Method and system for constructing equivalent direct-current topology of multi-stage alternating-current and direct-current hybrid power grid
By constructing the equivalent DC topology of multi-stage AC and DC hybrid power grid, the prediction problems of inter-provincial power transactions and scheduling plans are solved, and the safe operation and rapid clearance of the power grid are achieved, and the randomness and volatility of new energy are adapted to the randomness and volatility of new energy.
Patent Information
- Application Number
- CN202411033274.0
- Authority / Receiving Office
- CN · China
- Patent Type
- Applications(China)
- Current Assignee / Owner
- Filing Date
- 2024-07-30
- Publication Date
- 2024-11-19
AI Technical Summary
In multi-stage AC and DC hybrid power grid, inter-provincial power transactions and scheduling plans are difficult to accurately predict, resulting in safe operation problems. In addition, the ultra-high voltage DC connection line operation mode is complex and the results of inter-provincial power transaction clearance are difficult to achieve rapid optimization. clear.
By constructing the equivalent DC topology of multi-stage AC-DC hybrid power grid, using provincial AC section data to calculate the available transmission capacity, and perform DC approximation based on the process topology, construct an equivalent DC topology, and establish a real-time power that maximizes the consumption of new energy. Trading model ensures rapid calculation and formulation of power scheduling plans under the constraints of safe operation.
It realizes inter-provincial power dispatching plan and transaction clearing on a multi-stage AC-DC hybrid power grid independent of regional power trading markets and inter-provincial communication line power grid, ensuring the safe operation and rapid clearing of the power grid, and adapting to the randomness of new energy. and volatility.
Smart Images

Figure CN118983777A_ABST
Abstract
Description
Technical Field
[0001] The present invention belongs to the technical field of power system dispatching and operation, and specifically relates to a method and system for constructing an equivalent DC topology of a multi-level AC / DC hybrid power grid. Background Art
[0002] my country's largest power grid has a three-level grid structure: the State Grid's inter-provincial interconnection lines (mainly long-distance ultra-high voltage DC power grids, mixed with AC power grids) are divided into central grids and provincial grids (AC power grids), while the Southern Grid has a two-level grid structure, with the Southern Grid's inter-provincial interconnection lines and provincial grids.
[0003] The distribution of energy resources and power load in my country is extremely unbalanced, with thermal power, hydropower, wind power, and photovoltaic resources mainly concentrated in the west and north, while power load centers are concentrated in the east and southeast. The pressure of absorbing the rapid growth of renewable energy in the west and north, as well as the time difference between the peak loads in the west and the east, further highlight the imbalance trend of real-time power supply and demand in the country. Therefore, it is imperative to quickly clear short-term power transactions between provinces to solve the contradiction of supply and demand imbalance between the east and west and the north and south.
[0004] The ultra-high voltage DC interconnection line is equipped with a large-capacity supporting power supply. The coupling between its operation mode and the clearing results of inter-provincial power transactions is very complex. The operating conditions and output levels of the units are difficult to accurately predict, which can easily induce safety operation problems. Therefore, it is necessary to decouple the intra-provincial and inter-provincial AC loop flows to ensure the construction of an equivalent DC topology, so that the inter-provincial power dispatch plan or power transaction optimization clearing can be carried out in parallel with the safe operation plan of the power grid, while ensuring the rapid optimization and clearing of inter-provincial power transactions, especially real-time transactions. Summary of the invention
[0005] In order to address the deficiencies in the prior art, the present invention aims to provide a method for constructing an equivalent DC topology of a multi-level AC / DC hybrid power grid. The method approximates the complex AC power grid flow of the multi-level AC / DC hybrid power grid by the DC method, constructs an equivalent DC topology, and thereby conducts inter-provincial power trading on the multi-level large-scale AC / DC hybrid power grid, so as to closely follow the safe operation mode of ultra-high voltage DC during the inter-provincial power dispatching plan or power trading optimization and clearing process, and ensure rapid market clearing operations under the safe operation of the power grid.
[0006] In order to achieve the above object, the technical solution adopted by the present invention is:
[0007] A method for constructing an equivalent DC topology of a multi-level AC / DC hybrid power grid comprises the following steps:
[0008] 1) Obtain multi-level AC / DC hybrid power grid data;
[0009] 2) calculating the available transmission capacity of the selected provincial AC section for inter-provincial power trading based on the relevant multi-level AC / DC hybrid power grid data obtained in step 1);
[0010] 3) The process topology is obtained by processing the equivalent DC of the provincial AC section, and the equivalent DC topology is constructed based on the process topology through the DC approximation of the AC subnet of the inter-provincial tie line;
[0011] 4) Establish a real-time power trading model for maximizing the absorption of renewable energy under the constraints of equivalent DC stability limits; Based on the above equivalent DC topology, support the adaptation to the randomness and volatility of renewable energy output on multi-level AC / DC hybrid power grids, and quickly calculate and formulate transmission dispatch plans for maximizing the absorption of renewable energy in the western region under the constraints of safe operation of the power grid.
[0012] The multi-level AC / DC hybrid power grid data obtained in step 1) include the inter-provincial interconnection line AC / DC hybrid power grid topology, each provincial power grid topology, network association matrix and related parameters, and each provincial AC section available transmission capacity and power grid operation plan; the related parameters include branch resistance and reactance; the power grid operation plan includes the inter-provincial interconnection line operation plan before and / or during the day; wherein the AC power grid in each area is identified as a node.
[0013] In step 3), the equivalent DC approximation of the AC subnet of the inter-provincial tie line includes the following steps:
[0014] An AC subnet b of an inter-provincial tie line refers to the AC grid after deleting the DC tie line branches in the process topology, which includes the equivalent DC branches of all provincial sections;
[0015] Let K be the set of nodes in the AC subnet b associated with the DC branch or associated with the power supply or load, and E be the set of branches connected to K in the process topology; E contains AC branches or DC branches; let E c is the commutative subset of E, E d is the DC subset of E;
[0016] Each AC branch (j, k) of AC subnet b connects two nodes j and k. The absolute value of branch susceptance of AC branch (j, k) is y (ij) B is a diagonal element of y (ij) |E c ||E c |Diagonal matrix;
[0017] Let A be the branch set E c and the association matrix of the power grid topology composed of the node set K, that is, A is a |E c | row| K | column matrix; the injection transfer distribution factor of the AC subnet is:
[0018] S=BA(A'BA)- 1 ,
[0019] Where A' is the transposed matrix of A; let A d is the branch set E d and the node set K constitutes the grid topology, A'd is the association matrix of A d The transposed matrix of c The trend of F d (t) is the DC branch set E d The power flow on the node set K is G k (t), the load vector is L k (t), according to the DC approximation method, the power flow on the AC branch is:
[0020] F c (t) = S(A′ d F d (t)+G k (t)-L k (t)) (1).
[0021] In step 3), constructing a multi-level AC / DC hybrid power grid equivalent DC topology includes the following steps:
[0022] For the equivalent DC branch set E of the provincial AC section a , whose available transmission capacity in time period t is ATC a (t), and its corresponding power flow is F a (t), its equivalent DC constraint is:
[0023] -ATC a (t)≤F a (t)≤ATC a (t) (2);
[0024] For the DC branch E of the inter-provincial AC / DC hybrid power grid d , whose available transmission capacity in time period t is ATC d (t), and its corresponding power flow F d (t), whose stability limit constraint is:
[0025] -ATC d (t)≤F d (t)≤ATC d (t) (3);
[0026] For the AC branch E of the inter-provincial AC / DC hybrid power grid c , whose available transmission capacity in time period t is ATC c (t), and its corresponding power flow F c(t), whose stability limit constraint is:
[0027] -ATC c (t)≤F c (t)≤ATC c (t) (4);
[0028] Substituting formula (1) into formula (4), we get:
[0029] -ATC c (t)≤S(A′ d F d (t)+G k (t)-L k (t))≤ATC c (t) (5);
[0030] Inequalities (2), (3) and (5) are the stability limit constraints of the equivalent DC topology of the multi-level AC / DC hybrid power grid, where the decision variables are only the power output vector G associated with the inter-provincial AC subgrid. k (t), load vector L k (t), equivalent DC power flow F at provincial AC section a (t) and inter-provincial power grid DC power flow F d (t), and the AC power flow of the inter-provincial AC / DC hybrid power grid no longer appears in the stability limit constraint of the equivalent DC topology of the multi-level AC / DC hybrid power grid.
[0031] Step 4) specifically includes the following steps:
[0032] G r (t) is the output of the new energy station r in period t, G g (t) is the output of other power sources except renewable energy, L(t) is the upper limit of the load for absorbing renewable energy, F d (t-1) is the DC power flow of the inter-provincial power grid in period t-1; To predict the upper limit of the output of new energy r in time period t, The output limit of other power sources other than renewable energy. To absorb the load of new energy or the upper limit of electricity purchase, ΔF d is the upper limit of DC ramping; the transmission dispatch plan to maximize the consumption of new energy in western China in period t is the output result of the following optimization model:
[0033] Max∑ r G r (t) (6);
[0034] The constraints satisfied are:
[0035] Power output limit:
[0036]
[0037] Upper limit of load for absorbing new energy:
[0038]
[0039] DC branch climbing upper limit:
[0040] -ΔF d a≤F d (t)-F d (t-1)≤ΔF d (9);
[0041] The branch stability limit constraints are equations (2), (3) and (5).
[0042] Correspondingly, the present invention also proposes a system for constructing an equivalent DC topology of a multi-level AC / DC hybrid power grid, the system comprising a data acquisition module, a process topology and equivalent DC topology generation module, and a maximum absorption model generation module for new energy;
[0043] The data acquisition module is used to obtain multi-level AC / DC hybrid power grid data, including the inter-provincial interconnection line AC / DC hybrid power grid topology and parameters, each provincial AC section topology and parameters, and system operation section control requirements;
[0044] The process topology and equivalent DC topology generation module is used to obtain the process topology by converting the provincial AC section power flow into DC according to the multi-level AC / DC hybrid power grid data; and to construct the equivalent DC topology based on the process topology through the inter-provincial tie line AC subnet power flow DC approximation;
[0045] The maximum new energy consumption model generation module is used to generate a mathematical model for maximizing the new energy consumption according to an equivalent DC topology and calculate the value of the maximum new energy consumption and the power flow of each AC / DC branch of the multi-level AC / DC hybrid power grid that meets the stability limit safety constraints, wherein the power flow of the DC branch obeys the DC climbing constraint.
[0046] The beneficial effects of the present invention are:
[0047] The present invention constructs a product topology equivalent to a DC power grid by decoupling the provincial AC section current and the inter-provincial interconnection line loop AC current, supporting the establishment of an inter-provincial real-time power trading market on a multi-level AC / DC hybrid power grid. The equivalent DC topology is independent of the clearing current of the regional power trading market and the provincial AC section, and is also independent of the AC loop current of the inter-provincial interconnection line power grid, so that an inter-provincial power dispatching plan or a power trading clearing model can be independently constructed on this power grid topology, laying the foundation for maximizing the absorption of new energy in the west. Because it is an equivalent DC topology, in the process of establishing an inter-provincial power dispatching plan or optimizing the clearing of power trading, we can focus on the interaction and synchronous coordination between the operation mode of the ultra-high voltage DC power grid and the clearing current, ensuring rapid calculation and clearing, and ensuring that its calculation and clearing results meet the safe operation of the power grid. BRIEF DESCRIPTION OF THE DRAWINGS
[0048] Figure 1 The present invention is a flowchart of a method for constructing a power grid topology. DETAILED DESCRIPTION
[0049] The principles and features of the present invention are described below in conjunction with the accompanying drawings. The examples given are only used to explain the present invention and are not intended to limit the scope of use of the present invention.
[0050] like Figure 1 As shown, the method for constructing an equivalent DC topology of a multi-level AC / DC hybrid power grid of the present invention comprises the following steps:
[0051] 1) Obtain multi-level AC / DC hybrid power grid data and each AC bus section parameters.
[0052] The multi-level AC / DC hybrid power grid data includes the inter-provincial interconnection line AC / DC hybrid power grid topology (called basic topology), each provincial power grid topology, network association matrix and related parameters, as well as the available transmission capacity of each provincial AC section and the power grid operation plan (including the inter-provincial interconnection line day-ahead and / or day-in operation plan). These related parameters include the resistance and reactance of the branch. Among them, the AC power grid in each region is identified as a node.
[0053] 2) Based on the relevant multi-level AC / DC hybrid power grid data obtained in step 1), the available transmission capacity of the selected provincial AC section for inter-provincial power trading is calculated.
[0054] In the basic topology, each provincial AC section is equivalent to a DC branch. This is because the provincial AC sections used for inter-provincial power trading do not form an AC loop. The difference between the new grid topology constructed according to the above steps (called process topology) and the basic topology is that the provincial AC section in the basic topology is a DC equivalent branch in the process topology, and its available transmission capacity in time period t is ATC. a (t).
[0055] 3) Obtain the process topology by processing the equivalent DC of the provincial AC section, and construct the equivalent DC topology based on the process topology through the DC approximation of the AC subnet of the inter-provincial tie line. The following steps are included:
[0056] An AC subnet b of an inter-provincial tie line refers to the AC grid after deleting the DC tie line branches (including all equivalent DC branches of provincial sections) in the process topology. This AC subnet may be interconnected or not.
[0057] Let K be the set of nodes in the AC subnetwork b associated with the DC branch or associated with the power source or load, and E be the set of branches connected to K in the process topology; E may contain both AC branches and DC branches. c is the commutative subset of E, E d is the DC subset of E.
[0058] Each AC branch (j, k) of AC subnet b connects two nodes j and k. The absolute value of branch susceptance of AC branch (j, k) is y (ij) B is a diagonal element of y (ij) |E c ||E c |Diagonal matrix.
[0059] Let A be the branch set E c and the association matrix of the power grid topology composed of the node set K, that is, A is a |E c | row| K | column matrix; the injection transfer distribution factor of the AC subnet is:
[0060] S=BA(A'BA) -1 ,
[0061] Where A' is the transposed matrix of A. Let A d is the branch set E d and the association matrix of the power grid topology composed of the node set K, A' d Yes A d The transposed matrix of c The trend of F d (t) is the DC branch set E d The power output vector on the node set K is G k (t), the load vector is L k (t), according to the DC approximation method, the power flow on the AC branch is:
[0062] F c (t) = S(A′ d F d (t)+G k (t)-L k(t)) (1).
[0063] In addition, constructing the equivalent DC topology of a multi-level AC / DC hybrid power grid includes the following steps:
[0064] For the equivalent DC branch set E of the provincial AC section a , whose available transmission capacity in time period t is ATC a (t), and its corresponding power flow is F a (t), its equivalent DC constraint is:
[0065] -ATC a (t)≤F a (t)≤ATC a (t) (2);
[0066] For the DC branch E of the inter-provincial AC / DC hybrid power grid d , whose available transmission capacity in time period t is ATC d (t), and its corresponding power flow F d (t), whose stability limit constraint is:
[0067] -ATC d (t)≤F d (t)≤ATC d (t) (3);
[0068] For the AC branch E of the inter-provincial AC / DC hybrid power grid c , whose available transmission capacity in time period t is ATC c (t), and its corresponding power flow F c (t), whose stability limit constraint is:
[0069] -ATC c (t)≤F c (t)≤ATC c (t) (4);
[0070] Substituting formula (1) into formula (4), we get:
[0071] -ATC c (t)≤S(A d F d (t)+G k (t)-L k (t))≤ATC c (t) (5)
[0072] Inequalities (2), (3) and (5) are the stability limit constraints of the equivalent DC topology of the multi-level AC / DC hybrid power grid, where the decision variables are only the power output vector G associated with the inter-provincial AC subgrid. k (t), load vector L k(t), equivalent DC power flow F at provincial AC section a (t) and inter-provincial power grid DC power flow F d (t). However, the AC power flow of the inter-provincial AC / DC hybrid power grid no longer appears in the stability limit constraint of the equivalent DC topology of the multi-level AC / DC hybrid power grid.
[0073] 4) Establish a real-time power trading model for maximizing the consumption of new energy under the constraints of equivalent DC stability limits. Based on the above equivalent DC topology, quickly calculate and formulate a transmission dispatch plan for maximizing the consumption of new energy in the west under the constraints of safe operation of the power grid, so as to adapt to the randomness and volatility of new energy output on the multi-level AC / DC hybrid power grid. Specifically, the following steps are included:
[0074] G r (t) is the output of the new energy station r in period t, G g (t) is the output of other power sources except renewable energy, L(t) is the upper limit of the load for absorbing renewable energy, F d (t-1) is the DC power flow of inter-provincial power grid branch d in period t-1. To predict the upper limit of the output of new energy r in time period t, The output limit of other power sources other than renewable energy. To absorb the load of new energy or the upper limit of electricity purchase, ΔF d is the upper limit of DC ramping. The transmission dispatch plan to maximize the consumption of new energy in the west during period t is the output result of the following optimization model:
[0075] Max∑ r G r (t) (6);
[0076] The constraints satisfied are:
[0077] Power output limit:
[0078]
[0079] Upper limit of load for absorbing new energy:
[0080]
[0081] DC branch climbing upper limit:
[0082] -ΔF d ≤F d (t)-F d (t-1)≤ΔF d (9)
[0083] The branch stability limit constraints are equations (2), (3) and (5).
[0084] Correspondingly, the present invention also proposes a system for constructing an equivalent DC topology of a multi-level AC / DC hybrid power grid. The system includes a data acquisition module, a process topology and equivalent DC topology generation module, and a maximum absorption model generation module for new energy.
[0085] The data acquisition module is used to obtain multi-level AC / DC hybrid power grid data, including the inter-provincial interconnection line AC / DC hybrid power grid topology and parameters, the provincial AC section topology and parameters, and the system operation section control requirements.
[0086] The process topology and equivalent DC topology generation module is used to obtain the process topology by DCizing the provincial AC section power flow according to the multi-level AC / DC hybrid power grid data; and based on the process topology, the equivalent DC topology is constructed through the DC approximation of the AC subnet power flow of the inter-provincial interconnection line.
[0087] The maximum new energy absorption model generation module is used to generate a mathematical model for maximizing the absorption of new energy based on the equivalent DC topology and calculate the numerical value of the maximum new energy absorption and the power flow of each AC / DC branch of the multi-level AC / DC hybrid power grid that meets the stability limit safety constraints, among which the power flow of the DC branch obeys the DC climbing constraint.
[0088] The present invention constructs an equivalent DC topology by decoupling the provincial AC section current and the inter-provincial interconnection line AC loop current, supporting the establishment of inter-provincial power trading on a multi-level AC / DC hybrid power grid. Once constructed, the equivalent DC topology is independent of the regional power trading market clearing current and the provincial AC section, and is also independent of the AC loop current of the inter-provincial interconnection line power grid, so that inter-provincial power dispatching plans or inter-provincial power trading can be independently constructed on this power grid topology, laying the foundation for maximizing the absorption of new energy in the west. Because it is an equivalent DC topology, in the process of establishing the optimized clearing of inter-provincial power trading, we can focus on the interaction and synchronous coordination of the ultra-high voltage DC power grid operation mode and the clearing current, ensure rapid clearing, and ensure that its clearing results meet the safe operation of the power grid.
[0089] Obviously, the embodiments described above are only some embodiments of the present application, rather than all embodiments. The preferred embodiments of the present application are given in the accompanying drawings, but they do not limit the patent scope of the present application. The present application can be implemented in many different forms. On the contrary, the purpose of providing these embodiments is to make the understanding of the disclosure of the present application more thorough and comprehensive. Although the present application is described in detail with reference to the aforementioned embodiments, for those skilled in the art, it is still possible to modify the technical solutions recorded in the aforementioned specific implementation methods, or to perform equivalent replacement of some of the technical features therein. Any equivalent structure made using the contents of the specification and drawings of this application, directly or indirectly used in other related technical fields, is similarly within the scope of patent protection of this application.
Claims
1. Construction method of equivalent DC topology of multi-level AC / DC hybrid power grid, It is characterized in that The following steps are involved: 1) Obtain multi-level AC / DC hybrid power grid data; 2) calculating the available transmission capacity of the selected provincial AC section for inter-provincial power trading based on the relevant multi-level AC / DC hybrid power grid data obtained in step 1); 3) The process topology is obtained by processing the equivalent DC of the provincial AC section, and the equivalent DC topology is constructed based on the process topology through the DC approximation of the AC subnet of the inter-provincial tie line; 4) Establish a real-time power trading model for maximizing the absorption of renewable energy under the constraints of equivalent DC stability limits; Based on the above equivalent DC topology, support the adaptation to the randomness and volatility of renewable energy output on multi-level AC / DC hybrid power grids, and quickly calculate and formulate transmission dispatch plans for maximizing the absorption of renewable energy in the western region under the constraints of safe operation of the power grid.
2. The method for constructing an equivalent DC topology of a multi-level AC / DC hybrid power grid according to claim 1, Features: The multi-level AC / DC hybrid power grid data obtained in step 1) includes the inter-provincial interconnection line AC / DC hybrid power grid topology, each provincial power grid topology, network association matrix and related parameters, and each provincial AC section available transmission capacity and power grid operation plan; the related parameters include branch resistance and reactance; the power grid operation plan includes the inter-provincial interconnection line day-ahead and / or day-in operation plan; wherein the AC power grid in each area is identified as a node.
3. The method for constructing an equivalent DC topology of a multi-level AC / DC hybrid power grid according to claim 1, Features: In step 3), the equivalent DC approximation of the AC subnet of the inter-provincial tie line includes the following steps: An AC subnet b of an inter-provincial tie line refers to the AC grid after deleting the DC tie line branches in the process topology, which includes the equivalent DC branches of all provincial sections; Let K be the set of nodes in the AC subnet b associated with the DC branch or associated with the power supply or load, and E be the set of branches connected to K in the process topology; E contains AC branches or DC branches; let E c is the commutative subset of E, E d is the DC subset of E; Each AC branch (j, k) of AC subnet b connects two nodes j and k. The absolute value of branch susceptance of AC branch (j, k) is y (ij) B is a diagonal element of y (ij) |E c ||E c |Diagonal matrix; Let A be the branch set E c and the association matrix of the power grid topology composed of the node set K, that is, A is a |E c | row| K | column matrix; the injection transfer distribution factor of the AC subnet is: S = NO (NO) -1 , Where A' is the transposed matrix of A; let A d is the branch set E d and the association matrix of the power grid topology composed of the node set K, A' d Yes A d The transposed matrix of c The trend of F d (t) is the DC branch set E d The power flow on the node set K is G k (t), the load vector is L k (t), according to the DC approximation method, the power flow on the AC branch is: F c (t)=S(A′ d F d (t)+G k (t)-L k (t)) (1)。 4. The method for constructing an equivalent DC topology of a multi-level AC / DC hybrid power grid according to claim 3, Features: In step 3), constructing the equivalent DC topology of the multi-level AC / DC hybrid power grid includes the following steps: For the equivalent DC branch set E of the provincial AC section a , whose available transmission capacity in time period t is ATC a (t), and its corresponding power flow is F a (t), its equivalent DC constraint is: -ATC a (t)≤F a (t)≤ATC a (t) (2); For the DC branch E of the inter-provincial AC / DC hybrid power grid d , whose available transmission capacity in time period t is ATC d (t), and its corresponding power flow F d (t), whose stability limit constraint is: -ATC d (t)≤F d (t)≤ATC d (t) (3); For the AC branch E of the inter-provincial AC / DC hybrid power grid c , whose available transmission capacity in time period t is ATC c (t), and its corresponding power flow F c (t), whose stability limit constraint is: -ATC c (t)≤F c (t)≤ATC c (t) (4); Substituting formula (1) into formula (4), we get: -ATC c (t)≤S(A′ d F d (t)+G k (t)-L k (t))≤ATC c (t) (5); Inequalities (2), (3) and (5) are the stability limit constraints of the equivalent DC topology of the multi-level AC / DC hybrid power grid, where the decision variables are only the power output vector G associated with the inter-provincial AC subgrid. k (t), load vector L k (t), equivalent DC power flow F at provincial AC section a (t) and inter-provincial power grid DC power flow F d (t), and the AC power flow of the inter-provincial AC / DC hybrid power grid no longer appears in the stability limit constraint of the equivalent DC topology of the multi-level AC / DC hybrid power grid.
5. The method for constructing an equivalent DC topology of a multi-level AC / DC hybrid power grid according to claim 4, Features: Step 4) specifically includes the following steps: G r (t) is the output of the new energy station r in period t, G g (t) is the output of other power sources except renewable energy, L(t) is the upper limit of the load for absorbing renewable energy, F d (t-1) is the DC power flow of the inter-provincial power grid in period t-1; To predict the upper limit of the output of new energy r in time period t, The output limit of other power sources other than renewable energy. To absorb the load of new energy or the upper limit of electricity purchase, ΔF d is the upper limit of DC ramping; the transmission dispatch plan to maximize the consumption of new energy in western China in period t is the output result of the following optimization model: Max∑ r G r (t) (6); The constraints satisfied are: Power output limit: Upper limit of load for absorbing new energy: DC branch climbing upper limit: -ΔF d ≤F d (t)-F d (t-1)≤ΔF d (9); The branch stability limit constraints are equations (2), (3) and (5).
6. The method for constructing an equivalent DC topology of a multi-level AC / DC hybrid power grid according to any one of claims 1 to 5 is implemented based on a construction system for an equivalent DC topology of a multi-level AC / DC hybrid power grid, Features: The construction system includes a data acquisition module, a process topology and equivalent DC topology generation module, and a maximum absorption model generation module for new energy; The data acquisition module is used to obtain multi-level AC / DC hybrid power grid data, including the inter-provincial interconnection line AC / DC hybrid power grid topology and parameters, each provincial AC section topology and parameters, and system operation section control requirements; The process topology and equivalent DC topology generation module is used to obtain the process topology by converting the provincial AC section power flow into DC according to the multi-level AC / DC hybrid power grid data; and to construct the equivalent DC topology based on the process topology through the inter-provincial tie line AC subnet power flow DC approximation; The maximum new energy consumption model generation module is used to generate a mathematical model for maximizing the consumption of new energy according to the equivalent DC topology and calculate the value and The AC and DC branches of the multi-level AC / DC hybrid power grid meet the power flow constraints of the stability limit safety. The power flow of the DC branch is subject to the DC ramp constraint.