10kV single-phase grounding double-end fusion line selection method for transformer substation
By automatically building the substation-bus-loop model and calculating the grounding probability, the double-end fusion sorting generates a pull-out control area sequence, solving the problem of low accuracy of the existing 10kV single-phase grounding wire selection device, improving the accuracy of line selection and reducing the accuracy of line selection Cable fire risk.
Patent Information
- Application Number
- CN202410928649.3
- Authority / Receiving Office
- CN · China
- Patent Type
- Applications(China)
- Current Assignee / Owner
- Filing Date
- 2024-07-11
- Publication Date
- 2024-11-26
Smart Images

Figure SMS_1 
Figure SMS_3 
Figure SMS_4
Abstract
Description
Technical Field
[0001] The present invention relates to the field of phase-to-ground line selection, and in particular to a 10kV single-phase-to-ground double-terminal fusion line selection method for a substation. Background Art
[0002] At present, the proportion of 10kV cable outlets in major urban power grids has increased year by year, mostly exceeding 80%, and the single-phase grounding capacitance current has increased year by year. Since on-site operation and maintenance cannot keep up with the rapid changes in the power grid structure, most arc suppression coils are actually in an under-compensated state. Although some stations are currently deployed with various line selection devices based on transient or steady-state line selection principles, practice has shown that the line selection accuracy is less than 40%, and most line selection devices do not push line selection results when they are grounded. When grounding occurs, if the station-side line selection device does not push results, the dispatcher will be in a blind and disorderly line pulling state when facing grounding. Under the dual pressure of the time constraint that the dispatching regulations require the line pulling and grounding time to be controlled within 2 hours and the safety constraint of avoiding the cable grounding time being too long and causing continuous arcing to cause cable trench fire, the dispatcher mostly adopts remote line pulling operations in sequence for verification search. This process takes a long time, which may cause the grounding arc to continue to burn, causing the single-phase grounding fault to expand into a phase-to-phase fault or a cable trench fire accident.
[0003] However, the current line selection device has a low line selection accuracy. The reason is that on the one hand, according to the existing substation, the entire 10kV bus needs to be shut down according to the line selection device to install zero-sequence CT or the capacitor current needs to be tested every year to update the internal model parameters of the line selection device. There are many important users in the urban power grid and the power outage window period is difficult, resulting in the internal models of most line selection devices being unable to adapt to the current status of the power grid structure. On the other hand, after analyzing the voltage and current data at the time of grounding for many years, it was found that a considerable proportion of the grounding process lasted for 3-10 seconds. The instability of electrical quantities during the grounding process may also be an important reason for the low push accuracy of the station-side line selection device. In addition, in the way of generating the association model of substation-bus-loop information at the master station, the traditional way is to rely on the method specialist and other personnel to manually issue documents in advance to determine the basic sequence model of the line pulling. The workload is large and it is difficult to adapt to the real-time changes in the power grid topology, which poses a hidden danger to the accuracy of the software's basic model of the line pulling sequence.
[0004] Therefore, in the face of the problem of low line selection accuracy of current line selection devices, developing a line selection method that can improve the line selection accuracy is a technical problem that needs to be solved urgently. Summary of the invention
[0005] The purpose of the present invention is to provide a 10kV single-phase grounded double-end fusion line selection method for a substation to solve the problem of low accuracy of the existing station-end line selection.
[0006] In order to solve the above technical problems, the present invention provides a 10kV single-phase grounded double-terminal fusion line selection method for a substation, comprising the steps of:
[0007] S1: Automatically build substation-busbar-loop model;
[0008] S2: Determine whether there are multiple buses in the same station that meet the grounding phenomenon at similar times based on the bus voltage. If so, merge the substation-single bus-loop model into a substation-multiple buses-loop model, and then calculate the grounding probability of each main station loop in the substation-multiple buses-loop model based on the voltage and current data in the real-time database at the time of grounding;
[0009] S3: sort the loops of each master station in descending order according to the probability of grounding;
[0010] S4: Compare the highest ranked master station loop with the station end line selection loop selected by the station end line selection. If the highest ranked master station loop is consistent with the station end line selection loop, each master station loop is made to generate a line pulling control area sequence according to the sorting result of step S3; otherwise, the station end line selection loop is arranged before the loop with the highest probability ranking, and the remaining loops are arranged in sequence after the station end line selection loop according to the sorting result of step S3 to generate a line pulling control area sequence.
[0011] Furthermore, the step S1 specifically includes:
[0012] S11: Obtaining load outgoing line information from a parameter library in a power grid dispatching automation system to form a list containing only load outgoing lines;
[0013] S12: Using the load outgoing switch device number as the matching code, the connection relationship table and the topology connection table in the query parameter library are associated, and the corresponding busbar device and name are progressively searched to form a busbar-loop model; using the load outgoing switch device number as the matching code, the measurement parameter table is queried to obtain the three-phase current telemetry code of each load outgoing switch and the three-phase voltage telemetry code of the busbar; using the load outgoing device number to query the telemetering parameter table, and search for the line grounding telemetering code of each loop;
[0014] S13: Using the parameter table of the bus as an index, searching for the name of the substation to which the bus belongs, traversing the substation database and topology of the entire network, and forming a substation-single bus-loop model.
[0015] Furthermore, when multiple bus voltages at the same station at similar times meet any two of the following conditions, it is determined that the bus voltage meets the grounding phenomenon:
[0016] Condition 1: When the zero-sequence secondary voltage reaches 2kV;
[0017] Condition 2: When the amplitude of any phase voltage (Ua / Ub / Uc) of the bus voltage drops below 2kV;
[0018] Condition 3: When the amplitude of any phase voltage (Ua / Ub / Uc) of the bus voltage rises above 9kV;
[0019] Condition 4: When the anti-shake time exceeds the threshold.
[0020] Furthermore, the grounding probability of each loop in the substation-bus-loop model is calculated based on the voltage and current data in the real-time database at the time of grounding, including:
[0021] S21: When it is determined that the bus voltage meets the grounding phenomenon, the timing is started and recorded as time t0, and then the current values of all loops of the grounded phase in the real-time database are collected in real time;
[0022] S22: Calculate the average current of each loop collection point after grounding and waiting for the anti-shake time to pass:
[0023]
[0024] Among them, I i2 is the average current of point i in loop after grounding and waiting for the anti-shake time to pass, I tn is the current value of the loop i collection point at time tn; N is the number of current values collected by the loop i collection point after grounding and waiting for the anti-shake time to pass;
[0025] S23: Calculate the actual current mutation of each circuit before and after grounding:
[0026] △I i =I i2 -I i1
[0027] Among them, △I i is the actual sudden change of current in loop i before and after grounding; I i1 is the current value of the sampling point i of the loop before grounding;
[0028] S23: Calculate the statistical value of the sudden change of all loop grounding phases ∑|△I i |;
[0029] S24: Calculate the grounding probability of each circuit
[0030] Furthermore, the I tn The current is collected every 10 seconds. The average current of each loop collection point after the grounding and anti-shake time is calculated as follows:
[0031]
[0032] Among them, I t10 I is the current value of the sampling point of loop i at the 10th second after grounding and after the anti-shake time has passed, t20I is the current value of the loop i sampling point at the 20th second after grounding and avoiding the anti-shake time. t30 It is the current value of the sampling point of loop i at 30 seconds after grounding and avoiding the anti-shake time.
[0033] Furthermore, the master station loops with a grounding probability greater than a set probability are screened out to generate a priority line control area sequence, and the master station loops with a grounding probability greater than a set probability are used to generate a batch line control area sequence.
[0034] Furthermore, it also includes step S5: pushing the generated road control area sequence to the corresponding dispatcher, and issuing a grounding alarm. The dispatcher confirms whether to start the road grounding after confirming the road control area sequence, on-site information, dispatching information and ground adjustment information.
[0035] The beneficial effects of the present invention are:
[0036] 1. This application does not completely abandon the line selection results of the station-side line selection device. Instead, it calculates the grounding probability of each circuit based on the real-time library voltage and current data during grounding, and then integrates the line selection probabilities of the station and the main station for game sorting to obtain the final line pulling sequence for execution, which can ensure the accuracy of line selection.
[0037] 2. By automatically constructing the substation-busbar-loop model and obtaining the current and voltage data in the model, and then calculating the line control area sequence, it is no longer necessary for the dispatching department to issue a document in advance to determine the line sequence. This application effectively reduces the workload of model maintenance.
[0038] 3. This application detects whether there are multiple bus grounding phenomena at similar times in the same station, and automatically merges multiple bus-loop models based on the basic model of a single bus-loop to adapt to the situation where multiple 10kV busbars are in parallel during main transformer maintenance, avoiding large-area topological searches when calculating probabilities, reducing memory usage and time consumption. DETAILED DESCRIPTION
[0039] A 10kV single-phase grounded double-terminal fusion line selection method for a substation comprises the following steps:
[0040] S1: Automatically build substation-single bus-loop model;
[0041] S2: Determine whether the grounding phenomenon is met at similar times in the same station based on the bus voltage. If so, merge the buses in the substation-single bus-loop model to form a substation-multiple buses-loop model, and then calculate the grounding probability of each main station loop in the substation-multiple buses-loop model based on the voltage and current data in the real-time database at the time of grounding;
[0042] S3: sort the loops of each master station in descending order according to the probability of grounding;
[0043] S4: Compare the highest ranked master station loop with the station end line selection loop selected by the station end line selection. If the highest ranked master station loop is consistent with the station end line selection loop, each master station loop is made to generate a line pulling control area sequence according to the sorting result of step S3; otherwise, the station end line selection loop is arranged before the loop with the highest probability ranking, and the remaining loops are arranged in sequence after the station end line selection loop according to the sorting result of step S3 to generate a line pulling control area sequence.
[0044] The present application does not completely abandon the line selection results of the station-side line selection device, but calculates the grounding probability of each circuit based on the real-time library voltage and current data during grounding, and then integrates the line selection probabilities of the station and the main station for game sorting to obtain the final line pulling sequence for execution, which can ensure the accuracy of line selection.
[0045] According to an embodiment of the present application, step S1 specifically includes:
[0046] S11: Obtain the load outgoing line information from the parameter library in the power grid dispatching automation system to form a list containing only the load outgoing lines; mainly exclude key circuits such as 10kV station transformers, capacitors, reactors, and the low-voltage side of the main transformer;
[0047] S12: Using the load outgoing switch device number as the matching code, the connection relationship table and the topology connection table in the query parameter library are associated, and the corresponding busbar device and name are progressively searched to form a busbar-loop model; using the load outgoing switch device number as the matching code, the measurement parameter table is queried to obtain the three-phase current telemetry code of each load outgoing switch and the three-phase voltage telemetry code of the busbar; using the load outgoing device number to query the telemetering parameter table, and search for the line grounding telemetering code of each loop;
[0048] S13: Using the parameter table of the bus as an index, searching for the name of the substation to which the bus belongs, traversing the substation database and topology of the entire network, and forming a substation-single bus-loop model.
[0049] This embodiment automatically constructs a substation-single bus-loop model, obtains the current and voltage data in the model, and then calculates the line control area sequence. It no longer requires the dispatcher to issue a document in advance to determine the line sequence. This application effectively reduces the workload of model maintenance.
[0050] According to an embodiment of the present application, when there are multiple bus voltages at similar times in the same station that meet any two of the following conditions, it is determined that the bus voltage meets the grounding phenomenon:
[0051] Condition 1: When the zero-sequence secondary voltage reaches 2kV;
[0052] Condition 2: When the amplitude of any phase voltage (Ua / Ub / Uc) of the bus voltage drops below 2kV, the interval [0, 2kV] can be set;
[0053] Condition 3: When the amplitude of any phase voltage (Ua / Ub / Uc) of the bus voltage rises above 9kV, the interval [9kV, +) can be set;
[0054] Condition 4: When the anti-shake time exceeds the threshold.
[0055] By setting the anti-shake time threshold parameter, you can filter out false grounding errors caused by unstable electrical quantities during the grounding process, and avoid frequent pop-ups of the grounding alarm interface.
[0056] According to an embodiment of the present application, calculating the grounding probability of each loop in the substation-bus-loop model according to the voltage and current data in the real-time database at the time of grounding includes:
[0057] S21: When it is determined that the voltages of multiple buses at similar times in the same station meet the grounding phenomenon, the timing is started and recorded as time t0, and then the current values of all loops of the grounded phase in the real-time database are collected in real time;
[0058] S22: Calculate the average current of each loop collection point after grounding and waiting for the anti-shake time to pass:
[0059]
[0060] Among them, I i2 is the average current value of point i after grounding and avoiding the anti-shake time loop, I tn is the current value of the loop i collection point at time tn; N is the number of current values collected by the loop i collection point after grounding and waiting for the anti-shake time to pass;
[0061] S23: Calculate the actual current mutation of each circuit before and after grounding:
[0062] △I i =I i2 -I i1
[0063] Among them, △I i I is the actual sudden change of current in loop i before and after grounding and after avoiding the anti-shake time; i1 is the current value of the sampling point i of the loop before grounding;
[0064] S23: Calculate the statistical value of the sudden change of all loop grounding phases ∑|△I i |;
[0065] S24: Calculate the grounding probability of each circuit
[0066] According to one embodiment of the present application, the I tn The current is collected every 10 seconds. The average current of each loop collection point after the grounding and anti-shake time is calculated as follows:
[0067]
[0068] Among them, I t10 I is the current value of the sampling point of loop i at the 10th second after grounding and after the anti-shake time has passed, t20 I is the current value of the loop i sampling point at the 20th second after grounding and avoiding the anti-shake time. t30 It is the current value of the sampling point of loop i at 30 seconds after grounding and avoiding the anti-shake time.
[0069] This implementation starts collecting data at the 10th second after grounding and after the anti-shake time has passed, and collects data every 10 seconds, which can prevent unstable electrical quantities during the grounding process from affecting the calculation results and ensure the correctness of the calculation results.
[0070] According to one embodiment of the present application, the master station loops with a grounding probability greater than a set probability are screened out to generate a priority line pulling control area sequence, and the master station loops with a grounding probability greater than a set probability are used to generate a batch line pulling control area sequence. The loops with higher probabilities form a priority line pulling control area, where the probability of the loops being grounded is high, highlighting the accuracy of line selection, especially the grounded loop ranked first, and automatic line pulling control is implemented in this area. The remaining loops enter the batch line pulling control area, which is mainly used as a bottom-line measure when the priority line pulling control area is not pulled accurately, to achieve batch rapid automatic line pulling and speed up the efficiency of the line pulling process.
[0071] According to one embodiment of the present application, step S5 is also included: pushing the generated line pulling control area sequence to the corresponding dispatcher, and issuing a grounding alarm. The dispatcher confirms whether to start automatic line pulling and grounding after confirming the line pulling control area sequence, on-site information, dispatching information and grounding information.
[0072] Finally, it should be noted that the above embodiments are only used to illustrate the technical solution of the present invention rather than to limit it. Although the present invention has been described in detail with reference to the preferred embodiments, those skilled in the art should understand that the technical solution of the present invention can be modified or replaced by equivalents without departing from the purpose and scope of the technical solution of the present invention, which should be included in the scope of the claims of the present invention.
Claims
1. A 10kV single-phase grounded double-terminal fusion line selection method for a substation, characterized in that: Includes steps: S1: Automatically build substation-single bus-loop model; S2: Determine whether there are multiple buses in the same station that meet the grounding phenomenon at similar times based on the bus voltage. If so, merge the substation-single bus-loop model into a substation-multiple buses-loop model, and then calculate the grounding probability of each outgoing loop in the substation-multiple buses-loop model based on the voltage and current data in the real-time database at the time of grounding; S3: sorting the loops of each master station in descending order according to the grounding probability; S4: Compare the highest ranked master station loop with the station end line selection loop selected by the station end line selection. If the highest ranked master station loop is consistent with the station end line selection loop, each master station loop is made to generate a line pulling control area sequence according to the sorting result of step S3; otherwise, the station end line selection loop is arranged before the loop with the highest probability ranking, and the remaining loops are arranged in sequence after the station end line selection loop according to the sorting result of step S3 to generate a line pulling control area sequence.
2. The substation 10kV single-phase grounded double-terminal fusion line selection method according to claim 1 is characterized in that: The step S1 specifically includes: S11: Obtaining load outgoing line information from a parameter library in a power grid dispatching automation system to form a list containing only load outgoing lines; S12: Using the load outgoing switch device number as the matching code, the connection relationship table and the topology connection table in the query parameter library are associated, and the corresponding busbar device and name are progressively searched to form a busbar-loop model; using the load outgoing switch device number as the matching code, the measurement parameter table is queried to obtain the three-phase current telemetry code of each load outgoing switch and the three-phase voltage telemetry code of the busbar; using the load outgoing device number to query the telemetering parameter table, and search for the line grounding telemetering code of each loop; S13: Using the parameter table of the bus as an index, searching for the name of the substation to which the bus belongs, traversing the substation database and topology of the entire network, and forming a substation-single bus-loop model.
3. The 10kV single-phase grounded double-terminal fusion line selection method for substation according to claim 2 is characterized in that: If there are multiple bus voltages at the same station at similar times that meet any two of the following conditions, the bus voltage is considered to be grounded: Condition 1: When the zero-sequence secondary voltage reaches 2kV; Condition 2: When the voltage of any phase of the bus voltage drops below 2kV; Condition 3: When the voltage amplitude of any phase of the bus voltage rises to above 9kV; Condition 4: When the anti-shake time exceeds the threshold.
4. The 10kV single-phase grounded double-terminal fusion line selection method for substation according to claim 3 is characterized in that: The grounding probability of each loop in the substation-multiple bus-loop model is calculated based on the voltage and current data in the real-time database when the grounding occurs, including: S21: When it is determined that the bus voltage meets the grounding phenomenon, the timing starts and is recorded as time t0, and then the current values of multiple bus-loops in the same station that meet the grounding conditions in the real-time database are collected in real time; S22: After the grounding is calculated and the anti-shake time is over, the average current value of each loop collection point is calculated: Among them, I i2 is the average current of point i in the loop after grounding, I tn is the current value of the loop i collection point at time tn; N is the number of current values collected by the loop i collection point after grounding; S23: Calculate the actual current mutation of each circuit before and after grounding: △I i =I i2 -I i1 Among them, △I i is the actual sudden change of current in loop i before and after grounding; I i1 is the current value of the sampling point i of the loop before grounding; S23: Calculate the statistical value of the sudden change of all loop grounding phases ∑|△I i |; S24: Calculate the grounding probability of each circuit 5. The substation 10kV single-phase grounded double-terminal fusion line selection method according to claim 4 is characterized in that: I tn The data is collected every 10 seconds. After the calculation is grounded and the anti-shake time is avoided, the average current value of each loop collection point is: Among them, I t10 I is the current value of the sampling point of loop i at the 10th second after grounding and after the anti-shake time has passed, t20 I is the current value of the loop i sampling point at the 20th second after grounding and after the anti-shake time has passed. t30 It is the current value of the sampling point of loop i at 30 seconds after grounding and avoiding the anti-shake time.
6. The 10kV single-phase grounded double-terminal fusion line selection method for a substation according to any one of claims 1 to 5, characterized in that: The master station loops with a grounding probability greater than the set probability are screened out to generate a priority line control area sequence, and the master station loops with a grounding probability greater than the set probability are used to generate a batch line control area sequence.
7. The substation 10kV single-phase grounded double-terminal fusion line selection method according to claim 1 is characterized in that: Also includes the steps: S5: Push the generated line control area sequence to the corresponding dispatcher, and issue a grounding alarm. The dispatcher will confirm whether to start the line grounding after combining the line control area sequence, on-site information, dispatching information and grounding information.