Fabricated building roof with running water guiding structure
By designing a running water guide structure and an automatic garbage cleaning mechanism on the prefabricated roof, the water accumulation problem caused by debris accumulation in the roof drainage system is solved, which improves the service life and flow guide stability of the roof, and reduces operating costs.
Patent Information
- Application Number
- CN202411448534.0
- Authority / Receiving Office
- CN · China
- Patent Type
- Applications(China)
- Current Assignee / Owner
- Filing Date
- 2024-10-17
- Publication Date
- 2024-11-26
- Estimated Expiration
- Not applicable · inactive patent
AI Technical Summary
The drainage system of prefabricated roofs is easily affected by debris accumulation in windy and sandy areas, especially in heavy rain, rainwater cannot be discharged quickly, resulting in water accumulation, affecting the service life and drainage stability of the roof.
A prefabricated roof with a water-conducting structure is designed. Through the square holes and diversion mechanism on the outer wall of the frame, rainwater can enter the water pipe along the flow channel and discharge through the arc frame. Rainwater that has not entered the water pipe will continue to flow. At the drain outlet, the diversion mechanism effectively avoids rainwater being too concentrated, improving the flow diversion stability; at the same time, the garbage cleaning mechanism uses water pressure to drive the arc frame to flip, automatically clean up the garbage, reducing the cost of use and improving working stability.
It effectively avoids the accumulation of rainwater on the roof, improves the service life and flow diversion stability of prefabricated roofs, and reduces operating costs and improves cleaning efficiency through automatic garbage cleaning.
Smart Images

Figure CN119021432A_ABST
Abstract
Description
Technical Field
[0001] The invention relates to the technical field of assembled roofs, and in particular to an assembled building roof with a water flowing and guiding structure. Background Art
[0002] As an efficient construction method, the roof design of prefabricated buildings is crucial to the overall performance and service life of the building. Sloped roofs are widely used because of their good drainage performance, but over time, especially in windy and sandy areas, the roof drainage system may be affected by the accumulation of debris. In addition, when encountering heavy rain, rainwater quickly flows along the diversion groove and gathers at the drainage outlet. The water cannot be discharged quickly, which easily causes water accumulation. Summary of the invention
[0003] In order to overcome the above-mentioned technical problems, the purpose of the present invention is to provide an assembled building roof with a water-flowing water-guiding structure. The purpose of the present invention is to provide an assembled building roof with a water-flowing water-guiding structure. When it rains, rainwater will enter the diversion groove along the curvature of the outer wall of the frame. When passing through the diversion mechanism, part of the rainwater will enter the water pipe 2, and then be discharged from the arc frame along the square hole. The rainwater that has not entered the water pipe 2 will continue to flow along the diversion groove to the part between the frame and the square frame, and be discharged along the drain outlet. The diversion mechanism can effectively divert rainwater, especially when it rains heavily, to avoid rainwater being too concentrated in a certain place, causing water accumulation, effectively improving the stability of the diversion and the service life of the assembled roof mechanism.
[0004] An assembled building roof with a water-flowing and water-conducting structure, comprising:
[0005] The assembled roof structure comprises a frame, the outer walls at both ends of the frame are fixedly connected with square frames, and the outer walls of the square frames are provided with a plurality of square holes at equal intervals;
[0006] A diversion mechanism is used to divert and discharge rainwater. There are several diversion mechanisms, all of which are fixed in the guide groove of the frame;
[0007] The garbage cleaning mechanism is used to clean the garbage at the water outlet. Two garbage cleaning mechanisms are provided and are fixed on both sides of the outer wall of the frame near the center;
[0008] The garbage collecting mechanism is used for collecting garbage. Two garbage collecting mechanisms are arranged and are respectively fixed at two ends of the frame near the square frame.
[0009] Further, the assembled roof structure comprises:
[0010] A water tank 1 is arranged inside the square frame and below the square hole 1;
[0011] A filter frame 1 is fixed to the inner wall of the square hole 1 and is located at one end of the water tank 1;
[0012] Filter frame two is fixed on the outer wall of the square frame and is located at one end of the water tank.
[0013] Preferably: the assembled roof structure comprises:
[0014] Two water pipes are provided and are respectively fixed at two ends of the water tank;
[0015] The water tank is fixed to the bottom of the frame and is fixed to the water pipe end by end.
[0016] Preferably: the diversion mechanism comprises:
[0017] A second water pipe is fixed to the outer wall of the guide groove of the frame;
[0018] Two square plates are provided and fixed at both ends of water pipe 2 respectively;
[0019] The arc frame 1 is fixed to the outer wall of the guide groove of the frame and to one end of the water pipe 2.
[0020] Preferably: the garbage cleaning mechanism comprises:
[0021] A square tube fixed to the outer wall of the frame;
[0022] Round frame 1, fixed to the outer wall of one end of the square tube and fixed to the outer wall of the frame;
[0023] The second water tank is arranged inside the first round frame, and one end of the water tank is connected with the square tube;
[0024] The second arc frame slides inside the second water tank.
[0025] Preferably: the garbage cleaning mechanism comprises:
[0026] The arc frame 3 is fixed between the two arc frames 2, the rotating shaft of the arc frame 3 is rotatably connected to the outer wall of the round frame 1, and a coil spring is fixedly connected between the rotating shaft of the arc frame 3 and the outer wall of the round frame 1;
[0027] Two fixing seats are provided, which are respectively fixed to the outer walls at both ends of the square frame;
[0028] The scraper is fixed between the outer walls of the two fixing seats.
[0029] Preferably: the garbage cleaning mechanism comprises:
[0030] A semi-ring frame is fixed to the second outer wall of the arc frame;
[0031] The semi-ring groove is arranged inside the circular frame and is slidably plugged with the outer wall of the semi-ring frame.
[0032] Preferably: the garbage cleaning mechanism comprises:
[0033] A circular hole is provided on the second outer wall of the arc frame;
[0034] The second square plate is provided with two pieces, which are fixed at equal intervals on the inner wall of the circular hole;
[0035] Square holes 2 are provided with two holes, which are opened at equal angles on the inner wall of the circular hole;
[0036] A U-shaped clamping block slides inside the second square hole, and a spring is fixedly connected between the outer wall of the second square hole and the inner wall of the spring;
[0037] A round rod, sliding between two square plates;
[0038] The arc-shaped frames four are provided with two, fixed on the outer wall of the round rod at equal intervals, and plugged and matched with the U-shaped clamping blocks.
[0039] Preferably: the garbage cleaning mechanism comprises:
[0040] There are two circular grooves, which are respectively opened on the inner wall of the circular frame near the two ends of the water tank, and magnets are fixed inside the circular grooves;
[0041] The second round frame is fixed to one end of the round rod, and a magnet is fixed on the outer wall;
[0042] The round frame three is fixed at the other end of the round rod, and a magnet is fixed on the outer wall.
[0043] Preferably: the garbage collection mechanism comprises:
[0044] A rope winding wheel, fixed to the outer wall of the square frame at the center;
[0045] There are two sets of slide rails, which are respectively fixed to the bottom walls at both ends of the square frame, and a net fence is slidably inserted between the outer walls of the two sets of slide rails;
[0046] The traction rope is fixed on the outer wall of the fence along the rope winding wheel.
[0047] Beneficial effects of the present invention:
[0048] 1. The diversion mechanism can effectively divert rainwater, especially when it rains heavily, to avoid excessive concentration of rainwater in one place, resulting in water accumulation, effectively improving the stability of diversion and the service life of the assembled roof mechanism.
[0049] 2. The garbage cleaning mechanism drives the arc frame three to flip over by water pressure, so that the garbage can be poured out. No human operation and electric drive are required, which effectively reduces the cost of use and can effectively control the movement trajectory of the arc frame three. When it moves to one end, it can release water to reduce the water pressure, and then cooperate with the coil spring to make the arc frame three return to its original position, and seal the water release position so that water can be stored again, which effectively improves the working stability and mechanical linkage.
[0050] 3. Remove the fence by pulling the traction rope to facilitate cleaning, which effectively improves the convenience of cleaning. Finally, pull the fence up and fix the rope. BRIEF DESCRIPTION OF THE DRAWINGS
[0051] The present invention will be further described below in conjunction with the accompanying drawings.
[0052] Figure 1 It is a schematic diagram of the overall structure of the present invention;
[0053] Figure 2 It is a schematic diagram of the structure of the diversion mechanism in the present invention;
[0054] Figure 3 It is a schematic diagram of a partial cross-sectional structure of a middle frame in the present invention;
[0055] Figure 4 It is a schematic diagram of a partial cross-sectional structure of a circular frame in the present invention;
[0056] Figure 5 It is a schematic diagram of a cross-sectional structure of a circular frame in the present invention;
[0057] Figure 6 It is a partial structural schematic diagram of the garbage cleaning mechanism in the present invention;
[0058] Figure 7 This is a schematic diagram of the structure of the second arc frame in the present invention;
[0059] Figure 8 It is a schematic diagram of the fourth structure of the arc frame in the present invention;
[0060] Fig. 9 It is a schematic diagram of the structure of the garbage collection mechanism in the present invention.
[0061] In the figure: 100, assembled roof mechanism; 110, frame; 111, square frame; 112, square hole 1; 113, filter frame 1; 114, water tank 1; 115, filter frame 2; 120, water pipe 1; 121, water tank; 200, diversion mechanism; 210, water pipe 2; 211, square plate 1; 212, arc frame 1; 300, garbage cleaning mechanism; 310, square pipe; 320, round frame 1; 321, water tank 2; 322, semi-ring groove; 323 , circular groove; 330, arc frame two; 331, arc frame three; 332, semi-ring frame; 333, circular hole; 334, square plate two; 335, square hole two; 336, U-shaped block; 337, spring; 340, fixed seat; 341, scraper; 350, round rod; 351, circular frame two; 352, arc frame four; 353, circular frame three; 400, garbage collection mechanism; 410, rope wheel; 420, net fence; 421, traction rope; 422, slide rail. DETAILED DESCRIPTION
[0062] The following will be combined with the embodiments of the present invention to clearly and completely describe the technical solutions in the embodiments of the present invention. Obviously, the described embodiments are only part of the embodiments of the present invention, not all of the embodiments. Based on the embodiments of the present invention, all other embodiments obtained by ordinary technicians in this field without creative work are within the scope of protection of the present invention.
[0063] See also Figure 1-9As shown, an assembled building roof with a water flow and water diversion structure includes an assembled roof mechanism 100, which includes a frame 110 and the following parts: the outer walls at both ends of the frame 110 are fixedly connected with square frames 111, and the outer wall of the square frame 111 is provided with a plurality of square holes 112 at equal intervals, a diversion mechanism 200 is used to divert and discharge rainwater, and the diversion mechanism 200 is provided with a plurality of diversion mechanisms 200, which are all fixed in the diversion groove of the frame 110, and a garbage cleaning mechanism 300 is used to clean garbage at the water outlet, and the garbage cleaning mechanism 300 is provided with two, which are respectively fixed on the outer wall of the frame 110 near the center of both sides, and the garbage collecting mechanism 400 is used to collect garbage, and the garbage collecting mechanism 400 is provided with two, which are respectively fixed at both ends of the frame 110 near the square frame 1 11, its water tank 114 is opened inside the square frame 111 near the position below the square hole 112, and the filter frame 113 is fixed on the inner wall of the square hole 112 at one end of the water tank 114, and the filter frame 115 is fixed on the outer wall of the square frame 111 at one end of the water tank 114. There are two water pipes 120, which are respectively fixed at the two ends of the water tank 114, and the water tank 121 is fixed to the bottom of the frame 110 and fixed to one end of the water pipe 120. When water flows through the filter frame 113 and the filter frame 115, it will enter the inside of the water tank 114 and flow into the inside of the water tank 121 along the water pipe 120 to collect rainwater, which can be used for flushing toilets, etc., effectively reducing the cost of water resources used by residents. When the water tank 121 is full, the rainwater will be discharged from the water outlet or the square hole 112.
[0064] The diversion mechanism 200 includes the following parts: the water pipe 210 is fixed to the outer wall of the guide groove of the frame 110, and two square plates 211 are provided, which are respectively fixed at the two ends of the water pipe 210, and the arc frame 212 is fixed to the outer wall of the guide groove of the frame 110 and to one end of the water pipe 210. The diversion mechanism 200 can effectively divert rainwater, especially when it rains heavily, to avoid rainwater from being too concentrated in one place and causing water accumulation, thereby effectively improving the stability of the diversion and the service life of the assembled roof mechanism 100.
[0065] The garbage cleaning mechanism 300 includes the following parts: the square tube 310 is fixed to the outer wall of the frame 110, the round frame 1 320 is fixed to the outer wall of one end of the square tube 310 and is fixed to the outer wall of the frame 110, the water tank 2 321 is opened inside the round frame 1 320, and one end is connected to the square tube 310, the arc frame 2 330 slides inside the water tank 2 321, and the arc frame 3 331 is fixed between the two arc frames 2 330. The rotating shaft of the arc frame 331 is rotatably connected to the outer wall of the round frame 1 320, and the arc frame 3 The rotating shaft of the frame 331 is fixedly connected with the outer wall of the round frame 1 320 by a coil spring. The arc frame 331 is turned over by water pressure to dump the garbage. No human operation and electric drive are required, which effectively reduces the use cost. The fixed seat 340 is provided with two scrapers 341 fixed to the outer walls of the two ends of the square frame 111, and the scrapers 341 are fixed between the outer walls of the two fixed seats 340. The scrapers 341 can scrape off the garbage stuck on the arc frame 331, effectively improving the cleaning efficiency. The semi-ring frame 332 is fixed to the arc frame 111. The outer wall of the arc frame 2 330, the semi-ring groove 322 is opened inside the circular frame 1 320, and is slidably plugged with the outer wall of the semi-ring frame 332, the circular hole 333 is opened on the outer wall of the arc frame 2 330, and the square plate 2 334 is provided with two, which are fixed at equal intervals on the inner wall of the circular hole 333, and the square hole 2 335 is provided with two, which are opened at equal angles on the inner wall of the circular hole 333, and the U-shaped block 336 slides inside the square hole 2 335, and the spring 337 is fixedly connected between the outer wall of the square hole 2 335 and the inner wall of the spring 337, and the round rod 350 slides between the two square plates 334, and two arc-shaped frames 352 are provided, which are fixed on the outer wall of the round rod 350 at equal intervals and plugged with the U-shaped block 336. There are two circular grooves 323, which are respectively opened on the inner wall of the circular frame 1 320 near the two ends of the water tank 2 321, and magnets are fixed inside the circular grooves 323. The circular frame 2 351 is fixed to one end of the round rod 350, and a magnet is fixed to the outer wall. The circular frame 353 is fixed to the other end of the round rod 350, and a magnet is fixed to the outer wall.
[0066] The garbage collection mechanism 400 includes the following parts: its rope winding wheel 410 is fixed to the outer wall of the square frame 111 at the center, and two groups of slide rails 422 are provided, which are respectively fixed to the bottom walls at both ends of the square frame 111, and a net fence 420 is slidably inserted between the outer walls of the two groups of slide rails 422, and its traction rope 421 is fixed to the outer wall of the net fence 420 along the rope winding wheel 410. The garbage scraped off by the garbage cleaning mechanism 300 will fall into the inside of the net fence 420. The staff can remove the net fence 420 by pulling the traction rope 421, which is convenient for cleaning, effectively improving the convenience of cleaning, and finally pull up the net fence 420 and fix the rope.
[0067] Specifically, when it rains, rainwater will flow into the guide groove along the curvature of the outer wall of the frame 110. When passing through the diversion mechanism 200, part of the rainwater will enter the water pipe 210, and then be discharged from the arc frame 1 212 along the square hole 112. The rainwater that has not entered the water pipe 210 will continue to flow along the guide groove to the area between the frame 110 and the square frame 111, and be discharged along the drain port. When the water flows through the filter frame 1 113 and the filter frame 2 115, it will enter the inside of the water tank 1 114. And it flows into the water tank 121 along the water pipe 120, and the rainwater is collected and can be used for flushing toilets, etc., which effectively reduces the cost of water resources used by residents. When the water tank 121 is full, the rainwater will be discharged from the water outlet or the square hole 112. When it rains, the rainwater will flow into the square tube 310 along the diversion hole on the top of the frame 110. When the water in the square tube 310 reaches a certain amount, the water pressure will push the arc frame 2 330 to slide along the track of the water tank 2 321, driving the arc frame 331 to flip During this period, one end of the scraper 341 will generate friction with the outer wall of the moving arc frame 331 to scrape off the garbage accumulated on it. When the arc frame 2 330 is moved to one end of the water tank 2 321 under pressure, the magnet inside the circular groove 323 will attract the circular frame 353, so that the round rod 350 moves to the circular frame 353 and separates from the outer wall of the arc frame 2 330, thereby releasing the seal. The corresponding arc frame 4 352 is plugged into and matched with the U-shaped block 336, and water will be discharged along the circular hole 333, reducing the water inside the square tube 310. The arc frame three 331 is affected by the coil spring and slowly returns to its original position. The magnet inside the other circular groove 323 attracts the circular frame two 351, so that the round rod 350 moves to the circular frame three 353 and plugs into the circular hole 333 for sealing. The garbage scraped off by the garbage cleaning mechanism 300 falls into the net fence 420. The staff can remove the net fence 420 by pulling the traction rope 421 to facilitate cleaning, which effectively improves the convenience of cleaning. Finally, the net fence 420 is pulled up and the rope is fixed.
[0068] Embodiment 1
[0069] like Figure 2 As shown, in this embodiment, the diversion mechanism 200 includes the following parts: the water pipe 210 is fixed to the outer wall of the guide groove of the frame 110, and two square plates 211 are provided, which are respectively fixed at the two ends of the water pipe 210, and the arc frame 212 is fixed to the outer wall of the guide groove of the frame 110 and fixed to one end of the water pipe 210.
[0070] In this embodiment, when it rains, rainwater will enter the guide groove along the curvature of the outer wall of the frame 110. When passing through the diversion mechanism 200, part of the rainwater will enter the water pipe 2 210, and then be discharged from the arc frame 1 212 along the square hole 112. The rainwater that has not entered the water pipe 2 210 will continue to flow along the guide groove to the area between the frame 110 and the square frame 111, and be discharged along the drain outlet. The diversion mechanism 200 can effectively divert rainwater, especially when it rains heavily, to avoid rainwater being too concentrated in one place, causing water accumulation, thereby effectively improving the stability of the diversion and the service life of the assembled roof mechanism 100.
[0071] like Figure 4 and 8 As shown, in this embodiment, the garbage cleaning mechanism 300 includes the following parts: the square tube 310 is fixed to the outer wall of the frame 110, the round frame 1 320 is fixed to the outer wall of one end of the square tube 310 and is fixed to the outer wall of the frame 110, the water tank 2 321 is opened inside the round frame 1 320, and one end is connected to the square tube 310, the arc frame 2 330 slides inside the water tank 2 321, and the arc frame 331 is fixed between the two arc frames 2 330. The rotating shaft of the arc frame 331 is rotatably connected to the outer wall of the round frame 1 320, and a coil spring is fixedly connected between the rotating shaft of the arc frame 331 and the outer wall of the round frame 1 320. The fixed seat 340 is provided with two outer walls fixed to the two ends of the square frame 111, and the scraper 341 is fixed between the outer walls of the two fixed seats 340. The semi-ring frame 332 is fixed to the outer wall of the arc frame 2 330. The semi-ring groove 322 is opened inside the round frame 1 320 and is connected to the outer wall of the semi-ring frame 332. The circular hole 333 is provided on the outer wall of the arc frame 330, and the square plate 334 is provided with two, which are fixed at equal intervals on the inner wall of the circular hole 333, and the square hole 335 is provided with two, which are provided at equal angles on the inner wall of the circular hole 333, and the U-shaped block 336 slides inside the square hole 335, and the spring 337 is fixedly connected between the outer wall of the square hole 335 and the inner wall of the spring 337, and the round rod 350 slides between the two, between the square plate 334 There are two arc-shaped frames 352, which are fixed on the outer wall of the round rod 350 at equal intervals and are plugged into the U-shaped block 336. There are two circular grooves 323, which are respectively opened on the inner wall of the circular frame 1 320 near the two ends of the water tank 2 321, and magnets are fixed inside the circular grooves 323. The circular frame 2 351 is fixed to one end of the round rod 350, and a magnet is fixed to the outer wall. The circular frame 353 is fixed to the other end of the round rod 350, and a magnet is fixed to the outer wall.
[0072] In specific implementation, when it rains, rainwater will flow into the square tube 310 through the diversion hole at the top of the frame 110. When the water inside the square tube 310 reaches a certain amount, the water pressure will push the arc frame 2 330 to slide along the track of the water tank 2 321, driving the arc frame 3 331 to flip. The arc frame 3 331 is driven to flip by water pressure, so that the garbage can be poured out. No human operation and electric drive are required, which effectively reduces the cost of use. During this period, one end of the scraper 341 will generate friction with the outer wall of the moving arc frame 3 331 to scrape off the garbage accumulated on it. The scraper 341 can scrape off the garbage stuck on the arc frame 3 331, effectively improving the cleaning efficiency. When the arc frame 2 330 is moved to one end of the water tank 2 321 under pressure, the magnet inside the circular groove 323 will adsorb the circular frame 3 353, so that the round rod 350 moves to the circular frame three 353 and separates from the outer wall of the arc frame two 330 to release the seal, and the corresponding arc frame four 352 is plugged into the U-shaped block 336, and the water will be discharged along the circular hole 333 to reduce the water pressure inside the square tube 310. The arc frame three 331 is affected by the coil spring and slowly returns to the original position, and the magnet inside the other circular groove 323 will absorb the circular frame two 351, so that the round rod 350 moves to the circular frame three 353 and plugs into the circular hole 333 for sealing. Through this mechanism, the movement trajectory of the arc frame three 331 can be effectively controlled. When it moves to one end, the water pressure can be reduced by draining water, and then the coil spring is used to return the arc frame three 331 to the original position, and the water drain position is sealed so that water can be stored again, effectively improving the working stability and mechanical linkage.
[0073] Embodiment 2
[0074] like Fig. 9 As shown, the garbage collection mechanism 400 includes the following parts: its rope winding wheel 410 is fixed to the outer wall of the square frame 111 at the center, and two groups of slide rails 422 are provided, which are respectively fixed to the bottom walls at both ends of the square frame 111, and a net fence 420 is slidably inserted between the outer walls of the two groups of slide rails 422, and its traction rope 421 is fixed to the outer wall of the net fence 420 along the rope winding wheel 410.
[0075] During specific implementation, the garbage scraped off by the garbage cleaning mechanism 300 will fall into the inside of the net fence 420. The staff can remove the net fence 420 by pulling the traction rope 421 to facilitate cleaning, which effectively improves the convenience of cleaning. Finally, the net fence 420 is pulled up and the rope is fixed.
[0076] In the description of this specification, the description with reference to the terms "one embodiment", "example", "specific example", etc. means that the specific characteristic structure materials or features described in conjunction with the embodiment or example are included in at least one embodiment or example of the present invention. In this specification, the schematic representation of the above terms does not necessarily refer to the same embodiment or example. Moreover, the specific characteristic structure materials or features described can be combined in any one or more embodiments or examples in a suitable manner.
[0077] The above contents are merely examples and explanations of the present invention. Those skilled in the art may make various modifications or additions to the specific embodiments described or replace them in a similar manner. As long as they do not deviate from the invention or exceed the scope defined by the claims, they shall all fall within the protection scope of the present invention.
Claims
1. An assembled building roof with a water-flowing water-conducting structure, characterized in that: include: The assembled roof structure (100) comprises a frame (110), the outer walls at both ends of the frame (110) are fixedly connected with square frames (111), and the outer walls of the square frames (111) are provided with a plurality of square holes (112) at equal intervals; A diversion mechanism (200) is used to divert and discharge rainwater. A plurality of diversion mechanisms (200) are provided and are all fixed in the guide groove of the frame (110); A garbage cleaning mechanism (300) is used to clean garbage at the water outlet. Two garbage cleaning mechanisms (300) are provided and are respectively fixed to the outer wall of the frame (110) at positions close to both sides of the center. The garbage collection mechanism (400) is used to collect garbage. Two garbage collection mechanisms (400) are provided and are respectively fixed at two ends of the frame (110) near the square frame (111).
2. The assembled building roof with a water-flowing and water-conducting structure according to claim 1, characterized in that: The assembled roof structure (100) comprises: A water tank (114) is provided inside the square frame (111) and is located below the square hole (112); A filter frame (113) is fixed to the inner wall of the square hole (112) and located at one end of the water tank (114); The second filter frame (115) is fixed on the outer wall of the square frame (111) and is located at one end of the first water tank (114).
3. The assembled building roof with a water-flowing and water-conducting structure according to claim 2, characterized in that: The assembled roof structure (100) comprises: Two water pipes (120) are provided and are fixed at two ends of the water tank (114) respectively; The water tank (121) is fixed to the bottom of the frame (110) and is fixed to one end of the water pipe (120).
4. The assembled building roof with a water-flowing and water-conducting structure according to claim 3 is characterized in that: The diversion mechanism (200) comprises: A second water pipe (210) is fixed to the outer wall of the guide groove of the frame (110); Two square plates (211) are provided and are fixed at both ends of water pipe (210) respectively; The arc frame 1 (212) is fixed to the outer wall of the guide groove of the frame (110) and is fixed to one end of the water pipe 2 (210).
5. The assembled building roof with a water-flowing and water-conducting structure according to claim 4, characterized in that: The garbage cleaning mechanism (300) comprises: A square tube (310) is fixed to the outer wall of the frame (110); A round frame (320) is fixed to the outer wall of one end of the square tube (310) and is fixed to the outer wall of the frame (110); The second water tank (321) is disposed inside the first round frame (320) and one end of the water tank is connected to the square tube (310); The second arc frame (330) slides inside the second water tank (321).
6. The assembled building roof with a water-flowing and water-conducting structure according to claim 5, characterized in that: The garbage cleaning mechanism (300) comprises: The arc frame 3 (331) is fixed between the two arc frames 2 (330), the rotating shaft of the arc frame 3 (331) is rotatably connected to the outer wall of the circular frame 1 (320), and a coil spring is fixedly connected between the rotating shaft of the arc frame 3 (331) and the outer wall of the circular frame 1 (320); Two fixing seats (340) are provided and are respectively fixed to the outer walls at both ends of the square frame (111); The scraper (341) is fixed between the outer walls of the two fixing seats (340).
7. The assembled building roof with a water-flowing and water-conducting structure according to claim 6, characterized in that: The garbage cleaning mechanism (300) comprises: A semi-ring frame (332) is fixed to the outer wall of the second arc-shaped frame (330); The semi-ring groove (322) is provided inside the circular frame (320) and is slidably plugged with the outer wall of the semi-ring frame (332).
8. The assembled building roof with a water-flowing and water-conducting structure according to claim 7, characterized in that: The garbage cleaning mechanism (300) comprises: A circular hole (333) is formed on the outer wall of the second arc-shaped frame (330); Two square plates (334) are provided and fixed at equal intervals on the inner wall of the circular hole (333); Two square holes (335) are provided and are opened at equal angles on the inner wall of the circular hole (333); A U-shaped block (336) slides inside the second square hole (335), and a spring (337) is fixedly connected between the outer wall of the second square hole (335) and the inner wall of the spring (337); A round rod (350) slides between two square plates (334); There are two arc-shaped frames (352) which are fixed on the outer wall of the round rod (350) at equal intervals and are plugged into and matched with the U-shaped clamping block (336).
9. The assembled building roof with a water-flowing and water-conducting structure according to claim 8, characterized in that: The garbage cleaning mechanism (300) comprises: There are two circular grooves (323), which are respectively opened on the inner wall of the circular frame (320) near the two ends of the water tank (321), and magnets are fixed inside the circular grooves (323); The second round frame (351) is fixed to one end of the round rod (350), and a magnet is fixed on the outer wall; The round frame three (353) is fixed to the other end of the round rod (350), and a magnet is fixed on the outer wall.
10. The assembled building roof with a water-flowing and water-conducting structure according to claim 9, characterized in that: The garbage collection mechanism (400) comprises: A rope winding wheel (410) is fixed to the outer wall of the square frame (111) at the center; Two sets of slide rails (422) are provided, which are respectively fixed to the bottom walls at both ends of the square frame (111), and a net fence (420) is slidably inserted between the outer walls of the two sets of slide rails (422); The traction rope (421) is fixed on the outer wall of the net fence (420) along the rope winding wheel (410).