Deep cut road three-dimensional reconstruction and extension structure and construction method

By setting up retaining structures and prefabricated steel beams on deep-digging roads to support the newly installed bridge deck, a double-layer three-dimensional structure is formed, which solves the technical difficulty and environmental problems of the existing highway expansion and renovation methods, and achieves efficient and environmentally friendly three-dimensional renovation and expansion Effect.

CN119061750APending Publication Date: 2024-12-03RES INST OF HIGHWAY MINIST OF TRANSPORT
View PDF 0 Cites 1 Cited by

Patent Information

Application Number
CN202411484792.4
Authority / Receiving Office
CN · China
Patent Type
Applications(China)
Current Assignee / Owner
Filing Date
2024-10-23
Publication Date
2024-12-03

AI Technical Summary

Technical Problem

The existing highway expansion and renovation methods have problems such as high technical difficulties, long construction time, high investment costs, high land resource occupation, serious environmental damage and difficult to guarantee the quality of connection.

Method used

The three-dimensional reconstruction and expansion structure of the deep-dig road road is adopted. By setting up a retaining structure on the widened deep-dig road road ground, prefabricated steel beams are used to support the newly installed bridge deck, and prefabricated and cast-in-place bridge decks are laid on it to form a double layer Three-dimensional structure reduces slope excavation and land occupation, and at the same time, use the original highway route to achieve three-dimensional reconstruction and expansion.

Benefits of technology

It has achieved the addition of a new highway without affecting the passage of the original highway, which has reduced land resource demand and excavation operations, improved construction efficiency and product quality, reduced safety risks, and taken into account slope protection and load-bearing structure. function significantly improves economic benefits.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN119061750A_ABST
    Figure CN119061750A_ABST
Patent Text Reader

Abstract

The invention belongs to the technical field of road reconstruction and extension engineering construction, and discloses a deep cut road three-dimensional reconstruction and extension structure and a construction method.The deep cut road three-dimensional reconstruction and extension structure comprises a soil retaining structure, a plurality of prefabricated steel beams are arranged on the soil retaining structure, and a newly-installed bridge deck is arranged on the prefabricated steel beams; the soil retaining structure comprises two retaining walls symmetrically arranged on road shoulders on the two sides of the deep cut highway, and a plurality of prefabricated steel beams are supported between the opposite faces of the two retaining walls. The newly-installed bridge deck comprises a prefabricated bridge deck and a cast-in-place bridge deck which are sequentially arranged. The prefabricated bridge deck comprises a plurality of prefabricated bridge deck slabs, the prefabricated bridge deck slabs are spliced, and spliced joints fall on the top faces of the prefabricated steel beams. According to the structural scheme, three-dimensional reconstruction and expansion can be achieved by fully utilizing original road line positions, the land resource requirement and a large amount of excavation work are reduced, economy and environmental protection are achieved, meanwhile, the retaining wall has the bearing structure and the slope protection function, the construction efficiency is high, the prefabricated steel beams can serve as temporary supports and permanent structures, structural characteristics are fully utilized, and the construction cost is reduced. The economic benefit is obvious.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The invention belongs to the technical field of highway reconstruction and expansion engineering construction, and in particular relates to a three-dimensional reconstruction and expansion structure of a deep-cut highway and a construction method. Background Art

[0002] As the number of vehicles increases, the pressure on road traffic gradually increases. In order to meet the increasing demand for large traffic volumes, the original roads need to be expanded and renovated.

[0003] At present, there are usually two ways to expand and reconstruct highways. One is to increase the number of lanes by widening and expanding on one or both sides of the original highway. For deep-cut highway sections with high slopes on both sides, this method of widening and expanding requires a large amount of excavation work on the high slopes on both sides, which is technically difficult, takes a long time to construct, and has high investment costs. It will also occupy too much land resources, generate a large amount of excavation waste, and damage the original ecological environment, which is not conducive to environmental protection. In addition, it is difficult to ensure the connection quality between the roadbed and pavement of the newly widened highway and the original highway. Another expansion and reconstruction method is to change the two-way traffic of the original highway to one-way traffic, and build a new highway in the adjacent area to expand the original highway. Since the optimal line position has been selected through multiple schemes during the design and line selection of the original highway, the route of the new highway often needs to detour to avoid the mountains, hills and other terrains around the original highway, resulting in increased mileage and investment, and it also faces the problem of occupying too much land resources.

[0004] Therefore, the present application designs a three-dimensional reconstruction and expansion structure and construction method for a deep-cut highway to solve the above-mentioned technical problems. Summary of the invention

[0005] In order to solve the above technical problems, the present invention proposes a three-dimensional reconstruction and expansion structure and a construction method for a deep-cut highway.

[0006] To achieve the above-mentioned purpose, the present invention provides a three-dimensional reconstruction and expansion structure for a deep-cut road, comprising a retaining structure arranged on the widened deep-cut road surface, a plurality of prefabricated steel beams arranged on the retaining structure, and a newly installed bridge deck arranged on the prefabricated steel beams;

[0007] The retaining structure comprises two retaining walls arranged on the ground of the deep-cut road, the two retaining walls are symmetrically arranged on the shoulders on both sides of the deep-cut road, the bottom ends of the retaining walls are located on the retaining structure foundation deep underground, a plurality of the prefabricated steel beams are supported between the opposite surfaces of the two retaining walls, and the newly installed bridge deck is constructed on the top surfaces of the prefabricated steel beams;

[0008] The newly installed bridge deck includes a prefabricated bridge deck and a cast-in-place bridge deck which are sequentially arranged between the top surfaces of several prefabricated steel beams; the prefabricated bridge deck includes several prefabricated bridge panels which are spliced ​​together and the joints of which fall on the top surfaces of the prefabricated steel beams.

[0009] Preferably, a plurality of pre-embedded connectors are pre-embedded on the inner vertical surface of the retaining wall, and both ends of the prefabricated steel beam abut against the pre-embedded connectors and are locked and fixed.

[0010] Preferably, both ends of the prefabricated steel beam are respectively provided with steel plate connectors, and the steel plate connectors are arranged correspondingly to the embedded connectors and are detachably connected.

[0011] Preferably, a top plate is provided at the top end of the prefabricated steel beam, and a plurality of shear-resistant connectors are provided on the top plate, and the prefabricated bridge deck is locked and connected to the prefabricated steel beam via the shear-resistant connectors.

[0012] Preferably, a plurality of pre-set holes are preset in the middle and front and rear ends of the prefabricated bridge deck, and the pre-set holes are arranged corresponding to the shear connectors. After the prefabricated bridge deck is assembled, it is cast-connected with the prefabricated steel beams through the shear connectors.

[0013] Preferably, a plurality of prestressed tendons arranged along the longitudinal direction are embedded in the prefabricated bridge deck, and the prestressed tendons are anchored at the front and rear ends of the prefabricated bridge deck; embedded steel bars are arranged at the front and rear ends of the prefabricated bridge deck, and adjacent prefabricated bridge decks are welded and fixed by corresponding embedded steel bars.

[0014] Preferably, the retaining structure foundation includes a plurality of pile foundations arranged underground, the top ends of the pile foundations extend out of the ground on both sides of the deep-cut road and are connected to a cap cast on site, and the retaining wall is cast on site on the cap.

[0015] Preferably, an anti-collision guardrail is provided on the top of the retaining wall.

[0016] A construction method for a deep-cut highway three-dimensional reconstruction and expansion structure comprises the following steps:

[0017] Excavate the slopes on both sides of the original deep-cut highway and apply slope protection;

[0018] Construct the retaining structure foundation on the outer side of the hard shoulders on both sides of the original deep cut highway, and construct the retaining wall on the retaining structure foundation;

[0019] Produce and manufacture prefabricated steel beams and prefabricated bridge panels according to the cross-sectional specifications of the highway to be expanded and constructed, and transport them to the construction site;

[0020] Hoist the prefabricated steel beams to the designated location and fix several prefabricated steel beams at equal intervals between the retaining walls on both sides;

[0021] Backfill the space between the slope and the back of the retaining wall, and the top elevation of the soil shall not exceed the top surface of the retaining wall;

[0022] Hoist the precast bridge deck onto the top plate of the precast steel beam and assemble them to form a precast bridge deck;

[0023] The precast bridge deck is treated and the cast-in-place bridge deck is cast.

[0024] Preferably, after the adjacent prefabricated bridge panels are fixed by welding with embedded steel bars, fillers are poured in the gaps between the adjacent prefabricated bridge panels.

[0025] Compared with the prior art, the present invention has the following advantages and technical effects: the present invention discloses a three-dimensional reconstruction and expansion structure and construction method for a deep-cut road, a small amount of slope expansion is carried out on both sides of the original deep-cut road, and then retaining walls are constructed to protect the slopes, and prefabricated steel beams are set up between the retaining walls on both sides, and the retaining wall-prefabricated steel beams form a stable structure to ensure the stability of the supporting structure and strengthen the protective effect of the retaining wall on the slopes; the prefabricated steel beams are suspended above the deep-cut road, a prefabricated bridge deck is set up on the prefabricated steel beams, and existing The bridge deck and road surface are poured to form a new road surface, so that the expanded highway has a double-layer three-dimensional structure, and a new highway is formed above the original highway, so that a new layer of highway is added without affecting the traffic on the original highway, thereby playing the role of highway expansion and ensuring that the number of upper lanes is consistent with the original highway; prefabricated steel beams and prefabricated bridge panels are centrally prefabricated and produced, which can effectively ensure product quality and improve production efficiency. The original highway is used on site to arrange construction machinery and equipment, reducing temporary land occupation, and prefabricated assembly technology can achieve rapid construction and reduce on-site safety risks.

[0026] The structural scheme of the present invention can make full use of the original highway line to realize three-dimensional reconstruction and expansion, reduce the demand for land resources and a large amount of excavation work, and is economical and environmentally friendly. At the same time, the retaining wall takes into account both the load-bearing structure and the slope protection function, has high construction efficiency, can be used as a temporary support and a permanent structure, and makes full use of the structural characteristics, with significant economic benefits. BRIEF DESCRIPTION OF THE DRAWINGS

[0027] The drawings constituting a part of the present application are used to provide a further understanding of the present application. The illustrative embodiments and descriptions of the present application are used to explain the present application and do not constitute an improper limitation on the present application. In the drawings:

[0028] Figure 1 This is the structural axial view of the three-dimensional reconstruction and expansion of the deep-cut highway of the present invention;

[0029] Figure 2This is a side view of the three-dimensional reconstruction and expansion structure of the deep-cut highway of the present invention;

[0030] Figure 3 It is a schematic diagram of the side view of the foundation structure of the retaining structure of the present invention;

[0031] Figure 4 This is an axial view of the prefabricated bridge deck of the present invention;

[0032] Figure 5 This is an axial view of the prefabricated steel beam of the present invention;

[0033] In the figure: 1. Deep excavation of road cutting; 2. Retaining structure foundation; 3. Retaining wall; 4. Precast bridge deck; 5. Cast-in-place bridge deck; 6. Precast bridge deck; 7. Embedded connectors; 8. Precast steel beams; 9. Steel plate connectors; 10. Shear connectors; 11. Reserved holes; 12. Embedded steel bars; 14. Pile foundation; 15. Cap; 16. Backfill; 17. Slope; 18. Crash barrier; 19. Top plate; 20. Prestressed tendons. DETAILED DESCRIPTION

[0034] The following will be combined with the drawings in the embodiments of the present invention to clearly and completely describe the technical solutions in the embodiments of the present invention. Obviously, the described embodiments are only part of the embodiments of the present invention, not all of the embodiments. Based on the embodiments of the present invention, all other embodiments obtained by ordinary technicians in this field without creative work are within the scope of protection of the present invention.

[0035] In order to make the above-mentioned objects, features and advantages of the present invention more obvious and easy to understand, the present invention is further described in detail below with reference to the accompanying drawings and specific embodiments.

[0036] Reference Figure 1-Figure 5 As shown, this embodiment provides a three-dimensional reconstruction and expansion structure of a deep-cut road, including a retaining structure arranged on the ground of the widened deep-cut road 1, a plurality of prefabricated steel beams 8 are arranged on the retaining structure, and a newly installed bridge deck is arranged on the prefabricated steel beams 8;

[0037] The retaining structure includes two retaining walls 3 arranged on the ground of the deep-cut road 1. The two retaining walls 3 are symmetrically arranged on the shoulders on both sides of the deep-cut road 1. The bottom ends of the retaining walls 3 are located on the retaining structure foundation 2 deep underground. A number of prefabricated steel beams 8 are supported between the opposite surfaces of the two retaining walls 3. The newly installed bridge deck is constructed on the top surface of the prefabricated steel beams 8.

[0038] The newly installed bridge deck includes a precast bridge deck 4 and a cast-in-place bridge deck 5 which are sequentially arranged between the top surfaces of a plurality of precast steel beams 8; the precast bridge deck 4 includes a plurality of precast bridge panels 6 which are spliced ​​together and the joints of the spliced ​​panels fall on the top surfaces of the precast steel beams 8.

[0039] The present invention discloses a three-dimensional reconstruction and expansion structure and construction method for a deep-cut road. After a small amount of side slopes 17 are expanded on both sides of the original deep-cut road, retaining walls 3 are constructed to protect the side slopes 17. Prefabricated steel beams 8 are set up between the retaining walls 3 on both sides. The retaining walls 3-prefabricated steel beams 8 form a stable structure to ensure the stability of the supporting structure and strengthen the protective effect of the retaining walls 3 on the side slopes. The prefabricated steel beams are suspended above the deep-cut road 1, a prefabricated bridge deck 4 is set up on the prefabricated steel beams 8, and a cast-in-place road surface is laid on the prefabricated bridge deck 4. A new road surface is formed, so that the expanded highway forms a double-layer three-dimensional structure, and a new highway is formed above the original highway, so that a new layer of highway is added without affecting the traffic of the original highway, thereby playing the role of highway expansion, and the number of upper lanes can be kept consistent with the original highway; the prefabricated steel beams 8 and prefabricated bridge panels 6 are centrally prefabricated and produced, which can effectively ensure product quality and improve production efficiency. The original highway is used to arrange construction machinery and equipment on site to reduce temporary land occupation, and rapid construction is achieved through prefabricated assembly technology to reduce on-site safety risks. The structural scheme of the present invention can make full use of the original highway line to achieve three-dimensional reconstruction and expansion, reduce land resource demand and a large amount of excavation operations, and is economical and environmentally friendly. At the same time, the retaining wall 3 takes into account the load-bearing structure and the slope 17 protection function, and the construction efficiency is high. The prefabricated steel beam 8 can be used as a temporary support and permanent structure, making full use of the structural characteristics, and the economic benefits are significant.

[0040] Furthermore, the retaining wall 3 of this embodiment is arranged on the upper part of the retaining structure foundation 2, and a vertical facade is arranged on the inner side and is flush with the outer side of the shoulder of the deep-cut road 1, and the toe of the retaining wall 3 on the slope 17 side is located at the foot of the newly excavated slope 17.

[0041] Furthermore, the thickness of the retaining wall 3 of this embodiment is determined according to design calculations, and the height of the retaining wall 3 is greater than 6.5 m.

[0042] Furthermore, the retaining wall 3 is provided with a settlement joint at a certain interval according to the geological conditions and the designed length.

[0043] Furthermore, for the newly formed side slope 17 with a height of less than 8m, the slope rate is controlled at 1:1.5, for the part greater than 8m, the slope rate is controlled at 1:1.75, and for the remaining part, the slope rate is controlled at 1:2, and side slope 17 protection is applied.

[0044] Further optimizing the scheme, a plurality of embedded connectors 7 are embedded on the inner vertical surface of the retaining wall 3, and the two ends of the prefabricated steel beam 8 abut against the embedded connectors 7 and are locked and fixed. The embedded connector 7 is arranged at the top of the inner side surface of the retaining wall 3 and is exposed from the retaining wall 3. The two ends of the prefabricated steel beam 8 are locked and connected with the embedded connector 7 by high-strength bolts, which is convenient for installation and positioning.

[0045] Furthermore, the embedded connector 7 of this embodiment is connected to the steel skeleton structure in the retaining wall 3 to enhance stability.

[0046] Furthermore, the embedded connection member 7 of this embodiment is a threaded perforated steel plate.

[0047] Furthermore, the bottom of the embedded connector 7 is 5.0 m above the ground.

[0048] Further optimization scheme, the two ends of the prefabricated steel beam 8 are respectively provided with steel plate connectors 9, which are correspondingly provided with the embedded connector 7 and are detachably connected. The two ends of the prefabricated steel beam 8 are respectively provided with steel plate connectors 9, which are perforated steel plates, and whose size is the same as the embedded connector 7 embedded in the retaining wall 3. When hoisting, several prefabricated steel beams 8 are hoisted with steel plate connectors 9 and embedded connectors 7 aligned, and then connected by high-strength bolts.

[0049] Furthermore, the span of the prefabricated steel beam 8 of this embodiment is determined according to the original highway section width, which is generally 20.5m-30m.

[0050] Furthermore, the prefabricated steel beam 8 of the present embodiment is a rectangular variable-section steel beam, and the cross-sectional dimensions are determined according to design calculations.

[0051] Furthermore, the prefabricated steel beam 8 has a variable cross-section along the axial direction of the beam, the width of the beam end cross-section is 0.5m, the height is 1.0m, the width of the steel beam top plate 6 is 1.0m, and the width of the flange plates on both sides is 0.25m.

[0052] Furthermore, the lower parts of both ends of the prefabricated steel beam 8 are greater than 4.5 m above the hard shoulder of the original highway.

[0053] Furthermore, the prefabricated steel beams 8 are arranged at equal intervals with an axis spacing of 4.0 m.

[0054] Further optimization scheme, the top of the prefabricated steel beam 8 is provided with a top plate 19, and a plurality of shear connectors 10 are provided on the top plate 19, and the prefabricated bridge deck 6 is locked and connected with the prefabricated steel beam 8 through the shear connectors 10. The top surface of the prefabricated steel beam 8 is provided with a widened top plate 19 to increase the support area of ​​the prefabricated bridge deck 6 and improve stability; the top plate 19 is provided with a plurality of shear connectors 10 for connecting with the prefabricated bridge deck 6.

[0055] Furthermore, the shear connector 10 of this embodiment is preferably a clustered shear connector stud, and the stud length is greater than 15 cm.

[0056] Furthermore, the layout area of ​​the shear connector 10 in this embodiment is 0.25×0.25㎡.

[0057] Further optimization scheme, the middle part and front and rear ends of the precast bridge deck 6 are preset with a plurality of reserved holes 11, and the reserved holes 11 are set corresponding to the shear connectors 10. After the precast bridge deck 6 is assembled, it is poured and connected with the precast steel beam 8 through the shear connectors 10. The precast bridge deck 6 is erected between the precast steel beams 8, and the positions of the reserved holes 11 correspond to the shear connectors 10. When the precast bridge deck 6 is assembled into the precast bridge deck 4, the reserved holes 11 of the adjacent precast bridge decks 6 are assembled together in front and surround the shear connectors 10; then the reserved grooves of the adjacent precast bridge decks 6, the gaps between the reserved holes 11 and the shear connectors 10, and the precast bridge deck 6 and the retaining walls 3 on both sides are connected by pouring concrete.

[0058] Furthermore, the front-to-rear longitudinal length of the prefabricated bridge deck 6 is determined according to the spacing between the prefabricated steel beams 8 , and the left-to-right lateral width is determined according to the span of the prefabricated steel beams 8 .

[0059] Furthermore, the prefabricated bridge deck 6 of this embodiment adopts a prestressed reinforced concrete structure with a front-to-rear longitudinal length of 8m and a thickness of 10-12cm, which can effectively ensure the mechanical properties and the anti-slip and anti-shear properties between the steel-concrete composite structure.

[0060] Further optimization scheme, a plurality of prestressed tendons 20 arranged longitudinally are embedded in the precast bridge deck 6, and the prestressed tendons 20 are anchored at the front and rear ends of the precast bridge deck 6; embedded steel bars 12 are arranged at the front and rear ends of the precast bridge deck 6, and adjacent precast bridge decks 6 are welded and fixed by corresponding embedded steel bars 12. Prestressed tendons 20 are arranged in the precast bridge deck 6 to improve the overall strength and reduce the deflection deformation of the precast bridge deck 6; embedded steel bars 12 are arranged in the precast bridge deck 6 to play a reinforcing role, and at the same time, their ends extend out of the precast bridge deck 6. When adjacent precast bridge decks 6 are spliced, the corresponding embedded steel bars 12 correspond to each other and are then welded together to play a positioning and fixing role, so that the adjacent precast bridge decks 6 are relatively fixed; the gaps set between adjacent precast bridge decks 6 are poured with concrete or other materials for fixing, so that the adjacent precast bridge decks 6 form a whole, and the poured material is combined with the embedded steel bars 12 extended and welded to form a reinforced concrete structure, which ensures the strength of the connection.

[0061] Further optimizing the scheme, the retaining structure foundation 2 includes a plurality of pile foundations 14 set underground, the tops of the pile foundations 14 extend out of the ground on both sides of the deep cut road 1 and are connected to the cap 15 cast on site, and the retaining wall 3 is cast on site on the cap 15. The original deep cut road 1 is excavated on both sides to form a new slope 17, and then a plurality of pile foundations 14 are constructed at the shadow shoulder positions on both sides of the original road, the tops of the pile foundations 14 extend out of the ground, and then the plurality of pile foundations 14 are connected together through the cap 15 constructed on site to form a platform, and then the retaining wall 3 is cast on the cap 15 to form a stable retaining structure.

[0062] Furthermore, the pile foundations 14 are arranged on both sides of the hard shoulders of the deep-cut highway 1 , and the diameter and buried depth of the pile foundations 14 are determined according to actual design conditions.

[0063] To further optimize the solution, a crash barrier 18 is provided at the top of the retaining wall 3; the crash barrier is provided on both sides of the new road surface to realize the display of the roadside and also to prevent vehicles from running out of the road surface area.

[0064] A construction method for a deep-cut highway three-dimensional reconstruction and expansion structure comprises the following steps:

[0065] Excavate the side slopes 17 on both sides of the original deep-cut highway 1 and protect the side slopes 17; select the highway section to be expanded, then cut off and clean it, and use construction equipment to excavate on both sides, clean the excavated soil, form a new side slope 17, and then protect the side slope 17 by strengthening anchor rods and protective nets;

[0066] A retaining structure foundation 2 is constructed at the outer side of the hard shoulder on both sides of the original deep-cut road 1, and a retaining wall 3 is constructed on the retaining structure foundation 2; a pile foundation 14 is constructed at the newly excavated position, the pile foundation 14 is located on the outer side of the shoulder, and then the ends of several pile foundations 14 are connected into a whole through a cap 15, and then the retaining wall 3 is constructed on the cap 15;

[0067] Prefabricated steel beams 8 and prefabricated bridge decks 6 are produced and manufactured according to the cross-sectional specifications of the highway to be expanded and constructed, and transported to the construction site; prefabricated steel beams 8, prefabricated bridge decks 6 and other prefabricated components are manufactured in a factory or other infield locations according to the construction plan, and transported to the construction site by means of transportation after passing the quality inspection;

[0068] Hoist the prefabricated steel beams 8 to the designated position, and fix several prefabricated steel beams 8 at equal intervals between the retaining walls 3 on both sides; hoist the prefabricated steel beams 8 to the installation position by a crane or other hoisting equipment, align the steel plate connectors 9 at both ends with the embedded connectors 7 pre-embedded on the retaining wall 3, and then connect them together by high-strength bolts to form a stable structure;

[0069] Backfill 16 is performed between the slope 17 and the back of the retaining wall 3. The elevation of the top of the earthwork does not exceed the top surface of the retaining wall 3. During the backfill 16, drainage facilities need to be arranged to facilitate drainage and avoid risks such as landslides caused by water accumulation;

[0070] The prefabricated bridge deck 6 is hoisted onto the top plate of the prefabricated steel beam 8 and assembled to form the prefabricated bridge deck 4, and then the fixing material is poured at the gap position to connect; the transported prefabricated bridge deck 6 is hoisted between the adjacent prefabricated steel beams 8, so that the two ends of the prefabricated bridge deck 6 are overlapped on the prefabricated steel beam 8, and the reserved holes 11 at the two ends are clamped on the shear connector 10, and then other prefabricated bridge decks 6 are assembled in sequence, so that the prestressed tendons 20 of the adjacent prefabricated bridge decks 6 are correspondingly welded and connected together, and then the fixing material of concrete or epoxy resin is poured into the gap between the prefabricated bridge decks 6 and between the prefabricated bridge decks 6 and the shear connector 10;

[0071] The prefabricated bridge deck 4 is processed and the cast-in-place bridge deck 5 is cast; the top of the prepared prefabricated bridge deck 4 is roughened, and then the plate reinforcement of the cast-in-place bridge deck 5 is installed, and the cast-in-place bridge deck 5 is cast by a tank truck or other equipment, so that the top surface of the cast-in-place bridge deck 5 does not exceed the top surface of the retaining wall 3.

[0072] Furthermore, an anti-collision guardrail 18 is installed on the top of the retaining wall 3, and the surrounding environment damaged by the construction is repaired to complete the use.

[0073] Furthermore, the number of lanes added on the bridge deck in this embodiment remains consistent with that of the original highway and can be expanded to 8, 10 or 12 lanes.

[0074] In a further optimized solution, after the adjacent precast bridge panels 6 are welded and fixed by the embedded steel bars 12, fillers are poured in the gaps between the adjacent precast bridge panels 6. The newly poured fillers use the welded embedded steel bars 12 as a skeleton to form a new structure combined with the precast bridge panels 6, so that the adjacent precast bridge panels 6 form an integral bridge deck.

[0075] In the description of the present invention, it should be understood that the terms "longitudinal", "lateral", "up", "down", "front", "back", "left", "right", "vertical", "horizontal", "top", "bottom", "inside" and "outside" etc., indicating orientations or positional relationships, are based on the orientations or positional relationships shown in the accompanying drawings, and are only for the convenience of describing the present invention, and do not indicate or imply that the device or element referred to must have a specific orientation, be constructed and operated in a specific orientation, and therefore should not be understood as a limitation on the present invention.

[0076] The embodiments described above are only descriptions of the preferred modes of the present invention, and are not intended to limit the scope of the present invention. Without departing from the design spirit of the present invention, various modifications and improvements made to the technical solutions of the present invention by ordinary technicians in this field should all fall within the protection scope determined by the claims of the present invention.

Claims

1. A three-dimensional reconstruction and expansion structure for a deep-cut highway, characterized in that: It comprises a retaining structure arranged on the ground of a widened deep-cut road (1), wherein a plurality of prefabricated steel beams (8) are arranged on the retaining structure, and a newly installed bridge deck is arranged on the prefabricated steel beams (8); The retaining structure comprises two retaining walls (3) arranged on the ground of the deep-cut road (1), the two retaining walls (3) being symmetrically arranged on the shoulders on both sides of the deep-cut road (1), the bottom ends of the retaining walls (3) being located on a retaining structure foundation (2) deep underground, a plurality of prefabricated steel beams (8) being supported between opposite surfaces of the two retaining walls (3), and the newly installed bridge deck being constructed on the top surfaces of the prefabricated steel beams (8); The newly installed bridge deck comprises a prefabricated bridge deck (4) and a cast-in-place bridge deck (5) which are sequentially arranged between the top surfaces of a plurality of prefabricated steel beams (8); the prefabricated bridge deck (4) comprises a plurality of prefabricated bridge panels (6), and the plurality of prefabricated bridge panels (6) are spliced ​​together and the joints of the spliced ​​panels fall on the top surfaces of the prefabricated steel beams (8).

2. The deep-cut highway three-dimensional reconstruction and expansion structure according to claim 1 is characterized in that: A plurality of pre-embedded connecting pieces (7) are pre-embedded on the inner vertical surface of the retaining wall (3), and both ends of the prefabricated steel beam (8) abut against the pre-embedded connecting pieces (7) and are locked and fixed.

3. The deep-cut highway three-dimensional reconstruction and expansion structure according to claim 2 is characterized by: Steel plate connectors (9) are respectively provided at both ends of the prefabricated steel beam (8), and the steel plate connectors (9) are arranged correspondingly to the embedded connectors (7) and are detachably connected.

4. The deep-cut highway three-dimensional reconstruction and expansion structure according to claim 3 is characterized by: A top plate (19) is provided at the top end of the prefabricated steel beam (8), a plurality of shear-resistant connectors (10) are provided on the top plate (19), and the prefabricated bridge deck (6) is locked and connected to the prefabricated steel beam (8) via the shear-resistant connectors (10).

5. The deep-cut highway three-dimensional reconstruction and expansion structure according to claim 4 is characterized in that: A plurality of pre-set holes (11) are preset in the middle and front and rear ends of the prefabricated bridge deck (6), and the pre-set holes (11) are arranged corresponding to the shear-resistant connectors (10). After the prefabricated bridge deck (6) is assembled, it is cast-connected to the prefabricated steel beam (8) through the shear-resistant connectors (10).

6. The deep-cut highway three-dimensional reconstruction and expansion structure according to claim 1 is characterized by: A plurality of prestressed tendons (20) arranged longitudinally are embedded in the prefabricated bridge deck (6), and the prestressed tendons (20) are anchored at the front and rear ends of the prefabricated bridge deck (6); embedded steel bars (12) are arranged at the front and rear ends of the prefabricated bridge deck (6), and adjacent prefabricated bridge decks (6) are fixed by welding via the corresponding embedded steel bars (12).

7. The deep-cut highway three-dimensional reconstruction and expansion structure according to claim 1 is characterized by: The retaining structure foundation (2) includes a plurality of pile foundations (14) arranged underground, the top ends of the pile foundations (14) extending out of the ground on both sides of the deep-cut road (1) and connected to a cap (15) cast on site, and the retaining wall (3) is cast on site on the cap (15).

8. The deep-cut highway three-dimensional reconstruction and expansion structure according to claim 1 is characterized by: An anti-collision guardrail (18) is provided at the top of the retaining wall (3).

9. A construction method for a three-dimensional reconstruction and expansion structure of a deep-cut road, according to the three-dimensional reconstruction and expansion structure of a deep-cut road according to any one of claims 1 to 8, characterized by the following steps: Excavating the side slopes (17) on both sides of the original deep-cut road (1) and applying side slope (17) protection; Constructing a retaining structure foundation (2) at the outer side of the hard shoulders on both sides of the original deep-cut road (1), and constructing a retaining wall (3) on the retaining structure foundation (2); Producing and manufacturing prefabricated steel beams (8) and prefabricated bridge panels (6) according to the cross-sectional specifications of the highway to be expanded and constructed, and transporting them to the construction site; Hoisting the prefabricated steel beams (8) to the designated location, and fixing a plurality of prefabricated steel beams (8) at equal intervals between the retaining walls (3) on both sides; Backfilling (16) earthwork between the side slope (17) and the back of the retaining wall (3), with the top elevation of the earthwork not exceeding the top surface of the retaining wall (3); Hoisting the prefabricated bridge deck (6) onto the top plate of the prefabricated steel beam (8) and splicing them together to form a prefabricated bridge deck (4); The prefabricated bridge deck (4) is processed and the cast-in-place bridge deck (5) is cast.

10. The construction method of the deep-cut highway three-dimensional reconstruction and expansion structure according to claim 9 is characterized in that: After the adjacent prefabricated bridge panels (6) are welded and fixed by pre-buried steel bars (12), fillers are poured into the gaps between the adjacent prefabricated bridge panels (6).