Point selection method and device for construction control network of pumped storage power station and terminal equipment
Through three-dimensional real-life model and virtual reality technology, the precise point selection of the pumped storage power station construction control network is realized, solving the problems of high costs and difficult progress in traditional methods, and improving the efficiency and accuracy of point selection.
Patent Information
- Application Number
- CN202410892508.0
- Authority / Receiving Office
- CN · China
- Patent Type
- Applications(China)
- Current Assignee / Owner
- Filing Date
- 2024-07-04
- Publication Date
- 2024-11-29
AI Technical Summary
The traditional pumped storage power station construction control network point selection method is difficult to achieve accurate point selection under complex terrain conditions, resulting in high production costs, difficult progress to cope with, and difficult to meet the progress requirements of engineering construction for the control network.
The three-dimensional real-life model is used to select points in the construction control network, and the visual characteristics of the real topography and landform are restored through the indoor 360-degree virtual reality scene and the height of the height, and the density, quantity and general location of the control points are obtained, based on geological conditions, visual conditions and observation conditions. Analyze, simulate design to determine the target control points and observation schemes, and meet preset criteria conditions.
It improves the efficiency of point selection in the construction control network, reduces field work, saves production costs, and realizes accurate point selection in the construction control network of the pumped storage power station, adapts to complex terrain conditions and project construction progress requirements.
Smart Images

Figure CN119047098A_ABST
Abstract
Description
Technical Field
[0001] The present invention relates to the technical field of pumped storage power stations, and in particular to a method for selecting a point for a construction control network of a pumped storage power station, a device for selecting a point for a construction control network of a pumped storage power station, a computer-readable storage medium and a terminal device. Background Art
[0002] In recent years, the demand for electricity has continued to grow, and the power load of power grids in many places has reached new highs, which has led to a surge in the demand for regulating power. Pumped storage is currently the first choice for large-scale regulation of energy due to its mature technology, fast response speed, large single-unit capacity, good economy, and high safety. In view of the good development prospects of pumped storage power stations, a large number of surveying, design, and construction companies have participated in the construction of pumped storage.
[0003] Construction control network measurement is an important task to provide a unified control benchmark for the construction of pumped storage power station projects. It plays a macro-control role in the overall layout of the project design and the overall construction positioning, provides a measurement basis for the construction layout of buildings, limits the accumulation of measurement errors during construction layout, and ensures that the relative positions of the various buildings in the entire project can be correctly connected in plane and vertical directions, so that all types of buildings can be accurately calibrated on the ground in terms of location, shape, size and elevation according to design and construction requirements.
[0004] The site selection of pumped storage power stations is generally in complex mountainous areas with high mountains and low valleys and large elevation differences. The engineering hub area is large and the visibility between the upper and lower reservoirs is poor. The construction control network needs to meet the construction layout of buildings such as the upper reservoir dam site, the lower reservoir dam site, the water transmission system, the underground plant, the switch station, the access road, and the traffic safety tunnel. It requires high precision, high density, long cycle, and certain stability and reliability. The layout and construction of control points play a vital role in the quality and cost of the construction control network measurement. The traditional site selection method generally carries out preliminary design on the topographic map, conducts field investigation and comparison, investigates the traffic conditions, geological conditions, construction cost of observation piers, GNSS observation conditions, total station observation conditions, line of sight analysis, etc. of the survey point, and collects the coordinates of the control points based on the field investigation for internal simulation design, which mainly includes network design, accuracy analysis and reliability analysis. According to the results of the simulation design, some points of the control network are adjusted, and the points are re-selected in the field. The whole process requires surveying personnel to repeatedly go to the site to adjust the positions of the control points, which consumes a lot of manpower, material resources and time costs, resulting in an increase in the unit cost of production, and it is difficult to cope with the complex terrain conditions of pumped storage power stations and the progress requirements of engineering construction for the control network. Summary of the invention
[0005] The present invention aims to solve at least one of the technical problems in the related art to a certain extent. To this end, the first purpose of the present invention is to propose a method for selecting points for the construction control network of a pumped storage power station, which has a coordinate position attribute that is unified with the project through a three-dimensional real-scene model, can read the measurement function of coordinates, elevation, slope and other information, can be in the indoor 360-degree virtual reality scene and highly restore the visualization characteristics of the real terrain and landforms, improve the efficiency of the control network selection, reduce the field work of point selection, save production costs, and realize the accurate point selection of the construction control network of the pumped storage power station.
[0006] The second object of the present invention is to provide a point selection device for the construction control network of a pumped storage power station.
[0007] A third object of the present invention is to provide a computer-readable storage medium.
[0008] A fourth objective of the present invention is to provide a terminal device.
[0009] To achieve the above-mentioned purpose, the first aspect of the embodiment of the present invention proposes a method for selecting points for a construction control network of a pumped-storage power station, the method comprising: obtaining the density, quantity and approximate position of the control points; analyzing the geological conditions, visibility conditions and observation conditions of the approximate position of the control points based on a three-dimensional real-scene model to obtain the position of the initial control point and the observation plan; simulating the position of the initial control point and the observation plan, and determining, based on the simulation results, that the position of the control point and the observation plan meet preset criteria, and using the position of the initial control point and the observation plan as the target control point and the target observation plan.
[0010] According to the method for selecting points for the construction control network of a pumped storage power station according to an embodiment of the present invention, the density, quantity and approximate position of the control points are first obtained, and then the geological conditions, visibility conditions and observation conditions of the approximate position of the control points are analyzed based on the three-dimensional real scene model to obtain the position and observation plan of the initial control points, and finally the position and observation plan of the initial control points are simulated, and when the position and observation plan of the control points meet the preset criteria according to the simulation results, the position and observation plan of the initial control points are used as the target control points and the target observation plan. Therefore, the method has the coordinate position attribute unified with the project through the three-dimensional real scene model, and can read the measurement function of coordinates, elevation, slope and other information, and can restore the visualization features of the real terrain and landforms in the indoor 360-degree virtual reality scene and highly restore the real terrain and landforms, improve the efficiency of point selection of the control network, reduce the field work of point selection, save production costs, and realize the accurate point selection of the construction control network of the pumped storage power station.
[0011] In addition, the method for selecting a point for a construction control network of a pumped storage power station according to the above embodiment of the present invention may also have the following additional technical features:
[0012] According to one embodiment of the present invention, the geological conditions, visibility conditions and observation conditions are analyzed for the approximate position of the control point based on the three-dimensional real scene model, including: performing the geological condition analysis through the surface attachments on the three-dimensional real scene model to determine the soil layer or rock; connecting the control point with the control point, connecting the control point with a specific target, and performing the visibility condition analysis through at least one of the scaling, translation and rotation viewing angles of the three-dimensional real scene model; and performing the observation condition analysis of the environment around the control point through the three-dimensional real scene model.
[0013] According to one embodiment of the present invention, the preset criteria and conditions include: an accuracy criterion of the construction control network, a reliability criterion of the construction control network, and a cost criterion of the construction control network, wherein determining, based on simulation results, whether the positions of the control points and the observation scheme meet the preset criteria and conditions includes: determining the accuracy of the construction control network of the pumped-storage power station based on the project scale and the accuracy of the building layout; determining whether the accuracy criterion of the construction control network of the pumped-storage power station is met based on the accuracy of the construction control network of the pumped-storage power station and whether the mean error of the position and the relative mean error of the side length of the control points in the simulation results meet the accuracy requirements.
[0014] According to one embodiment of the present invention, the reliability criteria of the construction control network include: redundant observation components, internal reliability and external reliability. The positions of the control points and the observation scheme are determined to meet preset criteria based on simulation results, including: when the redundant observation components are within a preset range, the internal reliability is less than a first preset threshold, and the external reliability is less than a second preset threshold, determining that the reliability criteria of the construction control network are met.
[0015] According to an embodiment of the present invention, the cost criterion of the construction control network includes at least one of the number of the control points, point selection cost, construction cost, observation cost, and solution cost.
[0016] According to one embodiment of the present invention, the method further includes: when it is determined according to simulation results that the position of the control point and the observation plan do not meet preset criteria, adjusting the position of the initial control point and determining the corresponding observation plan based on the adjusted control point.
[0017] According to one embodiment of the present invention, the position of the initial control point and the observation scheme are simulated, including: obtaining the project scale and the accuracy of building layout to determine the level of the pumped-storage power station construction control network; determining the observation value direction error and the side length error according to the level; and performing simulation analysis based on the position of the control point, the observation value direction error and the side length error to obtain the simulation result.
[0018] To achieve the above-mentioned purpose, the second embodiment of the present invention proposes a point selection device for the construction control network of a pumped-storage power station, including: an acquisition module, used to obtain the density, number and approximate position of the control points; a first determination module, used to analyze the geological conditions, visibility conditions and observation conditions of the approximate positions of the control points based on a three-dimensional real-scene model, and obtain the positions of the initial control points and the observation plan; a simulation module, used to simulate the positions of the initial control points and the observation plan to obtain simulation results; a second determination module, used to determine the positions of the control points and the observation plan according to the simulation results, and when the positions of the control points and the observation plan meet the preset criteria, the positions of the initial control points and the observation plan are used as the target control points and the target observation plan.
[0019] According to the point selection device of the construction control network of the pumped storage power station of the embodiment of the present invention, the acquisition module obtains the density, quantity and approximate position of the control point; the first determination module analyzes the geological conditions, visibility conditions and observation conditions of the approximate position of the control point based on the three-dimensional real scene model to obtain the position and observation plan of the initial control point; the simulation module simulates the position and observation plan of the initial control point to obtain the simulation result; the second determination module determines that the position and observation plan of the control point meet the preset criteria according to the simulation result, and takes the position and observation plan of the initial control point as the target control point and the target observation plan. Therefore, the device has the coordinate position attribute unified with the project through the three-dimensional real scene model, can read the measurement function of coordinates, elevation, slope and other information, can restore the visualization features of the real terrain and landform in the indoor 360-degree virtual reality scene and height, improve the point selection efficiency of the control network, reduce the field work of point selection, save production costs, and realize the accurate point selection of the construction control network of the pumped storage power station.
[0020] To achieve the above-mentioned purpose, the third aspect of the embodiment of the present invention proposes a computer-readable storage medium, on which a point selection program for the construction control network of a pumped-storage power station is stored. When the point selection program for the construction control network of a pumped-storage power station is executed by a processor, the above-mentioned point selection method for the construction control network of a pumped-storage power station is implemented.
[0021] According to the computer-readable storage medium of an embodiment of the present invention, by executing the above-mentioned method for selecting points for the construction control network of a pumped-storage power station, it is possible to improve the efficiency of point selection of the control network, reduce field work for point selection, save production costs, and realize accurate point selection of the construction control network of a pumped-storage power station in an indoor 360-degree virtual reality scene and highly restore the visualization features of the real terrain and landforms.
[0022] To achieve the above-mentioned purpose, the fourth aspect of the present invention proposes a terminal device, including a memory, a processor, and a pumped-storage power station point selection program stored in the memory and executable on the processor, wherein when the processor executes the pumped-storage power station construction control network point selection program, the above-mentioned pumped-storage power station construction control network point selection method is implemented.
[0023] According to the terminal device of the embodiment of the present invention, by executing the above-mentioned method for selecting points for the construction control network of a pumped-storage power station, it is possible to improve the efficiency of point selection of the control network, reduce field work for point selection, save production costs, and realize accurate point selection of the construction control network of a pumped-storage power station in an indoor 360-degree virtual reality scene and highly restore the visualization features of the real terrain and landforms.
[0024] Additional aspects and advantages of the present invention will be given in part in the following description and in part will be obvious from the following description, or will be learned through practice of the present invention. BRIEF DESCRIPTION OF THE DRAWINGS
[0025] Figure 1 A flow chart of a method for selecting a point for a construction control network of a pumped storage power station according to an embodiment of the present invention;
[0026] Figure 2 A block diagram of a point selection device for a pumped storage power station construction control network according to an embodiment of the present invention;
[0027] Figure 3 FIG. 4 is a block diagram of a terminal device according to an embodiment of the present invention. DETAILED DESCRIPTION
[0028] Embodiments of the present invention are described in detail below, examples of which are shown in the accompanying drawings, wherein the same or similar reference numerals throughout represent the same or similar elements or elements having the same or similar functions. The embodiments described below with reference to the accompanying drawings are exemplary and are intended to be used to explain the present invention, and should not be construed as limiting the present invention.
[0029] The following describes, with reference to the accompanying drawings, a method for selecting a point for a construction control network of a pumped-storage power station, a device for selecting a point for a construction control network of a pumped-storage power station, a computer-readable storage medium, and a terminal device, which are proposed in embodiments of the present invention.
[0030] Figure 1 The present invention is a flowchart of a method for selecting a site for a construction control network of a pumped storage power station according to an embodiment of the present invention.
[0031] like Figure 1 As shown, the method for selecting a point for a construction control network of a pumped storage power station according to an embodiment of the present invention may include the following steps:
[0032] S1, obtain the density, number and approximate location of control points.
[0033] Among them, the density, number and approximate location of the control points are determined according to the layout of the engineering buildings, and the approximate location of the control points can be read or measured on the engineering layout drawing.
[0034] S2, based on the 3D real scene model, the geological conditions, visibility conditions and observation conditions of the approximate position of the control point are analyzed to obtain the position of the initial control point and the observation plan.
[0035] Specifically, the approximate position of the control point is first input into the existing three-dimensional real-life model in the form of coordinates, and the elevation of the point is modified according to the elevation of the point on the model to be presented on the surface of the model in 3D, or the synchronization of the point position is achieved through a platform that can simultaneously load the three-dimensional real-life model and the DLG (Digital Line Graph) vector file, such as the southern three-dimensional data acquisition platform CASS-3D. Then, based on the three-dimensional real-life model, the geological conditions, visibility conditions and observation conditions of the approximate position of the control point are analyzed, and an initial control point position and observation plan that meets both technical requirements and economic and environmental factors can be obtained, thereby ensuring that the selection of the control point is scientific and reasonable. Among them, the position coordinates and observation plan of the initial control point can be exported in the form of documents or graphics.
[0036] It should be understood that geological condition analysis is to analyze the geological structure of the area where the control point is located, assess whether there is a risk of geological disasters such as landslides and mudslides, and study the physical and mechanical properties of the soil and rocks in the area where the control point is located, such as bearing capacity, permeability, etc., to ensure the stability and safety of the control point; line of sight condition analysis is to use a three-dimensional real-scene model to simulate the line of sight between the control point and the observation target to ensure that there is no line of sight obstruction, and evaluate the impact of terrain undulations on the line of sight, such as hills, buildings and other obstacles that may block the line of sight; observation condition analysis is to analyze the environmental factors around the control point, such as temperature, humidity, wind speed, multipath effects, etc. These factors may affect the operation of the observation equipment and the accuracy of the data, and plan the layout of the observation equipment according to the observation needs to ensure the completeness and accuracy of the observation data.
[0037] S3, simulating the position and observation scheme of the initial control point, and determining, based on the simulation results, that the position and observation scheme of the control point meet the preset criteria, taking the position and observation scheme of the initial control point as the target control point and target observation scheme.
[0038] Specifically, after obtaining the position and observation plan of the initial control point in step S2, the position and observation plan of the initial control point can be input into simulation software, such as Tsinghua Shanwei, Wuhan University's COSA, etc., to perform simulation design of the construction control network to obtain simulation results. Then, according to the simulation results, it is judged whether the position and observation plan of the initial control point meet the preset criteria. When the preset criteria are met, the position and observation plan of the initial control point are used as the target control point and target observation plan. The target control point and target observation plan can be output in the form of a graphic to a mobile phone or other mobile terminal that can load an electronic map for use in on-site survey navigation. If the position and observation plan of the initial control point do not meet the requirements of the preset criteria, return to step S2 to reselect the point.
[0039] For example, a pumped storage power station project is located in a city in the southwest. It consists of an upper reservoir, a lower reservoir, a water delivery system, an underground powerhouse cavern group, a ground switch station and other parts. The dam heights of the north-south roller-compacted concrete gravity dam of the upper reservoir and the asphalt concrete face rockfill dam of the lower reservoir are both over 70m. The installed capacity of the power station is 1200MW, which is a large (type I) project. According to the building layout provided by the design, a certain number of control points are arranged at the dam site of the upper reservoir, the dam site of the lower reservoir, the entrance and exit of the water diversion tunnel, the switch station, the construction branch tunnel, the entrance of the traffic safety tunnel, etc., and the point density, number and approximate location are determined, and a CAD drawing of the control point location is made. This case can use the Southern Topographic Cadastral Mapping Software Platform, version CASS11.0. This platform can load three-dimensional real-life models and CAD data sources, and can perform graphic browsing and vector editing. In addition, the accuracy of the three-dimensional real-life model of this case is 20cm, and it was produced by drone and laser radar aerial photography during the feasibility study stage. The approximate position of the control point is input into the 3D real scene model in the form of coordinates. Based on the 3D real scene model, the geological conditions, visibility conditions and observation conditions of the approximate position of the control point are analyzed to obtain an initial control point position and observation plan that meets both technical requirements and economic and environmental factors. Then, the Tsinghua 3D NASEW3.0 adjustment software is used to simulate the design of the construction control network. The results of the simulation design meet the requirements of the preset criteria and form a final point selection plan. The results of the point selection plan can be output in the form of graphics to a mobile phone or other mobile terminal that can load an electronic map for on-site survey and navigation. Based on the electronic map terminal, navigate to the selected point location for on-site survey and field measurement, verify the accuracy and stability of the control point location, make local fine-tuning, determine the final point location, record the traffic route, material transportation route, and foundation form of the point observation mark, and formulate an observation plan.
[0040] Therefore, the present invention uses the virtual reality simulation technology of the three-dimensional real scene model to realize the method of selecting points for the construction control network of the pumped storage power station project with complex terrain conditions, large height difference and many buildings, which has the advantages of high precision, high efficiency, strong adaptability and real-time performance. Through this method, the efficiency of point selection can be significantly improved, the production cost can be reduced, and a strong guarantee can be provided for the smooth construction of the pumped storage power station. At the same time, the method also has a wide range of application prospects and can be extended to other similar engineering projects.
[0041] According to one embodiment of the present invention, the geological conditions, visibility conditions and observation conditions are analyzed for the approximate position of the control point based on the three-dimensional real scene model, including: performing geological condition analysis through surface attachments on the three-dimensional real scene model to determine the soil layer or rock; connecting control points with control points, and connecting control points with specific targets, and performing visibility condition analysis through at least one of the zooming, translation, and rotation perspectives of the three-dimensional real scene model; and performing observation condition analysis on the environment around the control point through the three-dimensional real scene model.
[0042] Specifically, first use the 3D real-life model to identify surface attachments, such as vegetation and buildings, which can indicate the type and characteristics of the soil. Through the model's elevation information and texture analysis, determine the distribution of soil layers or rocks, as well as their physical and mechanical properties. Then, in the 3D real-life model, virtually connect the control points, including the connection between the control points and the connection between the control points and specific targets. Use the model's zoom, translation or rotation function to evaluate the line of sight conditions at different observation heights, the line of sight between control points at different locations, and the line of sight from the control points to different target directions, to ensure that the line of sight between the control points and between the control points and the target to be determined is clear and unobstructed. Then, by looking around and measuring the distribution and distance of objects that interfere with satellite signals or produce multipath effects around the point on the 3D model, measure the ground elevation angles of buildings and vegetation around the point, and complete the analysis of the approximate position of the control point and the observation GNSS conditions.
[0043] According to one embodiment of the present invention, the preset criteria conditions include: the accuracy criteria of the construction control network, the reliability criteria of the construction control network and the cost criteria of the construction control network, wherein determining the positions of the control points and the observation scheme according to the simulation results to meet the preset criteria conditions includes: determining the accuracy of the pumped-storage power station construction control network according to the project scale and the accuracy of the building layout; determining that the accuracy criteria of the construction control network of the pumped-storage power station are met according to the accuracy of the control points in the simulation results and the mean error of the position and the relative mean error of the side length meet the accuracy requirements.
[0044] Specifically, simulation design is based on the three criteria of high accuracy, high reliability and low cost for the construction control network. Among them, the accuracy criterion of the construction control network means that the mean error of the control point and the relative mean error of the side length should not exceed the design requirements; the reliability criterion of the construction control network refers to the measurement of the ability to detect and resist model errors; the cost criterion of the construction control network means that the control network can achieve lower costs while meeting the accuracy criterion and reliability criterion.
[0045] Specifically, the required accuracy of the construction control network of the pumped storage power station is determined according to the project scale and the accuracy requirements of the building layout, where the control network accuracy includes the plane accuracy and elevation accuracy of the point. Then the point position error and the relative mean error of the side length of the control point in the simulation result are extracted, and the point position error and the relative mean error of the side length of the control point are compared with the preset accuracy standard to ensure that the point position error and the relative mean error of the side length of the control point meet the accuracy requirements, so that the position of the control point and the observation plan determine the accuracy criteria of the construction control network.
[0046] According to one embodiment of the present invention, the reliability criteria of the construction control network include: redundant observation components, internal reliability and external reliability, and the location of the control point and the observation scheme are determined to meet the preset criteria according to the simulation results, including: when the redundant observation components are within the preset range, the internal reliability is less than the first preset threshold, and the external reliability is less than the second preset threshold, it is determined that the reliability criteria of the construction control network are met. The first preset threshold and the second preset threshold can be calibrated according to actual conditions, for example, the first preset threshold can be 5, and the second preset threshold can be 3.
[0047] Specifically, the reliability criterion of the control network refers to the measure of the ability to discover and resist model errors, which includes three items: redundant observation components, internal reliability and external reliability. Among them: the redundant observation component is used to reflect whether the observation value is reliable. Its value is between 0 and 1. The larger the value, the better the reliability. However, the increase in the number of observations will lead to an increase in the cost of network construction. Internal reliability refers to the ability of the control network to discover gross errors; external reliability refers to the ability of the measurement system to resist the influence of undetectable gross errors on the adjustment results. It is generally believed that the internal reliability is less than 5 (the first preset threshold) for good, between 5 and 10 for general, and greater than 10 for poor; the external reliability is less than 3 (the second preset threshold) for good, between 3 and 8 for general, and greater than 8 for poor. Therefore, when the redundant observation component of the simulation result is within the preset range, the internal reliability is less than the first preset threshold, and the external reliability is less than the second preset threshold, it can be determined that the location of the control point and the observation plan meet the reliability criterion of the construction control network.
[0048] According to one embodiment of the present invention, the cost criterion of the construction control network includes at least one of the number of control points, point selection cost, construction cost, observation cost, and solution cost.
[0049] Specifically, the cost criterion of the construction control network refers to the control network achieving lower costs while meeting the accuracy and reliability criteria. It mainly includes the number of control points, point selection cost, construction cost, observation cost, solution cost, etc.
[0050] According to one embodiment of the present invention, the above method also includes: when the position of the control point determined according to the simulation results and the observation plan do not meet the preset criteria, adjusting the position of the initial control point and determining the corresponding observation plan based on the adjusted control point.
[0051] Specifically, when the simulation results show that the position of the control point and the observation plan do not meet the preset criteria, corresponding adjustments need to be made. First, the simulation results are reviewed in detail to find out the specific reasons why the control point position and the observation plan do not meet the preset criteria. Then, based on the analysis results, determine the direction in which the control point position needs to be adjusted, such as whether it needs to be raised, lowered, moved or changed in angle. Formulate one or more new positions of the control points and adjusted observation plans, and re-simulate using the new control point positions and observation plans.
[0052] According to one embodiment of the present invention, the position of the initial control point and the observation plan are simulated, including: obtaining the project scale and the accuracy of the building layout to determine the level of the pumped storage power station construction control network; determining the observation value direction error and side length error according to the level; and performing simulation analysis based on the position of the control point, the observation value direction error and the side length error to obtain a simulation result.
[0053] Specifically, since the level and accuracy requirements of the construction control network of the pumped-storage power station are determined according to the project scale and the accuracy of the building layout, the level of the construction control network of the pumped-storage power station can be determined according to the project scale and the accuracy of the building layout, and then the prior values of the observed value direction error and side length error can be set in the simulation software according to the level of the construction control network. Then, the position of the control point (point coordinates) is input into the simulation software according to the observation information text file corresponding to the observation plan, and the position of the control point, the observed value direction error and the side length error are simulated and analyzed to obtain the simulation results.
[0054] According to the method for selecting points for the construction control network of a pumped storage power station according to an embodiment of the present invention, the density, quantity and approximate position of the control points are first obtained, and then the geological conditions, visibility conditions and observation conditions of the approximate position of the control points are analyzed based on the three-dimensional real scene model to obtain the position and observation plan of the initial control points, and finally the position and observation plan of the initial control points are simulated, and when the position and observation plan of the control points meet the preset criteria according to the simulation results, the position and observation plan of the initial control points are used as the target control points and the target observation plan. Therefore, the method has the coordinate position attribute unified with the project through the three-dimensional real scene model, and can read the measurement function of coordinates, elevation, slope and other information, and can restore the visualization features of the real terrain and landforms in the indoor 360-degree virtual reality scene and highly restore the real terrain and landforms, improve the efficiency of point selection of the control network, reduce the field work of point selection, save production costs, and realize the accurate point selection of the construction control network of the pumped storage power station.
[0055] Corresponding to the above-mentioned embodiment, the present invention also proposes a point selection device for a construction control network of a pumped storage power station.
[0056] Figure 2 It is a block diagram of a point selection device for a construction control network of a pumped storage power station according to an embodiment of the present invention.
[0057] like Figure 2 As shown, the point selection device 100 of the construction control network of a pumped storage power station according to the embodiment of the present invention may include: an acquisition module 110 , a first determination module 120 , a simulation module 130 and a second determination module 140 .
[0058] Among them, the acquisition module 110 is used to obtain the density, number and approximate position of the control points. The first determination module 120 is used to analyze the geological conditions, visibility conditions and observation conditions of the approximate position of the control points based on the three-dimensional real scene model to obtain the position of the initial control points and the observation plan. The simulation module 130 is used to simulate the position of the initial control points and the observation plan to obtain the simulation results. The second determination module 140 is used to determine that the position of the control points and the observation plan meet the preset criteria according to the simulation results, and use the position of the initial control points and the observation plan as the target control points and the target observation plan.
[0059] According to one embodiment of the present invention, the first determination module 120 analyzes the geological conditions, visibility conditions and observation conditions of the approximate position of the control point based on the three-dimensional real scene model, and is specifically used to analyze the geological conditions through the surface attachments on the three-dimensional real scene model to determine the soil layer or rock; connect the control points with the control points, and the control points with specific targets, and analyze the visibility conditions through at least one of the scaling, translation, and rotation perspectives of the three-dimensional real scene model; and analyze the observation conditions of the environment around the control point through the three-dimensional real scene model.
[0060] According to one embodiment of the present invention, the preset criteria conditions include: the accuracy criteria of the construction control network, the reliability criteria of the construction control network and the cost criteria of the construction control network, wherein the second determination module 140 determines whether the position of the control point and the observation scheme meet the preset criteria conditions according to the simulation results, and is specifically used to determine the accuracy of the construction control network of the pumped-storage power station according to the project scale and the accuracy of the building layout; based on the accuracy of the construction control network of the pumped-storage power station and the point position mean error and the relative mean error of the side length of the control point in the simulation results meeting the accuracy requirements, determine whether the accuracy criteria of the construction control network are met.
[0061] According to one embodiment of the present invention, the reliability criteria of the construction control network include: redundant observation components, internal reliability and external reliability. The second determination module 140 determines whether the position of the control point and the observation scheme meet the preset criteria based on the simulation results. Specifically, it is used to determine whether the reliability criteria of the construction control network are met when the redundant observation components are within a preset range, the internal reliability is less than a first preset threshold, and the external reliability is less than a second preset threshold.
[0062] According to one embodiment of the present invention, the cost criterion of the construction control network includes at least one of the number of control points, point selection cost, construction cost, observation cost, and solution cost.
[0063] According to one embodiment of the present invention, the second determination module 140 is also used to adjust the position of the initial control point and determine the corresponding observation plan based on the adjusted control point when the position of the control point and the observation plan determined according to the simulation results do not meet the preset criteria.
[0064] According to one embodiment of the present invention, the simulation module 130 simulates the position and observation plan of the initial control point, specifically for obtaining the project scale and the accuracy of the building layout to determine the level of the pumped-storage power station construction control network; determining the direction error and side length error of the observation value according to the level; performing simulation analysis based on the position of the control point, the direction error and side length error of the observation value, and obtaining the simulation result.
[0065] It should be noted that for details not disclosed in the point selection device for the construction control network of the pumped-storage power station in the embodiment of the present invention, please refer to the details disclosed in the point selection method for the construction control network of the pumped-storage power station in the embodiment of the present invention, and the details will not be repeated here.
[0066] According to the point selection device of the construction control network of the pumped storage power station of the embodiment of the present invention, the acquisition module obtains the density, quantity and approximate position of the control point; the first determination module analyzes the geological conditions, visibility conditions and observation conditions of the approximate position of the control point based on the three-dimensional real scene model to obtain the position and observation plan of the initial control point; the simulation module simulates the position and observation plan of the initial control point to obtain the simulation result; the second determination module determines that the position and observation plan of the control point meet the preset criteria according to the simulation result, and takes the position and observation plan of the initial control point as the target control point and the target observation plan. Therefore, the device has the coordinate position attribute unified with the project through the three-dimensional real scene model, can read the measurement function of coordinates, elevation, slope and other information, can restore the visualization features of the real terrain and landform in the indoor 360-degree virtual reality scene and height, improve the point selection efficiency of the control network, reduce the field work of point selection, save production costs, and realize the accurate point selection of the construction control network of the pumped storage power station.
[0067] Corresponding to the above embodiment, the present invention also proposes a computer-readable storage medium.
[0068] The computer-readable storage medium of an embodiment of the present invention stores a point selection program for a construction control network of a pumped-storage power station. When the point selection program for the construction control network of a pumped-storage power station is executed by a processor, the above-mentioned point selection method for the construction control network of a pumped-storage power station is implemented.
[0069] According to the computer-readable storage medium of an embodiment of the present invention, by executing the above-mentioned method for selecting points for the construction control network of a pumped-storage power station, it is possible to improve the efficiency of point selection of the control network, reduce field work for point selection, save production costs, and realize accurate point selection of the construction control network of a pumped-storage power station in an indoor 360-degree virtual reality scene and highly restore the visualization features of the real terrain and landforms.
[0070] Corresponding to the above embodiment, the present invention further proposes a point selection device for a terminal device.
[0071] Figure 3 FIG. 4 is a block diagram of a terminal device according to an embodiment of the present invention.
[0072] like Figure 3 As shown, the terminal device 200 of the embodiment of the present invention includes a memory 210, a processor 220, and a point selection program for a pumped-storage power station stored in the memory 210 and executable on the processor 220. When the processor 220 executes the point selection program for the construction control network of the pumped-storage power station, the above-mentioned point selection method for the construction control network of the pumped-storage power station is implemented.
[0073] According to the terminal device of the embodiment of the present invention, by executing the above-mentioned method for selecting points for the construction control network of a pumped-storage power station, it is possible to improve the efficiency of point selection of the control network, reduce field work for point selection, save production costs, and realize accurate point selection of the construction control network of a pumped-storage power station in an indoor 360-degree virtual reality scene and highly restore the visualization features of the real terrain and landforms.
[0074] It should be noted that the logic and / or steps represented in the flowchart or otherwise described herein, for example, can be considered as a sequenced list of executable instructions for implementing logical functions, and can be specifically implemented in any computer-readable medium for use by an instruction execution system, device or apparatus (such as a computer-based system, a system including a processor, or other system that can fetch instructions from an instruction execution system, device or apparatus and execute instructions), or in combination with these instruction execution systems, devices or apparatuses. For the purposes of this specification, "computer-readable medium" can be any device that can contain, store, communicate, propagate or transmit a program for use by an instruction execution system, device or apparatus, or in combination with these instruction execution systems, devices or apparatuses. More specific examples of computer-readable media (a non-exhaustive list) include the following: an electrical connection portion with one or more wirings (electronic device), a portable computer disk box (magnetic device), a random access memory (RAM), a read-only memory (ROM), an erasable and programmable read-only memory (EPROM or flash memory), an optical fiber device, and a portable compact disk read-only memory (CDROM). In addition, the computer-readable medium may even be paper or other suitable medium on which the program is printed, since the program may be obtained electronically, for example, by optically scanning the paper or other medium and then editing, interpreting or processing in other suitable ways if necessary, and then stored in a computer memory.
[0075] In the description of this specification, the description with reference to the terms "one embodiment", "some embodiments", "examples", "specific examples", or "some examples" means that the specific features, structures, materials or characteristics described in conjunction with the embodiment or example are included in at least one embodiment or example of the present invention. In this specification, the schematic representation of the above terms does not necessarily refer to the same embodiment or example. Moreover, the specific features, structures, materials or characteristics described may be combined in any one or more embodiments or examples in a suitable manner.
[0076] In addition, the terms "first" and "second" are used for descriptive purposes only and should not be understood as indicating or implying relative importance or implicitly indicating the number of the indicated technical features. Therefore, the features defined as "first" and "second" may explicitly or implicitly include at least one of the features. In the description of the present invention, the meaning of "plurality" is at least two, such as two, three, etc., unless otherwise clearly and specifically defined.
[0077] In the present invention, unless otherwise clearly specified and limited, the terms "installed", "connected", "connected", "fixed" and the like should be understood in a broad sense, for example, it can be a fixed connection, a detachable connection, or an integral connection; it can be a mechanical connection or an electrical connection; it can be a direct connection or an indirect connection through an intermediate medium, it can be the internal connection of two elements or the interaction relationship between two elements, unless otherwise clearly defined. For ordinary technicians in this field, the specific meanings of the above terms in the present invention can be understood according to specific circumstances.
[0078] Although the embodiments of the present invention have been shown and described above, it is to be understood that the above embodiments are exemplary and are not to be construed as limitations of the present invention. A person skilled in the art may change, modify, replace and vary the above embodiments within the scope of the present invention.
Claims
1. A method for selecting a site for a construction control network of a pumped storage power station, characterized in that: The method comprises: Obtaining density, number and approximate locations of control points; Analyze the geological conditions, visibility conditions and observation conditions of the approximate positions of the control points based on the three-dimensional real scene model to obtain the positions of the initial control points and the observation plan; The position of the initial control point and the observation plan are simulated, and when it is determined based on the simulation results that the position of the control point and the observation plan meet preset criteria, the position of the initial control point and the observation plan are used as the target control point and the target observation plan.
2. The point selection method according to claim 1, characterized in that: The geological conditions, visibility conditions and observation conditions of the approximate location of the control point are analyzed based on the three-dimensional real scene model, including: The geological condition analysis is performed through the surface attachments on the three-dimensional real scene model to determine the soil layer or rock; Connecting the control points with the control points, connecting the control points with a specific target, and performing line of sight condition analysis by at least one of scaling, translating, and rotating the viewing angle of the three-dimensional real scene model; The observation conditions of the environment around the control point are analyzed through the three-dimensional real scene model.
3. The point selection method according to claim 1, characterized in that: The preset criteria include: the accuracy criteria of the construction control network, the reliability criteria of the construction control network and the cost criteria of the construction control network, wherein determining the position of the control point and the observation scheme according to the simulation results to meet the preset criteria includes: Determine the accuracy of the construction control network of the pumped storage power station according to the project scale and the accuracy of the building layout; According to the accuracy of the construction control network of the pumped storage power station and the point position mean error and side length relative mean error of the control points in the simulation results meeting the accuracy requirements, the accuracy criterion for satisfying the construction control network is determined.
4. The point selection method according to claim 3, characterized in that: The reliability criteria of the construction control network include: redundant observation components, internal reliability and external reliability. The positions of the control points and the observation schemes are determined according to the simulation results to meet the preset criteria, including: When the redundant observation component is within a preset range, the internal reliability is less than a first preset threshold, and the external reliability is less than a second preset threshold, it is determined that the reliability criterion of the construction control network is met.
5. The point selection method according to claim 3, characterized in that: The cost criteria of the construction control network include at least one of the number of control points, point selection cost, construction cost, observation cost, and solution cost.
6. The point selection method according to claim 1, characterized in that: The method further comprises: When it is determined according to the simulation results that the position of the control point and the observation scheme do not meet the preset criteria, the position of the initial control point is adjusted, and the corresponding observation scheme is determined according to the adjusted control point.
7. The point selection method according to claim 1, characterized in that: The position of the initial control point and the observation scheme are simulated, including: Obtaining the project scale and the accuracy of building layout to determine the level of the pumped storage power station construction control network; Determining the direction error and the side length error of the observation value according to the level; The simulation result is obtained by performing simulation analysis based on the position of the control point, the direction error of the observation value and the side length error.
8. A point selection device for a construction control network of a pumped storage power station, characterized in that: include: An acquisition module, used to acquire the density and quantity of control points and the approximate positions of the control points; A first determination module is used to analyze the geological conditions, visibility conditions and observation conditions of the approximate positions of the control points based on the three-dimensional real scene model to obtain the positions of the initial control points and the observation plan; A simulation module, used for simulating the position of the initial control point and the observation scheme to obtain a simulation result; The second determination module is used to determine, based on the simulation results, that when the position of the control point and the observation plan meet preset criteria, use the position of the initial control point and the observation plan as the target control point and the target observation plan.
9. A computer-readable storage medium, characterized in that: A point selection program for a pumped-storage power station construction control network is stored thereon, and when the point selection program for the pumped-storage power station construction control network is executed by a processor, a point selection method for a pumped-storage power station construction control network according to any one of claims 1-7 is implemented.
10. A terminal device, characterized in that: The invention comprises a memory, a processor and a point selection program for a construction control network of a pumped-storage power station which is stored in the memory and can be run on the processor. When the processor executes the point selection program for the construction control network of the pumped-storage power station, a point selection method for the construction control network of a pumped-storage power station is implemented according to any one of claims 1 to 7.