Automatic detection method for monitoring prism mark damage
By installing a camera on the intelligent total station, the three-dimensional coordinates and image data of the monitoring prism are automatically collected and analyzed, and the problem of untimely and inefficient damage detection of monitoring prism marks is solved, and efficient and reliable automatic detection of prism marks is achieved to ensure that The timeliness and accuracy of railway engineering safety monitoring.
Patent Information
- Application Number
- CN202411239690.6
- Authority / Receiving Office
- CN · China
- Patent Type
- Applications(China)
- Current Assignee / Owner
- Filing Date
- 2024-09-05
- Publication Date
- 2024-11-26
AI Technical Summary
In the prior art, monitoring prism mark damage detection relies on manual inspection, which has low efficiency and poor accuracy, resulting in untimely monitoring and high cost, affecting the timeliness and accuracy of railway engineering safety monitoring.
Install a camera on the intelligent total station to automatically collect and monitor the three-dimensional coordinates and image data of the prism, and determine whether the prism logo is damaged through differential grayscale matrix analysis to achieve automatic detection.
It improves the efficiency and accuracy of monitoring prism mark detection, reduces the need for manual patrols, ensures the smooth progress of safety monitoring of railway subgrade and rail projects, and is low-cost and high-yield.
Smart Images

Figure CN119022902A_ABST
Abstract
Description
Technical Field
[0001] The invention belongs to the technical field of engineering safety monitoring, and in particular is an automatic detection method for monitoring damage of prism marks. Background Art
[0002] With the rapid development of rail transit, the number of national railways, subways and other lines has increased rapidly, and it is inevitable that there will be cross-overs between lines. In the process of subway section tunnels passing under existing railway lines, tunnel construction will destroy the original balance of the strata, which will cause settlement and displacement of the surface, causing deformation of the soil above the tunnel, and then affecting the shape and position of the track, which will directly affect the operational safety of the railway. In addition, due to the excessive settlement of the surface caused by tunnel excavation, the uneven settlement of surrounding buildings will affect the cracking or even collapse of the buildings, posing a major safety hazard to the surrounding buildings.
[0003] In order to ensure the safety of railway operation during tunnel underpass construction, it is necessary to conduct periodic monitoring of railway subgrade settlement, railway track geometric deformation, etc. during the construction of the underpass tunnel to avoid accidents that endanger the safe operation of the railway.
[0004] When monitoring the railway tracks in operation, monitoring prism marks are often placed at certain intervals on the railway subgrade and railway tracks, and then the intelligent total station at the monitoring station is used to periodically observe each monitoring prism to determine whether the track subgrade or track has deformed. However, sometimes the monitoring prism marks may be greatly deformed or overturned for various reasons, resulting in damage, which makes the monitoring results unreliable, causing work stoppages or monitoring results that do not meet specifications.
[0005] At present, the damage of monitoring prism signs is mainly checked by manual inspection. Due to the large number of monitoring prism signs, usually up to thousands, the manual inspection method has problems such as low efficiency, large workload and poor accuracy. Each inspection requires a lot of manpower and material resources, which limits the timeliness and accuracy of railway project safety monitoring. In addition, during the monitoring of operating railways, the safe operation window time for personnel to enter the railway area is short, and it is difficult to carry out periodic and continuous inspections for thousands of monitoring points. Summary of the invention
[0006] The present invention aims to solve the deficiencies of the above-mentioned prior art and proposes an automatic detection method for monitoring prism mark damage, so as to automatically detect the status of the monitoring prism mark, thereby being able to efficiently and quickly determine whether the monitoring prism mark is damaged, and provide favorable support for the maintenance of the monitoring prism mark.
[0007] In order to achieve the above-mentioned purpose, the present invention adopts the following technical scheme:
[0008] The automatic detection method for monitoring prism mark damage of the present invention is characterized in that it includes the following steps:
[0009] Step 1: A camera is set on an intelligent total station with an automatic motor to sequentially obtain the initial image data of n monitoring prisms, and at the same time, the initial three-dimensional coordinate data of n monitoring prisms are obtained by coordinate measurement of the intelligent total station; wherein, the initial three-dimensional coordinates of the jth monitoring prism are marked as , the initial image data is recorded as ; j = 1, 2, 3, …, n;
[0010] Step 2: Define the current control cycle as i, and initialize i=1;
[0011] Will As the three-dimensional coordinates of the jth monitoring prism in the i-1th control cycle ;
[0012] Will As the image data in the i-1th control cycle ;
[0013] In the i-th control cycle, the intelligent total station receives a signal including The j-th control instruction is used to rotate the telescope direction of the intelligent total station to roughly align the azimuth of the j-th monitoring prism;
[0014] Step 3: After receiving the automatic search instruction, the intelligent total station searches for the j-th monitoring prism according to the left and right search angle range HAngle and the up and down search angle range VAngle in the automatic search instruction. If the feedback result is 0, it means that the j-th monitoring prism is successfully searched and locked, and step 4 is executed; otherwise, it means that the monitoring prism search fails, and step 5 is executed;
[0015] Step 4: After receiving the automatic measurement instruction, the intelligent total station measures the j-th monitoring prism. If the feedback result is 0, it means that the j-th monitoring prism is measured successfully, and step 6 is executed; otherwise, it means that the measurement fails, and step 7 is executed;
[0016] Step 5: After adjusting the search range, return to step 3. If the search fails multiple times in a row, go to step 8.
[0017] Step 6: After receiving the acquisition instruction, the intelligent total station obtains the three-dimensional coordinates of the jth monitoring prism in the i-th control cycle and image data , and judge and Is the change in value less than or equal to the set threshold value T deformation, if so, it means that the detection state of the jth monitoring prism in the i-th control cycle is normal, and the process ends; otherwise, execute step 9;
[0018] Step 7: After the intelligent total station receives the automatic measurement instruction again, it returns to step 4 for execution. If the measurement fails for multiple consecutive times, it executes step 8;
[0019] Step 8: After receiving the image acquisition instruction, the intelligent total station obtains the image data of the jth monitoring prism in the i-th control cycle , and execute step 9;
[0020] Step 9: Calculation The gray value matrix and The difference gray matrix between the gray value matrices , and statistically calculate the difference gray matrix The absolute value of the gray value is greater than the gray threshold T gray The number N;
[0021] If N≤T number When , it means that the detection status of the jth monitoring prism in the i-th control cycle is normal, otherwise, it means that the jth monitoring prism in the i-th control cycle is damaged, where T number Indicates the quantity threshold.
[0022] An electronic device of the present invention includes a memory and a processor, wherein the memory is used to store a program that supports the processor to execute the automatic detection method, and the processor is configured to execute the program stored in the memory.
[0023] The present invention provides a computer-readable storage medium, wherein a computer program is stored on the computer-readable storage medium, and the computer program executes the steps of the automatic detection method when the computer program is executed by a processor.
[0024] Compared with the prior art, the present invention has the following beneficial effects:
[0025] 1. The present invention effectively solves the problems of untimely detection of damage to monitoring prism marks, low efficiency, and high work intensity, and provides a basis for timely and accurate detection of damage to monitoring prism marks, improves the efficiency of monitoring prism mark detection, and ensures the smooth progress of safety monitoring of railway roadbeds, railway tracks and other projects.
[0026] 2. The present invention directly obtains image information by installing a camera on the intelligent total station. On the basis of not affecting the automated monitoring work, it effectively combines the automatic monitoring data and the image data to perform periodic automatic detection of the monitoring prism mark and judge the damage of the monitoring prism mark without increasing too much cost. It is an efficient, reliable, low-cost and high-yield automatic detection method for monitoring prism marks. BRIEF DESCRIPTION OF THE DRAWINGS
[0027] Figure 1 It is a schematic diagram of the structure of the detection device of the present invention;
[0028] Figure 2 This is a flow chart of the control method of the present invention;
[0029] Figure 3 A schematic diagram of the installation of a railway track monitoring prism provided in an embodiment of the present invention;
[0030] Figure 4 This is a diagram showing an example of installing a railway track monitoring prism according to an embodiment of the present invention. DETAILED DESCRIPTION
[0031] In order to make the purpose, technical solution and advantages of the present invention more clearly understood, the present invention is further described in detail below in conjunction with the accompanying drawings and embodiments. It should be understood that the specific embodiments described herein are only used to explain the present invention and are not used to limit the present invention.
[0032] It is understandable that in the prior art, the damage of monitoring prism marks is mainly determined by manual inspections, but there are many monitoring prism marks, the safe working window time is short, and manual inspections have problems such as low efficiency, high work intensity, and untimely detection. In order to ensure the smooth progress of safety monitoring of railway roadbeds, railway tracks and other projects, it is necessary to timely and accurately detect the damage of monitoring prism marks and improve the efficiency of monitoring prism mark repair.
[0033] In order to solve the above problems, the embodiment of the present invention sets a camera on the intelligent total station to automatically collect the three-dimensional coordinates and image data of the monitoring prism mark, and judges the damage of the monitoring prism mark by processing and analyzing the coordinates and image data. The present invention realizes the automatic detection of the damage of the monitoring prism mark, and effectively ensures the smooth progress of the engineering safety monitoring work.
[0034] like Figure 1 As shown, the Leica TM50 intelligent total station is used in this embodiment. Figure 1 A camera that can be controlled by software to take photos is installed at position 1 in the middle. Position 2 is an electronic device with a built-in software control program that can control the intelligent total station to automatically measure the monitoring prism periodically and obtain data.
[0035] In this embodiment, an automatic detection method for monitoring prism mark damage is provided. Figure 2 As shown, the steps are as follows:
[0036] Step S1: A camera is set on an intelligent total station with an automatic motor to sequentially obtain the initial image data of n monitoring prisms, and at the same time, the initial three-dimensional coordinate data of n monitoring prisms are obtained by coordinate measurement of the intelligent total station; wherein the initial three-dimensional coordinates of the jth monitoring prism are , the initial image data is recorded as ; j = 1, 2, 3, …, n;
[0037] Step S2: define the current control cycle as i, and initialize i=1;
[0038] Will As the three-dimensional coordinates of the jth monitoring prism in the i-1th control cycle ;
[0039] Will As the image data in the i-1th control cycle ;
[0040] In the i-th control cycle, the intelligent total station receives The jth control instruction "%R1Q, 9027: ”, and is used to rotate the telescope direction of the intelligent total station to roughly align the azimuth of the jth monitoring prism;
[0041] Step S3: After receiving the automatic search instruction "%R1Q,9037:HAngle,VAngle,0", the intelligent total station searches for the jth monitoring prism according to the left and right search angle range HAngle and the up and down search angle range VAngle in the automatic search instruction. In this embodiment, the first search is HAngle=0.03, VAngle=0.03. If the feedback result is 0, it means that the jth monitoring prism is successfully searched and locked, and step S4 is executed; otherwise, it means that the monitoring prism search fails, and step S5 is executed;
[0042] Step S4: After receiving the automatic measurement instruction "%R1Q,2008:1,1", the intelligent total station measures the j-th monitoring prism. If the feedback result is 0, it means that the j-th monitoring prism is measured successfully, and step S6 is executed; otherwise, it means that the measurement fails, and step S7 is executed;
[0043] Step S5: After adjusting the search range HAngle=0.08, VAngle=0.08, return to step S3. If the search fails for multiple times in a row, execute step S8. In this embodiment, the number of consecutive searches is set to 5.
[0044] Step S6: After receiving the acquisition instruction "%R1Q,2108:2000,2", the intelligent total station obtains the three-dimensional coordinates of the jth monitoring prism in the i-th control cycle and image data , using formula (1) to calculate the change in the three-dimensional coordinates of the j-th monitoring prism from the i-1-th control period to the i-th period ;
[0045] (1)
[0046] Using Variation , calculate the change of the jth monitoring prism according to formula (2): ;
[0047] (2)
[0048] Determine the amount of change Is it less than or equal to the set threshold T? deformation If yes, it means that the detection state of the jth monitoring prism in the i-th control cycle is normal, and the process ends; otherwise, execute step S9; in this embodiment, for the railway track deformation monitoring threshold T deformation , is 3mm.
[0049] Step S7: After the intelligent total station receives the automatic measurement instruction "%R1Q, 2008:1,1" again, it returns to step S4 for execution. If the measurement fails for multiple consecutive times, step S8 is executed. In this embodiment, the number of consecutive measurements is set to 5.
[0050] Step S8: After receiving the image acquisition instruction "%R1Q,2108:2000,1", the intelligent station obtains the image data of the jth monitoring prism in the i-th control cycle. , and execute step S9;
[0051] Step S9: Use the formula Gray=R×0.3+G×0.59+B×0.11 to calculate the gray value of each pixel in the image, and get and The gray matrix and . R, G, and B represent the red (R), green (G), and blue (B) color values corresponding to each pixel in the color image, ranging from 0 to 255.
[0052] Calculate according to formula (3) and The difference gray matrix :
[0053] (3)
[0054] And statistical difference gray matrix The absolute value of the gray value is greater than the gray threshold T grayIn this embodiment, the gray threshold T for monitoring the deformation of railway tracks is gray Set to 20;
[0055] If N≤T number When , it means that the detection status of the jth monitoring prism in the i-th control cycle is normal, otherwise, it means that the jth monitoring prism in the i-th control cycle is damaged, where T number In this embodiment, the quantity threshold T for railway track deformation monitoring is number Set to 10.
[0056] In order to further and more clearly show the monitoring prism sign installation structure, Figure 3 The schematic diagram of the prism installation in railway track deformation monitoring is shown, where: Figure 3 Part (a) is the monitoring prism in a normal state. Figure 3 In part (b), prism R2 is a damaged prism.
[0057] Figure 4 Shows an example of prism installation for railway track deformation monitoring.
[0058] In this embodiment, an electronic device includes a memory and a processor, wherein the memory is used to store a program that supports the processor to execute the above method, and the processor is configured to execute the program stored in the memory.
[0059] In this embodiment, a computer-readable storage medium stores a computer program on the computer-readable storage medium, and the computer program executes the steps of the above method when executed by a processor.
Claims
1. An automatic detection method for monitoring prism mark damage, characterized in that: The following steps are involved: Step 1: A camera is set on an intelligent total station with an automatic motor to sequentially obtain the initial image data of n monitoring prisms, and at the same time, the initial three-dimensional coordinate data of n monitoring prisms are obtained by coordinate measurement of the intelligent total station; wherein, the initial three-dimensional coordinates of the jth monitoring prism are marked as , the initial image data is recorded as ; j = 1, 2, 3, …, n; Step 2: Define the current control cycle as i, and initialize i=1; Will As the three-dimensional coordinates of the jth monitoring prism in the i-1th control cycle ; Will As the image data in the i-1th control cycle ; In the i-th control cycle, the intelligent total station receives a signal including The j-th control instruction is used to rotate the telescope direction of the intelligent total station to roughly align the azimuth of the j-th monitoring prism; Step 3: After receiving the automatic search instruction, the intelligent total station searches for the j-th monitoring prism according to the left and right search angle range HAngle and the up and down search angle range VAngle in the automatic search instruction. If the feedback result is 0, it means that the j-th monitoring prism is successfully searched and locked, and step 4 is executed; otherwise, it means that the monitoring prism search fails, and step 5 is executed; Step 4: After receiving the automatic measurement instruction, the intelligent total station measures the j-th monitoring prism. If the feedback result is 0, it means that the j-th monitoring prism is measured successfully, and step 6 is executed; otherwise, it means that the measurement fails, and step 7 is executed; Step 5: After adjusting the search range, return to step 3. If the search fails multiple times in a row, go to step 8. Step 6: After receiving the acquisition instruction, the intelligent total station obtains the three-dimensional coordinates of the jth monitoring prism in the i-th control cycle and image data , and judge and Is the change in value less than or equal to the set threshold value T deformation , if so, it means that the detection state of the jth monitoring prism in the i-th control cycle is normal, and the process ends; otherwise, execute step 9; Step 7: After the intelligent total station receives the automatic measurement instruction again, it returns to step 4 for execution. If the measurement fails for multiple consecutive times, it executes step 8; Step 8: After receiving the image acquisition instruction, the intelligent total station obtains the image data of the jth monitoring prism in the i-th control cycle , and execute step 9; Step 9: Calculation The gray value matrix and The difference gray matrix between the gray value matrices , and statistically calculate the difference gray matrix The absolute value of the gray value is greater than the gray threshold T gray The number N; If N≤T number When , it means that the detection status of the jth monitoring prism in the i-th control cycle is normal, otherwise, it means that the jth monitoring prism in the i-th control cycle is damaged, where T number Indicates the quantity threshold.
2. An electronic device, comprising a memory and a processor, characterized in that: The memory is used to store a program that supports the processor to execute the automatic detection method according to claim 1, and the processor is configured to execute the program stored in the memory.