Composite bearing type inclined supporting method and system

By using the composite load-bearing oblique support method in deep foundation pit construction, and using elastic waterproof bodies and extruded plate technology, the problem of groundwater affecting construction efficiency is solved, and more efficient concrete solidification and construction efficiency is achieved.

CN119041446APending Publication Date: 2024-11-29CSCEC STRAIT CONSTR & DEV
View PDF 0 Cites 0 Cited by

Patent Information

Application Number
CN202411351311.2
Authority / Receiving Office
CN · China
Patent Type
Applications(China)
Current Assignee / Owner
Filing Date
2024-09-26
Publication Date
2024-11-29

AI Technical Summary

Technical Problem

In the construction of deep foundation pits, the construction efficiency of the inclined support system is greatly affected by groundwater, resulting in the extension of the concrete solidification time, which in turn affects the construction difficulty and efficiency.

Method used

By adopting the composite load-bearing oblique support method, by winding the elastic waterproof body on the steel pipe and installing a guide steel cap, combining the extruded plate and control rod, the bottom dry filler and premixed concrete are filled in the steel pipe, and the elastic waterproof body is expanded and isolated. Groundwater, reduce the outer diameter of the extruded plate to reduce impact force and improve the solidification efficiency of concrete.

Benefits of technology

Effectively isolate groundwater, shorten the concrete solidification time, improve the construction efficiency of the inclined support system, and is suitable for areas with abundant groundwater and reduce construction difficulty.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN119041446A_ABST
    Figure CN119041446A_ABST
Patent Text Reader

Abstract

The invention relates to the technical field of foundation pit construction, and provides a composite bearing type diagonal bracing method and system.The method comprises the following steps that S1, measurement is conducted after a site is leveled so as to determine the size of a needed diagonal bracing steel pipe and the insertion position of the subsequent diagonal bracing steel pipe, and an insertion hole is formed corresponding to the insertion position of the diagonal bracing steel pipe; s2, a diagonal bracing steel pipe is manufactured, an elastic waterproof body is wound around the peripheral wall, located at the lower end, of a steel pipe body and wraps the lower end face of the steel pipe body, and then a guide steel cap is installed on the steel pipe body and covers the elastic waterproof body; the guiding steel cap comprises two arc-shaped guiding plates rotationally connected to the steel pipe body, the elastic waterproof body and the arc-shaped guiding plates are connected through connecting pieces, and when the elastic waterproof body does not expand, the two ends of the two arc-shaped guiding plates abut against each other. After the elastic waterproof body expands, the arc-shaped guide plates are pushed to move in the direction away from each other through the connecting piece. The overall construction efficiency of the inclined supporting system is improved.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The present application relates to the technical field of foundation pit construction, and in particular to a composite load-bearing inclined support method and system. Background Art

[0002] With the acceleration of my country's urbanization process, people are increasingly developing and utilizing underground space. Construction foundation pit projects are characterized by "large, deep, tight, and close", and various new types of enclosure forms and construction techniques are constantly emerging. For large-scale deep foundation pit projects, horizontal support structures are generally used to transfer the huge earth pressure to the support body on the other side. When the plane size of the foundation pit is large, a long support structure is required to transfer the earth pressure. In addition, when the support is removed, the supports on both sides must be removed symmetrically, which makes the construction more difficult.

[0003] In response to the above problems, there is currently an inclined support system, which is provided with an inclined support rod on one side of the support pile and a reinforcement layer fixedly arranged on the outside of the inclined support rod, and the reinforcement layer is buried in the soil layer of the deep foundation pit body. The reinforcement layer is specifically formed by pouring cement slurry into the corresponding drilling holes on the ground of the deep foundation pit body before driving the inclined support rod, and driving the inclined support rod into the drilling holes before the cement slurry solidifies, and forming a reinforcement layer after the cement slurry solidifies. This type of inclined support system is actually a cast-in-place pile, which uses the solidification of cement slurry to fix the bottom end of the inclined support rod, and has effective firmness.

[0004] However, when it is put into use, if the concrete poured in the drilled hole has not yet solidified, when it encounters groundwater, the solidification time of the concrete will be prolonged, thereby affecting the overall construction efficiency of the inclined support system, so further improvement is needed. Summary of the invention

[0005] In order to improve the overall construction efficiency of the inclined support system, the present application provides a composite load-bearing inclined support method and system.

[0006] The present application provides a composite load-bearing oblique support method, which adopts the following technical solution: A composite load-bearing oblique support method comprises the following steps: Step S1, after the site is leveled, measurement is performed to determine the required size of the diagonal bracing steel pipe (1) and the position where the diagonal bracing steel pipe (1) is to be subsequently inserted, and an insertion hole (2) is opened corresponding to the position where the diagonal bracing steel pipe (1) is to be inserted; Step S2, manufacturing a diagonal bracing steel pipe (1), winding an elastic waterproof body (3) around the outer peripheral wall of the steel pipe body at the lower end and covering the lower end surface of the steel pipe body, and then installing a guide steel cap (4) on the steel pipe body and covering the elastic waterproof body (3); the guide steel cap (4) comprises two arc-shaped guide plates (41) respectively rotatably connected to the steel pipe body, and the elastic waterproof body (3) and the arc-shaped guide plates (41) are connected by a connecting piece (42). When the elastic waterproof body (3) is not expanded, the two ends of the two arc-shaped guide plates (41) are in contact with each other. When the elastic waterproof body (3) is expanded, the arc-shaped guide plates (41) are pushed by the connecting piece (42) to move in a direction away from each other; Step S3, implanting the guide steel cap (4) on the diagonal bracing steel pipe (1) into the construction ground at a preset angle; Step S4, filling the bottom dry filler (5) into the steel pipe body from the top of the diagonal bracing steel pipe (1), and then pushing the extrusion plate (7) to compact the bottom dry filler (5) and expand the elastic waterproof body (3); Step S5, filling the premixed concrete (14) from the top of the diagonal bracing steel pipe (1) into the steel pipe body and repeatedly tamping the premixed concrete (14). During the process of filling the premixed concrete (14), when the premixed concrete (14) flows to the upper surface of the extrusion plate (7), the outer diameter of the extrusion plate (7) is reduced to provide a flow channel for the premixed concrete (14), so that water in the premixed concrete (14) penetrates downward into the bottom dry filler (5). At the same time, the extrusion plate (7) is pulled away from the steel pipe body, so that the compacted bottom dry filler (5) solidifies and hardens into a hard entity, thereby obtaining a composite diagonal bracing body (9) that is arranged obliquely and connected to the construction ground; Step S6: locking the top of the composite oblique support body (9) with the crown beam / surrounding purlin of the supporting structure (10) to obtain a composite load-bearing oblique support system.

[0007] By adopting the above technical solution, the bottom dry filler is compacted by an extrusion plate. During the compaction process, the elastic waterproof body expands. It should be noted that due to the waterproofness of the elastic waterproof body itself, the effect of groundwater can be effectively isolated to prevent groundwater from flowing back into the steel pipe body. It is suitable for areas with abundant groundwater to reduce the impact on the solidification time of concrete, thereby improving the overall construction efficiency of the inclined support system.

[0008] Before the premixed concrete contacts the bottom dry filler, the extrusion plate is used to maintain the compaction of the bottom dry filler and the expansion of the elastic waterproof body. When the premixed concrete flows to the upper surface of the extrusion plate, the outer diameter of the extrusion plate is reduced to allow the premixed concrete to flow to the bottom dry filler. While reducing the expansion of the elastic waterproof body, the extrusion plate can also be used to alleviate the impact force of the premixed concrete flowing to the bottom dry filler, reducing the impact of the impact force on the density of the bottom dry filler at this time. While compacting the premixed concrete and allowing the water in the premixed concrete to penetrate downward into the bottom dry filler, the extrusion plate is pulled out of the steel pipe body to reduce the solidification effect of the extrusion plate built into the steel pipe body on the premixed concrete and the bottom dry filler.

[0009] Preferably, in step S2, a cavity is left between the elastic waterproof body and the free end of the arc-shaped guide plate, so as to increase the expansion space for compacting the bottom dry filler in step S4 to expand the elastic waterproof body.

[0010] By adopting the above technical scheme, the expansion space for the elastic waterproof body is increased by the reserved cavity to reduce the difficulty of subsequent expansion of the elastic waterproof body, and during the expansion of the elastic waterproof body, the arc guide plates can be pushed to move away from each other through the connecting parts. When the distance between the free ends of the two arc guide plates is larger than the outer diameter of the steel pipe plate body, when the steel pipe body is rammed, the arc guide plates can be pushed to be inserted on both sides of the inner wall of the first insertion hole to improve the connection strength between the steel pipe body and the foundation pit body, thereby improving the oblique bearing capacity of the oblique support.

[0011] Preferably, in step S5, the height of the premixed concrete filled into the diagonal bracing steel pipe corresponds to the height of the bottom surface of the foundation pit body, so that the top surface of the premixed concrete filled in the diagonal bracing steel pipe is flush with the bottom surface of the foundation pit body or lower than the bottom surface of the foundation pit body.

[0012] Preferably, in step S4, a control rod is used to control the position of the extrusion plate within the steel pipe body, the control rod is connected to the middle of the extrusion plate, and the upper end of the control rod is exposed to the upper end surface of the steel pipe body, and scale lines are provided on the outer peripheral wall of the control rod.

[0013] By adopting the above technical solution, the position of the extrusion plate in the steel pipe body is controlled by the control rod. In step S4, the extrusion plate is pushed to compact the bottom dry filler. Since the premixed concrete is located in the steel pipe body and is not easy to check, the depth of the premixed concrete can be checked according to the scale line on the control rod, so that the poured premixed concrete can adapt to the height of the ground of the foundation pit body to be excavated later. It should be noted that in order to improve the density of the bottom dry filler, the control rod can also be tamped to apply force to the bottom dry filler.

[0014] Preferably, the extrusion plate includes a plurality of first connecting plates that are rotatably connected to the control rod and a sliding plate arranged between adjacent first connecting plates, one of the first connecting plates located on both sides of the sliding plate is provided with a sliding groove for the sliding plate to be slidably connected, the sliding groove extends to the side wall of the first connecting plate away from the control rod, a connecting rod is fixedly connected to the upper surface of the sliding plate, a rotating ring is coaxially sleeved on the control rod, a plurality of connecting rods are fixedly connected to the same rotating ring, and the connecting rod is arranged close to the other first connecting plate located on both sides of the sliding plate.

[0015] By adopting the above technical solution, in step S4, for compaction of the bottom dry filler, the control rod is pushed so that the lower surface of the extrusion plate is compressed and arranged perpendicular to the control rod, and then the rotating ring is rotated so that the sliding plate slides out of the slide groove and abuts against the side wall of the first connecting plate to compact the bottom dry filler. In step S5, for the reduction of the outer diameter of the extrusion plate, when the upper surface of the extrusion plate is squeezed by the ready-mixed concrete, the rotating ring is first rotated so that the sliding plate slides into the slide groove, and then the control rod is pulled so that the extrusion plate is compressed and rotated to be arranged in an umbrella shape, providing a flow channel for the ready-mixed concrete.

[0016] Preferably, the extrusion plate specifically includes a plurality of second connecting plates that are rotatably connected to the control rod and a folding plate arranged between adjacent second connecting plates, the folding plate being provided with folding lines that symmetrically arrange the folding plates, and the folding plates being bent away from both sides of the folding lines to form two adjacent second connecting plates.

[0017] By adopting the above technical solution, in step S4, for compaction of the bottom dry filler, when the control rod is pushed, the lower surface of the extrusion plate is pressed to unfold the folding plate to compact the bottom dry filler. In step S5, for reduction of the outer diameter of the extrusion plate, when the upper surface of the extrusion plate is squeezed by the ready-mixed concrete, the control rod is pulled, so that the folding plate is folded inward along the folding line, and the extrusion plate is arranged in an umbrella shape to provide a flow channel for the ready-mixed concrete.

[0018] Preferably, after step S6, the method further includes: Step S7: After the excavated foundation pit body meets the design requirements, the composite inclined support body is removed.

[0019] Preferably, the steel pipe body includes a first steel pipe, a second steel pipe arranged at the upper end of the first steel pipe, and a mounting part for detachably connecting the second steel pipe to the first steel pipe, the insertion hole includes a first insertion hole for inserting the first steel pipe and a second insertion hole for inserting the second steel pipe, the second insertion hole is arranged on the bottom surface of the foundation pit body, the top surface of the first steel pipe is flush with the bottom surface of the foundation pit body or lower than the bottom surface of the foundation pit body, and the top surface height of the premixed concrete is lower than the top surface height of the first steel pipe.

[0020] By adopting the above technical solution, when the excavation of the foundation pit body is completed, the second steel pipe is removed through the installation parts, so that the inclined support body can be removed according to needs through the first steel pipe, the second steel pipe and the installation parts, and the possibility of affecting the bottom surface of the foundation pit body by the vibration of the lower end of the steel pipe body caused by the cutting of the steel pipe body by an external machine can be reduced.

[0021] The present application also provides a composite load-bearing inclined support system, which adopts the following technical solution: A composite load-bearing oblique support system comprises a supporting structure vertically arranged in the side wall of a foundation pit body, a composite oblique support body obliquely arranged on the bottom surface of the foundation pit body, and a crown beam arranged on the top of the supporting structure for connection with the composite oblique support body.

[0022] In summary, this application has the following beneficial effects: 1. By setting up an elastic waterproof body, due to its own waterproof property, it can effectively isolate the effect of groundwater to prevent groundwater from flowing back into the steel pipe body. It is suitable for areas with abundant groundwater to reduce the impact on the solidification time of concrete, thereby improving the overall construction efficiency of the inclined support system.

[0023] 2. By providing an extrusion plate, in step S4, the bottom dry filler can be compacted and the elastic waterproof body can be expanded. In step S5, after the premixed concrete flows to the upper surface of the extrusion plate, the outer diameter of the extrusion plate is reduced to allow the premixed concrete to flow to the bottom dry filler, thereby reducing the expansion of the elastic waterproof body. At the same time, the extrusion plate can also be used to alleviate the impact force of the premixed concrete flowing to the bottom dry filler, thereby reducing the impact of the impact force on the density of the bottom dry filler at this time. While compacting the premixed concrete and allowing the water in the premixed concrete to penetrate downward into the bottom dry filler, the extrusion plate is pulled out of the steel pipe body to reduce the solidification effect of the extrusion plate built into the steel pipe body on the premixed concrete and the bottom dry filler. BRIEF DESCRIPTION OF THE DRAWINGS

[0024] Figure 1 This is a schematic diagram of the structure before site excavation in Example 1 of the present application; Figure 2 This is a schematic diagram of the structure of the base body formed after the site is excavated in Example 1 of the present application; Figure 3 is a schematic diagram of the structure of the mounting member in Example 1 of the present application; Figure 4 It is a schematic cross-sectional structure diagram of the elastic waterproof body and the guide steel cap in Example 1 of the present application; Figure 5 is a schematic structural diagram of the elastic waterproof body in Example 1 of the present application; Figure 6 is a schematic diagram of the structure of the elastic waterproof body after expansion in Example 1 of the present application; Figure 7 It is a schematic diagram of the internal structure of the steel pipe body in Example 1 of the present application; Figure 8 is a schematic diagram of the structure of the extruded plate in Example 1 of the present application; Fig. 9 It is a schematic diagram of the internal structure of the steel pipe body in Example 2 of the present application; Fig.10 It is a schematic diagram of the structure of the extruded plate in Example 2 of the present application.

[0025] Explanation of the reference numerals in the accompanying drawings: 1. diagonal bracing steel pipe; 11. first steel pipe; 111. plug-in pipe; 12. second steel pipe; 13. mounting piece; 14. ready-mixed concrete; 2. insertion hole; 21. first insertion hole; 22. second insertion hole; 3. elastic waterproof body; 31. tensile reinforcement layer; 4. guide steel cap; 41. arc-shaped guide plate; 42. connecting piece; 5. bottom dry filler; 6. foundation pit body; 7. extrusion plate; 71. first connecting plate; 711. slide groove; 72. sliding plate; 721. slider; 722. connecting rod; 73. second connecting plate; 74. folding plate; 741. folding line; 8. control lever; 81. scale line; 82. rotating ring; 9. composite diagonal support body; 10. supporting structure. DETAILED DESCRIPTION

[0026] The following is combined with Figure 1-10 , further details of this application are given.

[0027] The embodiments of the present application disclose a composite load-bearing oblique support method and system.

[0028] Embodiment 1: A composite load-bearing oblique support method comprises the following steps: Step S1, after the site is leveled, measurement is performed to determine the required size of the diagonal brace steel pipe 1 and the position where the diagonal brace steel pipe 1 is subsequently inserted, and an insertion hole 2 is opened corresponding to the position where the diagonal brace steel pipe 1 is inserted; Step S2, making the diagonal brace steel pipe 1, winding the elastic waterproof body 3 around the outer peripheral wall of the steel pipe body at the lower end and covering the lower end surface of the steel pipe body, then installing the guide steel cap 4 on the steel pipe body and covering the elastic waterproof body 3; the guide steel cap 4 includes two arc-shaped guide plates 41 respectively rotatably connected to the steel pipe body, the elastic waterproof body 3 and the arc-shaped guide plates 41 are connected by a connecting piece 42, when the elastic waterproof body 3 is not expanded, the two ends of the two arc-shaped guide plates 41 are abutted against each other, and when the elastic waterproof body 3 is expanded, the arc-shaped guide plates 41 are pushed by the connecting piece 42 to move away from each other; Step S3, implanting the guide steel cap 4 on the diagonal bracing steel pipe 1 into the construction ground at a preset angle; Step S4, filling the bottom dry filler 5 into the steel pipe body from the top of the diagonal bracing steel pipe 1, and then pushing the extrusion plate 7 to compact the bottom dry filler 5 and expand the elastic waterproof body 3; Step S5, filling the premixed concrete 14 from the top of the diagonal bracing steel pipe 1 into the steel pipe body and tamping repeatedly. In the process of filling the premixed concrete 14, when the premixed concrete 14 flows to the upper surface of the extrusion plate 7, the outer diameter of the extrusion plate 7 is reduced to provide a flow channel for the premixed concrete 14, so that the water in the premixed concrete 14 penetrates downward into the bottom dry filler 5, and at the same time, the extrusion plate 7 is pulled away from the steel pipe body, so that the compacted bottom dry filler 5 solidifies and hardens into a hard entity, thereby obtaining a composite diagonal support body 9 that is arranged obliquely and connected to the construction ground; Step S6, locking the top of the composite oblique support body 9 with the crown beam / surrounding purlin of the supporting structure 10 to obtain a composite load-bearing oblique support system; Step S7: After the excavated foundation pit body 6 meets the design requirements, the composite inclined support body 9 is removed.

[0029] Reference Figure 1 , Figure 2 , wherein, in step S2, the steel pipe body includes a first steel pipe 11, a second steel pipe 12 arranged at the upper end of the first steel pipe 11, and a mounting member 13 for detachably connecting the second steel pipe 12 to the first steel pipe 11. In this embodiment, the mounting member 13 is specifically a bolt. A plug-in pipe 111 inserted into the second steel pipe 12 is protruded from the upper end of the first steel pipe 11. The outer diameter of the plug-in pipe 111 is smaller than the inner diameter of the second steel pipe 12. The bolt thread is threadedly penetrated through the outer peripheral wall of the second steel pipe 12 and is threadedly connected with the plug-in pipe 111. A plurality of bolts are arranged around the axis of the second steel pipe 12, such as Figure 3 shown.

[0030] It should be noted that since the steel pipe body is detachable, the insertion hole 2 specifically includes a first insertion hole 21 for inserting the first steel pipe 11 and a second insertion hole 22 for inserting the second steel pipe 12. The second insertion hole 22 is arranged in the construction ground (i.e., the site before excavation), and the first insertion hole 21 is arranged on the bottom surface of the foundation pit body 6.

[0031] It should be noted that the top surface of the first steel pipe 11 is flush with or lower than the bottom surface of the foundation pit body 6, and the elastic waterproof body 3 and the guide cap body are both arranged at the lower end of the first steel pipe 11. A cavity is left between the free end of the elastic waterproof body 3 and the arc-shaped guide plate 41 to increase the expansion space for compacting the bottom dry filler 5 to expand the elastic waterproof body 3 in step S4.

[0032] Reference Figure 4 , Figure 5 , wherein, in step S2, the elastic waterproof body 3 is bonded to the outer peripheral wall of the second steel pipe 12 by a high-strength adhesive. In this embodiment, the elastic waterproof body 3 can be made of materials such as rubber and a high molecular polymer layer, and needs to have certain elasticity and tensile resistance. Further, in order to reduce the possibility of the elastic waterproof body 3 being ruptured by the scratches of soil and stones during the expansion process, a tensile reinforcement layer 31 can be fixedly connected to the two opposite surfaces of the elastic waterproof body 3, and the tensile reinforcement layer 31 can be made of non-woven fiber cloth, nylon or a combination of several high-strength materials. Of course, other materials with good tensile resistance can be used in practice. The function of this tensile reinforcement layer 31 is to protect the waterproof membrane layer to prevent the waterproof membrane layer from being damaged.

[0033] Reference Figure 4 , Figure 6 , wherein, in step S2, the connecting member 42 can specifically be a connecting rod 722 or a connecting plate, which is made of high-strength metal material, so that after the elastic waterproof body 3 expands, it can push the two arc-shaped guide plates 41 to move away from each other, and when tamping the steel pipe body, it can reduce the possibility of the arc-shaped guide plate 41 rebounding due to the reaction force of the soil or the connecting member 42 being deformed.

[0034] Among them, in step S3, the diagonal brace steel pipe 1 is implanted into the construction ground by hammering, vibration, hydraulic power or a combination thereof. It should be noted that when the diagonal brace steel pipe 1 is implanted, the implantation position and angle of the diagonal brace steel pipe 1 need to be measured. If the implantation position and angle of the diagonal brace steel pipe 1 are within the preset range, step S4 is entered; if the implantation position and angle of the diagonal brace steel pipe 1 are not within the preset range, the position and angle of the diagonal brace steel pipe 1 are adjusted until they are within the preset range.

[0035] Reference Figure 6 In step S4, the bottom dry filler 5 may be a concrete mixture without water added, a cement sand mixture without water added, or a combination of the two.

[0036] Reference Figure 7 For the extrusion of the bottom dry filler 5, a control rod 8 is provided on the extrusion plate 7, and the control rod 8 is fixedly connected to the middle of the extrusion plate 7 to control the position of the extrusion plate 7 in the steel pipe body. In this embodiment, the upper end of the control rod 8 is exposed to the upper end surface of the steel pipe body, and a scale line 81 is provided on the outer peripheral wall of the control rod 8 to check the position of the bottom dry filler 5. It should be noted that in step S4, the bottom dry filler 5 can be compacted by tamping the control rod 8.

[0037] Back to Figure 2, wherein, in step S5, the top surface height of the ready-mixed concrete 14 is flush with or lower than the bottom surface of the foundation pit body 6. Since the top surface of the first steel pipe 11 is flush with or lower than the bottom surface of the foundation pit body 6, in order to reduce the difficulty of disassembling the second steel pipe 12 from the first steel pipe 11, in this embodiment, the ready-mixed concrete 14 is lower than the top surface height of the first steel pipe 11. As for how to measure the height of the ready-mixed concrete 14, it can be checked through the scale line 81 on the control rod 8.

[0038] Reference Figure 7 , Figure 8 As to how to reduce the outer diameter of the extrusion plate 7, in this embodiment, the extrusion plate 7 specifically includes a plurality of first connection plates 71 that are all rotatably connected to the control rod 8 and a sliding plate 72 that is arranged between adjacent first connection plates 71. The first connection plates 71 can be rotatably connected to the control rod 8 by hinges. Among them, one of the first connection plates 71 located on both sides of the sliding plate 72 is provided with a slide groove 711, and the sliding plate 72 is protrudingly provided with a slider 721 that is slidably connected to the slide groove 711. A connecting rod 722 is fixedly connected to the upper surface of the sliding plate 72, and a rotating ring 82 is coaxially sleeved on the control rod 8. A plurality of connecting rods 722 are fixedly connected to the same rotating ring 82, and the connecting rod 722 is arranged close to another first connection plate 71 located on both sides of the sliding plate 72.

[0039] In step S5, the rotating ring 82 is rotated to make the sliding plate 72 slide into the sliding groove 711, and then the control rod 8 is pulled to make the first connecting plate 71 rotate in an umbrella shape after receiving the pressure of the ready-mixed concrete 14, so as to provide a flow channel for the ready-mixed concrete 14. For the compaction of the bottom dry filler 5 in step S4, the control rod 8 is pushed to make the lower surface of the extrusion plate 7 be perpendicular to the control rod 8 under pressure, and then the rotating ring 82 is rotated to make the sliding plate 72 slide out of the sliding groove 711 and abut against the side wall of the first connecting plate 71 to compact the bottom dry filler 5.

[0040] It should be noted that after the ready-mixed concrete 14 and the bottom dry filler 5 are in contact and the extrusion plate 7 is withdrawn from the second steel pipe 12, the density reached needs to be measured. When the density is equal to or greater than the preset value, step S6 is entered; when the density is less than the preset value, step S4 is returned. In practice, the density of the ready-mixed concrete 14 and the bottom dry filler 5 can be indirectly measured by three-hit penetration (i.e., the column hammer is raised to 6m and hit three times, and the depth of the column hammer penetrating into the filler).

[0041] Among them, in step S6, for the connection between the top of the composite oblique support body 9 and the crown beam / surrounding purlin of the supporting structure 10, the top of the composite oblique support body 9 and the crown beam / surrounding purlin of the supporting structure 10 can be locked by welding or bolting.

[0042] Among them, in step S7, after the construction ground is opened to a suitable height to form the foundation pit body 6 and meets the design requirements, the bolts are rotated to detach them from the second steel pipe 12 to remove the composite inclined support body 9.

[0043] The present embodiment also discloses a composite load-bearing oblique support system, which includes a support structure 10 vertically arranged in the side wall of the foundation pit body 6, a composite oblique support body 9 obliquely arranged on the bottom surface of the foundation pit body 6, and a crown beam / purlin arranged on the top of the support structure 10 for connection with the composite oblique support body 9.

[0044] Embodiment 2: Reference Fig. 9 The difference between this embodiment and the embodiment 1 is that, in step S5, for the reduction of the outer diameter of the extrusion plate 7, in this embodiment, the extrusion plate 7 specifically includes a plurality of second connecting plates 73 that are all rotatably connected to the control rod 8 and a folding plate 74 disposed between adjacent second connecting plates 73, and the control rod 8 is a square rod. The folding plate 74 is provided with folding lines 741 that symmetrically set the folding plate 74, and the folding plate 74 is bent and formed on two adjacent second connecting plates 73 away from both sides of the folding line 741. When the upper surface of the extrusion plate 7 is squeezed by the ready-mixed concrete 14, the control rod 8 is pulled, so that the folding plate 74 is concavely folded along the folding line 741, so that the extrusion plate 7 is arranged in an umbrella shape to provide a flow channel for the ready-mixed concrete 14.

[0045] In step S4 , for compacting the bottom dry filler 5 , the control rod 8 is pushed so that the lower surface of the pressing plate 7 is pressed to unfold the folding plate 74 to compact the bottom dry filler 5 .

[0046] The above are all preferred embodiments of the present application, and the protection scope of the present application is not limited thereto. Therefore, any equivalent changes made according to the structure, shape, and principle of the present application should be included in the protection scope of the present application.

Claims

1. A composite bearing type oblique support method, characterized in that: The following steps are involved: Step S1, after the site is leveled, measurement is performed to determine the required size of the diagonal bracing steel pipe (1) and the position where the diagonal bracing steel pipe (1) is to be subsequently inserted, and an insertion hole (2) is opened corresponding to the position where the diagonal bracing steel pipe (1) is to be inserted; Step S2, manufacturing a diagonal bracing steel pipe (1), winding an elastic waterproof body (3) around the outer peripheral wall of the steel pipe body at the lower end and covering the lower end surface of the steel pipe body, and then installing a guide steel cap (4) on the steel pipe body and covering the elastic waterproof body (3); the guide steel cap (4) comprises two arc-shaped guide plates (41) respectively rotatably connected to the steel pipe body, and the elastic waterproof body (3) and the arc-shaped guide plates (41) are connected by a connecting piece (42). When the elastic waterproof body (3) is not expanded, the two ends of the two arc-shaped guide plates (41) are in contact with each other. When the elastic waterproof body (3) is expanded, the arc-shaped guide plates (41) are pushed by the connecting piece (42) to move in a direction away from each other; Step S3, implanting the guide steel cap (4) on the diagonal bracing steel pipe (1) into the construction ground at a preset angle; Step S4, filling the bottom dry filler (5) into the steel pipe body from the top of the diagonal bracing steel pipe (1), and then pushing the extrusion plate (7) to compact the bottom dry filler (5) and expand the elastic waterproof body (3); Step S5, filling the premixed concrete (14) from the top of the diagonal bracing steel pipe (1) into the steel pipe body and repeatedly tamping the premixed concrete (14). During the process of filling the premixed concrete (14), when the premixed concrete (14) flows to the upper surface of the extrusion plate (7), the outer diameter of the extrusion plate (7) is reduced to provide a flow channel for the premixed concrete (14), so that water in the premixed concrete (14) penetrates downward into the bottom dry filler (5). At the same time, the extrusion plate (7) is pulled away from the steel pipe body, so that the compacted bottom dry filler (5) solidifies and hardens into a hard entity, thereby obtaining a composite diagonal bracing body (9) that is arranged obliquely and connected to the construction ground; Step S6: locking the top of the composite oblique support body (9) with the crown beam / surrounding purlin of the supporting structure (10) to obtain a composite load-bearing oblique support system.

2. A composite load-bearing oblique support method according to claim 1, characterized in that: In the step S2, a cavity is left between the elastic waterproof body (3) and the free end of the arc-shaped guide plate (41) so as to increase the expansion space for compacting the bottom dry filler (5) in the step S4 to expand the elastic waterproof body (3).

3. A composite load-bearing oblique support method according to claim 1, characterized in that: In the step S5, the height of the ready-mixed concrete (14) filled into the diagonal bracing steel pipe (1) corresponds to the height of the bottom surface of the foundation pit body (6), so that the top surface of the ready-mixed concrete (14) filled into the diagonal bracing steel pipe (1) is flush with the bottom surface of the foundation pit body (6) or lower than the bottom surface of the foundation pit body (6).

4. A composite load-bearing oblique support method according to claim 3, characterized in that: In step S4, a control rod (8) is used to control the position of the extrusion plate (7) within the steel pipe body. The control rod (8) is connected to the middle of the extrusion plate (7), and the upper end of the control rod (8) is exposed to the upper end surface of the steel pipe body. A scale line (81) is provided on the outer peripheral wall of the control rod (8).

5. A composite load-bearing oblique support method according to claim 4, characterized in that: The extrusion plate (7) comprises a plurality of first connection plates (71) which are all rotatably connected to the control rod (8) and a sliding plate (72) arranged between adjacent first connection plates (71); one of the first connection plates (71) located on both sides of the sliding plate (72) is provided with a sliding groove (711) for sliding connection of the sliding plate (72); the sliding groove (711) extends to the side wall of the first connection plate (71) away from the control rod (8); a connecting rod (722) is fixedly connected to the upper surface of the sliding plate (72); a rotating ring (82) is coaxially sleeved on the control rod (8); a plurality of connecting rods (722) are fixedly connected to the same rotating ring (82); and the connecting rod (722) is arranged close to another first connection plate (71) located on both sides of the sliding plate (72).

6. A composite load-bearing oblique support method according to claim 4, characterized in that: The extrusion plate (7) specifically comprises a plurality of second connecting plates (73) all rotatably connected to the control rod (8) and a folding plate (74) arranged between adjacent second connecting plates (73), wherein the folding plate (74) is provided with a folding line (741) which symmetrically arranges the folding plate (74), and the folding plate (74) is bent and formed on two adjacent second connecting plates (73) away from both sides of the folding line (741).

7. A composite load-bearing oblique support method according to claim 1, characterized in that: After step S6, the method further includes: Step S7: After the excavated foundation pit body (6) meets the design requirements, the composite inclined support body (9) is removed.

8. A composite load-bearing oblique support method according to claim 7, characterized in that: The steel pipe body comprises a first steel pipe (11), a second steel pipe (12) arranged at the upper end of the first steel pipe (11), and a mounting member (13) for detachably connecting the second steel pipe (12) to the first steel pipe (11); the insertion hole (2) comprises a first insertion hole (21) for inserting the first steel pipe (11) and a second insertion hole (22) for inserting the second steel pipe (12); the second insertion hole (22) is arranged on the bottom surface of the foundation pit body (6); the top surface of the first steel pipe (11) is flush with the bottom surface of the foundation pit body (6) or lower than the bottom surface of the foundation pit body (6); and the top surface height of the premixed concrete (14) is lower than the top surface height of the first steel pipe (11).

9. A composite load-bearing oblique support system, characterized in that: The composite load-bearing oblique support system is the composite load-bearing oblique support system according to any one of claims 1 to 8, and the composite load-bearing oblique support system comprises a supporting structure (10) vertically arranged in the side wall of the foundation pit body (6), a composite oblique support body (9) obliquely arranged on the bottom surface of the foundation pit body (6), and a crown beam / circumferential purlin arranged on the top of the supporting structure (10) for connection with the composite oblique support body (9).