Connecting device for embedded steel bars at bottom of structural beam and construction method of connecting device

By designing a structural beam bottom embedded steel bar connection device including docking cylinder, elastic clamp and snake joint, the problems of unstable welding quality and loose binding connection in the prior art are solved, and the high strength and construction efficiency of steel bar connections are achieved The improvement meets the efficient construction needs of modern buildings.

CN119021423APending Publication Date: 2024-11-26HAITONG CONSTR GRP
View PDF 0 Cites 0 Cited by

Patent Information

Application Number
CN202411425537.2
Authority / Receiving Office
CN · China
Patent Type
Applications(China)
Current Assignee / Owner
Filing Date
2024-10-13
Publication Date
2024-11-26

AI Technical Summary

Technical Problem

The existing method of embedded steel bars at the bottom of structural beams has problems such as unstable welding quality, loose binding connections and low construction efficiency, which cannot meet the requirements of modern buildings for efficient construction.

Method used

Design a connection device including a docking cylinder, an elastic ply plate, a pull tab, a pin, a first fluid reinforcement glue and a snake joint. Through a docking groove, a clamping groove, a spilling groove and a through hole, the elastic ply plate and fluid are used. Reinforcement glue achieves efficient fixing and connection of steel bars.

Benefits of technology

It has achieved high strength and construction efficiency of steel bar connections, simple operation, and can effectively improve the overall strength and stability of structural beams.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN119021423A_ABST
    Figure CN119021423A_ABST
Patent Text Reader

Abstract

The invention provides a connecting device for structural beam bottom embedded steel bars and a construction method thereof, and belongs to the technical field of structural beam steel bar connection.The connecting device comprises a butt-joint cylinder, butt-joint grooves are formed in the two ends of the butt-joint cylinder in the length direction, and clamping grooves are formed in the butt-joint grooves in the two ends of the butt-joint cylinder in a communicating mode along the periphery; the elastic clamping plate is arranged in the clamping groove, one end of the elastic clamping plate is fixedly connected in the clamping groove, and the other end is a free end; the pulling-on pieces correspond to the elastic clamping plates one to one, one ends of the pulling-on pieces are fixedly connected to the elastic clamping plates, and one ends of all the pulling-on pieces are fixedly connected together; the first fluid reinforcing glue is arranged in the first diaphragm and is arranged at the bottom of the butt joint groove; the inserting needle is fixedly connected to the pulling piece, faces the bottom wall of the butt-joint groove and is used for pulling the pulling piece to drive the inserting needle to pierce the first membrane when the reinforcing steel bar is inserted into the butt-joint groove. The reinforcing steel bars can be conveniently connected, and the connecting strength and the construction efficiency are improved.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The present invention relates to the technical field of structural beam reinforcement connection, and in particular to a connection device for pre-embedded reinforcement at the bottom of a structural beam and a construction method thereof. Background Art

[0002] In construction projects, pre-embedded steel bars are usually required at the bottom of structural beams to enhance the overall strength and stability of the structure. However, in the actual construction process, there are many technical difficulties and drawbacks in the connection of pre-embedded steel bars. In the prior art, welding or binding methods are usually used to connect pre-embedded steel bars to structural beams. These methods have some defects: First, welding operations require professional skills, and improper operation can easily cause problems with unstable welding quality, resulting in insufficient structural strength. Secondly, although the binding method is relatively simple, the connection between the steel bars is loose and cannot provide sufficient structural support. In addition, these traditional connection methods are time-consuming and inefficient in on-site construction, and cannot meet the requirements of modern buildings for efficient construction. Therefore, it is particularly important to design a new steel bar connection device to solve the above problems. Summary of the invention

[0003] The object of the present invention is to provide a connection device for pre-embedded steel bars at the bottom of a structural beam and a construction method thereof, which can facilitate the connection of the steel bars and improve the connection strength and construction efficiency.

[0004] In the first aspect, the embodiments of the present invention are implemented by the following technical solutions: A connecting device for pre-embedded steel bars at the bottom of a structural beam, comprising a butt joint sleeve, with butt joint grooves provided at both ends of the butt joint sleeve in the length direction, and clamping grooves are provided along the four sides of the butt joint grooves at both ends of the butt joint sleeve; An elastic clamping plate, wherein the elastic clamping plate is arranged in the clamping groove, one end of the elastic clamping plate is fixedly connected in the clamping groove, and the other end is arranged as a free end, and a clamping tooth is arranged on one side of the elastic clamping plate close to the docking groove; A pull tab, each of which corresponds to the elastic clamping plate one by one, one end of each pull tab is fixedly connected to the elastic clamping plate, and one end of all the pull tabs is fixedly connected together; A first fluid reinforcement glue, wherein the first fluid reinforcement glue is disposed in the first diaphragm and disposed at the bottom of the docking groove; The insertion pin is fixedly connected to the pull tab and arranged toward the bottom wall of the docking groove, and is used to pull the pull tab to drive the insertion pin to pierce the first membrane when the steel bar is inserted into the docking groove.

[0005] Furthermore, overflow glue holes are provided along the four sides of the bottom wall of the docking tube close to the docking groove, and the overflow glue holes are interconnected with the docking groove and are arranged in a long strip shape.

[0006] Furthermore, docking parts are provided at both ends of the docking tube, and the docking parts include a plurality of mutually hinged snake bone joints, one end of the docking parts formed by the plurality of snake bone joints is hinged to the docking tube, through holes for inserting steel bars are provided on the snake bone joints, and swing gaps are provided between adjacent snake bone joints.

[0007] Furthermore, the docking groove of the docking tube and the inner wall of the snake bone joint are both vertically provided with glue overflow grooves.

[0008] Furthermore, each of the snake bone joints is provided with a plurality of slots along the four sides, and an elastic card is arranged in the slot. One end of the elastic card is fixedly connected in the slot, and the other end is arranged as a free end and is used to be clamped to the side wall of the steel bar.

[0009] Furthermore, the card slot is arranged to penetrate the side wall of the snake bone joint, and a connecting hole is opened through the elastic card.

[0010] Furthermore, there are multiple docking cylinders, a main rod is arranged between the multiple docking cylinders, and the main rod passes through the multiple docking cylinders in the radial direction of the middle position of the docking cylinder. Each of the docking cylinders is provided with a fixing member for fixing the docking cylinder to the main rod.

[0011] Furthermore, the fixing part is arranged in the docking groove on one side of the docking tube, and the fixing part includes an insertion rod and a second fluid reinforcing glue. The insertion rod is slidably inserted into the bottom wall of the docking groove along the axial direction of the docking tube, and the main rod is provided with a plurality of slots along the length direction. The insertion rod is used to be inserted into the slots. The second fluid reinforcing glue is arranged in the second diaphragm and is annular in shape. The second fluid reinforcing glue sleeve is arranged on the insertion rod, and the tail end of the insertion rod abuts against the second fluid reinforcing glue, and the first fluid reinforcing glue abuts against the tail end of the insertion rod.

[0012] Furthermore, there are multiple main rods, and the docking tubes are correspondingly arranged on the main rods. Sleeves are fixedly arranged at both ends of the main rods, and two series rods are correspondingly passed through the sleeves at both ends of the multiple main rods. Both series rods have limiting holes along the length direction, and limiting rods are passed through the sleeves. The limiting rods are used to be clamped into the limiting holes.

[0013] In a second aspect, the embodiments of the present invention are implemented by the following technical solutions: A construction method for pre-embedded steel bars at the bottom of a structural beam, applicable to the connection device for pre-embedded steel bars at the bottom of a structural beam described in the above scheme, comprises the following steps: S1: Align the butt joint groove of the butt joint sleeve with the end of one of the steel bars and insert and knock the butt joint sleeve; S2: Align the steel bar to be butted with the butt joint groove at the upper end of the butt joint tube and insert it, so that the insertion needle pierces the first membrane, and the first fluid reinforcement glue flows out from the first membrane, thereby bonding the steel bar and the butt joint tube; S3: Install the butt-jointing sleeves one by one to connect the steel bars and complete the butt-jointing of the steel bars.

[0014] The technical solution of the embodiment of the present invention has at least the following advantages and beneficial effects: 1. The present invention provides a docking tube. When the ends of two steel bars are inserted into the docking grooves of the docking tube, the ends of the steel bars will abut against the pulling tab, thereby pulling the elastic clamp to clamp and fix the steel bars. The clamping teeth on the elastic clamp will play a role in fixing the steel bars, and the first diaphragm on the first fluid reinforcing glue will flow out after being punctured by the needle, further bonding and fixing the steel bars and the docking tube. This connection method is simple to operate and has high connection strength, and can effectively improve construction efficiency.

[0015] 2. The present invention provides a docking piece formed by multiple snake bones, and the snake bones can play a guiding role, making it convenient for two steel bars to be docked and inserted into the docking tube. At the same time, the glue overflow grooves, connecting holes and swing gaps between adjacent snake bones on the snake bones can facilitate the entry of glue and cement mortar, further improving the connection strength between the snake bones, steel bars and the docking tube. BRIEF DESCRIPTION OF THE DRAWINGS

[0016] In order to more clearly illustrate the technical solutions of the embodiments of the present invention, the drawings required for use in the embodiments are briefly introduced below. It should be understood that the following drawings only show certain embodiments of the present invention and therefore should not be regarded as limiting the scope. For ordinary technicians in this field, other related drawings can be obtained based on these drawings without creative work.

[0017] Figure 1 A schematic diagram of the overall structure of a connection device for pre-embedded steel bars at the bottom of a structural beam provided by the present invention; Figure 2 The present invention is intended to show an exploded view of the docking sleeve, the elastic splint, the pull tab, the insertion pin and the first fluid reinforcing adhesive; Figure 3 The present invention is intended to show the structural schematic diagram of the docking sleeve and the docking piece; Figure 4 The present invention is intended to show the internal structure of the docking sleeve and the docking piece; Figure 5 For the present invention Figure 4 A magnified view of part A; Figure 6 The present invention is intended to show the structural schematic diagram of the main rod and the series rod; Icons: 1-docking tube, 11-docking groove, 12-clamping groove, 121-elastic splint, 1211-clamping teeth, 13-overflow glue hole, 2-pull tab, 21-pin, 3-first fluid reinforcement glue, 31-first diaphragm, 4-docking piece, 41-snake bone joint, 411-through hole, 412-card slot, 42-swing gap, 43-elastic card, 431-connecting hole, 5-overflow glue groove, 6-main rod, 61-slot, 62-sleeve, 621-limit rod, 7-fixing piece, 71-insertion rod, 72-second fluid reinforcement glue, 721-second diaphragm, 8-tandem rod, 81-limiting hole. DETAILED DESCRIPTION

[0018] In order to make the purpose, technical solutions and advantages of the embodiments of the present invention clearer, the technical solutions in the embodiments of the present invention will be clearly and completely described below in conjunction with the drawings in the embodiments of the present invention. Obviously, the described embodiments are part of the embodiments of the present invention, not all of the embodiments. Generally, the components of the embodiments of the present invention described and shown in the drawings here can be arranged and designed in various different configurations.

[0019] Therefore, the following detailed description of the embodiments of the present invention provided in the accompanying drawings is not intended to limit the scope of the invention claimed for protection, but merely represents selected embodiments of the present invention. Based on the embodiments of the present invention, all other embodiments obtained by ordinary technicians in this field without creative work are within the scope of protection of the present invention. Example

[0020] The following is further described in conjunction with specific embodiments. Figure 1-Figure 6 As shown, the present invention is a connection device for pre-embedded steel bars at the bottom of a structural beam, comprising a butt joint tube 1, the butt joint tube 1 is cylindrical, butt joint grooves 11 are provided at both ends of the butt joint tube 1 in the length direction, the cross section of the butt joint grooves 11 is circular, and clamping grooves 12 are provided at the butt joint grooves 11 at both ends of the butt joint tube 1 along the four sides. In this embodiment, the number of the clamping grooves 12 on one side of the butt joint tube 1 is 4; The elastic clamping plate 121 is installed in the clamping groove 12 at an angle, one end of the elastic clamping plate 121 is welded in the clamping groove 12, and the other end is set as a free end. A clamping tooth 1211 is integrally formed on the side of the elastic clamping plate 121 close to the docking groove 11, and the clamping tooth 1211 is arranged perpendicular to the axial direction of the docking tube 1. The pull tab 2 corresponds to the elastic clamping plate 121 one by one, one end of the pull tab 2 is welded on the elastic clamping plate 121, and one end of all the pull tabs 2 on one side of the docking tube 1 are fixedly welded together, and the welding points of all the pull tabs 2 are located in the middle position of the docking groove 11; Reference Figure 4 and Figure 5As shown, the first fluid reinforcing glue 3 is arranged in the first diaphragm 31 and installed at the bottom of the docking groove 11, and the pin 21 is welded on the pull tab 2 and arranged toward the bottom wall of the docking groove 11, and is used to pull the pull tab 2 when the steel bar is inserted into the docking groove 11 to drive the pin 21 to pierce the first diaphragm 31. After the pin 21 pierces the first diaphragm 31, the first fluid reinforcing glue 3 will quickly flow out under the pressure applied by the steel bar to the pin 21, thereby realizing the bonding of the steel bar and the docking tube 1. The first fluid reinforcing glue 3 should be made of materials such as epoxy glue and polyurethane glue, mainly because they have high bonding strength and good toughness.

[0021] Reference Figure 2 and Figure 3 As shown, the bottom wall of the docking tube 1 close to the docking groove 11 is provided with overflow glue holes 13 along the periphery, and the overflow glue holes 13 are connected to the docking groove 11 and are arranged in a long strip shape.

[0022] Reference Figure 3 As shown, docking parts 4 are installed at both ends of the docking tube 1. The docking parts 4 include a plurality of mutually hinged snake bone joints 41. One end of the docking part 4 formed by the plurality of snake bone joints 41 is hinged to the docking tube 1. Through holes 411 for inserting steel bars are provided on the snake bone joints 41. Swinging gaps 42 are provided between adjacent snake bone joints 41. The snake bone joints 41 can guide and further fix the steel bars, so that two steel bars can be conveniently connected and inserted into the docking tube 1.

[0023] Reference Figure 3 and Figure 4 As shown, the docking groove 11 of the docking tube 1 and the inner wall of the snake bone joint 41 are both vertically provided with an overflow glue groove 5, which is semicircular. After the reinforcing glue flows into the overflow glue groove 5, the connection strength with the steel bar can be improved.

[0024] Reference Figure 4 and Figure 5 As shown, each snake bone joint 41 is provided with a plurality of slots 412 along the four sides, and an elastic card 43 is installed in the slot 412. One end of the elastic card 43 is fixedly connected in the slot 412, and the other end is set as a free end and is used to be connected to the side wall of the steel bar. The slot 412 is set to penetrate the side wall of the snake bone joint 41, and a connecting hole 431 is penetrated on the elastic card 43. The slot 412 and the connecting hole 431 can play a role in flowing concrete mortar, and the free end of the elastic card 43 can abut against the texture of the steel bar to prevent the steel bar from detaching.

[0025] Reference Figure 5As shown, in order to accommodate the simultaneous positioning of multiple embedded steel bars at the bottom of the structural beam, multiple docking tubes 1 are provided, and a main rod 6 is provided between the multiple docking tubes 1. The main rod 6 penetrates the multiple docking tubes 1 along the radial direction of the middle position of the docking tube 1, and each docking tube 1 is provided with a fixing part 7 for fixing the docking tube 1 to the main rod 6.

[0026] Reference Figure 5 As shown, in order to facilitate the positioning of the docking tube 1 on the main rod 6, the fixing member 7 is installed in the docking groove 11 on one side of the docking tube 1, and the fixing member 7 includes an insertion rod 71 and a second fluid reinforcing glue 72. The insertion rod 71 is slidably penetrated in the bottom wall position of the docking groove 11 along the axial direction of the docking tube 1, and the main rod 6 is provided with a plurality of slots 61 along the length direction. The insertion rod 71 is used to be inserted into the slot 61, and the second fluid reinforcing glue 72 is arranged in the second diaphragm 721 and is annular in shape. The second fluid reinforcing glue 72 is sleeved on the insertion rod 71, and the step with a larger diameter at the tail end of the insertion rod 71 abuts against the second fluid reinforcing glue 72, and the first fluid reinforcing glue 3 abuts against the tail end of the insertion rod 71. The second fluid reinforcing glue 72 should also be made of epoxy glue, polyurethane glue and other materials. After the second diaphragm 721 outside the second fluid reinforcing glue 72 is forcefully crushed by the insertion rod 71, the end of the insertion rod 71 will be inserted into the slot 61, so that the positioning of the docking tube 1 is achieved.

[0027] Reference Figure 1 and Figure 6 As shown, in order to cope with the centralized connection of multiple rows of multiple steel bars at the bottom of the structural beam, multiple main rods 6 are provided, and the cross-sectional shape of the main rod 6 can be circular or square, etc. At the same time, the docking tube 1 is slidably arranged on the main rod 6 according to the number of steel bars, and sleeves 62 are welded at both ends of the main rod 6. As an optimal embodiment, the sleeve 62 can be smaller than the cross-sectional size of the main rod 6 to facilitate the insertion of the docking tube 1 into the main rod 6, so as to achieve the installation and replacement of the docking tube 1. The sleeves 62 at both ends of the multiple main rods 6 are correspondingly penetrated with two series rods 8, and the two series rods 8 are provided with limited holes 81 along the length direction, and the sleeves 62 are penetrated with a limit rod 621, which is used to be snapped into the limit hole 81, so as to adjust the spacing of the multiple main rods 6.

[0028] In addition, a construction method for pre-embedded steel bars at the bottom of a structural beam is applicable to the connection device for pre-embedded steel bars at the bottom of a structural beam in the above scheme, comprising the following steps: S1: Align the butt joint groove 11 of the butt joint tube 1 with the end of one of the steel bars and insert and knock the butt joint tube 1; S2: Align the steel bar to be butted with the butt joint groove 11 at the upper end of the butt joint tube 1 and insert it, so that the insertion pin 21 pierces the first membrane 31, and the first fluid reinforcement glue 3 flows out from the first membrane 31, thereby bonding the steel bar and the butt joint tube 1; S3: Install the butt-jointing tubes 1 one by one to connect the steel bars and complete the butt-jointing of the steel bars.

[0029] The above are only preferred embodiments of the present invention and are not intended to limit the present invention. For those skilled in the art, the present invention may have various modifications and variations. Any modification, equivalent replacement, improvement, etc. made within the spirit and principle of the present invention shall be included in the protection scope of the present invention.

Claims

1. A connection device for pre-embedded steel bars at the bottom of a structural beam, Features: include: A docking sleeve (1), wherein both ends of the docking sleeve (1) in the length direction are provided with docking grooves (11), and the docking grooves (11) at both ends of the docking sleeve (1) are connected with clamping grooves (12) along the periphery; An elastic clamping plate (121), the elastic clamping plate (121) being arranged in the clamping groove (12), one end of the elastic clamping plate (121) being fixedly connected in the clamping groove (12), and the other end being arranged as a free end, and a clamping tooth (1211) being arranged on one side of the elastic clamping plate (121) close to the docking groove (11); A pull tab (2), wherein the pull tab (2) corresponds to the elastic clamp (121) one by one, one end of the pull tab (2) is fixedly connected to the elastic clamp (121), and one end of all the pull tabs (2) are fixedly connected together; A first fluid reinforcing glue (3), the first fluid reinforcing glue (3) being arranged in the first diaphragm (31) and arranged at the bottom of the docking groove (11); An insertion pin (21), the insertion pin (21) is fixedly connected to the pull tab (2) and is arranged toward the bottom wall of the docking groove (11), and is used to pull the pull tab (2) to drive the insertion pin (21) to puncture the first membrane (31) when the steel bar is inserted into the docking groove (11).

2. The connecting device for pre-embedded steel bars at the bottom of a structural beam according to claim 1, Features: The bottom wall of the docking tube (1) close to the docking groove (11) is provided with overflow glue holes (13) along the periphery. The overflow glue holes (13) are interconnected with the docking groove (11) and are arranged in a long strip shape.

3. The connecting device for pre-embedded steel bars at the bottom of a structural beam according to claim 1, Features: Both ends of the docking tube (1) are provided with docking parts (4), and the docking parts (4) include a plurality of mutually hinged snake bone joints (41), one end of the docking part (4) formed by the plurality of snake bone joints (41) is hingedly arranged with the docking tube (1), and the snake bone joints (41) are provided with through holes (411) for inserting steel bars, and swing gaps (42) are provided between adjacent snake bone joints (41).

4. The connecting device for pre-embedded steel bars at the bottom of a structural beam according to claim 3, Features: The docking groove (11) of the docking tube (1) and the inner wall of the snake bone joint (41) are both provided with a glue overflow groove (5) in the vertical direction.

5. The connecting device for pre-embedded steel bars at the bottom of a structural beam according to claim 3, Features: Each of the snake bone nodes (41) is provided with a plurality of slots (412) along the periphery thereof, wherein an elastic card (43) is arranged in the slot (412), wherein one end of the elastic card (43) is fixedly connected in the slot (412), and the other end is arranged as a free end and is used for being clamped to the side wall of the steel bar.

6. The connecting device for pre-embedded steel bars at the bottom of a structural beam according to claim 5, Features: The card slot (412) is arranged to penetrate the side wall of the snake bone joint (41), and a connecting hole (431) is opened through the elastic card (43).

7. The connecting device for pre-embedded steel bars at the bottom of a structural beam according to claim 1, Features: There are multiple docking cylinders (1), and a main rod (6) is arranged between the multiple docking cylinders (1). The main rod (6) penetrates the multiple docking cylinders (1) in the radial direction of the middle position of the docking cylinder (1), and each of the docking cylinders (1) is provided with a fixing member (7) for fixing the docking cylinder (1) to the main rod (6).

8. The connecting device for pre-embedded steel bars at the bottom of a structural beam according to claim 7, Features: The fixing member (7) is arranged in the docking groove (11) on one side of the docking tube (1), and the fixing member (7) comprises an insert rod (71) and a second fluid reinforcing glue (72). The insert rod (71) is slidably inserted into the bottom wall of the docking groove (11) along the axial direction of the docking tube (1). The main rod (6) is provided with a plurality of slots (61) along the length direction. The insert rod (71) is used to be inserted into the slots (61). The second fluid reinforcing glue (72) is arranged in the second diaphragm (721) and is annular in shape. The second fluid reinforcing glue (72) is sleeved on the insert rod (71), and the tail end of the insert rod (71) abuts against the second fluid reinforcing glue (72). At the same time, the first fluid reinforcing glue (3) abuts against the tail end of the insert rod (71).

9. The connecting device for pre-embedded steel bars at the bottom of a structural beam according to claim 8, Features: A plurality of main rods (6) are provided, and the docking sleeve (1) is correspondingly provided on the main rod (6). Sleeves (62) are fixedly provided at both ends of the main rod (6). Two serial rods (8) are correspondingly passed through the sleeves (62) at both ends of the plurality of main rods (6). Both serial rods (8) are provided with limiting holes (81) along the length direction. A limiting rod (621) is passed through the sleeve (62), and the limiting rod (621) is used to be snapped into the limiting hole (81).

10. A construction method for pre-embedded steel bars at the bottom of a structural beam, applicable to the connection device for pre-embedded steel bars at the bottom of a structural beam as claimed in any one of claims 1 to 9, Features: The following steps are involved: S1: Align the butt joint groove (11) of the butt joint tube (1) with the end of one of the steel bars and insert and knock the butt joint tube (1); S2: aligning the steel bar to be butted with the butt joint groove (11) at the upper end of the butt joint tube (1) and inserting it, so that the insertion needle (21) pierces the first membrane (31), and the first fluid reinforcement glue (3) flows out from the first membrane (31), thereby bonding the steel bar and the butt joint tube (1); S3: Install the butt joints (1) one by one to connect the steel bars and complete the butt joint of the steel bars.