Method for installing vertical bucket elevator in closed plant by normal installation method
By using the formal installation method of vertical bucket lifting machine in the closed factory in the chemical industry, and using tools such as winches and pulley sets to efficiently install vertical bucket lifting machines in the closed factory, the difficulty of installation of equipment in the closed factory is solved and safety is achieved , efficient installation and construction quality assurance.
Patent Information
- Application Number
- CN202411366145.3
- Authority / Receiving Office
- CN · China
- Patent Type
- Applications(China)
- Current Assignee / Owner
- Filing Date
- 2024-09-29
- Publication Date
- 2024-12-06
- Estimated Expiration
- 2044-09-29
AI Technical Summary
In the chemical industry, large equipment in closed factories cannot be installed with the help of large lifting machinery, which makes it difficult to install equipment in a limited space, and an efficient installation method is needed to realize the installation of vertical bucket elevators.
A method of installation of vertical bucket lifting machine in closed factory buildings is adopted. By reasonably arranging the construction process, the lower section, upper section and transmission device are installed using the hoist and pulley set, the casing is installed and corrected, and the surrounding factory structure is made Drive the platform and metal fixing frame to gradually complete the installation of the equipment.
It realizes safe and efficient installation on different floors of the closed factory building, ensures the quality of the project construction and installation efficiency, and ensures that the equipment passes acceptance in one go.
Smart Images

Figure CN119077311A_ABST
Abstract
Description
Technical Field
[0001] The invention relates to an installation method for large-scale chemical equipment, in particular to a method for installing a vertical bucket elevator in a closed factory building by a straight-mounting method. Background Art
[0002] In the chemical industry, material elevators are increasingly used due to their large conveying capacity, high lifting height, stable operation and long service life.
[0003] Most traditional material elevators are installed before the equipment plant is capped, mainly to facilitate the use of large-scale lifting machinery to assist installation, thereby improving efficiency. However, due to various practical situations, the chemical industry now often completes the capping of the equipment plant before the equipment is installed, resulting in some large equipment inside the plant being unable to be installed with the help of large-scale lifting machinery. Installing equipment in such a limited space places higher requirements on the equipment installation method. Summary of the invention
[0004] The object of the present invention is to provide a method for installing a vertical bucket elevator in a closed factory building by a normal installation method, so as to achieve the purpose of installing the vertical bucket elevator in different floors of the closed factory building by reasonably arranging the construction procedures.
[0005] To achieve the above object, the technical solution adopted by the present invention is: A method for installing a vertical bucket elevator in a closed factory building by a straight-mount method comprises the following steps: Step 1: Re-measure the foundation; before installing the equipment, mark the vertical and horizontal center lines of the lower section of the elevator; Step 2: Install the lower section. Use the front winch to slide and transport the equipment to the lifting position, and then use another winch to lift the lower section to the top of the equipment foundation through the high pulley block. Adjust the relative position of the lower section and the foundation bolts, slowly lower the lower section, and accurately install it on the equipment foundation. Step 3: Casing installation: According to the number of casings required for each floor of the plant, use a winch to hoist them from the reserved holes for equipment installation to the floor of each floor, and install them in sequence; Step 4: Install the housing bracket. After the housing of each floor of the plant is installed, install a fixed bracket on the housing of that floor, and the fixed bracket is fixedly installed on the nearest floor structure. Step 5: Install the upper section. Use a winch to hoist the upper section to the top of the top casing through a high pulley block. Insert asbestos ropes between the connection flanges of the top casing to ensure the seal and the levelness of the flange surface. Adjust the relative position between the upper section and the flange surface on the casing. Lower the upper section and accurately install it above the top casing. Step 6: Install the drive platform and metal fixing frame. Use the surrounding plant structures to make the drive platform and metal fixing frame, and reinforce the hoist at the same time. Step 7: Install the transmission device. Use a winch and pulley block to hoist the transmission device to the drive platform and connect it to the head wheel shaft of the upper section. Before connecting, first confirm that the backstop direction of the backstop on the transmission device is in the opposite state to the rotation direction of the transmission drum, and then use a dial indicator to align the output shaft of the transmission device with the head wheel shaft. Step 8, installation of traction wire rope tape; press the hopper bolt into the wire rope tape, install the wire rope tape into the elevator cavity according to the site and lifting conditions, raise the lower adjusting screw to the highest position, clamp one end of the wire rope tape with the wire rope tape clamp, and use the lifting rope to lift the wire rope tape head to the top of the elevator from the middle casing on the feed inlet side. Use the same method on the other end of the wire rope tape, clamp the wire rope tape clamp and lift the wire rope tape head from the discharge outlet side to the top of the elevator, and finally seal the ends of the tape with glue; Step 9: Install the hopper. When installing, a rubber pad should be placed on the back of the hopper. Install the hoppers one by one from the lower part of the feed inlet side and tighten each hopper bolt completely. Step 10: Test drive.
[0006] Furthermore, in step one, after the foundation re-measurement is completed, flat shims are placed at the anchor bolt holes using the seat mortar method. The elevation error of each set of shims is no more than 1 mm, and the horizontality error is no more than 0.1 / 1000.
[0007] Furthermore, in step 2, after the lower section is in place, its reference surface needs to be leveled, the tolerance of parallelism between the reference surface and the horizontal plane is 1 / 1000mm, and the adjustment shim must be close to the anchor bolt.
[0008] Furthermore, in step three, when the casing is installed, asbestos rope is placed between the connecting flanges of the middle casing to ensure the seal and the horizontality of the flange surface; after the casing is assembled, the center line of the casing of each channel is on the same plumb plane, and the linear deviation shall not exceed 2 / 1000, and the cumulative deviation shall not exceed 8 mm.
[0009] Furthermore, in step 4, a fixed bracket is installed on each floor of the factory building, and the installation of the fixed bracket does not restrict the free retraction of the elevator in the vertical direction.
[0010] Furthermore, in step five, after the upper section is installed, the center lines of the upper and lower transmission shafts of the elevator are calibrated so that the two shafts are horizontal and in the same vertical plane, the parallelism tolerance between the center line of the upper shaft and the horizontal plane is 0.3 / 1000mm, the vertical plane error between the upper and lower shafts is less than 4mm, and the vertical plane error between the upper and lower roller end faces is less than 5mm.
[0011] Furthermore, in step seven, the transmission device is recalibrated before installation, and the motor, hydraulic coupling and reducer are aligned with a dial indicator and a feeler gauge during adjustment. The radial runout and axial runout of the hydraulic coupling and the motor output shaft and the reducer input shaft are ≤0.3mm.
[0012] Furthermore, in step eight, the horizontal edge of the wire rope tape joint is perpendicular to the center line of the conveyor belt, the verticality error shall not be greater than 0.2% of the belt width, and the misalignment of the two ends of the wire rope tape joint shall be less than 2 mm.
[0013] Furthermore, in step ten, after all parts of the elevator are installed as required, a no-load test run is first carried out. During the test run, the elevator is started. During the elevator test run, the inspection door is opened and the operation of each part of the equipment is carefully observed. The operation time shall not be less than 2 hours.
[0014] Furthermore, in step ten, after the no-load test is completed and the equipment is confirmed to be completely normal, a load test can be carried out. During the test, the elevator is started under the conditions of the designed conveying capacity and the intended conveying material. First, observe the working condition of the transmission device, the load condition of the motor, whether it is fully loaded or overloaded, whether the electrical control equipment is working normally, whether the noise of the reducer is excessive, whether the working conditions of the upper section and the lower section are normal, whether the wire rope tape slips on the drum, and whether the running speed meets the design requirements. Finally, observe whether the elevator reaches the designed conveying capacity when the elevator is fed evenly, whether the unloading is normal, whether there is obvious material return and blockage, and when the elevator stops running, whether there is obvious reverse operation, etc. After there are no defects in the above-mentioned load test, it can be handed over to production.
[0015] The present invention discloses a method for installing a vertical bucket elevator in a closed factory building by a positive installation method. A winch and a pulley block are used to install the lower section, the upper section and the transmission device. After the casing is installed and calibrated, the surrounding factory building structures are used to make a driving platform and a metal fixing frame. The present invention is suitable for installing vertical bucket elevators on different floors of a closed factory building. The vertical bucket elevator can be installed safely and efficiently on different floors of a closed factory building. By reasonably arranging the construction process, the quality of the project construction is guaranteed, the installation efficiency is accelerated, and the equipment installation acceptance is guaranteed once. BRIEF DESCRIPTION OF THE DRAWINGS
[0016] Figure 1 It is the construction procedure of the installation method of the present invention; Figure 2 It is a structural schematic diagram of the vertical bucket elevator described in the present invention. In the figure, 1-equipment foundation, 2-lower section, 3-casing, 4-fixed bracket, 5-upper section, 6-driving platform, 7-metal fixing frame, 8-transmission device, 9-wire rope tape, 10-hopper. DETAILED DESCRIPTION
[0017] When the equipment building has been topped off, the vertical bucket elevator cannot be installed with the aid of large lifting machinery, and the installation method of the equipment must be optimized and improved.
[0018] Based on this, the present embodiment provides a method for installing a vertical bucket elevator in a closed factory building, including the following steps 1 to 10.
[0019] 1. Basic retest Before installing the equipment, draw the vertical and horizontal center lines of the lower section of the elevator according to the position of the equipment on the drawing and refer to the distance to the connected equipment. The error shall not exceed ±10mm.
[0020] After the re-survey of equipment foundation 1 is completed, flat shims shall be placed at the anchor bolt holes using the seat mortar method. The elevation error of each set of shims shall not be greater than 1mm, and the horizontality error shall not be greater than 0.1 / 1000.
[0021] 2. Installation of the lower section Use the front winch to slide and transport the equipment to the lifting position, and then use another winch to slowly and safely lift the lower section 2 to 5mm above the equipment foundation 1 through the high pulley block. Adjust the relative position of the lower section 2 and the foundation bolts, slowly lower the lower section 2, and accurately install it on the equipment foundation 1.
[0022] After the lower section 2 is in place, its reference surface needs to be leveled. The tolerance for parallelism between the reference surface and the horizontal plane is 1 / 1000mm, and the adjustment shims must be close to the anchor bolts.
[0023] 3. Installation of the housing 3 According to the number of housings 3 required for each floor of the plant, they are hoisted from the reserved holes for equipment installation to the floor of each floor with a winch, and arranged in the order of installation waiting for installation.
[0024] When installing the casing 3, a 3mm thick asbestos rope is placed between the connecting flanges of the middle casing 3 to ensure the seal and the levelness of the flange surface. Some butter can be applied to the asbestos rope, and then it can be wrapped around the bolts between the casing flanges to facilitate the positioning of the asbestos rope and increase the sealing effect.
[0025] During installation, the flange surface of each section of the casing 3 must be flat, and there must be no obvious misalignment when connecting.
[0026] After the casing is assembled, the center lines of the casing 3 of each channel should be on the same plumb plane, and the straight line deviation should not exceed 2 / 1000, and the cumulative deviation should not exceed 8mm.
[0027] 4. Installation of the chassis bracket After the installation of each layer of the factory building is completed, a fixed bracket 4 needs to be installed on the layer of the shell, and the fixed bracket 4 is reliably fixed on the nearest floor structure. It is advisable to install one fixed bracket 4 per layer, and the installation of the fixed bracket 4 is not allowed to limit the free retraction of the hoist in the vertical direction.
[0028] 5. Installation of the upper section Use a winch to slowly and safely hoist the upper section 5 to 5mm above the top casing through a high pulley block. Insert a 3mm thick asbestos rope between the connection flanges of the top casing to ensure the seal and the levelness of the flange surface. Adjust the relative position of the upper section and the flange surface on the casing, slowly lower the upper section 5, and accurately install it above the top casing.
[0029] After the upper section 5 is installed, the center lines of the upper and lower transmission shafts of the hoist must be calibrated to make the two shafts level and in the same vertical plane. The parallelism tolerance between the center line of the upper shaft and the horizontal plane is 0.3 / 1000mm, the vertical plane error between the upper and lower shafts must be less than 4mm, and the vertical plane error between the upper and lower roller end faces must be less than 5mm.
[0030] 6. Installation of drive platform and metal fixing frame After the hoist casing is installed and calibrated, the drive platform 6 and the metal fixing frame 7 are made by utilizing the surrounding factory buildings according to local conditions. At the same time, the hoist is reinforced and the vibration is further reduced to make the operation more stable.
[0031] When installing the metal fixing frame 7, since the elevator will generate heat during normal operation, which will increase the temperature of the casing, it is strictly forbidden to weld the bucket elevator casing and the metal fixing frame 7 together to avoid the elevator from bending or the fixing frame from cracking when the casing temperature rises, which may cause a safety accident.
[0032] 7. Transmission device installation The transmission device 8 is hoisted to the driving platform 6 with a winch and a pulley block and connected to the head wheel shaft of the upper section 5. Before connecting the above two parts, first confirm that the backstop direction of the backstop on the transmission device 8 and the rotation direction of the transmission drum must be in the opposite state. Then use a dial indicator to align the output shaft of the transmission device and the head wheel shaft. The coaxiality error of the output shaft of the transmission device 8 and the head wheel shaft is required to be ≤0.05mm.
[0033] Since the transmission device 8 is usually shipped to the site as a whole, the original accuracy has been destroyed during transportation, so it must be recalibrated before installation. When adjusting, use a dial indicator and a feeler gauge to align the motor, hydraulic coupler and reducer. The radial runout and axial runout of the hydraulic coupler and the motor output shaft and the reducer input shaft are ≤0.3mm.
[0034] 8. Installation of traction wire rope tape First confirm the specifications, models and length of the wire rope tape 9 to be installed, then press the hopper bolts into the tape, install the tape into the elevator cavity according to the site and lifting conditions, raise the lower adjustment screw to the highest position, clamp one end of the wire rope tape 9 with a wire rope tape clamp, and use a sling to lift the wire rope tape 9 head to the top of the elevator from the middle casing on the feed inlet side. Use the same method for the other end of the wire rope tape 9, clamp the wire rope tape clamp and lift the wire rope tape 9 head from the discharge port side to the top of the elevator, and finally seal the ends of the tape with glue. The horizontal edge of the wire rope tape joint must be perpendicular to the center line of the conveyor belt, and the verticality error must not be greater than 0.2% of the bandwidth. The misalignment of the two ends of the wire rope tape 9 joint must be less than 2mm.
[0035] Drill connecting holes of the same size at both ends of the traction wire rope tape, and ensure that the center line of the connecting hole is perpendicular to the center line of the tape, and the distance between the two sides of the tape and the edge of the joint device is equal. Then place the tape pad in the middle of the two tapes, and the two tape splints on the outside of the tape, put on high-strength bolts, and then adjust the joint device to be perpendicular to the center line of the tape, and the distance between the two ends and the edge of the tape is equal, and finally tighten the bolts.
[0036] After the two ends of the wire rope tape 9 are connected by bolts, retain 100mm long wire rope along the joint of the tape end, cut off the excess wire rope, and then install wire rope clamps at the ends of the wire rope at a spacing of 20mm, and tighten them one by one. Finally, clean the wire rope heads and wire rope clamps with acetone or rosin water, and use special matching glue to bond the joints.
[0037] 9. Hopper Installation When installing the hopper 10, a rubber pad should be placed on the back of the hopper 10. The hoppers 10 should be installed one by one from the lower part of the feed port side in sequence, and each hopper bolt should be fully tightened. It is strictly forbidden to install the hopper 10 on the discharge port side to prevent the gravity imbalance on both sides of the tape from causing rotation and causing personal injury.
[0038] When the hopper 10 is installed, the wire rope tape 9 moves along with the installation of the hopper 10. The movement of the wire rope tape 9 can be moved by the hand-operated hydraulic coupling. It is strictly forbidden to use a reducer auxiliary drive to drive the wire rope tape 9 to move to install the hopper 10.
[0039] 10. Test run 1. No-load test run After the parts of the hoist are installed as required, a no-load test run is required. During the test run, start the hoist, open the inspection door during the hoist test run, carefully observe the operation of each part of the equipment, and make timely adjustments if any problems are found. The operation time must not be less than 2 hours. After the no-load test run is completed and the equipment is confirmed to be completely normal, a load test run can be carried out.
[0040] During the no-load test run of the hoist, pay attention to whether the traction parts such as the wire rope tape 9 and the hopper 10 and the check mechanism are operating normally, whether there are abnormal noises and leakage in the motor and reducer, and then check whether the temperature rise of each bearing is greater than 40°C after the equipment has been running for 2 hours, and finally check whether all the fasteners of the equipment are loose. After the no-load test run is stopped, focus on checking whether the fastening of the fixing bolts on the hopper 10 and the wire rope tape 9 and the wire rope tape joint is normal.
[0041] 2. Load test After the equipment has passed the no-load test run and made necessary adjustments, it will start the load test run. During the test run, start the elevator under the conditions of the designed conveying capacity and the intended conveying material. First, observe the working condition of the transmission device, the load condition of the motor, whether it is fully loaded or overloaded, whether the electrical control equipment is working normally, whether the noise of the reducer is excessive, whether the working condition of the upper section and the lower section is normal, whether the wire rope tape slips on the drum, and whether the running speed meets the design requirements. Finally, observe whether the elevator reaches the designed conveying capacity under the condition of uniform feeding of the elevator, whether the unloading is normal, whether there is obvious material return and clogging, and whether there is obvious reverse operation when the elevator stops running. After there are no defects in the above-mentioned load test run, it can be transferred to production.
Claims
1. A method for installing a vertical bucket elevator in a closed factory building, characterized in that: The following steps are involved: Step 1: Re-measure the foundation; before installing the equipment, mark the vertical and horizontal center lines of the lower section of the elevator; Step 2: Install the lower section. Use the front winch to slide and transport the equipment to the lifting position, and then use another winch to lift the lower section to the top of the equipment foundation through the high pulley block. Adjust the relative position of the lower section and the foundation bolts, slowly lower the lower section, and accurately install it on the equipment foundation. Step 3: Casing installation: According to the number of casings required for each floor of the plant, use a winch to hoist them from the reserved holes for equipment installation to the floor of each floor, and install them in sequence; Step 4: Install the housing bracket. After the housing of each floor of the plant is installed, install a fixed bracket on the housing of that floor, and the fixed bracket is fixedly installed on the nearest floor structure. Step 5: Install the upper section. Use a winch to hoist the upper section to the top of the top casing through a high pulley block. Insert asbestos ropes between the connection flanges of the top casing to ensure the seal and the levelness of the flange surface. Adjust the relative position between the upper section and the flange surface on the casing. Lower the upper section and accurately install it above the top casing. Step 6: Install the drive platform and metal fixing frame. Use the surrounding plant structures to make the drive platform and metal fixing frame, and reinforce the hoist at the same time. Step 7: Install the transmission device. Use a winch and pulley block to hoist the transmission device to the drive platform and connect it to the head wheel shaft of the upper section. Before connecting, first confirm that the backstop direction of the backstop on the transmission device is in the opposite state to the rotation direction of the transmission drum, and then use a dial indicator to align the output shaft of the transmission device with the head wheel shaft. Step 8, installation of traction wire rope tape; press the hopper bolt into the wire rope tape, install the wire rope tape into the elevator cavity according to the site and lifting conditions, raise the lower adjusting screw to the highest position, clamp one end of the wire rope tape with the wire rope tape clamp, and use the lifting rope to lift the wire rope tape head to the top of the elevator from the middle casing on the feed inlet side. Use the same method on the other end of the wire rope tape, clamp the wire rope tape clamp and lift the wire rope tape head from the discharge outlet side to the top of the elevator, and finally seal the ends of the tape with glue; Step 9, hopper installation: During installation, a rubber pad should be placed on the back of the hopper. The hoppers should be installed one by one from the lower part of the feed inlet side, and each hopper bolt should be fully tightened. Step 10: Test drive.
2. The method for installing a vertical bucket elevator in a closed factory building according to claim 1, characterized in that: In step one, after the foundation re-survey is completed, flat shims are placed at the anchor bolt holes using the seat mortar method. The elevation error of each set of shims is no more than 1mm, and the horizontality error is no more than 0.1 / 1000.
3. The method for installing a vertical bucket elevator in a closed factory building according to claim 2, characterized in that: In step 2, after the lower section is in place, its reference surface needs to be leveled. The tolerance for parallelism between the reference surface and the horizontal plane is 1 / 1000mm, and the adjustment shims must be close to the anchor bolts.
4. The method for installing a vertical bucket elevator in a closed factory building according to claim 1, 2 or 3, characterized in that: In step three, when installing the casing, asbestos rope is placed between the connecting flanges of the middle casing to ensure the seal and the horizontality of the flange surface; after the casing is assembled, the center line of the casing of each channel is on the same plumb plane, and the linear deviation shall not exceed 2 / 1000, and the cumulative deviation shall not exceed 8mm.
5. The method for installing a vertical bucket elevator in a closed factory building according to claim 4, characterized in that: In step 4, a fixed bracket is installed on each floor of the factory building, and the installation of the fixed bracket does not restrict the free retraction of the elevator in the vertical direction.
6. The method for installing a vertical bucket elevator in a closed factory building according to claim 1 or 5, characterized in that: In step five, after the upper section is installed, calibrate the center lines of the upper and lower drive shafts of the elevator so that the two shafts are horizontal and in the same vertical plane. The parallelism tolerance between the center line of the upper shaft and the horizontal plane is 0.3 / 1000mm, the vertical plane error between the upper and lower shafts is less than 4mm, and the vertical plane error between the upper and lower roller end faces is less than 5mm.
7. The method for installing a vertical bucket elevator in a closed factory building according to claim 6, characterized in that: In step 7, the transmission device is recalibrated before installation. During adjustment, the motor, hydraulic coupling and reducer are aligned with a dial indicator and a feeler gauge. The radial runout and axial runout of the hydraulic coupling, motor output shaft and reducer input shaft are ≤0.3mm.
8. The method for installing a vertical bucket elevator in a closed factory building according to claim 1 or 7, characterized in that: In step eight, the horizontal edge of the wire rope tape joint is perpendicular to the center line of the conveyor belt, and the verticality error shall not be greater than 0.2% of the belt width. The misalignment of the two ends of the wire rope tape joint must be less than 2mm.
9. The method for installing a vertical bucket elevator in a closed factory building according to claim 8, characterized in that: In step ten, after all parts of the elevator are installed as required, a no-load test run is carried out first. During the test run, the elevator is started. During the elevator test run, the inspection door is opened and the operation of each part of the equipment is carefully observed. The operation time should not be less than 2 hours.
10. The method for installing a vertical bucket elevator in a closed factory building according to claim 9, characterized in that: In step ten, after the no-load test is completed, it is confirmed that the equipment is completely normal and a load test can be carried out. During the test, the elevator is started under the conditions of the designed conveying capacity and the intended conveying material. First, observe the working condition of the transmission device, the load condition of the motor, whether it is fully loaded or overloaded, whether the electrical control equipment is working normally, whether the noise of the reducer is excessive, whether the working conditions of the upper section and the lower section are normal, whether the wire rope tape slips on the drum, and whether the running speed meets the design requirements. Finally, observe whether the elevator reaches the designed conveying capacity when the elevator is fed evenly, whether the unloading is normal, whether there is obvious material return and blockage, and when the elevator stops running, whether there is obvious reverse operation, etc. After there are no defects in the above-mentioned load test, it can be handed over to production.
Citation Information
Patent Citations
Hoisting method for bucket type hoister tape
CN102502170A
Installation and construction method of large-sized tray dryer in confined space
CN108996396A
Chain bucket conveyor chain as well as installation method and installation system of hoppers
CN110255063A
Installation method of ultrahigh vertical feeding belt conveyor
CN113148839A
Method for quickly disassembling and assembling wire belt hopper of bucket elevator
CN114473404A