Device and method applied to steep curve shield tunnel three-dimensional path wire transmission

By using a measurement hanging basket and a three-dimensional transmission assembly in a sharp curve tunnel, combined with the design of a universal ball shaft and target prism, the problem of insufficient measurement space on the top of the trolley is solved, and the accuracy and efficiency of wire measurement are improved.

CN119022899APending Publication Date: 2024-11-26SHANGHAI FOUNDATION ENGINEERING GROUP CO LTD
View PDF 0 Cites 0 Cited by

Patent Information

Application Number
CN202411140508.1
Authority / Receiving Office
CN · China
Patent Type
Applications(China)
Current Assignee / Owner
Filing Date
2024-08-20
Publication Date
2024-11-26

AI Technical Summary

Technical Problem

During the shield excavation process, the measurement space on the top of the trolley in the sharp curve tunnel is small, resulting in obstruction of the line of sight of the wire measurement and observation, short observation distance, increasing the number of stations, reducing the measurement accuracy and engineering progress.

Method used

A device including a measuring basket, a three-dimensional transmission assembly and a forced tripod was designed. The combination of a universal ball axis and a target prism ensures the up and down transfer of the coordinates of the wire measurement point, and realizes the target prism on the same plumb line. Connection simplifies the measurement process.

Benefits of technology

The number of stations is reduced, the measurement accuracy and efficiency is improved, the cumbersome wire transfer process in the roof space of the trolley is avoided, and the construction efficiency is improved.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN119022899A_ABST
    Figure CN119022899A_ABST
Patent Text Reader

Abstract

According to the device applied to sharp curve shield tunnel three-dimensional path wire transmission and the construction method of the device, the first target prism and the second target prism are arranged on the same plumb line, and vertical transmission of wire measurement point coordinates is transmitted in a three-dimensional mode through the universal ball shaft; the universal ball shaft principle and gravity interaction and matching are reasonably utilized and perfectly fused into engineering measurement wire transmission, the work of three-dimensional wire transmission measurement is well achieved, point position transmission is direct and rapid, and the complexity that wires are transmitted in a narrow space at the top of a trolley in a one-station mode is avoided; when the device is used for conducting wire transmission of a sharp curve, the number of observation stations is reduced, the measurement precision is improved, the measurement time is greatly saved, and the measurement efficiency is improved.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The invention relates to the technical field of engineering measurement, and in particular to a device for transmitting a three-dimensional path conductor in a sharp curve shield tunnel and a construction method thereof. Background Art

[0002] With the gradual acceleration of the pace of urban engineering construction, urban building types are changing. In the face of increasingly prosperous urban needs, underground engineering construction must not only deal with complex geological conditions, but also take into account the impact on ground buildings. Line planning and design often use curves to avoid buildings. Compared with large-diameter tunnel traverse measurement operations, small-diameter, small-radius sharp-turn linear tunnels are the key points that need to be overcome during traverse measurement. Traverse measurement operations are a vital task in engineering construction, especially when the tunnel line design includes sharp curve sections. Measurement work is essential to ensure the accuracy, safety and efficiency of tunnel construction.

[0003] However, the difficulty of the measurement work also lies here. After the shield tunneling enters the sharp curve, the shield machine and each section of the trolley also enter the sharp curve area one after another with the construction and excavation of the shield. For the construction measurement of the shield, the measurement channel is generally set on one side of the top of the trolley, and the measurement point is set below the shield segment on the top of the trolley. The space on the top of the trolley is narrow and there are many oil pipelines and ventilation ducts on the top of the trolley. In addition, the belt conveyor equipment for transporting soil during the shield tunneling process is set on the top of the trolley, which causes the measurement space on the top of the trolley to become further narrow. After the mechanical equipment of each section of the trolley enters the sharp curve, the trolleys are arranged in a C-shape and an S-shape in the tunnel. The space of the top measurement channel is curved, and the line of sight is blocked, resulting in a greatly shortened measurement observation distance and the addition of multiple measuring station turning points, which leads to increased difficulty in wire measurement, more stations, shorter sides, and longer measurement time. The labor intensity of the surveying personnel increases, the wire accuracy decreases, and the progress of the project is affected, which can easily cause quality and safety hazards to the project.

[0004] In view of the shortcomings of the prior art in transmitting the coordinates of the wire to the direction of the shield machine through the space on the top of the trolley when the shield tunneling reaches special situations such as small diameter, small radius, and sharp curve, technical personnel in this field have been looking for solutions. Summary of the invention

[0005] The purpose of the present invention is to provide a device and a construction method for three-dimensional path wire transmission in a sharp curve shield tunnel, so as to solve the problems in the prior art that when the shield tunnel is excavated into a small diameter, a small radius, or a sharp curve, the wire coordinates are transmitted to the shield machine direction through the space on the top of the trolley, and there is insufficient space in the measurement channel on the top of the trolley, the observation line of sight is blocked during wire measurement, and the observation distance is short, resulting in an increase in measuring stations and a decrease in accuracy.

[0006] In order to solve the above technical problems, the present invention provides a device for transmitting a three-dimensional path wire in a sharp curve shield tunnel, and the device for transmitting a three-dimensional path wire in a sharp curve shield tunnel comprises:

[0007] A measuring basket is set under the shield segment on the top of the trolley;

[0008] Two stereo transmission components are fixed between the trolleys, each of which includes: a first target prism, a first center screw rod, a universal ball shaft, a second center screw rod, a screw rod connector, a third center screw rod, a second target prism and a hammer ball, and a transverse suspension screw rod, which are coaxially connected in sequence from top to bottom. One end of the transverse suspension screw rod is welded to the trolley, and the other end crosses the shaft hole of the universal ball shaft and is perpendicular to the first center screw rod, so that the universal ball shaft can swing vertically with mechanical gravity.

[0009] A first forced centering tripod is arranged in the middle channel below the trolley;

[0010] a second forced centering tripod, disposed at the rear side of the first forced centering tripod;

[0011] A total station is successively arranged on the first forced centering tripod and the measuring basket;

[0012] A rear-view prism is arranged on the second forced centering tripod.

[0013] Optionally, in the device for three-dimensional path wire transmission in a sharp curve shield tunnel, each three-dimensional transmission component also includes: a first nut of a universal ball shaft and a second nut of a universal ball shaft, the first nut of the universal ball shaft connecting the first center screw rod and the universal ball shaft; the second nut of the universal ball shaft connecting the second center screw rod and the universal ball shaft.

[0014] Optionally, in the device for three-dimensional path wire transmission in a sharp curve shield tunnel, each three-dimensional transmission component also includes: a suspension screw rod nut, which fixes the transverse suspension screw rod to the universal ball shaft.

[0015] Optionally, in the device for three-dimensional path wire transmission in a sharp curve shield tunnel, each three-dimensional transmission component also includes: two target prism nuts, one target prism nut connecting the first target prism and the first center screw rod; the other target prism nut connecting the second target prism and the third center screw rod.

[0016] Optionally, in the device for three-dimensional path wire transmission in a sharp curve shield tunnel, the center of the first target prism and the center of the second target prism in each three-dimensional transmission component are on the same plumb line.

[0017] The present invention also provides a construction method for a device for transmitting a three-dimensional path conductor in a sharp curve shield tunnel, and the construction method for the device for transmitting a three-dimensional path conductor in a sharp curve shield tunnel comprises:

[0018] S1. At the sharp curve of the trolley, the conductor route is selected to enter from the construction channel under the trolley;

[0019] S2, setting the first forced centering tripod at the middle channel below the trolley, setting the second forced centering tripod at a predetermined position behind the first forced centering tripod, and setting the rear-view prism on the second forced centering tripod;

[0020] S3, fixing the two stereo transmission assemblies at appropriate positions selected between the trolleys, and the hammer balls in the stereo transmission assemblies are vertically downward under the action of gravity, so that the first target prism and the second target prism are on the same plumb line;

[0021] S4, setting up a total station on the first forced centering tripod, and transmitting the coordinates of the traverse measurement points to the second target prism and the first target prism in sequence based on the total station;

[0022] S5. Transfer the total station to the measuring basket to continue the transmission of the coordinates of the traverse measurement points;

[0023] S6. Measure the forward-looking target prism of the shield machine based on the total station on the measuring basket to complete the wire coordinate transfer measurement work.

[0024] Optionally, in the construction method of the device for transmitting a three-dimensional wire path in a steep curve shield tunnel, S4 includes:

[0025] Using the first forced centering tripod and the second forced centering tripod as reference points, directly measuring the point coordinates of the second target prism by using a total station, so as to transfer the traverse measurement point coordinates to the second target prism;

[0026] The first target prism and the second target prism are placed on the same plumb line so that the coordinates of the wire measurement point are transmitted to the first target prism via the second target prism.

[0027] Optionally, in the construction method of the device for transmitting a three-dimensional wire path in a sharp curve shield tunnel, before executing S3, the method further includes:

[0028] Assemble the two stereo transfer components.

[0029] Optionally, in the construction method of the device for transmitting a three-dimensional path conductor in a sharp curve shield tunnel, the assembly process of each three-dimensional transmission component is as follows:

[0030] One end of the transverse suspension screw rod is welded to the trolley, and the other end is passed through the shaft hole of the universal ball shaft and fixed with a suspension screw rod nut;

[0031] Install the first target prism on the upper screw end of the first central screw rod, and tighten the lower screw end of the first central screw rod to the universal ball shaft through the first universal ball shaft nut located on the upper side of the universal ball shaft to fix it;

[0032] Tighten the upper screw end of the second center screw rod to fix it on the universal ball shaft through the second nut of the universal ball shaft located on the lower side of the universal ball shaft;

[0033] Install the screw rod connector between the lower screw end of the second center screw rod and the upper screw end of the third center screw rod;

[0034] The second target prism is mounted on the lower screw end of the third center screw rod, and the centers of the second target prism and the first target prism are concentric and coaxial with the first center screw rod, the second center screw rod and the third center screw rod;

[0035] A hammer ball is hung below the second target prism so that the first center screw rod and the second center screw rod connected to the upper and lower sides of the universal ball shaft always maintain a vertical state, and the first target prism and the second target prism are on the same plumb line.

[0036] In the device and construction method for three-dimensional path wire transmission in a sharp curve shield tunnel provided by the present invention, by arranging the first target prism and the second target prism on the same plumb line, the universal ball shaft is used to three-dimensionally transmit the wire measurement point coordinates up and down, and the universal ball shaft principle and the interaction and matching of gravity are reasonably utilized, which are perfectly integrated into the wire transmission of engineering measurement, and the work of three-dimensional wire transmission measurement is well solved. The point transmission is direct and fast, avoiding the tedious transmission of the wire from station to station in the small space on the top of the trolley; using this device to transmit the wire in a sharp curve not only reduces the number of measuring stations and improves the measurement accuracy, but also greatly saves the measurement time and improves the measurement efficiency. BRIEF DESCRIPTION OF THE DRAWINGS

[0037] The above and other objects, features and advantages of the present disclosure will become more apparent through a more detailed description of exemplary embodiments of the present disclosure in conjunction with the accompanying drawings, wherein like reference numerals generally represent like components throughout the exemplary embodiments of the present disclosure.

[0038] Figure 1It is a schematic diagram of a device for transmitting a three-dimensional wire path in a sharp curve shield tunnel during construction in one embodiment of the present invention;

[0039] Figure 2 is a schematic diagram of a universal ball shaft connection portion in one embodiment of the present invention;

[0040] Figure 3 is a schematic diagram of a disassembled three-dimensional transmission component in one embodiment of the present invention;

[0041] Figure 4 It is a flow chart of a construction method of a device for transmitting a three-dimensional path conductor in a sharp curve shield tunnel.

[0042] In the figure:

[0043] 1-total station; 2-measuring hanging basket; 3-first target prism; 4-target prism nut; 5-first center screw rod; 6-first nut of universal ball shaft; 7-universal ball shaft; 8-second nut of universal ball shaft; 9-lateral hanging screw rod; 10-hanging screw rod nut; 11-screw rod connector; 12-second center screw rod; 13-second target prism; 14-hammer ball; 15-third center screw rod; 16-rearview prism; 17-first forced centering tripod; 18-second forced centering tripod; 19-forward target prism of shield machine; 100-stereoscopic transmission component. DETAILED DESCRIPTION

[0044] The following is a further detailed description of the device for three-dimensional wire transmission in a sharp curve shield tunnel and its construction method proposed by the present invention in combination with the accompanying drawings and specific embodiments. The advantages and features of the present invention will become clearer according to the following description and claims. It should be noted that the drawings are all in a very simplified form and are not in precise proportions, and are only used to conveniently and clearly assist in explaining the purpose of the embodiments of the present invention.

[0045] The present invention will now be described in further detail with reference to the accompanying drawings. These drawings are simplified schematic diagrams, which only illustrate the basic structure of the present invention in a schematic manner, and therefore only show the components related to the present invention.

[0046] In the description of the invention, it is necessary to understand that the terms “center”, “longitudinal”, “lateral”, “length”, “width”, “thickness”, “up”, “down”, “front”, “back”, “left”, “right”, “vertical”, “horizontal”, “top”, “bottom”, “inside”, “outside”, “clockwise”, “counterclockwise”, etc., indicating the orientation or position relationship, are based on the orientation or position relationship shown in the drawings, and are only for the convenience of describing the invention and simplifying the description, and do not indicate or imply that the device or element referred to must have a specific orientation, be constructed and operated in a specific orientation, and therefore cannot be understood as a limitation on the invention.

[0047] In addition, the terms "first" and "second" are used for descriptive purposes only and should not be understood as indicating or implying relative importance or implicitly indicating the number of the indicated technical features. Therefore, a feature defined as "first" or "second" may explicitly or implicitly include one or more of the features. In the description of the invention, the meaning of "plurality" is two or more, unless otherwise clearly and specifically defined.

[0048] In the invention, unless otherwise clearly specified and limited, the terms "installed", "connected", "connected", "fixed" and the like should be understood in a broad sense, for example, it can be a fixed connection, a detachable connection, or an integral connection; it can be a mechanical connection or an electrical connection; it can be a direct connection, or it can be an indirect connection through an intermediate medium, or it can be the internal communication of two elements. For ordinary technicians in this field, the specific meanings of the above terms in the invention can be understood according to the specific circumstances.

[0049] Please refer to Figure 1 , which is a schematic diagram of the structure of the device for transmitting wires in a three-dimensional path of a steep curve shield tunnel according to the present invention. Figure 1 As shown, the device for three-dimensional path wire transmission in a sharp curve shield tunnel comprises: a measuring basket 2, two three-dimensional transmission components 100, a first forced centering tripod 17, a second forced centering tripod 18, a total station 1 and a rear-view prism 16. The measuring basket 2 is set below the shield segment on the top of the trolley during construction; the two three-dimensional transmission components 100 are fixed between the trolleys, and each three-dimensional transmission component 100 comprises: a first target prism 3, a first center screw rod 5, a universal ball shaft 7, a second center screw rod 12, and a screw rod connector 11 (function: connecting two or more screw rods to increase their length and keep the screw rods) coaxially connected in sequence from top to bottom The rods are kept in a straight line connection), a third center screw rod 15, a second target prism 13 and a hammer ball 14, and a transverse suspension screw rod 9, one end of the transverse suspension screw rod 9 is welded to the trolley, and the other end crosses the axial hole of the universal ball shaft 7 and is perpendicular to the first center screw rod 5, so that the universal ball shaft 7 can swing vertically with mechanical gravity; a first forced centering tripod 17 is arranged in the middle channel below the trolley; a second forced centering tripod 18 is arranged on the rear side of the first forced centering tripod 17; the total station 1 is successively arranged on the first forced centering tripod 17 and the measuring basket 2; the rearview prism 16 is arranged on the second forced centering tripod 18.

[0050] The working principle and function of each component of the device of the present invention are as follows:

[0051] 1) Total station 1, set up the total station instrument at a known point, observe any target point according to the coordinates of the measuring station and the orientation point or the orientation distance and azimuth, obtain the three-dimensional coordinate value of the target point, transfer the distance information and azimuth information from the known orientation side to the unknown side, and use it in conjunction with the rear-view prism to achieve the purpose of orientation. In the present invention, the total station is first set up on a forced centering tripod for observation, and finally set up on the forced centering point of the measuring basket for observation.

[0052] 2) Universal ball joint 7, also known as universal joint, is a transmission device used to connect two different axes and allow the angle between the two axes to vary within a certain range. The main function of universal ball joint is to make mechanical connection more flexible and stable.

[0053] 3) The central screw rods 5, 12, 15 are used to connect the first target prism, the second target prism, and the universal ball shaft into a whole, and are on the same axis, that is, the centers of the target prisms at both ends, the universal ball shaft, and the central screw rod are coaxial.

[0054] 4) The transverse suspension screw rod 9 is transversely welded and fixed at the top of the trolley, passes through the universal ball shaft 7 and fixes the transverse universal ball shaft, so that the vertical direction can swing with the mechanical gravity.

[0055] 5) Forced centering tripod 17: A forced centering tripod is used to transfer the coordinates of the conductor points in the middle channel under the trolley. Compared with ordinary wooden tripods, it is easy to set up and does not need to be aligned. Stations can be set up at will during the conductor transfer process. After the point coordinate transfer is completed, it can be removed at any time without affecting the passage of construction vehicles.

[0056] The device of the present invention reasonably utilizes the principle of the universal ball shaft, and the hammer ball 14 is vertically downward under the action of gravity, so that the first target prism 3 and the second target prism 13 are on the same plumb line, thereby realizing the up and down transmission of the coordinates of the wire measurement point at the sharp curve turn. The point transmission is direct and fast, avoiding the tedious transmission of the wire from station to station in the small space on the top of the trolley, reducing the number of measuring stations and improving the measurement accuracy, and greatly saving the measurement time and improving the measurement efficiency.

[0057] In this embodiment, the various components in the stereo transmission assembly are connected by nuts. Specifically, each stereo transmission assembly also includes: a first nut 6 of a universal ball shaft, a second nut 8 of a universal ball shaft, a suspension screw rod nut 10 and two target prism nuts 4. The first nut 6 of the universal ball shaft connects the first center screw rod 5 and the universal ball shaft 7; the second nut 8 of the universal ball shaft connects the second center screw rod 12 and the universal ball shaft 7; the suspension screw rod nut 10 fixes the transverse suspension screw rod 9 to the universal ball shaft 7; a target prism nut 4 connects the first target prism 3 and the first center screw rod 5; another target prism nut 4 connects the second target prism 13 and the third center screw rod 15.

[0058] Accordingly, this embodiment also provides a construction method for a device for transmitting a three-dimensional wire path in a steep curve shield tunnel. Figures 1 to 4 The construction method of the device for transmitting a three-dimensional wire path in a sharp curve shield tunnel described in this embodiment is described in detail.

[0059] First, execute step S1, and at the sharp curve of the trolley position, select the wire route to enter from the construction channel under the trolley.

[0060] Next, execute step S2, set the first forced centering tripod 17 at the middle channel below the trolley, set the second forced centering tripod 18 at a predetermined position behind the first forced centering tripod 17, and mount the rearview prism 16 on the second forced centering tripod 18.

[0061] Next, step S3 is executed to fix the two stereo transmission components 100 at appropriate positions selected between the trolleys, and the hammer ball 14 in the stereo transmission component 100 is vertically downward under the action of gravity so that the first target prism 3 and the second target prism 13 are on the same plumb line.

[0062] It can be understood that before executing step S3, the three-dimensional transmission component has been assembled. The specific assembly process is as follows:

[0063] S101, welding one end of the transverse suspension screw rod 9 to the trolley, and passing the other end through the shaft hole of the universal ball shaft 7, and fixing it with a suspension screw rod nut 10;

[0064] S102, mounting the first target prism 3 on the upper screw end of the first central screw rod 5, and tightening and fixing the lower screw end of the first central screw rod 5 on the universal ball shaft 7 through the universal ball shaft first nut 6 located on the upper side of the universal ball shaft 7;

[0065] S103, tightening and fixing the upper screw end of the second central screw rod 12 to the universal ball shaft 7 through the universal ball shaft second nut 8 located at the lower side of the universal ball shaft 7;

[0066] S104, installing the screw rod connector 11 between the lower screw end of the second center screw rod 12 and the upper screw end of the third center screw rod 15;

[0067] S105, installing the second target prism 13 on the lower screw end of the third center screw rod 15, the center of the second target prism 13 and the first target prism 3 is coaxial with the first center screw rod 5, the second center screw rod 12 and the third center screw rod 15;

[0068] S106, suspend a hammer ball 14 below the second target prism 13 so that the first center screw rod 5 and the second center screw rod 12 connected to the upper and lower sides of the universal ball shaft 7 always maintain a vertical state, and the first target prism 3 and the second target prism 13 are on the same plumb line.

[0069] Next, step S4 is executed to set up the total station 1 on the first forced centering tripod 17, and transmit the coordinates of the traverse measurement points to the second target prism 13 and the first target prism 3 based on the total station 1. The execution of step S4 specifically includes:

[0070] S41, using the first forced centering tripod 17 and the second forced centering tripod 18 as reference points, directly measuring the point coordinates of the second target prism 13 by the total station 1, so as to transfer the wire measurement point coordinates to the second target prism 13;

[0071] S42, using the first target prism 3 and the second target prism 13 on the same plumb line, so that the coordinates of the wire measurement point are transmitted to the first target prism 3 through the second target prism 13.

[0072] Next, step S5 is executed to transfer the total station 1 to the measuring basket 2 to continue the transmission of the coordinates of the wire measurement points.

[0073] Next, step S6 is executed to measure the forward-looking target prism 19 of the shield machine based on the total station 1 on the measuring basket 2 to complete the wire coordinate transfer measurement work.

[0074] It should be noted that, for the aforementioned method embodiments, for the sake of simplicity, they are all expressed as a series of action combinations, but those skilled in the art should be aware that the present application is not limited by the described order of actions, because according to the present application, certain steps can be performed in other orders or simultaneously. Secondly, those skilled in the art should also be aware that the embodiments described in the specification are all preferred embodiments, and the actions and modules involved are not necessarily required by the present application.

[0075] In summary, in the device and construction method for three-dimensional path wire transmission in a sharp curve shield tunnel provided by the present invention, the first target prism and the second target prism are set on the same plumb line, and the universal ball shaft is used to three-dimensionally transmit the wire measurement point coordinates up and down, which reasonably utilizes the interaction and matching of the universal ball shaft principle and gravity, and perfectly integrates them into the engineering measurement wire transmission, which well solves the work of three-dimensional wire transmission measurement. The point transmission is direct and fast, avoiding the tedious transmission of the wire from station to station in the narrow space on the top of the trolley; using this device for sharp curve wire transmission not only reduces the number of measuring stations and improves measurement accuracy, but also greatly saves measurement time and improves measurement efficiency.

[0076] The above description is only a description of the preferred embodiments of the present invention, and is not intended to limit the scope of the present invention. Any changes or modifications made by a person skilled in the art in the field of the present invention based on the above disclosure shall fall within the scope of protection of the claims.

Claims

1. A device for transmitting a three-dimensional wire path in a sharp curve shield tunnel, characterized in that: include: A measuring hanging basket (2) is arranged below the shield segment on the top of the trolley; Two stereo transmission components (100) are fixed between the trolleys, and each stereo transmission component (100) comprises: a first target prism (3), a first central screw rod (5), a universal ball shaft (7), a second central screw rod (12), a screw rod connector (11), a third central screw rod (15), a second target prism (13) and a hammer ball (14), and a transverse suspension screw rod (9) which are coaxially connected in sequence from top to bottom. One end of the transverse suspension screw rod (9) is welded to the trolley, and the other end thereof crosses the axial hole of the universal ball shaft (7) and is perpendicular to the first central screw rod (5), so that the universal ball shaft (7) can swing vertically with mechanical gravity. A first forced centering tripod (17) is arranged at the middle channel below the trolley; a second forced centering tripod (18) disposed at the rear side of the first forced centering tripod (17); A total station (1) is successively arranged on the first forced centering tripod (17) and the measuring basket (2); A rear-view prism (16) is arranged on the second forced centering tripod (18).

2. The device for transmitting a three-dimensional wire path in a sharp curve shield tunnel according to claim 1, characterized in that: Each three-dimensional transmission component also includes: a first universal ball shaft nut (6) and a second universal ball shaft nut (8), wherein the first universal ball shaft nut (6) connects the first central screw rod (5) and the universal ball shaft (7); and the second universal ball shaft nut (8) connects the second central screw rod (12) and the universal ball shaft (7).

3. The device for transmitting a three-dimensional wire path in a sharp curve shield tunnel according to claim 1, characterized in that: Each three-dimensional transmission component also includes: a suspension screw rod nut (10), wherein the suspension screw rod nut (10) fixes the transverse suspension screw rod (9) to the universal ball shaft (7).

4. The device for transmitting a three-dimensional wire path in a sharp curve shield tunnel according to claim 1, characterized in that: Each stereo transmission component also includes: two target prism nuts (4), one target prism nut (4) connects the first target prism (3) and the first center screw rod (5); the other target prism nut (4) connects the second target prism (13) and the third center screw rod (15).

5. The device for transmitting a three-dimensional wire path in a sharp curve shield tunnel according to any one of claims 1 to 4, characterized in that: The center of the first target prism (3) and the center of the second target prism (13) in each stereo transmission assembly are on the same plumb line.

6. A construction method for a device for transmitting a three-dimensional wire path in a sharp curve shield tunnel, characterized in that: include: S1. At the sharp curve of the trolley, the conductor route is selected to enter from the construction channel under the trolley; S2, setting the first forced centering tripod (17) at the middle channel below the trolley, setting the second forced centering tripod (18) at a predetermined position behind the first forced centering tripod (17), and mounting the rear-view prism (16) on the second forced centering tripod (18); S3, fixing the two stereo transmission components (100) at appropriate positions selected between the trolleys, and the hammer ball (14) in the stereo transmission component (100) is vertically downward under the action of gravity, so that the first target prism (3) and the second target prism (13) are on the same plumb line; S4, setting up the total station (1) on the first forced centering tripod (17), and transmitting the coordinates of the traverse measurement points to the second target prism (13) and the first target prism (3) in sequence based on the total station (1); S5, transferring the total station (1) to the measuring basket (2) to continue the transmission of the coordinates of the traverse measurement points; S6. Using the total station (1) on the measuring basket (2), the shield machine forward-looking target prism (19) is measured to complete the wire coordinate transfer measurement work.

7. The construction method of the device for transmitting a three-dimensional wire path in a sharp curve shield tunnel according to claim 6, characterized in that S4 include: Using the first forced centering tripod (17) and the second forced centering tripod (18) as reference points, directly measuring the point coordinates of the second target prism (13) through a total station (1) to transfer the wire measurement point coordinates to the second target prism (13); The first target prism (3) and the second target prism (13) are placed on the same plumb line so that the coordinates of the wire measurement point are transmitted to the first target prism (3) via the second target prism (13).

8. The construction method of the device for transmitting a three-dimensional wire path in a sharp curve shield tunnel according to claim 6, characterized in that: Before executing S3, also include: Assemble the two stereo transfer components.

9. The construction method of the device for transmitting three-dimensional wires in a sharp curve shield tunnel as claimed in claim 8, characterized in that: The assembly process of each stereo transfer component is as follows: One end of the transverse suspension screw rod (9) is welded to the trolley, and the other end is passed through the shaft hole of the universal ball shaft (7) and fixed with a suspension screw rod nut (10); The first target prism (3) is mounted on the upper screw end of the first central screw rod (5), and the lower screw end of the first central screw rod (5) is tightened and fixed on the universal ball shaft (7) through a universal ball shaft first nut (6) located on the upper side of the universal ball shaft (7); The upper screw end of the second central screw rod (12) is tightened and fixed on the universal ball shaft (7) through the universal ball shaft second nut (8) located on the lower side of the universal ball shaft (7); Install the screw rod connector (11) between the lower screw end of the second center screw rod (12) and the upper screw end of the third center screw rod (15); The second target prism (13) is mounted on the lower screw end of the third center screw rod (15), and the centers of the second target prism (13) and the first target prism (3) are coaxial with the first center screw rod (5), the second center screw rod (12) and the third center screw rod (15); A hammer ball (14) is suspended below the second target prism (13) so that the first center screw rod (5) and the second center screw rod (12) connected to the upper and lower sides of the universal ball shaft (7) always maintain a vertical state, and the first target prism (3) and the second target prism (13) are on the same plumb line.