Construction method for well completion pipe string for well mouth suspension and well bottom plugging of coiled tubing
Through the combination of prefabricated suspension tiles and oil pipe suspension, combined with the use of bottom-hole sealing and plugging, the safety hazards and sealing problems of wellhead suspension in the continuous pipe completion process are solved, and the safety and efficiency of the wellhead and bottom-hole are achieved , economical completion effect.
Patent Information
- Application Number
- CN202310643960.9
- Authority / Receiving Office
- CN · China
- Patent Type
- Applications(China)
- Current Assignee / Owner
- Filing Date
- 2023-06-01
- Publication Date
- 2024-12-03
Smart Images

Figure CN119062258A_ABST
Abstract
Description
Technical Field
[0001] The invention relates to the technical field of natural gas well completion, and in particular to a construction method for a continuous tubing wellhead suspension and well bottom plugging completion pipe string. Background Art
[0002] With the development of tight gas / shale gas, problems such as decreasing production and increasing water content caused by the use of tubing strings for well completion and gas production have gradually emerged, seriously affecting gas layer production; traditional tubing pressure operation is complex and inefficient, and the existing equipment has low pressure operation level and is expensive; in the later stage, the wellbore is filled with liquid, and the conventional tubing has poor liquid carrying capacity, so auxiliary processes are required for drainage and gas production, which increases the development cost. Continuous tubing has the advantages of no need to connect single pipes, small internal diameter, and fast completion speed. The corresponding characteristics are also reflected in the speed string process. Applying the inherent advantages of continuous tubing to the development of tight gas / shale gas, forming a continuous tubing completion and gas production integrated technology, leading and promoting the cost reduction and quality improvement of resource development, and safe and efficient construction operations, is of great significance in the low oil price environment.
[0003] Regarding the currently disclosed coiled tubing completion string process, patent CN105064940B discloses a built-in coiled tubing completion string and construction method. The string includes a built-in hanger, a coiled tubing, a plug and a plugging rod. The process sequence is to install the built-in hanger in the tubing head, lower the pipe to the designed position once, temporarily hang the coiled tubing shear pipe to install the locking type seat hanging joint, lower the pipe for the second time to seat the joint together with the coiled tubing into the hanger body, and then restore the wellhead gas production tree to complete the coiled tubing completion string for production. Patent CN115162999A discloses a large-diameter continuous gas production string delivery construction method. The process sequence is to lower the pipe to the designed position once, temporarily hang the shear pipe, connect the coiled tubing with the tubing hanger, lower the pipe for the second time to seat the tubing hanger to the wellhead, and then restore the wellhead gas production tree to complete the coiled tubing completion string for production. The above method is also the most widely used coiled tubing completion string process in oil fields and on the market. There are two problems with both completion processes:
[0004] (1) After the shearing, the coiled tubing is in a temporary suspension state. At this time, the coiled tubing is only suspended by the wellhead blowout prevention equipment, which has high safety performance requirements for the wellhead blowout prevention equipment. If the equipment suspension function fails, the coiled tubing will directly fall into the well and cause an accident. Therefore, this process has a great safety hazard;
[0005] (2) The annular passage between the coiled tubing and the wellbore is sealed only by the wellhead hanger. During the wellhead disassembly and assembly operation, the wellhead hanger is under long-term pressure. If the sealing operation is improper, there is a risk of leakage and top-up, threatening the wellhead operators. In addition, the annular space is exposed to the production environment for a long time, and the casing and production pipe string are prone to corrosion and perforation, which affects the subsequent drainage and production operations.
[0006] In view of the above problems existing in the existing coiled tubing completion technology and the need for an integrated coiled tubing completion and gas production technology, there is currently a lack of a safe, efficient and economical completion string technology that allows the coiled tubing to be suspended at the wellhead and plugged at the bottom of the well. Summary of the invention
[0007] The purpose of the present invention is to overcome the risk problem caused by temporary suspension of coiled pipe in the prior art.
[0008] In order to achieve the above object, the present invention provides a construction method for a coiled tubing wellhead suspension and well bottom plugging completion string, wherein the construction method comprises:
[0009] S1. Place the coiled tubing equipment, install the wellhead equipment and conduct pressure test. The wellhead equipment from top to bottom includes the injection head, blowout preventer box, four-gate blowout preventer, blowout preventer, pressure relief tee and operation window;
[0010] S2, passing the coiled tubing through the injection head, installing a well-entry tool string for well cleaning, lowering the tubing to the designed position, and performing well cleaning operations;
[0011] S3, lifting the coiled tubing to the operation window, replacing the well-entry tool string for the completion string, setting a tubing hanger on the coiled tubing, lowering the coiled tubing, allowing the tubing hanger to fall into the wellhead spool and seal it, and continuing to lower the coiled tubing to the designed depth;
[0012] S4, opening the operating window, installing hanging slips on the coiled tubing, lowering the coiled tubing so that the hanging slips fall into the tubing hanger, and continuing to lower the hanging slips until the hanging weight is zero, and then cutting the coiled tubing;
[0013] S5. Remove the wellhead equipment, restore the gas tree, and clear the plug to start production.
[0014] In some embodiments, a slip tooth is provided on the inner circumferential surface of the suspension slip, the outer circumferential surface of the suspension slip is formed as a tapered surface from top to bottom, and the inner circumferential surface of the upper end of the tubing hanger is formed as a tapered surface from top to bottom to accommodate and suspend the suspension slip.
[0015] In some embodiments, the suspension slip includes two semi-tubular portions and a connector for detachably connecting the two semi-tubular portions.
[0016] In some embodiments, the tubing hanger is sealingly engaged with the wellhead spool, and the tubing hanger is fixed by a top screw of the wellhead spool.
[0017] In some embodiments, in S3, the replacement of the wellbore tool string for the completion tubing string includes: opening the operation window, disassembling the wellbore tool string for well cleaning, installing a dropper, a packer, and a plugger at the lower end of the continuous tubing, and hanging the tubing hanger on the packer.
[0018] In some embodiments, in S3, after the coiled tubing is continued to be lowered to a designed depth, the inside of the tubing is pressurized so that the packer is set at a designed position, and the coiled tubing is continued to be lowered to release a portion of the suspended weight of the injection head.
[0019] In some embodiments, S3 further includes: opening the pressure relief tee and controlling the blowout through the ground throttle manifold to release the upper pressure of the packer, filling the annulus area with packer fluid, so that there is no pressure at the wellhead.
[0020] In some embodiments, in S3, continuing to lower the coiled tubing to the designed depth includes: lowering the coiled tubing at a speed not exceeding 5 m / min, and observing the operation of the equipment when the lowering depth reaches 50 m; then continuing to lower the coiled tubing at a speed of 25-30 m / min, and performing a lifting and hanging weight test every 500 m during the lowering process; when the coiled tubing is lowered to 300 m from the designed depth, reducing the speed to 10-15 m / min, and when the coiled tubing is lowered to 100 m from the designed depth, reducing the speed to 5 m / min, and lifting it to the designed depth after passing the designed depth of 15 m.
[0021] In some embodiments, in S1, the gate switch function of the four-gate blowout preventer is tested to be in the fully open position, and then the injection head, the blowout preventer box, the four-gate blowout preventer, the pressure relief tee, the blowout preventer, and the operating window are installed and connected to the ground high-pressure pump group pipeline to perform pressure tests on the ground pipeline and wellhead equipment.
[0022] In some embodiments, the pressure test requires increasing the pump pressure stepwise by 10%, 50%, and 100% to 35 MPa, and is qualified if the pressure is stabilized for 10 minutes and the pressure drop is less than 0.7 MPa. If a leak is found, the pump is immediately stopped to release the pressure for rectification.
[0023] In some embodiments, in S2, the coiled tubing is passed through the injection head and lowered to the operation window position; the operation window is opened, the lower end of the coiled tubing is chamfered, a connector is installed, and a tension test is performed; a motor head and a well cleaning tool are installed at the lower end of the connector, the operation window is closed, and the wellhead equipment is pressure tested through a ground high-pressure pump group pipeline; the flat valve is opened, the coiled tubing is lowered to the designed depth, and the ground high-pressure pump group pipeline is started to complete the well cleaning operation in the designed area.
[0024] In some embodiments, during the installation of the connector, the lower end of the coiled tube is chamfered at 45°; the connector is subjected to a 15-ton tensile test, and a displacement of less than 3-5 mm is considered qualified.
[0025] In some embodiments, in S4, the operating window is opened, and the hanging slips are installed to the outer wall of the coiled tubing and close to the upper part of the tubing hanger; the coiled tubing is continued to be lowered, and the hanging slips fall into the tubing hanger, and the coiled tubing is continued to be lowered until the hanging weight of the injection head is zero and the coiled tubing has no slippage and no abnormal load, and then the shear ram of the four-ram blowout preventer is used to shear the coiled tubing, lift the coiled tubing, and observe the load and pressure changes of the injection head to verify whether the shearing is successful.
[0026] In some embodiments, in S5, all equipment above the wellhead spool is removed, the coiled tubing above the hanging slips is cut off with a manual cutter, the upper end of the coiled tubing is chamfered, and the necking and burrs of the cut tubing are removed.
[0027] In some embodiments, a No. 1 liner and a No. 2 liner are installed in the gas tree, the gas tree is assembled, and the main valve of the gas tree is closed; the plug of the plugging device is removed by pressurizing the pipeline of the ground high-pressure pump group, and then the well is shut in.
[0028] Through the above technical solution, by prefabricating the hanging slips before cutting the pipe, the safety hazard caused by the temporary hanging of the wellhead equipment is avoided. BRIEF DESCRIPTION OF THE DRAWINGS
[0029] Figure 1 —Schematic diagram of coiled tubing completion string structure
[0030] Figure 2 —Schematic diagram of the coiled tubing completion string process wellhead device
[0031] Figure 3 —Schematic diagram of the wellhead process of coiled tubing completion string technology
[0032] Figure 4 —Schematic diagram of coiled tubing well cleaning tool string
[0033] Figure 5—Schematic diagram of coiled tubing completion tool string
[0034] Figure 6 —Schematic diagram of the process of installing hanging slips
[0035] Figure 7 —Schematic diagram of coiled tubing wellhead suspension process
[0036] Figure 8 — Continuous pipe suspension slip structure diagram
[0037] Fig. 9 —Tubing hanger structure diagram
[0038] Fig.10 —Structure diagram of continuous pipe connector
[0039] Fig.11 —Structure diagram of coiled tubing release
[0040] Fig.12 —Structure diagram of coiled tubing packer
[0041] Fig.13 —Structure diagram of coiled tubing plugger
[0042] Fig.14 — Wellhead gas tree structure diagram
[0043] Description of Reference Numerals
[0044] 1: Coiled tubing; 2: Hanging slips; 2-1: Slip teeth; 2-2: Hanger outer wall; 3-Tubing hanger; 3-1: Hanger body; 3-2: Seal assembly; 4: Connector; 4-1: Slip connection; 4-2: Rubber cartridge seal; 5: Hand release; 5-1: Upper joint; 5-2: Pin; 5-3: Lower joint; 6: Packer; 6-1: Rivet slips; 6-2: Annulus sealing rubber cartridge; 7: Plug; 7-1: double-flap back-pressure valve; 7-2: plug; 7-3: screen, 7-4: guide head; 8: injection head; 9: blowout preventer box; 10: four-gate blowout preventer; 11-blowout preventer; 12: pressure relief tee; 13: operation window; 14: flat valve; 15: wellhead spool; 16: motor head; 17: well cleaning tool; 18: gas tree; 18-1: No. 1 liner; 18-2: No. 2 liner. DETAILED DESCRIPTION
[0045] The specific implementation of the present invention is described in detail below in conjunction with the accompanying drawings. It should be understood that the specific implementation described here is only used to illustrate and explain the present invention, and is not used to limit the present invention.
[0046] Embodiment 1
[0047] This solution provides a construction method for a coiled tubing wellhead suspension and well bottom plugging completion string, wherein the construction method comprises:
[0048] S1, place the coiled tubing 1 operating equipment, install the wellhead equipment and test the pressure, wherein the wellhead equipment from top to bottom are injection head 8, blowout preventer box 9, four-gate blowout preventer 10, blowout preventer 11, pressure relief tee 12, operation window 13, reference Figure 2 As shown;
[0049] S2, passing the coiled tubing 1 through the injection head 8, installing a well-entry tool string for well cleaning, lowering the tubing to the designed position, and performing well cleaning operations;
[0050] S3, lifting the coiled tubing 1 to the operation window 13, replacing the downhole tool string for the completion string, setting the tubing hanger 3 on the coiled tubing 1, lowering the coiled tubing 1, making the tubing hanger 3 fall into the wellhead spool 15 and seal it, and continuing to lower the coiled tubing 1 to the designed depth;
[0051] S4, opening the operating window 13, installing the hanging slips 2 on the coiled tubing 1, lowering the coiled tubing 1 so that the hanging slips 2 fall into the tubing hanger 3, and continuing to lower the coiled tubing 1 until the hanging weight is zero, and then cutting the coiled tubing 1;
[0052] S5. Remove the wellhead equipment, restore the gas tree 18, and remove the plug 7 to start production.
[0053] The tubing hanger 3 is movably arranged on the coiled tubing 1. Therefore, when the coiled tubing 1 is lowered, the tubing hanger 3 can be dropped onto the wellhead spool 15 to be sealed. Figure 6 and Figure 7 As shown, the hanging slips 2 are fixed on the coiled tubing 1, and can be held in the tubing hanger 3 as the coiled tubing 1 moves downward, thereby hanging the coiled tubing 1 on the tubing hanger 3, thereby solving the risks caused by temporary hanging.
[0054] In this solution, by prefabricating the hanging slips before cutting the pipe, the potential safety hazard caused by the temporary hanging of the wellhead equipment is avoided.
[0055] Among them, reference Figure 8 and Fig. 9 As shown, the inner circumference of the hanging slip 2 is provided with a slip tooth 2-1, the outer circumference of the hanging slip 2 is formed as a tapered surface from top to bottom, and the inner circumference of the upper end of the tubing hanger 3 is formed as a tapered surface from top to bottom to accommodate and hang the hanging slip 2. Figure 8 As shown, the hanging slips 2 are engaged with the outer wall of the coiled tubing 1 through the slip teeth 2-1, and the outer circumference is matched with the inner circumference of the tubing hanger 3 to axially support the hanging slips 2 upward through the tubing hanger 3. After the coiled tubing 1 is connected to the hanging slips 2 by its own weight, the hanging slips 2 hang the coiled tubing 1 at the wellhead through the tubing hanger 3.
[0056] like Fig. 9 As shown, the tubing hanger 3 includes a hanger body 3 - 1 and a sealing assembly 3 - 2 , and the sealing groove on the inner circumference matches with the outer circumference of the suspension slip 2 .
[0057] The suspension slip 2 comprises two semi-tubular parts and a connecting piece for detachably connecting the two semi-tubular parts. Figure 8 As shown, the suspension slip 2 is mainly composed of two semi-tubular parts, which are detachably connected by a connecting piece. Such a structure makes it easy to install the suspension slip 2 on the continuous pipe 1.
[0058] The tubing hanger 3 is sealed and engaged with the wellhead spool 15, and the tubing hanger 3 is fixed by the top screw of the wellhead spool 15. Fig.14 As shown, the tubing hanger 3 is arranged in the wellhead spool 15, and its outer periphery is sealed and engaged with the inner periphery of the wellhead spool 15 to achieve sealing. The wellhead spool 15 is tightened with the tubing hanger 3 by radial jackscrews to achieve relative fixation.
[0059] Among them, in S3, the replacement of the well-entry tool string for the completion string includes: opening the operation window 13, disassembling the well-entry tool string for cleaning the well, installing the dropper 5, the packer 6, and the plug 7 at the lower end of the coiled tubing 1, and hanging the tubing hanger 3 on the packer 6, referring to Figure 5 The dropper 5, the packer 6, and the plug 7 are a completion tool string. After the well entry tool string is disassembled through the operation window 13, the completion tool string is installed at the lower end of the coiled tubing 1.
[0060] like Fig.11 As shown, the release 5 adopts a mechanical release structure, which includes an upper joint 5-1, a pin 5-2 and a lower joint 5-3 structure from top to bottom, and is installed between the connector 4 and the packer 6. When the tool string at the bottom end of the coiled tubing 1 is stuck, the pin 5-2 is sheared off by lifting the pipe string to achieve the release operation of the coiled tubing 1.
[0061] like Fig.12 As shown, the packer 6 is installed between the release hand 5 and the plugger 7. By pressurizing the inside of the pipe, the continuous pipe 1 and the casing annulus channel at the position of the packer 6 can be plugged.
[0062] like Fig.13As shown, the plug 7 adopts a functional integrated design, including a double-flap back-pressure valve 7-1, a plug 7-2, a screen 7-3 and a guide head 7-4 from top to bottom. The double-flap back-pressure valve 7-1 is located at the front end of the plug 7-2, and is constrained by the control sleeve to be in an open state. The control sleeve is knocked off by throwing a ball, and the double-flap back-pressure valve 7-1 is started to realize the pressure-lifting of the pipe. The plug 7-2 is placed at the end of the plug 7 to achieve the internal sealing of the pipe. The fixed pin is sheared off by pressure and the plug 7-2 is pumped down for production. The screen 7-3 is located at the lower end of the functional area of the plug 7, and adopts a grid-shaped design. The grid spacing can be adjusted according to production needs. The guide head 7-4 is located at the tail end of the plug 7, connected to the screen 7-3, and fixed by the rivets.
[0063] In addition, in S3, after the coiled tubing 1 is further lowered to the designed depth, the packer 6 is set at the designed position by pressurizing the inside of the tubing, and the coiled tubing 1 is further lowered to release a portion of the hanging weight of the injection head 8. When the lower end of the coiled tubing 1 reaches the designed depth, the packer 6 is set on the casing by pressurizing the inside of the coiled tubing 1, and the coiled tubing 1 is further lowered, thereby releasing a portion of the hanging weight of the injection head 8. The packer 6 can realize the plugging of the downhole annulus by the coiled tubing as a completion string, and the development of a specific production layer section can be carried out.
[0064] Furthermore, the step S3 also includes: opening the pressure relief tee 12 and controlling the blowout through the surface throttle manifold to release the pressure on the upper part of the packer 6, filling the annular area with packer fluid, and making the wellhead pressure-free. The packer fluid is injected into the annular area to protect the casing and the production string and the wellhead from pressure-induced safe operation.
[0065] Among them, in S3, the continuous lowering of the coiled tube 1 to the designed depth includes: lowering the coiled tube 1 at a speed not exceeding 5m / min, observing the operation of the equipment when the lowering depth reaches 50m; then continuing to lower the coiled tube 1 at a speed of 25m / min, and performing a lifting and hanging weight test every 500m during the lowering process; when it is lowered to 300m from the designed depth, the speed is reduced to 10m / min, and when it is lowered to 100m from the designed depth, the speed is reduced to 5m / min, and after the designed depth exceeds 15m, it is lifted to the designed depth. When lowering the coiled tube 1, first lower the tube at a lower speed, then lower the tube at a higher speed, and perform a hanging weight test, and finally lower the tube at a lower speed, and lift it up after the lowered depth exceeds the designed depth.
[0066] Among them, in S1, the gate switch function of the four-gate blowout preventer 10 is tested to make it in the fully open position, and then the injection head 8, the blowout preventer box 9, the four-gate blowout preventer 10, the pressure relief tee 12, the blowout preventer 11, and the operation window 13 are installed and connected to the ground high-pressure pump group pipeline to perform ground pipeline and wellhead equipment pressure testing. Through the ground high-pressure pump group pipeline (reference Figure 3 Test the pressure to detect leaks.
[0067] Furthermore, the pressure test requires that the pump pressure be increased step by step by 10%, 50%, and 100% to 35MPa, and the pressure must be maintained for 10 minutes and the pressure drop must be less than 0.7MPa to be qualified. If a leak is found, the pump must be stopped immediately to release the pressure and rectify the problem. During the pressure test, the pressure is increased step by step. When the maximum pressure is reached, the corresponding pressure must be maintained for a certain period of time. If there is a leak, rectification and repair are required.
[0068] In S2, the coiled tube 1 is passed through the injection head 8 and lowered to the position of the operation window 13; the operation window 13 is opened, the lower end of the coiled tube 1 is chamfered, the connector 4 is installed, and a tensile test is performed; Figure 4 As shown, a motor head 16 and a well cleaning tool 17 are installed at the lower end of the connector 4, the operation window 13 is closed, and the wellhead equipment is pressure tested through the surface high-pressure pump group pipeline; the flat valve 14 is opened, the coiled tubing 1 is lowered to the designed depth, and the surface high-pressure pump group pipeline is opened to complete the well cleaning operation in the designed area. Figure 4 As shown, a motor head 16 and a well cleaning tool 17 are installed at the lower end of the connector 4. Fig.10 As shown, the connector 4 adopts a rubber seal design, including a slip connection 4-1 and a rubber seal 4-2 from top to bottom, which is installed at the bottom of the coiled tubing 1 so that the coiled tubing 1 can be connected to the downhole tool assembly.
[0069] Furthermore, during the installation of the connector 4, the lower end of the coiled tube 1 is chamfered by 45°; the connector 4 is subjected to a 15t tensile test, wherein the displacement is less than 3-5mm and is considered qualified. The coiled tube 1 is chamfered to facilitate connection with the connector 4; the connector 4 is subjected to a tensile test to confirm its connection strength.
[0070] Among them, in S4, the operation window 13 is opened, and the hanging slip 2 is installed on the outer wall of the coiled tubing 1 and close to the upper part of the tubing hanger 3; the coiled tubing 1 is continued to be lowered, and the hanging slip 2 falls into the tubing hanger 3, and the coiled tubing 1 is continued to be lowered until the hanging weight of the injection head 8 is zero and the coiled tubing 1 has no slippage and no abnormal load, and the shear ram of the four-ram blowout preventer 10 is used to cut the coiled tubing 1, and the coiled tubing 1 is lifted and the load and pressure changes of the injection head 8 are observed to verify whether the pipe cutting is successful. After the hanging slip 2 is installed on the coiled tubing 1, the coiled tubing 1 is lowered, so that the hanging slip 2 is suspended on the tubing hanger 3, and the coiled tubing 1 is continued to be lowered, so that the downward pulling force of the coiled tubing 1 on the injection head 8 is zero, and the coiled tubing 1 is cut; the coiled tubing 1 above the shearing position is lifted to determine whether the coiled tubing 1 is cut.
[0071] In S5, all equipment above the wellhead spool 15 is removed, the coiled tubing 1 above the hanging slips 2 is cut off with a manual cutter, the upper end of the coiled tubing 1 is chamfered, and the neck and burrs of the cut pipe are removed.
[0072] Wherein, No. 1 liner and No. 2 liner are installed in the gas tree 18, the gas tree 18 is assembled, and the main valve of the gas tree 18 is closed; the plug 7-2 of the plug 7 is knocked out by the pipeline of the ground high-pressure pump group, and the well is shut in. Fig.14 As shown, the gas production tree 18 includes a multi-section structure. Before connecting the multi-section structure, No. 1 liner 18-1 and No. 2 liner 18-2 are installed therein so that No. 1 liner 18-1 and No. 2 liner 18-2 are docked with the continuous pipe 1. Then the multi-section structure is connected, and the main valve of the gas production tree 18 is closed; the pipeline of the ground high-pressure pump group is pressurized to knock out the plug 7-2 of the plug 7, connect the reservoir and the continuous pipe 1, and shut in the well.
[0073] Embodiment 2
[0074] This solution provides a construction method for a coiled tubing wellhead suspension and well bottom plugging completion string, wherein the construction method comprises:
[0075] S1, place the coiled tubing 1 operating equipment, install the wellhead equipment and test the pressure, wherein the wellhead equipment from top to bottom are injection head 8, blowout preventer box 9, four-gate blowout preventer 10, blowout preventer 11, pressure relief tee 12, operation window 13, reference Figure 2 As shown;
[0076] S2, passing the coiled tubing 1 through the injection head 8, installing a well-entry tool string for well cleaning, lowering the tubing to the designed position, and performing well cleaning operations;
[0077] S3, lifting the coiled tubing 1 to the operation window 13, replacing the downhole tool string for the completion string, setting the tubing hanger 3 on the coiled tubing 1, lowering the coiled tubing 1, making the tubing hanger 3 fall into the wellhead spool 15 and seal it, and continuing to lower the coiled tubing 1 to the designed depth;
[0078] S4, opening the operating window 13, installing the hanging slips 2 on the coiled tubing 1, lowering the coiled tubing 1 so that the hanging slips 2 fall into the tubing hanger 3, and continuing to lower the coiled tubing 1 until the hanging weight is zero, and then cutting the coiled tubing 1;
[0079] S5. Remove the wellhead equipment, restore the gas tree 18, and remove the plug 7 to start production.
[0080] The tubing hanger 3 is movably arranged on the coiled tubing 1. Therefore, when the coiled tubing 1 is lowered, the tubing hanger 3 can be dropped onto the wellhead spool 15 to be sealed. Figure 6 and Figure 7 As shown, the hanging slips 2 are fixed on the coiled tubing 1, and can be held in the tubing hanger 3 as the coiled tubing 1 moves downward, thereby hanging the coiled tubing 1 on the tubing hanger 3, thereby solving the risks caused by temporary hanging.
[0081] In this solution, by prefabricating the hanging slips before cutting the pipe, the potential safety hazard caused by the temporary hanging of the wellhead equipment is avoided.
[0082] Among them, reference Figure 8 and Fig. 9 As shown, the inner circumference of the hanging slip 2 is provided with a slip tooth 2-1, the outer circumference of the hanging slip 2 is formed as a tapered surface from top to bottom, and the inner circumference of the upper end of the tubing hanger 3 is formed as a tapered surface from top to bottom to accommodate and hang the hanging slip 2. Figure 8 As shown, the hanging slips 2 are engaged with the outer wall of the coiled tubing 1 through the slip teeth 2-1, and the outer circumference is matched with the inner circumference of the tubing hanger 3 to axially support the hanging slips 2 upward through the tubing hanger 3. After the coiled tubing 1 is connected to the hanging slips 2 by its own weight, the hanging slips 2 hang the coiled tubing 1 at the wellhead through the tubing hanger 3.
[0083] like Fig. 9 As shown, the tubing hanger 3 includes a hanger body 3 - 1 and a sealing assembly 3 - 2 , and the sealing groove on the inner circumference matches with the outer circumference of the suspension slip 2 .
[0084] The suspension slip 2 comprises two semi-tubular parts and a connecting piece for detachably connecting the two semi-tubular parts. Figure 8As shown, the suspension slip 2 is mainly composed of two semi-tubular parts, which are detachably connected by a connecting piece. Such a structure makes it easy to install the suspension slip 2 on the continuous pipe 1.
[0085] The tubing hanger 3 is sealed and engaged with the wellhead spool 15, and the tubing hanger 3 is fixed by the top screw of the wellhead spool 15. Fig.14 As shown, the tubing hanger 3 is arranged in the wellhead spool 15, and its outer periphery is sealed and engaged with the inner periphery of the wellhead spool 15 to achieve sealing. The wellhead spool 15 is tightened with the tubing hanger 3 by radial jackscrews to achieve relative fixation.
[0086] Among them, in S3, the replacement of the well-entry tool string for the completion string includes: opening the operation window 13, disassembling the well-entry tool string for cleaning the well, installing the dropper 5, the packer 6, and the plug 7 at the lower end of the coiled tubing 1, and hanging the tubing hanger 3 on the packer 6, referring to Figure 5 The dropper 5, the packer 6, and the plug 7 are a completion tool string, which is installed at the lower end of the coiled tubing 1 after the well entry tool string is disassembled through the operation window 13.
[0087] like Fig.11 As shown, the release 5 adopts a mechanical release structure, which includes an upper joint 5-1, a pin 5-2 and a lower joint 5-3 structure from top to bottom, and is installed between the connector 4 and the packer 6. When the tool string at the bottom end of the coiled tubing 1 is stuck, the pin 5-2 is sheared off by lifting the pipe string to achieve the release operation of the coiled tubing 1.
[0088] like Fig.12 As shown, the packer 6 is installed between the release hand 5 and the plugger 7. By pressurizing the inside of the pipe, the continuous pipe 1 and the casing annulus channel at the position of the packer 6 can be plugged.
[0089] like Fig.13 As shown, the plug 7 adopts a functional integrated design, including a double-flap back-pressure valve 7-1, a plug 7-2, a screen 7-3 and a guide head 7-4 from top to bottom. The double-flap back-pressure valve 7-1 is located at the front end of the plug 7-2, and is constrained by the control sleeve to be in an open state. The control sleeve is knocked off by throwing a ball, and the double-flap back-pressure valve 7-1 is started to realize the pressure-lifting of the pipe. The plug 7-2 is placed at the end of the plug 7 to achieve the internal sealing of the pipe. The fixed pin is sheared off by pressure and the plug 7-2 is pumped down for production. The screen 7-3 is located at the lower end of the functional area of the plug 7, and adopts a grid-shaped design. The grid spacing can be adjusted according to production needs. The guide head 7-4 is located at the tail end of the plug 7, connected to the screen 7-3, and fixed by the rivets.
[0090] In addition, in S3, after the coiled tubing 1 is further lowered to the designed depth, the packer 6 is set at the designed position by pressurizing the inside of the tubing, and the coiled tubing 1 is further lowered to release a portion of the hanging weight of the injection head 8. When the lower end of the coiled tubing 1 reaches the designed depth, the packer 6 is set on the casing by pressurizing the inside of the coiled tubing 1, and the coiled tubing 1 is further lowered, thereby releasing a portion of the hanging weight of the injection head 8. The packer 6 can realize the plugging of the downhole annulus by the coiled tubing as a completion string, and the development of a specific production layer section can be carried out.
[0091] Furthermore, the step S3 also includes: opening the pressure relief tee 12 and controlling the blowout through the surface throttle manifold to release the pressure on the upper part of the packer 6, filling the annular area with packer fluid, and making the wellhead pressure-free. The packer fluid is injected into the annular area to protect the casing and the production string and the wellhead from pressure-induced safe operation.
[0092] Among them, in S3, the continuous lowering of the coiled tube 1 to the designed depth includes: lowering the coiled tube 1 at a speed not exceeding 5m / min, observing the operation of the equipment when the lowering depth reaches 50m; then continuing to lower the coiled tube 1 at a speed of 30m / min, and performing a lifting and hanging weight test every 500m during the lowering process; when it is 300m away from the designed depth, reducing the speed to 15m / min, and when it is 100m away from the designed depth, reducing the speed to 5m / min, and lifting it to the designed depth after the designed depth of 15m is exceeded. When lowering the coiled tube 1, first lower the tube at a lower speed, then lower the tube at a higher speed, and perform a hanging weight test, and finally lower the tube at a lower speed, and lift it up after the lowered depth exceeds the designed depth.
[0093] Among them, in S1, the switch function of each gate of the four-gate blowout preventer 10 is tested to make it in the fully open position, and then the injection head 8, the blowout preventer box 9, the four-gate blowout preventer 10, the pressure relief tee 12, the blowout preventer 11, and the operation window 13 are installed, and connected to the ground high-pressure pump group pipeline to perform pressure testing on the ground pipeline and wellhead equipment respectively. The pressure test is performed through the ground high-pressure pump group pipeline to detect whether there is a leak.
[0094] Furthermore, the pressure test requires that the pump pressure be increased step by step by 10%, 50%, and 100% to 35MPa, and the pressure must be maintained for 10 minutes and the pressure drop must be less than 0.7MPa to be qualified. If a leak is found, the pump must be stopped immediately to release the pressure and rectify the problem. During the pressure test, the pressure is increased step by step. When the maximum pressure is reached, the corresponding pressure must be maintained for a certain period of time. If there is a leak, rectification and repair are required.
[0095] In S2, the coiled tube 1 is passed through the injection head 8 and lowered to the position of the operation window 13; the operation window 13 is opened, the lower end of the coiled tube 1 is chamfered, the connector 4 is installed, and a tensile test is performed; Figure 4 As shown, a motor head 16 and a well cleaning tool 17 are installed at the lower end of the connector 4, the operation window 13 is closed, and the wellhead equipment is pressure tested through the surface high-pressure pump group pipeline; the flat valve 14 is opened, the coiled tubing 1 is lowered to the designed depth, and the surface high-pressure pump group pipeline is opened to complete the well cleaning operation in the designed area. Figure 4 As shown, a motor head 16 and a well cleaning tool 17 are installed at the lower end of the connector 4. Fig.10 As shown, the connector 4 adopts a rubber seal design, including a slip connection 4-1 and a rubber seal 4-2 from top to bottom, which is installed at the bottom of the coiled tubing 1 so that the coiled tubing 1 can be connected to the downhole tool assembly.
[0096] Furthermore, during the installation of the connector 4, the lower end of the coiled tube 1 is chamfered by 45°; the connector 4 is subjected to a 15t tensile test, wherein the displacement is less than 3-5mm and is considered qualified. The coiled tube 1 is chamfered to facilitate connection with the connector 4; the connector 4 is subjected to a tensile test to confirm its connection strength.
[0097] Among them, in S4, the operation window 13 is opened, and the hanging slip 2 is installed on the outer wall of the coiled tubing 1 and close to the upper part of the tubing hanger 3; the coiled tubing 1 is continued to be lowered, and the hanging slip 2 falls into the tubing hanger 3, and the coiled tubing 1 is continued to be lowered until the hanging weight of the injection head 8 is zero and the coiled tubing 1 has no slippage and no abnormal load, and the shear ram of the four-ram blowout preventer 10 is used to cut the coiled tubing 1, and the coiled tubing 1 is lifted and the load and pressure changes of the injection head 8 are observed to verify whether the pipe cutting is successful. After the hanging slip 2 is installed on the coiled tubing 1, the coiled tubing 1 is lowered, so that the hanging slip 2 is suspended on the tubing hanger 3, and the coiled tubing 1 is continued to be lowered, so that the downward pulling force of the coiled tubing 1 on the injection head 8 is zero, and the coiled tubing 1 is cut; the coiled tubing 1 above the shearing position is lifted to determine whether the coiled tubing 1 is cut.
[0098] In S5, all equipment above the wellhead spool 15 is removed, the coiled tubing 1 above the hanging slips 2 is cut off with a manual cutter, the upper end of the coiled tubing 1 is chamfered, and the neck and burrs of the cut pipe are removed.
[0099] Wherein, No. 1 liner and No. 2 liner are installed in the gas tree 18, the gas tree 18 is assembled, and the main valve of the gas tree 18 is closed; the plug 7-2 of the plug 7 is knocked out by the pipeline of the ground high-pressure pump group, and the well is shut in. Fig.14As shown, the gas production tree 18 includes a multi-section structure. Before connecting the multi-section structure, No. 1 liner 18-1 and No. 2 liner 18-2 are installed therein so that No. 1 liner 18-1 and No. 2 liner 18-2 are docked with the continuous pipe 1. Then the multi-section structure is connected, and the main valve of the gas production tree 18 is closed; the pipeline of the ground high-pressure pump group is pressurized to knock out the plug 7-2 of the plug 7, connect the reservoir and the continuous pipe 1, and shut in the well.
[0100] The following describes a preferred embodiment of the present invention, wherein the method for constructing a coiled tubing wellhead suspension and well bottom plugging completion string includes the following steps:
[0101] Step 1: Arrange the coiled tubing equipment according to the recommended practice for coiled tubing operation in oil and gas wells, dismantle the original wellhead device, and only keep the flat valve 14. Test the switch function of each gate of the four-gate blowout preventer 10 to make it in the fully open position. Figure 2 As shown, the injection head 8, the blowout prevention box 9, the four-gate blowout preventer 10, the pressure relief tee 12, the blowout prevention pipe 11, and the operation window 13 are installed on the flat valve 14. Figure 3 As shown, the ground pipeline is connected, and the ground high-pressure pump group pipeline and the wellhead are pressure tested respectively. The pressure test requires increasing the pump pressure step by step by 10%, 50%, and 100% to 35MPa, and stabilizing the pressure for 10 minutes. The pressure drop is less than 0.7MPa to pass. If leakage is found, stop the pump immediately to relieve the pressure and make corrections.
[0102] Step 2: Pass the coiled tubing 1 through the injection head 8 and down to the operation window 13. Open the operation window 13, chamfer the lower end of the coiled tubing 1, and install the connector 4. During the installation of the connector 4, the lower end of the coiled tubing 1 is chamfered at 45° to ensure that the coiled tubing 1 is vertical as much as possible to avoid damaging the sealing ring during installation. After installation, a tensile test is performed. The tensile test is 15t, and the displacement is less than 3-5mm to pass. Figure 4 As shown, the motor head 16 and the well cleaning tool 17 are installed at the lower end of the connector 4, the operation window 13 is closed, and the wellhead equipment is pressure tested through the surface high-pressure pump group pipeline. The flat valve 14 is opened, the pipe is lowered to the designed depth, and the surface pump group is turned on to complete the well cleaning operation in the designed area to ensure the cleanliness of the inner wall of the wellbore.
[0103] Step 3: Lift the coiled tubing 1 to the position of the operating window 13 and close the flat valve 14. Open the operating window 13, remove the motor head 16 and the well cleaning tool 17, install the release hand 5, the packer 6 and the plug 7 at the lower end of the connector 4, and hang the tubing hanger 3 on the packer 6. Figure 5As shown, the downhole tool string is put into the blowout preventer 11. Close the operating window 13, and test the downhole tool string through the surface high-pressure pump group pipeline. Open the flat valve 14, slowly lower the pipe, and the tubing hanger 3 falls into the wellhead spool 15, and the top screw is fixed and sealed. The coiled tubing 1 passes through the tubing hanger 3 and continues to slowly lower the pipe. The lowering speed does not exceed 5m / min. When the lowering depth is 50m, observe the operation of the equipment. After the equipment operates normally, control the constant lowering speed to lower the pipe normally, and the speed is controlled at 25m / min. During the lowering process, a lifting and hanging weight test is performed every 500m. During the lowering process, pay attention to the changes in the pressure of the coiled tubing 1. When it is lowered to 300m from the design depth, reduce the speed to 10m / min, and when it is lowered to 100m from the design depth, reduce the speed to 5m / min. After the design depth is 15m, it is lifted to the design depth. The packer 6 is set at the designed position by pressurizing the pipe. The coiled pipe 1 is lowered continuously to release 1 / 3 of the maximum hanging weight of the injection head 8, confirming that the packer 6 is in normal working condition and realizing the sealing and isolation of the annulus position. The pressure relief tee 12 is opened to control the blowout through the ground throttle manifold to release the pressure on the upper part of the packer 6. After the pressure is released, the packer fluid is injected until the annulus area is completely filled and there is no pressure at the wellhead.
[0104] Step 4: If Figure 6 As shown, open the operating window 13 and install the hanging slip 2 to the outer wall of the coiled tubing 1 near the upper part of the tubing hanger 3. Figure 7 As shown, the coiled tubing 1 is lowered, and the hanging slips 2 fall into the inner groove of the tubing hanger 3. The coiled tubing 1 is lowered further until the hanging weight of the injection head 8 is zero and the coiled tubing 1 does not slip and the load is normal. Then, the four-gate blowout preventer 10 is used to shear the rams to shear the tubing. The tubing is lifted to observe the changes in the load and pressure of the injection head 8 to verify whether the tubing shearing is successful.
[0105] Step 5: Remove all equipment above the wellhead spool 15, cut off the coiled tubing 1 above the hanging slips 2 with a manual cutter, chamfer the upper end of the coiled tubing 1, and remove the cut neck and burrs. Install the No. 1 liner 18-1 and No. 2 liner 18-2 in the gas tree 18. Fig.14 As shown, the gas production wellhead is restored and the main valve of the gas production tree 18 is closed. The pipeline of the ground high-pressure pump group is pressurized until the wellhead pressure shows a sudden drop, and the plug 7-2 of the plugging device 7 is confirmed to be removed and the well is closed.
[0106] The preferred embodiments of the present invention are described in detail above in conjunction with the accompanying drawings, but the present invention is not limited thereto. Within the technical concept of the present invention, the technical solution of the present invention can be subjected to a variety of simple modifications, including the combination of various specific technical features in any suitable manner. In order to avoid unnecessary repetition, the present invention will not further describe various possible combinations. However, these simple modifications and combinations should also be regarded as the contents disclosed by the present invention and belong to the protection scope of the present invention.
Claims
1. A method for the construction of a coiled tubing wellhead suspension and well bottom plugging completion string, characterized in that: The construction method comprises: S1, placing the coiled tubing (1) operation equipment, installing the wellhead equipment and conducting a pressure test, wherein the wellhead equipment from top to bottom includes an injection head (8), a blowout preventer box (9), a four-gate blowout preventer (10), a blowout preventer (11), a pressure relief tee (12), and an operating window (13); S2, passing the coiled tubing (1) through the injection head (8), installing a well-entry tool string for well cleaning, lowering the tubing to the designed position, and performing well cleaning operations; S3, lifting the coiled tubing (1) to the operating window (13), replacing the well-entry tool string for the completion string, setting a tubing hanger (3) on the coiled tubing (1), lowering the coiled tubing (1), allowing the tubing hanger (3) to fall into the wellhead spool (15) and seal it, and continuing to lower the coiled tubing (1) to the designed depth; S4, opening the operating window (13), installing the hanging slip (2) on the coiled tubing (1), lowering the coiled tubing (1) so that the hanging slip (2) falls into the tubing hanger (3), and continuing to lower the hanging slip (2) until the hanging weight reaches zero, and then cutting the coiled tubing (1); S5, remove the wellhead equipment, restore the gas tree (18), open the plug (7) and start production.
2. The method for constructing a coiled tubing wellhead suspension and well bottom plugging completion string according to claim 1, characterized in that: The inner circumferential surface of the suspension slip (2) is provided with slip teeth (2-1), the outer circumferential surface of the suspension slip (2) is formed as a tapered surface from top to bottom, and the inner circumferential surface of the upper end of the oil pipe hanger (3) is formed as a tapered surface from top to bottom to accommodate and suspend the suspension slip (2).
3. The method for constructing a coiled tubing wellhead suspension and well bottom plugging completion string according to claim 2, characterized in that: The suspension slip (2) comprises two semi-tubular parts and a connecting piece for detachably connecting the two semi-tubular parts.
4. The method for constructing a coiled tubing wellhead suspension and well bottom plugging completion string according to claim 2, characterized in that: The tubing hanger (3) is sealingly engaged with the wellhead spool (15), and the tubing hanger (3) is fixed by means of a top screw of the wellhead spool (15).
5. The method for constructing a coiled tubing wellhead suspension and well bottom plugging completion string according to claim 2, characterized in that: In S3, the replacement of the downhole tool string for the completion tubing string includes: opening the operation window (13), disassembling the downhole tool string for well cleaning, installing a release hand (5), a packer (6), and a plug (7) at the lower end of the coiled tubing (1), and hanging the tubing hanger (3) on the packer (6).
6. The method for constructing a coiled tubing wellhead suspension and well bottom plugging completion string according to claim 5, characterized in that: In S3, after the coiled tubing (1) is further lowered to the designed depth, the inside of the tubing is pressurized so that the packer (6) is set at the designed position, and the coiled tubing (1) is further lowered to release a portion of the suspended weight of the injection head (8).
7. The method for constructing a coiled tubing wellhead suspension and well bottom plugging completion string according to claim 6, characterized in that: The step S3 also includes: opening the pressure relief tee (12) and controlling the blowout through the ground throttle manifold to release the pressure on the upper part of the packer (6), filling the annular area with packer fluid, and making the wellhead pressure-free.
8. The method for constructing a coiled tubing wellhead suspension and well bottom plugging completion string according to claim 2, characterized in that: In S3, the step of continuing to lower the coiled tubing (1) to the designed depth comprises: lowering the coiled tubing (1) at a speed not exceeding 5 m / min, and observing the operation of the equipment when the lowering depth reaches 50 m; continuing to lower the coiled tubing (1) at a speed of 25-30 m / min, and performing a lifting and hanging weight test every 500 m during the lowering process; when the coiled tubing is lowered to 300 m from the designed depth, reducing the speed to 10-15 m / min, and when the coiled tubing is lowered to 100 m from the designed depth, reducing the speed to 5 m / min, and lifting the coiled tubing to the designed depth after the coiled tubing has been lowered to 15 m.
9. The method for constructing a coiled tubing wellhead suspension and well bottom plugging completion string according to claim 2, characterized in that: In S1, the switch functions of each gate of the four-gate blowout preventer (10) are tested to make it fully open, and then the injection head (8), the blowout preventer box (9), the four-gate blowout preventer (10), the pressure relief tee (12), the blowout preventer (11), and the operating window (13) are installed and connected to the surface high-pressure pump group pipeline to perform pressure testing on the surface pipeline and wellhead equipment.
10. The method for constructing a coiled tubing wellhead suspension and well bottom plugging completion string according to claim 9, characterized in that: The pressure test requires increasing the pump pressure step by step by 10%, 50%, and 100% to 35MPa. The test is qualified if the pressure is stabilized for 10 minutes and the pressure drop is less than 0.7MPa. If leakage is found, the pump is stopped immediately to release the pressure and make corrections.
11. The method for constructing a coiled tubing wellhead suspension and well bottom plugging completion string according to claim 1, characterized in that: In S2, the coiled tubing (1) is passed through the injection head (8) and lowered to the position of the operation window (13); the operation window (13) is opened, the lower end of the coiled tubing (1) is chamfered, the connector (4) is installed, and a tension test is performed; a motor head (16) and a well cleaning tool (17) are installed at the lower end of the connector (4), the operation window (13) is closed, and the wellhead equipment is pressure tested through a surface high-pressure pump group pipeline; the flat valve (14) is opened, the coiled tubing (1) is lowered to the designed depth, and the surface high-pressure pump group pipeline is started to complete the well cleaning operation in the designed area.
12. The method for constructing a coiled tubing wellhead suspension and well bottom plugging completion string according to claim 11, characterized in that: During the installation of the connector (4), the lower end of the coiled tube (1) is chamfered at 45°; the connector (4) is subjected to a 15-ton tensile test, and a displacement of less than 3-5 mm is considered qualified.
13. The method for constructing a coiled tubing wellhead suspension and well bottom plugging completion string according to claim 1, characterized in that: In S4, the operation window (13) is opened, and the hanging slip (2) is installed on the outer wall of the coiled tubing (1) and close to the upper part of the tubing hanger (3); the coiled tubing (1) is continuously lowered, and the hanging slip (2) falls into the tubing hanger (3); the coiled tubing (1) is continuously lowered until the hanging weight of the injection head (8) is zero and the coiled tubing (1) has no slippage and no abnormal load; the shear ram of the four-ram blowout preventer (10) is used to shear the coiled tubing (1), and the coiled tubing (1) is lifted and the load and pressure changes of the injection head (8) are observed to verify whether the shearing is successful.
14. The method for constructing a coiled tubing wellhead suspension and well bottom plugging completion string according to claim 1, characterized in that: In S5, all equipment above the wellhead spool (15) is removed, the coiled tubing (1) above the hanging slips (2) is cut off with a manual cutter, the upper end of the coiled tubing (1) is chamfered, and the necking and burrs of the cut tubing are removed.
15. The method for constructing a coiled tubing wellhead suspension and well bottom plugging completion string according to claim 14, characterized in that: Install No. 1 liner (18-1) and No. 2 liner (18-2) in the gas tree (18), assemble the gas tree (18), close the main valve of the gas tree (18); and shut down the well after the plug (7-2) of the plug (7) is removed by pumping pressure through the pipeline of the ground high-pressure pump group.