Construction method for soft foundation replacement and filling of temporary road based on flow-state solidified soil

By dividing the soft soil layer into two parts for curing and refilling, and using temporary roads for material transportation, the problem of low construction efficiency during soft foundation replacement is solved, and efficient construction and cost reduction is achieved.

CN119021184AActive Publication Date: 2024-11-26CHINA CONSTR EIGHT ENG DIV CORP LTD
View PDF 4 Cites 0 Cited by

Patent Information

Application Number
CN202411307751.8
Authority / Receiving Office
CN · China
Patent Type
Applications(China)
Current Assignee / Owner
Filing Date
2024-09-19
Publication Date
2024-11-26
Estimated Expiration
2044-09-19

AI Technical Summary

Technical Problem

During the soft foundation replacement process, when there are no existing roads around the soft soil excavation and replacement area and the replacement area is large, the construction efficiency is low, and the surrounding land needs to be temporarily occupied as a loading or unloading area, resulting in economics and construction Poor efficiency.

Method used

Using the construction method of fluid solidified soil, the soft soil layer is divided into two parts for curing and refilling, and the temporary road is used for material transportation. First, part of it is completed and then the road is transferred to another part for construction, so as to improve the excavation and replacement of materials. efficiency.

Benefits of technology

It significantly improves construction efficiency, reduces construction costs and cycles, and can carry out other sub-projects during soft foundation replacement, which significantly shortens the construction cycle.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure HDA0005049764590000011
    Figure HDA0005049764590000011
  • Figure HDA0005049764590000012
    Figure HDA0005049764590000012
  • Figure HDA0005049764590000021
    Figure HDA0005049764590000021
Patent Text Reader

Abstract

The invention relates to a construction method for a soft foundation replacement and filling temporary road based on flow state solidified soil, the construction method is arranged on a soft soil layer, the soft soil layer comprises a first construction area and a second construction area, and the construction method comprises the following steps that the soft soil layer in the first construction area is solidified, and after soft soil in the first construction area is solidified, the second construction area is constructed; the construction position, corresponding to the temporary road, of the first construction area is excavated to form a first construction section; constructing on the first construction section to form a first temporary road; the soft soil layer in the second construction area is solidified, after the soft soil in the second construction area is solidified, the soft soil in the second construction area is replaced and filled, and materials needed for replacement and filling are transported through the first temporary road; and a second temporary road is constructed on the top of the second construction area, the first construction area is subjected to replacement filling, and materials needed for replacement filling are transported through the second temporary road.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The invention relates to the technical field of road construction, in particular to a construction method for a temporary road based on soft foundation replacement of fluidized solidified soil. Background Art

[0002] Soft foundation replacement is a common sub-project in highway and railway construction. The main reason is that there is soft soil in some sections of the route, which cannot meet the bearing capacity requirements of the highway or railway. The soft soil needs to be excavated and replaced with fillers with good permeability or high strength and good stability. When there is no existing road around the replacement area and the replacement area is large, it is difficult to excavate the soft soil and transport the replacement filler. Loading or unloading can only be concentrated at a certain location on the edge of the replacement area, with low construction efficiency. It may even be necessary to temporarily requisition part of the surrounding land as a construction loading or unloading area, which is poor in economy and construction efficiency. Summary of the invention

[0003] The purpose of the present invention is to overcome the defects of the prior art and provide a construction method for a temporary road for replacing soft foundation based on fluidized solidified soil, by constructing a temporary road on a soft soil layer so that construction workers can easily transfer the soft soil of the soft soil layer.

[0004] The technical solution to achieve the above purpose is a construction method for a temporary road based on a soft foundation replacement of fluidized solidified soil, which is arranged on a soft soil layer, wherein the soft soil layer includes a first construction area and a second construction area, and comprises the following steps:

[0005] Solidifying the soft soil layer in the first construction area, and after the soft soil in the first construction area is solidified, excavating the first construction area at the construction position corresponding to the temporary road to form a first construction section;

[0006] constructing a first temporary road on the first construction section;

[0007] Solidify the soft soil layer in the second construction area, and after the soft soil in the second construction area is solidified, replace the soft soil in the second construction area with new soil, and transport the materials required for replacement through the first temporary road;

[0008] A second temporary road is constructed on the top of the second construction area, and the first construction area is refilled, and the materials required for refilling are transported through the second temporary road.

[0009] Furthermore, when curing the soft soil layer in the first construction area, a soft soil curing agent is provided and added to the soft soil layer in the first construction area to cure the soft soil layer in the first construction area.

[0010] Furthermore, after adding a soft soil solidifying agent to the soft soil layer in the first construction area, stirring is performed in the first construction area.

[0011] Furthermore, when curing the soft soil layer in the second construction area, a soft soil curing agent is provided and added to the soft soil layer in the second construction area to cure the soft soil layer in the second construction area.

[0012] Furthermore, after adding a soft soil solidifying agent to the soft soil layer in the second construction area, stirring is performed in the second construction area.

[0013] Furthermore, the width of the first temporary road is determined according to on-site construction.

[0014] Furthermore, the width of the second temporary road is determined according to on-site construction.

[0015] Furthermore, after the first construction area and the second construction area are replaced and filled, a highway is constructed on top of the first construction area and the second construction area.

[0016] Furthermore, the first temporary road is set corresponding to the construction location of the highway.

[0017] Furthermore, the second temporary road is set corresponding to the construction location of the highway.

[0018] Compared with the prior art, the present invention has the following beneficial effects:

[0019] After completing the local soft foundation replacement, the temporary road of fluidized solidified soil can be excavated and transferred to the area where the replacement has been completed to construct the remaining soft foundation replacement, which greatly improves the efficiency of excavating and replacing materials. It can also be used as a temporary road to ensure the smooth construction of other sub-projects during the soft foundation replacement, which can significantly reduce construction costs and greatly shorten the construction period. BRIEF DESCRIPTION OF THE DRAWINGS

[0020] Figure 1 This is a pre-construction rendering of a construction method for replacing a temporary road with soft foundation based on fluidized solidified soil.

[0021] Figure 2 The present invention is a construction rendering of a second construction area for a construction method of replacing a temporary road with a soft foundation based on fluidized solidified soil.

[0022] Figure 3 The present invention is a construction rendering of the first construction area of ​​a construction method for replacing a temporary road with a soft foundation based on fluidized solidified soil.

[0023] Legend: 1. Soft soil layer; 11. Second construction area; 12. First construction area; 13. First temporary road; 14. Second temporary road; 2. Highway. DETAILED DESCRIPTION

[0024] The present invention will be further described below in conjunction with the accompanying drawings and specific embodiments.

[0025] See also Figures 1 to 3 A construction method for a temporary road for replacing a soft foundation with fluidized solidified soil is provided on a soft soil layer 1, wherein the soft soil layer 1 includes a first construction area 12 and a second construction area 11, and includes the following steps: solidifying the soft soil layer 1 in the first construction area 12, and after the soft soil in the first construction area 12 is solidified, excavating the first construction section at the construction position corresponding to the temporary road in the first construction area 12; constructing a first temporary road 13 on the first construction section; solidifying the soft soil layer 1 in the second construction area 11, and after the soft soil in the second construction area 11 is solidified, replacing the soft soil in the second construction area 11, and transporting the materials required for replacement through the first temporary road 13; constructing a second temporary road 14 on the top of the second construction area 11, replacing the first construction area 12, and transporting the materials required for replacement through the second temporary road 14.

[0026] In the present invention, a preferred implementation method is: in the process of road construction, when encountering a large area of ​​soft soil layer 1 of fluidized solidified soil, the soft soil layer 1 is first divided into two parts. Preferably, in the present invention, the soft soil layer 1 is divided by the road to be constructed as a dividing line to form a first construction area 12 and a second construction area 11. The first construction area 12 is first solidified, and a first temporary road 13 is constructed on the first construction area 12. The first temporary road 13 can be used as a temporary road to ensure the smooth construction of other sub-projects during the replacement of the second construction area 11, which can significantly reduce construction costs and greatly shorten the construction period; the second construction area 11 is solidified, and the soft soil layer 1 in the second construction area 11 is replaced. After the replacement is completed, a second temporary road 14 is constructed in the second construction area 11. The second temporary road 14 can be used as a temporary road to ensure the smooth construction of other sub-projects during the replacement of the first construction area 12, which can significantly reduce construction costs and greatly shorten the construction period; and the first construction area 12 is replaced.

[0027] Furthermore, when curing the soft soil layer 1 in the first construction area 12 , a soft soil curing agent is provided and added into the soft soil layer 1 in the first construction area 12 to cure the soft soil layer 1 in the first construction area 12 .

[0028] Preferably, the soft soil solidifying agent is an inorganic hydraulic cementing material used to solidify soft soil and other fine-grained soils. After being fully mixed with the soil, it can significantly improve the physical and mechanical properties of the soil through physical and chemical reactions between its own components and between the soil, and can form a solidified body that meets environmental standards and maintains long-term stability. The solidified body formed after the soft soil solidifying agent is fully mixed with the soil and cured is called fluidized solidified soil.

[0029] Furthermore, the main components of the soft soil solidifying agent are cement, lime, stone powder, silicate and other substances; among them, cement is one of the most commonly used ingredients in the soft soil solidifying agent; cement can bond with the fine particles contained in the soft soil to form a solid structure, thereby playing a role in solidifying the soft soil; in addition to cement, the soft soil solidifying agent also contains some auxiliary agents that can promote the solidification and stabilization of the soft soil, such as silicate, polymer, bentonite, etc.

[0030] Further, after adding the soft soil curing agent to the soft soil layer 1 in the first construction area 12, stirring is performed in the first construction area 12. Preferably, by stirring the soft soil layer 1, the soft soil curing agent and the soft soil layer 1 are fully mixed to ensure the effect of soft soil curing.

[0031] Furthermore, the construction steps of the soft soil replacement of the first construction area 12 include: removing debris and pollutants on the surface of the first construction area 12, ensuring that the ground of the first construction area 12 is dry and clean, adding a soft soil curing agent to the soft soil layer 1 of the first construction area 12 to solidify the soft soil in the first construction area 12; after the soft soil layer 1 of the second construction area 11 is solidified and replaced, the first construction area 12 is replaced with soil, and layered and evenly filled according to design requirements, and the replacement soil is compacted to ensure the compactness and stability of the replacement soil. The excavated materials and replacement materials during construction are transferred through the second temporary road 14. After the construction is completed, the construction quality is tested, such as the uniformity of the replacement soil, the degree of compaction, etc., and timely adjustments are made.

[0032] Furthermore, when curing the soft soil layer 1 in the second construction area 11 , a soft soil curing agent is provided and added into the soft soil layer 1 in the second construction area 11 to cure the soft soil layer 1 in the second construction area 11 .

[0033] Furthermore, the main components of the soft soil solidifying agent are cement, lime, stone powder, silicate and other substances; among them, cement is one of the most commonly used ingredients in the soft soil solidifying agent; cement can bond with the fine particles contained in the soft soil to form a solid structure, thereby playing a role in solidifying the soft soil; in addition to cement, the soft soil solidifying agent also contains some auxiliary agents that can promote the solidification and stabilization of the soft soil, such as silicate, polymer, bentonite, etc.

[0034] Further, after adding the soft soil curing agent to the soft soil layer 1 in the second construction area 11, stirring is performed in the second construction area 11. Preferably, by stirring the soft soil layer 1, the soft soil curing agent and the soft soil layer 1 are fully mixed to ensure the effect of soft soil curing.

[0035] Furthermore, the construction steps of the soft soil replacement in the second construction area 11 include: removing debris and pollutants on the surface of the second construction area 11 to ensure that the ground of the second construction area 11 is dry and clean, and adding a soft soil curing agent to the soft soil layer 1 of the second construction area 11 to solidify the soft soil in the second construction area 11; replacing the soil in the second construction area 11, and filling it in layers evenly according to the design requirements, and compacting the replacement soil to ensure the compactness and stability of the replacement soil. The excavated materials and replacement materials during construction are transferred through the first temporary road 13. After the construction is completed, the construction quality is tested, such as the uniformity of the replacement soil, the degree of compaction, etc., and timely adjustments are made.

[0036] Furthermore, the width of the first temporary road 13 is determined according to the on-site construction. The width of the first temporary road 13 is adjusted to meet the passage of transport vehicles.

[0037] Furthermore, the width of the second temporary road 14 is determined according to the on-site construction. The width of the second temporary road 14 is adjusted to meet the passage of transport vehicles.

[0038] Furthermore, after the first construction area 12 and the second construction area 11 are replaced and filled, the highway 2 is constructed on top of the first construction area 12 and the second construction area 11 .

[0039] Furthermore, the first temporary road 13 is set corresponding to the construction position of the highway 2.

[0040] Furthermore, the second temporary road 14 is set corresponding to the construction position of the highway 2.

[0041] The following is an explanation of the use process of the construction method of a temporary road for replacing soft foundation with fluidized solidified soil according to the present invention.

[0042] In the process of road construction, when encountering a large area of ​​soft soil layer 1 of fluidized solidified soil, the soft soil layer 1 is first divided into two parts. Preferably, in the present invention, the soft soil layer 1 is divided by the road to be constructed as a dividing line to form a first construction area 12 and a second construction area 11. The first construction area 12 is first solidified, and a first temporary road 13 is constructed on the first construction area 12. The first temporary road 13 can be used as a temporary road to ensure the smooth construction of other sub-projects during the replacement of the second construction area 11, which can significantly reduce the construction cost and greatly shorten the construction period; remove the debris and pollutants on the surface of the second construction area 11 to ensure that the ground of the second construction area 11 is dry and tidy, and add a soft soil curing agent to the soft soil layer 1 of the second construction area 11 to solidify the soft soil in the second construction area 11; replace the soil in the second construction area 11, and fill it evenly in layers according to the design requirements, and compact the replacement soil to ensure The compactness and stability of the replacement soil, the excavated materials and replacement materials during construction are transferred through the first temporary road 13. After the construction is completed, the construction quality, such as the uniformity of the replacement soil, the degree of compaction, etc., is detected, and adjustments are made in time. The second temporary road 14 is constructed in the second construction area 11 after the construction is completed. The second temporary road 14 can be used as a temporary road to ensure the smooth construction of other sub-projects during the replacement of the first construction area 12, which can significantly reduce the construction cost and greatly shorten the construction period; after the soft soil layer 1 of the second construction area 11 is solidified and the replacement is completed, the first construction area 12 is replaced with soil, and the layered and uniform filling is carried out according to the design requirements, and the replacement soil is compacted to ensure the compactness and stability of the replacement soil. The excavated materials and replacement materials during construction are transferred through the second temporary road 14. After the construction is completed, the construction quality, such as the uniformity of the replacement soil, the degree of compaction, etc., is detected, and adjustments are made in time.

[0043] The present invention is described in detail above in conjunction with the embodiments of the accompanying drawings. A person skilled in the art can make various variations of the present invention according to the above description. Therefore, certain details in the embodiments should not constitute a limitation of the present invention, and the scope of protection of the present invention shall be defined by the scope of the attached claims.

Claims

1. A construction method for a temporary road based on fluidized solidified soil for replacing soft foundation, which is arranged on a soft soil layer, wherein the soft soil layer includes a first construction area and a second construction area, and is characterized in that: The steps include: Solidifying the soft soil layer in the first construction area, and after the soft soil in the first construction area is solidified, excavating the first construction area at the construction position corresponding to the temporary road to form a first construction section; constructing a first temporary road on the first construction section; Solidify the soft soil layer in the second construction area, and after the soft soil in the second construction area is solidified, replace the soft soil in the second construction area with new soil, and transport the materials required for replacement through the first temporary road; A second temporary road is constructed on the top of the second construction area, and the first construction area is refilled, and the materials required for refilling are transported through the second temporary road.

2. The construction method of a temporary road based on fluidized solidified soil for soft foundation replacement according to claim 1 is characterized in that: When curing the soft soil layer in the first construction area, a soft soil curing agent is provided and added into the soft soil layer in the first construction area to cure the soft soil layer in the first construction area.

3. The construction method of a temporary road for replacing soft foundation with fluidized solidified soil according to claim 2 is characterized by: After adding the soft soil solidifying agent to the soft soil layer in the first construction area, stirring is performed in the first construction area.

4. The construction method of a temporary road based on fluidized solidified soil for soft foundation replacement according to claim 1 is characterized in that: When curing the soft soil layer in the second construction area, a soft soil curing agent is provided and added into the soft soil layer in the second construction area to cure the soft soil layer in the second construction area.

5. The construction method of a temporary road for replacing soft foundation with fluidized solidified soil according to claim 4 is characterized by: After adding the soft soil solidifying agent to the soft soil layer in the second construction area, stirring is performed in the second construction area.

6. The construction method of a temporary road for replacing soft foundation with fluidized solidified soil according to claim 1 is characterized by: The width of the first temporary road is determined according to on-site construction.

7. The construction method of a temporary road for replacing soft foundation with fluidized solidified soil according to claim 1 is characterized by: The width of the second temporary road is determined according to on-site construction.

8. The construction method of a temporary road based on fluidized solidified soil for soft foundation replacement according to claim 1 is characterized in that: After the first construction area and the second construction area are replaced and filled, a highway is constructed on top of the first construction area and the second construction area.

9. The construction method of a temporary road for replacing soft foundation with fluidized solidified soil according to claim 8, characterized in that: The first temporary road is set corresponding to the construction location of the highway.

10. The construction method of a temporary road for replacing soft foundation with fluidized solidified soil according to claim 8, characterized in that: The second temporary road is set corresponding to the construction location of the highway.

Citation Information

Patent Citations

  • Earth cutting construction method for soft soil deep foundation pit

    CN111395350A

  • Foundation replacement method

    CN114232397A

  • Polluted soil treatment system above subway tunnel

    CN212177210U

  • A method for hardened pavement using improved soil

    KR101251440B1