information, using a preset mathematical model to determine the target indicator of the preset operation strategy corresponding to the current operation result information, wherein the target indicator includes economic indicators, technical performance indicators and environmental benefit indicators; for each of the target indicators, using the hierarchical analysis method to determine the hierarchical weight of the current target indicator, and using the entropy weight method to determine the entropy weight of the current target indicator; using the hierarchical weight and the entropy weight to determine the evaluation value of the preset operation strategy.
[0038] Specifically, a mathematical model can be constructed in advance, such as an economic function, a technical performance function, and an environmental benefit function. The mathematical model can be used to obtain the target indicators of the preset operation strategy corresponding to the operation result information. For each operation result information, the hierarchical analysis method can be used to determine the indicator weight of each indicator, and the entropy weight method can be used to determine the entropy weight of each indicator. By performing preset mathematical operations on the operation result information, the indicator weight, and the entropy weight, the evaluation value of each preset operation strategy can be obtained.
[0039] Optionally, determining the operating strategy for each preset time period in the preset future date based on the evaluation value includes: for each preset time period in the preset future date, determining the preset operating strategy corresponding to the maximum evaluation value of the current preset time period as the operating strategy for the current preset time period.
[0040] Specifically, the preset operation strategy corresponding to the maximum evaluation value in each preset time period may be determined as the operation strategy for the preset time period.
[0041] Optionally, after determining the operating strategy for each preset time period in the preset future date according to the evaluation value, it also includes: comparing the actual operating income of the operating strategy for each preset time period in the preset future date with the preset static economic indicator, and outputting the comparison result information.
[0042] Specifically, a feasibility analysis can be conducted in advance based on historical data and demand to estimate the economic indicators of the preset control strategy. These indicators can be called static economic indicators. At the end of each day, the daily measured energy management benefits (i.e., actual operating benefits) can be compared with the daily energy management benefits calculated by the feasibility study (i.e., static economic indicators), and the result information of the comparison can be output. Compare the actual operating benefits after executing the optimal operating strategy on the day with the static economic indicators of the project construction phase, so that the difference between actual operation and feasibility study calculation can be more accurately understood, so as to make more reasonable investment decisions. This comparative analysis not only helps users understand the difference between actual operation and expectations, but also provides data support for operational decisions, enabling users to make more reasonable and accurate adjustments.
[0043] Embodiment 2
[0044] Figure 2 This is a flow chart of a method for determining an operating strategy provided in the second embodiment of the present invention. The technical solution of the embodiment of the present invention is further optimized on the basis of the above-mentioned optional technical solutions, and a specific method for determining the control strategy is given.
[0045] Optionally, the use of the power generation-related data to determine the target power forecast value for a preset future date includes: cleaning the actual power generation data in the power generation-related data to obtain data to be processed; inputting the data to be processed and the weather data in the power generation-related data into a preset prediction model to obtain an initial power forecast value of a first time resolution for a preset future date; interpolating the initial power forecast value to obtain a target power forecast value of a second time resolution, wherein the second time resolution is greater than the first time resolution. The advantage of such a setting is that a power forecast value with a finer time granularity can be obtained by interpolating the initial power forecast value.
[0046] Optionally, for each of the operation result information, a preset mathematical model is used to determine the target index of the preset operation strategy corresponding to the current operation result information, including: for each of the operation result information, the economic benefit information is determined using the first preset mathematical model, and the target economic benefit information of the preset operation strategy corresponding to the current operation result information is determined from the economic benefit information; the economic index is determined using the target economic benefit information, and for each of the operation result information, the technical performance index and the environmental benefit index are respectively determined using the second preset mathematical model, wherein the second preset mathematical model includes a technical performance function and an environmental benefit function. The advantage of such a setting is that, by determining the economic index, the technical performance index and the environmental benefit index, not only the influence of the technical performance on the operation strategy effect is considered, but also the influence of the economic and environmental impacts on the operation strategy effect is considered, and different strategies are comprehensively evaluated from multiple dimensions.
[0047] Optionally, the use of the hierarchical weight and the entropy weight to determine the evaluation value of the preset operation strategy includes: performing weighted summation on the hierarchical weight and the entropy weight to obtain a target weight value; and using the target weight value and the target indicator to determine the evaluation value of the preset operation strategy. The advantage of such a setting is that the evaluation value of the preset operation strategy is comprehensively and accurately determined in the above manner.
[0048] like Figure 2 As shown, a method for determining an operation strategy provided by Embodiment 2 of the present invention specifically includes the following steps:
[0049] S201, acquiring power generation related data, and cleaning actual power generation data in the power generation related data to obtain data to be processed.
[0050] Specifically, the cleaned data includes abnormally large values, abnormally small values, and consecutive repeated values.
[0051] S202: Input the data to be processed and weather data in the power generation related data into a preset prediction model to obtain an initial power prediction value of a first time resolution at a preset future date.
[0052] Exemplarily, after obtaining the data to be processed, 90% of the data to be processed in the past year (with a time resolution of 15 minutes) can be used as a training set, and 10% of the data to be processed can be used as a test set to establish and train a short-term prediction model. The model can combine the weather data of the next day to predict the optical power (i.e., the optical power prediction value) and load power data (i.e., the load power prediction value) of the next day. Among them, the first time resolution is 15 minutes. In order to ensure the accuracy of the preset prediction model, after each training cycle, the power generation-related data of the past month can be used to retrain and correct the preset prediction model.
[0053] S203: Perform interpolation processing on the initial power prediction value to obtain a target power prediction value with a second time resolution.
[0054] The second time resolution is greater than the first time resolution.
[0055] Specifically, an interpolation model can be established in advance, and the initial power prediction value can be interpolated using the model to obtain the target power prediction value of the next day with a second time resolution of 5 minutes. A dynamic correction model can also be established in combination with the actual power with a time resolution of 5 minutes, and the target power prediction value can be corrected using the model to obtain the corrected target power prediction value.
[0056] S204. Use the target power prediction value to determine the operation result information under different preset operation strategies for each preset time period, and for each of the operation result information, use the first preset mathematical model to determine the economic benefit information, and determine the target economic benefit information of the preset operation strategy corresponding to the current operation result information from the economic benefit information.
[0057] Specifically, the time can be divided into a preset period of 15 minutes, each preset period is used as a control decision point for an operation strategy, and the operation strategy for the preset period within the next 4 hours is determined every 4 hours.
[0058] For example, the economic benefit information includes the imbalance cost C unbalance , Battery cycle cost C cycle , Peak shaving and valley filling income R ph 、Peak-to-valley arbitrage income R arbitrage , demand optimization benefit R dp and environmental benefits R envir The economic benefit information can be determined by:
[0059] 1) The imbalance cost function in the first preset mathematical model is:
[0060] C unbalance =k unbalance ×(E demand -E supply )
[0061] Among them, k unbalance is the imbalance cost coefficient, E demand is the energy required, E supply It supplies energy.
[0062] 2) The battery cycle cost function in the first preset mathematical model is:
[0063] C cycle =k cycle ×(ncycles -C battery )
[0064] Among them, k cycle is the cost factor for each cycle, n cycles is the number of cycles in the time period, C battery is the initial cost of the battery.
[0065] 3) The peak shaving and valley filling profit function in the first preset mathematical model is:
[0066] R ph =P peak ×(E peak -E stored )
[0067] Among them, P peak is the electricity price during peak hours, E peak is the power demand during peak hours, E stored It is the amount of electricity released from energy storage during peak hours.
[0068] 4) The peak-to-valley arbitrage profit function in the first preset mathematical model is:
[0069] R arbitrage =(P peak -P valley )×E stored
[0070] Among them, P valley It is the electricity price during off-peak hours.
[0071] 5) The demand optimization benefit function in the first preset mathematical model is:
[0072] R dp =k demand ×(D max -D optimized )
[0073] Among them, k demand is the cost coefficient for demand optimization, D max is the maximum demand without optimization, D optimized is the maximum demand after optimization.
[0074] 6) The environmental benefit function in the first preset mathematical model is:
[0075]
[0076] Among them, k envir is the environmental benefit coefficient per unit emission reduction, It is the amount of carbon dioxide emissions reduced by the energy storage system.
[0077] For example, if the preset operation strategy corresponding to the current operation result information is the peak-shaving and valley-filling strategy, the target economic benefit information includes C unbalance , C cycle , R ph and R envir If the preset operation strategy corresponding to the current operation result information is the peak-valley arbitrage strategy, the target economic benefit information includes C unbalance , C cycle , R arbitrage and R envir If the preset operation strategy corresponding to the current operation result information is the demand optimization strategy, the target economic benefit information includes C unbalance , C cycle , R dp and R envir .
[0078] S205: Determine economic performance indicators using the target economic benefit information, and determine technical performance indicators and environmental benefit indicators using a second preset mathematical model for each piece of operation result information.
[0079] Wherein, the second preset mathematical model includes a technical performance function and an environmental benefit function.
[0080] Exemplary methods for determining economic indicators include:
[0081] 1) If the preset operation strategy corresponding to the current operation result information is the peak shaving and valley filling strategy, the economic index is CCF ph ,in:
[0082] CCF ph =C unbalance +C cycle -R ph -R envir
[0083] 2) If the preset operation strategy corresponding to the current operation result information of the economic indicator is the peak-valley arbitrage strategy, then the target economic benefit information is CCF arbitrage ,in:
[0084] CCF arbitrage =C unbalance +C cycle -R arbitrage -R envir
[0085] 3) If the preset operation strategy corresponding to the current operation result information is the demand optimization strategy, the economic index is CCF dp ,in:
[0086] CCF dp =Cunbalance +C cycle -R dp -R envir
[0087] Exemplarily, the technical performance indicator includes the energy storage system circular efficiency RTE, which is determined by:
[0088]
[0089] Among them, E output is the output power, E input is the input power.
[0090] Exemplarily, the environmental benefit indicator includes a carbon emission reduction used to represent the contribution of the energy storage system operation to reducing greenhouse gas emissions. and the local renewable energy utilization rate η, which is used to represent the impact of energy storage systems on increasing the utilization of renewable energy such as wind and solar energy renewable ,in:
[0091]
[0092] Among them, E avoided is the total amount of non-renewable energy that is reduced by the energy storage system, EF avoided is the corresponding energy carbon emission factor, E renewable_used is the amount of renewable energy used, E renewable_generated The amount of renewable energy generated.
[0093] S206: For each target indicator, determine the hierarchical weight of the current target indicator using the hierarchical analysis method, and determine the entropy weight of the current target indicator using the entropy weight method.
[0094] Among them, the target indicators include economic indicators, technical performance indicators and environmental benefit indicators.
[0095] Specifically, we can subjectively score the relevance and importance of the above indicators according to our own needs and preferences, and calculate the hierarchical weight of each indicator by applying the hierarchical analysis method. After the consistency test of the hierarchical analysis method is passed, the hierarchical weight w can be obtained. i The AHP is more inclined to subjective evaluation. In order to more comprehensively evaluate the operation of the system, the concept of information entropy can be introduced on the basis of the AHP. The entropy weight method can be used to determine the uncertainty of the indicator itself. The distribution weight of the evaluation indicator can be improved through objective information entropy to obtain the entropy weight v of the target indicator. i .
[0096] S207: Perform weighted summation on the hierarchical weight and the entropy weight to obtain a target weight. For example, the target weight ω iMethods of determination include:
[0097] ω i =k1w i +k2v i
[0098] Where k1 is the first weight coefficient corresponding to the first weight (entropy weight), k2 is the second weight coefficient corresponding to the second weight (entropy weight), and k1+k2=1. Assuming k1=0.5, k2=0.5, the target weight values of different indicators can be obtained, and i is the target indicator count. Preset operation strategy
[0099] S208: Determine an evaluation value of a preset operation strategy using the target weight value and the target indicator.
[0100] Exemplarily, the evaluation value y of the preset operation strategy j Methods of determination include:
[0101]
[0102] Among them, C ij is the i-th indicator under the j-th preset operation strategy, i=1,2,3. i=1 represents the economic indicator, i=2 represents the technical performance indicator, i=3 represents the environmental benefit indicator, y j Represents the evaluation value under the j-th preset operation strategy.
[0103] Optionally, the evaluation value may be standardized to obtain a standardized evaluation value d j , including:
[0104]
[0105] Among them, max() means taking the maximum value.
[0106] S209: For each preset time period in the preset future date, determine the preset operation strategy corresponding to the maximum evaluation value of the current preset time period as the operation strategy of the current preset time period.
[0107] S210: Compare the actual operating income of the operating strategy in each preset period of the preset future date with the preset static economic indicator, and output the comparison result information.
[0108] The method for determining the operating strategy provided in the embodiment of the present invention can obtain a power prediction value with a finer time granularity by interpolating the initial power prediction value, and by determining the economic index, technical performance index and environmental benefit index, not only the influence of technical performance on the effect of the operating strategy is considered, but also the influence of economy and environmental impact on the effect of the operating strategy is considered. Different strategies are comprehensively evaluated from multiple dimensions, the evaluation value of the preset operating strategy is comprehensively and accurately determined, and the optimal control strategy of the system is determined by dynamic optimization and real-time feedback.
[0109] Embodiment 3
[0110] Figure 3 This is a schematic diagram of the structure of a device for determining an operation strategy provided by Embodiment 3 of the present invention. Figure 3 As shown, the device includes: a power prediction module 301, an operation strategy evaluation module 302 and an operation strategy determination module 303, wherein:
[0111] A power prediction module, used to obtain power generation related data, and use the power generation related data to determine a target power prediction value for a preset future date, wherein the power generation related data includes actual power generation data and weather data affecting power generation, and the target power prediction value includes a light power prediction value and a load power prediction value;
[0112] An operation strategy evaluation module, used to determine the operation result information under different preset operation strategies in each preset time period by using the target power prediction value, and determine the evaluation value of the preset operation strategy by using the hierarchical analysis method and the entropy weight method for each of the operation result information;
[0113] An operation strategy determination module is used to determine the operation strategy for each preset time period in the preset future date according to the evaluation value.
[0114] The operating strategy determination device provided in the embodiment of the present invention uses the predicted target power to predict each preset operating strategy, the operating result information of each preset time period at a preset future date, and uses the hierarchical analysis method and the entropy weight method to determine the evaluation value of the preset operating strategy, thereby achieving a comprehensive evaluation of different strategies, so as to identify and select the optimal operating strategy for each preset time period, ensure that the system operates in a maximized benefit and optimal manner, significantly improve the adaptability and efficiency of the system, while reducing operational risks, and bringing users a higher rate of return on investment and market competitiveness.
[0115] Optionally, the power prediction module includes:
[0116] A cleaning unit, used for cleaning the actual power generation data in the power generation related data to obtain data to be processed;
[0117] A first prediction unit, configured to input the data to be processed and weather data in the power generation-related data into a preset prediction model to obtain an initial power prediction value of a first time resolution at a preset future date;
[0118] The second prediction unit is used to perform interpolation processing on the initial power prediction value to obtain a target power prediction value with a second time resolution, wherein the second time resolution is greater than the first time resolution.
[0119] Optionally, the operation strategy evaluation module includes:
[0120] An indicator determination unit, for determining, for each of the operation result information, a target indicator of a preset operation strategy corresponding to the current operation result information by using a preset mathematical model, wherein the target indicator includes an economic indicator, a technical performance indicator, and an environmental benefit indicator;
[0121] An entropy weight determination unit is used to determine the hierarchical weight of the current target indicator by using the hierarchical analysis method for each of the target indicators, and to determine the entropy weight of the current target indicator by using the entropy weight method;
[0122] An evaluation value determination unit is used to determine the evaluation value of a preset operation strategy using the hierarchical weight and the entropy weight.
[0123] Optionally, for each of the operation result information, a preset mathematical model is used to determine the target indicator of the preset operation strategy corresponding to the current operation result information, including: for each of the operation result information, economic benefit information is determined using a first preset mathematical model, and target economic benefit information of the preset operation strategy corresponding to the current operation result information is determined from the economic benefit information; economic indicators are determined using the target economic benefit information, and for each of the operation result information, technical performance indicators and environmental benefit indicators are respectively determined using a second preset mathematical model, wherein the second preset mathematical model includes a technical performance function and an environmental benefit function.
[0124] Optionally, the use of the hierarchical weight and the entropy weight to determine the evaluation value of the preset operating strategy includes: performing weighted summation of the hierarchical weight and the entropy weight to obtain a target weight value; and using the target weight value and the target indicator to determine the evaluation value of the preset operating strategy.
[0125] Optionally, the operation strategy determination module is specifically used to determine, for each preset time period in the preset future date, a preset operation strategy corresponding to the maximum evaluation value of the current preset time period as the operation strategy of the current preset time period.
[0126] Optionally, the device further comprises:
[0127] A comparison module is used to compare the actual operating income of the operating strategy for each preset time period in the preset future date with the preset static economic indicator after determining the operating strategy for each preset time period in the preset future date according to the evaluation value, and output the comparison result information.
[0128] The operating strategy determination device provided in the embodiment of the present invention can execute the operating strategy determination method provided in any embodiment of the present invention, and has the corresponding functional modules and beneficial effects of the execution method.
[0129] Embodiment 4
[0130] Figure 4 A schematic diagram of the structure of an electronic device 40 that can be used to implement an embodiment of the present invention is shown. The electronic device is intended to represent various forms of digital computers, such as laptop computers, desktop computers, workstations, personal digital assistants, servers, blade servers, mainframe computers, and other suitable computers. The electronic device can also represent various forms of mobile devices, such as personal digital processing, cellular phones, smart phones, wearable devices (such as helmets, glasses, watches, etc.) and other similar computing devices. The components shown herein, their connections and relationships, and their functions are merely examples and are not intended to limit the implementation of the present invention described and / or required herein.
[0131] like Figure 4 As shown, the electronic device 40 includes at least one processor 41, and a memory connected to the at least one processor 41, such as a read-only memory (ROM) 42, a random access memory (RAM) 43, etc., wherein the memory stores a computer program that can be executed by at least one processor, and the processor 41 can perform various appropriate actions and processes according to the computer program stored in the read-only memory (ROM) 42 or the computer program loaded from the storage unit 48 to the random access memory (RAM) 43. In the RAM 43, various programs and data required for the operation of the electronic device 40 can also be stored. The processor 41, the ROM 42, and the RAM 43 are connected to each other through a bus 44. An input / output (I / O) interface 45 is also connected to the bus 44.
[0132] A number of components in the electronic device 40 are connected to the I / O interface 45, including: an input unit 46, such as a keyboard, a mouse, etc.; an output unit 47, such as various types of displays, speakers, etc.; a storage unit 48, such as a disk, an optical disk, etc.; and a communication unit 49, such as a network card, a modem, a wireless communication transceiver, etc. The communication unit 49 allows the electronic device 40 to exchange information / data with other devices through a computer network such as the Internet and / or various telecommunication networks.
[0133] The processor 41 may be a variety of general and / or special processing components with processing and computing capabilities. Some examples of the processor 41 include, but are not limited to, a central processing unit (CPU), a graphics processing unit (GPU), various dedicated artificial intelligence (AI) computing chips, various processors running machine learning model algorithms, digital signal processors (DSPs), and any appropriate processors, controllers, microcontrollers, etc. The processor 41 executes the various methods and processes described above, such as a method for determining an operation strategy.
[0134] In some embodiments, the method for determining the operation strategy may be implemented as a computer program, which is tangibly contained in a computer-readable storage medium, such as a storage unit 48. In some embodiments, part or all of the computer program may be loaded and / or installed on the electronic device 40 via the ROM 42 and / or the communication unit 49. When the computer program is loaded into the RAM 43 and executed by the processor 41, one or more steps of the method for determining the operation strategy described above may be performed. Alternatively, in other embodiments, the processor 41 may be configured to execute the method for determining the operation strategy in any other appropriate manner (e.g., by means of firmware).
[0135] Various implementations of the systems and techniques described above herein can be implemented in digital electronic circuit systems, integrated circuit systems, field programmable gate arrays (FPGAs), application specific integrated circuits (ASICs), application specific standard products (ASSPs), systems on chips (SOCs), load programmable logic devices (CPLDs), computer hardware, firmware, software, and / or combinations thereof. These various implementations can include: being implemented in one or more computer programs that can be executed and / or interpreted on a programmable system including at least one programmable processor, which can be a special purpose or general purpose programmable processor that can receive data and instructions from a storage system, at least one input device, and at least one output device, and transmit data and instructions to the storage system, the at least one input device, and the at least one output device.
[0136] Computer programs for implementing the methods of the present invention may be written in any combination of one or more programming languages. These computer programs may be provided to a processor of a general-purpose computer, a special-purpose computer, or other programmable data processing device, so that when the computer program is executed by the processor, the functions / operations specified in the flow chart and / or block diagram are implemented. The computer program may be executed entirely on the machine, partially on the machine, partially on the machine and partially on a remote machine as a stand-alone software package, or entirely on a remote machine or server.
[0137] The computer device provided above can be used to execute the method for determining the operation strategy provided in any of the above embodiments, and has corresponding functions and beneficial effects.
[0138] Embodiment 5
[0139] In the context of the present invention, a computer-readable storage medium may be a tangible medium, wherein the computer-executable instructions, when executed by a computer processor, are used to perform a method for determining an operation strategy, the method comprising:
[0140] Acquire power generation related data, and use the power generation related data to determine a target power forecast value for a preset future date, wherein the power generation related data includes actual power generation data and weather data affecting power generation, and the target power forecast value includes a light power forecast value and a load power forecast value;
[0141] Determine the operation result information under different preset operation strategies in each preset time period by using the target power prediction value, and determine the evaluation value of the preset operation strategy by using the hierarchical analysis method and the entropy weight method for each operation result information;
[0142] An operation strategy for each preset time period in the preset future date is determined according to the evaluation value.
[0143] In the context of the present invention, a computer-readable storage medium may be a tangible medium that may contain or store a computer program for use by an instruction execution system, device or equipment or used with an instruction execution system, device or equipment or used in combination with an instruction execution system, device or equipment. A computer-readable storage medium may include, but is not limited to, electronic, magnetic, optical, electromagnetic, infrared, or semiconductor systems, devices or equipment, or any suitable combination of the foregoing. Alternatively, a computer-readable storage medium may be a machine-readable signal medium. A more specific example of a machine-readable storage medium may include an electrical connection based on one or more lines, a portable computer disk, a hard disk, a random access memory (RAM), a read-only memory (ROM), an erasable programmable read-only memory (EPROM or flash memory), an optical fiber, a portable compact disk read-only memory (CD-ROM), an optical storage device, a magnetic storage device, or any suitable combination of the foregoing.
[0144] The computer device provided above can be used to execute the method for determining the operation strategy provided in any of the above embodiments, and has corresponding functions and beneficial effects.
[0145] It is worth noting that in the embodiment of the above-mentioned operation strategy determination device, the various units and modules included are only divided according to functional logic, but are not limited to the above-mentioned division, as long as the corresponding functions can be achieved; in addition, the specific names of the functional units are only for the convenience of distinguishing each other, and are not used to limit the scope of protection of the present invention.
[0146] Note that the above are only preferred embodiments of the present invention and the technical principles used. Those skilled in the art will understand that the present invention is not limited to the specific embodiments described herein, and that various obvious changes, readjustments and substitutions can be made by those skilled in the art without departing from the scope of protection of the present invention. Therefore, although the present invention has been described in more detail through the above embodiments, the present invention is not limited to the above embodiments, and may include more other equivalent embodiments without departing from the concept of the present invention, and the scope of the present invention is determined by the scope of the appended claims.
Claims
1. A method for determining an operation strategy, characterized in that: include: Acquire power generation related data, and use the power generation related data to determine a target power forecast value for a preset future date, wherein the power generation related data includes actual power generation data and weather data affecting power generation, and the target power forecast value includes a light power forecast value and a load power forecast value; Determine the operation result information under different preset operation strategies in each preset time period by using the target power prediction value, and determine the evaluation value of the preset operation strategy by using the hierarchical analysis method and the entropy weight method for each operation result information; An operation strategy for each preset time period in the preset future date is determined according to the evaluation value.
2. The method according to claim 1, characterized in that The step of using the power generation related data to determine a target power forecast value for a preset future date includes: Cleaning the actual power generation data in the power generation related data to obtain data to be processed; Inputting the data to be processed and weather data in the power generation-related data into a preset prediction model to obtain an initial power prediction value of a first time resolution at a preset future date; The initial power prediction value is interpolated to obtain a target power prediction value of a second time resolution, wherein the second time resolution is greater than the first time resolution.
3. The method according to claim 1, characterized in that The step of determining the evaluation value of the preset operation strategy by using the analytic hierarchy process and the entropy weight method for each operation result information includes: For each of the operation result information, a preset mathematical model is used to determine the target index of the preset operation strategy corresponding to the current operation result information, wherein the target index includes an economic index, a technical performance index and an environmental benefit index; For each of the target indicators, the hierarchical weight of the current target indicator is determined by using the hierarchical analysis method, and the entropy weight of the current target indicator is determined by using the entropy weight method; The evaluation value of the preset operation strategy is determined using the hierarchical weight and the entropy weight.
4. The method according to claim 3, characterized in that For each of the operation result information, a preset mathematical model is used to determine the target indicator of the preset operation strategy corresponding to the current operation result information, including: For each of the operation result information, determine the economic benefit information using the first preset mathematical model, and determine the target economic benefit information of the preset operation strategy corresponding to the current operation result information from the economic benefit information; The target economic benefit information is used to determine the economic index, and for each of the operation result information, the second preset mathematical model is used to respectively determine the technical performance index and the environmental benefit index, wherein the second preset mathematical model includes a technical performance function and an environmental benefit function.
5. The method according to claim 3, characterized in that: The step of using the hierarchical weight and the entropy weight to determine the evaluation value of the preset operation strategy includes: Performing a weighted summation on the hierarchical weight and the entropy weight to obtain a target weight value; The target weight value and the target indicator are used to determine the evaluation value of the preset operation strategy.
6. The method according to claim 1, characterized in that The step of determining the operation strategy for each preset time period in the preset future date according to the evaluation value includes: For each preset time period in the preset future date, the preset operation strategy corresponding to the maximum evaluation value of the current preset time period is determined as the operation strategy of the current preset time period.
7. The method according to any one of claims 1 to 6, characterized in that After determining the operation strategy for each preset time period in the preset future date according to the evaluation value, the method further includes: The actual operating income of the operating strategy in each preset period of the preset future date is compared with the preset static economic indicator, and the result information of the comparison is output.
8. A device for determining an operation strategy, characterized in that: include: A power prediction module, used to obtain power generation related data, and use the power generation related data to determine a target power prediction value for a preset future date, wherein the power generation related data includes actual power generation data and weather data affecting power generation, and the target power prediction value includes a light power prediction value and a load power prediction value; An operation strategy evaluation module, used to determine the operation result information under different preset operation strategies in each preset time period by using the target power prediction value, and determine the evaluation value of the preset operation strategy by using the hierarchical analysis method and the entropy weight method for each of the operation result information; An operation strategy determination module is used to determine the operation strategy for each preset time period in the preset future date according to the evaluation value.
9. An electronic device, characterized in that: The electronic device comprises: at least one processor; and a memory communicatively connected to the at least one processor; wherein, The memory stores a computer program executable by the at least one processor, and the computer program is executed by the at least one processor so that the at least one processor can execute the method for determining the operation strategy according to any one of claims 1 to 7.
10. A computer-readable storage medium, characterized in that: The computer-readable storage medium stores computer instructions, and the computer instructions are used to enable a processor to implement the method for determining the operation strategy according to any one of claims 1 to 7 when executed.