Operation and maintenance control method and system for substation equipment and related device

By obtaining and analyzing the target substation data sets of substation equipment, monitoring safety signals, performing safety evaluation and adjustment control, the problem of inefficiency in traditional operation and maintenance methods is solved, and the operation efficiency of the substation and the safety of the power grid are improved.

CN119051272APending Publication Date: 2024-11-29SHENZHEN POWER SUPPLY BUREAU
View PDF 0 Cites 0 Cited by

Patent Information

Application Number
CN202411248203.2
Authority / Receiving Office
CN · China
Patent Type
Applications(China)
Current Assignee / Owner
Filing Date
2024-09-05
Publication Date
2024-11-29

Smart Images

  • Figure CN119051272A_ABST
    Figure CN119051272A_ABST
Patent Text Reader

Abstract

The embodiment of the invention discloses an operation and maintenance control method and system for substation equipment and a related device. By adopting the embodiment of the invention, the operation state of the substation equipment is monitored in real time, the signal data of the substation equipment is subjected to safety judgment, then the substation equipment is subjected to safety evaluation, and corresponding operation and maintenance suggestions are provided according to the safety evaluation value, so that the response speed of substation operation and maintenance is accelerated, and the safety of the substation equipment is improved. And the operation efficiency of the transformer substation is improved.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The present application relates to the field of electric power technology, and in particular to an operation and maintenance control method, system and related devices for substation equipment. Background Art

[0002] A substation is a place in the power system that transforms voltage and current, receives electric energy and distributes electric energy. The substation in a power plant is a step-up substation, and its function is to step up the voltage of the electric energy generated by the generator and feed it into the high-voltage power grid. At the same time, the substation requires real-time monitoring by staff to avoid operational failures and inadequate maintenance.

[0003] With the growth of power demand and the development of technology, substation equipment is becoming increasingly complex, and its operation and maintenance management faces higher requirements. The traditional operation and maintenance method relies on manual monitoring and regular inspections. This method is not only inefficient, but also difficult to respond to the rapid changes in equipment status in real time, and there are dual problems of safety risks and high operation and maintenance costs.

[0004] Therefore, how to achieve real-time monitoring and intelligent analysis of the operating status of substation equipment to improve the operating efficiency of the substation, reduce maintenance costs, and enhance the reliability and security of the power grid has become an urgent problem to be solved. Summary of the invention

[0005] The embodiments of the present application provide an operation and maintenance control method, system and related devices for substation equipment. By real-time monitoring and intelligent analysis of the operating status of the substation equipment, safety judgment of operation and maintenance is made based on the processing and analysis results, thereby facilitating rapid management and adjustment of the operation and maintenance of the substation, thereby improving the operating efficiency of the substation, reducing maintenance costs, and enhancing the reliability and safety of the power grid.

[0006] In a first aspect, an embodiment of the present application provides an operation and maintenance control method for substation equipment, including:

[0007] Obtain a target substation data group of substation equipment within a preset time period; the target substation data group includes: substation data, operation start time data, operation end time data, operation frequency data, operation noise data, substation zero point data, substation maintenance point data, substation start data, and substation life data;

[0008] Evaluate the operating status of the substation equipment according to the target substation data group to obtain a target safety data group; the target safety data group includes a replacement safety range value and a maintenance safety range value;

[0009] Monitor the safety signal of the substation equipment according to the target substation data group to obtain a target substation signal group; the target substation signal group includes a frequency separation signal and a noise separation signal;

[0010] Performing a safety evaluation on the substation equipment according to the target safety data group and the target substation signal group to obtain a target safety evaluation value;

[0011] The substation equipment is regulated and controlled according to the target safety evaluation value.

[0012] In a second aspect, an embodiment of the present application provides an operation and maintenance control system for substation equipment, including:

[0013] An acquisition unit is used to acquire a target substation data group of substation equipment within a preset time period; the target substation data group includes: substation data, operation start time data, operation end time data, operation frequency data, operation noise data, substation zero point data, substation maintenance point data, substation start data, and substation life data;

[0014] A first analysis unit is used to evaluate the operating status of the substation equipment according to the target substation data group to obtain a target safety data group; the target safety data group includes a replacement safety range value and a maintenance safety range value;

[0015] A second analysis unit is used to monitor the safety signal of the substation equipment according to the target substation data group to obtain a target substation signal group; the target substation signal group includes a frequency separation signal and a noise separation signal;

[0016] An evaluation unit, configured to perform a safety evaluation on the substation equipment according to the target safety data group and the target substation signal group to obtain a target safety evaluation value;

[0017] A control unit is used to adjust and control the substation equipment according to the target safety evaluation value.

[0018] In a third aspect, an embodiment of the present application provides an electronic device, comprising: a processor, a memory, a communication interface, and one or more programs, wherein the one or more programs are stored in the memory and configured to be executed by the processor, and the program includes instructions for executing the steps in the first aspect of the embodiment of the present application.

[0019] In a fourth aspect, an embodiment of the present application provides a computer-readable storage medium, wherein the computer-readable storage medium stores a computer program for electronic data exchange, wherein the computer program enables a computer to execute part or all of the steps described in the first aspect of the embodiment of the present application.

[0020] In a fifth aspect, an embodiment of the present application provides a computer program product, wherein the computer program product includes a non-transitory computer-readable storage medium storing a computer program, and the computer program is operable to cause a computer to execute some or all of the steps described in the first aspect of the embodiment of the present application. The computer program product may be a software installation package.

[0021] By implementing the embodiments of the present application, first obtain a target substation data group of substation equipment within a preset time period; the target substation data group includes: substation data, operation start time data, operation end time data, operation frequency data, operation noise data, substation zero point data, substation maintenance point data, substation start data, and substation life data; evaluate the operating status of the substation equipment according to the target substation data group to obtain a target safety data group; the target safety data group includes a replacement safety range value and a maintenance safety range value; monitor the safety signal of the substation equipment according to the target substation data group to obtain a target substation signal group; the target substation signal group includes a frequency separation signal and a noise separation signal; perform a safety evaluation on the substation equipment according to the target safety data group and the target substation signal group to obtain a target safety evaluation value; adjust and control the substation equipment according to the target safety evaluation value. The present application monitors the operating status of substation equipment in real time, makes safety judgments on the signal data of substation equipment, and then conducts safety evaluation on the substation equipment, and makes corresponding operation and maintenance suggestions based on the safety evaluation values, thereby speeding up the response speed of substation operation and maintenance and improving the operation efficiency of the substation. BRIEF DESCRIPTION OF THE DRAWINGS

[0022] In order to more clearly illustrate the technical solutions in the embodiments of the present application or the background technology, the drawings required for use in the embodiments of the present application or the background technology will be described below.

[0023] Figure 1 It is a flow chart of an operation and maintenance control method of a substation equipment provided by an embodiment of the present application;

[0024] Figure 2 This is a system architecture diagram of an operation and maintenance control system for a substation equipment provided by an embodiment of the present application;

[0025] Figure 3 This is a system architecture diagram of another operation and maintenance control system of a substation equipment provided in an embodiment of the present application;

[0026] Figure 4 It is a structural schematic diagram of an electronic device proposed in an embodiment of the present application. DETAILED DESCRIPTION

[0027] In order to enable those skilled in the art to better understand the solution of the present application, the technical solution in the embodiments of the present application will be clearly and completely described below in conjunction with the drawings in the embodiments of the present application. Obviously, the described embodiments are only part of the embodiments of the present application, not all of the embodiments. Based on the embodiments in the present application, all other embodiments obtained by ordinary technicians in this field without creative work are within the scope of protection of this application.

[0028] The terms "first", "second", etc. in the specification and claims of this application and the above-mentioned drawings are used to distinguish different objects, rather than to describe a specific order. In addition, the terms "including" and "having" and any variations thereof are intended to cover non-exclusive inclusions. For example, a process, method, system, product or device that includes a series of steps or units is not limited to the listed steps or units, but optionally includes steps or units that are not listed, or optionally includes other steps or units inherent to these processes, methods, products or devices.

[0029] Reference to "embodiments" herein means that a particular feature, structure, or characteristic described in conjunction with the embodiments may be included in at least one embodiment of the present application. The appearance of the phrase in various locations in the specification does not necessarily refer to the same embodiment, nor is it an independent or alternative embodiment that is mutually exclusive with other embodiments. It is explicitly and implicitly understood by those skilled in the art that the embodiments described herein may be combined with other embodiments.

[0030] The following is an explanation of the relevant contents, concepts, meanings, technical issues, technical solutions, beneficial effects, etc. involved in the embodiments of the present application.

[0031] See also Figure 1 , Figure 1 1 is a flow chart of an operation and maintenance control method for substation equipment provided by an embodiment of the present application, the method includes but is not limited to the following steps:

[0032] S101. Obtain a target substation data group of substation equipment within a preset time period.

[0033] Among them, the target substation data group includes: substation data, operation start time data, operation end time data, operation frequency data, operation noise data, substation zero point data, change time data, substation time data, substation point data, substation start data, and substation life data.

[0034] The preset time period may be a system default or pre-set time period. It is mainly determined based on the maintenance cycle, operation log or specific analysis requirements of the substation equipment. For example, the preset time period may be the last 24 hours, the last week or the entire time period since the last maintenance.

[0035] Among them, the substation equipment is responsible for the conversion, distribution, protection and regulation of electricity, which can be transformers, circuit breakers, disconnect switches, voltage transformers, current transformers, lightning arresters, capacitors and reactors, etc., without limitation here.

[0036] Specifically, by installing sensors on key equipment in the substation, such as temperature sensors, vibration sensors, sound sensors, and electrical parameter sensors, and collecting data on the operation and maintenance of substation equipment within a preset time period from the sensors through a data acquisition system, the operation and maintenance data of the substation equipment can be obtained. The operation and maintenance data are divided into variable operation data and variable dimension data, wherein the variable operation data includes: operation start time data, operation end time data, operation frequency data, and operation noise data, and the variable dimension data includes: variable solid data, variable zero point data, change time data, variable dimension time data, variable dimension point data, variable equipment start data, and variable equipment life data. A target substation data group is constructed based on the variable operation data and variable dimension data, and performance analysis, status monitoring, and maintenance decisions can be made on the substation equipment based on the target substation data group.

[0037] It should be noted that the variable solid data is the substation equipment data, which can be the model, rated power and other data of the substation equipment. The operation start time data is the time point when the substation equipment starts to operate each time, the operation end time data is the time point when the substation equipment ends to operate each time, the operation frequency data is the vibration frequency of the substation equipment each time it operates, the operation noise data is the noise level of the substation equipment each time it operates, the variable zero point data is the time point when the internal parts of the substation equipment are replaced each time, the change time data is the length of time it takes for the substation equipment to replace parts each time, the variable maintenance time data is the length of time required for each maintenance of the substation equipment, the variable maintenance point data is the time point when the substation equipment is maintained each time, the variable equipment start data is the time when the substation equipment is put into use, and the variable equipment life data is the elimination time of the substation equipment.

[0038] S102: Evaluate the operating status of the substation equipment according to the target substation data group to obtain a target safety data group.

[0039] The target safety data group includes a replacement safety range value and a maintenance safety range value.

[0040] Among them, the operating status refers to the actual operating conditions and performance of the substation equipment within a preset time period, usually including the working efficiency, stability, whether there are abnormal conditions, etc. of the substation equipment. In this embodiment of the application, the performance of the substation equipment when replacing parts or performing repairs is evaluated and predicted based on the replacement safety range value and the maintenance safety range value.

[0041] Specifically, the number of times parts are replaced and repairs are performed during the entire operation cycle of the substation equipment is analyzed, and the operating performance of the substation equipment is judged based on the number of times parts are replaced and repairs are performed. By evaluating the replacement safety range value and repair safety range value of the substation equipment, preventive maintenance can be implemented to reduce the problems of unexpected downtime and emergency repairs of substation equipment, thereby improving the working efficiency of the substation equipment.

[0042] Optionally, the above step S102, evaluating the operating status of the substation equipment according to the target substation data group to obtain a target safety data group, may also include the following steps:

[0043] A21, determining a plurality of operation start time data, a plurality of operation end time data, a plurality of change zero point data, and a plurality of change dimension point data in the target power transformation data group;

[0044] A22, determining a plurality of operation time periods according to the plurality of operation start time data and the plurality of operation end time data;

[0045] A23, matching the plurality of zero-point data with the plurality of operating time periods to obtain a plurality of replacement number value groups; each replacement number value group includes a plurality of replacement number values;

[0046] A24, matching the multiple dimension change point data with the multiple operating time periods to obtain multiple maintenance number value groups;

[0047] A25, performing range value processing according to the plurality of replacement number value groups to obtain the replacement safety range value;

[0048] A26, performing range value processing according to the plurality of maintenance frequency value groups to obtain the maintenance safety range value;

[0049] A27. Construct the target safety data group according to the replacement safety range value and the maintenance safety range value.

[0050] Specifically, after obtaining the operating data of the substation equipment within a preset time period, multiple start time data, multiple end time data, multiple zero point data, and multiple dimension point data in the target substation data group can be determined, among which the start time data and the end time data are used to determine the operating time period of the substation equipment. It should be noted that the operating time period includes the time when the substation equipment replaces parts or performs repairs.

[0051] Further, multiple operation time periods can be determined based on multiple operation start time data and multiple operation end time data. For each operation time period, it is checked whether there is a part replacement event in the time period. The zero point data can be matched with the operation time period. If there is a corresponding time point in the operation time period that successfully matches the zero point data, a replacement signal is generated, indicating that the substation equipment has undergone a part replacement. Otherwise, a first normal signal is generated, indicating that the substation equipment has not undergone a part replacement. At the same time, it is checked whether there is a maintenance event in the time period. The dimension change point data can be matched with the operation time period. If there is a corresponding time point in the operation time period that successfully matches the dimension change point data, a maintenance signal is generated, indicating that the substation equipment has undergone maintenance. Otherwise, a second normal signal is generated, indicating that the substation equipment has not undergone maintenance. Further, the number of times the replacement signal appears in the operation time period is calibrated as the replacement number value. The replacement number value in a period of operation time forms a replacement number value group, and then multiple replacement number value groups are formed according to multiple operation time periods. At the same time, multiple maintenance number value groups are formed according to multiple operation time periods.

[0052] Furthermore, by performing range value processing based on multiple replacement number value groups, a replacement safety range value can be obtained, and by performing range value processing based on multiple maintenance number value groups, a maintenance safety range value can be obtained. A target safety data group can be constructed based on the replacement safety range value and the maintenance safety range value, and accurate matching of replacement and maintenance events can be achieved based on the target safety data group, so as to reasonably plan the maintenance plan of the substation equipment.

[0053] Optionally, the above step A25, performing range value processing according to the multiple replacement number value groups to obtain the replacement safety range value, may also include the following steps:

[0054] B21, selecting the replacement number value with the largest number of occurrences from the plurality of replacement number value groups to obtain a target replacement mode value;

[0055] B22, determining an average value of the number of replacements according to the plurality of replacement number value groups, and obtaining a target replacement average value;

[0056] B23, performing difference calculation on the target replacement mode value and the target replacement mean value to obtain a target replacement difference;

[0057] B24, determining a target replacement floating value according to the target replacement difference and a preset replacement weight coefficient;

[0058] B25. Determine the replacement safety range value according to the target replacement mode value and the target replacement floating value.

[0059] Specifically, the replacement number value with the largest number of occurrences is selected from multiple replacement number value groups as the target replacement mode value, and the average value of the replacement number is determined based on the multiple replacement number value groups to obtain the target replacement average value, the target replacement mode value and the target replacement average value are difference calculated to obtain the target replacement difference, the target replacement difference and the preset replacement weight coefficient are substituted into the calculation formula of the target replacement floating value, wherein the calculation formula of the target replacement floating value is: replacement floating value = replacement difference / 2×replacement weight coefficient, wherein the preset replacement weight coefficient is the system default or pre-set, which can be determined through historical maintenance data, and the impact of different replacement frequencies on the safety and performance of substation equipment is analyzed to determine the replacement weight coefficient. For example, the replacement frequency is compared with the maintenance frequency, and the impact of replacement or maintenance at the same frequency on the safety and performance of substation equipment is analyzed to determine the weight coefficients corresponding to the two frequencies.

[0060] Furthermore, the replacement safety range value can be determined based on the target replacement mode value and the target replacement floating value. The replacement safety range value can be expressed as: replacement safety range value = replacement mode value ± replacement floating value. The replacement safety range value is determined by adding or subtracting the target replacement floating value with the target replacement mode value as the center.

[0061] Optionally, the maintenance safety range value can be determined by the maintenance mode value and the maintenance floating value, and the maintenance safety range value can be expressed as: maintenance safety range value=maintenance mode value±maintenance floating value.

[0062] It can be seen that by calculating the replacement safety range value and the maintenance safety range value, the safe replacement frequency range of substation equipment and the maintenance frequency range of equipment can be accurately planned to avoid excessive or insufficient replacement to ensure the improvement of substation equipment reliability and stability. At the same time, reasonable replacement of substation equipment parts and equipment maintenance can reduce maintenance costs and avoid equipment failures caused by untimely replacement or maintenance.

[0063] Optionally, the actual operating time of the substation equipment can also be evaluated based on the target substation data group. The actual operating time can be used to evaluate the operating status of the substation equipment. Since the entire operating time period of the substation equipment includes the time when the substation equipment replaces parts or performs repairs, the actual operating time of the substation equipment is determined by calculating the time when the substation equipment replaces parts or performs repairs.

[0064] Specifically, the first operation start time data and the last operation end time data of the substation equipment are obtained, and the difference between the two is calculated to calculate the total operation time value. The calculation formula for the actual operation time value is as follows:

[0065]

[0066] In the above formula, Y i is the actual duration value of the i-th substation equipment, is the total running time value; It is the floating runtime value; is the replacement times value; To change the runtime value; is the number of maintenance times; pc is the deviation correction factor calculated from the actual duration.

[0067] Among them, multiple change time data and multiple dimension change time data in the target substation data group are determined, each change time data corresponds to a replacement number, and each dimension change time data corresponds to a maintenance number. Then, the average change time of multiple change time data is calculated to obtain the floating operation duration value, and the average dimension change time of multiple dimension change time data is calculated to obtain the change operation duration value. Among them, pc is the deviation correction factor of the actual duration value calculation, which is used to adjust the calculation result to reflect the deviation in actual operation.

[0068] In one possible embodiment, the actual operating time can be calculated to evaluate whether the substation equipment meets the operating standards. Based on the actual operating time and the standard safety data group, possible failures of the substation equipment can be predicted, so that corresponding measures can be taken in advance to optimize the operating efficiency of the substation equipment.

[0069] S103: Monitor the safety signals of the substation equipment according to the target substation data group to obtain a target substation signal group.

[0070] Among them, the target substation signal group includes frequency separation signals and noise separation signals.

[0071] Specifically, the operating frequency, noise level, temperature and other parameters of the substation equipment are monitored according to the target substation data group to obtain the safety signal of the substation equipment, and different measures are taken according to different safety signals to help timely detect abnormalities of the substation equipment or predict the occurrence of failures.

[0072] Among them, the frequency separation signal includes a frequency increase signal, a frequency decrease signal, a frequency level signal, a frequency increase unchanged signal, a frequency decrease unchanged signal, a frequency level unchanged signal, a frequency increase bad signal, a frequency decrease bad signal and a frequency level bad signal. Each frequency signal is assigned a value in turn, and the assigned value is a safety identification value of each frequency signal. For example, the frequency increase signal is assigned a value of 9, the frequency decrease signal is assigned a value of 8, and the frequency level signal is assigned a value of 7. The larger the assigned value, the higher the safety of the substation equipment. The noise separation signal includes a noise increase signal, a noise decrease signal, a noise level signal, a noise increase unchanged signal, a noise decrease unchanged signal, a noise level unchanged signal, a noise increase bad signal, a noise decrease bad signal and a noise level bad signal. Each noise signal also corresponds to an assigned identification value.

[0073] Optionally, the above step S103, monitoring the safety signal of the substation equipment according to the target substation data group to obtain the target substation signal group, may also include the following steps:

[0074] A31, determining a plurality of operating frequency data, a plurality of operating noise data, a transformer startup data, and a transformer life data in the target transformer data group; each operating frequency data corresponds to a time point; each operating noise data corresponds to a time point;

[0075] A32, fitting is performed according to the multiple operating frequency data and the time point corresponding to each operating frequency data to obtain a target frequency fluctuation curve; the origin of the target frequency fluctuation curve is the variable input start data, the horizontal axis of the target frequency fluctuation curve is time and the vertical axis is the operating frequency;

[0076] A33. Analyze the change trend of the operating frequency according to the target frequency fluctuation curve to obtain a frequency change signal group; the frequency change signal group includes: a frequency increase signal, a frequency flat signal, and a frequency decrease signal;

[0077] A34, determining the frequency signal according to the variable life data and the frequency change signal group;

[0078] A35. Fitting is performed according to the multiple noise data and the time point corresponding to each noise data to obtain a target noise fluctuation curve; the origin of the target noise fluctuation curve is the variable setting initial data, the horizontal axis of the target noise fluctuation curve is time and the vertical axis is noise;

[0079] A36. Analyze the noise change trend according to the target noise fluctuation curve to obtain a noise change signal group;

[0080] A37, determining the noise separation signal according to the variable life data and the noise change signal group;

[0081] A38. Construct the target substation signal group according to the frequency separation signal and the noise separation signal.

[0082] Specifically, multiple operating frequency data, multiple operating noise data, transformer startup data, and transformer life data in the target substation data group are determined, each operating frequency data corresponds to a time point, and each operating noise data corresponds to a time point. The transformer startup data is taken as the origin, and fitting is performed according to the multiple operating frequency data and the time point corresponding to each operating frequency data to obtain a target frequency fluctuation curve, wherein the horizontal axis of the target frequency fluctuation curve is time and the vertical axis is the operating frequency.

[0083] Furthermore, the change trend of the operating frequency is analyzed according to the target frequency fluctuation curve to obtain a frequency change signal group, which includes: frequency increase signal, frequency level signal, frequency reduction signal, which indicates the increase, stability or decrease trend of the operating frequency of the substation equipment. Then, the relationship between the elimination time of the substation equipment and the change in each frequency change signal is analyzed, and a frequency signal is set according to each change relationship. The frequency signal is used to indicate the life of the substation equipment in different change signals, that is, the frequency signal can be determined according to the transformer life data and the frequency change signal group.

[0084] Next, a target noise fluctuation curve is obtained by fitting multiple noise data and the time point corresponding to each noise data. The origin of the target noise fluctuation curve is the variable device input data, and the horizontal axis of the target noise fluctuation curve is time and the vertical axis is noise. The noise change trend is analyzed according to the target noise fluctuation curve to obtain a noise change signal group, and the noise separation signal is determined according to the variable device life data and the noise change signal group.

[0085] Furthermore, the frequency separation signal and the noise separation signal are constructed into a target substation signal group, and the safety status of the substation equipment can be evaluated based on the target substation signal group, providing a basis for the maintenance and overhaul of the equipment.

[0086] Optionally, the above step A33, analyzing the change trend of the operating frequency according to the target frequency fluctuation curve to obtain the frequency change signal group, may also include the following steps:

[0087] B31, intercepting a partial frequency fluctuation curve from the target frequency fluctuation curve to obtain a partial frequency fluctuation curve;

[0088] B32, determining the initial point and the end point of the partial frequency fluctuation curve to obtain a target initial point and a target end point;

[0089] B33, selecting a plurality of data points from the partial frequency fluctuation curve according to the target initial point and the target end point to obtain a plurality of operating frequency values;

[0090] B34, performing difference calculations based on the multiple operating frequency values ​​and the target initial point to obtain multiple difference values;

[0091] B35. Determine the number of differences greater than zero among the multiple differences to obtain a target number of differences;

[0092] B36. If the number of target difference values ​​is greater than a preset threshold, it is determined that the partial frequency fluctuation curve is in an ascending state, and a frequency increase signal is generated;

[0093] B37. If the target difference number is equal to the preset threshold, it is determined that the part of the frequency fluctuation curve is in a horizontal floating state, and a frequency leveling signal is generated;

[0094] B38. If the number of target difference values ​​is less than the preset threshold, it is determined that the partial frequency fluctuation curve is in a decreasing state, and a frequency reduction signal is generated;

[0095] B39. Construct the frequency change signal group according to the frequency increase signal, the frequency level signal, and the frequency reduction signal.

[0096] Specifically, a partial frequency fluctuation curve is intercepted from the target frequency fluctuation curve to obtain a partial frequency fluctuation curve, which can represent the operating frequency change of the substation equipment in the time period. The frequency change trend of the substation equipment can be determined by analyzing the partial frequency fluctuation curve. The initial point and the end point of the partial frequency fluctuation curve are selected to obtain the target initial point and the target end point. The target initial point is a data point on one side of the partial frequency fluctuation curve close to the origin, and the target end point is a data point on the other side of the partial frequency fluctuation curve. According to the target initial point and the target end point, a preset number of data points are selected from the partial frequency fluctuation curve to obtain multiple operating frequency values. Next, the difference calculation is performed in turn according to the multiple operating frequency values ​​and the target initial point to obtain multiple differences, and the number of differences greater than zero in the multiple differences is determined to obtain the target difference number.

[0097] Further, if the number of target differences is greater than a preset threshold, it is determined that part of the frequency fluctuation curve is in an ascending state, and a frequency increase signal is generated, wherein the preset threshold can be a system default or preset. If the number of target differences is equal to the preset threshold, it is determined that part of the frequency fluctuation curve is in a horizontal floating state, and a frequency leveling signal is generated. If the number of target differences is less than the preset threshold, it is determined that part of the frequency fluctuation curve is in a descending state, and a frequency reduction signal is generated.

[0098] Optionally, the above step A34, determining the frequency separation signal according to the variable life data and the frequency change signal group, may further include the following steps:

[0099] C31. Obtain the transformer life of the substation equipment under the frequency increase signal, the frequency level signal and the frequency reduction signal respectively, and obtain the frequency increase life, the frequency level life and the frequency reduction life;

[0100] C32, determining a frequency increase benefit signal, a frequency level benefit signal, and a frequency reduction benefit signal according to the variable life data, the frequency increase life, the frequency level life, and the frequency reduction life;

[0101] C33, determining a frequency-increasing unchanged signal, a frequency-level unchanged signal, and a frequency-reducing unchanged signal according to the variable life data, the frequency-increasing life, the frequency-leveling life, and the frequency-reducing life;

[0102] C34, determining a frequency increase inferior signal, a frequency flat inferior signal, and a frequency reduction inferior signal according to the variable life data, the frequency increase life, the frequency flat life, and the frequency reduction life;

[0103] C35. Construct the frequency separation signal according to the frequency increase signal, the frequency reduction signal, the frequency level signal, the frequency increase unchanged signal, the frequency reduction unchanged signal, the frequency level unchanged signal, the frequency increase inferior signal, the frequency reduction inferior signal and the frequency level inferior signal.

[0104] Specifically, the transformer life of the substation equipment under the frequency increase signal, frequency level signal and frequency reduction signal is obtained to obtain the frequency increase life, frequency level life and frequency reduction life. The frequency increase life represents the transformer life when the operating frequency of the substation equipment is on an upward trend. In the embodiment of the present application, the transformer life data is the expected elimination time of the substation equipment, and the transformer life of the substation equipment will also be affected in different frequency signals. Therefore, by analyzing the transformer life under different frequency signals, a comprehensive evaluation of the substation equipment can be achieved.

[0105] Further, when the variable device life data is less than the frequency increase life, a frequency increase benefit signal is generated, and the frequency increase benefit signal indicates that the substation equipment can increase the life of the substation equipment when the frequency increase signal is on; when the variable device life data is less than the frequency level life, a frequency level benefit signal is generated; when the variable device life data is less than the frequency reduction life, a frequency reduction benefit signal is generated; when the variable device life data is equal to the frequency increase life, a frequency increase unchanged signal is generated; when the variable device life data is equal to the frequency level life, a frequency level unchanged signal is generated; when the variable device life data is equal to the frequency reduction life, a frequency reduction unchanged signal is generated; when the variable device life data is greater than the frequency increase life, a frequency increase inferior signal is generated; when the variable device life data is greater than the frequency level life, a frequency level inferior signal is generated; when the variable device life data is greater than the frequency reduction life, a frequency reduction inferior signal is generated.

[0106] Furthermore, a frequency separation signal can be constructed according to the frequency increase advantage signal, the frequency decrease advantage signal, the frequency flat advantage signal, the frequency increase unchanged signal, the frequency decrease unchanged signal, the frequency flat unchanged signal, the frequency increase inferior signal, the frequency decrease inferior signal and the frequency flat inferior signal.

[0107] S104. Perform safety evaluation on the substation equipment according to the target safety data group and the target substation signal group to obtain a target safety evaluation value.

[0108] Specifically, the target safety evaluation value can be obtained by conducting a safety evaluation on the substation equipment according to the target safety data group and the target substation signal group. Among them, the target safety data group includes the replacement safety range value and the maintenance safety range value, and the target substation signal group includes the frequency separation signal and the noise separation signal. The replacement safety range value, the maintenance safety range value, the frequency separation signal and the noise separation signal are substituted into the calculation formula of the safety evaluation value to obtain the target safety evaluation value. The target safety evaluation value is used to divide the substation equipment into different levels, such as safety, warning, danger, etc. According to the target safety evaluation value, the potential risks in the operation of the substation equipment can be identified and managed to improve the efficiency and effectiveness of risk management.

[0109] Optionally, the above step S104, performing safety evaluation on the substation equipment according to the target safety data group and the target substation signal group to obtain a target safety evaluation value, may further include the following steps:

[0110] The target safety evaluation value is determined according to a first preset formula, and the first preset formula is as follows:

[0111]

[0112] In the above formula, P s is the target safety evaluation value; is the replacement safety range value; f1 is the safety error threshold of the replacement safety range value; u1 is the evaluation weight coefficient of the replacement safety range value; is the maintenance safety range value; f2 is the safety error threshold of the maintenance safety range value; u2 is the evaluation weight coefficient of the maintenance safety range value; is the value assigned to the frequency-respective signal; u3 is the evaluation weight coefficient of the value assigned to the frequency-respective signal; is the value assigned to the noise separation signal; u4 is the evaluation weight coefficient of the value assigned to the noise separation signal; gle is the deviation adjustment factor of the target safety evaluation value.

[0113] In a possible embodiment, the substation equipment is a transformer, and in a 10-year operation cycle, the replacement safety range value is 4, and the safety error threshold of the replacement safety range value is 1. When calculating, the average of the sum of the replacement safety range value plus the reciprocal of the safety error threshold and the replacement safety range value minus the reciprocal of the safety error threshold is taken as the replacement safety range value score. Since replacement has a greater impact on the life of the transformer, the evaluation weight coefficient of the replacement safety range value is set to 0.5, the maintenance safety range value is 6, the safety error threshold of the maintenance safety range value is 2, and the evaluation weight coefficient of the maintenance safety range value is 0.3. The current frequency separation signal is a frequency increase signal, then the frequency separation signal is assigned 9, and the evaluation weight coefficient of the frequency separation signal assignment is 0.15. The current noise separation signal is a noise level unchanged signal, then the noise separation signal is assigned 4, and the evaluation weight coefficient of the noise separation signal assignment is 0.05. The deviation adjustment factor of the target safety evaluation value is set to 1.1 to consider uncertain factors, and the final target safety evaluation value is 1.91.

[0114] S105. Regulating and controlling the substation equipment according to the target safety evaluation value.

[0115] Specifically, the safety evaluation threshold can be determined based on historical substation equipment data, and the target safety evaluation value can be compared with the safety evaluation threshold. Based on the comparison result, corresponding control signaling can be generated for automated regulation and control to improve the response speed to changes in equipment status.

[0116] Optionally, the above step S105, regulating and controlling the substation equipment according to the target safety evaluation value, may further include the following steps:

[0117] A51. Obtain the safety evaluation threshold;

[0118] A52. When the target safety evaluation value is greater than the safety evaluation threshold, generating a maintenance-free signaling; the maintenance-free signaling is used to issue a prompt indicating that maintenance of the substation equipment is not required;

[0119] A53. When the target safety evaluation value is equal to the safety evaluation threshold, generating a regular maintenance signaling; the regular maintenance signaling is used to issue a warning to remind regular maintenance of the substation equipment;

[0120] A54. When the target safety evaluation value is less than the safety evaluation threshold, an immediate maintenance signaling is generated; the immediate maintenance signaling is used to issue an alarm to remind the immediate maintenance of the substation equipment.

[0121] Specifically, a safety evaluation threshold is obtained, wherein the safety evaluation threshold can be obtained by performing safety evaluation analysis on the data of historical substation equipment. When the target safety evaluation value is greater than the safety evaluation threshold, a maintenance-free signal is generated to prompt the substation equipment to maintain the current operating parameters; when the target safety evaluation value is equal to the safety evaluation threshold, a regular maintenance signal is generated to warn to adjust the operation plan of the substation equipment and arrange downtime for maintenance; when the target safety evaluation value is less than the safety evaluation threshold, an immediate maintenance signal is generated to issue an alarm to notify the immediate maintenance of the substation equipment.

[0122] In a possible embodiment, the substation equipment is a transformer, and the target safety evaluation value of the transformer currently measured is 1.91, and the safety evaluation threshold is 1.5, then it is considered that the transformer is in good operating condition and does not require immediate maintenance.

[0123] Furthermore, by continuously monitoring the operating status of substation equipment and updating the safety evaluation value in real time, the control strategy is dynamically adjusted according to the latest safety evaluation value to ensure that the substation equipment is always operating in the best and safest state, effectively improving the response speed of the entire substation operation and maintenance and improving the operating efficiency of the substation.

[0124] To summarize, by implementing the embodiments of the present application, first, a target substation data group of substation equipment within a preset time period is obtained; the target substation data group includes: substation data, operation start time data, operation end time data, operation frequency data, operation noise data, substation zero point data, substation maintenance point data, substation start data, and substation life data; the operating status of the substation equipment is evaluated according to the target substation data group to obtain a target safety data group; the target safety data group includes a replacement safety range value and a maintenance safety range value; the safety signal of the substation equipment is monitored according to the target substation data group to obtain a target substation signal group; the target substation signal group includes a frequency separation signal and a noise separation signal; the substation equipment is safety evaluated according to the target safety data group and the target substation signal group to obtain a target safety evaluation value; the substation equipment is adjusted and controlled according to the target safety evaluation value. The present application monitors the operating status of substation equipment in real time, makes safety judgments on the signal data of substation equipment, and then conducts safety evaluation on the substation equipment, and makes corresponding operation and maintenance suggestions based on the safety evaluation values, thereby speeding up the response speed of substation operation and maintenance and improving the operation efficiency of the substation.

[0125] See also Figure 2 , Figure 2 : is a system architecture diagram of an operation and maintenance control system of a substation equipment provided in an embodiment of the present application, and the operation and maintenance control system 200 of the substation equipment includes:

[0126] The acquisition unit 201 is used to acquire a target substation data group of substation equipment within a preset time period; the target substation data group includes: substation data, operation start time data, operation end time data, operation frequency data, operation noise data, substation zero point data, substation maintenance point data, substation start data, and substation life data;

[0127] A first analysis unit 202 is used to evaluate the operating status of the substation equipment according to the target substation data group to obtain a target safety data group; the target safety data group includes a replacement safety range value and a maintenance safety range value;

[0128] The second analysis unit 203 is used to monitor the safety signal of the substation equipment according to the target substation data group to obtain a target substation signal group; the target substation signal group includes a frequency separation signal and a noise separation signal;

[0129] An evaluation unit 204, configured to perform a safety evaluation on the substation equipment according to the target safety data group and the target substation signal group to obtain a target safety evaluation value;

[0130] The control unit 205 is used to adjust and control the substation equipment according to the target safety evaluation value.

[0131] Optionally, in the aspect of evaluating the operating status of the substation equipment according to the target substation data group to obtain a target safety data group, the first analyzing unit 202 is further specifically configured to:

[0132] Determine a plurality of operation start time data, a plurality of operation end time data, a plurality of change zero point data, and a plurality of change dimension point data in the target power transformation data group;

[0133] Determine a plurality of operation time periods according to the plurality of operation start time data and the plurality of operation end time data;

[0134] Matching the plurality of zero-point data with the plurality of operating time periods to obtain a plurality of replacement number value groups; each replacement number value group includes a plurality of replacement number values;

[0135] Matching the multiple dimension change point data with the multiple operating time periods to obtain multiple maintenance number value groups;

[0136] Performing range value processing according to the plurality of replacement number value groups to obtain the replacement safety range value;

[0137] Performing range value processing according to the plurality of maintenance frequency value groups to obtain the maintenance safety range value;

[0138] The target safety data set is constructed according to the replacement safety range value and the maintenance safety range value.

[0139] Optionally, in the aspect of performing range value processing according to the multiple replacement number value groups to obtain the replacement safety range value, the first analysis unit 202 is further specifically configured to:

[0140] Selecting the replacement number value with the largest number of occurrences from the plurality of replacement number value groups to obtain a target replacement mode value;

[0141] Determine an average value of the number of replacements according to the plurality of replacement number value groups to obtain a target replacement average value;

[0142] Calculate the difference between the target replacement mode value and the target replacement mean value to obtain a target replacement difference;

[0143] Determine a target replacement floating value according to the target replacement difference and a preset replacement weight coefficient;

[0144] The replacement safety range value is determined according to the target replacement mode value and the target replacement floating value.

[0145] Optionally, in the aspect of monitoring the safety signal of the substation equipment according to the target substation data group to obtain the target substation signal group, the second analysis unit 203 is further specifically used for:

[0146] Determine a plurality of operating frequency data, a plurality of operating noise data, a transformer startup data, and a transformer life data in the target transformer data group; each operating frequency data corresponds to a time point; each operating noise data corresponds to a time point;

[0147] Fitting is performed according to the plurality of operating frequency data and the time point corresponding to each operating frequency data to obtain a target frequency fluctuation curve; the origin of the target frequency fluctuation curve is the variable input start data, the horizontal axis of the target frequency fluctuation curve is time and the vertical axis is the operating frequency;

[0148] Analyze the change trend of the operating frequency according to the target frequency fluctuation curve to obtain a frequency change signal group; the frequency change signal group includes: a frequency increase signal, a frequency level signal, and a frequency decrease signal;

[0149] Determine the frequency separation signal according to the variable life data and the frequency change signal group;

[0150] Fitting is performed according to the multiple noise data and the time point corresponding to each noise data to obtain a target noise fluctuation curve; the origin of the target noise fluctuation curve is the variable setting initial data, the horizontal axis of the target noise fluctuation curve is time and the vertical axis is noise;

[0151] Analyze the noise variation trend according to the target noise fluctuation curve to obtain a noise variation signal group;

[0152] Determine the noise separation signal according to the variable life data and the noise change signal group;

[0153] The target substation signal group is constructed according to the frequency separation signal and the noise separation signal.

[0154] Optionally, in the aspect of analyzing the change trend of the operating frequency according to the target frequency fluctuation curve to obtain the frequency change signal group, the second analysis unit 203 is further specifically used for:

[0155] intercepting a partial frequency fluctuation curve from the target frequency fluctuation curve to obtain a partial frequency fluctuation curve;

[0156] Determine the initial point and the end point of the partial frequency fluctuation curve to obtain a target initial point and a target end point;

[0157] Selecting a plurality of data points from the partial frequency fluctuation curve according to the target initial point and the target end point to obtain a plurality of operating frequency values;

[0158] Performing difference calculations based on the multiple operating frequency values ​​and the target initial point to obtain multiple difference values;

[0159] Determine the number of differences greater than zero among the multiple differences to obtain a target number of differences;

[0160] If the number of target difference values ​​is greater than a preset threshold, it is determined that the partial frequency fluctuation curve is in an ascending state, and a frequency increase signal is generated;

[0161] If the target difference number is equal to the preset threshold, it is determined that the part of the frequency fluctuation curve is in a horizontal floating state, and a frequency leveling signal is generated;

[0162] If the target difference number is less than the preset threshold, it is determined that the partial frequency fluctuation curve is in a decreasing state, and a frequency reduction signal is generated;

[0163] The frequency change signal group is constructed according to the frequency increase signal, the frequency level signal, and the frequency reduction signal.

[0164] Optionally, in determining the frequency separation signal according to the variable life data and the frequency change signal group, the second analysis unit 203 is further specifically configured to:

[0165] Obtain the transformer life of the substation equipment under the frequency increase signal, the frequency level signal and the frequency reduction signal respectively, and obtain the frequency increase life, the frequency level life and the frequency reduction life;

[0166] Determine a frequency increase benefit signal, a frequency level benefit signal, and a frequency decrease benefit signal according to the variable life data, the frequency increase life, the frequency level life, and the frequency decrease life;

[0167] Determine a frequency-increasing unchanged signal, a frequency-level unchanged signal, and a frequency-reducing unchanged signal according to the variable life data, the frequency-increasing life, the frequency-leveling life, and the frequency-reducing life;

[0168] Determine a frequency increase inferior signal, a frequency flat inferior signal, and a frequency reduction inferior signal according to the variable life data, the frequency increase life, the frequency flat life, and the frequency reduction life;

[0169] The frequency separation signal is constructed according to the frequency increase signal, the frequency reduction signal, the frequency level signal, the frequency increase unchanged signal, the frequency reduction unchanged signal, the frequency level unchanged signal, the frequency increase inferior signal, the frequency reduction inferior signal and the frequency level inferior signal.

[0170] Optionally, in the aspect of performing safety evaluation on the substation equipment according to the target safety data group and the target substation signal group to obtain a target safety evaluation value, the evaluation unit 204 is further specifically used for:

[0171] The target safety evaluation value is determined according to a first preset formula, and the first preset formula is as follows:

[0172]

[0173] In the above formula, P s is the target safety evaluation value; is the replacement safety range value; f1 is the safety error threshold of the replacement safety range value; u1 is the evaluation weight coefficient of the replacement safety range value; is the maintenance safety range value; f2 is the safety error threshold of the maintenance safety range value; u2 is the evaluation weight coefficient of the maintenance safety range value; is the value assigned to the frequency-respective signal; u3 is the evaluation weight coefficient of the value assigned to the frequency-respective signal; is the value assigned to the noise separation signal; u4 is the evaluation weight coefficient of the value assigned to the noise separation signal; gle is the deviation adjustment factor of the target safety evaluation value.

[0174] Optionally, in the aspect of regulating and controlling the substation equipment according to the target safety evaluation value, the control unit 205 is further specifically configured to:

[0175] Obtain the safety evaluation threshold;

[0176] When the target safety evaluation value is greater than the safety evaluation threshold, a maintenance-free signaling is generated; the maintenance-free signaling is used to issue a prompt indicating that maintenance of the substation equipment is not required;

[0177] When the target safety evaluation value is equal to the safety evaluation threshold, a regular maintenance signaling is generated; the regular maintenance signaling is used to issue a warning to remind the regular maintenance of the substation equipment;

[0178] When the target safety evaluation value is less than the safety evaluation threshold, an immediate maintenance signaling is generated; the immediate maintenance signaling is used to issue an alarm to remind the immediate maintenance of the substation equipment.

[0179] The operation and maintenance control system 200 of the substation equipment described in the present application can obtain a target substation data group for the substation equipment within a preset time period; the target substation data group includes: substation data, operation start time data, operation end time data, operation frequency data, operation noise data, substation zero point data, substation maintenance point data, substation start data, and substation life data; the operation status of the substation equipment is evaluated according to the target substation data group to obtain a target safety data group; the target safety data group includes a replacement safety range value and a maintenance safety range value; the safety signal of the substation equipment is monitored according to the target substation data group to obtain a target substation signal group; the target substation signal group includes a frequency separation signal and a noise separation signal; the substation equipment is safety evaluated according to the target safety data group and the target substation signal group to obtain a target safety evaluation value; the substation equipment is adjusted and controlled according to the target safety evaluation value. The present application monitors the operating status of substation equipment in real time, makes safety judgments on the signal data of substation equipment, and then conducts safety evaluation on the substation equipment, and makes corresponding operation and maintenance suggestions based on the safety evaluation values, thereby speeding up the response speed of substation operation and maintenance and improving the operation efficiency of the substation.

[0180] See also Figure 3 , Figure 3 300 is a system architecture diagram of another operation and maintenance control system of a substation equipment provided in an embodiment of the present application. The operation and maintenance control system 300 of the substation equipment includes: an electric transformer acquisition and storage update unit 301, an electric transformer operation state processing unit 302, an electric transformer environmental monitoring analysis unit 303, an electric transformer safety determination unit 304, and an electric transformer control and warning unit 305. The electric transformer acquisition and storage update unit 301 also includes an electric transformer acquisition unit 3011 and an electric transformer cloud storage unit 3012.

[0181] The electric transformer acquisition, storage and update unit 301 is used to collect operation and maintenance data of substation equipment according to the electric transformer acquisition unit 3011 and calibrate it to obtain a target electric transformer data group, wherein the target electric transformer data group includes: transformer solid data, operation start time data, operation end time data, operation frequency data, operation noise data, transformer zero point data, change time data, transformer maintenance time data, transformer maintenance point data, transformer start data, transformer life data, and the target electric transformer data group is stored in the electric transformer cloud storage unit 3012.

[0182] The power substation operation state processing unit 302 is used to evaluate the operation state of the substation equipment according to the target power substation data group to obtain a target safety data group; the target safety data group includes a replacement safety range value and a maintenance safety range value;

[0183] The substation environmental monitoring and analysis unit 303 is used to monitor the safety signals of the substation equipment according to the target substation data group to obtain the target substation signal group; the target substation signal group includes a frequency separation signal and a noise separation signal;

[0184] The electric transformer safety determination unit 304 is used to perform safety evaluation on the substation equipment according to the target safety data group and the target substation signal group, obtain the target safety evaluation value, and generate a prompt signal group for regulating and controlling the substation equipment according to the target safety evaluation value; the prompt signal group includes a maintenance-free signal, a regular maintenance signal, and an immediate maintenance signal;

[0185] The transformer control and warning unit 305 is used to receive maintenance-free signaling, regular maintenance signaling and immediate maintenance signaling. When a maintenance-free signaling is identified, the transformer control and warning unit 305 generates the words "substation safety" and sends it to the monitoring display terminal to prompt that no maintenance is required for the substation equipment. When a regular maintenance signaling is identified, the words "substation maintenance" are generated and sent to the monitoring display terminal to remind the regular maintenance of the substation equipment. When an immediate maintenance signaling is identified, the words "substation maintenance" are generated and an alarm is issued to remind the immediate maintenance of the substation equipment.

[0186] The operation and maintenance control system 300 of the substation equipment described in the present application realizes real-time monitoring of the operating status of the substation equipment and safety judgment of the signal data of the substation equipment, and then conducts safety evaluation of the substation equipment, and makes corresponding operation and maintenance suggestions based on the safety evaluation value, thereby accelerating the response speed of substation operation and maintenance and improving the operation efficiency of the substation.

[0187] See also Figure 4 , Figure 4: is a structural diagram of an electronic device provided in an embodiment of the present application, the electronic device may include a processor, a memory, a communication interface and one or more programs, the processor, the memory and the communication interface may be interconnected through a bus; the one or more programs are stored in the memory and configured to be executed by the processor; in the embodiment of the present application, the program includes instructions for executing the following steps:

[0188] Obtain a target substation data group of substation equipment within a preset time period; the target substation data group includes: substation data, operation start time data, operation end time data, operation frequency data, operation noise data, substation zero point data, substation maintenance point data, substation start data, and substation life data;

[0189] Evaluate the operating status of the substation equipment according to the target substation data group to obtain a target safety data group; the target safety data group includes a replacement safety range value and a maintenance safety range value;

[0190] Monitor the safety signal of the substation equipment according to the target substation data group to obtain a target substation signal group; the target substation signal group includes a frequency separation signal and a noise separation signal;

[0191] Performing a safety evaluation on the substation equipment according to the target safety data group and the target substation signal group to obtain a target safety evaluation value;

[0192] The substation equipment is regulated and controlled according to the target safety evaluation value.

[0193] The electronic device described in the present application can obtain a target substation data group for substation equipment within a preset time period; the target substation data group includes: substation data, operation start time data, operation end time data, operation frequency data, operation noise data, substation zero point data, substation maintenance point data, substation start data, and substation life data; the operating status of the substation equipment is evaluated according to the target substation data group to obtain a target safety data group; the target safety data group includes a replacement safety range value and a maintenance safety range value; the safety signal of the substation equipment is monitored according to the target substation data group to obtain a target substation signal group; the target substation signal group includes a frequency separation signal and a noise separation signal; the substation equipment is safety evaluated according to the target safety data group and the target substation signal group to obtain a target safety evaluation value; the substation equipment is adjusted and controlled according to the target safety evaluation value. The present application monitors the operating status of substation equipment in real time, makes safety judgments on the signal data of substation equipment, and then conducts safety evaluation on the substation equipment, and makes corresponding operation and maintenance suggestions based on the safety evaluation values, thereby speeding up the response speed of substation operation and maintenance and improving the operation efficiency of the substation.

[0194] An embodiment of the present application also provides a computer-readable storage medium, wherein the computer-readable storage medium stores a computer program for electronic data exchange, wherein the computer program enables a computer to execute part or all of the steps of any method described in the above method embodiments, and the above computer includes an electronic device.

[0195] The embodiment of the present application also provides a computer program product, the computer program product includes a non-transitory computer-readable storage medium storing a computer program, the computer program is operable to cause a computer to execute some or all of the steps of any method described in the method embodiment. The computer program product may be a software installation package, and the computer includes an electronic device.

[0196] Those skilled in the art can understand that to implement all or part of the processes in the above-mentioned embodiments, the processes can be completed by computer programs to instruct related hardware, and the programs can be stored in computer-readable storage media. When the programs are executed, they can include the processes of the above-mentioned method embodiments. The aforementioned storage media include: ROM or random access memory RAM, magnetic disk or optical disk and other media that can store program codes.

[0197] The steps of the method or algorithm described in the embodiments of the present application can be implemented in hardware or by executing software instructions by a processor. The software instructions can be composed of corresponding software modules, and the software modules can be stored in RAM, flash memory, ROM, EPROM, electrically erasable programmable read-only memory (electrically EPROM, EEPROM), registers, hard disks, mobile hard disks, read-only compact disks (CD-ROMs) or any other form of storage medium known in the art. An exemplary storage medium is coupled to the processor so that the processor can read information from the storage medium and write information to the storage medium. Of course, the storage medium can also be a component of the processor. The processor and the storage medium can be located in an ASIC. In addition, the ASIC can be located in a terminal device or a management device. Of course, the processor and the storage medium can also be present in a terminal device or a management device as discrete components.

[0198] Those skilled in the art should be aware that in one or more of the above examples, the functions described in the embodiments of the present application can be implemented in whole or in part by software, hardware, firmware, or any combination thereof. When implemented using software, it can be implemented in whole or in part in the form of a computer program product. The computer program product includes one or more computer instructions. When the computer program instructions are loaded and executed on a computer, the process or function described in the embodiments of the present application is generated in whole or in part. The computer can be a general-purpose computer, a special-purpose computer, a computer network, or other programmable device. The computer instructions can be stored in a computer-readable storage medium or transmitted from one computer-readable storage medium to another computer-readable storage medium. For example, the computer instructions can be transmitted from a website site, computer, server, or data center to another website site, computer, server, or data center by wired (e.g., coaxial cable, optical fiber, digital subscriber line (digital subscriber line, DSL)) or wireless (e.g., infrared, wireless, microwave, etc.) mode. The computer-readable storage medium can be any available medium that a computer can access or a data storage device such as a server or data center that includes one or more available media integrations. The available medium may be a magnetic medium (eg, a floppy disk, a hard disk, a magnetic tape), an optical medium (eg, a digital video disc (DVD)), or a semiconductor medium (eg, a solid state disk (SSD)).

[0199] The modules / units included in the devices and products described in the above embodiments may be software modules / units or hardware modules / units, or may be partially software modules / units and partially hardware modules / units. For example, for the devices and products applied to or integrated in the chip, the modules / units included therein may all be implemented in the form of hardware such as circuits, or at least some of the modules / units may be implemented in the form of software programs, which run on the processor integrated inside the chip, and the remaining (if any) modules / units may be implemented in the form of hardware such as circuits; for the devices and products applied to or integrated in the chip module, the modules / units included therein may all be implemented in the form of hardware such as circuits, and different modules / units may be located in the same component (such as a chip, circuit module, etc.) or in different components of the chip module, or at least some of the modules / units may be implemented in the form of software programs. The software programs run on the processor integrated inside the chip, and the remaining (if any) modules / units may be implemented in the form of hardware such as circuits. It is implemented in the form of a software program, which runs on a processor integrated inside the chip module, and the remaining (if any) modules / units can be implemented in hardware such as circuits; for various devices and products applied to or integrated in the terminal equipment, the various modules / units contained therein can be implemented in hardware such as circuits, and different modules / units can be located in the same component (for example, chip, circuit module, etc.) or in different components in the terminal equipment, or, at least some modules / units can be implemented in the form of a software program, which runs on a processor integrated inside the terminal equipment, and the remaining (if any) modules / units can be implemented in hardware such as circuits.

[0200] The specific implementation methods described above further illustrate the purpose, technical solutions and beneficial effects of the embodiments of the present application. It should be understood that the above description is only the specific implementation method of the embodiments of the present application and is not intended to limit the protection scope of the embodiments of the present application. Any modifications, equivalent substitutions, improvements, etc. made on the basis of the technical solutions of the embodiments of the present application should be included in the protection scope of the embodiments of the present application.

Claims

1. A method for operation and maintenance control of substation equipment, characterized in that: The method comprises: Obtain a target substation data group of substation equipment within a preset time period; the target substation data group includes: substation data, operation start time data, operation end time data, operation frequency data, operation noise data, substation zero point data, substation maintenance point data, substation start data, and substation life data; Evaluate the operating status of the substation equipment according to the target substation data group to obtain a target safety data group; the target safety data group includes a replacement safety range value and a maintenance safety range value; Monitor the safety signal of the substation equipment according to the target substation data group to obtain a target substation signal group; the target substation signal group includes a frequency separation signal and a noise separation signal; Performing a safety evaluation on the substation equipment according to the target safety data group and the target substation signal group to obtain a target safety evaluation value; The substation equipment is regulated and controlled according to the target safety evaluation value.

2. The method according to claim 1, characterized in that The step of evaluating the operating status of the substation equipment according to the target substation data group to obtain a target safety data group includes: Determine a plurality of operation start time data, a plurality of operation end time data, a plurality of change zero point data, and a plurality of change dimension point data in the target power transformation data group; Determine a plurality of operation time periods according to the plurality of operation start time data and the plurality of operation end time data; Matching the plurality of zero-point data with the plurality of operating time periods to obtain a plurality of replacement number value groups; each replacement number value group includes a plurality of replacement number values; Matching the multiple dimension change point data with the multiple operating time periods to obtain multiple maintenance number value groups; Performing range value processing according to the plurality of replacement number value groups to obtain the replacement safety range value; Performing range value processing according to the plurality of maintenance frequency value groups to obtain the maintenance safety range value; The target safety data set is constructed according to the replacement safety range value and the maintenance safety range value.

3. The method according to claim 2, characterized in that The performing range value processing according to the plurality of replacement number value groups to obtain the replacement safety range value includes: Selecting the replacement number value with the largest number of occurrences from the plurality of replacement number value groups to obtain a target replacement mode value; Determine an average value of the number of replacements according to the plurality of replacement number value groups to obtain a target replacement average value; Calculate the difference between the target replacement mode value and the target replacement mean value to obtain a target replacement difference; Determine a target replacement floating value according to the target replacement difference and a preset replacement weight coefficient; The replacement safety range value is determined according to the target replacement mode value and the target replacement floating value.

4. The method according to claim 1, characterized in that The step of monitoring the safety signal of the substation equipment according to the target substation data group to obtain the target substation signal group includes: Determine a plurality of operating frequency data, a plurality of operating noise data, a transformer startup data, and a transformer life data in the target transformer data group; each operating frequency data corresponds to a time point; each operating noise data corresponds to a time point; Fitting is performed according to the plurality of operating frequency data and the time point corresponding to each operating frequency data to obtain a target frequency fluctuation curve; the origin of the target frequency fluctuation curve is the variable input start data, the horizontal axis of the target frequency fluctuation curve is time and the vertical axis is the operating frequency; Analyze the change trend of the operating frequency according to the target frequency fluctuation curve to obtain a frequency change signal group; the frequency change signal group includes: a frequency increase signal, a frequency level signal, and a frequency decrease signal; Determine the frequency separation signal according to the variable life data and the frequency change signal group; Fitting is performed according to the multiple noise data and the time point corresponding to each noise data to obtain a target noise fluctuation curve; the origin of the target noise fluctuation curve is the variable setting initial data, the horizontal axis of the target noise fluctuation curve is time and the vertical axis is noise; Analyze the noise variation trend according to the target noise fluctuation curve to obtain a noise variation signal group; Determine the noise separation signal according to the variable life data and the noise change signal group; The target substation signal group is constructed according to the frequency separation signal and the noise separation signal.

5. The method according to claim 4, characterized in that The step of analyzing the change trend of the operating frequency according to the target frequency fluctuation curve to obtain a frequency change signal group includes: intercepting a partial frequency fluctuation curve from the target frequency fluctuation curve to obtain a partial frequency fluctuation curve; Determine the initial point and the end point of the partial frequency fluctuation curve to obtain a target initial point and a target end point; Selecting a plurality of data points from the partial frequency fluctuation curve according to the target initial point and the target end point to obtain a plurality of operating frequency values; Performing difference calculations based on the multiple operating frequency values ​​and the target initial point to obtain multiple difference values; Determine the number of differences greater than zero among the multiple differences to obtain a target number of differences; If the number of target difference values ​​is greater than a preset threshold, it is determined that the partial frequency fluctuation curve is in an ascending state, and a frequency increase signal is generated; If the target difference number is equal to the preset threshold, it is determined that the part of the frequency fluctuation curve is in a horizontal floating state, and a frequency leveling signal is generated; If the target difference number is less than the preset threshold, it is determined that the partial frequency fluctuation curve is in a decreasing state, and a frequency reduction signal is generated; The frequency change signal group is constructed according to the frequency increase signal, the frequency level signal, and the frequency reduction signal.

6. The method according to claim 5, characterized in that The determining the frequency signal according to the variable life data and the frequency change signal group includes: Obtain the transformer life of the substation equipment under the frequency increase signal, the frequency level signal and the frequency reduction signal respectively, and obtain the frequency increase life, the frequency level life and the frequency reduction life; Determine a frequency increase benefit signal, a frequency level benefit signal, and a frequency decrease benefit signal according to the variable life data, the frequency increase life, the frequency level life, and the frequency decrease life; Determine a frequency-increasing unchanged signal, a frequency-level unchanged signal, and a frequency-reducing unchanged signal according to the variable life data, the frequency-increasing life, the frequency-leveling life, and the frequency-reducing life; Determine a frequency increase inferior signal, a frequency flat inferior signal, and a frequency reduction inferior signal according to the variable life data, the frequency increase life, the frequency flat life, and the frequency reduction life; The frequency separation signal is constructed according to the frequency increase signal, the frequency reduction signal, the frequency level signal, the frequency increase unchanged signal, the frequency reduction unchanged signal, the frequency level unchanged signal, the frequency increase inferior signal, the frequency reduction inferior signal and the frequency level inferior signal.

7. The method according to any one of claims 1 to 6, characterized in that: The step of performing safety evaluation on the substation equipment according to the target safety data group and the target substation signal group to obtain a target safety evaluation value includes: The target safety evaluation value is determined according to a first preset formula, and the first preset formula is as follows: In the above formula, P s is the target safety evaluation value; is the replacement safety range value; f1 is the safety error threshold of the replacement safety range value; u1 is the evaluation weight coefficient of the replacement safety range value; is the maintenance safety range value; f2 is the safety error threshold of the maintenance safety range value; u2 is the evaluation weight coefficient of the maintenance safety range value; is the value assigned to the frequency-respective signal; u3 is the evaluation weight coefficient of the value assigned to the frequency-respective signal; is the value assigned to the noise separation signal; u4 is the evaluation weight coefficient of the value assigned to the noise separation signal; gle is the deviation adjustment factor of the target safety evaluation value.

8. The method according to claim 7, characterized in that The regulating and controlling the substation equipment according to the target safety evaluation value includes: Obtain the safety evaluation threshold; When the target safety evaluation value is greater than the safety evaluation threshold, a maintenance-free signaling is generated; the maintenance-free signaling is used to issue a prompt indicating that maintenance of the substation equipment is not required; When the target safety evaluation value is equal to the safety evaluation threshold, a regular maintenance signaling is generated; the regular maintenance signaling is used to issue a warning to remind the regular maintenance of the substation equipment; When the target safety evaluation value is less than the safety evaluation threshold, an immediate maintenance signaling is generated; the immediate maintenance signaling is used to issue an alarm to remind the immediate maintenance of the substation equipment.

9. An operation and maintenance control system for substation equipment, characterized in that: include: An acquisition unit, used to acquire a target substation data group of substation equipment within a preset time period; The target substation data group includes: substation data, operation start time data, operation end time data, operation frequency data, operation noise data, substation zero point data, substation maintenance point data, substation start data, and substation life data; A first analysis unit is used to evaluate the operating status of the substation equipment according to the target substation data group to obtain a target safety data group; the target safety data group includes a replacement safety range value and a maintenance safety range value; A second analysis unit is used to monitor the safety signal of the substation equipment according to the target substation data group to obtain a target substation signal group; the target substation signal group includes a frequency separation signal and a noise separation signal; An evaluation unit, configured to perform a safety evaluation on the substation equipment according to the target safety data group and the target substation signal group to obtain a target safety evaluation value; A control unit is used to adjust and control the substation equipment according to the target safety evaluation value.

10. An electronic device, characterized in that: include: A processor, a memory, a communication interface, and one or more programs; The one or more programs are stored in the memory and configured to be executed by the processor, the programs comprising instructions for executing the steps in the method according to any one of claims 1 to 8.