Generator stator winding test method

Through the generator stator winding test method, combined with surface potential and DC withstand voltage test, and high-voltage surface potential test is carried out when necessary, the accuracy and efficiency of stator winding insulation defect detection is solved, significantly reducing the risk of accidents.

CN118980896APending Publication Date: 2024-11-19CHINA ENERGY CONSTR GRP HUAZHONG ELECTRIC POWER TEST & RES INST CO LTD
View PDF 0 Cites 0 Cited by

Patent Information

Application Number
CN202411219560.6
Authority / Receiving Office
CN · China
Patent Type
Applications(China)
Current Assignee / Owner
Filing Date
2024-09-02
Publication Date
2024-11-19

AI Technical Summary

Technical Problem

The insulation quality of the generator stator winding handbag has defects, resulting in the risk of insulation breakdown and short circuit accidents. It is difficult for the existing technology to effectively detect and locate defect locations.

Method used

A generator stator winding test method is adopted, including surface potential test and DC withstand voltage test, and the accuracy and efficiency of detection are improved by increasing the high-voltage surface potential test.

Benefits of technology

Effectively detect and locate the insulation defects of the generator stator winding, improve the accuracy and efficiency of the test, reduce the complexity of the operation process, and reduce the risk of accidents.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN118980896A_ABST
    Figure CN118980896A_ABST
Patent Text Reader

Abstract

The invention discloses a generator stator winding test method, which can realize the detection of the insulation defect of a generator stator winding and the accurate positioning of the specific insulation defect position by adding the step of high-voltage surface potential test, thereby effectively improving the test accuracy. And the high-voltage surface potential test is only carried out on the circuit with problems during the direct-current test of the generator stator winding, so that the test is more targeted, the operation process of testers is simplified, and the overall test efficiency is improved.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The present application relates to the technical field of power generation, and in particular to a method for testing a stator winding of a generator. Background Art

[0002] After the generator stator end outgoing wire is connected to the outgoing wire room on site, it needs to be insulated and wrapped by the manufacturer's professionals, so the insulation here is also called hand-wrapped insulation. The hand-wrapped insulation nose of the stator winding of a large generator has a complex shape and is prone to defects during the manufacturing process. There is a risk of insulation breakdown and short circuit accidents caused by problems with the quality of the hand-wrapped insulation at the end of the stator winding. Therefore, detecting the insulation condition of the generator stator winding and promptly discovering defects in the hand-wrapped insulation have become issues that need to be urgently addressed. Summary of the invention

[0003] The present application aims to propose a generator stator winding test method, which can detect insulation defects in the generator stator winding and find the location of the insulation defects.

[0004] A generator stator winding test method according to a first aspect of the present application includes:

[0005] In the case where internal cooling water is not passed through the stator winding of the generator, determining a first detection insulation parameter of the stator winding of the generator;

[0006] When the first detected insulation parameter satisfies a first preset insulation parameter condition, a surface potential test is performed on the stator winding of the generator using a first voltage as a test voltage to obtain a first surface potential at each lead-out end of the stator winding of the generator;

[0007] When the first surface potential of each of the lead-out terminals is less than a first preset surface potential and when internal cooling water flows through the stator winding of the generator, determining a second detection insulation parameter of the stator winding of the generator;

[0008] When the second detected insulation parameter meets the second preset insulation parameter condition, a DC withstand voltage test is performed to obtain the leakage current of each phase of the stator winding of the generator;

[0009] Determining the fault state of each phase line of the stator winding of the generator according to the leakage current of each phase;

[0010] When the fault state of each phase line indicates that at least one phase line is faulty, a high voltage surface potential test is performed on the line with the fault using a second voltage as a test voltage to obtain a second surface potential at each lead-out terminal on the line with the fault; the second voltage is greater than the first voltage;

[0011] The insulation defect position of the generator stator winding is determined according to the second surface potential.

[0012] The generator stator winding test method according to the embodiment of the present application has at least the following beneficial effects:

[0013] The surface potential test was passed when the internal cooling water was not passed in the generator stator winding, but the DC withstand voltage test was not passed when the internal cooling water was passed in the generator stator winding. When a faulty phase line was detected, the step of performing a high-voltage surface potential test was added, which could further determine the specific insulation defect position in the faulty line. The high-voltage surface potential test could find insulation defects that could not be found by conventional surface potential tests, and could accurately locate the fault point. The generator stator winding test method of the embodiment of the present application can detect the insulation defects of the generator stator winding and accurately locate the specific insulation defect position by adding the step of performing a high-voltage surface potential test, effectively improving the accuracy of the test, and only performing a high-voltage surface potential test on the line found to have problems during the DC test of the generator stator winding, making the test more targeted, streamlining the operating procedures of the test personnel, and improving the overall test efficiency.

[0014] According to some embodiments of the present application, the second voltage is a first preset coefficient times the first voltage, the first preset coefficient is greater than a lower threshold value and less than a higher threshold value, and the lower threshold value is greater than 1.

[0015] According to some embodiments of the present application, the step of performing a high voltage surface potential test on a line with a fault by using the second voltage as a test voltage to obtain a second surface potential at each lead-out terminal on the line with the fault includes:

[0016] Wrapping tin foil around each lead-out end of the faulty line of the generator stator winding;

[0017] Applying the second voltage from each lead-out terminal on the line with the fault;

[0018] The surface potential at each lead-out terminal on the line with the fault is measured to obtain the second surface potential.

[0019] According to some embodiments of the present application, determining the insulation defect position of the stator winding of the generator according to the second surface potential includes:

[0020] comparing each of the second surface potentials with a second predetermined surface potential;

[0021] In the case that the second surface potential is greater than or equal to the second preset surface potential, the lead-out end corresponding to the second surface potential greater than or equal to the second preset surface potential is determined as the insulation defect position of the stator winding of the generator.

[0022] According to some embodiments of the present application, determining the insulation defect position of the stator winding of the generator according to the second surface potential includes:

[0023] In the case where each of the second surface potentials is less than the second preset surface potential, the first preset coefficient is incremented by a preset increment value, and the second voltage is updated according to the incremented first preset coefficient;

[0024] Jump to the step of using the second voltage as the test voltage and perform a high voltage surface potential test on the faulty line.

[0025] According to some embodiments of the present application, after determining the insulation defect position of the stator winding of the generator according to the second surface potential, the method further includes:

[0026] The insulating hand wrap at the lead-out end corresponding to the insulation defect position is removed and re-insulated and wrapped, and then dried;

[0027] Jump to the step of determining a second detected insulation parameter of the generator stator winding.

[0028] According to some embodiments of the present application, the generator stator winding test method further includes:

[0029] When the fault status of each phase line indicates that there is no fault in each phase line, determining a third detection insulation parameter of the stator winding of the generator;

[0030] When the third detected insulation parameter meets the third preset insulation parameter condition, performing an AC withstand voltage test on the stator winding of the generator to obtain a breakdown state of the stator winding of the generator;

[0031] In the case where the breakdown state indicates that the generator stator winding has broken down, the insulating hand bag at the lead-out end corresponding to the breakdown position is removed and re-insulated and dried, and the process jumps to the second detection insulation parameter of determining the generator stator winding;

[0032] When the breakdown status indicates that no breakdown occurs in the stator winding of the generator, a qualified label is generated.

[0033] According to some embodiments of the present application, the step of performing a surface potential test on the stator winding of the generator using the first voltage as the test voltage to obtain the first surface potential at each lead-out end of the stator winding of the generator includes:

[0034] Wrap tin foil at each lead-out end of the generator stator winding;

[0035] Applying the first voltage from each lead-out end of the stator winding of the generator;

[0036] The surface potential at each lead-out end of the stator winding of the generator is measured to obtain the first surface potential.

[0037] According to some embodiments of the present application, the generator stator winding test method further includes:

[0038] In the case where the first surface potential of the lead-out end is greater than or equal to the first preset surface potential, the insulating hand wrap at the lead-out end where the first surface potential is greater than or equal to the first preset surface potential is removed and re-insulated and wrapped, and then dried;

[0039] Jump to the step of determining a first detected insulation parameter of the generator stator winding.

[0040] According to some embodiments of the present application, the insulating hand wrap at the lead-out end is removed and re-insulated, including:

[0041] The glass ribbon wrapped by the insulation box of the lead-out terminal is peeled off, and the surface of the lead-out terminal is cleaned;

[0042] The lead-out end is wrapped with a silicone rubber tape, covered with a glass ribbon, and painted with epoxy paint.

[0043] Other features and advantages of the present application will be set forth in the following description, and in part will become apparent from the description, or may be understood by practicing the present application. BRIEF DESCRIPTION OF THE DRAWINGS

[0044] The above and / or additional aspects and advantages of the present application will become apparent and easily understood from the description of the embodiments in conjunction with the following drawings, in which:

[0045] Figure 1 It is a flow chart of an embodiment of the generator stator winding test method of the present application. DETAILED DESCRIPTION

[0046] The embodiments of the present application are described in detail below, and examples of the embodiments are shown in the accompanying drawings, wherein the same or similar reference numerals throughout represent the same or similar elements or elements having the same or similar functions. The embodiments described below with reference to the accompanying drawings are exemplary and are only used to explain the present application, and cannot be understood as limiting the present application.

[0047] In the description of this application, if there is a description of first, second, etc., it is only for the purpose of distinguishing technical features, and cannot be understood as indicating or implying relative importance or implicitly indicating the number of the indicated technical features or implicitly indicating the order of the indicated technical features.

[0048] In the description of the present application, it should be understood that the descriptions involving orientation, such as the orientation or positional relationship indicated as up, down, etc., are based on the orientation or positional relationship shown in the drawings, and are only for the convenience of describing the present application and simplifying the description, and do not indicate or imply that the device or element referred to must have a specific orientation, be constructed and operated in a specific orientation, and therefore should not be understood as a limitation on the present application.

[0049] In the description of this application, it should be noted that, unless otherwise clearly defined, terms such as setting, installing, connecting, etc. should be understood in a broad sense, and technicians in the relevant technical field can reasonably determine the specific meaning of the above terms in this application based on the specific content of the technical solution.

[0050] The technical solution of the present application will be clearly and completely described below in conjunction with the accompanying drawings. Obviously, the embodiments described below are only part of the embodiments of the present application, not all of the embodiments.

[0051] Figure 1 This is a flow chart of the generator stator winding test method according to the embodiment of the present application. Figure 1 , the embodiments of the present application are further described.

[0052] The present application embodiment provides a generator stator winding test method, the generator stator winding test method comprising the following steps:

[0053] Step 101, determining a first detection insulation parameter of the stator winding of the generator when no internal cooling water is passed through the stator winding of the generator;

[0054] Step 102: When the first detected insulation parameter meets the first preset insulation parameter condition, a surface potential test is performed on the generator stator winding using the first voltage as the test voltage to obtain a first surface potential at each lead-out end of the generator stator winding;

[0055] Step 103, when the first surface potential of each lead-out terminal is less than the first preset surface potential and when cooling water flows through the stator winding of the generator, determining a second detection insulation parameter of the stator winding of the generator;

[0056] Step 104: When the second detected insulation parameter meets the second preset insulation parameter condition, a DC withstand voltage test is performed to obtain leakage current of each phase of the stator winding of the generator;

[0057] Step 105: determining the fault state of each phase line of the generator stator winding according to the leakage current of each phase;

[0058] Step 106: When the fault status of each phase line indicates that at least one phase line is faulty, a high voltage surface potential test is performed on the line with the fault using the second voltage as the test voltage to obtain a second surface potential at each lead-out terminal on the line with the fault; the second voltage is greater than the first voltage;

[0059] Step 107: Determine the insulation defect position of the generator stator winding according to the second surface potential.

[0060] The surface potential test was passed when the internal cooling water was not passed in the generator stator winding, but the DC withstand voltage test was not passed when the internal cooling water was passed in the generator stator winding. When a faulty phase line was detected, the step of performing a high-voltage surface potential test was added, which could further determine the specific insulation defect position in the faulty line. The high-voltage surface potential test could find insulation defects that could not be found by conventional surface potential tests, and could accurately locate the fault point. The generator stator winding test method of the embodiment of the present application can detect the insulation defects of the generator stator winding and accurately locate the specific insulation defect position by adding the step of performing a high-voltage surface potential test, effectively improving the accuracy of the test, and only performing a high-voltage surface potential test on the line found to have problems during the DC test of the generator stator winding, making the test more targeted, streamlining the operating procedures of the test personnel, and improving the overall test efficiency.

[0061] In the above step 101, when no internal cooling water flows through the stator winding of the generator, a first detection insulation parameter of the stator winding of the generator is determined.

[0062] The above-mentioned determination of the first detection insulation parameter of the generator stator winding may be performed by performing an insulation resistance test without passing internal cooling water through the generator stator winding, and obtaining the first detection insulation parameter according to the insulation resistance test.

[0063] The above insulation resistance test has relevant provisions in some standards, such as "GB 50150-2016 Electrical Equipment Acceptance Test Standard for Electrical Installation Engineering". The above insulation resistance test can be carried out according to the relevant standards and adaptively adjusted as the standards are updated.

[0064] The above insulation resistance test can be carried out in two conditions: when the generator stator winding is not flowing with water or when the generator stator winding is flowing with water. When the generator is not flowing with water, the insulation resistance test is measured using an ordinary 2500V insulation resistance tester. When the generator is flowing with water, the insulation resistance test is measured using a 2500V water-cooled insulation resistance tester. According to the "GB 50150-2016 Electrical Equipment Acceptance Test Standard for Electrical Installation Engineering": (1) The unbalance coefficient of the insulation resistance should not be greater than 2; (2) The insulation absorption ratio of epoxy powder mica should not be less than 1.6. The polarization index should be measured for units with a capacity of 200MW and above, and the polarization index should not be less than 2.0; (3) The insulation resistance of the stator winding of the water-cooled generator should be measured without the influence of residual water; (4) For generators with dead grounding of the manifold, the test should be carried out without water; for generators with non-dead grounding of the manifold, the insulation resistance of the winding and the manifold should be measured separately. When measuring the insulation resistance of the winding, the shielding method should be used to eliminate the influence of water. The measurement results should comply with the manufacturer's regulations.

[0065] The above-mentioned first detection insulation parameters include various parameters specified in the "GB 50150-2016 Electrical Equipment Acceptance Test Standard for Electrical Installation Engineering" such as insulation resistance and unbalance coefficient.

[0066] In the above step 102, when the first detected insulation parameter meets the first preset insulation parameter condition, a surface potential test is performed on the generator stator winding using the first voltage as the test voltage to obtain the first surface potential at each lead-out terminal of the generator stator winding.

[0067] The above-mentioned first preset insulation parameter can be based on the provisions of "GB 50150-2016 Electrical Equipment Acceptance Test Standard for Electrical Installation Engineering"; the first detection insulation parameter meets the first preset insulation parameter condition, which can be that the first detection insulation parameter complies with the various provisions of "GB 50150-2016 Electrical Equipment Acceptance Test Standard for Electrical Installation Engineering" when the stator winding of the generator is not water-free.

[0068] Generally speaking, if the insulation resistance test fails, drying treatment is generally adopted, and subsequent tests are carried out after the insulation meets the requirements.

[0069] The above-mentioned surface potential test has relevant provisions in some standards, such as "GB 50150-2016 Electrical Equipment Acceptance Test Standard for Electrical Installation Engineering". The above-mentioned surface potential test can be carried out in accordance with the relevant standards and adaptively adjusted as the standards are updated.

[0070] The surface potential test can be carried out by applying a DC rated voltage from the generator stator winding lead-out end using the "positive pressure" method, and measuring the stator wire rods by wrapping the stator wire rods with tin foil on both ends of the stator wire rods. According to the "GB 50150-2016 Electrical Equipment Acceptance Test Standard for Electrical Installation Engineering", (1) When assembling the end leads of the generator on site, a DC voltage should be applied after the insulation wrapping material is dry; (2) The DC voltage value applied to the stator winding should be the rated voltage of the generator; (3) The measured surface DC potential should not be greater than the value specified by the manufacturer.

[0071] The lead ends of the generator stator winding, i.e., the end lead connectors of the generator stator winding, include hand-wrapped insulated lead connectors, turbine side phase-separated connectors, end connectors (including water pipe cone insulation) and transition lead parallel blocks.

[0072] In the above step 103, when the first surface potential of each lead-out terminal is less than the first preset surface potential and when cooling water flows through the stator winding of the generator, the second detection insulation parameter of the stator winding of the generator is determined.

[0073] The first preset surface potential can be a specified value preset in advance by the manufacturer. When the first surface potential of each lead-out terminal is less than the first preset surface potential, the surface potential test of the generator stator winding has passed, and the next test can be performed.

[0074] The above-mentioned determination of the second detection insulation parameter of the generator stator winding may be performed by performing an insulation resistance test when cooling water is passed through the generator stator winding, and obtaining the second detection insulation parameter according to the insulation resistance test.

[0075] The above-mentioned internal cooling water can have a conductivity of less than 1.5μs / cm. This standard is based on the consideration of the safety and efficiency of the generator stator cooling water system. Conductivity is an indicator to measure the electrical conductivity of a solution. For the generator stator cooling water, maintaining a low conductivity helps reduce the corrosion of ions in the water flow to the internal metal parts of the generator, thereby protecting the long-term stable operation of the equipment. In addition, water with low conductivity also helps to maintain good thermal conductivity, ensuring that the generator can effectively dissipate heat during operation and avoid overheating damage. In practical applications, it is necessary to regularly detect and monitor the conductivity of the stator cooling water to ensure that it remains within a safe range. If the conductivity is too high, appropriate treatment measures may need to be taken, such as changing the water source or performing water quality treatment, to reduce the conductivity and ensure the safe operation of the generator.

[0076] In the above step 104, when the second detected insulation parameter meets the second preset insulation parameter condition, a DC withstand voltage test is performed to obtain the leakage current of each phase of the stator winding of the generator;

[0077] The above-mentioned second preset insulation parameter can be based on the provisions of "GB 50150-2016 Electrical Equipment Acceptance Test Standard for Electrical Installation Engineering"; the second detection insulation parameter meets the second preset insulation parameter condition, which can be that the second detection insulation parameter complies with the provisions of "GB 50150-2016 Electrical Equipment Acceptance Test Standard for Electrical Installation Engineering" when water flows through the stator winding of the generator.

[0078] The above-mentioned DC withstand voltage test has relevant provisions in some standards, such as "GB 50150-2016 Electrical Equipment Acceptance Test Standard for Electrical Installation Engineering". The above-mentioned DC withstand voltage test can be carried out according to the relevant standards and adaptively adjusted as the standards are updated.

[0079] The above-mentioned DC withstand voltage test needs to be carried out in phases. According to the "GB 50150-2016 Electrical Equipment Acceptance Test Standard for Electrical Installation Engineering", the following provisions are required: (1) The test voltage is 3 times the rated voltage of the generator; (2) The test voltage should be increased in stages by 0.5 times the rated voltage, and each stage should be kept for 1 minute. The leakage current should be recorded, and the difference in leakage current between phases should not be greater than 100% of the minimum value. When the maximum leakage current is below 20μA and is judged to be good based on the comprehensive judgment of the insulation resistance value and the AC withstand voltage test results, the difference between phases can be ignored.

[0080] In the above step 105, the fault state of each phase line of the generator stator winding is determined according to the leakage current of each phase.

[0081] The above leakage current is too large, and the leakage current gradually increases with the extension of the withstand voltage time. The phase-to-phase leakage current is extremely unbalanced and exceeds the specified value of the regulations. If the imbalance exceeds 50%, it indicates that there is a defect in the insulation of the corresponding phase line of the generator stator winding. Specifically, according to the provisions of "GB 50150-2016 Electrical Equipment Acceptance Test Standard for Electrical Installation Engineering", the fault state of each phase line of the generator stator winding can be judged by the above leakage current.

[0082] For example, when the leakage current of a certain phase is greater than the specified maximum value, it can be determined that there is a fault in the phase line, the DC withstand voltage test fails, and the specific fault location needs to be located.

[0083] For example, when the leakage current of a certain phase is not greater than the specified value, but the difference with the minimum phase leakage current is greater than 100% of the minimum phase leakage current, it can be determined that there is a fault in the phase line, the DC withstand voltage test fails, and the specific fault location needs to be located.

[0084] For example, when the three-phase leakage current is less than the specified minimum value, the difference between the phases can be ignored, and it is determined that there is no fault in the three-phase line. The DC withstand voltage test is passed and the next test can be carried out.

[0085] In the above step 106, when the fault status of each phase line indicates that at least one phase line is faulty, a high voltage surface potential test is performed on the faulty line using the second voltage as the test voltage to obtain a second surface potential at each lead-out terminal on the faulty line; the second voltage is greater than the first voltage.

[0086] In the case where the fault status of each phase line indicates that at least one phase line has a fault, the DC withstand voltage test may fail. In this case, a high potential surface potential test is required to locate the specific fault.

[0087] The above-mentioned high voltage surface potential test is only performed on the circuits that are found to have problems during the DC test of the generator stator winding, so as to make the test more targeted, streamline the operating procedures of the test personnel and improve the overall test efficiency.

[0088] In the above step 107, the insulation defect position of the stator winding of the generator is determined according to the second surface potential.

[0089] The test voltage of the above-mentioned high voltage surface potential test is greater than the test voltage of the surface potential test, and can detect insulation defects that cannot be detected by conventional surface potential tests, and accurately locate the fault point.

[0090] This is because for the defects left inside the hand-wrapped insulation during the wrapping process, i.e., gaps or bubbles, when the conventional test voltage is applied to the stator winding, i.e., one times the rated voltage of the generator, the air in the gaps or bubbles in the deep insulation cannot be freed and conductive, which is not enough to find all the defects. As the applied test voltage increases, the gaps or bubbles inside the hand-wrapped insulation will be freed faster, and the potential will move outward to the surface faster, and finally develop to insulation breakdown. Therefore, a high-potential surface potential test is carried out to obtain the second surface potential at each lead-out terminal. If there is a sudden change in the second surface potential at each lead-out terminal and it is greater than a certain set threshold, it can be determined that the lead-out terminal corresponding to the second surface potential has an insulation defect, and the fault point can be accurately located.

[0091] In some embodiments, the second voltage is a first preset coefficient times the first voltage, the first preset coefficient is greater than a lower threshold value and less than a higher threshold value, and the lower threshold value is greater than 1.

[0092] In this embodiment, the test voltage of the high voltage surface potential test, i.e., the second voltage, is a first preset coefficient times the first voltage, and the first preset coefficient is between the low threshold value and the high threshold value, which can achieve better test performance of the high voltage surface potential test.

[0093] In some implementations, the first voltage may be the rated voltage Un of the generator, the lower threshold value may be 2, and the upper threshold value may be 3, that is, the first preset coefficient may be 2-3, and the second voltage may be 2-3Un.

[0094] In some implementations, using the second voltage as the test voltage, performing a high voltage surface potential test on the line with the fault, and obtaining the second surface potential at each lead-out terminal on the line with the fault, comprises:

[0095] Wrap tin foil around each lead-out terminal on the faulty line of the generator stator winding;

[0096] Applying a second voltage from each lead-out terminal on the line where the fault occurs;

[0097] The surface potential at each lead-out terminal on the line with the fault is measured to obtain a second surface potential.

[0098] In this embodiment, by wrapping tin foil around each lead-out terminal on the faulty line of the generator stator winding, the tin foil can shield the external electric field and prevent charge escape, thereby ensuring the accuracy of the test results and facilitating the implementation of the high voltage surface potential test.

[0099] The above-mentioned wrapping of tin foil at each lead-out terminal on the faulty line of the generator stator winding can be achieved by wrapping tin foil at each lead-out terminal separately, which helps to test each lead-out terminal separately.

[0100] The above-mentioned tin foil can shield the external electric field, prevent the escape of charge, and ensure the accuracy of the test results. In addition, the tin foil is relatively soft and can fit the shape of the test electrode well, thereby reducing the test error. In addition to serving as a shielding layer to protect the electrode, the tin foil can also reduce external electromagnetic interference. In an industrial environment, other equipment sometimes emits high-frequency electromagnetic waves, which interfere with the wire rod withstand voltage test. At this time, the tin foil can act as a shielding layer to absorb these interferences, thereby ensuring the accuracy of the test results.

[0101] In some embodiments, determining the insulation defect position of the stator winding of the generator according to the second surface potential includes:

[0102] comparing each second surface potential with a second predetermined surface potential;

[0103] In the case that the second surface potential is greater than or equal to the second preset surface potential, the lead-out end corresponding to the second surface potential greater than or equal to the second preset surface potential is determined as the insulation defect position of the stator winding of the generator.

[0104] In this embodiment, if the second surface potential at each lead-out terminal is greater than or equal to the second preset surface potential, it can be determined that the lead-out terminal corresponding to the second surface potential has an insulation defect, and the insulation fault point can be accurately located.

[0105] Since the test voltage is relatively high, as the test voltage is applied, the gaps or bubbles at the defective position inside the hand-wrapped insulation will be freed faster, the potential will move outward to the surface faster, the surface potential value will gradually increase, and the insulation performance will gradually decrease, and finally develop to insulation breakdown. Therefore, the surface potential at the defective position inside the hand-wrapped insulation will rise sharply, and the surface potential may even be many times higher than other parts. The second preset surface potential can be determined based on historical test data and equipment specifications to accurately locate the fault point.

[0106] In some embodiments, determining the insulation defect position of the stator winding of the generator according to the second surface potential includes:

[0107] In the case where each second surface potential is less than the second preset surface potential, the first preset coefficient is incremented by a preset increment value, and the second voltage is updated according to the incremented first preset coefficient;

[0108] Jump to using the second voltage as the test voltage and perform a high voltage surface potential test on the faulty line.

[0109] In this embodiment, after performing a high-voltage surface potential test with the second voltage as the test voltage, when each second surface potential obtained is smaller than the second preset surface potential, the insulation defect location of the generator stator winding still cannot be determined. The high-voltage surface potential test can be continued by increasing the second voltage until a second surface potential greater than the second preset surface potential is obtained, thereby determining the insulation defect location of the generator stator winding.

[0110] Since after the DC withstand voltage test, when the fault status of each phase line indicates that at least one phase line is faulty, the second voltage is used as the test voltage to perform a high-voltage surface potential test on the faulty line. Therefore, there must be insulation defects in the line. Therefore, after the initial second voltage is used as the test voltage for the high-voltage surface potential test and passes, the second voltage needs to be increased and the high-voltage surface potential test needs to be continued until the insulation defects are found.

[0111] The above-mentioned second voltage is a first preset coefficient times the first voltage. The above-mentioned first preset coefficient increases by a preset increment value, so the second voltage will also increase accordingly. However, it should be noted that the first preset coefficient is between the low threshold value and the high threshold value and cannot increase indefinitely to avoid damaging the device.

[0112] For example, the first voltage may be the rated voltage Un of the generator, the lower threshold value may be 2, the upper threshold value may be 3, that is, the first preset coefficient may be 2-3, the preset increment value may be 0.2, the initial value of the second voltage may be 2Un, and a high voltage surface potential test is performed with 2Un as the test voltage. After the test passes, the second voltage is increased to 2.2Un for the test again. After the test passes, the second voltage is increased to 2.4Un for the test again, and so on. It should be noted that the second voltage is increased to 3Un at most. During the increasing process of the second voltage, the second surface potential at a certain lead end is greater than the second preset surface potential, thereby determining that the lead end is the insulation defect location of the stator winding of the generator.

[0113] In some embodiments, the insulation defect position of the stator winding of the generator is determined according to the second surface potential, and then the method further includes:

[0114] Remove the insulation hand wrap at the lead-out end corresponding to the insulation defect position, re-insulate and wrap it, and dry it;

[0115] Jump to determining a second detected insulation parameter of the generator stator winding.

[0116] In this embodiment, after the insulation defect position of the generator stator winding is confirmed through the high voltage surface potential test, the insulation hand bag at the lead-out end corresponding to the insulation defect position needs to be repaired, and then the insulation resistance test is returned and the DC withstand voltage test step is returned after passing.

[0117] In some embodiments, the generator stator winding test method further includes:

[0118] When the fault status of each phase line indicates that there is no fault in each phase line, determining a third detection insulation parameter of the stator winding of the generator;

[0119] When the third detected insulation parameter meets the third preset insulation parameter condition, performing an AC withstand voltage test on the stator winding of the generator to obtain a breakdown state of the stator winding of the generator;

[0120] When the breakdown state indicates that the generator stator winding has broken down, the insulating hand bag at the lead-out end corresponding to the breakdown position is removed and re-insulated and dried, and the process jumps to determining the second detection insulation parameter of the generator stator winding;

[0121] In the case where the breakdown status indicates that no breakdown has occurred in the stator winding of the generator, a qualified label is generated.

[0122] In this embodiment, if the DC withstand voltage test is passed, the insulation resistance test is performed again. After the insulation resistance test is passed, the AC withstand voltage test is finally performed. When the AC withstand voltage test is passed, it can be confirmed that the stator winding of this motor is qualified; however, if the AC withstand voltage test fails, breakdown will occur, and the insulating hand bag at the corresponding lead-out terminal needs to be repaired, and then the insulation resistance test is returned and the DC withstand voltage test step is returned after passing.

[0123] The above-mentioned AC withstand voltage test has relevant provisions in some standards, such as "GB 50150-2016 Electrical Equipment Acceptance Test Standard for Electrical Installation Engineering". The above-mentioned AC withstand voltage test can be carried out according to the relevant standards and adaptively adjusted as the standards are updated.

[0124] The above AC withstand voltage test needs to be conducted in phases. When the power frequency AC withstand voltage test equipment cannot meet the requirements, the resonant withstand voltage test can be used instead. According to the "GB 50150-2016 Electrical Equipment Acceptance Test Standard for Electrical Installation Engineering": (1) The test voltage is (1000+2Un)*0.8 or negotiated with the manufacturer; (2) The water-cooled motor is tested under water flow, and the water quality should be qualified; the hydrogen-cooled generator should be tested before hydrogen filling, and it is strictly forbidden to test during the replacement process.

[0125] The confirmation of the lead-out terminal corresponding to the breakdown position mentioned above can be divided into two situations. If the AC withstand voltage test fails, there will be insulation breakdown. The explicit insulation breakdown can be found by the naked eye, and the lead-out terminal corresponding to the breakdown position can be determined by observation; the invisible insulation breakdown, when checking the insulation resistance, when the insulation resistance tester applies a short-term high voltage, it will cause discharge at the defective position, and the fault defect point can be determined by finding the discharge position.

[0126] The third detection insulation parameter of the generator stator winding can be determined by performing an insulation resistance test with internal cooling water flowing through the generator stator winding, and obtaining the third detection insulation parameter according to the insulation resistance test. The internal cooling water can have a conductivity of less than 1.5 μs / cm to ensure that it remains within a safe range. If the conductivity is too high, corresponding treatment measures may need to be taken, such as changing the water source or performing water quality treatment, to reduce the conductivity and ensure the safe operation of the generator.

[0127] The above-mentioned third preset insulation parameter can be based on the provisions of "GB 50150-2016 Electrical Equipment Acceptance Test Standard for Electrical Installation Engineering"; the third detection insulation parameter meets the third preset insulation parameter condition, which can be that the third detection insulation parameter complies with the provisions of "GB 50150-2016 Electrical Equipment Acceptance Test Standard for Electrical Installation Engineering" when water flows through the stator winding of the generator.

[0128] In some embodiments, using the first voltage as the test voltage, performing a surface potential test on the stator winding of the generator to obtain the first surface potential at each lead-out terminal of the stator winding of the generator includes:

[0129] Wrap tin foil around each lead-out end of the generator stator winding;

[0130] Applying a first voltage from each lead-out terminal of the stator winding of the generator;

[0131] The surface potential at each lead-out terminal of the stator winding of the generator is measured to obtain a first surface potential.

[0132] In this embodiment, by wrapping tin foil around each lead-out end of the generator stator winding, the tin foil can shield the external electric field, prevent charge escape, ensure the accuracy of the test results, and facilitate the implementation of high-voltage surface potential tests.

[0133] In some embodiments, the generator stator winding test method further includes:

[0134] In the case where the first surface potential of the lead-out terminal is greater than or equal to the first preset surface potential, the insulating hand wrap at the lead-out terminal where the first surface potential is greater than or equal to the first preset surface potential is removed and re-insulated and wrapped, and then dried;

[0135] Jump to determining a first detected insulation parameter of the generator stator winding.

[0136] In this embodiment, if the first surface potential of the lead-out terminal is greater than or equal to the first preset surface potential, that is, the surface potential test fails, it is necessary to repair the insulating hand bag at the lead-out terminal corresponding to the insulation defect position, and then return to the insulation resistance test and repeat the surface potential test step after passing the test.

[0137] In some embodiments, the insulating hand wrap at the lead-out end is removed and the insulating wrap is re-wrapped, including:

[0138] Peel off the glass ribbon wrapped in the insulation box of the lead-out terminal and clean the surface of the lead-out terminal;

[0139] The lead-out terminal is wrapped with silicone rubber tape, covered with glass ribbon, and painted with epoxy paint.

[0140] In this embodiment, the lead-out terminal at the defective position is completely cleaned of the outer glass ribbon and filler. Generally, it is found that the insulation tape inside the insulation box is unevenly wrapped, or the internal filler is not completely cured, feels soft, and there are gaps or bubbles inside the insulation, which requires re-insulation wrapping. By peeling off the glass ribbon, cleaning the surface, then wrapping the silicone rubber tape, and finally wrapping the glass ribbon, and applying epoxy paint, the lead-out terminal with insulation defects can be repaired, which ensures the safety and reliability of the lead-out terminal to a certain extent. Through such treatment, the risk of electrical failure can be effectively reduced and the safety of equipment and personnel can be ensured.

[0141] The surface of the lead-out terminal is cleaned to remove any dirt, grease or other impurities that may exist, so as to ensure that the silicone rubber belt can be firmly adhered to the lead-out terminal.

[0142] The above-mentioned silicone rubber tape can enhance the insulation performance of the lead-out terminal and prevent current leakage or short circuit. Therefore, the lead-out terminal is wrapped with the silicone rubber tape after cleaning the surface.

[0143] The outer glass further enhances the safety and durability of the lead-out terminal and protects the silicone rubber belt from being affected by the external environment.

[0144] In some embodiments, the generator stator winding test method of the present application has been applied in two 660MW power plants, effectively solving the defect problem of hand-wrapped insulation at the end of the generator stator winding.

[0145] In the description of this specification, the description with reference to the terms "one embodiment", "some implementations", "illustrative embodiments", "examples", "specific examples", or "some examples" means that the specific features, structures, materials, or characteristics described in conjunction with the embodiment or example are included in at least one embodiment or example of the present application. In this specification, the schematic representation of the above terms does not necessarily refer to the same embodiment or example. Moreover, the specific features, structures, materials, or characteristics described may be combined in any one or more embodiments or examples in a suitable manner.

[0146] Although the embodiments of the present application are described in detail above in conjunction with the accompanying drawings, the present application is not limited to the above embodiments. A person of ordinary skill in the art can understand that various changes, modifications, substitutions and variations can be made to these embodiments without departing from the principle and purpose of the present application. The scope of the present application is defined by the claims and their equivalents.

Claims

1. A generator stator winding test method, characterized in that: include: In the case where internal cooling water is not passed through the stator winding of the generator, determining a first detection insulation parameter of the stator winding of the generator; When the first detected insulation parameter satisfies a first preset insulation parameter condition, a surface potential test is performed on the stator winding of the generator using a first voltage as a test voltage to obtain a first surface potential at each lead-out end of the stator winding of the generator; When the first surface potential of each of the lead-out terminals is less than a first preset surface potential and when internal cooling water flows through the stator winding of the generator, determining a second detection insulation parameter of the stator winding of the generator; When the second detected insulation parameter meets the second preset insulation parameter condition, a DC withstand voltage test is performed to obtain the leakage current of each phase of the stator winding of the generator; Determining the fault state of each phase line of the stator winding of the generator according to the leakage current of each phase; When the fault state of each phase line indicates that at least one phase line is faulty, a high voltage surface potential test is performed on the line with the fault using the second voltage as the test voltage to obtain a second surface potential at each lead-out terminal on the line with the fault; The second voltage is greater than the first voltage; The insulation defect position of the generator stator winding is determined according to the second surface potential.

2. The generator stator winding test method according to claim 1, characterized in that: The second voltage is a first preset coefficient times the first voltage, the first preset coefficient is greater than a lower threshold value and less than a higher threshold value, and the lower threshold value is greater than 1.

3. The generator stator winding test method according to claim 1, characterized in that: The method of performing a high voltage surface potential test on the line with the fault by using the second voltage as the test voltage to obtain the second surface potential at each lead-out terminal on the line with the fault comprises: Wrapping tin foil around each lead-out end of the faulty line of the generator stator winding; Applying the second voltage from each lead-out terminal on the line with the fault; The surface potential at each lead-out terminal on the line with the fault is measured to obtain the second surface potential.

4. The generator stator winding test method according to claim 2, characterized in that: Determining the insulation defect position of the stator winding of the generator according to the second surface potential includes: comparing each of the second surface potentials with a second predetermined surface potential; In the case that the second surface potential is greater than or equal to the second preset surface potential, the lead-out end corresponding to the second surface potential greater than or equal to the second preset surface potential is determined as the insulation defect position of the stator winding of the generator.

5. The generator stator winding test method according to claim 4, characterized in that: Determining the insulation defect position of the stator winding of the generator according to the second surface potential includes: In the case where each of the second surface potentials is less than the second preset surface potential, the first preset coefficient is incremented by a preset increment value, and the second voltage is updated according to the incremented first preset coefficient; Jump to the step of using the second voltage as the test voltage and perform a high voltage surface potential test on the faulty line.

6. The generator stator winding test method according to claim 1, characterized in that: After determining the insulation defect position of the stator winding of the generator according to the second surface potential, the method further comprises: The insulating hand wrap at the lead-out end corresponding to the insulation defect position is removed and re-insulated and wrapped, and then dried; Jump to the step of determining a second detected insulation parameter of the generator stator winding.

7. The generator stator winding test method according to claim 1, characterized in that: The generator stator winding test method further includes: When the fault status of each phase line indicates that there is no fault in each phase line, determining a third detection insulation parameter of the stator winding of the generator; When the third detected insulation parameter meets the third preset insulation parameter condition, performing an AC withstand voltage test on the stator winding of the generator to obtain a breakdown state of the stator winding of the generator; In the case where the breakdown state indicates that the generator stator winding has broken down, the insulating hand bag at the lead-out end corresponding to the breakdown position is removed and re-insulated and dried, and the process jumps to the second detection insulation parameter of determining the generator stator winding; When the breakdown status indicates that no breakdown occurs in the stator winding of the generator, a qualified label is generated.

8. The generator stator winding test method according to claim 1, characterized in that: The step of performing a surface potential test on the generator stator winding using the first voltage as the test voltage to obtain a first surface potential at each lead-out end of the generator stator winding comprises: Wrap tin foil at each lead-out end of the generator stator winding; Applying the first voltage from each lead-out end of the stator winding of the generator; The surface potential at each lead-out end of the stator winding of the generator is measured to obtain the first surface potential.

9. The generator stator winding test method according to claim 1, characterized in that: The generator stator winding test method further includes: In the case where the first surface potential of the lead-out end is greater than or equal to the first preset surface potential, the insulating hand wrap at the lead-out end where the first surface potential is greater than or equal to the first preset surface potential is removed and re-insulated and wrapped, and then dried; Jump to the step of determining a first detected insulation parameter of the generator stator winding.

10. The generator stator winding test method according to claim 6, 7 or 9, characterized in that: The insulating hand wrap at the lead-out end is removed and re-insulated, including: The glass ribbon wrapped by the insulation box of the lead-out terminal is peeled off, and the surface of the lead-out terminal is cleaned; The lead-out end is wrapped with a silicone rubber tape, covered with a glass ribbon, and painted with epoxy paint.