Emergency plan management method, emergency linkage control method and system
By dismantling the emergency plan into a minimum executable unit and updating the emergency plan database in real time, combining big data analysis to assist decision-making, the existing emergency plan is solved, and the problem of insufficient flexibility and real-time performance in responding to emergencies is realized. efficient, flexible and real-time response capabilities.
Patent Information
- Application Number
- CN202411505208.9
- Authority / Receiving Office
- CN · China
- Patent Type
- Applications(China)
- Current Assignee / Owner
- Filing Date
- 2024-10-28
- Publication Date
- 2024-11-26
AI Technical Summary
The existing emergency plans are not flexible and real-time in responding to emergencies, and cannot be updated and adjusted in time, resulting in lagging content when facing real-time changing emergencies.
Disassemble the emergency plan into a minimum executable unit, build and update the emergency plan database in real time, optimize the emergency plan through machine learning algorithms, combine big data analysis to assist decision-making, and quickly and accurately find matching emergency plans from the emergency plan database and execute them.
It improves the real-time and flexibility of emergency plans, ensures that emergency plans are always synchronized with actual needs, and improves the implementation efficiency of emergency response and the flexibility and real-timeness of responding to emergencies.
Smart Images

Figure CN119026959A_ABST
Abstract
Description
Technical Field
[0001] The present invention belongs to the field of data processing technology, and relates to emergency response plan processing technology for sudden incidents, and in particular to an emergency response plan management method for sudden incidents, an emergency linkage control method and a system. Background Art
[0002] During the operation of highway tunnels, if the emergency plan is not activated in time when an emergency occurs (for example, a fire, or an accident or blockage under heavy traffic or bad weather conditions), a secondary accident is very likely to occur. Once a secondary accident occurs, the consequences are much more serious than the primary accident. As a pre-made action plan, the emergency plan aims to ensure that when an emergency occurs, it can be responded to quickly and effectively. The advantage of the emergency plan is that it clarifies the responsibilities and response procedures of all parties in advance and prepares emergency resources, so as to guide the rapid, efficient and orderly implementation of emergency rescue. In this way, the personal injury, property loss and environmental damage caused by the emergency are minimized. Therefore, in the operation of highway tunnels, the emergency plan for emergencies plays a vital role.
[0003] However, fixed emergency plans also have some limitations in practical applications. Emergency events are highly unpredictable and changeable, and the specific circumstances and changing factors of each event may be different. Therefore, when facing real-time changing emergencies, fixed emergency plans often cannot be updated and adjusted in a timely manner, and there is a phenomenon of lagging content.
[0004] In summary, although the existing emergency plans play an important guiding role in emergency management, they are obviously insufficient in flexibility and real-time performance when responding to emergencies. Summary of the invention
[0005] In view of the above-mentioned problems that existing emergency plans lack flexibility and real-time performance when dealing with emergencies, the present invention provides an emergency plan management method, an emergency linkage control method and a system for emergencies, which breaks down the emergency plan into minimum executable units, builds and updates the emergency plan database in real time, realizes the electronicization of the emergency plan, optimizes the management of the emergency plan by scenario and level, can provide effective handling guidance when dealing with emergencies, quickly and accurately finds the corresponding emergency plan from the emergency plan database, and improves the real-time performance and flexibility of dealing with emergencies.
[0006] In a first aspect, the present invention provides a method for managing an emergency plan for an emergency, comprising the following steps: Data acquisition steps: obtain historical emergency on-site monitoring data and its corresponding emergency response plan; Data processing steps: structure the emergency plan, decompose it into multiple minimum executable units with a clear execution order, establish the relationship between the minimum executable units, divide the emergency plans into different levels according to the type, severity and impact of the emergency, and form an emergency plan database; Update steps: Every time an emergency occurs, the on-site monitoring data of the emergency, the final emergency plan implemented, and the actual rescue decision-making data are recorded. The on-site monitoring data of the emergency and the actual rescue decision-making data are learned through machine learning algorithms to update and optimize the emergency plan database.
[0007] In some embodiments, in the data processing step, emergency plans are divided into four categories according to the type of emergency event: fire, earthquake, chemical leakage, and traffic accident.
[0008] In some embodiments, in the data processing step, emergency plans are divided into four levels according to the severity and scope of impact of the emergency, with the first-level emergency plan corresponding to the greatest severity and scope of impact of the emergency, and the fourth-level emergency plan corresponding to the smallest severity and scope of impact of the emergency; the activation conditions and response procedures of emergency plans at each level are clarified to ensure that emergency plans of corresponding levels can be quickly activated in emergency situations.
[0009] In a second aspect, the present invention provides an emergency linkage control method based on big data analysis and auxiliary decision-making, comprising the following steps: Data acquisition steps: obtain historical emergency on-site monitoring data and its corresponding emergency response plan and emergency on-site real-time monitoring data; Data processing steps: structure the emergency plan, decompose it into multiple minimum executable units with a clear execution order, and divide it into emergency plans of different levels for different scenarios according to the type, severity and impact scope of the emergency, so as to form an emergency plan database; divide the on-site monitoring data of historical emergencies into training sets and test sets; Prediction model construction step: constructing an emergency prediction model with emergency on-site monitoring data as input and emergency accident characteristics as output, training the emergency prediction model through a training set, and verifying the trained emergency prediction model through a test set, wherein the emergency accident characteristics include emergency time, emergency location, emergency type and emergency level; Prediction step: input the real-time monitoring data of the emergency scene into the emergency prediction model to predict the accident characteristics of the emergency; Decision-making steps: According to the predicted accident characteristics of the emergency, search the emergency plan database for the emergency plan that matches the accident characteristics of the emergency, and take the emergency plan that best matches as the final emergency plan; Emergency steps: Control and execute the final emergency plan; Update steps: Every time an emergency occurs, the on-site monitoring data of the emergency, the final emergency plan implemented, and the actual rescue decision-making data are recorded. The on-site monitoring data of the emergency and the actual rescue decision-making data are learned through machine learning algorithms to update and optimize the emergency plan database.
[0010] In some embodiments, in the emergency step, the emergency plan is controlled to be executed according to a preset control strategy based on the type of emergency event, and the methods of controlling the execution of the emergency plan include automatic joint control, manual joint control, and delayed start joint control; the automatic joint control is to automatically execute the minimum executable unit in the emergency plan according to the preset control strategy based on the type of emergency event; the manual joint control is to manually control the execution of the minimum executable unit in the emergency plan according to the preset control strategy based on the type of emergency event; the delayed start joint control is to delay the execution of the minimum executable unit in the emergency plan according to the preset control strategy based on the type of emergency event.
[0011] In a third aspect, the present invention provides an emergency linkage control system based on big data analysis and auxiliary decision-making, which is used to implement the emergency linkage control method based on big data analysis and auxiliary decision-making described in the second aspect of the present invention, including: Data acquisition module, used to obtain historical emergency on-site monitoring data and its corresponding emergency response plan; Data monitoring system, used to monitor the on-site environmental data, traffic data and facility working status data of emergencies in real time; The data processing module is used to perform structured processing on the emergency plan, decompose the emergency plan into multiple minimum executable units with a clear execution order, and divide it into emergency plans of different levels for different scenarios according to the type, severity and impact scope of the emergency, so as to form an emergency plan database; divide the on-site monitoring data of historical emergencies into training sets and test sets; The prediction model building module uses the on-site monitoring data of emergencies as input and the accident characteristics of emergencies as output to build an emergency prediction model; The training and verification module is used to train the emergency prediction model through the training set and verify the trained emergency prediction model through the test set; The prediction module inputs the real-time monitoring data of the emergency scene into the emergency prediction model to predict the accident characteristics of the emergency; The auxiliary decision-making module searches for an emergency plan that matches the characteristics of the predicted emergency event from the emergency plan database, and outputs the most matching emergency plan as the final emergency plan; The emergency control unit is linked with the data monitoring system to control the execution of the final emergency plan; The update module records the on-site monitoring data of the emergency, the final emergency plan implemented, and the actual rescue decision-making data every time an emergency occurs. It also uses machine learning algorithms to learn the on-site monitoring data of the emergency and the actual rescue decision-making data, and updates and optimizes the emergency plan database.
[0012] In some embodiments, the data monitoring system includes any one or a combination of a fire monitoring unit, a video monitoring unit, a traffic monitoring unit, a lighting monitoring unit, and a ventilation monitoring unit.
[0013] In some embodiments, the fire monitoring unit includes: a flame detector installed on the top or side wall of a highway tunnel to detect flames in the highway tunnel; a temperature detector installed on the top or side wall of a highway tunnel to detect the temperature in the highway tunnel; a smoke detector installed on the top or side wall of a highway tunnel to detect the smoke concentration in the highway tunnel; a fire alarm control module to determine whether it is necessary to issue an alarm or start a fire extinguishing procedure based on the signals detected by the flame detector, the temperature detector and the smoke detector and preset conditions; a control panel connected between the fire alarm control module and the gas fire extinguishing system, when the fire alarm control module determines that the fire extinguishing procedure needs to be started, the control panel activates the gas fire extinguishing system to enable the gas fire extinguishing system to work and extinguish the fire; an alarm module to send an alarm signal when the fire alarm control module determines that an alarm needs to be issued; a fire graphics workstation connected to the fire alarm control module to display fire information in graphics; The video monitoring unit includes: a network camera for acquiring video images in the highway tunnel; a network hard disk recorder for recording and storing video data; a video management server for managing and controlling video streams and automatically switching monitoring images, and the video management server is linked with other monitoring units in the data monitoring system; a display module connected to the video management server for displaying video images; The traffic monitoring unit includes: a vehicle detector for real-time monitoring of vehicle flow, vehicle speed, and vehicle type in a highway tunnel; an overheight detector for detecting whether there is an overheight vehicle; a video analysis device for converting information detected by the vehicle detector and the overheight detector into traffic intelligence information, wherein the traffic intelligence information includes road condition information, guidance information, and speed limit prompt information; a display device for displaying traffic intelligence information; and an indication device for indicating lane usage and tunnel traffic status. The lighting monitoring unit includes: a light intensity detector for detecting the light intensity of the lighting fixture; a lighting control module for obtaining the brightness setting in the current environment through a machine learning algorithm according to the detected light intensity and a preset lighting standard, and adjusting the brightness of the lighting fixture according to the brightness setting; The ventilation monitoring unit includes: a CO / VI detector installed on the side wall of a highway tunnel for detecting the carbon monoxide (CO) concentration and the visibility (VI); a wind speed and direction detector for detecting the wind speed and direction in the highway tunnel; a fan for increasing the gas pressure in the highway tunnel and discharging the gas; and a ventilation control module for controlling the operating state of the fan according to the monitored carbon monoxide (CO) concentration, visibility (VI) and ventilation demand.
[0014] In some embodiments, the emergency control unit includes an emergency control module and a communication unit, wherein the emergency control module is used to perform linkage control with the data monitoring system, control the execution of the final emergency plan, and control the communication unit to perform emergency communication.
[0015] In some embodiments, the emergency control module includes: The automatic joint control module automatically executes the smallest executable unit in the emergency plan according to the preset control strategy based on the type of emergency event; The manual joint control module manually controls the execution of the minimum executable unit in the emergency plan according to the preset control strategy based on the type of emergency event; The delayed start joint control module delays the execution of the smallest executable unit in the emergency plan according to the preset control strategy based on the type of emergency event.
[0016] In some embodiments, the communication unit includes a wired broadcast unit and a wired telephone unit; the wired broadcast unit is used to issue emergency instructions and notifications to relevant personnel at the emergency scene, and to dispatch personnel and vehicles and organize evacuation guidance; the wired telephone unit is used to provide a communication network for emergency communications.
[0017] Compared with the related art, the emergency plan management method for sudden incidents provided by the present invention structures the emergency plan, decomposes it into multiple minimum executable units to be executed in sequence, and then divides it into emergency plans of different levels to form an emergency plan database, and updates it according to the actual situation of each sudden incident to ensure that the emergency plan is always synchronized with actual needs, realize the electronicization of the emergency plan, optimize the management of the emergency plan by scenario and level, and can provide effective handling guidance when handling sudden incidents, thereby improving the execution efficiency of the emergency plan in the actual emergency handling execution process of sudden incidents.
[0018] Compared with related technologies, the emergency linkage control method and system based on big data analysis and assisted decision-making provided by the present invention utilize big data analysis technology to build an emergency prediction model, accurately evaluate emergencies, select emergency plans from a timely updated emergency plan database, and recommend the final emergency plan corresponding to the emergency to emergency personnel, assist in decision-making, quickly and correctly link and control various systems to perform emergency rescue work, thereby improving the flexibility and real-time response to emergencies. BRIEF DESCRIPTION OF THE DRAWINGS
[0019] The drawings described herein are used to provide a further understanding of the present invention and constitute a part of the present invention. The exemplary embodiments of the present invention and their descriptions are used to explain the present invention and do not constitute an improper limitation of the present invention. In the drawings: Figure 1 This is a flow chart of the method for managing an emergency plan for an emergency according to an embodiment of the present invention; Figure 2 This is a flow chart of an emergency linkage control method based on big data analysis and auxiliary decision-making according to an embodiment of the present invention; Figure 3 This is a structural block diagram of an emergency linkage control system based on big data analysis and auxiliary decision-making according to an embodiment of the present invention; Figure 4 This is a structural block diagram of a fire monitoring unit according to an embodiment of the present invention; Figure 5 is a structural block diagram of a video monitoring unit according to an embodiment of the present invention; Figure 6 This is a structural block diagram of a traffic monitoring unit according to an embodiment of the present invention.
[0020] In the figure: 1. Data acquisition module, 2. Data monitoring system, 211. Flame detector, 212. Temperature detector, 213. Smoke detector, 214. Fire alarm control module, 215. Control panel, 216. Alarm module, 217. Fire graphics workstation, 221. Network camera, 222. Network hard disk recorder, 223. Video management server, 224. Display module, 225. Signal transmission and conversion module, 226. Video switch, 227. Video recycling station, 231. Vehicle detector, 232. Super height detector, 233. Video analysis device, 234. Display device, 235. Indication device, 3. Data processing module, 4. Prediction model building module, 5. Training and verification module, 6. Prediction module, 7. Decision support module, 8. Emergency control unit, 9. Update module. DETAILED DESCRIPTION
[0021] In order to make the purpose, technical scheme and advantages of the present invention more clearly understood, the present invention is described and illustrated below in conjunction with the accompanying drawings and embodiments. It should be understood that the specific embodiments described herein are only used to explain the present invention and are not intended to limit the present invention. Based on the embodiments provided by the present invention, all other embodiments obtained by ordinary technicians in this field without making creative work belong to the scope of protection of the present invention.
[0022] Obviously, the drawings described below are only some examples or embodiments of the present invention. For ordinary technicians in this field, the present invention can also be applied to other similar scenarios based on these drawings without creative work. In addition, it can also be understood that although the efforts made in this development process may be complicated and lengthy, for ordinary technicians in this field related to the content disclosed by the present invention, some changes in design, manufacturing or production based on the technical content disclosed by the present invention are just conventional technical means, and should not be understood as insufficient content disclosed by the present invention.
[0023] Reference to "embodiments" in the present invention means that a particular feature, structure, or characteristic described in conjunction with the embodiments may be included in at least one embodiment of the present invention. The appearance of the phrase in various places in the specification does not necessarily refer to the same embodiment, nor is it an independent or alternative embodiment that is mutually exclusive with other embodiments. It is explicitly and implicitly understood by those of ordinary skill in the art that the embodiments described in the present invention may be combined with other embodiments without conflict.
[0024] Unless otherwise defined, the technical terms or scientific terms involved in the present invention shall have the usual meanings understood by persons with ordinary skills in the technical field to which the present invention belongs. The words "one", "a", "a", "the" and the like involved in the present invention do not indicate a quantity limitation and may indicate the singular or plural. The terms "include", "comprise", "have" and any of their variations involved in the present invention are intended to cover non-exclusive inclusions; for example, a process, method, system, product or device including a series of steps or modules (units) is not limited to the listed steps or units, but may also include steps or units that are not listed, or may also include other steps or units inherent to these processes, methods, products or devices. The words "connect", "connected", "coupled" and the like involved in the present invention are not limited to physical or mechanical connections, but may include electrical connections, whether direct or indirect. The "multiple" involved in the present invention refers to two or more. "And / or" describes the association relationship of associated objects, indicating that there may be three relationships. For example, "A and / or B" may indicate: A exists alone, A and B exist at the same time, and B exists alone. The character " / " generally indicates that the objects in the front and back relation are in an "or" relationship. The terms "first", "second", "third" and the like involved in the present invention are only used to distinguish similar objects and do not represent a specific ordering of the objects.
[0025] The first embodiment of the present invention provides a method for managing emergency response plans for emergencies. Figure 1 : is a flow chart of the emergency plan management method for emergencies according to an embodiment of the present invention. Figure 1As shown, the process includes the following steps: S1. Data acquisition step: Acquire historical on-site monitoring data of emergencies and their corresponding emergency plans. Specifically, on-site monitoring data includes environmental data, traffic data, and facility working status data.
[0026] S2. Data processing steps: structure the emergency plan, decompose it into multiple minimum executable units with a clear execution order, establish the relationship between the minimum executable units, divide the emergency plans into different levels according to the type, severity and scope of impact of the emergency, and form an emergency plan database.
[0027] It should be noted that the emergency plan is structured so that the description and execution standards of each minimum executable unit are unified, which is convenient for emergency personnel to accurately understand and operate during the execution process. Each minimum executable unit is clear, specific and operational, so that the actions of emergency personnel can be clearly guided during the execution process. The minimum executable units are logically sorted, the order of execution is clarified, and the relationship between the minimum executable units is established to ensure smooth connection during the execution process.
[0028] Specifically, the emergency plans are divided into four categories according to the types of emergencies: fire, earthquake, chemical leakage, and traffic accidents. It should be noted that for each type of emergency plan, a specific emergency handling process is formulated, including initial response, resource allocation, on-site disposal and other links.
[0029] Specifically, emergency plans are divided into four levels according to the severity and scope of impact of the emergency. The first-level emergency plan corresponds to the emergency with the greatest severity and scope of impact, while the fourth-level emergency plan corresponds to the emergency with the smallest severity and scope of impact. The activation conditions and response procedures of emergency plans at all levels are clarified to ensure that emergency plans of corresponding levels can be quickly activated in emergency situations.
[0030] S3. Update step: Every time an emergency occurs, the on-site monitoring data of the emergency, the final emergency plan implemented, and the actual rescue decision-making data are recorded, and the on-site monitoring data of the emergency and the actual rescue decision-making data are learned through machine learning algorithms to update and optimize the emergency plan database.
[0031] The emergency plan is learned by machine learning algorithms, and updated and optimized in real time according to the actual implementation situation. The update and optimization include: adjusting the order of the minimum executable units, adding or reducing certain minimum executable units, and modifying the content of the minimum executable units. Through continuous updating and optimization, the emergency plan is ensured to always keep pace with the actual situation, and the flexibility and real-time performance of the emergency plan for sudden events are improved.
[0032] It should be noted that whenever an accident occurs, the staff will correct the accident information to ensure the accuracy of the data. The corrected accident information includes key information such as accident type, accident level, and accident environmental factors. At the same time, the decisions made by the staff in actual emergency rescue are recorded. The machine learning algorithm uses these corrected accident information and actual rescue decision data for learning. The machine learning algorithm analyzes the characteristics of the accident, the rescue results, and the correlation between the decision and the results. As time goes by and data accumulates, the machine learning algorithm can identify which decisions are more effective in specific environments, thereby continuously optimizing the emergency plan. Specifically, the machine learning algorithm will update the accident information and emergency plan that assist decision-making based on each accident and its corresponding emergency rescue policy. This update is not a simple replacement, but a fine-tuning or reconstruction of the existing emergency plan through the machine learning algorithm to ensure that the emergency plan is more in line with the actual situation and rescue needs.
[0033] The above-mentioned emergency plan management method for sudden incidents in the embodiment of the present invention digitizes the emergency plan, manages the emergency plan by scenario and level, and updates and optimizes the emergency plan according to the actual execution situation through a machine learning algorithm. It can provide effective emergency handling when handling sudden incidents, assist emergency personnel in decision-making, and improve the flexibility and real-time nature of responding to sudden incidents.
[0034] The second embodiment of the present invention provides an emergency linkage control method based on big data analysis and auxiliary decision-making. Figure 2 is a flow chart of an emergency linkage control method based on big data analysis and auxiliary decision-making according to an embodiment of the present invention. Figure 2 As shown, the process includes the following steps: S1. Data acquisition step: Acquire historical on-site monitoring data of emergencies and their corresponding emergency plans. Specifically, on-site monitoring data includes environmental data, traffic data, and facility working status data.
[0035] S2. Data processing steps: Structural processing of emergency plans, decomposition of emergency plans into multiple minimum executable units with clear execution order, establishment of associations between the minimum executable units, classification of emergency plans of different levels according to the type, severity and scope of impact of the emergency, and formation of an emergency plan database. Divide the historical emergency on-site monitoring data into training sets and test sets.
[0036] It should be noted that the emergency plan is structured so that the description and execution standards of each minimum executable unit are unified, which is convenient for emergency personnel to accurately understand and operate during the execution process. Each minimum executable unit is clear, specific and operational, so that the actions of emergency personnel can be clearly guided during the execution process. The minimum executable units are logically sorted, the order of execution is clarified, and the relationship between the minimum executable units is established to ensure smooth connection during the execution process.
[0037] Specifically, the emergency plans are divided into four categories according to the types of emergencies: fire, earthquake, chemical leakage, and traffic accidents. It should be noted that for each type of emergency plan, a specific emergency handling process is formulated, including initial response, resource allocation, on-site disposal and other links.
[0038] Specifically, emergency plans are divided into four levels according to the severity and scope of impact of the emergency. The first-level emergency plan corresponds to the emergency with the greatest severity and scope of impact, while the fourth-level emergency plan corresponds to the emergency with the smallest severity and scope of impact. The activation conditions and response procedures of emergency plans at all levels are clarified to ensure that emergency plans of corresponding levels can be quickly activated in emergency situations.
[0039] Specifically, in some embodiments, the severity and impact range of the emergency corresponding to the first-level emergency plan are: causing more than 3 deaths; or less than 3 deaths, and more than 5 serious injuries; or more than 10 serious injuries. Causing direct economic losses of more than 10 million yuan. Vehicle collisions occur in tunnels and overpasses, and fuel tanks leak and cause fires. The severity and impact range of the emergency corresponding to the second-level emergency plan are: causing less than 3 deaths; or more than 3 and less than 10 serious injuries; or more than 10 minor injuries. Causing direct economic losses of more than 1 million yuan and less than 10 million yuan. More than 3 vehicles collide continuously in tunnels and overpasses, or more than one vehicle collide, and fuel tanks leak; or vehicles naturally. The severity and impact range of the emergency corresponding to the third-level emergency plan are: causing less than 3 serious injuries; or more than 3 and less than 10 minor injuries. Causing direct economic losses of more than 100,000 yuan and less than 1 million yuan. The severity and impact range of the emergency corresponding to the fourth-level emergency plan are: causing less than 3 minor injuries. Causing direct economic losses of less than 100,000 yuan.
[0040] S3, prediction model construction step: construct an emergency prediction model with emergency on-site monitoring data as input and emergency accident characteristics as output, train the emergency prediction model through the training set, and verify the trained emergency prediction model through the test set. The emergency accident characteristics include emergency time, emergency location, emergency type and emergency level.
[0041] The constructed emergency prediction model can accurately identify emergencies and obtain rescue needs that are more in line with actual conditions.
[0042] S4, prediction step: input the real-time monitoring data of the emergency scene into the emergency prediction model to predict the accident characteristics of the emergency.
[0043] S5, decision-making step: according to the predicted emergency accident characteristics, search the emergency plan that matches the emergency accident characteristics from the emergency plan database, and take the emergency plan that best matches as the final emergency plan.
[0044] S6. Emergency steps: Control the implementation of the final emergency plan.
[0045] Specifically, when controlling the execution of the final emergency plan, the emergency plan is executed according to the preset control strategy based on the type of emergency. The methods of controlling the execution of the emergency plan include automatic joint control, manual joint control, and delayed start joint control. The preset control strategy is configured according to the different types of emergencies, directions, and start and end pile numbers. For different types of emergencies, control strategies are formulated to clarify which equipment actions are triggered under what circumstances, and control strategies are set for various types of equipment, including startup, shutdown, and adjustment parameters. Users can choose appropriate joint control methods to control the execution of emergency plans for different types of emergencies. For example: when the type of emergency is a fire accident, the fire extinguishing system is started, the smoke exhaust equipment is turned on, and an evacuation order is issued through the broadcasting system according to the preset control strategy.
[0046] Specifically, automatic joint control is the smallest executable unit in the emergency plan that is automatically executed according to the preset control strategy based on the type of emergency. Specifically, when the preset control conditions are met (for example, smoke or high temperature is detected), the preset control strategy is automatically triggered to execute the corresponding emergency plan without manual intervention. For example, when a fire occurs, the fire extinguishing device and smoke exhaust equipment are automatically activated.
[0047] Specifically, manual joint control is to manually control the smallest executable unit in the emergency plan according to the preset control strategy based on the type of emergency. It should be noted that manual joint control is suitable for scenarios that require manual confirmation or manual intervention in special circumstances. For example: after confirming that the fire has been extinguished, the operator can manually shut down the fire extinguishing system.
[0048] Delayed start joint control is to delay the execution of the smallest executable unit in the emergency plan according to the preset control strategy based on the type of emergency. It should be noted that the start of some equipment or systems requires delayed operation to avoid misoperation or to cooperate with the actions of other equipment. For example: after a fire alarm, it may be necessary to first make an evacuation broadcast, and then start the fire extinguishing system after a delay of a few seconds to ensure that people have enough time to evacuate. Delayed start is achieved by setting a timer or conditional trigger.
[0049] S7. Update step: Every time an emergency occurs, the on-site monitoring data of the emergency, the final emergency plan implemented, and the actual rescue decision-making data are recorded, and the on-site monitoring data of the emergency and the actual rescue decision-making data are learned through machine learning algorithms to update and optimize the emergency plan database.
[0050] The emergency plan is learned by machine learning algorithms, and updated and optimized in real time according to the actual implementation situation. The update and optimization include: adjusting the order of the minimum executable units, adding or reducing certain minimum executable units, and modifying the content of the minimum executable units. Through continuous updating and optimization, the emergency plan is ensured to always keep pace with the actual situation, and the flexibility and real-time performance of the emergency plan for sudden events are improved.
[0051] It should be noted that whenever an accident occurs, the staff will correct the accident information to ensure the accuracy of the data. The corrected accident information includes key information such as accident type, accident level, and accident environmental factors. At the same time, the decisions made by the staff in actual emergency rescue are recorded. The machine learning algorithm uses these corrected accident information and actual rescue decision data for learning. The machine learning algorithm analyzes the characteristics of the accident, the rescue results, and the correlation between the decision and the results. As time goes by and data accumulates, the machine learning algorithm can identify which decisions are more effective in specific environments, thereby continuously optimizing the emergency plan. Specifically, the machine learning algorithm will update the accident information and emergency plan that assist decision-making based on each accident and its corresponding emergency rescue policy. This update is not a simple replacement, but a fine-tuning or reconstruction of the existing emergency plan through the machine learning algorithm to ensure that the emergency plan is more in line with the actual situation and rescue needs.
[0052] The above-mentioned emergency linkage control method based on big data analysis to assist decision-making in the embodiment of the present invention utilizes big data analysis technology to construct an emergency prediction model, accurately evaluates emergencies, selects emergency plans from a timely updated emergency plan database, and recommends the final emergency plan corresponding to the emergency to emergency personnel, assists in decision-making, quickly and correctly links and controls various systems to perform emergency rescue work, thereby improving the flexibility and real-time response to emergencies.
[0053] It should be noted that the steps shown in the above process or the flowchart in the accompanying drawings can be executed in a computer system such as a set of computer executable instructions, and although a logical order is shown in the flowchart, in some cases, the steps shown or described can be executed in an order different from that shown here.
[0054] The third aspect of the embodiment of the present invention provides an emergency linkage control system based on big data analysis and assisted decision-making, which is used to implement the emergency linkage control method based on big data analysis and assisted decision-making described in the second aspect of the embodiment of the present invention. Figure 3 : is a structural block diagram of an emergency linkage control system based on big data analysis and auxiliary decision-making according to an embodiment of the present invention, and the emergency linkage control system based on big data analysis and auxiliary decision-making includes: Data acquisition module 1, used to obtain historical emergency on-site monitoring data and its corresponding emergency response plan; Data monitoring system 2, used to monitor the on-site environmental data, traffic data and facility working status data of emergencies in real time; Data processing module 3 is used to perform structured processing on the emergency plan, decompose the emergency plan into multiple minimum executable units with a clear execution order, establish the association between the minimum executable units, and divide the emergency plans into different scenarios and different levels according to the type, severity and impact scope of the emergency, so as to form an emergency plan database; divide the historical emergency site monitoring data into training sets and test sets; Prediction model building module 4, using the on-site monitoring data of the emergency as input and the accident characteristics of the emergency as output to build an emergency prediction model; The training and verification module 5 is used to train the emergency prediction model through the training set and verify the trained emergency prediction model through the test set; Prediction module 6, inputs the real-time monitoring data of the emergency scene into the emergency prediction model to predict the accident characteristics of the emergency; The auxiliary decision-making module 7 searches for an emergency plan that matches the characteristics of the emergency event from the emergency plan database according to the predicted characteristics of the emergency event, and outputs the most matching emergency plan as the final emergency plan; The emergency control unit 8 is linked with the data monitoring system 2 to control the execution of the final emergency plan; Update module 9 records the on-site monitoring data of the emergency, the final emergency plan executed, and the actual rescue decision data every time an emergency occurs, and uses machine learning algorithms to learn the on-site monitoring data of the emergency and the actual rescue decision data to update and optimize the emergency plan database.
[0055] Specifically, the data monitoring system 2 includes any one or a combination of more than one of a fire monitoring unit, a video monitoring unit, a traffic monitoring unit, a lighting monitoring unit and a ventilation monitoring unit.
[0056] Specifically, in some embodiments, the fire monitoring unit includes a flame detector 211, a temperature detector 212, a smoke detector 213, a fire alarm control module 214, a control panel 215, an alarm module 216, and a fire graphic workstation 217. The fire alarm control module 214 is connected to the flame detector 211, the temperature detector 212, the smoke detector 213, the control panel 214, the alarm module 215, and the fire graphic workstation 216, and is used to determine whether it is necessary to issue an alarm or start a fire extinguishing program according to the signals detected by the flame detector 211, the temperature detector 212, and the smoke detector 213 and preset conditions, and send a control signal to the control panel 215 and the alarm module 216 to control the control panel 215 and the alarm module 216 to work.
[0057] The flame detector is installed on the top or side wall of the highway tunnel to detect the flame in the highway tunnel. Specifically, in a specific embodiment, the flame detector adopts a dual-wavelength flame detector. The flame detector sends the detected flame signal to the fire alarm control module, and the fire alarm control module generates an alarm control signal and sends it to the alarm module to control the alarm module to alarm.
[0058] The temperature detector is installed on the top or side wall of the highway tunnel to detect the temperature in the highway tunnel. Specifically, in some specific embodiments, the temperature detector adopts a distributed temperature-sensing optical fiber detector. The temperature detector sends the detected temperature signal to the fire alarm control module. When the temperature in the highway tunnel reaches a preset threshold, the fire alarm control module generates an alarm control signal and sends it to the alarm module to control the alarm module to alarm.
[0059] The smoke detector is installed on the top or side wall of the highway tunnel to detect the smoke concentration in the highway tunnel. Specifically, in some specific embodiments, the smoke detector adopts a photoelectric smoke detector. The smoke detector sends the detected smoke concentration signal to the fire alarm control module. When the smoke concentration in the highway tunnel is detected to reach a preset threshold, the fire alarm control module generates an alarm control signal and sends it to the alarm module to control the alarm module to alarm.
[0060] The control panel is connected between the fire alarm control module and the gas fire extinguishing system. When the fire alarm control module determines that the fire extinguishing program needs to be started, it receives the fire extinguishing control signal sent by the fire alarm control module. The control panel activates the gas fire extinguishing system according to the control signal to enable the gas fire extinguishing system to work and extinguish the fire.
[0061] The alarm module sends out an alarm signal when the fire alarm control module determines that an alarm needs to be issued. Specifically, the fire alarm control module generates an alarm control signal when it determines that an alarm needs to be issued, and controls the alarm module to send out an alarm signal. In some embodiments, the alarm module includes a manual alarm button and an audible and visual alarm. The manual alarm button manually triggers an alarm when a person discovers a fire, and the audible and visual alarm is activated to send out an audible and visual signal when receiving the alarm control signal to remind people to evacuate.
[0062] The working principle of the fire alarm unit is: when the detector in the tunnel detects flames, smoke or abnormal temperature, it will immediately transmit the signal to the fire alarm control module. The fire alarm control module determines the severity and location of the fire according to the preset algorithm and logic, and then displays the relevant information through the fire graphic workstation. If it is determined that the fire extinguishing procedure needs to be started, the fire alarm control module will activate the fire extinguishing system through the control panel. At the same time, the control sound and light alarm will sound an alarm to remind people to evacuate in time.
[0063] The fire graphic workstation is connected to the fire alarm control module and is used to display fire information graphically. The fire graphic workstation provides a simple graphical interface to display fire information and help operators quickly identify the location of the fire source and the fire situation.
[0064] Specifically, in some embodiments, the video monitoring unit includes a network camera 221 , a network hard disk recorder 222 , a video management server 223 and a display module 224 .
[0065] Specifically, the network camera is used to obtain video images in the highway tunnel.
[0066] Specifically, in some embodiments, the network camera adopts a high-definition network camera, which captures real-time high-definition video of the monitored area in real time to ensure the clarity and detail of the picture.
[0067] Specifically, in some embodiments, the video signal collected by the network camera is converted into an optical signal by the signal transmission and conversion module 225 for long-distance, high-speed transmission, and the receiving end then converts the optical signal into a data signal to ensure signal stability and anti-interference ability. Specifically, the signal transmission and conversion module uses an EPON optical terminal.
[0068] Specifically, in some embodiments, the signal transmission and conversion module distributes the electrical signal to the video management server 223 , the network hard disk video recorder 222 and the display module 224 through the video switch 226 .
[0069] Specifically, the network video recorder is used to record and store video data. The network video recorder can record and store video data 24 hours a day to ensure that historical data can be traced.
[0070] Specifically, in some embodiments, the network hard disk video recorder 222 sends the stored video data to the video recycling station 227, and plays it back through the Luxing recycling station to facilitate subsequent analysis and evidence collection.
[0071] Specifically, the video management server is used to manage and control the video stream, automatically switch the monitoring screen, and the video management server is linked with other monitoring units in the data monitoring system. For example, in the event of a fire, the video management server can automatically switch to the monitoring screen of the fire area. The video management server is linked with other monitoring units such as the fire monitoring unit to improve the response speed in emergency situations.
[0072] Specifically, the display module is connected to the video management server and is used to display video images.
[0073] Specifically, in some embodiments, the display module includes a color LCD monitor and an ultra-narrow LCD splicing screen, and the color LCD monitor and the ultra-narrow LCD splicing screen display the monitoring screen in real time to provide intuitive visual information for the monitoring personnel.
[0074] Specifically, in some embodiments, the traffic monitoring unit includes a vehicle detector 231 , an ultra-high detector 232 , a video analysis device 233 , a display device 234 and an indication device 235 .
[0075] Vehicle detectors are used to collect real-time data on traffic volume, speed, and vehicle type in highway tunnels.
[0076] The super-height detector is used to detect whether there is a super-height vehicle. Specifically, in some embodiments, the super-height detector has a built-in sound and light alarm, which can perform sound and light alarm.
[0077] The video analysis device is used to convert the information detected by the vehicle detector and the super-height detector into traffic intelligence information, which includes road condition information, guidance information and speed limit prompt information.
[0078] Specifically, in some embodiments, the video analysis device includes a video analysis processor, a video analysis server, a video analysis switch, and a video analysis workstation. The video analysis processor and the video analysis server are responsible for receiving and processing video data from various monitoring points. The video analysis switch is responsible for the rapid exchange of data to ensure the smooth transmission of real-time information. The video analysis workstation is used by operators to perform traffic condition analysis.
[0079] The display device is used to display traffic intelligence information.
[0080] Specifically, in some embodiments, the display device is a variable information board, a variable induction board and a variable speed limit board. The variable information board and the variable induction board are arranged outside the highway tunnel to provide real-time traffic information and induction information, and the variable speed limit board is arranged inside the highway tunnel to provide real-time speed limit information.
[0081] The indicating device is used to indicate the lane usage and tunnel traffic status.
[0082] Specifically, in some embodiments, the indicating device includes a lane indicator and a tunnel confinement indicator light, the lane indicator is used to indicate the lane usage, and the tunnel confinement indicator light is used to indicate the tunnel traffic status.
[0083] The working principle of the traffic monitoring unit is as follows: First, the vehicle detector and the super-high detector collect vehicle information on the road in real time, including traffic flow, speed, vehicle type, and whether there are super-high vehicles. This information is quickly transmitted to the video analysis processor and the video analysis server through the video analysis switch for processing. The analyzed data is converted into valuable traffic intelligence, and then released to the driver in real time through the variable information board, variable induction board and variable speed limit board to help them make reasonable driving decisions. At the same time, the lane indicator and tunnel confinement indicator will dynamically adjust the display content according to the traffic conditions to ensure smooth and safe traffic. In an emergency, if an over-high vehicle or traffic congestion is detected, the traffic monitoring unit immediately activates the sound and light alarm, and releases emergency information through the variable information board, etc., to respond and handle emergencies as quickly as possible.
[0084] Specifically, in some embodiments, the lighting monitoring unit includes a light intensity detector and a lighting control module. The light intensity detector is used to detect the light intensity of the lighting fixture. The lighting control module is used to obtain the brightness setting in the current environment through a machine learning algorithm based on the detected light intensity and a preset lighting standard, and adjust the brightness of the lighting fixture according to the brightness setting.
[0085] The lighting control unit uses an advanced machine learning algorithm. This algorithm can analyze the ambient light intensity and lighting requirements in real time, and then automatically adjust the brightness of the lamps to achieve the best lighting effect. This intelligent adjustment not only improves the comfort and practicality of lighting, but also significantly improves energy efficiency and achieves the goal of energy conservation and emission reduction.
[0086] Specifically, the light intensity detector continuously monitors the intensity of ambient light and feeds this data back to the lighting control module, which uses a machine learning algorithm to intelligently calculate the most appropriate brightness setting for the current environment based on the light intensity data and preset lighting standards. The lighting control module then automatically adjusts the brightness of the lighting fixtures to ensure uniform, comfortable and energy-saving lighting effects on site.
[0087] Specifically, in some embodiments, the ventilation monitoring unit includes a CO / VI detector, a wind speed and direction detector, a fan and a ventilation control module. The CO / VI detector is installed on the side wall of the highway tunnel to detect the carbon monoxide CO concentration and visibility VI. The wind speed and direction detector is used to detect the wind speed and wind direction in the highway tunnel. The fan is used to increase the gas pressure in the highway tunnel and discharge the gas. The ventilation control module is used to control the operating state of the fan according to the monitored carbon monoxide CO concentration, visibility VI and ventilation demand.
[0088] The working principle of the ventilation monitoring unit is: the environmental data is collected in real time through the CO / VI detector and the wind speed and direction detector. The ventilation control module determines the current air quality and ventilation demand, and adjusts the operating status of the fan according to the ventilation demand, such as starting, stopping or adjusting the wind speed, to ensure that the on-site air quality is maintained at the best state.
[0089] Specifically, in some embodiments, the emergency control unit includes an emergency control module and a communication unit, and the emergency control module is used to perform linkage control with the data monitoring system, control the execution of the final emergency plan, and control the communication unit to perform emergency communication.
[0090] Specifically, in some embodiments, the emergency control module includes an automatic joint control module, a manual joint control module and a delayed start joint control module. The automatic joint control module automatically executes the minimum executable unit in the emergency plan according to the preset control strategy according to the type of emergency event. The manual joint control module manually controls the execution of the minimum executable unit in the emergency plan according to the preset control strategy according to the type of emergency event. The delayed start joint control module delays the execution of the minimum executable unit in the emergency plan according to the preset control strategy according to the type of emergency event.
[0091] Specifically, in some embodiments, the communication unit includes a wired broadcast unit and a wired telephone unit; the wired broadcast unit is used to issue emergency instructions and notifications to relevant personnel at the emergency scene, and to dispatch personnel and vehicles and organize evacuation guidance; the wired telephone unit is used to provide a communication network for emergency communications.
[0092] Specifically, in some embodiments, the wired broadcast unit includes a broadcast server (integrating a network audio server and a speech synthesizer), a broadcast switch, a digital tuner, a broadcast control box, a microphone, a digital audio processor, a power amplifier unit, a fault detector, a field monitor, a monitor speaker, an Ethernet serial port server, a broadcast audio zone controller, a broadcast distribution box and a speaker.
[0093] The broadcast server is used to manage broadcast content and distribute audio signals according to preset playlists or real-time needs.
[0094] The broadcast switch is connected to the broadcast server through a network and is used to distribute the audio signal assigned by the broadcast server to each broadcast area.
[0095] The broadcast control box is used to control the broadcast content and broadcast area.
[0096] The microphone is used to record emergency information. Specifically, the microphone includes a wireless microphone and a broadcast microphone.
[0097] The digital audio processor is responsible for optimizing the audio quality and ensuring the clarity of your broadcasts.
[0098] The power amplification unit (including power controller and power amplifier) is used to amplify the audio signal to drive the speaker to cover a wider area.
[0099] Fault detectors and on-site monitors monitor the operating status of the wired broadcast unit in real time to ensure that the wired broadcast unit can work normally at critical moments. Monitor speakers allow operators to monitor broadcast content to ensure broadcast quality. Ethernet serial port servers enable network management of wired broadcast units, while broadcast audio zone control boxes and broadcast distribution boxes are used to accurately control broadcast content in different areas.
[0100] The speaker is used to play the amplified audio signal.
[0101] The specific working principle of the wired broadcast unit is as follows: Under normal circumstances, the broadcast server will distribute the audio signal to each broadcast area through the broadcast switch according to the preset playlist or real-time demand. When an emergency notice needs to be issued, the operator can enter the emergency information through the broadcast control box, wireless microphone or broadcast microphone. After being optimized by the digital audio processor, this information is amplified by the power amplifier controller and power amplifier, and finally broadcasted through the speaker network. At the same time, the fault detector and the on-site monitor constantly monitor the status of the wired broadcast unit to ensure the accurate transmission of information. Throughout the process, the Ethernet serial port server provides remote monitoring and management functions, making the wired broadcast unit more intelligent and efficient.
[0102] Specifically, in some embodiments, the wired telephone unit includes a soft switch server, a network switch, a telephone console, a recording device, a maintenance gateway workstation, an audio distribution frame, a branching device, a digital telephone and an emergency telephone. The soft switch server is connected to other devices of the wired telephone unit through a network switch to achieve rapid data exchange and processing. The telephone console serves as an operation interface of the wired telephone unit and provides intuitive call management and monitoring functions. The recording device is used to record important call content for subsequent analysis and verification. The maintenance network management workstation is responsible for the daily maintenance and troubleshooting of the system to ensure the continuous and stable operation of the wired telephone unit. The main function of the wired telephone unit is to provide stable and reliable communication in alarm, disaster relief and other special situations to ensure that information can reach the emergency control unit quickly and accurately.
[0103] Compared with conventional wired telephone systems, wired telephone units are characterized by their high scalability and powerful emergency communication capabilities. As the core of the system, the soft switch server not only provides flexible line configuration and expansion space, but also ensures communication stability under extreme conditions. The network switch ensures high-speed data transmission and exchange, providing a strong guarantee for the real-time nature of communication. In terms of equipment connection, when an emergency or special event occurs, the wired telephone unit can quickly start the emergency communication mode. As a dedicated emergency communication device, the emergency telephone can establish contact with the emergency control unit at the first time, report the on-site situation and request support. At the same time, the digital telephone also provides high-quality voice communication functions to ensure the accurate transmission of information at critical moments such as disaster relief.
[0104] The working principle of the above emergency linkage control system is explained by taking fire as an example.
[0105] S1. The system detects fire alarm information through the fire monitoring unit; S2, the prediction module retrieves real-time video and traffic conditions near the fire location to assist emergency personnel in predicting the emergency situation; S3. Emergency personnel determine and confirm the accident situation based on the predicted emergency situation; S4. The minimum executable unit recommended by the auxiliary decision-making module to handle the accident situation is: (1) Turn on all nearby lighting. (2) Turn on nearby fire extinguishers. (3) Control the front and rear traffic lights to prohibit pedestrians and vehicles from entering the scene. (4) Turn on the communication unit to broadcast the accident information.
[0106] S5. Emergency personnel judge and select the minimum executable unit one by one, and implement the minimum executable unit through the emergency control module.
[0107] S6. Save the event process as data for subsequent machine learning to optimize the emergency plan.
[0108] The above-mentioned emergency linkage control system based on big data analysis to assist decision-making in the embodiment of the present invention utilizes big data analysis technology to construct an emergency prediction model, accurately evaluates emergencies, selects emergency plans from a timely updated emergency plan database, and recommends the final emergency plan corresponding to the emergency to emergency personnel, assists in decision-making, quickly and correctly links and controls various systems to perform emergency rescue work, thereby improving the flexibility and real-time response to emergencies.
[0109] The technical features of the above-described embodiments may be arbitrarily combined. To make the description concise, not all possible combinations of the technical features in the above-described embodiments are described. However, as long as there is no contradiction in the combination of these technical features, they should be considered to be within the scope of this specification.
[0110] The above-mentioned embodiments only express several implementation methods of the present invention, and the descriptions thereof are relatively specific and detailed, but they cannot be understood as limiting the scope of the invention patent. It should be pointed out that, for ordinary technicians in this field, several variations and improvements can be made without departing from the concept of the present invention, and these all belong to the protection scope of the present invention. Therefore, the protection scope of the patent of the present invention shall be subject to the attached claims.
Claims
1. A method for managing emergency response plans for emergencies, characterized in that: The following steps are involved: Data acquisition steps: obtain historical emergency on-site monitoring data and its corresponding emergency response plan; Data processing steps: structure the emergency plan, decompose it into multiple minimum executable units with a clear execution order, divide the emergency plans into different levels according to the type, severity and impact of the emergency, and form an emergency plan database; Update steps: Every time an emergency occurs, the on-site monitoring data of the emergency, the final emergency plan implemented, and the actual rescue decision-making data are recorded. The on-site monitoring data of the emergency and the actual rescue decision-making data are learned through machine learning algorithms to update and optimize the emergency plan database.
2. The method for managing emergency plans for emergencies according to claim 1, characterized in that: In the data processing step, the emergency plans are divided into four categories according to the types of emergencies: fire, earthquake, chemical leakage, and traffic accident.
3. The method for managing emergency plans for emergencies according to claim 1, characterized in that: In the data processing step, emergency plans are divided into four levels according to the severity and scope of impact of the emergency. The first-level emergency plan corresponds to the greatest severity and scope of impact of the emergency, and the fourth-level emergency plan corresponds to the smallest severity and scope of impact of the emergency. The activation conditions and response procedures of emergency plans at all levels are clarified to ensure that emergency plans of corresponding levels can be quickly activated in emergency situations.
4. An emergency linkage control method based on big data analysis and decision-making assistance, characterized in that: The following steps are involved: Data acquisition steps: obtain historical emergency on-site monitoring data and its corresponding emergency response plan and emergency on-site real-time monitoring data; Data processing steps: structure the emergency plan, decompose it into multiple minimum executable units with a clear execution order, establish the relationship between the minimum executable units, and divide it into different scenarios and different levels of emergency plans according to the type, severity and impact scope of the emergency to form an emergency plan database; divide the historical emergency site monitoring data into training sets and test sets; Prediction model construction step: constructing an emergency prediction model with emergency on-site monitoring data as input and emergency accident characteristics as output, training the emergency prediction model through a training set, and verifying the trained emergency prediction model through a test set, wherein the emergency accident characteristics include emergency time, emergency location, emergency type and emergency level; Prediction step: input the real-time monitoring data of the emergency scene into the emergency prediction model to predict the accident characteristics of the emergency; Decision-making steps: According to the predicted accident characteristics of the emergency, search the emergency plan database for the emergency plan that matches the accident characteristics of the emergency, and take the emergency plan that best matches as the final emergency plan; Emergency steps: Control and execute the final emergency plan; Update steps: Every time an emergency occurs, the on-site monitoring data of the emergency, the final emergency plan implemented, and the actual rescue decision-making data are recorded. The on-site monitoring data of the emergency and the actual rescue decision-making data are learned through machine learning algorithms to update and optimize the emergency plan database.
5. The emergency linkage control method based on big data analysis and auxiliary decision-making as claimed in claim 4 is characterized in that: In the emergency step, when controlling the execution of the final emergency plan, the emergency plan is executed according to the preset control strategy based on the type of emergency event, and the methods of controlling the execution of the emergency plan include automatic joint control, manual joint control, and delayed start joint control; the automatic joint control is to automatically execute the minimum executable unit in the emergency plan according to the preset control strategy based on the type of emergency event; the manual joint control is to manually control the execution of the minimum executable unit in the emergency plan according to the preset control strategy based on the type of emergency event; the delayed start joint control is to delay the execution of the minimum executable unit in the emergency plan according to the preset control strategy based on the type of emergency event.
6. An emergency linkage control system based on big data analysis and auxiliary decision-making, used to implement the emergency linkage control method based on big data analysis and auxiliary decision-making as claimed in claim 4 or 5, characterized in that: include: Data acquisition module, used to obtain historical emergency on-site monitoring data and its corresponding emergency response plan; Data monitoring system, used to monitor the on-site environmental data, traffic data and facility working status data of emergencies in real time; The data processing module is used to perform structured processing on the emergency plan, decompose the emergency plan into multiple minimum executable units with a clear execution order, establish the association between the minimum executable units, and divide the emergency plans into different scenarios and different levels according to the type, severity and impact scope of the emergency, so as to form an emergency plan database; divide the historical emergency on-site monitoring data into training sets and test sets; The prediction model building module uses the on-site monitoring data of emergencies as input and the accident characteristics of emergencies as output to build an emergency prediction model; The training and verification module is used to train the emergency prediction model through the training set and verify the trained emergency prediction model through the test set; The prediction module inputs the real-time monitoring data of the emergency scene into the emergency prediction model to predict the accident characteristics of the emergency; The auxiliary decision-making module searches for an emergency plan that matches the characteristics of the predicted emergency event from the emergency plan database, and outputs the most matching emergency plan as the final emergency plan; The emergency control unit is linked with the data monitoring system to control the execution of the final emergency plan; The update module records the on-site monitoring data of the emergency, the final emergency plan implemented, and the actual rescue decision-making data every time an emergency occurs. It also uses machine learning algorithms to learn the on-site monitoring data of the emergency and the actual rescue decision-making data, and updates and optimizes the emergency plan database.
7. The emergency linkage control system based on big data analysis and auxiliary decision-making as claimed in claim 6, characterized in that: The data monitoring system includes any one or a combination of a fire monitoring unit, a video monitoring unit, a traffic monitoring unit, a lighting monitoring unit and a ventilation monitoring unit.
8. The emergency linkage control system based on big data analysis and auxiliary decision-making as claimed in claim 7, characterized in that: The fire monitoring unit includes: a flame detector installed on the top or side wall of a highway tunnel to detect flames in the highway tunnel; a temperature detector installed on the top or side wall of a highway tunnel to detect the temperature in the highway tunnel; a smoke detector installed on the top or side wall of a highway tunnel to detect the smoke concentration in the highway tunnel; a fire alarm control module to determine whether it is necessary to issue an alarm or start a fire extinguishing procedure according to the signals detected by the flame detector, the temperature detector and the smoke detector and preset conditions; a control panel connected between the fire alarm control module and the gas fire extinguishing system, and when the fire alarm control module determines that the fire extinguishing procedure needs to be started, the control panel activates the gas fire extinguishing system to enable the gas fire extinguishing system to work and extinguish the fire; an alarm module to send an alarm signal when the fire alarm control module determines that an alarm needs to be issued; a fire graphic workstation connected to the fire alarm control module to display fire information in graphics; The video monitoring unit includes: a network camera for acquiring video images in the highway tunnel; a network hard disk recorder for recording and storing video data; a video management server for managing and controlling video streams and automatically switching monitoring images, and the video management server is linked with other monitoring units in the data monitoring system; a display module connected to the video management server for displaying video images; The traffic monitoring unit includes: a vehicle detector for real-time monitoring of vehicle flow, vehicle speed, and vehicle type in a highway tunnel; an overheight detector for detecting whether there is an overheight vehicle; a video analysis device for converting information detected by the vehicle detector and the overheight detector into traffic intelligence information, wherein the traffic intelligence information includes road condition information, guidance information, and speed limit prompt information; a display device for displaying traffic intelligence information; and an indication device for indicating lane usage and tunnel traffic status. The lighting monitoring unit includes: a light intensity detector for detecting the light intensity of the lighting fixture; a lighting control module for obtaining the brightness setting in the current environment through a machine learning algorithm according to the detected light intensity and a preset lighting standard, and adjusting the brightness of the lighting fixture according to the brightness setting; The ventilation monitoring unit includes: a CO / VI detector installed on the side wall of a highway tunnel for detecting the carbon monoxide (CO) concentration and the visibility (VI); a wind speed and direction detector for detecting the wind speed and direction in the highway tunnel; a fan for increasing the gas pressure in the highway tunnel and discharging the gas; and a ventilation control module for controlling the operating state of the fan according to the monitored carbon monoxide (CO) concentration, visibility (VI) and ventilation demand.
9. The emergency linkage control system based on big data analysis and auxiliary decision-making as claimed in claim 6, characterized in that: The emergency control unit includes an emergency control module and a communication unit. The emergency control module is used to perform linkage control with the data monitoring system, control the execution of the final emergency plan, and control the communication unit to perform emergency communication.
10. The emergency linkage control system based on big data analysis and auxiliary decision-making as claimed in claim 9, characterized in that: The emergency control module comprises: The automatic joint control module automatically executes the smallest executable unit in the emergency plan according to the preset control strategy based on the type of emergency event; The manual joint control module manually controls the execution of the minimum executable unit in the emergency plan according to the preset control strategy based on the type of emergency event; Delayed start joint control module, delay execution of the minimum executable unit in the emergency plan according to the preset control strategy based on the type of emergency event; The communication unit includes a wired broadcast unit and a wired telephone unit; the wired broadcast unit is used to issue emergency instructions and notifications to relevant personnel at the emergency scene, and to dispatch personnel and vehicles and organize evacuation guidance; the wired telephone unit is used to provide a communication network for emergency communications.
Citation Information
Patent Citations
Rapid response and decision support platform for important emergent event based on distributed cooperation
CN106886884A
Highway tunnel operation management and control system
CN112885100A
Method for generating emergency rescue scheme for emergencies
CN113222361A
High-speed intelligent fire alarm rescue system
CN115762020A
Cited By
Road protection multi-scene coupling simulation method and system based on digital twinning
CN120277972A
A multi-scenario coupling simulation method and system for highway protection based on digital twins
CN120277972B
Adaptive generation method and system for emergency strategy of highway tunnel emergencies