Project risk assessment method, system and equipment and storage medium

By decomposing the engineering project into sub-projects, a progress and risk assessment model is established, data management and manual judgment error problems in engineering project risk assessment are solved, and more accurate risk assessment and fund calculation are achieved.

CN119005684AInactive Publication Date: 2024-11-22广东信仕德建设项目管理有限公司

Patent Information

Application Number
CN202411023799.6
Authority / Receiving Office
CN · China
Patent Type
Applications(China)
Current Assignee / Owner
Filing Date
2024-07-29
Publication Date
2024-11-22
Estimated Expiration
Not applicable · inactive patent

AI Technical Summary

Technical Problem

Engineering project risk assessment faces problems such as inadequate data management, difficulty in data mining and large errors in manual judgment, resulting in inaccurate evaluation results.

Method used

By obtaining the project structure of the project, decomposing it into sub-projects, obtaining progress data and progress influencing factor data, establishing a progress prediction model, obtaining the price trend curve of manpower and raw materials, determining the capital calculation results, and entering the project risk assessment model to output Risk index.

Benefits of technology

It achieves a more accurate assessment of the risks of engineering projects, overcomes the manual judgment errors caused by large data volume and complex relationships, improves the accuracy of progress prediction and fund calculation, and avoids the limitations of manual empirical judgment.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN119005684A_ABST
    Figure CN119005684A_ABST
Patent Text Reader

Abstract

The invention provides a project risk assessment method, system and device and a storage medium, and relates to the technical field of engineering. The method comprises the steps of obtaining a project structure of an engineering project, and decomposing the engineering project into a plurality of sub-projects according to the project structure; obtaining project progress data of a plurality of sub-projects and progress influence factor data of each sub-project, and inputting the project progress data of the sub-projects and the progress influence factor data of each sub-project into a preset progress prediction model to obtain a project period of each sub-project; obtaining a human price trend curve and a raw material price trend curve, and determining a project fund calculation result according to the project period of each sub-project, the human price trend curve, the raw material price trend curve and the manpower condition and the raw material correspondingly required by each sub-project; and inputting the project fund calculation result into the preset project risk assessment model, and outputting the project risk index, so that the engineering project risk can be assessed more accurately.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The present application relates to the field of engineering, and specifically to a project risk assessment method, system, equipment and storage medium. Background Art

[0002] Project risk assessment is a very important link in various industries. It can assess the risk status of engineering projects and provide important support for project decision-making. However, in practice, project risk assessment faces many difficulties and challenges.

[0003] First, inadequate data management is an important problem faced by engineering project risk assessment. Engineering projects involve a large amount of data, including engineering progress, engineering quality, personnel management, financial management and other aspects. However, due to the scattered data sources, inconsistent data formats, and uneven data quality, data management becomes very difficult. Secondly, data mining difficulties are another difficulty in engineering project risk assessment. The amount of data in engineering projects is huge, and there are various complex relationships between the data. How to extract effective information from these data and discover potential laws has become an important issue in engineering project risk assessment. Finally, large errors in manual judgment are also a difficulty faced by engineering project risk assessment. Due to the large amount of data and the complex relationships between data, traditional manual judgment methods are prone to misjudgment, resulting in inaccurate evaluation results and bringing risks to project decision-making. Summary of the invention

[0004] The present application provides a project risk assessment method, system, device and storage medium, which can more accurately assess the risks of engineering projects.

[0005] In a first aspect, the present application provides a project risk assessment method, the method comprising: Obtain the project structure of the engineering project, and decompose the engineering project into several sub-projects according to the project structure; Obtain project progress data of several subprojects and progress influencing factor data of each subproject, and input the project progress data of the subprojects and the progress influencing factor data of each subproject into a preset progress prediction model to obtain the engineering cycle of each subproject; Obtain the labor price trend curve and raw material price trend curve, and determine the project fund estimation result according to the engineering cycle of each sub-project, the labor price trend curve, the raw material price trend curve and the corresponding labor and raw materials required for each sub-project; Input the project funding calculation results into the preset project risk assessment model and output the project risk index.

[0006] By adopting the above technical solution, the project structure of the engineering project is obtained and the engineering project is decomposed into multiple sub-projects according to the structure, so that the components of the project can be more clearly understood, which is conducive to the subsequent independent analysis of each sub-project and improves the pertinence of the analysis. The progress data and progress influencing factor data of each sub-project are obtained, and the preset progress prediction model is input to predict the engineering cycle of the sub-project. The artificial intelligence technology can be fully utilized to establish an accurate progress prediction model suitable for specific projects, overcome the manual judgment errors caused by large data volume and complex relationships, and improve the prediction accuracy of the engineering cycle of the sub-project. Further obtain the price trend curve of manpower and raw materials, determine the project fund calculation result according to the engineering cycle, price trend curve of the sub-project, and the demand for manpower and raw materials of the sub-project, and comprehensively consider the impact of multiple factors on the project cost, so that the fund calculation result is more accurate. Finally, the fund calculation result is input into the preset project risk assessment model to output the risk index. By establishing a risk assessment model suitable for a specific project, the limitations of manual experience judgment can be avoided, and the risk of the engineering project can be more accurately assessed.

[0007] Optionally, obtain a preset progress forecast model, including: Obtain sub-project indicators of several sub-projects, and build an engineering project indicator system based on the sub-project indicator data; Construct a progress prediction model based on the engineering project indicator system; Inputting the preset project progress sample data into the progress prediction model, and training the progress prediction model based on the preset project progress sample data; When the risk assessment value accuracy reaches the preset assessment value accuracy, the preset progress prediction model is obtained.

[0008] By adopting the above technical scheme, obtaining the sub-project indicators of several sub-projects and constructing the engineering project indicator system based on these indicator data, an indicator system suitable for specific engineering projects can be established to improve the comprehensiveness and pertinence of the indicators. Further constructing a progress prediction model based on the constructed engineering project indicator system can make the prediction model fully reflect the actual situation of the project. Input the preset project progress sample data into the constructed progress prediction model and perform model training to achieve the preset evaluation value accuracy, so that the parameters of the model can be optimized by sample data to improve the prediction accuracy of the model. During the training process, when the model prediction result meets the preset evaluation accuracy, a better preset progress prediction model can be obtained. By constructing an indicator system suitable for specific engineering projects and a progress prediction model obtained by training, the engineering cycle of each sub-project can be predicted more accurately, providing a solid foundation for subsequent project risk assessment. In short, this method realizes accurate prediction of project progress by constructing an indicator system for specific projects and training a prediction model, overcoming the problem of prediction errors caused by relying on manual experience in the past.

[0009] Optionally, obtain sub-project indicators of several sub-projects, and build an engineering project indicator system based on the sub-project indicator data, including: Determine the project indicators of each sub-project according to each sub-project; Construct an engineering project indicator system based on the project indicators of sub-projects.

[0010] By adopting the above technical scheme, the corresponding sub-project indicators are determined according to each sub-project, so that the sub-project indicators can be more in line with the actual situation and characteristics of each sub-project, and the pertinence of the indicators can be improved. On this basis, the overall indicator system of the engineering project is further constructed based on the project indicators of each sub-project, which can comprehensively reflect all aspects of the engineering project. Constructing highly targeted sub-project indicators and an overall engineering project indicator system is conducive to comprehensively reflecting the detailed information of the project from multiple dimensions and levels, and laying a solid foundation for the subsequent use of this indicator system to establish a prediction model. By determining the indicators according to the sub-projects and then constructing the project indicator system, the constructed prediction model can be closer to the actual situation of the engineering project, and the accuracy of the model prediction can be effectively improved. In short, this method can overcome the prediction deviation problem caused by the disconnection between the indicator system and the actual project situation by constructing the project indicator system starting from the sub-project indicators, and realize accurate prediction of the project progress.

[0011] Optionally, the project fund calculation results are determined based on the engineering cycle of each sub-project, the labor price trend curve, the raw material price trend curve, and the labor and raw materials required for each sub-project, including: Determine the human resources and funds for each sub-project based on the engineering cycle of each sub-project, the human resources required for each sub-project, and the human resource price trend curve; Determine the raw material funds for each sub-project based on the engineering cycle of each sub-project, the raw materials required for each sub-project, and the raw material price trend curve; Determine the project funding calculation results based on the raw material funds and human resources funds of each sub-project.

[0012] By adopting the above technical solution, according to the engineering cycle of each sub-project and its corresponding required manpower situation and manpower price trend curve, the manpower capital demand of each sub-project during the engineering cycle can be accurately calculated, taking into account the characteristics of the sub-project itself and the trend of changes in manpower costs, and the calculation results are more accurate. According to the engineering cycle of each sub-project, the required raw materials situation and the raw material price trend curve, the impact of raw material demand and price changes on the cost of the sub-project can be fully considered, and the raw material capital demand of each sub-project can be accurately calculated. After determining the manpower capital and raw material capital of each sub-project, the overall capital calculation results of the engineering project can be obtained by summarizing them as a whole. This method of analyzing the manpower and material demand of each sub-project, combining the relevant price trends to determine the funds of each sub-project, and then summarizing the global capital calculation method can more comprehensively and accurately reflect the overall capital demand of the project, overcome the errors caused by simple summing or relying on experience judgment, and provide a more reliable basis for capital calculation for subsequent risk assessment.

[0013] Optionally, the method further includes: Get the loss type of each sub-item; According to the loss type, determine the time loss cost and financial loss cost of each type; Adjust the capital calculation results based on time loss cost and capital loss cost.

[0014] By adopting the above technical means to obtain the loss type of each sub-project, the specific loss situation that may occur in the implementation of each sub-project can be clarified. According to different loss types, the corresponding time loss cost and capital loss cost can be determined, and the impact of various types of losses on the project can be quantified, making the analysis of the impact of losses on project costs more specific and accurate. After determining the time and capital costs of various types of losses, the preliminary capital estimation results of the project are adjusted by these loss costs, so that the project capital estimation can better reflect the cost impact that various types of losses may bring, and the evaluation results are more accurate. This method of clarifying the loss type and quantifying its impact on the project cost can avoid simply relying on experience to judge the loss cost, so that the project capital estimation has a clear prediction of various possible losses, and provides a reference for subsequent project risk control. In short, this method realizes the loss adjustment of the preliminary capital estimation results by analyzing the loss type of sub-projects and quantifying the loss cost, making the final estimation more accurate and comprehensive.

[0015] Optionally, the method further includes: Determine the overdue liquidated damages for each sub-project based on the engineering cycle and contract cycle of each sub-project, and adjust the funding calculation results based on the overdue liquidated damages.

[0016] By adopting the above technical solution, it is possible to determine whether a subproject may be overdue based on the comparison of the engineering cycle and contract cycle of each subproject, and to quantify the liquidated damages losses caused by overdue. After determining the possible overdue liquidated damages for each subproject, the liquidated damages cost is included in the capital calculation, so that the calculation results can more comprehensively reflect the possible cost expenditures of the project. This method of assessing overdue risks based on the subproject schedule and agreed period, and adjusting the capital calculation through the liquidated damages cost, can, on the one hand, spur each subproject unit to speed up the project progress, and on the other hand, enable the project capital calculation to take into account the increased liquidated damages costs caused by overdue, and the evaluation results are more reasonable. By quantifying the impact of overdue liquidated damages on capital calculation, errors caused by relying on experience judgment can be avoided, and an economic lever can be provided for project risk prevention. In short, this method achieves a more comprehensive and accurate project cost calculation by considering the adjustment effect of overdue liquidated damages on capital calculation.

[0017] Optional, data on factors affecting the progress of each sub-project, including: Weather factor data, personnel impact data and material progress impact data.

[0018] By adopting the above technical solution, the data on factors affecting the progress of subprojects including weather factors, personnel factors and material factors can be comprehensively considered from multiple dimensions to comprehensively consider various factors that may affect the progress of subprojects. Among them, considering weather factor data can evaluate the delay of bad weather on the construction period; considering personnel factors can evaluate the impact of staffing, efficiency, etc. on the progress; considering material factors can evaluate the impact of material supply on the construction period. These factors affecting the progress of subprojects can well reflect the actual situation of the engineering project and serve as model input for in-depth analysis. By considering multiple aspects of progress influencing factor data, the progress prediction model can evaluate the impact of various complex factors, overcome the prediction deviation caused by relying only on a single or local factor, and achieve a comprehensive and accurate prediction of the progress of subprojects, providing a solid foundation for subsequent engineering project risk assessment.

[0019] In a second aspect of the present application, a project risk assessment method system is provided, comprising: The project splitting module is used to obtain the project structure of the engineering project and decompose the engineering project into several sub-projects according to the project structure; A data acquisition module is used to acquire the project progress data of several sub-projects and the progress influencing factor data of each sub-project, and input the project progress data of the sub-projects and the progress influencing factor data of each sub-project into a preset progress prediction model to obtain the engineering cycle of each sub-project; The capital calculation module is used to obtain the labor price trend curve and the raw material price trend curve, and determine the project capital calculation result according to the engineering cycle of each sub-project, the labor price trend curve, the raw material price trend curve and the corresponding labor situation and raw materials required for each sub-project; The project risk prediction module is used to input the project fund calculation results into the preset project risk assessment model and output the project risk index.

[0020] In a third aspect of the present application, a computer storage medium is provided, wherein the computer storage medium stores a plurality of instructions, and the instructions are suitable for being loaded by a processor and executing the above method steps.

[0021] In the fourth aspect of the present application, an electronic device is provided, including a processor, a memory, a user interface and a network interface, the memory is used to store instructions, the user interface and the network interface are used to communicate with other devices, and the processor is used to execute the instructions stored in the memory so that the electronic device executes the above method.

[0022] In summary, one or more technical solutions provided in the embodiments of the present application have at least the following technical effects or advantages: 1. This application can more clearly understand the components of the project by obtaining the project structure of the engineering project and decomposing the engineering project into multiple sub-projects according to the structure, which is conducive to the subsequent independent analysis of each sub-project and improves the pertinence of the analysis. Obtain the progress data and progress influencing factor data of each sub-project, input the preset progress prediction model to predict the sub-project engineering cycle, and make full use of artificial intelligence technology to establish an accurate progress prediction model suitable for specific projects, overcome the manual judgment errors caused by large data volume and complex relationships, and improve the prediction accuracy of the sub-project engineering cycle. Further obtain the price trend curve of manpower and raw materials, determine the project fund calculation results according to the sub-project engineering cycle, price trend curve, and sub-project manpower and raw material demand, and comprehensively consider the impact of multiple factors on project costs, so that the fund calculation results are more accurate. Finally, the fund calculation results are input into the preset project risk assessment model to output the risk index. By establishing a risk assessment model suitable for a specific project, the limitations of manual experience judgment can be avoided, and the risk of the engineering project can be more accurately assessed.

[0023] 2. This application can establish an index system suitable for specific engineering projects by obtaining sub-project indicators of several sub-projects and constructing an engineering project index system based on these index data, thereby improving the comprehensiveness and pertinence of the indicators. Further constructing a progress prediction model based on the constructed engineering project index system can make the prediction model fully reflect the actual situation of the project. Input the preset project progress sample data into the constructed progress prediction model and perform model training to achieve the preset evaluation value accuracy, so that the parameters of the model can be optimized through sample data to improve the prediction accuracy of the model. During the training process, a better preset progress prediction model can be obtained when the model prediction result meets the preset evaluation accuracy. By constructing an index system suitable for specific engineering projects and a progress prediction model obtained through training, the engineering cycle of each sub-project can be predicted more accurately, providing a solid foundation for subsequent project risk assessment. In short, this method achieves accurate prediction of project progress by constructing an index system for specific projects and training prediction models, overcoming the problem of prediction errors caused by relying on manual experience in the past.

[0024] 3. This application determines the corresponding sub-project indicators according to each sub-project, which can make the sub-project indicators more in line with the actual situation and characteristics of each sub-project and improve the pertinence of the indicators. On this basis, the overall indicator system of the engineering project is further constructed based on the project indicators of each sub-project, which can comprehensively reflect the various aspects of the engineering project. Constructing sub-project indicators with strong pertinence and an overall engineering project indicator system is conducive to comprehensively reflecting the detailed information of the project from multiple dimensions and levels, and laying a solid foundation for the subsequent use of this indicator system to establish a prediction model. By determining the indicators according to the sub-projects and then constructing the project indicator system, the constructed prediction model can be closer to the actual situation of the engineering project, and the accuracy of the model prediction can be effectively improved. In short, this method can overcome the prediction deviation problem caused by the disconnection between the indicator system and the actual project situation by constructing a project indicator system starting from the sub-project indicators, and realize accurate prediction of the project progress. BRIEF DESCRIPTION OF THE DRAWINGS

[0025] Figure 1 A schematic diagram of a project risk assessment method provided in an embodiment of the present application; Figure 2 An architectural diagram of a project risk assessment system provided in an embodiment of the present application; Figure 3 A schematic diagram of the structure of an electronic device provided in this application. DETAILED DESCRIPTION

[0026] In order to enable technicians in this field to better understand the technical solutions in this specification, the technical solutions in the embodiments of this specification will be clearly and completely described below in conjunction with the drawings in the embodiments of this specification. Obviously, the described embodiments are only part of the embodiments of this application, not all of the embodiments.

[0027] In the description of the embodiments of the present application, words such as "for example" or "for example" are used to indicate examples, illustrations or explanations. Any embodiment or design described as "for example" or "for example" in the embodiments of the present application should not be interpreted as being more preferred or more advantageous than other embodiments or designs. Specifically, the use of words such as "for example" or "for example" is intended to present related concepts in a specific way.

[0028] In the description of the embodiments of the present application, the meaning of the term "multiple" refers to two or more. For example, multiple systems refer to two or more systems, and multiple screen terminals refer to two or more screen terminals. In addition, the terms "first" and "second" are used for descriptive purposes only and cannot be understood as indicating or implying relative importance or implicitly indicating the indicated technical features. Thus, the features defined as "first" and "second" may explicitly or implicitly include one or more of the features. The terms "include", "comprise", "have" and their variations all mean "including but not limited to", unless otherwise specifically emphasized.

[0029] In order to facilitate understanding of the method and system provided by the embodiments of the present application, before introducing the embodiments of the present application, the background of the embodiments of the present application is first introduced.

[0030] Project risk assessment is an important part of project management. It can identify potential risks of projects in advance and provide support for project decision-making. However, in actual operation, there are many problems in project risk assessment that need to be solved. First, the integrated management of massive multi-source heterogeneous data is the bottleneck of project risk assessment. The data formats and quality of different stages and aspects are different, which brings great difficulties to the regularization of data. Secondly, in the big data environment, the lack of ability to extract valuable information is also the crux of project risk assessment. In addition, relying on manual experience for risk judgment is prone to large errors and cannot make accurate risk warnings. Therefore, how to achieve efficient integrated management of project data throughout the life cycle, and use intelligent algorithms for deep mining, replace subjective experience judgment, release data value, and realize accurate assessment and warning of project risks is a difficult problem that needs to be solved in project risk management, and it is also an important direction to further improve the level of project management.

[0031] After the background introduction of the above content, those skilled in the art can understand the problems existing in the prior art. The technical solutions in the embodiments of the present application will be clearly and completely described below in conjunction with the drawings in the embodiments of the present application. Obviously, the described embodiments are only part of the embodiments of the present application, not all of the embodiments.

[0032] Based on the above background technology, please refer to Figure 1 , Figure 1 A flowchart of a project risk assessment method provided in an embodiment of the present application. The system can be implemented by a computer program or can be run as an independent tool application. Specifically, in an embodiment of the present application, the method can be applied on a server, but can also be applied on electronic devices such as a server. A project risk assessment method includes the following steps: S101, obtaining a project structure of the engineering project, and decomposing the engineering project into a plurality of sub-projects according to the project structure; Specifically, obtaining the project structure of the engineering project and decomposing the engineering project into multiple sub-projects according to the project structure is an important first step in achieving accurate risk assessment. For complex engineering projects, the project structure may involve multiple subsystems, equipment, process flows, etc. If the overall project is directly risk assessed without structural decomposition, it will be difficult to conduct targeted analysis of each specific aspect, resulting in incomplete assessment results. In specific implementation, tools such as Gantt charts can be used to analyze project plans and processes, clarify the deliverables of each stage, and gain insight into the hierarchical structure of the project; you can also refer to the structured experience of similar projects to divide the project into several relatively independent sub-projects or work packages. In this way, the entire large project is decomposed into multiple small manageable units. After obtaining the project structure and sub-project division, independent risk identification and assessment of each sub-project, and then integrating it into the overall risk results of the project, can significantly improve the meticulousness and accuracy of risk analysis, making the risk assessment results more comprehensive and reliable.

[0033] S102, obtaining project progress data of several subprojects and progress influencing factor data of each subproject, and inputting the project progress data of the subprojects and the progress influencing factor data of each subproject into a preset progress prediction model to obtain the engineering period of each subproject; Specifically, obtaining the progress data and influencing factor data of the subproject and inputting them into the progress prediction model to predict the engineering cycle of the subproject is a key step in conducting accurate risk assessment. In complex engineering projects, any delay in the progress of a subproject may affect the final delivery period. Traditionally, it is difficult to fully consider various influencing factors when predicting the progress of subprojects based on manual experience, resulting in inaccurate progress assessment. In specific implementation, the progress execution data of subprojects, such as planned progress, actual progress, and progress deviation, can be collected through the progress management system; at the same time, data on various factors affecting the progress, such as material progress and labor conditions, can be collected. These structured data are input into the progress prediction model trained based on the historical data of the project. The model can automatically analyze the correlation and influence of different influencing factors, evaluate the overall progress risk, and make the prediction of the engineering cycle of the subproject more comprehensive and accurate. If the engineering cycle of each subproject can be accurately predicted, the overall project progress will be clear, and the subsequent funding and risk assessment will be more reliable. Therefore, this method of predicting the engineering cycle of subprojects based on data and models can significantly improve the effect of risk assessment.

[0034] Based on the above embodiment, as an optional embodiment, the data of factors affecting the progress of each sub-project includes: Weather factor data, personnel impact data and material progress impact data.

[0035] Specifically, the data of factors affecting the progress of subprojects include weather factors, personnel factors and material factors, which can comprehensively consider various factors that may affect the progress of subprojects from multiple dimensions. Among them, considering weather factor data can evaluate the delay of bad weather on the construction period; considering personnel factors can evaluate the impact of staffing, efficiency and other factors on the progress; considering material factors can evaluate the impact of material supply on the construction period. These factors affecting the progress of subprojects can well reflect the actual situation of the project and serve as model input for in-depth analysis. By considering the data of progress factors affecting multiple aspects, the progress prediction model can evaluate the impact of various complex factors, overcome the prediction deviation caused by relying only on a single or local factor, and achieve a comprehensive and accurate prediction of the progress of subprojects, providing a solid foundation for the subsequent risk assessment of engineering projects. Compared with over-reliance on one or several factors, this multi-dimensional analysis of progress factors can make the progress assessment more comprehensive and accurate, reduce the blind spots caused by ignoring certain key factors, and improve the effect of risk identification.

[0036] Based on the above embodiment, as an optional embodiment, obtaining a preset progress prediction model further includes: S201, obtaining sub-project indicators of several sub-projects, and constructing an engineering project indicator system based on the sub-project indicator data; Specifically, obtaining sub-project indicators and building a project indicator system are important preparations for establishing an accurate risk assessment model. Compared with the overall project, indicators at the sub-project level can more comprehensively reflect the various detailed factors that need to be considered in risk assessment. During specific implementation, statistical data such as the execution progress, capital expenditure, staffing, and material procurement of each sub-project can be collected through research to establish a standardized sub-project risk assessment indicator system. On this basis, the key risk indicators at the project level can be summarized and the overall indicator system of the project can be constructed. In this way, the indicator system that supports the project from the sub-project can enable the risk model to be established on the basis of indicators that reflect the actual details of the project, ensuring that the model takes into account various important influencing factors. Compared with establishing an indicator system directly at the project level, this bottom-up approach can more comprehensively reflect the actual situation of the project, establish an indicator system that is more in line with the specific situation of the project, and make the output results of the subsequent risk assessment model more accurate and reliable.

[0037] Based on the above embodiment, as an optional embodiment, obtaining sub-project indicators of several sub-projects and constructing an engineering project indicator system based on the sub-project indicator data also includes: S301, determining the project indicators of each sub-project according to each sub-project; Specifically, determining the corresponding sub-project indicators according to each sub-project is an important step in building an accurate project risk assessment model. Compared with directly using unified project indicators, customized sub-project indicators can better reflect the characteristics of each sub-project. In specific implementation, the key risk factors for each sub-project can be identified by investigating and analyzing the business processes, participating entities, resource dependencies, etc. of each sub-project. On this basis, determine the indicators that reflect these risk factors and build a customized indicator system for sub-projects. In this way, accurate sub-project indicators can better predict actual risks such as sub-project schedule deviations and cost overruns. After all sub-projects have completed the indicator determination, the overall key risk indicators of the project are further comprehensively determined. This bottom-up indicator construction method can make the indicators more closely linked to the actual project risks, laying a solid foundation for building an accurate risk assessment model.

[0038] S302, constructing an engineering project indicator system based on the project indicators of the sub-projects.

[0039] Specifically, constructing a project indicator system based on sub-project indicators is a key step to further improve the effectiveness of risk assessment. After determining the customized indicators for each sub-project, it is also necessary to build a comprehensive indicator system at the project level. In specific implementation, the indicators of each sub-project can be compared and analyzed horizontally to identify the common indicators in the sub-project indicators. This part of the common indicators can reflect the key risk factors of the project as a whole and select them as indicators at the project level. In addition, the importance of each sub-project to the overall project can be evaluated. On the basis of the common indicators, the personalized indicators of some important sub-projects can be appropriately absorbed into the project indicator system to form a project risk indicator system that is both universal and targeted. The project indicator system based on the customized indicators of sub-projects can make the indicator selection more in line with the actual situation of the project and the risk control needs. Supported by this indicator system, the constructed risk assessment model can achieve comprehensive and accurate measurement and prediction of the overall risk of the project.

[0040] S202, constructing a progress prediction model based on the engineering project indicator system; Specifically, building a progress prediction model based on the engineering project indicator system is the key to achieving accurate risk prediction. Compared with simply relying on manual experience, model prediction can significantly improve the accuracy of progress assessment. In specific implementation, on the basis of building a project indicator system, key indicators related to progress can be selected as model inputs, and a progress prediction model can be built using a machine learning algorithm. The model can be trained with historical project data to learn the relevance and influence of different indicators on project progress. During the training process, continue to optimize the parameters of the model to improve prediction accuracy. The final trained progress prediction model can input new project indicator data, automatically analyze the correlation and importance of indicators, and output project progress estimates, making progress assessment more intelligent and accurate. Compared with traditional experience prediction, this method based on project indicator system and machine learning can significantly reduce progress prediction deviations, and also lay the foundation for subsequent project risk identification and quantitative evaluation. S203, inputting preset project progress sample data into a progress prediction model, and training the progress prediction model based on the preset project progress sample data; S204: When the risk assessment value accuracy reaches a preset assessment value accuracy, a preset progress prediction model is obtained.

[0041] Specifically, inputting sample data into the progress prediction model for training is a key step in optimizing the model and improving the prediction accuracy. After building the initial model, it is necessary to continuously iterate and optimize the model through sufficient sample data to make it more accurate. In specific implementation, a rich historical project progress data set can be collected as samples to input into the progress prediction model, and the mapping relationship between the model-related project indicators and the actual progress results can be trained. After multiple training iterations, it can be verified whether the model prediction output and the actual progress deviation meet the preset accuracy requirements. When the model accuracy meets the standard, a reliable progress prediction model is obtained. Compared with directly using the initial model, this method based on sufficient sample training can significantly improve the accuracy of the model prediction and make it more adaptable to the actual project environment. The high-precision prediction model obtained by training can provide reliable input for subsequent project risk assessment and greatly improve the evaluation effect. In short, continuous iterative optimization through sample training is a key step in obtaining a reliable and accurate progress prediction model.

[0042] S103, obtaining a labor price trend curve and a raw material price trend curve, and determining a project fund estimation result according to the engineering cycle of each sub-project, the labor price trend curve, the raw material price trend curve, and the labor situation and raw materials required for each sub-project; Specifically, obtaining the price trend curve of labor and raw materials and determining the project funding calculation based on it is an important part of assessing project risks. The funding demand of engineering projects is affected by many factors. If the calculation is inaccurate, it will affect the subsequent risk control. In specific implementation, historical data on market prices of labor and materials can be collected, and statistical methods can be used to draw the trend curve of resource price changes. Then, considering the engineering cycle requirements and corresponding resource requirements of each sub-project, the calculation is carried out according to the trend of price curve changes, which can accurately predict the impact of resource price changes on costs during the project execution period. Compared with the simple calculation directly according to the current static price, this dynamic prediction based on the price curve can make the funding calculation more accurate, fully consider the risk of cost changes, and provide an important basis for project risk management. In addition, the price adjustment clauses agreed in the contract can be considered, and possible change costs can be added to the calculation to make the results more comprehensive. This comprehensive funding calculation method will help to more accurately assess the overall risk of the project in the future.

[0043] S104, input the project fund estimation result into a preset project risk assessment model, and output the project risk index.

[0044] Specifically, inputting the project funding calculation results into the preset risk assessment model to output the project risk index is the last key step to achieve quantitative risk assessment. Based on the data such as the project plan schedule and funding requirements obtained in the previous steps, it is also necessary to establish a comprehensive model to calculate and judge the overall risk of various factors. In specific implementation, a project risk assessment model can be constructed. The model comprehensively considers many factors such as project scale, construction schedule, funding calculation, contract terms, resource supply, etc., and adopts a quantitative risk calculation method to perform an overall risk rating on the project. The model can be trained based on a large amount of historical project data, and the evaluation results are more accurate. The project funding calculation data obtained in the previous steps is input into the risk assessment model, and the model can automatically calculate the comprehensive risk index of the project. This model-based quantitative risk calculation method can make the project risk assessment clearer and more comprehensive, output standardized risk index results, provide a basis for subsequent project decisions, and realize model-based and intelligent risk management.

[0045] Based on the above embodiment, as an optional embodiment, the method further includes: S401, obtaining the loss type of each sub-item; Specifically, obtaining the loss type of each sub-project is the first step in assessing the project's loss risk. Different types of sub-projects are prone to different losses. During specific implementation, the possible loss types of each sub-project, such as manpower loss, material loss, equipment loss, etc., can be analyzed by investigating the business type, resource dependency, and management model of the sub-project. Clarifying the loss type of the sub-project will help identify key risk factors and conduct targeted risk prevention and control. Compared with directly considering the loss type from the overall project, this method of determining the loss type based on the specific situation of the sub-project can more comprehensively identify various loss risks in the project process and avoid ignoring certain loss types due to simplification. Fully clarifying the loss type of the sub-project can lay the foundation for the subsequent assessment of the project's loss risk.

[0046] S402, determining the time loss cost and capital loss cost of each type according to the loss type; Specifically, determining the time and financial costs according to different types of losses is a key step in assessing the degree of loss risk. Different types of losses will lead to different degrees of time delays and cost overruns. In specific implementation, historical project loss data can be collected to analyze the time and financial losses corresponding to different types of losses. For example, the time delay cost caused by manpower loss, the maintenance cost caused by equipment failure, etc. After establishing the correspondence between loss types and time and financial costs, when assessing the loss risk of sub-projects, the corresponding parameters can be found according to the specific loss type of the sub-project, so as to calculate the expected time and cost losses of this type of loss, so that the risk assessment parameters are more in line with the actual project. Compared with simple evaluation using average values, this detailed cost calculation based on loss types can significantly improve the accuracy of loss risk assessment and provide a basis for subsequent loss prevention and control measures.

[0047] S403, adjusting the capital calculation result by using the time loss cost and capital loss cost.

[0048] Specifically, incorporating the time and money loss costs into the capital calculation adjustment is the end point of assessing the project loss risk. After clarifying the loss type and the corresponding time and money costs, the original project capital calculation results need to be adjusted to reflect the loss risk. In specific implementation, the time and money losses can be measured according to the corresponding parameters based on the possible loss types of each sub-project, and included in the original project capital calculation. In this way, the adjusted project capital calculation results can be obtained, which more comprehensively reflects the additional time and money costs caused by the losses that may occur during the project execution. Compared with directly using the original calculation results, this adjustment calculation that takes into account the loss risk can make the project risk analysis more comprehensive and accurate, and prevent insufficient funds due to ignoring the loss risks. The project capital calculation after the loss cost adjustment will help to formulate more accurate and reliable project decision-making plans in the future.

[0049] Based on the above embodiment, as an optional embodiment, the method further includes: Determine the overdue liquidated damages for each sub-project based on the engineering cycle and contract cycle of each sub-project, and adjust the funding calculation results based on the overdue liquidated damages.

[0050] Specifically, by determining the overdue liquidated damages based on the sub-project engineering cycle and contract cycle, and making adjustments to the funding calculation, the impact of the project delay risk on the funds can be evaluated. During specific implementation, the estimated engineering cycle of each sub-project and the completion time agreed in the contract can be obtained, and the difference between the two can be compared. The liquidated damages cost that may be incurred due to the delay can be calculated based on the number of overdue days and the liquidated damages ratio parameters agreed in the contract. Then the liquidated damages costs of all sub-projects are accumulated and incorporated into the original project funding calculation results to form a new funding calculation result that takes into account the risk of delayed default. This method can quantify the impact of project schedule delays on funds and avoid funding gaps in actual implementation. Compared with simply relying on manual judgment of the risk of delay, this method can clearly calculate the economic losses that may be caused by the delay, and the calculation of the project funding needs is more accurate and comprehensive, providing a basis for further risk assessment and decision-making of the project.

[0051] See also Figure 2 , Figure 2 A project risk assessment system architecture diagram provided in an embodiment of the present application, the project risk assessment system may include: The project splitting module 1 is used to obtain the project structure of the engineering project and split the engineering project into several sub-projects according to the project structure; Data acquisition module 2, used to acquire project progress data of several sub-projects and progress influencing factor data of each sub-project, and input the project progress data of the sub-projects and the progress influencing factor data of each sub-project into a preset progress prediction model to obtain the engineering cycle of each sub-project; The capital calculation module 3 is used to obtain the labor price trend curve and the raw material price trend curve, and determine the project capital calculation result according to the engineering cycle of each sub-project, the labor price trend curve, the raw material price trend curve and the corresponding labor situation and raw materials required for each sub-project; The project risk prediction module 4 is used to input the project fund calculation results into a preset project risk assessment model and output a project risk index.

[0052] It should be noted that: when the system provided in the above embodiment realizes its functions, only the division of the above functional modules is used as an example. In actual applications, the above functions can be assigned to different functional modules as needed, that is, the internal structure of the device is divided into different functional modules to complete all or part of the functions described above. In addition, the system and method embodiments provided in the above embodiment belong to the same concept, and the specific implementation process is detailed in the method embodiment, which will not be repeated here.

[0053] Please refer to Figure 3 The application also discloses an electronic device. Figure 3The electronic device 300 may include: at least one processor 301, at least one network interface 304, a user interface 303, a memory 305, and at least one communication bus 302 or end-to-end wireless communication.

[0054] The communication bus 302 is used to realize the connection and communication between these components.

[0055] The user interface 303 may include a display screen (Display) and a camera (Camera). Optionally, the user interface 303 may also include a standard wired interface and a wireless interface.

[0056] The network interface 304 may optionally include a standard wired interface or a wireless interface (such as a WI-FI interface).

[0057] Among them, the processor 301 may include one or more processing cores. The processor 301 uses various interfaces and lines to connect various parts in the entire server, and executes various functions of the server and processes data by running or executing instructions, programs, code sets or instruction sets stored in the memory 305, and calling data stored in the memory 305. Optionally, the processor 301 can be implemented in at least one hardware form of digital signal processing (Digital Signal Processing, DSP), field programmable gate array (Field~Programmable Gate Array, FPGA), and programmable logic array (Programmable Logic Array, PLA). The processor 301 can integrate one or a combination of a central processing unit (Central Processing Unit, CPU), a graphics processing unit (Graphics Processing Unit, GPU) and a modem. Among them, the CPU mainly processes the operating system, user interface and application programs; the GPU is responsible for rendering and drawing the content to be displayed on the display screen; the modem is used to process wireless communications. It can be understood that the above-mentioned modem may not be integrated into the processor 301, and it can be implemented separately through a chip.

[0058] Among them, the memory 305 may include a random access memory (Random Access Memory, RAM) and may also include a read-only memory (Read~Only Memory). Optionally, the memory 305 includes a non-transitory computer-readable medium. The memory 305 can be used to store instructions, programs, codes, code sets or instruction sets. The memory 305 may include a program storage area and a data storage area, wherein the program storage area may store instructions for implementing an operating system, instructions for at least one function (such as a touch function, a sound playback function, an image playback function, etc.), instructions for implementing the above-mentioned various method embodiments, etc.; the data storage area may store data involved in the above-mentioned various method embodiments, etc. The memory 305 may optionally be at least one storage system located away from the aforementioned processor 301. Refer to Figure 3 , the memory 305 as a computer storage medium may include an operating system, a network communication module, a user interface module and an application program of a project risk assessment method.

[0059] exist Figure 3 In the electronic device 300 shown, the user interface 303 is mainly used to provide an input interface for the user and obtain the data input by the user; and the processor 301 can be used to call the application program storing the road assessment method in the memory 305. When executed by one or more processors 301, the electronic device 300 executes one or more methods in the above-mentioned embodiments. It should be noted that for the aforementioned method embodiments, for the sake of simple description, they are all expressed as a series of action combinations, but those skilled in the art should know that the present application is not limited to the described order of actions, because according to the present application, certain steps can be performed in other orders or simultaneously. Secondly, those skilled in the art should also know that the embodiments described in the specification are all preferred embodiments, and the actions and modules involved are not necessarily required for the present application. In the above embodiments, the description of each embodiment has its own emphasis. For the parts that are not described in detail in a certain embodiment, please refer to the relevant description of other embodiments.

[0060] In the several implementations provided in this application, it should be understood that the disclosed system can be implemented in other ways. For example, the system embodiments described above are only schematic, such as the division of modules, which is only a logical function division. There may be other division methods in actual implementation, such as multiple modules or components can be combined or integrated into another system, or some features can be ignored or not executed. Another point is that the mutual coupling or direct coupling or communication connection shown or discussed can be through some service interfaces, indirect coupling or communication connection of systems or modules, which can be electrical or other forms.

[0061] The modules described as separate components may or may not be physically separated, and the components shown as modules may or may not be physical modules, that is, they may be located in one place or distributed on multiple network modules. Some or all of the modules may be selected according to actual needs to achieve the purpose of the solution of this embodiment.

[0062] The present application also provides a computer storage medium that can store multiple instructions, which are suitable for being loaded and executed by a processor as described above. Figure 1 The road assessment method of the embodiment shown in the figure can be found in the specific implementation process. Figure 1 The specific description of the illustrated embodiment will not be repeated here.

[0063] In addition, each functional module in each embodiment of the present application can be integrated into a processing module, or each module can exist physically separately, or two or more modules can be integrated into one module. The above integrated modules can be implemented in the form of hardware or software functional modules.

[0064] If the integrated module is implemented in the form of a software function module and sold or used as an independent product, it can be stored in a computer-readable memory. Based on this understanding, the technical solution of the present application, or the part that contributes to the prior art, or all or part of the technical solution can be embodied in the form of a software product, which is stored in a memory and includes several instructions for a computer device (which can be a personal computer, server or network device, etc.) to execute all or part of the steps of the various embodiments of the present application. The aforementioned memory includes: various media that can store program codes, such as USB flash drives, mobile hard drives, magnetic disks or optical disks.

[0065] The above are only exemplary embodiments of the present disclosure and cannot be used to limit the scope of the present disclosure. That is, any equivalent changes and modifications made according to the teachings of the present disclosure are still within the scope of the present disclosure. After considering the disclosure of the specification and the truth of practice, those skilled in the art will easily think of other embodiments of the present disclosure.

[0066] This application is intended to cover any variation, use or adaptation of the present disclosure, which follows the general principles of the present disclosure and includes common knowledge or customary technical means in the art not described in the present disclosure. The description and examples are to be regarded as exemplary only, and the scope and spirit of the present disclosure are defined by the claims.

Claims

1. A project risk assessment method, It is characterized in that The method comprises: Obtaining a project structure of the engineering project, and decomposing the engineering project into a plurality of sub-projects according to the project structure; Acquire project progress data of the plurality of subprojects and progress influencing factor data of each subproject, and input the project progress data of the subprojects and the progress influencing factor data of each subproject into a preset progress prediction model to obtain the engineering period of each subproject; Obtaining a labor price trend curve and a raw material price trend curve, and determining a project fund estimation result according to the engineering cycle of each sub-project, the labor price trend curve, the raw material price trend curve, and the labor situation and raw materials required for each sub-project; The project fund estimation result is input into a preset project risk assessment model to output a project risk index.

2. A project risk assessment method according to claim 1, It is characterized in that The obtaining of the preset progress prediction model includes: Obtaining sub-project indicators of a plurality of said sub-projects, and constructing an engineering project indicator system based on said sub-project indicator data; Constructing a progress prediction model based on the engineering project indicator system; Inputting preset project progress sample data into the progress prediction model, and training the progress prediction model based on the preset project progress sample data; When the risk assessment value accuracy reaches the preset assessment value accuracy, the preset progress prediction model is obtained.

3. A project risk assessment method according to claim 2, It is characterized in that The obtaining of sub-project indicators of a plurality of the sub-projects and constructing an engineering project indicator system based on the sub-project indicator data includes: Determine the project indicators of each sub-project according to each sub-project; An engineering project indicator system is constructed based on the project indicators of the sub-projects.

4. A project risk assessment method according to claim 1, It is characterized in that Determining the project fund calculation result according to the engineering cycle of each sub-project, the labor price trend curve, the raw material price trend curve and the labor situation and raw materials required for each sub-project, includes: Determine the human resources funds for each sub-project according to the engineering cycle of each sub-project, the human resources required for each sub-project and the human resources price trend curve; Determine the raw material funds for each sub-project according to the engineering cycle of each sub-project, the raw materials required for each sub-project and the raw material price trend curve; The project fund calculation result is determined based on the raw material funds and human resources funds of each sub-project.

5. A project risk assessment method according to claim 1, It is characterized in that The method further comprises: Obtain the loss type of each sub-item; According to the loss types, determine the time loss cost and financial loss cost of each type; The funds calculation result is adjusted by the time loss cost and the funds loss cost.

6. A project risk assessment method according to claim 1, It is characterized in that The method further comprises: The overdue liquidated damages for each sub-project are determined based on the engineering period and contract period of each sub-project, and the funds estimation result is adjusted based on the overdue liquidated damages.

7. A project risk assessment method according to claim 1, It is characterized in that The data of factors affecting the progress of each sub-project include: Weather factor data, personnel impact data and material progress impact data.

8. A project risk assessment system, It is characterized in that The system comprises: A project splitting module is used to obtain the project structure of the engineering project and to split the engineering project into several sub-projects according to the project structure; A data acquisition module is used to acquire project progress data of several sub-projects and progress influencing factor data of each sub-project, and input the project progress data of the sub-projects and the progress influencing factor data of each sub-project into a preset progress prediction model to obtain the engineering period of each sub-project; A fund calculation module is used to obtain a labor price trend curve and a raw material price trend curve, and determine a project fund calculation result according to the engineering cycle of each sub-project, the labor price trend curve, the raw material price trend curve, and the labor situation and raw materials required for each sub-project; The project risk prediction module is used to input the project fund calculation results into a preset project risk assessment model and output a project risk index.

9. A computer-readable storage medium, It is characterized in that The computer-readable storage medium stores a plurality of instructions, and the instructions are suitable for being loaded by a processor and executing the method according to any one of claims 1 to 7.

10. An electronic device, It is characterized in that It includes a processor, a memory and a transceiver, the memory is used to store instructions, the transceiver is used to communicate with other devices, and the processor is used to execute the instructions stored in the memory so that the electronic device executes the method according to any one of claims 1 to 7.

Citation Information

Patent Citations

  • Technical engineering calculation method and system based on digital modeling

    CN115169818A

  • Construction budget generation method and system, terminal equipment and storage medium

    CN117172549A

  • Engineering project progress prediction method and system based on RBF neural network

    CN117391464A

  • System and method for automated project performance analysis and project success rate prediction

    US20160140474A1

  • Index computation device, prediction system, progress prediction evaluation method, and program

    WO2019187341A1

Cited By

  • Quality evaluation method and terminal for house steel structure project

    CN119784241A

  • Engineering project data early warning method and device

    CN119918857A