Main and temporary combined foundation pit supporting process

Through the main-market bonding foundation pit support technology, the construction quality and construction period of foundation pit support in small spaces are solved, and the stability of the anchor bolt composite is improved and the construction efficiency is improved, and resource waste and environmental pollution are avoided.

CN119041445APending Publication Date: 2024-11-29CHINA CHEM CONSTR (HAINAN) CO LTD
View PDF 0 Cites 0 Cited by

Patent Information

Application Number
CN202411162620.5
Authority / Receiving Office
CN · China
Patent Type
Applications(China)
Current Assignee / Owner
Filing Date
2024-08-23
Publication Date
2024-11-29

AI Technical Summary

Technical Problem

The existing foundation pit support methods are difficult to ensure quality and construction period when constructed in a small space, and the piles and steel beams after the foundation pit are excavated cannot be reused, resulting in waste of resources and high requirements for the surrounding environment.

Method used

Adopting the main-market bonding foundation pit support process, through detailed construction preparation and layered excavation, anchor bolt formation, steel wire hanging and concrete spraying, anchor bolt composites are formed, the construction process is simplified, and the site occupation and environment are reduced. Contaminate and shorten the concrete settling time by adding a quick-setting agent.

Benefits of technology

It significantly improves slope stability, simplifies construction technology, reduces costs, reduces site restrictions and environmental pollution, and improves construction efficiency.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN119041445A_ABST
    Figure CN119041445A_ABST
Patent Text Reader

Abstract

The invention discloses a main and temporary combined foundation pit supporting process, and relates to the technical field of foundation pit supporting construction, the main and temporary combined foundation pit supporting process comprises the steps of S1, construction preparation work, S2, elevation determination, S3, foundation pit excavation, S4, anchor bolt hole forming, S5, reinforcement mesh hanging, S6, concrete spraying and S7, maintenance, and an anchor bolt composite body formed through the scheme can remarkably improve the overall stability of a side slope; the construction process is simple and convenient; the construction does not need to occupy a site independently, the limitation on the requirement of a construction site is reduced, the construction cost is low, meanwhile, the pollution to the surrounding environment of the construction site is reduced, the time from initial setting to final setting of concrete is controlled by adding an accelerator during spraying operation, the solidification time of a support is greatly shortened, and the efficiency of support construction is improved.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The invention relates to the technical field of foundation pit support construction, in particular to a primary and temporary combined foundation pit support process. Background Art

[0002] The current foundation pit support method is to directly drive slope protection piles (reinforced concrete cast-in-place piles) at the edge before foundation pit excavation, and then set steel beams at certain intervals as the foundation pit is excavated. After the foundation pit is backfilled, the piles and steel beams cannot be reused, resulting in waste. When other methods are used in the prior art for construction, the requirements for the surrounding construction environment and site are relatively high, generally requiring a relatively open environment around. Therefore, working in a smaller space and ensuring construction quality and construction period have become problems that need to be solved urgently in the prior art. For this reason, this solution proposes a foundation pit support process that can be applied to working in a smaller space. Summary of the invention

[0003] In view of the deficiencies in the prior art, the present invention provides a primary-temporary combined foundation pit support process, which solves the problems raised in the background technology.

[0004] To achieve the above objectives, the present invention is implemented through the following technical solutions: a primary and temporary combined foundation pit support process, the steps of which are as follows:

[0005] S1: Construction preparation work. Before excavation, conduct a comprehensive survey of obstacles on the ground and underground of the site, further determine whether there are underground pipelines in and around the site, determine the location and direction on site, and protect them during the excavation process. According to the foundation pit support plan, determine the foundation pit excavation line, and make arrangements for the passages of excavation machinery and earth-moving vehicles, the excavation sequence and the location of the earth pile. It is strictly forbidden to pile the excavated soil around the foundation pit, and use lime to lay out the edge line;

[0006] S2: Determine the elevation, use a level and a benchmark to determine the elevation, and strictly control the excavation depth as the excavation progresses. Set up guardrails 0.50m outside the top of the foundation pit slope, with a height of not less than 1.20m. When transporting earthwork outward, care should be taken to prevent damage to drainage ditches, guardrails and other facilities; during the construction and operation of the foundation pit support, the overload on the top of the slope is not allowed to exceed the design standard. According to the site and surrounding road conditions, set up a ramp for transporting earthwork out of the foundation pit, with a width of 8m and a slope of 1:8. Both sides use 1:1.5 slope protection. The ramp needs to be compacted and poured with 200mm thick C20 concrete on the surface;

[0007] S3: Excavate the foundation pit. The excavation depth should be considered in combination with the anchor bolt position. The excavation depth is 60-70 cm below the anchor bolt hole position, and the excavation width is 15-20 cm. The earthwork is excavated in five layers, with the first layer being 3.5-4.0 meters, and each subsequent layer being 1.0-1.3 meters; and the excavation of the next layer of earthwork is carried out after the anchor bolts and shotcrete of the upper working surface are completed;

[0008] S4: Anchor bolt holes are drilled at the corresponding positions of the anchor bolts, with a diameter of 100 mm to 150 mm. A 15 cm hook is set at the outer end of the main reinforcement of the anchor bolt. A central bracket is welded to the main reinforcement every 2 m. The main reinforcement and the grouting pipe are placed in the hole together, and pure cement slurry with a water-cement ratio of 0.5 is injected into the hole;

[0009] S5: Hang the steel mesh, overlap and tie the steel meshes, the overlap length of the steel meshes on the upper and lower sections of the slope should be greater than 300mm, and the steel meshes are welded to the hooks at the outer ends of the anchor bolts, and the gap between the steel meshes and the slope surface is greater than 30mm;

[0010] S6: Sprayed concrete, the concrete components include cement, water, sand and gravel, and the mass ratio of cement: water: stone: sand: gravel is 1: 0.35 ~ 0.4: 1.1 ~ 1.2: 2.7 ~ 2.8; 80mm thick concrete is sprayed in the slope section. Considering the need to avoid rain erosion on the top of the foundation pit in the later stage and to ensure safety and reliability, the top of the foundation pit is leveled and the sprayed concrete is sprayed to the red line enclosure edge. The strength grade of the sprayed concrete is C20. The spraying operation should be carried out in sections, and the spraying operation in the same section should be from top to bottom;

[0011] S7: Curing: the thickness of the sprayed layer should be uniform. After the sprayed concrete has finally set, it should be sprayed with water for curing. The curing period is 10 days. When the temperature is below 5℃, water spraying is not allowed.

[0012] Preferably, the foundation pit excavation in S1 is sloped in proportion to the requirements of the drawings on each side, the sidewalk needs to be safely protected, the walkway width is not less than 1000mm, the distance between the vertical poles is not more than 1200mm, the slope of the sidewalk is the same as the slope of the foundation pit, an anti-slip wooden strip with a cross-section of not less than 20×30mm should be set on the scaffolding every 250mm to 300mm, skirting boards should be set on both sides of the ramp, and guardrails and sidewalks should be protected.

[0013] Preferably, before spraying concrete in S6, the mechanical equipment should be inspected and tested, the air compressor pressure should be not less than 0.5MPa, the air volume should be not less than 9m3 / min to ensure the quality of concrete, the water pressure should be not less than 0.2MPa, and when spraying concrete, the nozzle should be kept vertical to the sprayed surface, and the distance should be 0.6-1.0m.

[0014] Preferably, before fully hanging the steel mesh in S6, the base layer must be manually sloped, leveled, and compacted, and the concrete surface layer must be turned over the top of the foundation pit and extended to the red line edge to form a slope protection.

[0015] Preferably, in S6, the back of the steel bars should be sprayed first and then the front of the steel bars at the cross-lined parts to prevent gaps from appearing behind the steel bars. A 45° slope should be made at the joints between layers to facilitate firm concrete lap joints.

[0016] Preferably, in the spraying operation in S6, an expansion joint with a width of 2 to 3 cm is set horizontally at an interval of 15 m along the slope direction, and the joint is filled with asphalt hemp tendons.

[0017] Preferably, the hole in S4 has a diameter of 150-200 mm, and the grouting pipe is 0.5 m away from the bottom of the hole, and crushed stone with a particle size of 5-15 mm is poured into the hole.

[0018] Preferably, during the spraying operation in S6, the time from initial setting to final setting of concrete is controlled to be 5-9 minutes by adding an accelerator, and the accelerator comprises the following raw material components in parts by weight: 30-40% soda ash, 10-20% bauxite, 20-30% sodium chlorate, and the balance is quicklime.

[0019] Preferably, during excavation in S3, the pile load within 20m around the foundation pit (measured from the top of the foundation pit slope outward) shall not be greater than 10kN / m2, the total construction load (including the pile load) shall not be greater than 20kN / m2, no soil shall be stored within 10m around the foundation pit, no construction materials shall be piled within 2m of the trench edge, and no transportation vehicles or machinery shall be moved along the edge of the foundation pit.

[0020] The present invention provides a primary and temporary combined foundation pit support process, which has the following beneficial effects:

[0021] This main and temporary combined foundation pit support process can significantly improve the overall stability of the slope through the anchor bolt complex formed by this scheme; its construction process is simple; the construction does not need to occupy a separate site, reducing the restrictions on the construction site requirements, low construction costs, and at the same time reducing pollution to the environment around the construction site; and during the spraying operation, the initial setting to final setting time of concrete is controlled by adding an accelerator, which greatly shortens the solidification time of the support and improves the efficiency of the support construction. BRIEF DESCRIPTION OF THE DRAWINGS

[0022] Figure 1 It is a schematic diagram of the process of the present invention. DETAILED DESCRIPTION

[0023] The following will be combined with the drawings in the embodiments of the present invention to clearly and completely describe the technical solutions in the embodiments of the present invention. Obviously, the described embodiments are only part of the embodiments of the present invention, not all of the embodiments. Based on the embodiments of the present invention, all other embodiments obtained by ordinary technicians in this field without creative work are within the scope of protection of the present invention.

[0024] Embodiment 1:

[0025] A main and temporary combined foundation pit support process, the steps of which are as follows: S1: construction preparation work, before excavation, a comprehensive investigation of obstacles on the ground and underground of the site is carried out, and whether there are underground pipelines in and around the site is further determined, and the position and direction are determined on site, and they are protected during the earth excavation process. According to the foundation pit support plan, the foundation pit excavation line is determined, and the passage layout of the excavation machinery and earth-moving vehicles, the excavation sequence and the arrangement of the soil pile position are well done. It is strictly forbidden to pile the excavated soil around the foundation pit, and the boundary line is laid out with lime; S2: determine the elevation, use a level and a benchmark to determine the elevation, and strictly control the excavation depth as the excavation progresses. A guardrail is set around the top of the pit slope 0.50m away, with a height of not less than 1.20m. When transporting earthwork, care should be taken to prevent damage to drainage ditches, guardrails and other facilities; during the construction and operation of the foundation pit support, the overload on the top of the slope is not allowed to exceed the design standard. According to the site and surrounding road conditions, a ramp for transporting earthwork from the foundation pit is set up with a width of 8m and a slope of 1:8. 1:1.5 slope protection is used on both sides. The ramp needs to be compacted and 200mm thick C20 concrete is poured on the surface; S3: Excavate the foundation pit. The excavation depth should be considered in combination with the position of the anchor bolts. The excavation depth is 70cm below the anchor bolt hole position, and the excavation width is 20cm. The earthwork is excavated in five layers. The first The first layer is 4.0 meters, and the following layers are 1.3 meters; and after completing the anchor bolts and spraying concrete on the upper working surface, the next layer of earthwork is excavated; S4: Anchor bolt holes are drilled at the corresponding positions of the anchor bolts, with a diameter of 150mm. The outer end of the main reinforcement of the anchor bolt is provided with a 15cm hook. The main reinforcement is welded with a central bracket every 2m. The main reinforcement and the grouting pipe are placed in the hole together, and pure cement slurry with a water-cement ratio of 0.5 is injected into the hole; S5: Hang the steel mesh, and the steel mesh sheets are overlapped and tied. The overlap length of the steel mesh on the upper and lower sections of the slope should be greater than 300mm, and the steel mesh sheet is welded to the hook at the outer end of the anchor bolt. The gap between the steel mesh sheet and the slope surface is large. 30mm; S6: sprayed concrete, the concrete components include cement, water, sand and gravel, and the mass ratio of cement: water: stone: sand: gravel is 1:0.4:1.2:2.8; 80mm thick concrete is sprayed in the slope section. Considering the avoidance of rain erosion on the top of the foundation pit in the later stage and ensuring safety and reliability, the top of the foundation pit is flat and the sprayed concrete is sprayed to the red line enclosure edge. The strength grade of the sprayed concrete is C20. The spraying operation should be carried out in sections, and the spraying operation in the same section should be from top to bottom; S7: maintenance, the thickness of the sprayed layer should be uniform, and after the sprayed concrete is finally set, it should be sprayed with water for maintenance. The maintenance period is 10d. When the temperature is below 5℃, water spraying is not allowed;

[0026] The excavation of the foundation pit in S1 is carried out in accordance with the required proportions of the drawings on each side. The pedestrian walkway needs to be protected. The width of the walkway is not less than 1000mm, the distance between the vertical poles is not more than 1200mm, and the slope of the walkway is the same as the slope of the foundation pit. An anti-slip wooden strip with a cross-section of not less than 30mm should be set on the scaffolding board every 300mm. Skirting boards and protective railing pedestrian walkways should be set on both sides of the ramp. Before spraying concrete in S6, the mechanical equipment should be inspected and tested. The air compressor pressure should be not less than 0.5MPa and the air volume should be not less than 9m3 / min to ensure the quality of concrete. The water pressure should be not less than 0.2MPa. When spraying concrete, the nozzle should be kept vertical to the sprayed surface, and the distance should be 1.0m. Before fully hanging the steel mesh in S6, the base layer must be manually sloped, leveled, and compacted. The concrete surface layer should be turned over the top of the foundation pit and extend to the red line edge to form a slope protection. In the S6, the back of the steel bars should be sprayed first and then the front of the steel bars at the cross-lined parts to prevent gaps behind the steel bars. A 45° slope angle should be made at the joints between layers to facilitate the firm overlap of concrete. In the spraying operation in the S6, a 3cm wide expansion joint is set horizontally at an interval of 15m along the slope direction, and the seam is filled with asphalt hemp tendons. The aperture of the hole in the S4 is 200mm, and the grouting pipe is 0.5m away from the bottom of the hole. Crushed stone with a particle size of 15mm is used to be put into the hole. During the spraying operation in the S6, the time from initial setting to final setting of concrete is controlled to 9min by adding an accelerator. The accelerator includes the following raw material components by weight: 40% soda ash, 20% bauxite, 30% sodium chlorate, and the balance is quicklime. During excavation in S3, the pile load within 20m around the foundation pit (measured from the top of the foundation pit slope outward) shall not be greater than 10kN / m2, the total construction load (including the pile load) shall not be greater than 20kN / m2, no soil shall be stored within 10m around the foundation pit, no construction materials shall be piled within 2m of the trench edge, and no transportation tools or machinery shall be moved along the edge of the foundation pit.

[0027] Embodiment 2:

[0028] A main and temporary combined foundation pit support process, the steps of which are as follows: S1: construction preparation work, before excavation, a comprehensive investigation of obstacles on the ground and underground of the site is carried out, and whether there are underground pipelines in and around the site is further determined, and the position and direction are determined on site, and they are protected during the earth excavation process. According to the foundation pit support plan, the foundation pit excavation line is determined, and the passage layout of the excavation machinery and earth-moving vehicles, the excavation sequence and the arrangement of the soil pile position are well done. It is strictly forbidden to pile the excavated soil around the foundation pit, and the boundary line is laid out with lime; S2: determine the elevation, use a level and a benchmark to determine the elevation, and strictly control the excavation depth as the excavation progresses. A guardrail is set around the top of the pit slope 0.50m away, with a height of not less than 1.20m. When transporting earthwork, care should be taken to prevent damage to drainage ditches, guardrails and other facilities; during the construction and operation of the foundation pit support, the overload on the top of the slope is not allowed to exceed the design standard. According to the site and surrounding road conditions, a ramp for transporting earthwork from the foundation pit is set up with a width of 8m and a slope of 1:8. 1:1.5 slope protection is used on both sides. The ramp needs to be compacted and 200mm thick C20 concrete is poured on the surface; S3: Excavate the foundation pit. The excavation depth should be considered in combination with the position of the anchor bolts. The excavation depth is 60cm below the anchor bolt hole position and the excavation width is 15cm. The earthwork is excavated in five layers. The first The first layer is 3.5 meters, and each layer below is 1.0 meter; and after completing the anchor bolts and spraying concrete on the upper working surface, the next layer of earthwork is excavated; S4: Anchor bolt holes are drilled at the corresponding positions of the anchor bolts, with a diameter of 100mm. The outer end of the main reinforcement of the anchor bolt is provided with a 15cm hook. The main reinforcement is welded with a central bracket every 2m. The main reinforcement and the grouting pipe are placed in the hole together, and pure cement slurry with a water-cement ratio of 0.5 is injected into the hole; S5: Hang the steel mesh, and the steel mesh sheets are overlapped and tied. The overlap length of the steel mesh on the upper and lower sections of the slope should be greater than 300mm, and the steel mesh sheet is welded to the hook at the outer end of the anchor bolt. The gap between the steel mesh sheet and the slope surface is large. 30mm; S6: sprayed concrete, the concrete components include cement, water, sand and gravel, and the mass ratio of cement: water: stone: sand: gravel is 1:0.35:1.1:2.7; 80mm thick concrete is sprayed in the slope section. Considering the avoidance of rain erosion on the top of the foundation pit in the later stage and ensuring safety and reliability, the top of the foundation pit is flat and the sprayed concrete is sprayed to the red line enclosure edge. The strength grade of the sprayed concrete is C20. The spraying operation should be carried out in sections, and the spraying operation in the same section should be from top to bottom; S7: maintenance, the thickness of the sprayed layer should be uniform, and after the sprayed concrete is finally set, it should be sprayed with water for maintenance. The maintenance period is 10d. When the temperature is below 5℃, water spraying is not allowed;

[0029] The excavation of the foundation pit in S1 is carried out in accordance with the requirements of the drawings on each side. The pedestrian walkway needs to be protected. The width of the walkway is not less than 1000mm, the distance between the vertical poles is not more than 1200mm, and the slope of the walkway is the same as the slope of the foundation pit. A non-slip wooden strip with a cross-section of not less than 20×30mm should be set on the scaffolding board every 250mm. Skirting boards and protective railing pedestrian walkways should be set on both sides of the ramp. Before spraying concrete in S6, the mechanical equipment should be inspected and tested. The air compressor pressure should be not less than 0.5MPa and the air volume should be not less than 9m3 / min to ensure the quality of concrete. The water pressure should be not less than 0.2MPa. When spraying concrete, the nozzle should be kept vertical to the sprayed surface, and the distance should be 0.6m. Before fully hanging the steel mesh in S6, the base must be manually sloped, leveled, and compacted. The concrete surface layer should be turned over the top of the foundation pit and extend to the red line edge to form a slope protection. In the S6, the back of the steel bars should be sprayed first and then the front of the steel bars at the cross-lined parts to prevent gaps behind the steel bars. A 45° slope angle should be made at the joints between layers to facilitate the firm overlap of concrete. In the spraying operation in the S6, a 2cm wide expansion joint is set horizontally at an interval of 15m along the slope direction, and the seam is filled with asphalt hemp tendons. The aperture of the hole in the S4 is 150mm, and the grouting pipe is 0.5m away from the bottom of the hole. Crushed stone with a particle size of 5mm is used to be put into the hole. During the spraying operation in the S6, the time from initial setting to final setting of concrete is controlled to 5min by adding an accelerator. The accelerator includes the following raw material components by weight: 30% soda ash, 10% bauxite, 20% sodium chlorate, and the balance is quicklime. During excavation in S3, the pile load within 20m around the foundation pit (measured from the top of the foundation pit slope outward) shall not be greater than 10kN / m2, the total construction load (including the pile load) shall not be greater than 20kN / m2, no soil shall be stored within 10m around the foundation pit, no construction materials shall be piled within 2m of the trench edge, and no transportation tools or machinery shall be moved along the edge of the foundation pit.

[0030] In summary, the anchor bolt complex formed by this scheme can significantly improve the overall stability of the slope; its construction process is simple; the construction does not need to occupy a separate site, reducing the restrictions on the requirements of the construction site, and the construction cost is low. At the same time, the pollution to the surrounding environment of the construction site is reduced, and the time from the initial setting to the final setting of the concrete is controlled by adding an accelerator during the spraying operation, which greatly shortens the solidification time of the support and improves the efficiency of the support construction. It solves the problem in the prior art that the piles and steel beams cannot be reused after the foundation pit is backfilled, resulting in waste, and when other construction methods are used, the requirements for the surrounding construction environment site are relatively high.

[0031] The above shows and describes the basic principles and main features of the present invention and the advantages of the present invention. It is obvious to those skilled in the art that the present invention is not limited to the details of the above exemplary embodiments, and the present invention can be implemented in other specific forms without departing from the spirit or basic features of the present invention. Therefore, no matter from which point of view, the embodiments should be regarded as exemplary and non-restrictive. The scope of the present invention is defined by the attached claims rather than the above description, and it is intended that all changes falling within the meaning and scope of the equivalent elements of the claims are included in the present invention. Any figure mark in the claims should not be regarded as limiting the claims involved.

[0032] In addition, it should be understood that although the present specification is described according to implementation modes, not every implementation mode contains only one independent technical solution. This description of the specification is only for the sake of clarity. Those skilled in the art should regard the specification as a whole. The technical solutions in each embodiment may also be appropriately combined to form other implementation modes that can be understood by those skilled in the art.

Claims

1. A primary and temporary combined foundation pit support process, characterized in that: The steps are as follows: S1: Construction preparation work. Before excavation, conduct a comprehensive survey of obstacles on the ground and underground of the site, further determine whether there are underground pipelines in and around the site, determine the location and direction on site, and protect them during the excavation process. According to the foundation pit support plan, determine the foundation pit excavation line, and make arrangements for the passages of excavation machinery and earth-moving vehicles, the excavation sequence and the location of the earth pile. It is strictly forbidden to pile the excavated soil around the foundation pit, and use lime to lay out the edge line; S2: Determine the elevation, use a level and a benchmark to determine the elevation, and strictly control the excavation depth as the excavation progresses. Set up guardrails 0.50m outside the top of the foundation pit slope, with a height of not less than 1.20m. When transporting earthwork outward, care should be taken to prevent damage to drainage ditches, guardrails and other facilities; during the construction and operation of the foundation pit support, the overload on the top of the slope is not allowed to exceed the design standard. According to the site and surrounding road conditions, set up a ramp for transporting earthwork out of the foundation pit, with a width of 8m and a slope of 1:

8. Both sides use 1:1.5 slope protection. The ramp needs to be compacted and poured with 200mm thick C20 concrete on the surface; S3: Excavate the foundation pit. The excavation depth should be considered in combination with the anchor bolt position. The excavation depth is 60-70 cm below the anchor bolt hole position, and the excavation width is 15-20 cm. The earthwork is excavated in five layers, with the first layer being 3.5-4.0 meters, and each subsequent layer being 1.0-1.3 meters; and the excavation of the next layer of earthwork is carried out after the anchor bolts and shotcrete of the upper working surface are completed; S4: Anchor bolt holes are drilled at the corresponding positions of the anchor bolts, with a diameter of 100 mm to 150 mm. A 15 cm hook is set at the outer end of the main reinforcement of the anchor bolt. A central bracket is welded to the main reinforcement every 2 m. The main reinforcement and the grouting pipe are placed in the hole together, and pure cement slurry with a water-cement ratio of 0.5 is injected into the hole; S5: Hang the steel mesh, overlap and tie the steel meshes, the overlap length of the steel meshes on the upper and lower sections of the slope should be greater than 300mm, and the steel meshes are welded to the hooks at the outer ends of the anchor bolts, and the gap between the steel meshes and the slope surface is greater than 30mm; S6: Sprayed concrete, the concrete components include cement, water, sand and gravel, and the mass ratio of cement: water: stone: sand: gravel is 1:0.35~0.4:1.1~1.2:2.7~2.8; 80mm thick concrete is sprayed in the slope section. Considering the need to avoid rain erosion on the top of the foundation pit in the later stage and to ensure safety and reliability, the top of the foundation pit is leveled and the sprayed concrete is sprayed to the red line enclosure edge. The strength grade of the sprayed concrete is C20. The spraying operation should be carried out in sections, and the spraying operation in the same section should be from top to bottom; S7: Maintenance: the thickness of the sprayed layer should be uniform. After the shotcrete has finally set, it should be sprayed with water for maintenance. The maintenance period is 10 days. Water spraying is not allowed when the temperature is below 5°C.

2. According to claim 1, a primary and temporary combined foundation pit support process is characterized by: The excavation of the foundation pit in S1 shall be sloped in proportion to the requirements of the drawings on each side. The pedestrian walkway shall be safely protected. The walkway width shall not be less than 1000mm, the spacing between vertical poles shall not be greater than 1200mm, the slope of the walkway shall be the same as the slope of the foundation pit, and an anti-slip wooden strip with a cross-section of not less than 20×30mm shall be set on the scaffolding every 250mm to 300mm. Skirting boards and guardrails shall be set on both sides of the ramp.

3. According to claim 1, a primary and temporary combined foundation pit support process is characterized by: Before spraying concrete in S6, the mechanical equipment should be inspected and tested. The air compressor pressure should be no less than 0.5MPa and the air volume should be no less than 9m3 / min to ensure the quality of concrete. The water pressure should be no less than 0.2MPa. When spraying concrete, the nozzle should be kept vertical to the sprayed surface, and the distance should be 0.6-1.0m.

4. According to claim 1, a primary and temporary combined foundation pit support process is characterized by: Before fully hanging the steel mesh in S6, the base layer must be artificially sloped, leveled and compacted, and the concrete surface layer must be turned over the top of the foundation pit and extended to the red line edge to form a slope protection.

5. The primary and temporary combined foundation pit support process according to claim 1 is characterized by: In S6, at the cross-lined parts of the steel bars, the back of the steel bars should be sprayed first, and then the front of the steel bars should be sprayed to prevent gaps from appearing behind the steel bars. A 45° slope should be made at the joints between layers to facilitate firm concrete lap joints.

6. The primary and temporary combined foundation pit support process according to claim 1 is characterized by: In the spraying operation in S6, a 2-3 cm wide expansion joint is set at a horizontal interval of 15 m along the slope direction, and the joint is filled with asphalt hemp tendons.

7. The primary and temporary combined foundation pit support process according to claim 1 is characterized by: The hole in S4 has a diameter of 150-200 mm, and the grouting pipe is 0.5 m away from the bottom of the hole. Crushed stone with a particle size of 5-15 mm is poured into the hole.

8. The primary and temporary combined foundation pit support process according to claim 1 is characterized by: During the spraying operation in S6, the time from initial setting to final setting of concrete is controlled to be 5-9 minutes by adding an accelerating setting agent, and the accelerating setting agent comprises the following raw material components in parts by weight: 30-40% soda ash, 10-20% bauxite, 20-30% sodium chlorate, and the balance is quicklime.

9. The primary and temporary combined foundation pit support process according to claim 1, characterized in that: When excavating in S3, the load within 20m around the foundation pit (calculated from the top of the foundation pit slope outward) shall not exceed 10kN / m 2 The total construction load (including stacking load) shall not exceed 20kN / m 2 No soil shall be stored within 10m around the foundation pit, no construction materials shall be piled within 2m of the trench edge, and no transportation vehicles or machinery shall be moved along the edge of the foundation pit.