Grit chamber and operation method

By designing a sand sedimentation tank suitable for low flow and low liquid level states, combining the filler filter area and filter tank, efficient sand sedimentation and hydrolysis and acidification are achieved, solving the problems of sediment deposition and operation and maintenance in township sewage plants, and improving the Sewage treatment effect and equipment reliability.

CN119075493APending Publication Date: 2024-12-06CHONGQING THREE GORGES ECO-ENVIRONMENTAL TECH INNOVATION CENT CO LTD +1
View PDF 5 Cites 0 Cited by

Patent Information

Application Number
CN202411176754.2
Authority / Receiving Office
CN · China
Patent Type
Applications(China)
Current Assignee / Owner
Filing Date
2024-08-26
Publication Date
2024-12-06

AI Technical Summary

Technical Problem

Due to the small water inlet, large water fluctuation, and high sediment concentration in township sewage plant stations, the sediment deposits in the regulation pool, causing pipeline blockage and equipment damage, and the professional quality of operation and maintenance personnel is difficult to manage sand-water separation, which affects sewage treatment. run.

Method used

Design a sand sedimentation tank, including the pool body, partition plate, perforated aeration pipe, sand lifting pump and filler area, and realize sediment deposition and sand discharge through a one-way movable cover plate and agitator, combining the filler filter area and filtration The tank is secondary intercepted and hydrolyzed and acidified, suitable for low flow and low liquid level states.

Benefits of technology

It realizes efficient sand deposition under restricted site conditions, has oil isolation and hydrolysis and acidification functions, reduces the risk of pump and pipeline blockage, is simple to operate, is suitable for township factories and stations with low operation and maintenance capabilities, and improves the sewage treatment effect.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN119075493A_ABST
    Figure CN119075493A_ABST
Patent Text Reader

Abstract

The invention provides a grit chamber and an operation method, the grit chamber comprises a chamber body, the lower part of the chamber body is provided with a mud bucket, a partition plate is arranged in the chamber body close to a water inlet, and the transverse distance between the partition plate and the water inlet is 1-1.5 m; a group of perforated aeration pipes are respectively arranged on the inner wall of the middle part and the bottom of the tank body, a one-way movable cover plate is hinged on one side of the mud bucket at the water inlet, the one-way movable cover plate can only turn over towards the inside of the tank body, a filter tank is further arranged at the top of the tank body, a sand lifting pump is arranged at the bottom of the tank body, and stirrers are further arranged on two sides of the sand lifting pump. An outlet of the sand lifting pump is communicated with the filter tank through a pipeline. According to the grit chamber and the operation method provided by the invention, the volume of the regulating tank can be fully utilized under the conditions of limited field and normal operation, and the installation of grit process equipment with water can be realized. According to the present invention, the efficient sand setting can be achieved, the oil separation and hydrolytic acidification functions can be provided, the obvious gain effect on the subsequent biochemical section is provided, and the method is especially suitable for the village and town plant station with low operation and maintenance ability.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The invention belongs to the technical field of sewage treatment, and in particular relates to a sand settling tank and an operation method thereof. Background Art

[0002] In township sewage treatment plants, due to the small water inflow and large fluctuations in water volume, many sewage treatment plants only consider regulating tanks during construction, without considering sand removal process structures. The situation of rainwater and sewage confluence in township pipe networks is serious, especially in mountainous and hilly areas. During the rainy season, the concentration of water and sand in the water in the plant is high, which is prone to large amounts of sediment in the regulating tank or biochemical pool, and even worse, pipeline blockage and equipment damage, seriously affecting the operation of sewage treatment plants.

[0003] In addition, the land of township sewage treatment plants is generally compact, making it difficult to add a complete sand removal system, and the professional quality of plant and station operation and maintenance personnel is generally low, making it difficult to manage the fine sand and water separation in the plant and station. The above situations are all problems that some old township sewage treatment plants are currently facing and need to be solved urgently. Summary of the invention

[0004] The purpose of the present invention is to provide a sand settling tank and an operation method to address the defects of the prior art. The device and method can be used to obtain accurate flow data under low flow and low liquid level conditions in a drainage network.

[0005] According to a first aspect of the present invention, a sand settling tank is provided, comprising a tank body, wherein one side of the upper part of the tank body is provided with a water inlet, and the other side is provided with a water outlet, the lower part of the tank body is provided with a mud hopper, and the outer wall of the tank body is provided with a plurality of supporting legs; a partition plate is provided in the tank body near the water inlet, and the lateral distance between the partition plate and the water inlet is 1 to 1.5 m; a group of perforated aeration pipes are respectively provided on the middle inner wall and the bottom of the tank body, the mud hopper is hingedly connected to a one-way movable cover plate at one side of the water inlet, and the one-way movable cover plate can only be flipped toward the inside of the tank body, a filter tank is also provided on the top of the tank body, a sand lifting pump is provided at the bottom of the tank body, agitators are also provided on both sides of the sand lifting pump, and the outlet of the sand lifting pump is connected to the filter tank through a pipeline.

[0006] Preferably, the perforated aeration pipe has a diameter of 50-80 mm, an opening of 5-8 mm, and an opening rate of 30%.

[0007] Preferably, a packing area is provided at the water outlet, the top of the packing area is level with the water outlet, and the packing in the packing area is braided, with a porosity greater than 90% and a specific surface area greater than 1000m 2 / m 3 .

[0008] Preferably, the mud hopper is also hinged with a one-way movable cover plate at the lower part of the water outlet, and the one-way movable cover plate can only be flipped toward the inside of the pool body.

[0009] Preferably, the filter tank is made of stainless steel, and a filter layer is provided in the filter tank, the filter layer is composed of a gravel layer with a thickness of 20 cm and a coir mattress with a thickness of 10 cm, wherein the diameter of the gravel is 5-20 mm.

[0010] A second aspect of the present invention provides a method for operating a grit chamber as described in any one of the above, comprising: According to the size of the existing regulating pond, determine the length, height, inlet and outlet size and position of the grit chamber, so that the water surface in the regulating pond exceeds the inlet by no less than 0.5m, and the effective grit chamber time is no less than 10 minutes; The grit chamber is hoisted into the regulating tank, and the water in the regulating tank enters the grit chamber through the one-way movable cover plate to balance the water pressure inside and outside the grit chamber, thereby realizing the installation with water operation; After the grit chamber is hoisted into place, water is introduced and operated according to the following process: Sewage enters the grit chamber through the water inlet. Under the guidance of the partition plate, the silt begins to settle at the bottom, and the remaining lighter suspended matter is intercepted for the second time in the filler filtration area. The partition plate isolates part of the grease at the front end, which is manually cleared regularly. At the beginning of operation, a certain amount of activated sludge is added to the grit chamber. After an anaerobic biofilm is formed on the filler in the filter area, the macromolecular organic matter on the intercepted suspended particles is hydrolyzed and acidified into small molecules. After the silt is deposited in the silt bucket, it is discharged regularly through the sand pump, and the deposited silt is stirred and lifted up by the agitator. The sand lifting flow rate each time shall not exceed 1 / 3 of the sedimentation volume of the sand settling tank.

[0011] Preferably, the perforated aeration pipe is opened once a week for aeration, the aeration time is 2 minutes, and the water intake is stopped for 30 minutes during aeration. The perforated aeration pipe is used to disturb the accumulated silt and filler filter area on both sides of the mud bucket, allowing the silt to settle to the bottom and then be discharged through the sand lifting pump.

[0012] Preferably, when flushing or replacing the filler, the upper one-way movable cover is opened, and the water level of the grit chamber is lowered before flushing or replacing.

[0013] Compared with the prior art, the present invention has the following beneficial effects: The present invention provides a grit chamber and an operating method. The grit chamber can fully utilize the volume of a regulating tank under conditions of limited site and normal operation, and can realize water-carrying installation of grit process equipment.

[0014] In addition to achieving efficient sand settling, the present invention also has the functions of oil separation and hydrolysis acidification, which has an obvious benefit effect on the subsequent biochemical stage and is particularly suitable for township plants and stations with low operation and maintenance capabilities.

[0015] The sand lifting pump selected by the present invention can effectively avoid blockage of the pump and the pipeline, and at the same time is simple to operate, has low requirements on personnel ability, and has a low operation and maintenance failure rate.

[0016] The present invention arranges guide plates and filler filtering areas to intercept and remove silt and suspended matter, and has better effects than traditional grit chambers. BRIEF DESCRIPTION OF THE DRAWINGS

[0017] Figure 1 It is a schematic diagram of the structure of the invention.

[0018] Figure 2 The present invention is a schematic structural diagram of a one-way movable cover plate in an embodiment of the present invention.

[0019] In the figure: 1. tank body; 2. supporting legs; 3. water inlet; 4. partition plate; 5. perforated aeration pipe; 6. sand pump; 7. mud bucket; 8. filling area; 9. one-way movable cover; 10. water outlet; 11. filter tank; 11-1. gravel layer; 11-2. palm mattress; 12. pipeline. DETAILED DESCRIPTION

[0020] In order to enable those skilled in the art to better understand the technical solution of the present invention, the preferred implementation scheme of the present invention is described below in conjunction with specific embodiments. However, it should be understood that the drawings are only used for exemplary descriptions and cannot be understood as limitations on this patent; in order to better illustrate this embodiment, some parts of the drawings may be omitted, enlarged or reduced, and do not represent the size of the actual product; for those skilled in the art, it is understandable that some well-known structures and their descriptions in the drawings may be omitted; the positional relationship described in the drawings is only used for exemplary descriptions and cannot be understood as limitations on this patent.

[0021] As an embodiment of the present invention, see the attached Figure 1-Figure 2 The present embodiment provides a grit chamber, comprising a chamber body 1, wherein a water inlet 3 is arranged on one side of the upper part of the chamber body 1, and a water outlet 10 is arranged on the other side; a mud hopper 7 is arranged on the lower part of the chamber body 1, and a plurality of supporting legs 2 are arranged on the outer wall of the chamber body 1; a partition plate 4 is arranged near the water inlet 3 in the chamber body 1, and a lateral distance between the partition plate 4 and the water inlet 3 is 1-1.5 m; a group of perforated aeration pipes 5 are arranged on the middle inner wall and the bottom of the chamber body 1, the mud hopper 7 is hingedly connected with a one-way movable cover plate 9 at one side of the water inlet 2, and the one-way movable cover plate 9 can be turned toward the inside of the chamber body 1; a filter tank 11 is also arranged on the top of the chamber body 1, a sand lifting pump 6 is arranged on the bottom of the chamber body 1, and a stirrer 12 is also arranged on both sides of the sand lifting pump 6, and the outlet of the sand lifting pump 6 is connected with the filter tank 11 through a pipe 12.

[0022] Among them, Figure 1 indivual Figure 2As shown, a pull rope can be connected to the one-way movable cover plate 9, and the pull rope extends outside the pool body, so as to actively control the opening and closing of the one-way movable cover plate 9 according to the use needs.

[0023] Specifically, in the above embodiment, the perforated aeration tube 5 has a diameter of 50-80 mm, an opening of 5-8 mm, and an opening rate of 30%.

[0024] In some preferred embodiments, a packing area 8 is provided at the water outlet 10, the top of the packing area 8 is flush with the water outlet 10, and the packing in the packing area 8 is braided, with a porosity greater than 90% and a specific surface area greater than 1000m 2 / m 3 .

[0025] In some embodiments, Figure 1 and Figure 2 As shown, the mud bucket 7 is located at the lower part of the water outlet 10 and is also hinged with a one-way movable cover plate 9, and the one-way movable cover plate 9 can be turned toward the inside of the pool body 1.

[0026] In some embodiments, the filter tank 11 is made of stainless steel, and a filter layer is provided in the filter tank 11. The filter layer is composed of a gravel layer 11-1 with a thickness of 20 cm and a palm mattress 11-2 with a thickness of 10 cm, wherein the diameter of the gravel is 5-20 mm, and the outlet of the filter tank 11 flows into the regulating tank. After the filter tank 11 is set, the sand and water are separated in the filter tank 11, and the filtered water flows back to the regulating tank through the bottom drain pipe. When the height of the sand settling in the filter tank 11 exceeds 10 cm, the silt needs to be cleaned. Taking a township sewage treatment plant with a capacity of 800 m3 / d as an example, the volume of the sand settling tank is not less than 1m 3 .

[0027] The use process of the above preferred embodiment, that is, a method for operating a grit chamber, includes: According to the size of the existing regulating pond, determine the length, height, inlet and outlet size and position of the grit chamber, so that the water surface in the regulating pond exceeds the inlet by no less than 0.5m, and the effective grit settling time is no less than 10min. 3 / d as an example, the existing regulating pond size is 4.0m*6.0m*5.0m, the water inlet height is 3.5m, the determined sand settling tank size is 2.0m*4.0m*4.0m, the water inlet elevation is 3.5m, the water outlet elevation is 3.4m, and the effective sand settling time is 11min; The grit chamber is hoisted into the regulating tank, and the water in the regulating tank enters the grit chamber through the one-way movable cover plate 9 to balance the water pressure inside and outside the grit chamber, thus realizing the installation with water operation; After the grit chamber is hoisted into place, water is introduced and operated according to the following process: Sewage enters the grit chamber through the water inlet 3. Under the guidance of the partition plate 4, the silt begins to settle at the bottom, and the remaining lighter suspended matter is intercepted for the second time in the filler filtration area 8. The partition plate 4 isolates part of the grease at the front end, which is manually scooped out regularly. At the initial stage of operation, a certain amount of activated sludge is added to the grit chamber, and after an anaerobic biofilm is formed on the filler in the filter zone 8, the macromolecular organic matter on the intercepted suspended particles is hydrolyzed and acidified into small molecules; After the sediment is deposited in the mud bucket, the sand is discharged regularly through the sand pump 6, and the deposited sediment is stirred by the stirrer 12. The sand lifting flow rate each time does not exceed 1 / 3 of the sedimentation volume of the sand settling tank.

[0028] Taking a township sewage treatment plant as an example, after placing a grit chamber, 0.1m 3 The concentration of activated sludge was 8000 mg / L. After continuous addition for one week, the average SS value passing through the grit chamber decreased from 260 mg / L to 120 mg / L, and the average BOD5 / COD value of the effluent increased from 0.43 to 0.58. The effluent TN was significantly improved in winter, and the removal rate increased by 10%~20%, which could be stabilized below 15 mg / L.

[0029] In some preferred embodiments, the perforated aeration pipe 5 is opened once a week for aeration, and the aeration time is 1-3 minutes. After aeration, water intake is stopped for 30 minutes. The perforated aeration pipe 5 is used to disturb the accumulated silt and filler filter area on both sides of the hopper, allowing the silt to settle to the bottom and then discharged through the sand pump 6.

[0030] In other preferred embodiments, when flushing or replacing the filler, the upper one-way movable cover plate 9 is opened to lower the water level of the grit chamber before flushing or replacing.

[0031] Finally, it should be noted that the above embodiments are only used to illustrate the technical solution of the present invention rather than to limit it. Although the present invention has been described in detail with reference to the preferred embodiments, those skilled in the art should understand that the technical solution of the present invention can be modified or replaced by equivalents without departing from the purpose and scope of the technical solution of the present invention, which should be included in the scope of the claims of the present invention.

Claims

1. A grit chamber, characterized in that: The invention comprises a pool body (1), wherein one side of the upper part of the pool body (1) is provided with a water inlet (3), and the other side is provided with a water outlet (10), the lower part of the pool body (1) is provided with a mud bucket (7), and the outer wall of the pool body (1) is provided with a plurality of supporting legs (2); a partition plate (4) is provided in the pool body (1) near the water inlet (3), and the lateral distance between the partition plate (4) and the water inlet (3) is 1 to 1.5 m; a middle inner wall and a bottom of the pool body (1) are each provided with a A perforated aeration pipe (5) is provided, the mud bucket (7) is hingedly connected to a one-way movable cover plate (9) on one side of the water inlet (2), and the one-way movable cover plate (9) can be turned toward the inside of the pool body (1). A filter tank (11) is also provided on the top of the pool body (1), and a sand lifting pump (6) is provided at the bottom of the pool body (1). Agitators (12) are also provided on both sides of the sand lifting pump (6), and the outlet of the sand lifting pump (6) is connected to the filter tank (11) through a pipe (12).

2. A grit chamber according to claim 1, characterized in that: The perforated aeration pipe (5) has a diameter of 50-80 mm, an opening of 5-8 mm, and an opening rate of 30%.

3. A grit chamber according to claim 1, characterized in that: A packing area (8) is provided at the water outlet (10), the top of the packing area (8) is flush with the water outlet (10), and the packing in the packing area (8) is braided, has a porosity greater than 90%, and a specific surface area greater than 1000m 2 / m 3 .

4. A grit chamber according to claim 1, characterized in that: The mud bucket (7) is also hingedly connected to a one-way movable cover plate (9) at the lower part of the water outlet (10), and the one-way movable cover plate (9) can be turned toward the inside of the pool body (1).

5. A grit chamber according to claim 1, characterized in that: The filter tank (11) is made of stainless steel, and a filter layer is provided in the filter tank (11), wherein the filter layer is composed of a gravel layer (11-1) with a thickness of 20 cm and a palm mattress (11-2) with a thickness of 10 cm, wherein the diameter of the gravel is 5-20 mm.

6. A method for operating a grit chamber according to any one of claims 1 to 5, characterized in that: include: According to the size of the existing regulating pond, determine the length, height, inlet and outlet size and position of the grit chamber, so that the water surface in the regulating pond exceeds the inlet by no less than 0.5m, and the effective grit chamber time is no less than 10 minutes; The grit chamber is hoisted into the regulating tank, and the water in the regulating tank enters the grit chamber through the one-way movable cover plate (9), balancing the water pressure inside and outside the grit chamber, thereby achieving installation with water operation; After the grit chamber is hoisted into place, water is introduced and operated according to the following process: Sewage enters the grit chamber through the water inlet (3). Under the guidance of the partition plate (4), the silt begins to settle at the bottom, and the remaining lighter suspended matter is intercepted for a second time in the filler filtration area (8). The partition plate (4) isolates part of the grease at the front end, which is manually scooped out regularly. At the initial stage of operation, a certain amount of activated sludge is added to the grit chamber. After an anaerobic biofilm is formed on the filler in the filtration zone (8), the macromolecular organic matter on the intercepted suspended particles is hydrolyzed and acidified into small molecules. After the sediment is deposited in the mud bucket, the sediment is discharged regularly by the sand pump (6), and the deposited sediment is stirred by the stirrer (12). The sand discharge rate each time does not exceed 1 / 3 of the sedimentation volume of the sedimentation tank.

7. A grit chamber according to claim 6, characterized in that: The perforated aeration pipe (5) is opened once a week for aeration for 1-3 minutes. After aeration, water is stopped for 30 minutes. The perforated aeration pipe (5) is used to disturb the sediment accumulated on both sides of the hopper and the filler filter area, allowing the sediment to settle to the bottom and then be discharged through the sand lifting pump (6).

8. A grit chamber according to claim 6, characterized in that: When flushing or replacing the filler, open the upper one-way movable cover (9) and lower the water level of the grit chamber before flushing or replacing.

Citation Information

Patent Citations

  • Internal and external water pressure automatic balance steel protecting cylinder

    CN106836215A

  • Aeration grit chamber used for sewage treatment and use method thereof

    CN107715513A

  • Integrated rainwater purification inspection well

    CN213834749U

  • Three-stage sedimentation tank convenient to hoist

    CN214105933U

  • Purification regulation and storage tank system

    CN220283798U