Demolition method for large-span gantry crane in limited space

By dividing the gantry crane into five parts and disassembly according to the system steps, the difficulty and safety issues of large-span gantry crane removal in limited space are solved, and a more efficient and safe dismantling process is achieved.

CN118992848APending Publication Date: 2024-11-22CHINA RAILWAY FIRST GRP FIRST CONSTR CO LTD +2
View PDF 0 Cites 0 Cited by

Patent Information

Application Number
CN202411177359.6
Authority / Receiving Office
CN · China
Patent Type
Applications(China)
Current Assignee / Owner
Filing Date
2024-08-26
Publication Date
2024-11-22

AI Technical Summary

Technical Problem

In limited space, it is difficult to remove the gantry crane, especially due to its large span and space limitations in the construction bridge section, the demolition process is complicated and unsafe.

Method used

The gantry crane is removed into five parts: lifting mechanism, electrical equipment and wires and cables, trolley walking mechanism, legs and main beam, and is disassembled, packaged and stored one by one according to specific steps and processes, including on-site inspection, numbering, Fix the cable wind rope assembly, use a car crane for disassembly and lifting to ensure the stability and safety of each part.

Benefits of technology

By decomposing the disassembly process, the convenience and safety of the disassembly of the large-span gantry crane are improved, the complexity and risks of operation in limited space are reduced, and the safe and efficient disassembly of the equipment is ensured.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN118992848A_ABST
    Figure CN118992848A_ABST
Patent Text Reader

Abstract

The invention relates to the technical field of gantry crane dismantling methods, in particular to a limited-space large-span gantry crane dismantling method which comprises a gantry crane body, and the gantry crane body comprises a hoisting mechanism, electrical equipment, wires and cables, a trolley walking mechanism, supporting legs and a main beam. The dismantling method of the portal crane body comprises the following steps that S1, preparation before dismantling and on-site arrangement are conducted; s2, disassembling the lifting appliance of the hoisting mechanism; s3, disassembling the electrical equipment and the cable wire; s4, the trolley walking mechanism is disassembled; s5, the supporting legs are fixed; s6, the main beam is disassembled; s7, the supporting legs are disassembled; S8, the main beam and the supporting legs are disassembled on the ground; s9, the disassembled parts are packaged; and S10, loading and transporting to a storage place. The large-span gantry crane has the effect that the large-span gantry crane can be conveniently dismantled in a limited space.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The present application relates to the technical field of gantry crane dismantling methods, and in particular to a method for dismantling a large-span gantry crane in a limited space. Background Art

[0002] Gantry crane, also known as portal crane. Gantry crane is a common heavy lifting equipment, widely used in docks, cargo yards, construction sites and other places. Its structure is similar to a door frame, hence the name "gantry crane".

[0003] In the construction project of the co-linear double-deck bridge, which is about 2.815km long, the upper structure of the bridge adopts assembled prestressed concrete small box beams, which are simply supported first and then the bridge deck is continuous. The bridge piers adopt double-layer gantry piers and pile foundations. According to the geographical location, topography, bridge structure type, number of prefabricated beams and construction characteristics of the construction project, and in accordance with the principle of economy and practicality, a gantry crane is set up at piers 36# to 40# of the 1# super-large bridge for lifting prefabricated beams. The gantry crane track is 140m long, and the track foundation is set on both sides of the cap beam. The expanded foundation is adopted. The span of the beam lifting gantry crane is 30m and the height is 39m. It is used for the construction of prefabricated beams in this construction project, and the maximum lifting weight is about 100t. The lower bridge cap beam of pier 38# is completed first, and the upper bridge pier cap beam is not constructed for the time being to facilitate the gantry crane to lift the beam, and then the gantry crane is installed.

[0004] After a gantry crane completes its lifting task, it often needs to be dismantled. However, the gantry crane in a construction project has a large span and the space in the construction section is limited, so the dismantling of the gantry crane is difficult. Summary of the invention

[0005] In order to facilitate the dismantling of a large-span gantry crane in a limited space, the present application provides a method for dismantling a large-span gantry crane in a limited space.

[0006] This application provides a method for dismantling a large-span gantry crane in a limited space, which adopts the following technical solution: A method for dismantling a large-span gantry crane in a limited space, comprising a gantry crane body, the gantry crane body comprising a hoisting mechanism, electrical equipment and wires and cables, a trolley travel mechanism, legs and a main beam, and the method for dismantling the gantry crane body comprises the following steps: S1: Pre-dismantling preparation and on-site layout; S2: disassembling the lifting mechanism sling; S3: Dismantle electrical equipment and cables and wires; S4: disassembling the trolley travel mechanism; S5: Fixing the legs; S6: disassembling the main beam; S7: Disassembling the legs: S8: the main beam and the legs are disintegrated on the ground; S9: packaging disassembled parts; S10: Loading and transporting to storage location.

[0007] By adopting the above technical solution, the gantry crane body is divided into five parts, namely, the lifting mechanism, electrical equipment and wires and cables, the trolley traveling mechanism, the legs and the main beam. The five parts are disassembled, packaged and stored one by one in turn, which is conducive to improving the convenience of disassembling the large-span gantry crane.

[0008] Optionally, the pre-disassembly preparation in step S1 includes the following work: S1.1: On-site inspection, including inspection of the lifting point position, inspection of the lifting points of each component after removal, inspection of the placement of the removed components, etc.; S1.2: Check and remove all unsafe factors at the construction site. If there are any unsafe factors, demolition is not allowed. The demolition work can only be started after rectification is completed and the unsafe factors are eliminated; S1.3: Check the safety of wire ropes, hooks and other equipment used in each lifting operation; S1.4: Are all the demolition professionals in place? A dedicated person is required to give unified command during demolition. S1.5: Reasonably arrange the time for demolition work, and do not carry out demolition work in bad weather; S1.6: Before the gantry crane body is dismantled, ensure that the legs are always securely anchored. Anchorage inspections should be carried out after get off work on the same day and before dismantling the next day.

[0009] By adopting the above technical solution, before the gantry crane body is disassembled, all processes of the gantry crane body disassembly steps are reviewed and checked to improve the safety of the gantry crane body disassembly.

[0010] Optionally, step S3 further includes the following steps: S3.1: After the equipment is decommissioned, the components and electrical systems of the gantry crane body shall be numbered to avoid loss or confusion during dismantling and transportation operations; S3.2: Remove all types of lines arranged on the door crane.

[0011] By adopting the above technical solution, since the gantry crane body is a large-scale equipment with numerous cables and wires, numbering the components of the gantry crane body and the electrical system is conducive to improving the convenience of reassembly.

[0012] Optionally, step S4 also includes the following steps: S4.1: Install a 300t truck crane on the bridge; S4.2: The total weight of the trolley traveling mechanism is 5t. It uses 6*37w-24-1670 steel wire rope with a length of 5 meters and a quantity of 4. The steel wire rope is fixed to the lifting lug of the trolley traveling mechanism with a 9.5t shackle, and the trolley traveling mechanism is dismantled and transported with a 300t truck crane.

[0013] By adopting the above technical solution, the trolley traveling mechanism is first dismantled and lifted using a truck crane, which is beneficial to improving the safety of disassembly of the gantry crane body and improving the convenience of subsequent disassembly of the main beam.

[0014] Optionally, step S5 also includes the following steps: S5.1: Locking the trolley rail clamp at the position of the gantry crane body; S5.2: A first pull ear is fixed on both sides of the support leg, a second pull ear is fixed on the ground and the top surface of the pier respectively, and a guy rope assembly is provided between the first pull ear and the second pull ear for connection and fixation.

[0015] By adopting the above technical solution, the gantry crane body is first fixed at the current position, and then the legs are fixed to reinforce the structure of the gantry crane body, which is beneficial to improve the stability of the subsequent main beam disassembly of the gantry crane body.

[0016] Optionally, step S6 also includes the following steps: S6.1: Check the fixing of the guy rope assembly and adjust it in time if it is loose or under excessive force; S6.2: The 300t truck crane is stationed at the position during installation, and the hook of the 300t truck crane is connected to the hoisting wire rope of the main beam with a slight force. The crane operator and the truck crane operator are responsible for controlling the lifting force; S6.3: Release the connecting beam members of the main beam, and release the constraints such as flanges and pins between the main beam and the legs; S6.4: Lift the main beam to the ground and dismantle it.

[0017] By adopting the above technical solution, the reinforced cable wind rope assembly is first checked before the main beam is disassembled, and then the main beam is hoisted by a crane after the main beam is completely disassembled, which is beneficial to improve the stability of the main beam disassembly.

[0018] Optionally, step S7 further includes the following steps: S7.1: Check the anchorage of the guy rope assembly and make timely adjustments if it is found to be loose or under excessive stress; S7.2: 300t truck crane is in place, lifting points are set, and the hook is tightened; S7.3: The outrigger includes an upper outrigger section and a lower outrigger section. Use special tools to gradually remove the guy wire assembly of the upper outrigger section. The lifting force of the 300t truck crane is slightly increased. S7.4: All connections of the guy rope assembly on the upper section of the outrigger are released, and the lifting force of the crane is adjusted; S7.5: Use a 300t truck crane to lay the upper section of the outrigger flat on the bridge deck, disassemble and transport to the designated location; S7.6: Repeat the operations of step S7.1 to step S7.5 to remove the lower section of the leg.

[0019] By adopting the above technical solution, the disassembly of the legs is divided into an upper section and a lower section, thereby improving the convenience of disassembly of the legs.

[0020] Optionally, step S6.4 includes the following process: S6.4.1: Use 2 6×37w-38-1670 steel wire ropes with a length of 8 meters, and hang the steel wire ropes on the upper chord beam of the heaviest single main beam with a bag. Use a 300t truck crane as the main lifting equipment to dismantle and transport the trolley travel mechanism; S6.4.2: The 300t truck crane shall stand in the position during installation, and the steel wire rope and hook shall be tied on the main beam. Before lifting, the working position and operating radius of the crane shall be checked, the angle positions of the lifting points and the binding points of the main beam shall be checked, and all obstacles in the moving direction of the outriggers shall be cleared. During lifting, the crane shall be commanded by a dedicated person. After the lifting steel wire rope is tightened, the construction personnel shall enter the upper working platform of the outriggers and remove the connecting bolts between the main beam and the flange on the outriggers and the connecting rods of the end beams; S6.4.3: After the personnel leave, first lift the main beam away from the connection plane by at least 10cm, and observe it for 1-2 minutes. After checking and confirming that there is no abnormality, the crane will lift it. The command personnel and safety supervisors should observe closely to keep the entire main beam horizontal and lift it steadily. When the flange surface of the support of the main beam and the flange of the leg are lifted at least 500mm away from each other, the lifting will be stopped. The crane will adjust the boom angle until the main beam can avoid the leg and is in a safe falling position. The crane will drop the hook to lower the main beam and place the main beam on the sleepers on the bridge deck for dismantling. S6.4.4: Repeat steps S6.4.1-S6.4.3 to remove another main beam.

[0021] By adopting the above technical solution, the main beam is the component with the largest span of the gantry crane body. Through rigorous operation, it is helpful to improve the safety of disassembling the two main beams in sequence.

[0022] Optionally, the guy rope assembly includes a hand winch, a rope buckle, a guy rope body and a U-shaped ring, one end of the guy rope body is fixedly connected to the first pulling ear via the U-shaped ring, the other end of the guy rope body is fixedly connected to one end of the hand winch via the rope buckle, and the other end of the hand winch is fixedly connected to the second pulling ear.

[0023] By adopting the above technical solution, the first pull ear and the second pull ear are fixed by combining the hand winch with the cable wind rope body, and the tension of the cable wind rope body is adjusted by the hand winch, which is beneficial to improve the stability of the support leg fixation.

[0024] In summary, this application includes the following beneficial technical effects: The gantry crane body is divided into five parts, namely, the lifting mechanism, electrical equipment and wires and cables, the trolley traveling mechanism, the outriggers and the main beam. The five parts are disassembled, packaged and stored one by one in turn, which helps to improve the convenience of disassembling the large-span gantry crane. BRIEF DESCRIPTION OF THE DRAWINGS

[0025] Figure 1 It is a flowchart of the steps of the method for dismantling a large-span dragon store in the preferred space of this application; Figure 2 It is a plan view of the trolley mechanism dismantling and lifting of the present application; Figure 3 It is a schematic elevation diagram of the dismantling and hanging of the trolley mechanism of the present application; Figure 4 It is a schematic structural diagram of the cable wind rope assembly of the present application; Figure 5 It is a plan view of the main beam dismantling and lifting of the present application; Figure 6 It is a schematic elevation diagram of the main beam dismantling and hanging of this application; Figure 7 It is a plan view of the upper section of the outrigger being dismantled and lifted in the present application; Figure 8 It is a plan view of the dismantling and lifting of the lower section of the outrigger of the present application.

[0026] Explanation of the accompanying reference numerals: 1. gantry crane body; 2. lifting mechanism; 3. trolley traveling mechanism; 4. outrigger; 5. main beam; 6. truck crane; 7. first pulling ear; 8. second pulling ear; 9. hand chain hoist; 10. rope buckle; 11. guy rope body; 12. U-shaped ring; 13. upper section of outrigger; 14. lower section of outrigger. DETAILED DESCRIPTION

[0027] The following is combined with Figure 1-8 This application is described in further detail.

[0028] Example: See also Figure 1-Figure 3 A method for dismantling a large-span gantry crane in a limited space includes a gantry crane body 1, the model of the gantry crane body 1 is MG100 / 5t-30m, and the gantry crane body 1 includes a hoisting mechanism 2, electrical equipment and wires and cables, a trolley travel mechanism 3, legs 4 and a main beam 5. The method for dismantling the gantry crane body 1 includes the following steps: S1: Pre-dismantling preparation and on-site layout; S2: dismantle the lifting device used by the lifting mechanism 2; S3: Dismantle electrical equipment and cables and wires; S4: dismantle the trolley travel mechanism 3; S5: Reinforce the outrigger 4; S6: dismantle the two main beams 5 one by one; S7: Disassemble the outrigger 4: S8: dismantle the main beam 5 and the outrigger 4 on the ground; S9: The disassembled parts of the packaging; S10: Loading and transporting to storage location.

[0029] The gantry crane body 1 is divided into five parts, namely, a lifting mechanism 2, electrical equipment and wires and cables, a trolley travel mechanism 3, legs 4 and a main beam 5. When the gantry crane body 1 needs to be disassembled, the five parts are disassembled, packaged and stored one by one in turn.

[0030] Specifically, the pre-disassembly preparation in step S1 includes the following tasks: S1.1: On-site inspection, including inspection of the lifting point position, inspection of the lifting points of each component after removal, inspection of the placement of the removed components, etc.; S1.2: Check and remove all unsafe factors at the construction site. If there are any unsafe factors, demolition is not allowed. The demolition work can only be started after rectification is completed and the unsafe factors are eliminated; S1.3: Check the safety of wire ropes, hooks and other equipment used in each lifting operation; S1.4: Are all the demolition professionals in place? A dedicated person is required to give unified command during demolition. S1.5: Reasonably arrange the time for demolition work, and do not carry out demolition work in bad weather; S1.6: Before the gantry crane body 1 is dismantled, ensure that the outriggers 4 are always securely anchored. Anchorage checks should be carried out after get off work that day and before dismantling the next day.

[0031] Specifically, when performing step S3, the following steps need to be performed: S3.1: After the equipment is decommissioned, the components and electrical systems of the gantry crane body 1 shall be numbered to avoid loss or confusion during dismantling and transportation operations; S3.2: Remove all types of lines arranged on the door crane.

[0032] It should be noted that since electric shock and falling from heights are prone to occur during line removal operations, the power supply of the gantry crane body 1 should be removed first before starting the cable removal operation. At the same time, safety education and on-site supervision should be strengthened, and workers working at heights should wear non-slip shoes and wear safety belts.

[0033] For details, see Figure 2 and Figure 3 When performing step S4, the following steps are included: S4.1: Install a 300t truck crane 6 on the bridge; S4.2: The total weight of the trolley travel mechanism 3 is 5t. Now we use 6*37w-24-1670 steel wire rope, 5m long, 4 pieces. Fix the steel wire rope to the lifting lug of the trolley travel mechanism 3 with a 9.5t shackle, and use a 300t truck crane 6 to dismantle and transport the trolley travel mechanism 3. The operation method is as follows: S4.2.1: The lifting commander sends a lifting signal to lift the trolley of the trolley travel mechanism 3 300mm away from the trolley track, and suspend it for 3-5 minutes to check whether there are any abnormalities in the wire rope and the foundation. After the inspection is completed and confirmed to be normal, the lifting commander sends a lifting signal to command the mobile crane 6 to slowly and steadily lift the trolley. When the bottom surface of the trolley wheel exceeds the surface of the trolley track by about 500mm, the lifting is stopped. The ground lifting commander uses the intercom to instruct the mobile crane 6 to slowly rotate the boom to move the trolley to the vertical safety area and then slowly descend in the plane to place the trolley on the prepared sleepers; S4.2.2: After the lifting commander issues a hook removal signal, the truck crane 6 drops the hook and removes the lifting wire rope, shackles and other locks; S4.2.3: Remove and label other accessories separately and transport them to the storage location.

[0034] In the above operation methods, attention should be paid to lifting injuries that occur during hoisting, as well as workers working at heights falling from heights.

[0035] To this end, the lifting operation procedures must be strictly controlled, on-site supervision must be strengthened, and safety operating procedures must be followed during lifting operations. In addition, when removing the trolley and accessories, it is necessary to first clean up the debris that may fall from the hanging objects, and no one should stand under the hanging objects. At the same time, safety education and on-site supervision must be strengthened, and workers working at heights must wear non-slip shoes and wear safety belts.

[0036] For details, see Figure 3 and Figure 4 , step S5 includes the following process contents: S5.1: Deactivate the gantry crane body 1, select the current position of the gantry crane body 1 as the dismantling operation point, and then lock the trolley track clamp; S5.2: Fix the first pull ears 7 on both sides of the supporting leg 4, fix the second pull ears 8 on the ground and the top surface of the pier respectively, and set a cable wind rope assembly between the first pull ear 7 and the second pull ear 8 to connect and fix them.

[0037] It should be noted that improper installation of the wind rope assembly can easily lead to a great impact on the safety of the structural system during the subsequent removal of the main beam 5 and the outrigger 4, and can easily cause accidents such as collapse. Secondly, when installing the wind rope assembly, the operator will set a tie point at the top of the outrigger 4, so it is easy to fall when working at height. Thirdly, auxiliary machinery and tools will be used in conjunction with the installation of the wind rope assembly. Improper use of machinery and tools can easily lead to object impact and collapse accidents.

[0038] To this end, before starting construction, the temporary cable wind rope assembly must be specially calculated and reviewed, and the on-site technicians must check the on-site implementation to ensure that the mechanical force safety meets the requirements. Secondly, safety education and on-site supervision must be strengthened, and workers working at heights must wear non-slip shoes and wear safety belts. Thirdly, in the demolition work, intact machinery and equipment must be used, and it is forbidden to use machinery and equipment with defects.

[0039] For details, see Figure 4 The guy rope assembly includes a hand winch 9, a rope buckle 10, a guy rope body 11 and a U-shaped ring 12. One end of the guy rope body 11 is fixedly connected to the first pull ear 7 through the U-shaped ring 12, and the other end of the guy rope body 11 is fixedly connected to one end of the hand winch 9 through the rope buckle 10, and the other end of the hand winch 9 is fixedly connected to the second pull ear 8.

[0040] For details, see Figure 5 and Figure 6 , step S6 also includes the following steps: S6.1: Check the fixing of the guy rope assembly and adjust it in time if it is loose or under excessive force; S6.2: The 300t truck crane 6 stands at the position during installation, and the hook of the 300t truck crane 6 is connected to the hoisting wire rope of the main beam 5 with a slight force. The crane operator and the truck crane 6 operator are responsible for controlling the lifting force; S6.3: Release the connecting beam members of the main beam 5, and release the constraints such as flanges and pins between the main beam 5 and the legs 4; S6.4: hoist the main beam 5 to the ground for dismantling, wherein the process steps for hoisting the main beam 5 are as follows: S6.4.1: Use 2 6×37w-38-1670 steel wire ropes with a length of 8 meters, and hang the steel wire ropes on the upper chord beam of the heaviest single main beam 5 with a bag. Use a 300t truck crane 6 as the main lifting equipment to dismantle and transport the trolley travel mechanism 3; S6.4.2: The 300t truck crane 6 stands at the position during installation, and the steel wire rope and hook are tied on the main beam 5. Before lifting, the working position and operating radius of the crane must be checked, and the angle positions of the lifting points and the binding points of the main beam 5 must be checked. All obstacles in the moving direction of the outrigger 4 must be cleared. During lifting, the crane is commanded by a dedicated person in charge. After the lifting steel wire rope is tightened, the construction personnel enter the upper working platform of the outrigger 4 and remove the connecting bolts between the flange of the main beam 5 and the outrigger 4, and the end beam connecting rods; S6.4.3: After the personnel leave, lift the main beam 5 at least 10cm away from the connection plane, and observe it for 1-2 minutes. After checking and confirming that there is no abnormality, the crane will lift it. The command personnel and safety supervisors should observe closely to keep the entire main beam 5 horizontal and lift it steadily. When the flange surface of the support of the main beam 5 and the flange of the leg 4 are lifted at least 500mm away from the height, stop lifting. The crane adjusts the boom angle until the main beam 5 can avoid the leg 4 and is in a safe falling position. The crane drops the hook to lower the main beam 5 and place the main beam 5 on the sleepers on the bridge deck for dismantling. S6.4.4: Repeat steps S6.4.1 to S6.4.3 to remove another main beam 5.

[0041] It should be noted that improper crane settings, improper use of slings, insufficient load-bearing capacity of cable wind rope components, etc. can easily lead to lifting injuries and collapse, and should be focused on. In addition, it should be noted that workers working at heights are prone to falling from heights during work.

[0042] To this end, the selection and layout of the crane should be designed and verified before demolition, and the on-site technicians and crane operators should control the on-site operation. Secondly, the setting of the cable wind rope assembly must be checked and confirmed before starting the demolition operation, and the subsequent demolition operation can only be carried out after the cable wind rope assembly is adjusted. Thirdly, the force applied by the crane hook before the main beam 5 is separated from the outrigger 4 should not be too large to avoid shaking when the main beam 5 is separated from the outrigger 4. Thirdly, strengthen safety education and on-site supervision, and workers at heights should wear non-slip shoes and wear safety belts. When the main beam 5 is separated from the outrigger 4, the cooperating personnel should stand firmly and hold on, or go down to the ground. Thirdly, when the operator at the connection between the main beam 5 and the outrigger 4 confirms that the main beam 5 and the outrigger 4 have been separated, the lifting commander and the crane operator should control the hook speed and load step by step to avoid lifting injuries and collapse caused by the incomplete release of the connection constraints between the main beam 5 and the outrigger 4. Once again, after the main beam 5 is fully hoisted to the ground, the cable wind rope assembly of the outrigger 4 should be checked immediately, and any looseness or excessive stress should be adjusted in time.

[0043] For details, see Figure 7 and Figure 8 , step S7 also includes the following steps: S7.1: Check the anchorage of the guy rope assembly and make timely adjustments if it is found to be loose or under excessive stress; S7.2: 300t truck crane 6 is in place, the lifting points are set, and the hook is tightened; S7.3: The outrigger 4 includes an upper outrigger section 13 and a lower outrigger section 14. Use special tools to gradually remove the guy wire assembly of the upper outrigger section 13. The lifting force of the 300t truck crane 6 is slightly increased. S7.4: All connections of the guy rope assembly of the upper leg 13 are released, and the crane lifting force is adjusted; S7.5: Use a 300t truck crane 6 to lay the upper section 13 of the outrigger flat on the bridge deck, disassemble and transport it to the designated location; S7.6: Repeat the operations of step S7.1 to step S7.5 to remove the lower section 14 of the support leg.

[0044] It should be noted that insufficient bearing capacity of the cable wind rope assembly and unbalanced tensioning force can easily lead to collapse. In addition, if the car crane is improperly positioned, the slings are improperly used, and the lifting force is improperly set, it is easy to cause lifting injuries and collapse.

[0045] To this end, first of all, the selection and layout of the crane should be designed and verified before dismantling, and the on-site technicians and crane operators should control it during the on-site operation. Secondly, the setting of the cable wind rope assembly must be checked and confirmed before starting the dismantling operation, and the subsequent dismantling operation can only be carried out after the cable wind rope assembly is adjusted. Thirdly, the lifting force should not be too large when the crane is connected to the outrigger 4 for the first time to avoid affecting the stability of the cable wind rope assembly. The lifting direction of the hook must be vertical, and the on-site crane operator must adjust and confirm repeatedly. Thirdly, the crane hook should respond to the force during the gradual loosening of the cable wind rope assembly to avoid the overturning of the outrigger 4. Thirdly, after the cable wind rope assembly is completely released, the hand chain hoist 9 and the cable wind rope body 11 should be released. Thirdly, when the connection between the outrigger 4 and the platform is released, the hook should be slowly raised and lowered to ensure that the hook is not overloaded. Thirdly, when the outrigger 4 is lowered, it should be noted that it should not collide with the cable wind rope assembly of the outrigger 4 on the other side, and no one should stand at both ends of the outrigger 4 when it is lowered.

[0046] To sum up, when the gantry crane body 1 needs to be disassembled, the lifting mechanism 2, electrical equipment and wires and cables, trolley traveling mechanism 3, legs 4 and main beam 5 are disassembled, packaged and stored one by one in turn, which is conducive to improving the convenience of disassembling the large-span gantry crane in a limited space.

[0047] The above are all preferred embodiments of the present application, and the protection scope of the present application is not limited thereto. Therefore, any equivalent changes made according to the structure, shape, and principle of the present application should be included in the protection scope of the present application.

Claims

1. A method for dismantling a large-span gantry crane in a limited space, comprising a gantry crane body (1), characterized in that: The gantry crane body (1) comprises a lifting mechanism (2), electrical equipment and wires and cables, a trolley travel mechanism (3), legs (4) and a main beam (5). The method for dismantling the gantry crane body (1) comprises the following steps: S1: Pre-dismantling preparation and on-site layout; S2: disassembling the lifting device of the lifting mechanism (2); S3: Dismantle electrical equipment and cables and wires; S4: disassembling the trolley travel mechanism (3); S5: Fixing the supporting leg (4); S6: disassembling the main beam (5); S7: Disassembling the supporting leg (4): S8: the main beam (5) and the supporting legs (4) are disassembled on the ground; S9: packaging disassembled parts; S10: Loading and transporting to storage location.

2. A method for dismantling a large-span gantry crane in a limited space according to claim 1, characterized in that: The pre-disassembly preparation in step S1 includes the following tasks: S1.1: On-site inspection, including inspection of the lifting point position, inspection of the lifting points of each component after removal, inspection of the placement of the removed components, etc.; S1.2: Check and remove all unsafe factors at the construction site. If there are any unsafe factors, demolition is not allowed. The demolition work can only be started after rectification is completed and the unsafe factors are eliminated; S1.3: Check the safety of wire ropes, hooks and other equipment used in each lifting operation; S1.4: Are all the demolition professionals in place? A dedicated person is required to give unified command during demolition. S1.5: Reasonably arrange the time for demolition work, and do not carry out demolition work in bad weather; S1.6: Before the gantry crane body (1) is dismantled, it is necessary to ensure that the legs (4) are always securely anchored. An anchorage inspection should be carried out after get off work on the same day and before dismantling the next day.

3. A method for dismantling a large-span gantry crane in a limited space according to claim 1, characterized in that: Step S3 also includes the following steps: S3.1: After the equipment is decommissioned, the components and electrical system of the gantry crane body (1) are numbered to avoid loss or confusion during dismantling and transportation operations; S3.2: Remove all types of lines arranged on the door crane.

4. A method for dismantling a large-span gantry crane in a limited space according to claim 1, characterized in that: Step S4 also includes the following steps: S4.1: Install a 300t truck crane (6) on the bridge; S4.2: The total weight of the trolley traveling mechanism (3) is 5 t. It uses 6*37w-24-1670 steel wire ropes with a length of 5 meters and a quantity of 4. The steel wire ropes are fixed to the lifting lugs of the trolley traveling mechanism (3) with 9.5 t shackles, and the trolley traveling mechanism (3) is dismantled and transported with a 300 t truck crane (6).

5. The method for dismantling a large-span gantry crane in a limited space according to claim 1, characterized in that: Step S5 also includes the following steps: S5.1: Locking the trolley rail clamp at the position of the gantry crane body (1); S5.2: A first pull ear (7) is fixed on both sides of the support leg (4), a second pull ear (8) is fixed on the ground and the top surface of the pier respectively, and a guy rope assembly is provided between the first pull ear (7) and the second pull ear (8) to connect and fix them.

6. A method for dismantling a large-span gantry crane in a limited space according to claim 5, characterized in that: Step S6 also includes the following steps: S6.1: Check the fixing of the guy rope assembly and adjust it in time if it is loose or under excessive force; S6.2: The 300t truck crane (6) is positioned according to the installation position, and the hook of the 300t truck crane (6) is connected to the lifting wire rope of the main beam (5) with a slight force, and the crane operator and the truck crane (6) operator are responsible for controlling the lifting force; S6.3: Release the connecting beam member of the main beam (5), and release the constraints such as flanges and pins between the main beam (5) and the supporting legs (4); S6.4: Lift the main beam (5) to the ground and dismantle it.

7. The method for dismantling a large-span gantry crane in a limited space according to claim 1, characterized in that: Step S7 also includes the following steps: S7.1: Check the anchorage of the guy rope assembly and make timely adjustments if it is loose or under excessive stress; S7.2: The 300t truck crane (6) is in place, the lifting points are set, and the hook is tightened; S7.3: The outrigger (4) comprises an upper outrigger section (13) and a lower outrigger section (14). The guy rope assembly of the upper outrigger section (13) is gradually removed using a special tool, and the lifting force of the 300t truck crane (6) is slightly increased; S7.4: All connections of the guy rope assembly of the upper leg section (13) are released, and the lifting force of the crane is adjusted; S7.5: Use a 300t truck crane (6) to lay the upper section of the outrigger (13) flat on the bridge deck, disassemble and transport it to a designated location; S7.6: Repeat the operations of step S7.1 to step S7.5 to remove the lower section of the leg (14).

8. The method for dismantling a large-span gantry crane in a limited space according to claim 6, characterized in that: Step S6.4 includes the following process: S6.4.1: Use 2 6×37w-38-1670 steel wire ropes with a length of 8 meters, and hang the steel wire ropes on the upper chord beam of the heaviest single main beam (5) with a bag. Use a 300t truck crane (6) as the main lifting equipment to dismantle and transport the trolley travel mechanism (3); S6.4.2: The 300t truck crane (6) shall stand at the position during installation, and tie the steel wire rope and hook on the main beam (5). Before the 300t truck crane (6) is lifted, the working position and operating radius of the crane shall be checked, the angle positions of the lifting points and the binding points of the main beam (5) shall be checked, and all obstacles in the moving direction of the outrigger (4) shall be removed. During lifting, the crane shall be commanded by a dedicated person. After the lifting steel wire rope is tightened, the construction personnel shall enter the upper working platform of the outrigger (4) and remove the connecting bolts between the main beam (5) and the upper flange of the outrigger (4) and the end beam connecting rods; S6.4.3: After the personnel leave, first lift the main beam (5) away from the connection plane by at least 10 cm, and observe it for 1-2 minutes. After checking and confirming that there is no abnormality, the crane will lift it. The command personnel and safety monitoring personnel should observe closely to keep the entire main beam (5) horizontal and lift it steadily. When the flange surface of the support of the main beam (5) and the flange of the support leg (4) are lifted at least 500 mm away from each other, the lifting is stopped. The crane adjusts the boom angle until the main beam (5) can avoid the support leg (4) and is in a safe falling position. The crane drops the hook to lower the main beam (5), and the main beam (5) is placed on the sleepers on the bridge deck for dismantling; S6.4.4: Repeat steps S6.4.1 to S6.4.3 to remove another main beam (5).

9. The method for dismantling a large-span gantry crane in a limited space according to claim 5, characterized in that: The guy rope assembly comprises a hand chain hoist (9), a rope buckle (10), a guy rope body (11) and a U-shaped ring (12); one end of the guy rope body (11) is fixedly connected to the first pull ear (7) via the U-shaped ring (12); the other end of the guy rope body (11) is fixedly connected to one end of the hand chain hoist (9) via the rope buckle (10); and the other end of the hand chain hoist (9) is fixedly connected to the second pull ear (8).