Foundation construction method of offshore special-shaped root rock-socketed jacket pile
By adding a conduit pile foundation guide on the side of the fan to install the ship, combining the ship's DP power positioning and lifting equipment, the offshore rock embedding construction technology is simplified, the problems of complex process and safety risks in the existing technology are solved, and high efficiency is achieved. Safe rock embedded construction.
Patent Information
- Application Number
- CN202411247895.9
- Authority / Receiving Office
- CN · China
- Patent Type
- Applications(China)
- Current Assignee / Owner
- Filing Date
- 2024-09-05
- Publication Date
- 2024-11-29
AI Technical Summary
In the existing offshore wind power projects, the rock embedded construction process is complex, with many and large equipment, which increases construction process and safety risks, making it difficult to carry out construction efficiently.
Use fan installation ship to add a conduit pile foundation guide on the side of the ship, as a rock-embedded pile stabilization platform, combined with the ship's DP power positioning system and self-produced lifting equipment, simplify the construction technology and improve resource utilization and construction efficiency.
It realizes safe and reliable rock-embedding construction, reduces construction costs, shortens construction cycles, improves construction safety and efficiency, and is suitable for typhoon conditions of level 15 and below.
Smart Images

Figure CN119041476A_ABST
Abstract
Description
[Technical field]
[0001] The invention relates to a pipe frame construction technology, and in particular to a foundation construction method for offshore special-shaped root rock-embedded pipe frame piles. [Background technology]
[0002] As a kind of jacket foundation with advantages such as light weight, good adaptability to seabed geological conditions, good stability, large overall rigidity, and relatively small impact of environmental loads such as waves and water flow, it has been widely used in offshore wind turbine foundations, offshore booster station foundations and offshore oil platform foundations. As the power collection center of offshore wind farms, offshore booster stations are key facilities for power transmission and transformation, and are also the key to the success of the entire offshore wind farm.
[0003] Most foreign offshore substation structures adopt the jacket structure, in which the jacket and steel pipe piles are connected by grouting. In a large number of offshore wind power projects such as domestic wind farms, the foundation structure of offshore substations mostly adopts the rear pile method inclined pile jacket foundation.
[0004] At present, offshore wind power is developing rapidly, especially the installed capacity in offshore areas is increasing day by day. However, in offshore areas with low water depth and hard geology, it is difficult for single pile foundation and jacket steel pipe pile foundation to be driven into the hard soil layer. At this time, the jacket rock-embedded foundation forms cast-in-place piles through rock embedding, forming a rigid connection between the foundation and the soil layer to meet the support and bearing requirements of the upper components of the foundation. However, in the current rock-embedded construction industry, the general construction process is to use a specially made rock-embedded pile stabilizing platform, with crawler cranes, drilling equipment, concrete mixing equipment, casting equipment and other construction equipment. All of the above equipment are large-scale equipment. For example, crawler cranes and rotary drilling equipment need to be hoisted in sections to the rock-embedded pile stabilizing platform for assembly, which increases the construction process, and the construction process is complicated, the construction efficiency is low, and the safety risk of offshore construction operations is increased. [Summary of the invention]
[0005] The present invention provides a foundation construction method for offshore special-shaped root-embedded rock jacket piles, which uses a jacket pile foundation guide frame as a rock-embedded pile stabilizing platform by adding a jacket pile foundation guide frame on the side of a wind turbine installation ship. The existing wind turbine installation ship is used as the main body, and the existing ship and machine resources are fully utilized through transformation to efficiently carry out construction operations, thereby accelerating the construction of offshore wind power projects.
[0006] In order to achieve the above-mentioned invention object, the technical solution adopted by the present invention is:
[0007] A foundation construction method for offshore special-shaped root-embedded rock jacket piles comprises the following steps:
[0008] S1. Preparation:
[0009] Transform the wind turbine installation vessel into a rock-embedded pile stabilization platform that meets construction requirements;
[0010] S2. Ship in position:
[0011] The wind turbine installation vessel completes the ship positioning and leg standing at the designed machine position coordinates, so that the center of the guide hole coincides with the center of the pile foundation to meet the requirements for the jacket pile foundation sinking;
[0012] S3. Construction pile transport barge is in place:
[0013] The engineering pile transport barge slowly moved into position and berthed beside the wind turbine installation vessel by means of anchor boat-assisted anchoring and positioning;
[0014] S4. Engineering pile sinking operation:
[0015] The engineering pile transport barge is moved into position, and the main hook of the wind turbine installation ship crane completes the removal and erection of engineering piles, and the engineering piles are aligned by rotating the crane boom;
[0016] After the alignment is completed, the piles are inserted and self-sunk. During the self-sinking process, the surveyors monitor the verticality of the piles at any time. When the self-sinking is completed, the main hook lifting point is released. The main hook is used to lift the hydraulic hammer, and the rigging hook is used to lift the oil pipe to complete the pile sinking.
[0017] S5. Pile foundation embedded in rock construction:
[0018] After the piles are sunk, rock embedding is carried out. The rotary drilling rig is lifted by a crane hook for drilling operations. A mud processor is used for hole cleaning. After the drilling is completed, a steel cage is installed, and then mud air lift reverse circulation is used for secondary hole cleaning.
[0019] After the hole is cleaned, the concrete pouring is carried out using the pouring equipment and pumping equipment on the fan installation ship;
[0020] S6. Pile foundation hole cleaning and water replacement:
[0021] After the pile foundation pouring construction is completed, the water in the engineering pile is turbid. The muddy water in the engineering pile needs to be cleaned and replaced with clean water to ensure the water quality in the pile is clear. When cleaning the hole and changing the water, two pumps are used for operation. One pump extracts the muddy water in the pile out of the pile, and the other pumps clean seawater into the pile. When cleaning the hole and changing the water, the two pumps are not turned on at the same time. First, use one water pump to extract a part of the muddy water in the pile, and then use another water pump to inject clean seawater. Repeat the above steps until the water quality in the engineering pile is clear;
[0022] S7. Cutting and lifting of steel cage:
[0023] After the rock-embedded construction is completed, the underwater arc-oxygen cutting technology is used to allow divers to cut the underwater steel cage. The cut steel cage is lifted out of the engineering pile by a crane and stored on the transport barge;
[0024] S8. Underwater cutting construction of engineering piles:
[0025] After the steel cage is hoisted out, the main boom crane is used to hoist the underwater high-pressure jet cutting equipment to cut the underwater engineering piles;
[0026] S9. Hoisting of the cut section of engineering piles:
[0027] After the underwater cutting is completed, the main boom crane is used to lift the cut extension section of the engineering pile to the transport barge for storage;
[0028] S1 0, lowering the platform and moving the ship:
[0029] After the underwater cutting of all engineering piles is completed, the wind turbine installation ship lowers the platform to the water surface. After the platform is lowered to the water surface, the pile legs are pulled out. After the installation ship has retracted all the pile legs, it can move to the next machine position.
[0030] Furthermore, the step S1 also includes:
[0031] S1.1. According to the root width of the jacket pile foundation, the engineering pile sinking guide frames are welded on the ship's side on both sides of the ship, and a total of 4 guide frames are welded;
[0032] S1.2. Four hydraulic push cylinders are installed on each guide frame.
[0033] Furthermore, the step S2 also includes:
[0034] S2.1. The wind turbine installation vessel completes the ship positioning at the designed wind turbine position through the ship's own DP dynamic positioning system, and the centers of the guide holes of the four guide frames coincide with the pile centers of the jacket pile foundation;
[0035] S2.2. After the ship is positioned, the pile legs are lowered and lifted to complete the leg standing and lifting of the ship.
[0036] Furthermore, the step S4 also includes:
[0037] S4.1. Use the ship's main crane and auxiliary crane to lift, turn over and insert the engineering piles from the transport barge;
[0038] S4.2. After the bottom of the engineering pile passes through the guide hole of the construction platform smoothly, the on-site commander instructs the on-site personnel to use the jacking hydraulic cylinder on the guide frame platform to gradually adjust the verticality of the engineering pile according to the measurement feedback data. When the verticality meets the requirements, the hook is lowered to carry out the self-sinking operation of the engineering pile until the hook is no longer stressed and the hook lifting point is removed;
[0039] S4.3. After the self-sinking of the engineering pile is completed, the hammer pile sinking operation is then carried out. The final stop hammer elevation is calculated by back-calculating the measured elevation at the pile hole to obtain the hammer cap scale line corresponding to the engineering pile sinking to the design elevation; when the hammer cap scale line is flush with the measuring point, it is considered to have sunk to the design elevation;
[0040] S4.4. After the pile is sunk, weld the limit steel to fix the engineering pile at the position of the guide hole;
[0041] Furthermore, the step S5 also includes:
[0042] Rock-embedded construction converts offshore construction into onshore construction by placing rotary drilling and grouting system equipment on the installation ship platform and completing rock-embedded pile drilling and concrete pouring construction tasks based on the above equipment;
[0043] The rock-embedded drilling construction adopts the rotary drilling construction technology, and different drill bits are used for drilling in different strata. After the hole is formed, the hole is cleaned and the steel cage is installed after the sediment slurry index meets the requirements;
[0044] Then, the hole is cleaned for the second time by using mud air lift reverse circulation;
[0045] After the hole is cleaned, the concrete is poured using platform-mounted pouring equipment and pumping equipment. Sand, gravel, powder, etc. are mixed and configured on shore, then bagged, sealed and transported to the ship for storage. Water is added and stirred on site before pouring.
[0046] Furthermore, the step S7 also includes:
[0047] The steel cage is cut by underwater arc-oxygen cutting. During underwater cutting, divers will cut the steel cage from 2 to 3 meters above the hard surface of the pile foundation concrete to the top of the pile as a whole to facilitate the lifting of the steel cage. The cut steel cage is lifted out of the engineering pile by a crane and stored on the transport barge.
[0048] Furthermore, the step S9 also includes:
[0049] S9.1. After the underwater cutting of the engineering pile is completed, the slings for the extension of the engineering pile are installed. After the slings are hung, the crane hook belt force makes the lifting wire rope slightly straightened, and then the oxygen cutting gun is used to release the limit steel of the engineering pile at the temporary pile guide frame.
[0050] S9.2. After the limit steel is released, lift the long section of steel pipe pile. Pay attention to the lifting speed during the lifting process. When the pile body does not fluctuate much up and down, lift the steel pipe pile off the guide frame. Rotate the crane boom to lift the steel pipe pile onto the transport barge for storage.
[0051] The beneficial effects of the present invention are:
[0052] In view of the fact that the bottom of some wind turbine jacket pile foundation piles needs to be driven into fully weathered or strongly weathered granite gneiss during the construction of existing offshore wind power projects, the present invention uses the existing wind turbine installation ship as a rock-embedded pile stabilization platform to provide a safe, reliable and feasible construction method, which specifically has the following advantages:
[0053] (1) For existing wind turbine installation vessels, a guide frame for the jacket pile foundation is added to the side of the wind turbine installation vessel as a construction method for using the rock-embedded pile stabilization platform, thereby improving the utilization rate of existing ship resources and effectively reducing the investment in construction costs;
[0054] (2) The wind turbine installation vessel is used as the rock-embedded pile stabilization platform, and the ship's DP dynamic positioning system is used to complete the positioning operation at the wind turbine location; the pile legs of the wind turbine installation vessel are used as the positioning piles of the rock-embedded pile stabilization platform; the ship's own lifting equipment can be directly used, the construction process is simpler and faster, and has strong applicability, which can effectively shorten the construction period and improve the construction efficiency;
[0055] (3) Using the wind turbine installation vessel as a rock-embedded pile stabilization platform can ensure construction safety under normal working conditions and directly resist typhoons of level 15 or below under non-working conditions, thereby increasing construction safety.
[0056] (4) The wind turbine installation vessel is used as a rock-embedded pile stabilization platform, which has the functions of pile sinking and pile verticality adjustment.
[0057] (5) The wind turbine installation vessel is equipped with a complete power supply and water supply system to meet the requirements of on-site construction operations.
Brief Description of the Drawings
[0058] Figure 1 It is a process flow chart of the present invention;
[0059] Figure 2 is a top view of the installation of the guide frame of the wind turbine installation vessel in the present invention;
[0060] Figure 3 This is a front view of the installation of the guide frame of the wind turbine installation vessel in the present invention;
[0061] Figure 4 It is a schematic diagram of the ship in position in the present invention. [Specific implementation method]
[0062] The embodiments of the present invention are described in detail below, and examples of the embodiments are shown in the accompanying drawings, wherein the same or similar reference numerals throughout represent the same or similar parts or parts having the same or similar functions. The embodiments described below with reference to the accompanying drawings are exemplary and are intended to be used to explain the present invention, and should not be construed as limiting the present invention.
[0063] In the description of the present invention, unless otherwise clearly specified and limited, the terms "connected", "connected", and "fixed" should be understood in a broad sense, for example, it can be a fixed connection or a detachable connection, it can be a mechanical connection or an electrical connection, it can be a direct connection or an indirect connection through an intermediate medium, it can be the internal connection of two elements or the interaction relationship between two elements. For ordinary technicians in this field, the specific meanings of the above terms in the present invention can be understood according to specific circumstances.
[0064] In the description of the present invention, unless otherwise clearly specified and limited, a first feature being "above" or "below" a second feature may include the first feature being in direct contact with the second feature, or may include the first feature being in contact with the second feature through another feature between them instead of being in direct contact. Moreover, a first feature being "above", "above" and "above" a second feature includes the first feature being directly above and obliquely above the second feature, or simply indicates that the first feature is higher in level than the second feature. A first feature being "below", "below" and "below" a second feature includes the first feature being directly below and obliquely below the second feature, or simply indicates that the first feature is lower in level than the second feature.
[0065] In order to further understand the content, features and effects of the present invention, the following embodiments are given as examples and described in detail with reference to the accompanying drawings:
[0066] A foundation construction method for offshore special-shaped root-embedded rock jacket piles, such as Figure 1 As shown, the following steps are included:
[0067] S1. Preparation:
[0068] Transform the wind turbine installation vessel into a rock-embedded pile stabilization platform that meets construction requirements; Figure 2 and Figure 3 As shown, the specific steps are as follows:
[0069] S1.1. According to the root width of the jacket pile foundation, the engineering pile sinking guide frames are welded on the ship's side on both sides of the ship, and a total of 4 guide frames are welded 1;
[0070] S1.2, four hydraulic push cylinders 2 are installed on each guide frame 1;
[0071] S2. Ship in position:
[0072] The wind turbine installation vessel completes the ship positioning and leg standing at the designed machine position coordinates, so that the center of the guide hole coincides with the center of the pile foundation to meet the requirements of the jacket pile foundation sinking; Figure 4 As shown, the specific steps are as follows:
[0073] S2.1. The wind turbine installation vessel completes the ship positioning at the designed wind turbine position through the ship's own DP dynamic positioning system, and the centers of the guide holes of the four guide frames coincide with the pile centers of the jacket pile foundation;
[0074] S2.2. After the ship is positioned, the installation ship pile legs are lowered and lifted to complete the ship's leg standing and lifting;
[0075] S3. Construction pile transport barge is in place:
[0076] The engineering pile transport barge slowly moved into position and berthed beside the wind turbine installation vessel by means of anchor boat-assisted anchoring and positioning;
[0077] S4. Engineering pile sinking operation:
[0078] The engineering pile transport barge is moved into position, and the main hook of the wind turbine installation ship crane completes the removal and erection of engineering piles, and the engineering piles are aligned by rotating the crane boom;
[0079] After the alignment is completed, the piles are inserted and self-sunk. During the self-sinking process, the surveyors monitor the verticality of the piles at any time. When the self-sinking is completed, the main hook lifting point is released. The main hook is used to lift the hydraulic hammer, and the rigging hook is used to lift the oil pipe to complete the pile sinking. The specific steps are as follows:
[0080] S4.1. Use the ship's main crane and auxiliary crane to lift, turn over, erect and insert the engineering piles from the transport barge;
[0081] S4.2. After the bottom of the engineering pile passes through the guide hole of the construction platform smoothly, the on-site commander will instruct the on-site personnel to use the jacking hydraulic cylinder on the guide frame platform to gradually adjust the verticality of the engineering pile according to the measurement feedback data. After the verticality meets the requirements, the hook will be lowered to carry out the self-sinking operation of the engineering pile until the hook is no longer stressed, and then the hook lifting point will be removed;
[0082] S4.3. After the self-sinking of the engineering pile is completed, the hammer pile sinking operation is then carried out. The final stop hammer elevation is calculated by back-calculating the measured elevation at the pile hole to obtain the hammer cap scale line corresponding to the engineering pile sinking to the design elevation; when the hammer cap scale line is flush with the measuring point, it is considered to have sunk to the design elevation;
[0083] S4.4. After the pile is sunk, weld the limit steel to fix the engineering pile at the position of the guide hole;
[0084] S5. Pile foundation embedded in rock construction:
[0085] After the piles are sunk, rock embedding is carried out. The rotary drilling rig is lifted by a crane hook for drilling operations. A mud processor is used for hole cleaning. After the drilling is completed, a steel cage is installed, and then mud air lift reverse circulation is used for secondary hole cleaning.
[0086] After the hole is cleaned, the concrete pouring is carried out using the pouring equipment and pumping equipment on the fan installation ship;
[0087] In this step, unlike concrete mixing ships, rock-embedded construction converts offshore construction into onshore construction by placing equipment such as rotary drilling and grouting systems on the installation ship platform, and completing rock-embedded pile hole formation, concrete pouring and other construction tasks based on the above equipment; rock-embedded drilling construction adopts rotary drilling construction technology, and uses different drill bits for drilling in different strata. After the hole is formed, the hole is cleaned. After the sediment slurry index meets the requirements, the steel cage is installed, and then the mud gas lift reverse circulation is used for secondary hole cleaning; after the hole is cleaned, the pouring equipment and pumping equipment installed on the platform are used for concrete pouring. After the sand, gravel, powder, etc. are mixed and configured on shore, they are bagged and sealed and transported to the ship for storage, and poured after adding water and stirring on site;
[0088] S6. Pile foundation hole cleaning and water replacement:
[0089] After the pile foundation pouring construction is completed, the water in the engineering pile is turbid. The muddy water in the engineering pile needs to be cleaned and replaced with clean water to ensure the water quality in the pile is clear. When cleaning the hole and changing the water, two pumps are used for operation, one to extract the muddy water out of the pile, and the other to extract clean seawater into the pile; when cleaning the hole and changing the water, the two pumps are not turned on at the same time. First, use one water pump to extract part of the muddy water in the pile, and then use another water pump to inject clean seawater, and repeat the above steps until the water quality in the engineering pile is clear;
[0090] S7. Cutting and lifting of steel cage:
[0091] After the rock-embedded construction is completed, the underwater arc-oxygen cutting technology is used to allow divers to cut the underwater steel cage. The cut steel cage is lifted out of the engineering pile by a crane and stored on the transport barge;
[0092] In this step, the steel cage is cut by underwater arc-oxygen cutting. During underwater cutting, divers will cut the steel cage from 2 to 3 meters above the hard surface of the pile foundation concrete to the top of the pile as a whole to facilitate the lifting of the steel cage. The cut steel cage is lifted out of the engineering pile by a crane and stored on the transport barge.
[0093] S8. Underwater cutting construction of engineering piles:
[0094] After the steel cage is hoisted out, the main boom crane is used to hoist the underwater high-pressure jet cutting equipment to cut the underwater engineering piles.
[0095] The cutting of engineering piles adopts underwater high-pressure abrasive water jet cutting technology. The abrasive jet mode is post-mixed abrasive jet, and the abrasive is transported in dry transport. When the underwater cutting system is in operation, the high-pressure water supply equipment and the air compressor transmit the high-pressure water and abrasive to the internal cutting equipment through pipelines and independent sand supply hoses respectively. The two are combined to form a high-pressure abrasive water jet, which is then ejected through the nozzle to cut the engineering piles. The whole process requires precise coordination of various equipment in the underwater cutting system.
[0096] S9. Hoisting of the cut section of engineering piles:
[0097] After the underwater cutting is completed, the main boom crane is used to lift the cut extension section of the engineering pile to the transport barge for storage; the specific steps are as follows:
[0098] S9.1. After the underwater cutting of the engineering pile is completed, the slings for the extension of the engineering pile are installed. After the slings are hung, the crane hook belt force makes the lifting wire rope slightly straightened, and then the oxygen cutting gun is used to release the limit steel of the engineering pile at the temporary pile guide frame.
[0099] S9.2. After the limit steel is released, the long section of steel pipe pile is hoisted. During the hoisting process, pay attention to the hoisting speed. When the pile body does not fluctuate much, the steel pipe pile is hoisted off the guide frame. The crane rotates the boom to hoist the steel pipe pile onto the transport barge for storage.
[0100] S1 0, lowering the platform and moving the ship:
[0101] After the underwater cutting of all engineering piles is completed, the wind turbine installation ship lowers the platform to the water surface. After the platform is lowered to the water surface, the pile legs are pulled out. After the installation ship has retracted all the pile legs, it can move to the next machine position.
[0102] In this embodiment, for the existing wind turbine installation ship, a conductor frame pile foundation guide frame is added to the side of the wind turbine installation ship to be used as a rock-embedded pile stabilizing platform, and the ship's DP dynamic positioning system is used to complete the positioning operation at the wind turbine position, and the pile legs of the wind turbine installation ship are used as positioning piles of the rock-embedded pile stabilizing platform; the ship's own lifting equipment can be directly used, the construction process is simpler and faster, and the applicability is strong, which can effectively shorten the construction period and improve the construction efficiency; it can ensure construction safety under normal working conditions, and can directly resist typhoons of level 15 and below under non-working conditions, thereby increasing construction safety; and it has the functions of pile sinking operation of engineering piles and adjustment of the verticality of the pile body; it effectively shortens the construction period and improves construction efficiency.
[0103] The above-described embodiments are only preferred embodiments of the present invention and are not intended to limit the scope of implementation of the present invention. All equivalent changes made based on the shape, structure and principle of the present invention should be included in the protection scope of the present invention.
Claims
1. A foundation construction method for offshore special-shaped root-embedded rock jacket piles, characterized in that: The following steps are involved: S1. Preparation: Transform the wind turbine installation vessel into a rock-embedded pile stabilization platform that meets construction requirements; S2. Ship in position: The wind turbine installation vessel completes the ship positioning and leg standing at the designed machine position coordinates, so that the center of the guide hole coincides with the center of the pile foundation to meet the requirements of the jacket pile foundation sinking; S3. Construction pile transport barge is in place: The engineering pile transport barge slowly moved into position and berthed beside the wind turbine installation vessel by means of anchor boat-assisted anchoring and positioning; S4. Engineering pile sinking operation: The engineering pile transport barge is moved into position, and the main hook of the wind turbine installation ship crane completes the removal and erection of engineering piles, and the engineering piles are aligned by rotating the crane boom; After the alignment is completed, the piles are inserted and self-sunk. During the self-sinking process, the surveyors monitor the verticality of the piles at any time. When the self-sinking is completed, the main hook lifting point is released. The main hook is used to lift the hydraulic hammer, and the rigging hook is used to lift the oil pipe to complete the pile sinking. S5. Pile foundation embedded in rock construction: After the piles are sunk, rock embedding is carried out. The rotary drilling rig is lifted by a crane hook for drilling operations. A mud processor is used for hole cleaning. After the drilling is completed, a steel cage is installed, and then mud air lift reverse circulation is used for secondary hole cleaning. After the hole is cleaned, the concrete pouring is carried out using the pouring equipment and pumping equipment on the fan installation ship; S6. Pile foundation hole cleaning and water replacement: After the pile foundation pouring construction is completed, the water in the engineering pile is turbid. The muddy water in the engineering pile needs to be cleaned and replaced with clean water to ensure the water quality in the pile is clear. When cleaning the hole and changing the water, two pumps are used for operation. One pump extracts the muddy water in the pile out of the pile, and the other pumps clean seawater into the pile. When cleaning the hole and changing the water, the two pumps are not turned on at the same time. First, use one water pump to extract a part of the muddy water in the pile, and then use another water pump to inject clean seawater. Repeat the above steps until the water quality in the engineering pile is clear; S7. Cutting and lifting of steel cage: After the rock-embedded construction is completed, the underwater arc-oxygen cutting technology is used to allow divers to cut the underwater steel cage. The cut steel cage is lifted out of the engineering pile by a crane and stored on the transport barge; S8. Underwater cutting construction of engineering piles: After the steel cage is hoisted out, the main boom crane is used to hoist the underwater high-pressure jet cutting equipment to cut the underwater engineering piles; S9. Hoisting of the cut section of engineering piles: After the underwater cutting is completed, the main boom crane is used to lift the cut extension section of the engineering pile to the transport barge for storage; S10, lowering the platform and moving the ship: After the underwater cutting of all engineering piles is completed, the wind turbine installation ship lowers the platform to the water surface. After the platform is lowered to the water surface, the pile legs are pulled out. After the installation ship has retracted all the pile legs, it can move to the next machine position.
2. The foundation construction method of an offshore special-shaped root rock-embedded jacket pile according to claim 1, characterized in that: The step S1 also includes: S1.
1. According to the root width of the jacket pile foundation, the engineering pile sinking guide frames are welded on the ship's side on both sides of the ship, and a total of 4 guide frames are welded; S1.
2. Install 4 hydraulic push cylinders on each guide frame.
3. The foundation construction method of an offshore special-shaped root rock-embedded jacket pile according to claim 1, characterized in that: The step S2 also includes: S2.
1. The wind turbine installation vessel completes the ship positioning at the designed wind turbine position through the ship's own DP dynamic positioning system, and the centers of the guide holes of the four guide frames coincide with the pile centers of the jacket pile foundation; S2.
2. After the ship is positioned, the pile legs are lowered and lifted to complete the leg standing and lifting of the ship.
4. The foundation construction method of an offshore special-shaped root rock-embedded jacket pile according to claim 1, characterized in that: The step S4 also includes: S4.
1. Use the ship's main crane and auxiliary crane to lift, turn over and insert the engineering piles from the transport barge; S4.
2. After the bottom of the engineering pile passes through the guide hole of the construction platform smoothly, the on-site commander instructs the on-site personnel to use the jacking hydraulic cylinder on the guide frame platform to gradually adjust the verticality of the engineering pile according to the measurement feedback data. When the verticality meets the requirements, the hook is lowered to carry out the self-sinking operation of the engineering pile until the hook is no longer stressed and the hook lifting point is removed; S4.
3. After the self-sinking of the engineering pile is completed, the hammer pile sinking operation is then carried out. The final stop hammer elevation is calculated by back-calculating the measured elevation at the pile hole to obtain the hammer cap scale line corresponding to the engineering pile sinking to the design elevation; when the hammer cap scale line is flush with the measuring point, it is considered to have sunk to the design elevation; S4.
4. After the piles are sunk, limit steel is welded at the guide hole to fix the engineering piles.
5. The foundation construction method of offshore special-shaped root rock-embedded jacket piles according to claim 1, characterized in that: The step S5 also includes: Rock-embedded construction converts offshore construction into onshore construction by placing rotary drilling and grouting system equipment on the installation ship platform and completing rock-embedded pile drilling and concrete pouring construction tasks based on the above equipment; The rock-embedded drilling construction adopts the rotary drilling construction technology, and different drill bits are used for drilling in different strata. After the hole is formed, the hole is cleaned and the steel cage is installed after the sediment slurry index meets the requirements; Then, the hole is cleaned for the second time by using mud air lift reverse circulation; After the hole is cleaned, the concrete is poured using platform-mounted pouring equipment and pumping equipment. Sand, gravel, powder, etc. are mixed and configured on shore, then bagged, sealed and transported to the ship for storage. Water is added and stirred on site before pouring.
6. The foundation construction method of offshore special-shaped root rock-embedded jacket piles according to claim 1, characterized in that: The step S7 also includes: The steel cage is cut by underwater arc-oxygen cutting. During underwater cutting, divers will cut the steel cage from 2 to 3 meters above the hard surface of the pile foundation concrete to the top of the pile as a whole to facilitate the lifting of the steel cage. The cut steel cage is lifted out of the engineering pile by a crane and stored on the transport barge.
7. The foundation construction method of offshore special-shaped root rock-embedded jacket piles according to claim 1, characterized in that: The step S9 also includes: S9.
1. After the underwater cutting of the engineering pile is completed, the slings for the extension of the engineering pile are installed. After the slings are hung, the crane hook belt force makes the lifting wire rope slightly straightened, and then the oxygen cutting gun is used to release the limit steel of the engineering pile at the temporary pile guide frame. S9.
2. After the limit steel is released, lift the long section of steel pipe pile. Pay attention to the lifting speed during the lifting process. When the pile body does not fluctuate much up and down, lift the steel pipe pile off the guide frame. Rotate the crane boom to lift the steel pipe pile onto the transport barge for storage.
Citation Information
Cited By
Offshore cutting method for barrel type foundation structure and implementation device of offshore cutting method
CN120139214A
Method for offshore cutting of a bucket foundation and an implementation thereof
CN120139214B
Rock-socketed raking pile reinforcement cage guide frame and construction method
CN120575575A