JPCCP state intelligent monitoring system and construction regulation and control method
By arranging multiple sensors in key areas of the JPCCP pipeline and uploading data wirelessly, a construction status prediction model is established, and the problem of insufficient parameter measurement difficulty and monitoring during the jacking process of JPCCP pipeline is solved, and intelligent control and safety of the jacking process is realized. Sex improvement.
Patent Information
- Application Number
- CN202411205577.6
- Authority / Receiving Office
- CN · China
- Patent Type
- Applications(China)
- Current Assignee / Owner
- Filing Date
- 2024-08-30
- Publication Date
- 2024-11-29
AI Technical Summary
During the jacking process, it is difficult to measure parameters of JPCCP pipelines, and traditional monitoring methods fail to effectively monitor the status of the pipeline, affecting construction efficiency and safety.
Design a JPCCP pipeline state intelligent monitoring system, by laying a variety of sensors at the bearing end, middle of the pipe body and socket end of the pipe, including soil pressure gauge, pore water pressure gauge, outer protective layer concrete strain gauge, wire strain gauge and The medium-layer strain gauge of die concrete uses wireless transmission to upload data to the cloud platform, establish a construction status prediction model, and realize intelligent regulation of the pinch process.
Real-time monitoring of JPCCP pipeline multi-parameters is realized, the impact of sensor layout on pipeline structural performance is reduced, construction efficiency and safety is improved, and the intelligent and informatization development of pipe jacking projects is promoted.
Smart Images

Figure CN119042407A_ABST
Abstract
Description
Technical Field
[0001] The present invention belongs to the field of trenchless underground construction engineering, and in particular relates to a JPCCP pipeline state intelligent monitoring system and a construction control method. Background Art
[0002] Traditionally, prestressed concrete cylinder pipe (PCCP) is laid in trenches, but using this method in key areas such as cities with deep burial depths and complex environments will dramatically increase social and economic costs. Therefore, in order to solve the installation problem of large-section PCCP, engineers have integrated efficient, safe, and environmentally friendly jacking methods to transform PCCP into JPCCP (prestressed concrete cylinder jacking pipe), which can be jacked. This can give full play to the respective advantages of PCCP and jacking method, and better meet the needs of urbanization development. Compared with traditional reinforced concrete jacking pipe (DRCP), JPCCP pipe has higher load-bearing and pressure-maintaining capacity, with a maximum diameter of 4000mm and a maximum internal pressure of more than 2.0MPa. It is currently receiving widespread attention in China's pipeline construction field.
[0003] For pipe jacking projects, jacking force control and grouting control are key factors affecting jacking efficiency. Excessive jacking force will also affect the safety of the pipeline structure. Therefore, the actual construction process requires accurate control of the pipeline jacking status. As a modified PCCP pipe for pipe jacking, the JPCCP pipe is a typical composite pipe, consisting of a five-layer structure, and structures such as steel cylinders and prestressed steel wires are not allowed to be destroyed as required. Therefore, it is difficult to measure the parameters of the JPCCP pipeline during the jacking process. At the same time, JPCCP pipes are generally used for large-diameter water supply and drainage pipelines. The durability and pressure resistance of the pipeline are closely related to the pipeline status during the jacking construction process. The status monitoring and analysis of the pipeline during the jacking process is indispensable.
[0004] In view of the current research gap in JPCCP pipe monitoring methods, the present invention proposes a JPCCP pipeline status intelligent monitoring system and construction control method based on measured multivariate data, which can monitor the stress and deformation of various important structures of the pipeline in real time, and through structural design modification, minimize the impact of sensor layout on pipeline structural performance. The data acquisition system uploads the measured data to the cloud platform in real time via wireless transmission, which is convenient for the staff to accurately adjust the jacking status and realize intelligent control of JPCCP jacking. The present invention has a very high driving significance for the development of JPCCP pipe intelligent monitoring and control technology. Summary of the invention
[0005] In order to achieve the above-mentioned purpose, the technical solution provided by the present invention is: a JPCCP pipeline state intelligent monitoring system, the JPCCP pipe includes at least an outer protective layer of concrete, structural steel bars, prestressed steel wires, a pipe core concrete middle layer, a steel cylinder, a pipe core concrete inner layer and a socket steel ring from the outside to the inside, and the layout method is as follows:
[0006] Step 1. Distribution of monitoring system: The monitoring system includes three monitoring areas along the longitudinal direction of the pipe body, namely, the socket end, the middle part of the pipe body, and the spigot end; the required sensors include at least soil pressure gauges, pore water pressure gauges, outer protective layer concrete strain gauges, steel wire strain gauges, pipe core concrete middle layer strain gauges, steel cylinder strain gauges, and pipe core concrete inner layer surface strain gauges; the soil pressure gauges and pore water pressure gauges are only arranged in the two areas of the socket end and the spigot end, the steel cylinder strain gauges and pipe core concrete inner layer surface strain gauges are only arranged in the two areas of the middle part of the pipe body and the spigot end, and the outer protective layer concrete strain gauges, steel wire strain gauges, and pipe core concrete middle layer strain gauges are arranged in all three areas;
[0007] Step 2. Installation of steel wire strain gauge and steel cylinder strain gauge: Attach steel wire strain gauge and steel cylinder strain gauge to the surface of the prestressed steel wire and steel cylinder respectively;
[0008] Step 3. Installation of the outer protective layer concrete strain gauge and the pipe core concrete middle layer strain gauge: Before pouring the outer protective layer concrete and the pipe core concrete middle layer, use positioning steel bars or ropes to fix the outer protective layer concrete strain gauge to the middle position of the outer protective layer concrete layer, and fix the pipe core concrete middle layer strain gauge to the middle position of the pipe core concrete layer, and then pour to form the outer protective layer concrete and the pipe core concrete middle layer;
[0009] Step 4. Installation of earth pressure gauge and pore water pressure gauge: The earth pressure gauge and pore water pressure gauge are respectively arranged in the outer protective layer concrete. Specifically, the earth pressure gauge and pore water pressure gauge are installed when the outer protective layer concrete is poured for the second time and the end faces of the earth pressure gauge and pore water pressure gauge are flush with the outer surface of the pipe body; before the second pouring, the end faces of the earth pressure gauge and pore water pressure gauge are protected with waterproof materials, and the corresponding protective materials are removed after the second pouring is completed;
[0010] Step 5. Installation of the strain gauge on the inner surface of the core concrete layer: Install the strain gauge on the inner surface of the core concrete layer, i.e., the inner surface of the pipe body;
[0011] Step 6. Installation of sensor signal lines: 4 to 8 grouting holes are arranged in a circular manner on the socket steel ring, and the grouting holes are designed to allow the signal lines to pass through. The signal extension lines of all sensors are extended to the socket end and then arranged through the grouting holes to the inside of the JPCCP pipe through the wiring design; after the signal extension line passes through the grouting hole, the grouting hole is filled with quick-setting concrete to block the gap;
[0012] Step 7: The signal extension line entering the interior is fixed on the inner surface of the pipe body and connected to a network IO data acquisition instrument, which includes at least a main controller, a measurement module, a wiring port and a battery device; the network IO data acquisition instrument transmits the signal to the starting well, which is also provided with a roller meter.
[0013] Moreover, the earth pressure gauge, pore water pressure gauge, outer protective layer concrete strain gauge, steel wire strain gauge and pipe core concrete middle layer strain gauge at the socket end in step 1 are located in the same cross section of the JPCCP pipe; the steel cylinder strain gauge, pipe core concrete inner layer surface strain gauge, outer protective layer concrete strain gauge, steel wire strain gauge and pipe core concrete middle layer strain gauge in the middle of the pipe body are located in the same cross section of the JPCCP pipe; the earth pressure gauge, pore water pressure gauge, steel cylinder strain gauge, pipe core concrete inner layer surface strain gauge, outer protective layer concrete strain gauge, steel wire strain gauge and pipe core concrete middle layer strain gauge at the spigot end are located in the same cross section of the JPCCP pipe.
[0014] Moreover, the soil pressure gauge and pore water pressure gauge in step 3 and the strain gauge on the inner surface of the core concrete in step 4 are installed using a base, and the base is fastened to the concrete surface of the corresponding layer by expansion bolts or screws.
[0015] Moreover, in step 7, the signals of the network IO data acquisition instrument and the roller meter are transmitted wirelessly to the data control terminal and the intelligent Internet of Things cloud platform.
[0016] Moreover, before installing the socket joint, first install two sealing rubber rings at the socket steel ring, and install a double-layer wooden pad at the socket end; and there is an offset gap between the double-layer wooden pads, and a gap between the wooden pads and the socket ring. The signal extension line described in step 6 passes through the offset gap of the double-layer wooden pads and the gap between the wooden pads and the socket ring at the socket end face, and then passes through the grouting hole.
[0017] And the construction control method of the JPCCP pipeline status intelligent monitoring system: the jacking status data and pipeline status data of the JPCCP pipe obtained by the sensor are wirelessly transmitted to the cloud platform and the data control terminal via the data acquisition instrument, and a construction status prediction model is established. Under the support of the cloud platform algorithm, the prediction model is iterated with the calculation of the first section of the main monitoring pipe, and the prediction model is improved with more data from subsequent pipe sections. During the construction process, the jacking cylinder and grouting pump control, pipeline jacking force and graded grouting drag reduction are regulated according to the data; the jacking status data of the JPCCP pipe at least includes jacking force, jacking distance and jacking speed, and the pipeline status data at least includes water and soil pressure around the pipe, steel wire deformation, steel cylinder deformation and three-layer concrete deformation
[0018] Compared with the prior art, the beneficial effects of this technical solution are:
[0019] (1) An intelligent monitoring system for pipeline parameters of large-diameter JPCCP pipes is proposed. By designing and installing different sensors in three monitoring areas, namely, the socket end, the middle of the pipe body, and the spigot end, multiple parameters including water and soil pressure around the pipe, deformation of steel wires, deformation of steel cylinders, and deformation of three layers of concrete are monitored. Specific instrument types, layout schemes, data processing methods, layout and wiring schemes for extending signal extension lines to the inside of the pipe, and socket joint structures are provided to minimize the impact of sensor layout on pipeline structural performance;
[0020] (2) A prediction model and control method for the long-distance pipe jacking construction status are proposed. All monitoring data are wirelessly transmitted to the cloud platform for integrated analysis. A multivariate measured data network analysis and prediction framework is established to facilitate the staff to control the oil pressure of the jacking cylinder and graded grouting in each monitoring section to achieve intelligent control of JPCCP pipe jacking.
[0021] (3) In line with the current development trend of smart engineering, the key parameters of the pipe jacking construction process are collected in real time, and combined with the cloud platform big data analysis and prediction, it has the characteristics of fast, efficient, high precision, digital automation, etc., promoting the intelligent, information-based, and refined development of the pipe jacking engineering field.
[0022] (4) A method for installing the outer protective layer concrete strain gauge and the pipe core concrete middle layer strain gauge is provided: before pouring the outer protective layer concrete and the pipe core concrete middle layer, positioning steel bars or ropes are used to fix them in the middle position of the concrete of the corresponding layer, and then pouring is performed to form the outer protective layer concrete and the pipe core concrete middle layer to achieve this purpose.
[0023] (5) The installation method of the earth pressure gauge and the pore water pressure gauge is provided: the earth pressure gauge and the pore water pressure gauge are installed during the secondary pouring of the outer protective layer concrete. Before the secondary pouring, the end faces of the earth pressure gauge and the pore water pressure gauge are protected with waterproof materials. After the secondary pouring is completed, the corresponding protective materials are removed. The end face of the sensor is as flush as possible with the outer surface of the pipe section to avoid damage to the sensor caused by the sensing end protruding from the surface.
[0024] (6) A method for installing the sensor signal line is provided: 4 to 8 grouting holes are arranged in a circular manner on the socket steel ring, and the grouting holes are designed to allow the signal line to pass through, and the signal extension lines of all sensors are extended to the socket end and then gathered through the grouting holes to the inside of the JPCCP pipe through the wiring design; after the signal extension line passes through the grouting hole, the grouting hole is filled with quick-setting concrete to block the gap. This can ensure that the prestressed steel wire and steel cylinder are not damaged, and the signal line can be extended to the inside of the JPCCP pipe, which is convenient for data transmission to the outside. BRIEF DESCRIPTION OF THE DRAWINGS
[0025] Attached Figure 1 It is a schematic diagram of the JPCCP structure;
[0026] Attached Figure 2 To monitor the longitudinal section of the pipe segment;
[0027] Attached Figure 3 To monitor the cross-section of the pipe segment;
[0028] Attached Figure 4 This is the JPCCP joint installation diagram;
[0029] Attached Figure 5 It is a three-dimensional layout diagram of the wooden pad;
[0030] Attached Figure 6 This is the cross-section layout of the wooden pad;
[0031] Attached Figure 7 This is a schematic diagram of the intelligent monitoring system for pipe jacking;
[0032] Attached Figure 8 Schematic diagram of the intelligent monitoring system and control method provided by the present invention
[0033] Explanation of the accompanying drawings: 1-external protective layer concrete, 2-structural steel bars, 3-prestressed steel wire, 4-middle layer of tube core concrete, 5-steel cylinder, 6-inner layer of tube core concrete, 7-socket steel ring, 8-pressure test hole, 9-grouting hole, 10-socket steel ring, 11-wooden pad, 12-soil pressure gauge, 13-pore water pressure gauge, 14-external protective layer concrete strain gauge, 15-steel wire strain gauge, 16-middle layer of tube core concrete strain gauge, 17-steel cylinder strain gauge, 18-surface strain gauge of inner layer of tube core concrete, 19-signal extension line, 20-sealing rubber ring, 21-offset gap of double-layer wooden pad, 22-gap between wooden pad and socket ring, 23-quick-setting concrete, 24-support frame, 25-network IO data acquisition instrument, 26-roller meter, 27-data control terminal, 28-intelligent Internet of Things cloud platform, 29-jacking cylinder, 30-grouting pump. DETAILED DESCRIPTION
[0034] The present invention is described in detail below with reference to the accompanying drawings and embodiments, but the content of the present invention is not limited to the following embodiments.
[0035] JPCCP is a new type of prestressed steel cylinder concrete jacking pipe based on the PCCP pipe modification. Its structural diagram is shown in the figure below. Figure 1 As shown in the figure, the basic components of the JPCCP pipe include an outer protective layer of concrete 1, structural steel bars 2, prestressed steel wires 3, a pipe core concrete middle layer 4, a steel tube 5, a pipe core concrete inner layer 6, a socket steel ring 7, a pressure test hole 8, a grouting hole 9, and a socket steel ring 10. The structural steel bars improve the axial bearing capacity of the JPCCP pipe, and 4 to 8 grouting holes are arranged circumferentially on the socket steel ring 7, which can facilitate lubrication and drag reduction grouting and secondary grouting during the JPCCP jacking process.
[0036] A JPCCP pipeline state intelligent monitoring system, the JPCCP pipe from the outside to the inside at least includes an outer protective layer of concrete, structural steel bars, prestressed steel wires, a pipe core concrete middle layer, a steel cylinder, a pipe core concrete inner layer and a socket steel ring, the layout method is as follows:
[0037] Step 1. Distribution of monitoring system: The monitoring system includes three monitoring areas along the longitudinal direction of the pipe body, namely, the socket end, the middle part of the pipe body, and the spigot end; the required sensors include at least soil pressure gauges, pore water pressure gauges, outer protective layer concrete strain gauges, steel wire strain gauges, pipe core concrete middle layer strain gauges, steel cylinder strain gauges, and pipe core concrete inner layer surface strain gauges; the soil pressure gauges and pore water pressure gauges are only arranged in the two areas of the socket end and the spigot end, the steel cylinder strain gauges and pipe core concrete inner layer surface strain gauges are only arranged in the two areas of the middle part of the pipe body and the spigot end, and the outer protective layer concrete strain gauges, steel wire strain gauges, and pipe core concrete middle layer strain gauges are arranged in all three areas;
[0038] Step 2. Installation of steel wire strain gauge and steel cylinder strain gauge: Attach steel wire strain gauge and steel cylinder strain gauge to the surface of the prestressed steel wire and steel cylinder respectively;
[0039] Step 3. Installation of the outer protective layer concrete strain gauge and the pipe core concrete middle layer strain gauge: Before pouring the outer protective layer concrete and the pipe core concrete middle layer, use positioning steel bars or ropes to fix the outer protective layer concrete strain gauge to the middle position of the outer protective layer concrete layer, and fix the pipe core concrete middle layer strain gauge to the middle position of the pipe core concrete layer, and then pour to form the outer protective layer concrete and the pipe core concrete middle layer;
[0040] Step 4. Installation of earth pressure gauge and pore water pressure gauge: The earth pressure gauge and pore water pressure gauge are respectively arranged in the outer protective layer concrete. Specifically, the earth pressure gauge and pore water pressure gauge are installed when the outer protective layer concrete is poured for the second time and the end faces of the earth pressure gauge and pore water pressure gauge are flush with the outer surface of the pipe body; before the second pouring, the end faces of the earth pressure gauge and pore water pressure gauge are protected with waterproof materials, and the corresponding protective materials are removed after the second pouring is completed;
[0041] Step 5. Installation of the strain gauge on the inner surface of the core concrete layer: Install the strain gauge on the inner surface of the core concrete layer, i.e., the inner surface of the pipe body;
[0042] Step 6. Installation of sensor signal lines: 4 to 8 grouting holes are arranged in a circular manner on the socket steel ring, and the grouting holes are designed to allow the signal lines to pass through. The signal extension lines of all sensors are extended to the socket end and then arranged through the grouting holes to the inside of the JPCCP pipe through the wiring design; after the signal extension line passes through the grouting hole, the grouting hole is filled with quick-setting concrete to block the gap;
[0043] Step 7: The signal extension line entering the interior is fixed on the inner surface of the pipe body and connected to a network IO data acquisition instrument, which includes at least a main controller, a measurement module, a wiring port and a battery device; the network IO data acquisition instrument transmits the signal to the starting well, which is also provided with a roller meter.
[0044] The structure of the embodiment obtained according to the above arrangement method is as follows:
[0045] A JPCCP pipeline status intelligent monitoring system, the longitudinal section diagram of the monitoring pipe segment is as follows Figure 2 As shown, the main monitoring items of this system include the annular and axial strains of the concrete layer and the steel tube 5, the annular strain of the prestressed steel wire 3, the water and soil pressure around the pipe, etc. The selected sensors include the soil pressure gauge 12, the pore water pressure gauge 13, the outer protective layer concrete strain gauge 14, the steel wire strain gauge 15, the pipe core concrete middle layer strain gauge 16, the steel tube strain gauge 17 and the pipe core concrete inner layer surface strain gauge 18. Figure 2 The monitoring system in the longitudinal section is divided into three sections along the longitudinal direction of the pipe body, namely the bell end, the middle part of the pipe body, and the spigot end. Among them, the earth pressure gauge 12 and the pore water pressure gauge 13 are only arranged in two sections, namely the bell end and the spigot end, the steel tube strain gauge 17 and the pipe core concrete inner layer surface strain gauge 18 are only arranged in two sections, namely the middle part of the pipe body and the spigot end. Other types of sensors are arranged in the three sections. Each sensor is connected to the spigot end of the pipe section through a signal extension line 19, and is aggregated through a specially designed grouting hole 9 for passing the signal line to the inside of the pipeline.
[0046] The outer protective layer concrete strain gauge 14 and the tube core concrete middle layer strain gauge 16 are respectively located in the middle of the corresponding layer of concrete. Before pouring concrete, the strain gauge can be placed in the corresponding position by positioning steel bars or ropes, and the strain gauge is fixed in the pouring process to prevent damage during the pouring process. The steel wire strain gauge 15 and the steel cylinder strain gauge 17 are respectively pasted on the surface of the prestressed steel wire 3 and the steel cylinder 5. Here, the sensor can not only use strain gauges, but also distributed optical fibers, etc. for replacement. The specific selection can be based on economic cost, installation difficulty, test needs, etc. The tube core concrete inner layer surface strain gauge 18 can be installed on the inner surface using a base, and the base is fastened to the inner surface of the concrete by expansion bolts or screws. The earth pressure gauge 12 and the pore water pressure gauge 13 are respectively arranged in the outer protective layer concrete 1 in the same direction of the strain gauge. When the layer of concrete is poured for the second time, the two types of sensors are installed to the base position, and the sensor end faces are protected with waterproof materials such as foam before pouring. After the pouring is completed, the corresponding protective materials are removed. The sensor end faces are as flush as possible with the outer surface of the pipe section to avoid sensor bumps and damage caused by the sensing end protruding from the surface.
[0047] Figure 3The figure shows a cross-sectional view of the monitoring pipe segment. The orientation and number of the sensor ring can be set according to the pipe diameter. Generally, 4 to 8 sensors are arranged. The principle followed is that the sensor arrangement will not affect the safety and stability of the overall structural performance of the pipeline. Due to the complex structure of the JPCCP, the prestressed steel wire 3 and the steel cylinder 5 are not allowed to be damaged. Therefore, the signal extension line 19 of the sensor needs to be extended to the end face of the socket in each concrete layer and passed through the interior of the pipe through a wiring design. Therefore, the grouting holes 9 of the test pipe can be increased by 1 to 4 on top of the standard number, and the increased grouting holes 9 can be used as the signal extension line 19 to pass through the hole. Figure 3 As shown, the signal extension lines 19 of the adjacent longitudinal monitoring end faces can share a grouting hole 9, and the unactivated grouting hole 9 is still used for grouting during the jacking process. After the signal extension line 19 passes through the grouting hole 9, the grouting hole 9 is filled with quick-setting concrete 23 to block the gap to avoid the influence of high water pressure when deeply buried.
[0048] The signal extension line 19 entering the pipe is fixedly wound around the inner surface of the pipe to the network IO data acquisition instrument 25. The network IO data acquisition instrument 25 is a box structure, located on the support frame 24 to avoid collision during construction; the network IO data acquisition instrument 25 mainly includes a main controller, a measurement module, a wiring port and a battery device, which can work for a certain period of time under power-off conditions; the instrument can not only collect sensor data, but also has a wireless transmission function to transmit various analog signals to the starting well. Figure 7 The figure shows a schematic diagram of the intelligent monitoring system for pipe jacking. The first monitoring pipe section is as close to the pipe jacking machine head as possible, and the number and position of subsequent monitoring pipe sections can be set in multiple sections according to the jacking length. A roller meter 26 is arranged above the pipe section near the hole position of the starting well to record the jacking length and speed of the jacking pipe; the signals of the network IO data acquisition instrument 25 and the roller meter 26 can be wirelessly transmitted to the data control terminal 27 and the intelligent Internet of Things cloud platform 28. The cloud platform 28 can use Alibaba Cloud IoT, Tencent Cloud IoT, Baidu Cloud IoT, etc., and receive different types of network signals such as WiFi, Ethernet, 4G, GPRS, etc. Through the control terminal 27 and the cloud platform 28, the staff can conduct a comprehensive analysis of the measured data of each monitoring pipe section; after analysis, the staff can control the jacking cylinder 29 and the grouting pump 30 to control the jacking force and grouting pressure / grouting volume.
[0049] Furthermore, when the socket joint is installed, two sealing rubber rings 20 need to be installed at the socket steel ring 7, and a wooden pad 11 needs to be installed at the socket end. Figure 4 As shown, the wooden pad 11 is a double-layer wooden pad, and passes through the grouting hole 9 at the end face of the socket through the double-layer wooden pad offset gap 21 and the gap 22 between the wooden pad and the socket ring. The three-dimensional layout of the wooden pad and the cross-sectional layout of the wooden pad are shown in Figures 1 and 2. Figure 5 and Figure 6As shown, in order to avoid the influence of the pressure surface of the socket joint on the sensor signal extension line 19, the position of the double-layer wooden pad 11 can be reasonably configured to leave a gap or a guide groove to facilitate the output of the signal extension line 19.
[0050] Figure 8 The figure shows a flow chart of the construction control method of the intelligent monitoring system. The jacking status (jacking force, jacking distance and jacking speed, etc.) and pipeline status (water and soil pressure around the pipe, steel wire deformation, steel tube deformation and three-layer concrete deformation, etc.) of the JPCCP pipe can be wirelessly transmitted to the cloud platform and data control terminal by each monitoring pipe / test pipe through a data acquisition instrument (network IO data acquisition instrument and roller meter). The staff can control the status of each monitoring pipe and the status of the entire pipeline according to the jacking status and pipeline status. At the same time, the construction personnel can judge the conditions of different jacking sections according to each monitoring pipe, establish a construction status prediction model, and with the support of the cloud platform algorithm, the prediction model is calculated and iterated with the first section of the main monitoring pipe, and optimized and improved with more data from subsequent pipe sections, making the prediction model more accurate and efficient. Finally, during the construction process, the jacking cylinder and grouting pump can be adjusted according to actual needs to achieve pipeline jacking force control and graded grouting resistance reduction.
Claims
1. A JPCCP pipeline status intelligent monitoring system, the JPCCP pipe from the outside to the inside at least includes an outer protective layer of concrete, structural steel bars, prestressed steel wires, a pipe core concrete middle layer, a steel cylinder, a pipe core concrete inner layer and a socket steel ring, characterized in that The layout method is as follows: Step 1. Distribution of monitoring system: The monitoring system includes three monitoring areas along the longitudinal direction of the pipe body, namely, the socket end, the middle part of the pipe body, and the spigot end; the required sensors include at least an earth pressure gauge, a pore water pressure gauge, an outer protective layer concrete strain gauge, a steel wire strain gauge, a pipe core concrete middle layer strain gauge, a steel cylinder strain gauge, and a pipe core concrete inner layer surface strain gauge; Among them, the earth pressure gauge and pore water pressure gauge are only arranged in the two areas of the socket end and the spigot end, the steel tube strain gauge and the inner surface strain gauge of the pipe core concrete are only arranged in the middle of the pipe body and the spigot end, and the outer protective layer concrete strain gauge, steel wire strain gauge and pipe core concrete middle layer strain gauge are arranged in all three areas; Step 2. Installation of steel wire strain gauge and steel cylinder strain gauge: Attach steel wire strain gauge and steel cylinder strain gauge to the surface of the prestressed steel wire and steel cylinder respectively; Step 3. Installation of the outer protective layer concrete strain gauge and the pipe core concrete middle layer strain gauge: Before pouring the outer protective layer concrete and the pipe core concrete middle layer, use positioning steel bars or ropes to fix the outer protective layer concrete strain gauge to the middle position of the outer protective layer concrete layer, and fix the pipe core concrete middle layer strain gauge to the middle position of the pipe core concrete layer, and then pour to form the outer protective layer concrete and the pipe core concrete middle layer; Step 4. Installation of earth pressure gauge and pore water pressure gauge: The earth pressure gauge and pore water pressure gauge are respectively arranged in the outer protective layer concrete. Specifically, the earth pressure gauge and pore water pressure gauge are installed when the outer protective layer concrete is poured for the second time and the end faces of the earth pressure gauge and pore water pressure gauge are flush with the outer surface of the pipe body; before the second pouring, the end faces of the earth pressure gauge and pore water pressure gauge are protected with waterproof materials, and the corresponding protective materials are removed after the second pouring is completed; Step 5. Installation of the strain gauge on the inner surface of the core concrete layer: Install the strain gauge on the inner surface of the core concrete layer, i.e., the inner surface of the pipe body; Step 6. Installation of sensor signal lines: 4 to 8 grouting holes are arranged in a circular manner on the socket steel ring, and the grouting holes are designed to allow the signal lines to pass through. The signal extension lines of all sensors are extended to the socket end and then arranged through the grouting holes to the inside of the JPCCP pipe through the wiring design; after the signal extension line passes through the grouting hole, the grouting hole is filled with quick-setting concrete to block the gap; Step 7: The signal extension line entering the interior is fixed on the inner surface of the pipe body and connected to a network IO data acquisition instrument, which includes at least a main controller, a measurement module, a wiring port and a battery device; the network IO data acquisition instrument transmits the signal to the starting well, which is also provided with a roller meter.
2. According to claim 1, a JPCCP pipeline status intelligent monitoring system is characterized by: In step 1, the earth pressure gauge, pore water pressure gauge, outer protective layer concrete strain gauge, steel wire strain gauge and pipe core concrete middle layer strain gauge at the socket end are located in the same cross section of the JPCCP pipe; the steel cylinder strain gauge, pipe core concrete inner layer surface strain gauge, outer protective layer concrete strain gauge, steel wire strain gauge and pipe core concrete middle layer strain gauge in the middle of the pipe body are located in the same cross section of the JPCCP pipe; the earth pressure gauge, pore water pressure gauge, steel cylinder strain gauge, pipe core concrete inner layer surface strain gauge, outer protective layer concrete strain gauge, steel wire strain gauge and pipe core concrete middle layer strain gauge at the spigot end are located in the same cross section of the JPCCP pipe.
3. The JPCCP pipeline status intelligent monitoring system according to claim 1 is characterized by: The soil pressure gauge and pore water pressure gauge in step 3 and the strain gauge on the inner surface of the core concrete in step 4 are installed using a base, and the base is fastened to the concrete surface of the corresponding layer by expansion bolts or screws.
4. The JPCCP pipeline status intelligent monitoring system according to claim 1 is characterized in that: In step 7, the signals of the network IO data acquisition instrument and the roller meter are transmitted wirelessly to the data control terminal and the intelligent Internet of Things cloud platform.
5. The JPCCP pipeline status intelligent monitoring system according to claim 1 is characterized by: Before installing the socket joint, first install two sealing rubber rings at the socket steel ring, and install a double-layer wooden pad at the socket end; and there is an offset gap between the double-layer wooden pads, and a gap between the wooden pads and the socket ring. The signal extension line described in step 6 passes through the offset gap between the double-layer wooden pads and the gap between the wooden pads and the socket ring at the socket end face, and then passes through the grouting hole.
6. The construction control method of a JPCCP pipeline status intelligent monitoring system according to claim 1 is characterized in that: The jacking status data and pipeline status data of the JPCCP pipe obtained by the sensor are wirelessly transmitted to the cloud platform and the data control terminal via the data acquisition instrument to establish a construction status prediction model. Under the support of the cloud platform algorithm, the prediction model is iterated with the calculation of the first section of the main monitoring pipe, and the prediction model is improved with more data from subsequent pipe sections. During the construction process, the jacking cylinder and grouting pump control are regulated according to the data, and the pipeline jacking force and graded grouting are used to reduce drag. The jacking status data of the JPCCP pipe at least includes the jacking force, jacking distance and jacking speed, and the pipeline status data at least includes the water and soil pressure around the pipe, steel wire deformation, steel cylinder deformation and three-layer concrete deformation.