Preset gas pipeline quick connecting device based on BIM (Building Information Modeling) technology

By combining the elastic locking mechanism and the staggered split self-locking engagement mechanism, the problem of insufficient connection strength and stability in BIM modeling pipe connection devices is solved, achieving efficient and stable pipe connection and sealing performance, and improving the aesthetics of the connection device.

CN119042431AInactive Publication Date: 2024-11-29CHINA CONSTR FIFTH ENG DIV CORP LTD

Patent Information

Application Number
CN202411546628.1
Authority / Receiving Office
CN · China
Patent Type
Applications(China)
Current Assignee / Owner
Filing Date
2024-11-01
Publication Date
2024-11-29
Estimated Expiration
Not applicable · inactive patent

AI Technical Summary

Technical Problem

In existing technologies, pipe connection devices based on BIM modeling suffer from insufficient connection strength and stability, while traditional joint connection devices are cumbersome to operate and have difficulty in ensuring sealing and connection speed.

Method used

It adopts an elastic locking mechanism, a staggered split self-locking engagement mechanism, and a manual overall fastening mechanism. The elastic locking mechanism automatically compensates for the aging or thinning of the sealing gasket, and uses a rotating locking collar to achieve synchronous locking and batch positioning. Combined with magnetic fixation, it improves connection efficiency and stability.

Benefits of technology

It achieves efficient and stable pipe connections, ensures sealing performance, reduces the loosening caused by aging or thinning of sealing gaskets, and improves the overall stability and aesthetics of the connection device.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN119042431A_ABST
    Figure CN119042431A_ABST
Patent Text Reader

Abstract

The invention belongs to the technical field of pipeline connecting devices, and particularly discloses a preset gas pipeline quick connecting device based on a BIM (Building Information Modeling) technology, which comprises a preset pipeline mechanism, an elastic locking mechanism, a staggered split type self-locking clamping mechanism and a manual integral fastening mechanism. According to the scheme, the sealing gasket has the same function as a spring gasket, the thickness change of the rubber gasket can be compensated through the deformation of the spring when the rubber gasket is aged or extruded to be thinned, on one hand, the sealing performance can be kept, and on the other hand, the influence on the connection stability can be reduced; moreover, according to the scheme, locking and unlocking of the staggered split type self-locking clamping mechanism are automatically achieved by means of axial sliding of the rotary locking lantern ring itself under the condition that locking is not conducted by means of the mode of'splicing seam dislocation ', and the staggered split type self-locking clamping mechanism is automatically locked and unlocked by means of the axial sliding of the rotary locking lantern ring itself.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The present invention belongs to the technical field of pipeline connection devices, and specifically refers to a pre-installed gas pipeline quick connection device based on BIM technology. Background Art

[0002] The core of BIM is a digital technology that provides visualization solutions for construction by establishing a virtual three-dimensional model of the construction project. Therefore, based on the BIM modeling and design solution, more pipes will be pre-buried inside the walls of the building to improve the appearance and safety of the entire pipe distribution system. Generally speaking, this operation method is to bury some specific pipes in the wall first, and leave the joints of the pipes. Pipes that cannot be pre-buried or are not suitable for pre-buried are installed on the outside of the wall, and finally the connection between the two is completed through the joints.

[0003] Because the embedded fixed joints are inconvenient to replace, high-strength and wear-resistant metal materials are generally used. In order to further reduce wear, the parts connected to them are generally made of materials with lower hardness, reducing the wear on the fixed joints at the expense of shortening the life of easily replaceable parts; however, this will also bring about problems of low connection strength and poor stability.

[0004] For general annular bolts, the locking sequence is mostly diagonal locking, the purpose of which is to minimize the problem of deviation of the sealing gasket caused by uneven distribution of extrusion force. Compared with diagonal locking, synchronous locking is a synchronous extrusion at all angles, so it can often make the sealing gasket more evenly stressed; however, the current operating steps of synchronous locking are still relatively cumbersome.

[0005] Because there are many joints used to connect embedded pipes and external pipes in large-scale piping systems, traditional joint connection devices are not only difficult to ensure stability and consistency at the same time, but the connection speed is also relatively low, which to a certain extent limits the efficiency advantage of BIM technology. Summary of the invention

[0006] In view of the above situation, in order to overcome the defects of the prior art, the present invention proposes a pre-installed gas pipeline quick connection device that can be bolted in batches; general spring washers do not rely on springs to transmit pressure, but on the basis of nut locking, increase the friction between the threads through spring washers, and their main function is to prevent loosening; in addition to having the same function as the spring washer, this solution can also compensate for the thickness change of the rubber pad through the deformation of the spring when the rubber pad is aged or squeezed and thinned. On the one hand, it can maintain the sealing performance, and on the other hand, it can reduce the impact on the connection stability.

[0007] Moreover, the present solution also utilizes the method of "misaligned splicing seams" to automatically achieve locking and unlocking of the misaligned split self-locking engagement mechanism by utilizing the axial sliding that the rotating locking collar itself should perform without locking; and in the case of temporary fixation by magnetic attraction, the positioning and tightening of all special-shaped nuts are completed at one time through batch linkage, which not only improves efficiency, but also ensures that the embedded flange and the external flange are squeezed synchronously around them through synchronous locking, thereby avoiding the problem of uneven compression of the sealing gasket due to deviations in extrusion pressure in different directions.

[0008] The technical solution adopted by the present invention is as follows: The present invention proposes a pre-installed gas pipeline quick connection device based on BIM technology, including a pre-installed pipeline mechanism, an elastic locking mechanism, a staggered split self-locking clamping mechanism and a manual integral fastening mechanism, the elastic locking mechanism is evenly arranged on the pre-installed pipeline mechanism in a ring shape, the staggered split self-locking clamping mechanism is detachably arranged on the pre-installed pipeline mechanism, and the manual integral fastening mechanism is arranged on the staggered split self-locking clamping mechanism.

[0009] Furthermore, the pre-installed pipeline mechanism includes a fixed joint assembly and an external joint assembly, the elastic locking mechanism includes a locking and retaining assembly and a rotating locking assembly, the external joint assembly is connected and fixed to the fixed joint assembly via a rotating locking assembly, and the rotating locking assembly is sleeved on the locking and retaining assembly.

[0010] The two separate components on the preset pipeline mechanism can be locked and fixed by the elastic locking mechanism. The elastic fixing method of the elastic locking mechanism can solve the problem of balancing connection strength and wear resistance on the one hand, and on the other hand, it can also avoid obvious loosening when the sealing gasket is aged or thinned through automatic compensation of the locking spring.

[0011] Preferably, the fixed joint assembly comprises a wall, a pre-buried pipe and a sealing cover, the wall is provided with a pipe groove, the pre-buried pipe is buried in the pipe groove, an embedded flange is provided at the outer end of the pre-buried pipe, and the sealing cover is arranged between the pre-buried pipe and the pipe groove.

[0012] As a further preferred embodiment of the present invention, the external joint assembly includes an external pipe and a sealing gasket, the external pipe is provided with an external flange portion corresponding to the embedded flange portion, the embedded flange portion, the sealing gasket and the external flange portion are provided with through holes, a polygonal countersunk groove is provided on one side of the through hole of the external flange portion, and the sealing gasket is arranged between the embedded flange portion and the external flange portion.

[0013] By arranging and clamping a sealing gasket between the embedded flange and the external flange, the sealing of the connection can be effectively ensured, and the gap between the wall and the embedded pipe can be blocked by the sealing cover, thereby making the wall more beautiful.

[0014] The bolt head of the locking bolt can be inserted into the polygonal countersunk groove to limit the rotation of the locking bolt, and after the arc bracket is installed, the inner boss portion can prevent the locking bolt from sliding out axially, thereby keeping the position of the locking bolt itself fixed during the rotation and tightening process of the manual integral tightening mechanism.

[0015] Furthermore, the locking and retaining assembly includes a locking bolt, a special-shaped nut and a locking spring. The locking bolt passes through the through holes of the embedded flange portion, the sealing gasket and the external flange portion. The bolt head of the locking bolt is engaged in the polygonal countersunk groove. The special-shaped nut and the locking bolt are threadedly connected. The special-shaped nut is provided with a nut annular groove in the direction close to the embedded flange portion. A spring bottom ring and a spring top ring are respectively provided at both ends of the locking spring. A spring rotating ring is also provided on the spring top ring, and the spring rotating ring is rotatably arranged in the nut annular groove.

[0016] The locking spring is different from ordinary elastic washers. Ordinary elastic washers do not transmit pressure (the pressure is still applied through the nut itself, and the function of the spring washer is to maintain the friction of the nut and prevent it from falling off during vibration). The locking spring, as a part that transmits pressure, can not only prevent the special-shaped nut from falling off, but also prevent the embedded flange and the external flange from being unable to clamp the sealing gasket when the sealing gasket ages or becomes thinner due to extrusion through the elastic deformation of the locking spring itself, thereby avoiding affecting the air tightness.

[0017] Preferably, the rotary locking assembly includes a first bevel gear and a movable adsorption magnetic ring, and the first bevel gear is provided with a hexagonal countersunk groove and a magnet mounting groove on both sides respectively. The first bevel gear is sleeved on the special-shaped nut through the hexagonal countersunk groove, and the movable adsorption magnetic ring is fixed in the magnet mounting groove.

[0018] The first bevel gear and the rotary locking ring are engaged with each other through the bevel teeth. On the one hand, they can transmit the rotational motion normally. On the other hand, they can also apply an axial component force to the first bevel gear through the rotary locking ring. Under the action of this axial component force, the first bevel gear will move along with the axial motion of the special-shaped nut. The axial displacement of the first bevel gear can also be achieved by manually pushing the rotary locking ring.

[0019] As a further preferred embodiment of the present invention, the offset split self-locking locking mechanism includes a first opening and closing component and a second opening and closing component. The first opening and closing component and the second opening and closing component are coaxially arranged with the embedded flange part and the external flange part during installation. The first opening and closing component is engaged with the external flange part, and the second opening and closing component is arranged on the first opening and closing component.

[0020] Through the design of staggered first joint seam and first straight slide groove, combined with the characteristic that the position of sleeve joint seam is the same as that of first joint seam, when the dovetail boss part slides in the first straight slide groove, the staggered split self-locking engagement mechanism can be disassembled and installed; and when the dovetail boss part slides in the second straight slide groove, annular slide groove one or annular slide groove two, since the position of the sleeve joint seam does not correspond to the position of the second joint seam, the second arc-shaped shell is locked by the rotating locking ring and cannot be unfolded.

[0021] Furthermore, the first opening and closing assembly includes a first arc-shaped shell and a first hinge, the first arc-shaped shell is hinged by the first hinge, a first joint seam is provided on the first arc-shaped shell, and a first straight slide groove is symmetrically provided on the outer wall of the first arc-shaped shell.

[0022] The dovetail boss portion can slide in the first straight groove, the second straight groove, the annular groove one and the annular groove two, but cannot fall off therefrom. Through the overall sliding of the rotating locking ring, when the rotating locking ring wraps and covers the second arc-shaped outer shell, the rotating locking ring can be used to block the first arc-shaped outer shell and prevent the second arc-shaped outer shell from unfolding.

[0023] Preferably, the second opening and closing assembly includes a second arc-shaped shell and a second hinge, the second arc-shaped shell is hinged by the second hinge, a second joint seam is provided on the second arc-shaped shell, the first arc-shaped shell and the second arc-shaped shell are both composed of two parts hinged to each other, the two parts of the first arc-shaped shell and the second arc-shaped shell open and close synchronously, a second straight slide groove connected to the first straight slide groove is symmetrically provided on the outer wall of the second arc-shaped shell, an annular slide groove 1 and an annular slide groove 2 intersecting with the second straight slide groove are also provided on the outer wall of the second arc-shaped shell in sequence, and positioning baffles are evenly distributed in an inner ring of the second arc-shaped shell.

[0024] By the axial sliding of the rotating locking collar, the locking and unlocking of the offset split self-locking engagement mechanism can be adaptively completed without performing a separate locking action by the axial sliding that is originally required when the rotating locking collar is connected to the first bevel gear.

[0025] As a further preferred embodiment of the present invention, the manual integral fastening mechanism includes a rotary locking ring and a magnetic pre-fixing component, the rotary locking ring is composed of two asymmetric independent arc surfaces, the two connection points of the arc surfaces are respectively a ring splicing seam and a ring connecting seam, wherein the ring connecting seam is a non-disconnectable connection, and the ring splicing seam is a disconnectable connection, when the ring connecting seam is located directly below the first hinge and the second hinge, the ring splicing seam and the first splicing seam are at the same angle, the first splicing seam and the second splicing seam are not at the same angle, one end of the rotary locking ring is symmetrically provided with a dovetail boss portion, the dovetail boss portion is snap-fitted and slidably arranged in the first straight slide groove, the second straight slide groove, the annular slide groove one and the annular slide groove two, the interior of the rotary locking ring is provided with internal bevel teeth matching the first bevel gear, and the outer surface of the rotary locking ring is provided with an anti-slip boss.

[0026] Furthermore, the magnetic pre-fixing component includes an arc-shaped bracket, a connecting column, an arc-shaped base frame and a fixed magnetic ring, the arc-shaped bracket is fixedly connected to the rotating locking ring, the arc-shaped bracket is provided with an inner boss portion, the connecting column is fixedly connected to the inner boss portion, the arc-shaped base frame is fixedly connected to the end of the connecting column, the arc-shaped base frame is provided with a guide cylinder coaxial with the locking bolt, the fixed magnetic ring is fixedly connected to the bottom of the guide cylinder, and there is a magnetic adsorption force between the fixed magnetic ring and the movable adsorption magnetic ring.

[0027] By fixing the magnetic attraction of the magnetic ring and the guidance of the guide cylinder, the position of the first bevel gear can be fixed, so that the position adjustment of the first bevel gear can be completed in batches without controlling the position of the first bevel gear one by one.

[0028] The beneficial effects achieved by the present invention using the above structure are as follows: (1) The first bevel gear and the rotary locking ring are engaged with each other through the helical teeth. On the one hand, the rotational motion can be transmitted normally. On the other hand, the rotary locking ring can apply an axial force component to the first bevel gear. Under the action of this axial force component, the first bevel gear will move along with the axial motion of the special-shaped nut. The axial displacement of the first bevel gear can also be achieved by manually pushing the rotary locking ring.

[0029] (2) By designing the first joint seam and the first straight groove to be offset, combined with the fact that the position of the collar joint seam is the same as that of the first joint seam, when the dovetail boss slides in the first straight groove, the offset split self-locking engagement mechanism can be disassembled and installed; and when the dovetail boss slides in the second straight groove, the annular groove one or the annular groove two, since the position of the collar joint seam does not correspond to the position of the second joint seam, the second arc-shaped shell is locked by the rotating locking collar and cannot be unfolded.

[0030] (3) The locking spring is different from the ordinary elastic gasket. The ordinary elastic gasket does not transmit pressure (the pressure is still applied by the nut itself, and the role of the spring gasket is to maintain the friction of the nut and prevent it from falling off during vibration). The locking spring, as a part that transmits pressure, can not only prevent the special-shaped nut from falling off, but also prevent the embedded flange and the external flange from being unable to clamp the sealing gasket when the sealing gasket ages or becomes thinner due to extrusion through the elastic deformation of the locking spring itself, thereby avoiding affecting the air tightness.

[0031] (4) The bolt head of the locking bolt can be inserted into the polygonal countersunk groove to limit the rotation of the locking bolt. After the arc bracket is installed, the inner boss portion can prevent the locking bolt from sliding out axially, thereby keeping the position of the locking bolt fixed during the rotation and tightening of the manual integral tightening mechanism.

[0032] (5) By means of the axial sliding of the rotating locking collar, the locking and unlocking of the offset split self-locking engagement mechanism can be adaptively completed without performing a separate locking action by means of the axial sliding that is originally required when the rotating locking collar is connected to the first bevel gear.

[0033] (6) By fixing the magnetic attraction force of the magnetic attraction ring and the guidance of the guide cylinder, the position of the first bevel gear can be fixed, so that the position adjustment of the first bevel gear can be completed in batches without controlling the position of the first bevel gear one by one. BRIEF DESCRIPTION OF THE DRAWINGS

[0034] Figure 1 A three-dimensional diagram of a pre-installed gas pipeline quick connection device based on BIM technology proposed by the present invention; Figure 2 This is a front view of a pre-installed gas pipeline quick connection device based on BIM technology proposed by the present invention; Figure 3 This is a left view of a pre-installed gas pipeline quick connection device based on BIM technology proposed by the present invention; Figure 4 A top view of a pre-installed gas pipeline quick connection device based on BIM technology proposed by the present invention; Figure 5 for Figure 2 A cross-sectional view along the cutting line AA; Figure 6 for Figure 2 A cross-sectional view along the cutting line BB; Figure 7 for Figure 3 A cross-sectional view along the cutting line CC; Figure 8This is an exploded schematic diagram of a pre-installed gas pipeline quick connection device based on BIM technology proposed by the present invention; Fig. 9 for Figure 5 A partial enlarged view of point Ⅰ in the middle; Fig.10 for Figure 6 A partial enlarged view of the middle II; Fig.11 for Figure 8 A partial enlarged view of the middle part III; Fig.12 for Figure 1 A partial enlarged view of the middle IV; Fig.13 for Figure 8 A partial enlarged view of point V in the middle.

[0035] Among them, 1. Pre-installed pipeline mechanism; 2. Elastic locking mechanism; 3. Displaced split self-locking clamping mechanism; 4. Manual integral fastening mechanism; 5. Fixed joint assembly; 6. External joint assembly; 7. Wall; 8. Pre-buried pipeline; 9. Blocking cover; 10. External pipeline; 11. Sealing gasket; 12. Pipeline groove; 13. Pre-buried flange; 14. External flange; 15. Polygonal countersunk groove; 16. Locking and holding assembly; 17. Rotary locking assembly; 18. Locking bolt; 19. Special-shaped nut; 20. Locking spring; 21. First bevel gear; 22. Movable adsorption magnetic ring; 23. Nut annular groove; 24. Spring bottom ring; 25. Spring top ring; 26. Spring rotating ring; 27. Hexagonal countersunk groove ; 28. Magnet mounting groove; 29. ​​First opening and closing component; 30. Second opening and closing component; 31. First arc-shaped shell; 32. First hinge; 33. Second arc-shaped shell; 34. Second hinge; 35. First joint seam; 36. First straight slide groove; 37. Second joint seam; 38. Second straight slide groove; 39. Annular slide groove one; 40. Annular slide groove two; 41. Positioning baffle; 42. Rotary locking collar; 43. Magnetic pre-fixing component; 44. Dovetail boss portion; 45. Internal bevel gear; 46. Ring connecting seam; 47. Anti-slip boss; 48. Arc-shaped bracket; 49. Connecting column; 50. Arc-shaped base frame; 51. Fixed magnetic suction ring; 52. Internal boss portion; 53. Guide cylinder; 54. Ring joint seam.

[0036] The accompanying drawings are used to provide further understanding of the present invention and constitute a part of the specification. They are used to explain the present invention together with the embodiments of the present invention and do not constitute a limitation of the present invention. DETAILED DESCRIPTION

[0037] The technical solutions in the embodiments of the present invention will be clearly and completely described below in conjunction with the drawings in the embodiments of the present invention. Obviously, the described embodiments are only part of the embodiments of the present invention, rather than all the embodiments; based on the embodiments of the present invention, all other embodiments obtained by ordinary technicians in this field without making creative work are within the scope of protection of the present invention.

[0038] In the description of the present invention, it should be understood that terms such as “upper”, “lower”, “front”, “back”, “left”, “right”, “top”, “bottom”, “inside” and “outside” indicating directions or positional relationships are based on the directions or positional relationships shown in the accompanying drawings, and are only for the convenience of describing the present invention and simplifying the description, rather than indicating or implying that the device or element referred to must have a specific direction, be constructed and operated in a specific direction, and therefore should not be understood as limiting the present invention.

[0039] like Figure 1 to Figure 13 As shown, the present invention proposes a pre-installed gas pipeline quick connection device based on BIM technology, including a pre-installed pipeline mechanism 1, an elastic locking mechanism 2, a staggered split self-locking clamping mechanism 3 and a manual integral fastening mechanism 4, the elastic locking mechanism 2 is evenly arranged on the pre-installed pipeline mechanism 1 in a ring shape, the staggered split self-locking clamping mechanism 3 is detachably arranged on the pre-installed pipeline mechanism 1, and the manual integral fastening mechanism 4 is arranged on the staggered split self-locking clamping mechanism 3.

[0040] The pre-installed pipeline mechanism 1 includes a fixed joint assembly 5 and an external joint assembly 6, the elastic locking mechanism 2 includes a locking and retaining assembly 16 and a rotating locking assembly 17, the external joint assembly 6 is connected and fixed to the fixed joint assembly 5 via the rotating locking assembly 17, and the rotating locking assembly 17 is sleeved on the locking and retaining assembly 16.

[0041] The two separate components on the preset pipeline mechanism 1 can be locked and fixed by the elastic locking mechanism 2. The elastic fixing method of the elastic locking mechanism 2 can solve the problem of balancing connection strength and wear resistance on the one hand, and on the other hand, it can also automatically compensate through the locking spring 20 to avoid obvious loosening when the sealing gasket 11 is aged or thinned.

[0042] The fixed joint assembly 5 includes a wall 7, a pre-buried pipe 8 and a sealing cover 9. A pipe groove 12 is provided on the wall 7, the pre-buried pipe 8 is buried in the pipe groove 12, an embedded flange portion 13 is provided at the outer end of the pre-buried pipe 8, and the sealing cover 9 is arranged between the pre-buried pipe 8 and the pipe groove 12.

[0043] The external joint assembly 6 includes an external pipe 10 and a sealing gasket 11. The external pipe 10 is provided with an external flange portion 14 corresponding to the embedded flange portion 13. The embedded flange portion 13, the sealing gasket 11 and the external flange portion 14 are provided with through holes. A polygonal countersunk groove 15 is provided on one side of the through hole of the external flange portion 14. The sealing gasket 11 is arranged between the embedded flange portion 13 and the external flange portion 14.

[0044] By arranging and clamping a sealing gasket 11 between the embedded flange portion 13 and the external flange portion 14, the sealing of the connection can be effectively ensured, and the gap between the wall 7 and the embedded pipe 8 can be blocked by the sealing cover 9, thereby making the wall 7 more beautiful.

[0045] The bolt head of the locking bolt 18 can be inserted into the polygonal countersunk groove 15 to limit the rotation of the locking bolt 18, and after the arc bracket 48 is installed, the inner boss portion 52 can prevent the locking bolt 18 from sliding out axially, thereby keeping the position of the locking bolt 18 fixed during the rotation and tightening of the manual integral tightening mechanism 4.

[0046] The locking and retaining assembly 16 includes a locking bolt 18, a special-shaped nut 19 and a locking spring 20. The locking bolt 18 passes through the through holes of the embedded flange portion 13, the sealing gasket 11 and the external flange portion 14. The bolt head of the locking bolt 18 is engaged in the polygonal countersunk groove 15. The special-shaped nut 19 and the locking bolt 18 are threadedly connected. The special-shaped nut 19 is provided with a nut annular groove 23 in the direction close to the embedded flange portion 13. The two ends of the locking spring 20 are respectively provided with a spring bottom ring 24 and a spring top ring 25. The spring top ring 25 is also provided with a spring rotating ring 26, and the spring rotating ring 26 is rotatably arranged in the nut annular groove 23.

[0047] The locking spring 20 is different from ordinary elastic washers. Ordinary elastic washers do not transmit pressure (the pressure is still applied through the nut itself, and the function of the spring washer is to maintain the friction of the nut and prevent it from falling off during vibration). However, as a part that transmits pressure, the locking spring 20 can not only prevent the special-shaped nut 19 from falling off, but also prevent the embedded flange part 13 and the external flange part 14 from being unable to clamp the sealing gasket 11 through the elastic deformation of the locking spring 20 itself when the sealing gasket 11 is aged or squeezed and thinned, thereby avoiding affecting the air tightness.

[0048] The rotary locking assembly 17 includes a first bevel gear 21 and a movable adsorption magnetic ring 22. The first bevel gear 21 has a hexagonal countersunk groove 27 and a magnet mounting groove 28 on both sides thereof. The first bevel gear 21 is sleeved on the special-shaped nut 19 through the hexagonal countersunk groove 27, and the movable adsorption magnetic ring 22 is fixedly connected to the magnet mounting groove 28.

[0049] The first bevel gear 21 and the rotary locking ring 42 are engaged with each other through the bevel teeth. On the one hand, the rotational motion can be transmitted normally. On the other hand, the rotary locking ring 42 can apply an axial component force to the first bevel gear 21. Under the action of this axial component force, the first bevel gear 21 will move along with the axial motion of the special-shaped nut 19. The axial displacement of the first bevel gear 21 can also be achieved by manually pushing the rotary locking ring 42.

[0050] The offset split self-locking locking mechanism 3 includes a first opening and closing component 29 and a second opening and closing component 30. When installed, the first opening and closing component 29 and the second opening and closing component 30 are coaxially arranged with the embedded flange part 13 and the external flange part 14. The first opening and closing component 29 is engaged with the external flange part 14, and the second opening and closing component 30 is arranged on the first opening and closing component 29.

[0051] Through the staggered design of the first joint seam 35 and the first straight groove 36, combined with the characteristic that the position of the ring joint seam 54 is the same as that of the first joint seam 35, when the dovetail boss portion 44 slides in the first straight groove 36, the staggered split self-locking engaging mechanism 3 can be disassembled and installed; and when the dovetail boss portion 44 slides in the second straight groove 38, the annular groove 1 39 or the annular groove 2 40, since the position of the ring joint seam 54 does not correspond to the position of the second joint seam 37, the second arc-shaped shell 33 is locked by the rotating locking ring 42 and cannot be unfolded.

[0052] The first opening and closing assembly 29 includes a first arc-shaped shell 31 and a first hinge 32 . The first arc-shaped shell 31 is hinged by the first hinge 32 . A first joint seam 35 is provided on the first arc-shaped shell 31 . A first straight slide groove 36 is symmetrically provided on the outer wall of the first arc-shaped shell 31 .

[0053] The dovetail boss portion 44 can slide in the first straight groove 36, the second straight groove 38, the annular groove 1 39 and the annular groove 2 40, but cannot fall out therefrom. By the overall sliding of the rotating locking ring 42, when the rotating locking ring 42 wraps and covers the second arc-shaped outer shell 33, the rotating locking ring 42 can block the first arc-shaped outer shell 31 and the second arc-shaped outer shell 33 from unfolding.

[0054] The second opening and closing component 30 includes a second arc-shaped shell 33 and a second hinge 34. The second arc-shaped shell 33 is hinged by the second hinge 34. A second joint seam 37 is provided on the second arc-shaped shell 33. The first arc-shaped shell 31 and the second arc-shaped shell 33 are both composed of two parts hinged to each other. The two parts of the first arc-shaped shell 31 and the second arc-shaped shell 33 open and close synchronously. A second straight slide groove 38 connected to the first straight slide groove 36 is symmetrically provided on the outer wall of the second arc-shaped shell 33. An annular slide groove 1 39 and an annular slide groove 2 40 intersecting with the second straight slide groove 38 are also provided on the outer wall of the second arc-shaped shell 33 in sequence. Positioning baffles 41 are evenly distributed in an inner ring of the second arc-shaped shell 33.

[0055] By the axial sliding of the rotating locking collar 42 , the locking and unlocking of the offset split self-locking engagement mechanism 3 can be adaptively completed without performing a separate locking action by the axial sliding that is originally required when the rotating locking collar 42 is connected to the first bevel gear 21 .

[0056] The manual integral fastening mechanism 4 includes a rotating locking collar 42 and a magnetic pre-fixing component 43. The rotating locking collar 42 is composed of two asymmetric independent arc surfaces. The two connecting parts of the arc surfaces are respectively a collar joint seam 54 and a collar connection seam 46. The collar connection seam 46 is a non-disconnectable connection, and the collar joint seam 54 is a disconnectable connection. When the collar connection seam 46 is located directly below the first hinge 32 and the second hinge 34, the collar joint seam 54 and the first hinge 32 and the second hinge 34 are connected. A splicing seam 35 is located at the same angle, the first splicing seam 35 and the second splicing seam 37 are not located at the same angle, one end of the rotating locking ring 42 is symmetrically provided with a dovetail boss portion 44, the dovetail boss portion 44 is slidably engaged in the first straight slide groove 36, the second straight slide groove 38, the annular slide groove 1 39 and the annular slide groove 2 40, the interior of the rotating locking ring 42 is provided with internal bevel teeth 45 matching the first bevel gear 21, and the outer surface of the rotating locking ring 42 is provided with an anti-slip boss 47.

[0057] The magnetic pre-fixing component 43 includes an arc-shaped bracket 48, a connecting column 49, an arc-shaped base frame 50 and a fixed magnetic ring 51. The arc-shaped bracket 48 is fixedly connected to the rotating locking ring 42. The arc-shaped bracket 48 is provided with an inner boss portion 52. The connecting column 49 is fixedly connected to the inner boss portion 52. The arc-shaped base frame 50 is fixedly connected to the end of the connecting column 49. The arc-shaped base frame 50 is provided with a guide cylinder 53 coaxial with the locking bolt 18. The fixed magnetic ring 51 is fixedly connected to the bottom of the guide cylinder 53. There is a magnetic adsorption force between the fixed magnetic ring 51 and the movable adsorption magnetic ring 22.

[0058] By fixing the magnetic attraction of the magnetic ring 51 and the guidance of the guide cylinder 53, the position of the first bevel gear 21 can be fixed, so that the position adjustment of the first bevel gear 21 can be completed in batches without controlling the position of the first bevel gear 21 one by one.

[0059] When in use, the user first needs to embed the embedded pipe 8 in the pipe groove 12, and then use the blocking cover 9 to block the gap between the protruding part of the embedded pipe 8 and the wall 7, and then fix the external pipe 10 outside the building wall 7 through the bracket, and finally place the sealing gasket 11 between the embedded flange part 13 and the external flange part 14, and lock and fix them through the elastic locking mechanism 2, so as to complete the connection and fixation of the pipe joint. The specific steps are as follows: Pass the locking bolt 18 through the holes of the embedded flange 13, the sealing gasket 11 and the external flange 14, and place the bolt head of the locking bolt 18 in the polygonal countersunk groove 15, and then put the locking spring 20 on the locking bolt 18; After the special-shaped nut 19 is inserted into the hexagonal countersunk groove 27, the first bevel gear 21 is temporarily fixed to the fixed magnetic ring 51 by the magnetic attraction between the movable adsorption magnetic ring 22 and the fixed magnetic ring 51; Then, one hand holds the dislocated split self-locking engaging mechanism 3, and the other hand holds the rotating locking collar 42. When the rotating locking collar 42 is located on the first arc-shaped shell 31, the first arc-shaped shell 31 and the second arc-shaped shell 33 are unfolded and wrapped around the embedded flange portion 13 and the external flange portion 14. The dislocated split self-locking engaging mechanism 3 can be axially positioned by the positioning baffle 41, and the locking bolt 18 cannot be ejected from the polygonal countersunk groove 15 by the blocking of the positioning baffle 41. Although the two parts of the first arc-shaped shell 31 and the second arc-shaped shell 33 that can be hinged are not joined together, they are fixedly connected respectively. When the first arc-shaped shell 31 and the second arc-shaped shell 33 are closed, the rotating locking collar 42 is also closed and forms a complete circle. Since the dovetail boss portion 44 cannot slide out of the first straight slide groove 36, the second straight slide groove 38, the annular slide groove 1 39 and the annular slide groove 2 40, the dovetail boss portion 44 can be slid from the first straight slide groove 36 along the second straight slide groove 38 to the annular slide groove 1 39 by pushing the rotating locking collar 42 at this time. When the dovetail boss portion 44 is separated from the first straight slot 36, the rotating locking collar 42 will be wrapped around the outside of the second arc-shaped shell 33. Since the position of the second joint seam 37 does not coincide with the position of the collar joint seam 54, and the rotating locking collar 42 cannot be unfolded alone without the second arc-shaped shell 33 being unfolded, the top of the second arc-shaped shell 33 cannot be unfolded at this time due to the wrapping and locking of the rotating locking collar 42. Therefore, when the rotating locking collar 42 is separated from the first straight slot 36, both the first arc-shaped shell 31 and the second arc-shaped shell 33 cannot be unfolded.

[0060] At this time, the rotary locking collar 42 can be held in hand, and the first bevel gear 21 can be approached and squeezed while being rotated back and forth in a small amplitude. Because the arc-shaped base frame 50 has a small amplitude of elasticity, when the dovetail boss portion 44 is swung back and forth in the annular groove 39 in a small amplitude, the outer bevel teeth of the first bevel gear 21 will successively mesh with the inner bevel teeth 45, and those that have already been meshed will maintain the current meshing state due to the rebound of the arc-shaped base frame 50 and rotate with the rotation of the rotary locking collar 42; whether they are all meshed can be easily distinguished by the sound: there will be metal friction and collision sounds when they are not meshed, while there is basically no sound when they are meshed.

[0061] After all the first bevel gears 21 are meshed with the rotary locking collar 42, the dovetail boss portion 44 is rotated to the position where the second straight slide groove 38 and the annular slide groove 1 39 intersect, and is slowly pushed along the second straight slide groove 38 toward the direction where the wall 7 is located. Due to the meshing characteristics of the bevel teeth (it has the ability to transmit both rotational motion and axial motion, when there is no restriction on the axial position, the rotary locking collar 42 slides with the first bevel gear 21 for axial motion, and when there is a restriction on the axial position, the rotary locking collar 42 slides with the first bevel gear 21 for rotation), during this process, the first bevel gear 21 allows the rotary locking collar 42 to slide by rotating in situ; When the rotating locking collar 42 slides to the end of the second straight slide groove 38, the rotating locking collar 42 is pulled back to the position of the second annular slide groove 40 at a relatively fast speed; due to the relatively fast speed of the rotating locking collar 42, the movable adsorption magnetic ring 22 and the fixed magnetic adsorption ring 51 are separated under the action of the pulling force, and slide to the locking bolt 18 along with the rotating locking collar 42; When the first bevel gear 21 just contacts and presses against the end of the locking bolt 18, the dovetail boss portion 44 is still a short distance away from completely entering the annular slide groove 40. At this time, the locking collar 42 is slowly pushed and rotated to rotate the first bevel gear 21. By designing the direction of the thread and the direction of the bevel teeth, the special-shaped nut 19 can be threadedly connected with the locking bolt 18 for a certain length while the first bevel gear 21 is squeezed and rotated. After the dovetail boss portion 44 enters the annular groove 40, the rotary locking collar 42 is manually rotated. At this time, the dovetail boss portion 44 rotates in the annular groove 40, and the first bevel gear 21 continues to rotate through the rotation of the rotary locking collar 42, thereby continuing to push the special-shaped nut 19 to rotate; although the special-shaped nut 19 will slide axially during the rotation, the first bevel gear 21 also has a certain axial movement tendency under the drive of the internal bevel teeth 45, so during this process the special-shaped nut 19 and the first bevel gear 21 will remain engaged and will not separate.

[0062] When the special-shaped nut 19 compresses the locking spring 20, the sealing gasket 11 is pressed by the elastic force transmitted by the locking spring 20 and the connection between the embedded flange part 13 and the external flange part 14 is completed. After tightening, the rotating locking ring 42 is adjusted to the angle when the dovetail boss part 44 is located in the second straight slide groove 38, and then the rotating locking ring 42 is quickly pushed toward the wall 7. At this time, the first bevel gear 21 is driven by the rotating locking ring 42 to separate from the special-shaped nut 19 and slide back to the guide cylinder 53 alone, and is adsorbed and fixed by the magnetic attraction between the fixed magnetic attraction ring 51 and the movable adsorption magnetic ring 22; Finally, slowly slide the rotating locking ring 42 in the direction away from the wall 7. During this process, the first bevel gear 21 rotates, and the fixed magnetic ring 51 and the movable adsorption magnetic ring 22 will not separate. After the rotating locking ring 42 and the first bevel gear 21 are separated, the dovetail boss portion 44 can be quickly slid into the first straight groove 36. When the rotating locking ring 42 does not restrict the unfolding of the second arc-shaped shell 33, the first arc-shaped shell 31 and the second arc-shaped shell 33 can be unfolded and the device can be removed.

[0063] During use, since the locking spring 20 is always transmitting pressure, when the sealing gasket 11 is aged or squeezed and thinned, the locking spring 20 can prevent the embedded flange part 13 and the external flange part 14 from becoming loose through its own small rebound, and this deformation has little effect on the elastic force of the locking spring 20, so it will not have a significant impact on the connection strength.

[0064] It should be noted that, in this article, relational terms such as first and second, etc. are only used to distinguish one entity or operation from another entity or operation, and do not necessarily require or imply any such actual relationship or order between these entities or operations. Moreover, the terms "include", "comprise" or any other variants thereof are intended to cover non-exclusive inclusion, so that a process, method, article or device including a series of elements includes not only those elements, but also other elements not explicitly listed, or also includes elements inherent to such process, method, article or device.

[0065] The present invention and its embodiments are described above, and such description is not restrictive. The drawings show only one embodiment of the present invention, and the actual structure is not limited thereto. In short, if ordinary technicians in the field are inspired by it, without departing from the purpose of the invention, they can design a structure and embodiment similar to the technical solution without creativity, which should belong to the protection scope of the present invention.

Claims

1. A pre-installed gas pipeline quick connection device based on BIM technology, It is characterized in that The invention comprises a pre-installed pipeline mechanism (1), an elastic locking mechanism (2), a dislocated split self-locking clamping mechanism (3) and a manual integral fastening mechanism (4), wherein the elastic locking mechanism (2) is arranged in an annular shape on the pre-installed pipeline mechanism (1), the dislocated split self-locking clamping mechanism (3) is detachably arranged on the pre-installed pipeline mechanism (1), and the manual integral fastening mechanism (4) is arranged on the dislocated split self-locking clamping mechanism (3); The elastic locking mechanism (2) comprises a locking and retaining component (16) and a rotating locking component (17), wherein the rotating locking component (17) is sleeved on the locking and retaining component (16); The locking and retaining assembly (16) comprises a locking bolt (18), a special-shaped nut (19) and a locking spring (20); the bolt head of the locking bolt (18) is engaged in the polygonal countersunk groove (15); and the special-shaped nut (19) and the locking bolt (18) are threadedly connected; The rotary locking assembly (17) comprises a first bevel gear (21) and a movable adsorption magnetic ring (22); two sides of the first bevel gear (21) are respectively provided with a hexagonal countersunk groove (27) and a magnet mounting groove (28); the first bevel gear (21) is sleeved on the special-shaped nut (19) through the hexagonal countersunk groove (27); the movable adsorption magnetic ring (22) is fixed in the magnet mounting groove (28); when the first bevel gear (21) rotates, it can not only axially displace the special-shaped nut (19), but also synchronously lock the locking bolt (18); The staggered split self-locking snap-fit ​​mechanism (3) comprises a first opening and closing component (29) and a second opening and closing component (30); the first opening and closing component (29) comprises a first arc-shaped shell (31), and the first arc-shaped shell (31) is provided with a first joint seam (35); the second opening and closing component (30) comprises a second arc-shaped shell (33), and the second arc-shaped shell (33) is provided with a second joint seam (37); the manual integral fastening mechanism (4) comprises a rotating locking collar (42); the positions of the first joint seam (35) and the second joint seam (37) are staggered, and the locking and unlocking of the staggered split self-locking snap-fit ​​mechanism (3) can be controlled by sliding the rotating locking collar (42).

2. According to claim 1, a pre-installed gas pipeline quick connection device based on BIM technology, Features: The pre-installed pipeline mechanism (1) comprises a fixed joint assembly (5) and an external joint assembly (6), wherein the external joint assembly (6) is connected and fixed to the fixed joint assembly (5) via a rotating locking assembly (17); The fixed joint assembly (5) comprises a wall (7), a pre-buried pipe (8) and a blocking cover (9); a pipe groove (12) is provided on the wall (7); the pre-buried pipe (8) is buried in the pipe groove (12); an outer end of the pre-buried pipe (8) is provided with a pre-buried flange (13); and the blocking cover (9) is arranged between the pre-buried pipe (8) and the pipe groove (12).

3. According to claim 2, a pre-installed gas pipeline quick connection device based on BIM technology, Features: The external joint assembly (6) comprises an external pipe (10) and a sealing gasket (11); the external pipe (10) is provided with an external flange portion (14) corresponding to the embedded flange portion (13); the embedded flange portion (13), the sealing gasket (11) and the external flange portion (14) are provided with through holes; a polygonal countersunk groove (15) is provided on one side of the through hole of the external flange portion (14); and the sealing gasket (11) is arranged between the embedded flange portion (13) and the external flange portion (14).

4. According to claim 3, a pre-installed gas pipeline quick connection device based on BIM technology, Features: The locking bolt (18) passes through the through holes of the embedded flange (13), the sealing gasket (11) and the external flange (14); the special-shaped nut (19) is provided with a nut annular groove (23) in a direction close to the embedded flange (13); two ends of the locking spring (20) are respectively provided with a spring bottom ring (24) and a spring top ring (25); the spring top ring (25) is also provided with a spring rotating ring (26); the spring rotating ring (26) is rotatably arranged in the nut annular groove (23).

5. According to claim 4, a pre-installed gas pipeline quick connection device based on BIM technology, Features: The first opening and closing assembly (29) and the second opening and closing assembly (30) are both coaxially arranged with the embedded flange portion (13) and the external flange portion (14) during installation; the first opening and closing assembly (29) is snap-fitted onto the external flange portion (14), and the second opening and closing assembly (30) is arranged on the first opening and closing assembly (29).

6. According to claim 5, a pre-installed gas pipeline quick connection device based on BIM technology, Features: The first opening and closing assembly (29) further comprises a first hinge (32), the first arc-shaped shell (31) being hinged via the first hinge (32), and a first straight slide groove (36) being symmetrically provided on an outer wall of the first arc-shaped shell (31).

7. According to claim 6, a pre-installed gas pipeline quick connection device based on BIM technology, Features: The second opening and closing assembly (30) further comprises a second hinge (34), the second arc-shaped shell (33) is hinged via the second hinge (34), the first arc-shaped shell (31) and the second arc-shaped shell (33) are both composed of two parts hinged to each other, the two parts of the first arc-shaped shell (31) and the second arc-shaped shell (33) are opened and closed synchronously, the outer wall of the second arc-shaped shell (33) is symmetrically provided with a second straight slide groove (38) connected to the first straight slide groove (36), the outer wall of the second arc-shaped shell (33) is also sequentially provided with an annular slide groove 1 (39) and an annular slide groove 2 (40) intersecting with the second straight slide groove (38), and the inner ring of the second arc-shaped shell (33) is evenly distributed with positioning baffles (41).

8. According to claim 7, a pre-installed gas pipeline quick connection device based on BIM technology, Features: The rotating locking collar (42) is composed of two asymmetric independent arc surfaces, the two connecting parts of the arc surfaces are respectively a collar joint seam (54) and a collar connection seam (46), wherein the collar connection seam (46) is a non-disconnectable connection, and the collar joint seam (54) is a disconnectable connection. When the collar connection seam (46) is located directly below the first hinge (32) and the second hinge (34), the collar joint seam (54) and the first joint seam (35) are located at the same angle, and the first joint seam (35) is located at the same angle. 5) and the second joint seam (37) are not located at the same angle, one end of the rotating locking ring (42) is symmetrically provided with a dovetail boss portion (44), the dovetail boss portion (44) is slidably engaged in the first straight slide groove (36), the second straight slide groove (38), the annular slide groove 1 (39) and the annular slide groove 2 (40), the interior of the rotating locking ring (42) is provided with internal bevel teeth (45) matching the first bevel gear (21), and the outer surface of the rotating locking ring (42) is provided with an anti-slip boss (47).

9. The pre-installed gas pipeline quick connection device based on BIM technology according to claim 8, Features: The manual integral fastening mechanism (4) further comprises a magnetic pre-fixing assembly (43), the magnetic pre-fixing assembly (43) comprising an arc-shaped bracket (48), a connecting column (49), an arc-shaped base frame (50) and a fixed magnetic attraction ring (51), the arc-shaped bracket (48) being fixedly connected to the rotating locking ring (42), the arc-shaped bracket (48) being provided with an inner boss portion (52), the connecting column (49) being fixedly connected to the inner boss portion (52), the arc-shaped base frame (50) being fixedly connected to the end of the connecting column (49), the arc-shaped base frame (50) being provided with a guide cylinder (53) coaxial with the locking bolt (18), the fixed magnetic attraction ring (51) being fixedly connected to the bottom of the guide cylinder (53), and a magnetic attraction force existing between the fixed magnetic attraction ring (51) and the movable attraction magnetic ring (22).

Citation Information

Patent Citations

  • Bolt fastened type ocean high-pressure reinforced thermoplastic pipe (RTP) connector and assembling method thereof

    CN105333261A

  • Pipe joint

    EP1225382A2