Assembly equipment for insert bearing

By designing external spherical bearing assembly equipment, using components such as mounting support, bending support rod and position adjustment mechanism, the problem of multiple movement of components during the assembly process of existing technology in foreign spherical bearings is solved, and more efficient assembly speed and Accuracy.

CN119021993AInactive Publication Date: 2024-11-26HEBEI BOREN BEARING TECHNOLOGY CO LTD
View PDF 0 Cites 2 Cited by

Patent Information

Application Number
CN202411236028.5
Authority / Receiving Office
CN · China
Patent Type
Applications(China)
Current Assignee / Owner
Filing Date
2024-09-04
Publication Date
2024-11-26
Estimated Expiration
Not applicable · inactive patent

AI Technical Summary

Technical Problem

During the assembly process of existing spherical bearings, moving parts between multiple auxiliary equipment is required, resulting in large labor and material consumption and slow assembly speed.

Method used

An outer spherical bearing assembly equipment is designed, including mounting support, circular support, bending support rod, placement pallet, position adjustment mechanism and grease injection assembly, through which the stable installation and lubrication of steel balls and cages are achieved Oil injection reduces component transfer and improves assembly efficiency.

Benefits of technology

The equipment ensures stable position when installing cages and steel balls, improves assembly speed and accuracy, and completes the installation of steel balls and cages through continuous operation, significantly improving the assembly speed of outer spherical bearings.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN119021993A_ABST
    Figure CN119021993A_ABST
Patent Text Reader

Abstract

The invention relates to the technical field of bearing assembly, and provides insert bearing assembly equipment which comprises a mounting support, a circular support and a placement tray, stamping equipment is arranged at the top of the mounting support, the circular support is fixedly connected to the mounting support, a plurality of bent supporting rods are fixedly connected to the inner wall of the circular support, and the placement tray is fixedly connected to the inner wall of the circular support. A grease injection assembly is arranged between the multiple bent supporting rods and the mounting support, the containing tray is arranged between the multiple bent supporting rods in a sliding mode, and a lifting moving assembly is arranged between the containing tray and the mounting support. By means of the technical scheme, the problems that in the prior art, in the assembling process of the insert bearing, when the insert bearing needs to be subjected to assembling work of different procedures, all parts are driven to move among multiple auxiliary assembling devices, and the assembling efficiency is high are solved. Therefore, manpower and material resources in the assembly process of the insert bearing are improved, and the assembly speed of the insert bearing is reduced.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The invention relates to the technical field of bearing assembly, and in particular to an outer spherical bearing assembly device. Background Art

[0002] The outer spherical bearing is a type of bearing in the prior art. The bearing is a component used to reduce the friction between the shaft and the components during the rotation of the shaft and to support the shaft. As the use environment and the equipment used are different, there are certain differences in the appearance of different bearings. The outer spherical bearing is a type of deep groove ball bearing. The main difference between the outer spherical bearing and the ordinary bearing is that the outer diameter surface of the outer ring is spherical. During the assembly process of the outer spherical bearing, a plurality of steel balls are usually placed between the inner ring and the outer ring of the bearing, and then a positioner composed of a plurality of positioning rods is used to determine the steel balls in the inner ring of the bearing. and the outer ring of the bearing, and then use a stamping device to fix and install a retaining frame between the inner ring of the bearing, the outer ring of the bearing and multiple steel balls (in order to facilitate installation, the retaining frame of the prior art usually uses two semicircular retaining frames, and when installing the retaining frame, the retaining frames are installed on both sides of the outer ring of the bearing and the inner ring of the bearing), the position between the multiple steel balls is kept fixed by the retaining frame, and the multiple steel balls are ensured to rotate stably between the inner ring of the bearing and the outer ring of the bearing during rotation, and then lubricating grease is injected between the multiple steel balls, and finally a sealing ring is installed between the inner ring of the bearing and the outer ring of the bearing to complete the assembly of the external spherical bearing.

[0003] Therefore, according to the above-mentioned summary of the assembly method of the outer spherical bearing, the process of assembling the outer spherical bearing includes moving in the steel ball, determining the position of the steel ball, installing the retaining frame, injecting lubricating grease and installing the sealing ring. Because different equipment is needed to assist in the different assembly steps of the outer spherical bearing, for example, the position of the steel ball in the outer ring and the inner ring of the bearing is determined by a positioner, and when installing the retaining frame, a stamping device is needed to fix the retaining frame between the outer ring and the inner ring of the bearing. When it is necessary to inject lubricating grease into the bearing, the assembled bearing outer ring, bearing inner ring, steel ball and retaining frame need to be moved to a special device for injecting lubricating grease for operation. Therefore, in the assembly process of the outer spherical bearing in the prior art, the bearing needs to be moved between multiple auxiliary equipment. This assembly method not only needs to install more equipment, uses more manpower and slows down the assembly speed of the outer spherical bearing. Summary of the invention

[0004] The present invention proposes an outer spherical bearing assembly device, which solves the problem in the related art that during the outer spherical bearing assembly process, the outer spherical bearing needs to be driven to move various components between multiple auxiliary assembly devices when performing assembly operations in different steps, thereby improving the manpower and material resources of the outer spherical bearing assembly process and slowing down the outer spherical bearing assembly speed.

[0005] The technical solution of the present invention is as follows: an outer spherical bearing assembly device, comprising a mounting support, a stamping device is arranged on the top of the mounting support, and further comprising: A circular support, the circular support is fixedly connected to the mounting support, a plurality of bent support rods are fixedly connected to the inner wall of the circular support, and a grease injection assembly is provided between the plurality of bent support rods and the mounting support; A placement tray, wherein the placement tray is slidably arranged between the plurality of the bent support rods, a lifting and moving assembly is arranged between the placement tray and the mounting support, two bearing ring placement assemblies are arranged on the placement tray, the bearing ring placement assemblies are used to place the outer ring of the bearing or the inner ring of the bearing, and a steel ball lifting assembly is arranged on the placement tray; A position adjustment mechanism, wherein the position adjustment mechanism is arranged on the circular support, and the bearing ring placement component and the steel ball lifting component both cooperate with the position adjustment mechanism; An annular stamping die is provided on the output end of the stamping equipment, and the annular stamping die is located on the upper side of the steel ball lifting assembly.

[0006] In order to inject lubricating grease into between multiple steel balls, further, the grease injection assembly includes an injection pipe, a delivery pump device and a semi-cylinder. The injection pipe is fixedly connected to the inside of multiple bent support rods. The delivery pump device is arranged on the mounting support. The semi-cylinder is connected between multiple injection pipes located on the same side, and the output end of the delivery pump device is connected to the multiple semi-cylinders through a multi-directional delivery pipe.

[0007] In order to adjust the position of the placement tray between multiple bent support rods, further, the lifting and moving assembly includes a rotating cylinder, a lifting screw and an elastic connection structure, the middle part of the mounting support is fixedly connected to a rotating ring, the rotating cylinder is rotatably connected in the rotating ring, a threaded seat is provided on the top of the rotating cylinder, a rotating assembly is provided between the rotating cylinder and the mounting support, the lifting screw is threadedly connected to the threaded seat, a sliding groove is provided on the lifting screw, a sliding member is slidably connected to the sliding groove, the sliding member is fixedly connected to the mounting support, and the elastic connection structure is provided between the lifting screw and the placement tray.

[0008] In order to avoid damage to components such as the lifting screw when installing the retaining frame, the elastic connection structure further includes a sliding sleeve, a sliding rod and a spring damper. The sliding sleeve is fixedly connected to the top of the lifting screw, and the bottom of the tray is fixedly connected to the sliding rod. The sliding rod is slidably arranged in the sliding sleeve, and the spring damper is arranged between the bottom end of the sliding rod and the inner wall of the sliding sleeve.

[0009] In order to place the outer ring or the inner ring of the bearing, on the basis of the present solution, the bearing ring placement assembly includes an arc-shaped support bar and a connecting piece, the number of the arc-shaped support bars is set to two, a groove is provided on the placement tray corresponding to the arc-shaped support bar, the arc-shaped support bar is located in the corresponding groove, two connecting pieces are fixedly connected between the two arc-shaped support bars, and the connecting piece is slidably connected to the placement tray.

[0010] In order to keep multiple steel balls stable when installing the retaining frame, on the basis of the present solution, further, the steel ball lifting assembly includes an annular support and a support member, a groove is also provided on the placement tray corresponding to the annular support, the annular support is located in the corresponding annular support, a plurality of arc grooves are provided on the annular support, the support members are fixedly connected to both sides of the bottom of the annular support, and the support member is slidably connected to the placement tray.

[0011] In order to keep the arc-shaped support bar and the annular support fixed after adjusting the position, on the basis of the above-mentioned scheme, it also includes a magnetic fixing component, which is arranged between the connecting member and the placing tray, and the magnetic fixing component is also arranged between the supporting member and the placing tray. The magnetic fixing component includes an electromagnetic sleeve and an iron bar. The number of the electromagnetic sleeves is set to multiple, and the electromagnetic sleeve is arranged at the bottom of the placing tray. The connecting member or the supporting member is slidably arranged inside the corresponding electromagnetic sleeve. Multiple iron bars are fixedly connected to the connecting member and the supporting member, and the iron bar is magnetically connected to the electromagnetic sleeve.

[0012] In order to adjust the position of the arc-shaped support bar and the annular support on the tray, on the basis of the present solution, further, the position adjustment mechanism includes a pushing seat and a position moving component, the number of the pushing seats is set to two, the pushing seat is used to drive the connecting member or the supporting member to move longitudinally, and the position moving component is provided on both sides of the top of the circular support.

[0013] In order to adjust the position of the pushing seat, on the basis of the above-mentioned scheme, further, the position moving assembly includes a sliding frame, a transmission screw, a mounting seat and a driving electric cylinder, the sliding frame is fixedly connected to the circular support, the transmission screw is rotatably connected in the sliding frame, a first driving motor is arranged on the sliding frame, the output end of the first driving motor is fixedly connected to the transmission screw, the mounting seat is slidably connected in the sliding frame, the mounting seat is threadedly connected to the transmission screw, the driving electric cylinder is arranged on the mounting seat, and the pushing seat is arranged on the output end of the driving electric cylinder.

[0014] In order to make the bottom of the annular stamping die match the shape of the retaining frame, based on the present solution, further, a matching groove is provided at the bottom of the annular stamping die.

[0015] The working principle and beneficial effects of the present invention are: 1. In the present invention, when it is necessary to complete the installation of the steel balls and the retaining frame of the outer spherical bearing and inject lubricating grease between the multiple steel balls located between the inner ring of the bearing, the outer ring of the bearing and the retaining frame, the steel ball is first placed between the outer ring of the bearing and the inner ring of the bearing, and then the outer ring of the bearing and the inner ring of the bearing are respectively placed between two corresponding arc support bars on the placement tray, and the height of different arc support bars is adjusted by a position adjustment mechanism so that the outer ring of the bearing corresponds to the inner ring of the bearing, and the steel balls maintain the same spacing under the action of multiple bent support rods, and the height of the annular support is adjusted by the position adjustment mechanism so that the multiple arc grooves on the annular support fit with the bottom of the steel ball, so that the position of the steel ball is kept fixed between the outer ring of the bearing and the inner ring of the bearing.

[0016] 2. In the present invention, when it is necessary to place the retainer between the bearing outer ring, the bearing inner ring and the steel ball, the shape of the retainer is irregular because the shape of the retainer is adapted to the steel ball. In the prior art, the retainer is installed after the steel ball is placed and then moved to the stamping equipment. During the transportation process, the steel ball is easily displaced between the bearing outer ring and the bearing inner ring. In the process of installing the retainer, the present application always ensures that the position of the steel ball between the bearing outer ring and the bearing inner ring remains unchanged, so it can be ensured that when the retainer is installed, the position between the retainer and the plurality of steel balls remains corresponding. When the stamping equipment is used to drive the annular stamping die to descend, the matching groove at the bottom of the annular stamping die can also be kept in contact with the end face of the retainer, and the corresponding relationship between the retainer and the plurality of steel balls is further determined. Then, the stamping equipment is started to drive the annular stamping die to descend, so that the retainer is fixedly installed between the plurality of steel balls. The installation method between the retainer and the steel balls of the present application not only improves the installation speed of the retainer, but also ensures that the installation between the retainer and the steel balls is sufficiently accurate. 3. In the present invention, after the installation of the retainer and the steel balls is completed, when the placement tray is driven to rise, when the outer ring of the bearing, the inner ring of the bearing, the steel balls and the retainer are about to be moved out from between the multiple bent support rods, a grease injection assembly is used to inject grease between the multiple steel balls to complete the oiling operation of the outer spherical bearing; 4. Therefore, the outer spherical bearing assembly equipment can avoid excessive transportation of various components during the installation process between the bearing outer ring, the bearing inner ring, the steel ball and the cage, and complete the installation work between the steel ball and the cage with high continuity, thereby improving the assembly speed of the outer spherical bearing. BRIEF DESCRIPTION OF THE DRAWINGS

[0017] The present invention will be further described in detail below in conjunction with the accompanying drawings and specific embodiments.

[0018] Figure 1 It is a schematic diagram of the overall structure of the present invention; Figure 2 It is a schematic diagram of the structure of a partial cross-section of the present invention; Figure 3 It is a structural schematic diagram of a partial cross-section from another viewing angle of the present invention; Figure 4 For the present invention Figure 3 A schematic diagram of the local enlarged structure at point A in the middle; Figure 5 It is a partial cross-sectional structural diagram of the grease injection assembly, the lifting and moving assembly, the bearing ring placement assembly, the steel ball lifting assembly and the position adjustment mechanism in the present invention; Figure 6 It is a schematic diagram of a partial cross-section of the structure of the placement tray and the lifting and moving assembly in the present invention; Figure 7 For the present invention Figure 6 A schematic diagram of the local enlarged structure at B in the middle; Figure 8 It is a schematic diagram of a partial cross-section of the structure of the placement tray, the grease injection assembly and the position adjustment mechanism in the present invention; Fig. 9 It is a schematic diagram of a partial cross-section of the structure of the placement tray, the bearing ring placement assembly, the steel ball lifting assembly and the magnetic fixing assembly in the present invention; Fig.10 For the present invention Fig. 9 Schematic diagram of the local enlarged structure at point C in the middle.

[0019] In the figure: 100, grease injection assembly; 200, lifting and moving assembly; 300, bearing ring placement assembly; 400, steel ball lifting assembly; 500, magnetic fixing assembly; 600, position adjustment mechanism; 1. Mounting support; 2. Stamping equipment; 3. Circular support; 4. Bending support rod; 5. Placing tray; 6. Annular stamping die; 7. Injection pipe; 8. Delivery pump equipment; 9. Semi-cylinder; 10. Rotating cylinder; 11. Rotating ring; 12. Threaded seat; 13. Lifting screw; 14. Sliding part; 15. Sliding sleeve; 16. Sliding rod; 17. Spring damper; 18. Arc support bar; 19. Connecting part; 20. Annular support; 21. Arc groove; 22. Support part; 23. Electromagnetic sleeve; 24. Iron strip; 25. Push seat; 26. Sliding frame; 27. Transmission screw; 28. First drive motor; 29. ​​Mounting seat; 30. Driving electric cylinder; 31. Matching groove; 32. Second drive motor; 33. Transmission gear. DETAILED DESCRIPTION The following will be combined with the embodiments of the present invention to clearly and completely describe the technical solutions in the embodiments of the present invention. Obviously, the described embodiments are only part of the embodiments of the present invention, not all of the embodiments. Based on the embodiments of the present invention, all other embodiments obtained by ordinary technicians in this field without creative work are within the scope of protection of the present invention.

[0020] like Figures 1 to 10 As shown, this embodiment proposes an outer spherical bearing assembly device, including a mounting support 1, and a stamping device 2 is arranged on the top of the mounting support 1. The stamping device 2 is a common device in the prior art for driving parts to move quickly, and is a prior art device well known to technical personnel in this field. When it is necessary to install a retaining frame between multiple steel balls, it is necessary to use the stamping device 2 to drive the retaining frame to be quickly installed between the multiple steel balls.

[0021] like Figures 1 to 3 and Figure 8As shown, it also includes a circular support 3, which is fixedly connected to the mounting support 1. A plurality of bent support rods 4 are fixedly connected to the inner wall of the circular support 3. A grease injection assembly 100 is arranged between the plurality of bent support rods 4 and the mounting support 1. The grease injection assembly 100 includes an injection pipe 7, a delivery pump device 8 and a semi-cylinder 9. The interiors of the plurality of bent support rods 4 are all fixedly connected with injection pipes 7. The delivery pump device 8 is arranged on the mounting support 1. The plurality of injection pipes 7 on the same side are connected with a semi-cylinder 9. The output end of the delivery pump device 8 is connected with the plurality of semi-cylinders 9 through a multi-directional delivery pipe. When the operation of installing the retainer between the plurality of steel balls is completed, in order to improve the subsequent outer spherical surface In order to ensure the smooth movement of the steel balls during the use of the bearing, it is necessary to add lubricating grease between multiple steel balls. During the use of the present application, after driving the placement tray 5 to move upward and moving multiple steel balls to the top area of ​​multiple bent support rods 4, the lubricating grease is driven into the semi-cylindrical body 9 through the delivery pump device 8, and then the lubricating grease is allowed to enter the injection pipe 7, and finally the lubricating grease is discharged through the injection pipe 7, so that the lubricating grease is added between multiple steel balls, completing the oiling operation of the assembled outer spherical bearing. The delivery pump device 8 is a pump device in the prior art used to transport liquids with a certain viscosity, and is a prior art device known to technicians in this field.

[0022] like Figures 1 to 10As shown, the placement tray 5 is slidably arranged between a plurality of bent support rods 4, a lifting and moving assembly 200 is arranged between the placement tray 5 and the mounting support 1, two bearing ring placement assemblies 300 are arranged on the placement tray 5, the bearing ring placement assembly 300 is used to place the outer ring of the bearing or the inner ring of the bearing, a steel ball lifting assembly 400 is arranged on the placement tray 5, the lifting and moving assembly 200 includes a rotating cylinder 10, a lifting screw 13 and an elastic connection structure, a rotating ring 11 is fixedly connected to the middle of the mounting support 1, and the rotating cylinder 10 is rotatably connected to the rotating ring 1 1, a threaded seat 12 is arranged on the top of the rotating cylinder 10, a rotating assembly is arranged between the rotating cylinder 10 and the mounting support 1, the rotating assembly includes a second driving motor 32, the second driving motor 32 is arranged on the mounting support 1, a transmission gear 33 is arranged on the output end of the second driving motor 32 and the rotating cylinder 10, the two transmission gears 33 are meshed, the lifting screw 13 is threadedly connected with the threaded seat 12, a sliding groove is opened on the lifting screw 13, a sliding member 14 is slidably connected to the sliding groove, the sliding member 14 is fixedly connected to the mounting support 1, and the lifting screw 1 3 and the placement tray 5 are provided with an elastic connection structure, which includes a sliding sleeve 15, a sliding rod 16 and a spring damper 17. The sliding sleeve 15 is fixedly connected to the top of the lifting screw 13, and the bottom of the placement tray 5 is fixedly connected with the sliding rod 16. The sliding rod 16 is slidably arranged in the sliding sleeve 15, and a spring damper 17 is arranged between the bottom end of the sliding rod 16 and the inner wall of the sliding sleeve 15. When it is necessary to drive the placement tray 5 to move longitudinally, the second driving motor 32 is started to drive the rotation of the second driving motor 32 through the meshing relationship of the two transmission gears 33. The movable cylinder 10 rotates in the rotating ring 11, and the lifting screw 13 is driven to move longitudinally through the threaded connection between the lifting screw 13 and the threaded seat 12 and the sliding connection between the lifting screw 13 and the sliding member 14. When the lifting screw 13 moves longitudinally, the sliding sleeve 15, the sliding rod 16 and the spring damper 17 also move with the placement tray 5. When the lifting screw 13 drives the placement tray 5 to move longitudinally, the sliding rod 16 is affected by the gravity of the placement tray 5, so that the spring damper 17 will slide in the sliding sleeve 15, causing the spring damper 17 to contract. When the stamping device 2 is used to install the retaining frame later, in order to prevent the placement tray 5 from being damaged by the gravity of the stamping device 2, the lifting screw 13 and other components are caused, when the placement tray 5 is driven to contact the transverse sections of the plurality of bent support rods 4, the lifting screw 13 is made to continue to descend, so that the spring damper 17 is kept in a relaxed state in the sliding sleeve 15, and when the retaining frame is stamped and installed, it can be ensured that the lifting screw 13 and other components are not affected; The bearing ring placement assembly 300 includes an arc-shaped support bar 18 and a connecting piece 19. The number of the arc-shaped support bars 18 is set to two. A groove is provided on the placement tray 5 corresponding to the arc-shaped support bar 18. The arc-shaped support bar 18 is located in the corresponding groove. Two connecting pieces 19 are fixedly connected between the two arc-shaped support bars 18. The connecting piece 19 penetrates and is slidably connected to the placement tray 5. When a steel ball is loaded between the bearing outer ring and the bearing inner ring and placed on the placement tray 5, because the thickness of the bearing outer ring is higher than that of the bearing inner ring, in order to ensure that the bearing outer ring and the bearing inner ring maintain a corresponding relationship and avoid the problem of deviation between the bearing outer ring and the bearing inner ring during the subsequent assembly process, the corresponding arc-shaped support bar 18 can be driven to rise to different heights in the groove, so that the bearing outer ring and the bearing inner ring remain corresponding. The steel ball lifting assembly 400 includes an annular support 20 and a support member 22. A groove is also provided on the placement tray 5 corresponding to the annular support 20. The annular support 20 is located in the corresponding annular support 20. A plurality of arc grooves 21 are provided on the annular support 20. Support members 22 are fixedly connected to both sides of the bottom of the annular support 20. The support member 22 penetrates and is slidably connected to the placement tray 5. In order to keep the steel ball stable between the outer ring of the bearing and the inner ring of the bearing, the position of the annular support 20 in the groove is adjusted by driving the support member 22 to slide in the placement tray 5, so that the steel ball fits the inner wall of the arc groove 21, which is also convenient for keeping multiple steel balls stable when the retaining frame is installed later. The magnetic fixing assembly 500 is also included. The magnetic fixing assembly 500 is arranged between the connecting member 19 and the placing tray 5. The magnetic fixing assembly 500 is also arranged between the supporting member 22 and the placing tray 5. The magnetic fixing assembly 500 includes an electromagnetic sleeve 23 and an iron strip 24. The number of the electromagnetic sleeves 23 is set to be multiple. The electromagnetic sleeve 23 is arranged at the bottom of the placing tray 5. The connecting member 19 or the supporting member 22 is slidably arranged inside the corresponding electromagnetic sleeve 23. The connecting member 19 and the supporting member 22 are fixedly connected with multiple iron strips 24. The iron strips 24 are connected to the The electromagnetic sleeve 23 is magnetically connected. After adjusting the height of the connecting piece 19 and the supporting piece 22, the electromagnetic sleeve 23 is powered on to generate magnetism, so that the electromagnetic sleeve 23 maintains a magnetic connection with the ferrous bar 24 of the corresponding height, ensuring that the arc-shaped supporting bar 18 and the annular support 20 remain stable on the placement tray 5. The electromagnetic sleeve 23 is an electromagnetic device well known to technical personnel in this field. By powering the electromagnetic sleeve 23, magnetism is generated inside the electromagnetic sleeve 23, so that the electromagnetic sleeve 23 can be magnetically connected with the corresponding ferrous bar 24.

[0023] like Figures 1 to 5 , Figure 8 and Fig. 9As shown, the position adjustment mechanism 600 is arranged on the circular support 3, the bearing ring placement component 300 and the steel ball lifting component 400 are both matched with the position adjustment mechanism 600, the position adjustment mechanism 600 includes a pushing seat 25 and a position moving component, the number of the pushing seats 25 is set to two, the pushing seat 25 is used to drive the connecting member 19 or the supporting member 22 to move longitudinally, and the position moving components are arranged on both sides of the top of the circular support 3, the position moving components include a sliding frame 26, a transmission screw 27, a mounting seat 29 and a driving electric cylinder 30, the sliding frame 26 is fixedly connected to the circular support 3, the transmission screw 27 is rotatably connected in the sliding frame 26, a first driving motor 28 is arranged on the sliding frame 26, the output end of the first driving motor 28 is fixedly connected to the transmission screw 27, the mounting seat 29 is slidably connected in the sliding frame 26, and the mounting seat 29 It is threadedly connected to the transmission screw 27, the driving electric cylinder 30 is arranged on the mounting seat 29, and the pushing seat 25 is arranged on the output end of the driving electric cylinder 30. When it is necessary to drive the connecting parts 19 and the supporting parts 22 on both sides to move longitudinally, the first driving motor 28 is started to drive the transmission screw 27 to rotate in the sliding frame 26, so that the mounting seat 29, the driving electric cylinder 30 and the pushing seat 25 threadedly connected to the transmission screw 27 are moved laterally, so that the pushing seat 25 moves to the bottom of the corresponding connecting part 19 and the supporting part 22, and the driving electric cylinder 30 is started to drive the pushing seat 25 to rise, so that the bottom of the connecting part 19 or the supporting part 22 contacts with the pushing seat 25, and the pushing seat 25 is driven to rise by the driving electric cylinder 30, so that the pushing seat 25 drives the connecting part 19 or the supporting part 22 to rise, thereby adjusting the height of the arc support bar 18 and the annular support 20.

[0024] The annular stamping die 6 is arranged on the output end of the stamping equipment 2. The annular stamping die 6 is located on the upper side of the steel ball lifting assembly 400. A matching groove 31 is provided at the bottom of the annular stamping die 6. When the stamping equipment 2 is used to drive the annular stamping die 6 to descend, the matching groove 31 at the bottom of the annular stamping die 6 is kept in contact with the end face of the retaining frame to further determine the corresponding relationship between the retaining frame and the multiple steel balls. Then, the stamping equipment 2 is started to drive the annular stamping die 6 to descend, so that the retaining frame and the multiple steel balls are fixedly installed.

[0025] The working principle of the outer spherical bearing assembly equipment is as follows: first, a corresponding number of steel balls are loaded between the outer ring and the inner ring of the bearing, and then the outer ring, the inner ring and the steel balls are placed on the placement tray 5. During the placement process, multiple steel balls and multiple bent support rods 4 are staggered, and the positions of the steel balls between the outer ring and the inner ring of the bearing are fixed by the bent support rods 4, and then the outer ring, the inner ring and the steel balls are placed on the placement tray 5; Then, the first driving motor 28 is started to drive the transmission screw 27 to rotate in the sliding frame 26, so that the mounting seat 29, the driving electric cylinder 30 and the pushing seat 25 which are threadedly connected with the transmission screw 27 are moved laterally, so that the pushing seat 25 is moved to the bottom of the corresponding connecting member 19 and the supporting member 22, and the driving electric cylinder 30 is started to drive the pushing seat 25 to rise, so that the bottom of the connecting member 19 or the supporting member 22 contacts with the pushing seat 25, and the pushing seat 25 is driven to rise by the driving electric cylinder 30, so that the pushing seat 25 drives the connecting member 19 or the supporting member 22 to rise, thereby adjusting the height of the arc support bar 18 and the annular support 20, so that the positions between the outer ring of the bearing, the inner ring of the bearing and the steel ball remain corresponding, and then the retaining frame is placed between the multiple steel balls; The second driving motor 32 is started, and the rotating cylinder 10 is driven to rotate in the rotating ring 11 through the meshing relationship of the two transmission gears 33. The lifting screw 13 is driven to move longitudinally through the threaded connection between the lifting screw 13 and the threaded seat 12 and the sliding connection between the lifting screw 13 and the sliding member 14. When the lifting screw 13 moves longitudinally, the sliding sleeve 15, the sliding rod 16 and the spring damper 17 will also move with the placement tray 5, so that the bottom end of the placement tray 5 is in contact with the transverse sections of the multiple bent support members 22, and then the impact is started. When the pressing device 2 drives the annular stamping die 6 to descend, the matching groove 31 at the bottom of the annular stamping die 6 is kept in contact with the end face of the retainer, and the corresponding relationship between the retainer and the multiple steel balls is further determined. Then, the pressing device 2 is started to drive the annular stamping die 6 to descend, so that the retainer and the multiple steel balls are fixedly installed. Then, the outer ring of the bearing, the inner ring of the bearing, the steel balls and one side of the retainer can be removed, and the outer ring of the bearing, the inner ring of the bearing, the steel balls and one side of the retainer are turned over and placed on the placement tray 5, and the retainer is continued to be installed on the other side of the multiple steel balls. After the retaining frames are installed on both sides of the multiple steel balls, the placement tray 5 is driven to rise by the lifting screw 13, and the multiple steel balls are moved to the top area of ​​the multiple bent support rods 4. The lubricating grease is driven into the semi-cylindrical body 9 through the delivery pump device 8, and then the lubricating grease is allowed to enter the injection pipe 7. Finally, the lubricating grease is discharged through the injection pipe 7, and the lubricating grease is filled between the multiple steel balls, completing the oil filling operation of the assembled outer spherical bearing.

[0026] The above are only preferred embodiments of the present invention and are not intended to limit the present invention. Any modifications, equivalent substitutions, improvements, etc. made within the spirit and principles of the present invention should be included in the protection scope of the present invention.

Claims

1. An outer spherical bearing assembly device, comprising a mounting support (1), a stamping device (2) being arranged on the top of the mounting support (1), characterized in that: Also includes: A circular support (3), the circular support (3) being fixedly connected to the mounting support (1), a plurality of bent support rods (4) being fixedly connected to the inner wall of the circular support (3), and a grease injection assembly (100) being provided between the plurality of bent support rods (4) and the mounting support (1); A placement tray (5), the placement tray (5) being slidably disposed between the plurality of bent support rods (4), a lifting and moving assembly (200) being disposed between the placement tray (5) and the mounting support (1), two bearing ring placement assemblies (300) being disposed on the placement tray (5), the bearing ring placement assemblies (300) being used to place a bearing outer ring or a bearing inner ring, and a steel ball lifting assembly (400) being disposed on the placement tray (5); A position adjustment mechanism (600), the position adjustment mechanism (600) being arranged on the circular support (3), the bearing ring placement assembly (300) and the steel ball lifting assembly (400) both cooperating with the position adjustment mechanism (600); An annular stamping die (6), wherein the annular stamping die (6) is arranged on the output end of the stamping device (2), and the annular stamping die (6) is located on the upper side of the steel ball lifting assembly (400).

2. The outer spherical bearing assembly device according to claim 1, characterized in that: The grease injection assembly (100) comprises: An injection pipe (7), the interior of each of the plurality of bent support rods (4) being fixedly connected to the injection pipe (7); A delivery pump device (8), wherein the delivery pump device (8) is arranged on the mounting support (1); A semi-cylindrical body (9) is connected between the plurality of injection pipes (7) located on the same side, and the output end of the delivery pump device (8) is connected to the plurality of semi-cylindrical bodies (9) via a multi-directional delivery pipe.

3. The outer spherical bearing assembly equipment according to claim 2, characterized in that: The lifting and moving assembly (200) comprises: A rotating cylinder (10), a rotating ring (11) is fixedly connected to the middle of the mounting support (1), the rotating cylinder (10) is rotatably connected inside the rotating ring (11), a threaded seat (12) is provided at the top of the rotating cylinder (10), and a rotating assembly is provided between the rotating cylinder (10) and the mounting support (1); A lifting screw (13), the lifting screw (13) being threadedly connected to the threaded seat (12), the lifting screw (13) being provided with a slide groove, the slide groove being slidably connected to a sliding member (14), and the sliding member (14) being fixedly connected to the mounting support (1); An elastic connection structure is provided between the lifting screw rod (13) and the placement tray (5).

4. The outer spherical bearing assembly equipment according to claim 3, characterized in that: The elastic connection structure comprises: A sliding sleeve (15), the sliding sleeve (15) being fixedly connected to the top of the lifting screw (13); A sliding rod (16), the bottom of the placement tray (5) being fixedly connected to the sliding rod (16), the sliding rod (16) being slidably disposed in the sliding sleeve (15); A spring damper (17) is provided between the bottom end of the sliding rod (16) and the inner wall of the sliding sleeve (15).

5. The outer spherical bearing assembly device according to claim 4, characterized in that: The bearing ring placement assembly (300) comprises: An arc-shaped support bar (18), wherein the number of the arc-shaped support bars (18) is set to two, and a groove is provided on the placement tray (5) corresponding to the arc-shaped support bar (18), and the arc-shaped support bar (18) is located in the corresponding groove; A connecting piece (19), wherein two connecting pieces (19) are fixedly connected between the two arc-shaped support bars (18), and the connecting pieces (19) penetrate and are slidably connected to the placement tray (5).

6. The outer spherical bearing assembly device according to claim 5, characterized in that: The steel ball lifting assembly (400) comprises: An annular support (20), the placement tray (5) also has a groove corresponding to the annular support (20), the annular support (20) is located in the corresponding annular support (20), and the annular support (20) has a plurality of arc grooves (21); A support member (22), wherein both sides of the bottom of the annular support (20) are fixedly connected to the support member (22), and the support member (22) penetrates and is slidably connected to the placement tray (5).

7. The outer spherical bearing assembly device according to claim 6, characterized in that: It also includes a magnetic fixing component (500), the magnetic fixing component (500) being arranged between the connecting member (19) and the placement tray (5), and the magnetic fixing component (500) being also arranged between the supporting member (22) and the placement tray (5), and the magnetic fixing component (500) comprising: An electromagnetic sleeve (23), wherein the number of the electromagnetic sleeves (23) is set to be multiple, the electromagnetic sleeves (23) are arranged at the bottom of the placement tray (5), and the connecting member (19) or the supporting member (22) is slidably arranged inside the corresponding electromagnetic sleeve (23); Ferrous bars (24), a plurality of the ferrous bars (24) are fixedly connected to the connecting member (19) and the supporting member (22), and the ferrous bars (24) are magnetically connected to the electromagnetic sleeve (23).

8. The outer spherical bearing assembly device according to claim 7, characterized in that: The position adjustment mechanism (600) comprises: A pushing seat (25), wherein the number of the pushing seats (25) is set to two, and the pushing seat (25) is used to drive the connecting member (19) or the supporting member (22) to move longitudinally; Position moving components are provided on both sides of the top of the circular support (3).

9. The outer spherical bearing assembly device according to claim 8, characterized in that: The position moving component comprises: A sliding frame (26), the sliding frame (26) being fixedly connected to the circular support (3); a transmission screw (27), the transmission screw (27) being rotatably connected inside the sliding frame (26), a first drive motor (28) being provided on the sliding frame (26), an output end of the first drive motor (28) being fixedly connected to the transmission screw (27); A mounting seat (29), the mounting seat (29) being slidably connected in the sliding frame (26), and the mounting seat (29) being threadedly connected to the transmission screw (27); A driving electric cylinder (30), wherein the driving electric cylinder (30) is arranged on the mounting seat (29), and the pushing seat (25) is arranged on the output end of the driving electric cylinder (30).

10. The outer spherical bearing assembly equipment according to claim 9, characterized in that: A matching groove (31) is provided at the bottom of the annular stamping die (6).

Citation Information

Cited By

  • Automatic steel ball adding device for automobile hub bearing

    CN120062250A

  • Automatic steel ball adding device for automotive wheel hub bearings

    CN120062250B